You are on page 1of 1

SL.NO.

ACTIVITY
1 Deep Earth Boring
2 Cable Trench Excavation
3 PVC Sleeves for Crossings installation inside trench
4 Concretet Skid Installation for Power Skid & Solar Unit
5 Solar Unit & Power Skid Installation
6 Supports for Instrument JB's / Panels installation
7 Cable laying inside trench
8 Earth Pits Installation
9 Instrument JB's / Panels installation
10 Cable IR Check - Before termination
11 Cable Tray Installation
12 Cable dressing, Glanding & Termination
13 Earth Pits Resistance Check
14 Lighting Installation
15 Cable IR Check - After termination
16 Trench Closing
17 Testing of panels, instruments, earth bars etc.,
18 Pre-commissioning Checks
19 Commissioning of Plant