SIR-007 - Insufficient Lighting
SIR-007 - Insufficient Lighting
PRIORITY
DIGITAL PHOTO: If picture is not necessary or not applicable please put (N/A)
Despite observations from JV Safety and numbers of internal SHES Discrepancies generated with regards to poor illumination in working areas, still
found several locations, particularly at Launching Shaft (LS1) area, were not provided with sufficient lightings with at least 100 lux reading.
STATUS : VERIFIED BY :
On-Going Completed JK Uniforme
Safety Engineer
Received by: DP Gatmaitan Recommended corrective action: 1. Provide additional flood lights and electrical cables
that can be installed in strategic locations.
Expected date of completion: 10/24/2022 2. Request for additional tower lights to be used for
areas which has no access to power supply.
3. Electrician and machine tender must be informed in
advance whenever there are activities that required
additional lightings.