Hse Plan Example
Hse Plan Example
: 26071-100-G01-GHX-00002
___________
Djoko Koen Soewito
Chief Engineer (KTT)
PERTAMINA RDMP RU-V
RE-ISSUED FOR
002 28 Oct 19 YUZAR ISPRANTO Y.D.KIM
CONSTRUCTION
RE-ISSUED FOR
001 01 Oct 19 YUZAR ISPRANTO Y.D.KIM
CONSTRUCTION
ISSUED FOR
000 13 Aug 19 YUZAR ISPRANTO Y.D.KIM
CONSTRUCTION
00C 10 July 19 RE-ISSUED FOR REVIEW YUZAR ISPRANTO Y.D.KIM
REVISION LOG
i
Doc. No.: 26071-100-G01-GHX-00002
Table of Contents
Table of Contents............................................................................................................................................. ii
1. INTRODUCTIONS ..................................................................................................................................... 1
2. PURPOSE ................................................................................................................................................. 1
3. SCOPE ...................................................................................................................................................... 1
5. REFERENCES ............................................................................................................................................ 4
ii
Doc. No.: 26071-100-G01-GHX-00002
iii
Doc. No.: 26071-100-G01-GHX-00002
iv
Doc. No.: 26071-100-G01-GHX-00002
16. COMMUNICATION................................................................................................................................. 60
TOOLBOX MEETING (TBM) .................................................................................................................. 60
PRE-JOB SAFETY MEETING (PJSM)....................................................................................................... 61
GENERAL SAFETY TALK ........................................................................................................................ 62
WEEKLY SITE HSE COORDINATION MEETING ...................................................................................... 62
PROJECT MANAGEMENT SAFETY COMMITTEE MEETING ................................................................... 63
MONTHLY HSE COMMITTEE MEETING................................................................................................ 63
HSE POSTER, SLOGAN, NOTICE BOARD ............................................................................................... 63
CONTRACTOR RADIO COMMUNCATION NETWORK ........................................................................... 64
v
Doc. No.: 26071-100-G01-GHX-00002
List of Tables
Table 1. HSE KPI’s .................................................................................................................................... 8
Table 2. MOC Risk Assessment Requirements...................................................................................... 17
Table 3. MOC Authorization Level Required......................................................................................... 18
Table 4. Listing of Personnel Included in the Hearing Conservation Program ..................................... 29
Table 5. Requirements for Respirable and Non-Respirable Confined Space........................................ 37
Table 6. Colour Code Period ................................................................................................................. 39
Table 7. List of Required Authority to Certify Heavy Mobile Equipment ............................................. 45
Table 8. Personal Protective Equipment (PPE) Standard ...................................................................... 50
Table 9. HT Radio Communication Channel ......................................................................................... 64
Table 10. Emergency Siren Tones ......................................................................................................... 66
Table 11. Disciplinary Action to be Taken up to The Penalty Points .................................................... 71
List of Figures
Figure 1. Probability/Severity Matrix .................................................................................................... 13
Figure 2. Risk Categories ....................................................................................................................... 13
Figure 3. Severity Definition.................................................................................................................. 14
Figure 4. CSMS Process Flow ................................................................................................................ 22
Figure 5. Calculation for Potential Fall Distance ................................................................................... 44
Figure 6. Lock, Tag and HASP for LOTO................................................................................................. 49
Figure 7. Out of Service Tag .................................................................................................................. 49
Figure 8. Muster Point Map .................................................................................................................. 67
vi
Doc. No.: 26071-100-G01-GHX-00002
1. INTRODUCTIONS
Refinery Development Master Plan Project hereinafter RDMP Project is comprised of Revamp
of existing units, and construction of new licensed unit, non-licensed unit (for ISBL) as well as
new offsite and utilities (OS & US) in Pertamina RU V Balikpapan Located in Balikpapan, East
Kalimantan. The Project focuses on the need to modernize the refining configuration and
capabilities to produce more gasoline and other products by converting residue or fuel oil into
more valuable products, primarily gasoline and diesel. An Integrated Performance Management
System, as part of the ICSS, will be implemented to improve the quality of service and
production reliability of the Refinery.
This plan addresses the Health, Safety, and Environment requirements established by Owner,
as stated in exhibit H of the contract and enables the Contractor’s project teams to successfully
manage HSE throughout the project’s life cycle to achieve the goal of zero Lost Time Injury (LTI)
during the execution of the project. In the event of conflicts between Project HSE Plan,
Contractor standards, and applicable government rules & regulations, further discussion shall
be conducted with Owner (government rules and regulations over rules the other
requirements).
2. PURPOSE
The purpose of Project HSE Plan is a specific plan to ensure all job activities in this project has
complied with Owner standards, Contractor standards, and applicable government rules and
regulations in order to get the best quality for Health, Safety, and Environmental to prevent the
adverse (human, property, and environment) incident. In addition, Project HSE Plan described
the detail of HSE schedule (based on project requirements) to support all of project activities.
3. SCOPE
This Plan will be applied at boundary/demarcation of RDMP RU-V Project under control of
Contractor Management. The boundary area is limited to:
• In site fencing plant include ISBL and Offsites and Utilities (OS & US).
• Temporary facilities area (site office, warehouses, and lay down).
• Kariangau shop area.
Within the Brown field operation all Pertamina procedures and policies which are in line with
MIGAS requirements must be followed and are under the absolute authority of the Chief
Engineer (KTT).
The MIGAS regulations apply only to Brownfield areas (Oil and Gas Production facilities or
projects undertaken within the operating site).
In compliance with MIGAS regulations, the Greenfield area shall be clearly partitioned from
the Brownfield area, such that it is not possible for persons to arbitrarily cross between
Page 1 of 71
Doc. No.: 26071-100-G01-GHX-00002
the greenfield/brownfield areas without passing through a strict security check point (Under
the scope of work Pertamina retain responsibility for security at all access points). Safety
rules in that area are the responsibility of Pertamina’s Chief Engineer (KTT), who must ensure
that adequate safety management is applied given the nature of the work.
Page 2 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 3 of 71
Doc. No.: 26071-100-G01-GHX-00002
5. REFERENCES
Contractor shall implement HSE Management System refer to Government Regulations,
National & International Standard, Rules and others Regulation, such as but not limited:
1. Law No. 1/1970 regarding Occupational HSE (Consists of Health and Safety)
2. Law No. 23/1992 regarding Occupational Health
3. Law No. 32/2009 regarding Protection and Management of Life and Environment
4. Regulation of Indonesian Government No. 11/1979 regarding Work Safety at MIGAS
Refinery
5. Law No. 24/2011 regarding Social Security Organizing Body
6. Law No. 22/2001 regarding Oil and Gas
Page 4 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 5 of 71
Doc. No.: 26071-100-G01-GHX-00002
28. Decree of the Head of Environmental Impact Control Agency No. 205/BAPEDAL/07/1996
regarding Technical Guidelines for Air Pollution Control Stationary Sources.
29. Regulation of Manpower Ministry No. 09 Year 2016 regarding Working at Height
30. Regulation of Manpower Ministry No. 37 Year 2016 regarding Pressure Vessel and
Storage Tank
31. Regulation of Energy and Mineral Resources Ministry No. 18 Year 2018 regarding
Installation and Tools Inspection for Oil and Gas Activity
32. Local Regulation of East Kalimantan No. 02 Year 2011 regarding Water Quality
Management and Water Pollution Control
33. Local Regulation of Balikpapan No. 03 / 2012 regarding Permit for Building
34. Health, Safety, Security, and Environmental (HSSE) Plan Doc. No. 26070-203-G01-GHX-
J0001-000
35. Health, Safety, Security and Environmental (HSSE) Plan Document No. G01-GHX-J0001.
36. ISO 14001:2015 Environmental Management System – Requirements with guidance for
use.
37. ISO 45001:2018 Health and Safety Management System – Requirements with guidance
for use.
38. Regulation of the Minister of Manpower No. 01/MEN/I/2007 regarding Guidelines for
HSE Award.
39. Environmental Impact Analysis (EIA) of RDMP RU V Balikpapan Project.
40. Project HSE Management System Document No. 26071-100-G01-GHX-00008.
41. NFPA 30: Flammable and Combustible Liquids Code.
42. EN 397:2012 – Industrial Helmets.
43. ANSI Z89.1 – Safety Requirements for Industrial Head Protection.
44. EN 166 – Personal Eye Protection Specifications.
45. ANSI Z87.1 – American National Standard for Occupational and Educational Personal Eye
and Face.
46. ANSI Z88.2 – Practices for Respiratory Protection.
47. BS EN 4275 – Guide to Implementing an Effective Respiratory Protective.
48. BS EN 139 – Respiratory protective devices. Compressed air line breathing apparatus for
use with a full face mask, half mask or a mouthpiece assembly. Requirements, testing,
marking.
49. BS EN 137 – Specification for respiratory protective devices: self-contained open-circuit
compressed air breathing apparatus.
50. ANSI S3.19 – Noise Reduction Rating (NRR) Labelling
51. BS EN 420 – Protective gloves. General requirements and test methods.
52. BS EN 345-1 – Safety footwear for professional use. Specification.
53. ANSI Z.41 – Personal Protection - Protective Footwear.
54. ANSI A10.14 – Construction and Demolition Operations - Requirements for Safety Belts,
Harnesses.
55. BS 1139-1.1:1990 Metal Scaffolding, Tubes, Specification for Steel Tubes.
Page 6 of 71
Doc. No.: 26071-100-G01-GHX-00002
Contractor’s HSE management system established for this project is centered on Contractor’s
top management commitment to execute the work in such manner that health, environment,
and property are protected in accordance with all applicable laws and regulations as well as HSE
policy of RDMP project (which is in line with Owner and Contractor HSE policy). To do so,
Contractor’s top management has strong commitment that throughout the execution of the
project:
1. Establish Health, Safety and Environment (HSE) as a priority in every work in order to
achieve the best level of quality and optimum time completion.
2. Provide safety and comfort in the work for client, employee, partner, and communities,
by maintain the best safety and security in every activity.
3. Increase the level of Health, Safety and Environment, in order to prevent all unsafe action
and / or condition, workplace accidents, and environment pollution in RDMP project.
The Strategic objective for the RDMP Project RU V Balikpapan is Zero Accident, which is defining
as:
Contractor HSE Plan aligned with Owner’s Document 26070-203-G01-GHX-J0001 HSSE Plan to
minimize the gap between Contractor and Owner in terms of HSE Requirement including
Objectives, Target, and Program (OTP) that may be included in this HSE Plan.
To achieve project goals in HSE and minimize risks associated in the project activities, Contractor
will implement Incident Injury Free (IIF®) Programs covering all Contractor activities and
personnel. Contractor also set performance standards with the aim of eliminating and
controlling risks. The ultimate project specific HSE Performance Target as tabulated on the HSE
Objectives for this project in Table 1. HSE KPI’s Performance Target:
Page 7 of 71
Doc. No.: 26071-100-G01-GHX-00002
LAGGING INDICATOR
Total case number 0
1 Fatality
0
2 Lost Time Incident Total case number
Lost Time Incident Frequency Rate <1
3 Ratio
(LTIFR)
Lost Time Incident Severity Rate <1
4 Ratio
(LTISR)
Incident impacted to 0
5 Total case number
Environmental pollution
Incident impacted to fire / asset 0
6 Total case number
damage
Per million
7 Total Recordable Injury Rate (TRIR) Ratio <0.09
manhours
Total
8 First Aid Case Total case number 4% manpower
on board
LEADING INDICATOR
MoM / Attendant list Min. 1 / month
1 HSE Meeting
Attendant list Daily
2 HSE Talk / briefing / toolbox
Report submission Weekly
3 HSE Reporting
record
4 HSE Management Visit/ MWT MWT record Quarterly Level PMT
Follow up action 100% Closed
5 Closure Action
report
Audit/ Inspection Monthly
6 Inspection / audit
report
PPE compliance 100%
7 PPE Compliance
report
Compliance on Waste Waste management 100% Comply
8
Management report
Hygiene Industry 100% Comply
9 Compliance on Hygiene Industry
report
Comply to Good housekeeping e-COP & Audit 100% at the end
10
management Record of project
Table 1. HSE KPI’s
The progress of KPI and program shall be updated regularly. Contractor shall submit, on a
weekly basis, a formal report summarizing Contractor and Subcontractors’ HSE performance to
the Owner representative. The report will be including total man-hours, leading and lagging
indicator as stated on HSE Objectives, Target, Programs, and any related additional data.
Page 8 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 9 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 10 of 71
Doc. No.: 26071-100-G01-GHX-00002
6.3.9. INSPECTOR
• Assist Chief HSE to inspect all scaffolding, construction electricity system, heavy
equipment, machineries, tools, vehicles, and other equipment will be used in
RDMP project as per competency
• Develop an inspection report and communicate it with Chief HSE.
• Conduct regular inspections at infrastructure facility area.
• Has a qualification or certified as Inspector for each respective area. E.g.
Inspector for scaffolding shall be a qualified or certified Scaffolding Inspector.
Page 11 of 71
Doc. No.: 26071-100-G01-GHX-00002
6.3.13. PARAMEDIC
• Respond immediately and deliver initial stabilization for injured / illness person
at the scene prior transfer to site clinic.
• Assist Site Doctor in implementation of health management programs,
• Assist Site Doctor to identify health hazards in the work place, implement
control and monitoring program
6.3.14. SUBCONTRACTOR/SUPPLIER/VENDORS
• Comply with minimum HSE requirement, procedures, and related HSE
agreement.
• Report accidents / incidents immediately direct to HSE committee /
representative.
• Assist in any accident / incident investigation in their area.
• Maintain good housekeeping and physical arrangements.
Page 12 of 71
Doc. No.: 26071-100-G01-GHX-00002
7. RISK MANAGEMENT
HIRAC
Refer to Attachment 10. HIRAC Form
Contractor shall develop HIRAC (Hazard Identification, Risk Analysis and Control) throughout
project phase. HIRAC will be used as reference to develop JSA for specific activities at site.
Page 13 of 71
Doc. No.: 26071-100-G01-GHX-00002
Job Safety Analysis (JSA) relevant for the project in order to control risks of specific activities
which carried out at RDMP Project. Approved JSA shall be attached to the PTW.
JSA will be required for all jobs performed On or Off site. Construction Superintendent or
Supervisor shall be responsible to provide JSA and understood by all the work team member.
HSE are responsible to review the JSA. Normally during daily Tool Box Meeting (TBM). Employee
shall sign the JSA Attendance list and involving in any review of activity change. New hazard
identified in JSA shall be add on HIRAC register.
As minimum JSA shall described breakdown steps for the task and hazards identified for each
step including control measures.
Page 14 of 71
Doc. No.: 26071-100-G01-GHX-00002
Work Leader or Discipline Superintendent involved, shall identify the sequence of the job,
including HSE requirement for each of the sequence.
Break the job down into sequential steps. Everyone should understand what is taking place and
where; what people are required; what equipment or plant is in use; and any other components
involved.
To identify the potential hazards that could reasonably cause damage on each steps. Consider:
A whole range of controls (elimination, substitution, etc.) should arise from such JSA, not just
procedural ones, as these are the least effective. Many of the non-procedural controls require
action before the job starts (E.g. purchasing of equipment (signs, harnesses etc), training and
certification of workers, re-design of equipment, installation of barriers, etc).
Step 5. Review the JSA with all workers on the works (Pre-Job Safety Meeting).
During Pre-Job Safety Meeting, work group will have a final discussion which includes HSE and
Discipline Superintendent review on the JSA then approval to proceed with the Work. Pre-job
Safety Meetings will be conducted at each work site prior to the start of job activities. During
these meetings the contents of the JSA will be discussed in detail in such a manner to meet the
expectations. In this meeting, The Supervisor or Crew Lead facilitates the JSA and asks specific
questions of multiple workers to obtain their input regarding planning and conducting Work
safely. Each crew member shall offer input, asks questions, and actively listens during the JSA
discussion. After completing final JSA discussion, all components of the JSA are accurately
documented on the appropriate project JSA form. The JSA is reviewed and signed by each crew
member, and signature approval is provided by the Supervisor or Crew Lead.
Page 15 of 71
Doc. No.: 26071-100-G01-GHX-00002
JSAs should be reviewed periodically but especially after changes in the work situation; after
related incidents; changes in legislation etc.
Generic JSAs should be reviewed each time they are used in a new work environment (E.g., a
JSA used by a Subcontractor to install scaffolding should be reviewed at the start of each job).
Supervisor or Foreman shall be responsible to provide JHA and to ensure that the work crew
aware and understand all the associated hazards with the jobs they will be performing. and also
know what are the preventive measures to be taken to eliminate or reduce them into
acceptable risk.
Supervisor and Foreman need to conduct periodical review to JHA to ensures that it remains
relevant to reduce workplace incidents.
Supervisor and Foreman shall be deliver and discuss about JHA with their work crews just before
starting the work (Pre-Job Safety Meeting).
During Pre-Job Safety Meeting, Supervisor or Foreman and their work crew will have a final
discussion to review on the JHA then approval to proceed with the Work. Pre-job Safety
Meetings will be conducted at each work site prior to the start of job activities. During these
meetings the contents of the JHA shall be discussed and confirmation/check to ensure all
precaution already at place. After completing final JHA discussion, JHA are accurately
documented on the appropriate JHA form. The JHA is signed by each crew member, and
Supervisor or Crew Lead.
Page 16 of 71
Doc. No.: 26071-100-G01-GHX-00002
Once a change or a need for future change is identified, it is necessary for that change to be
managed by the appropriate person which will be guided by the associated risk assessment as
to whether the proposed change(s) represents an acceptable level of risk.
The Change Management System consist of six (6) step process as follow:
Step 1 requires the Change Initiator to ask a series of questions with the aim of providing
clarification as to whether the change management process is required.
If “yes” is the response to any of the questions then the Change Initiator must move to the next
step.
This Step need to determine the level of risk for a variety of change impact types.
The Change Initiator is also required to make comment on the risks of undertaking and not
undertaking the proposed change.
Based on the level of risk identified, the following levels of risk assessment will be required to
be completed and details attached to the Change Management Request Form:
CHANGE RISK
RISK ASSESSMENT REQUIREMENTS
CATEGORY
1. JSA to be re-reviewed and re-written to incorporate
Low
with the change occur.
2. Requirements 1 and method statement may need to be
Medium
provided and approved.
3. Requirements 2, Conduct a Risk Assessment Workshop
High
and Prepare Action Plan.
Table 2. MOC Risk Assessment Requirements
• Describe the reasons for change, providing hard evidence to support the need/opportunity.
• Describe the benefits of this change.
Page 17 of 71
Doc. No.: 26071-100-G01-GHX-00002
• List any Technical Expert who needs to be consulted about / approve the proposed change.
• List the people / groups who need to be consulted on the proposed change.
• List systems, policies, procedures, plans, schedules, competencies, etc which affected by
these changes.
A Technical Expert is generally the person who may own legal obligation/business accountability
in the area covering the change and may not necessarily be the Change Authorizer.
The Change Initiator is required to seek approval from the Technical Expert for the proposed
change if the risk is deemed to be High.
This step requires the Change Initiator to develop an Action Plan for the successful
implementation of the proposed change.
It is required to review the effectiveness of the change at an agreed period following the change.
Step 6 Approval
• The Risk Category for the requested change is the highest risk rating from Step 2. That is, if
one category has a risk rating of Medium, but another has a risk rating of High, the overall
risk rating is High.
• This step is break down into two stages. The first stage, if required, is the review and
approval by a Technical Expert. This shall apply for all High-risk changes.
• The second stage is the approval by the Change Authorizer. The Change Authorizer is
identified by completing Step 2 Risk Assessment of the Change Management Request
Form. The Change Authorizer depends on the level of risk as defined in the following table.
Changes that are High risk shall be subject to a Post Implementation Review. The date for review
and person responsible for organizing the review shall be detailed in the Action Plan.
Page 18 of 71
Doc. No.: 26071-100-G01-GHX-00002
Contractor’s HSE will keep a register of all approved change management activities.
9. PRE-MOBILIZATION MANAGEMENT
Premobilization inspections between Contractor and Subcontractor will be performed prior to
mobilization for agreed scopes of work to ensure readiness prior to mobilization. Subcontractor
shall fulfil all of premobilization readiness requirements before obtaining Contractor approved
and verified of workers SIML (Surat Ijin Masuk Lokasi= Site Entry Permit) and ID Badge and
Permit to Work. As a minimum, the scope of the inspection shall include but not limited to the
following:
MANPOWER READINESS
Requirements for Man Power Readiness that shall be submitted and followed by Subcontractor
are as follow:
• Copy of valid competence certificate (including driving license) for specific position such as
heavy and light vehicles driver, heavy equipment operator, welder, scaffolder, rigger, etc.;
• Copy Medical Check Up (MCU) result;
• Complete filled of man power register form (for each personnel);
• Formal photograph (3x4) with Red colour as a background;
• Copy of identity card (for each personnel);
• Copy of Kartu Keluarga (for each personnel);
• Copy of Surat Domisili (for each personnel);
• Copy of employment card / BPJS (for each personnel);
• Attend HSE induction and matrix training (based on work position).
Visitor shall be accompanied by an appointed Contractor person (user / host). Visitor shall also
complete the visitor SIML & ID Badge following requirement:
All of man power data will be documented on a man power register web-based system called
HSE e-Board. This data could be accessed regularly in line with RFID card system.
Page 19 of 71
Doc. No.: 26071-100-G01-GHX-00002
After mobilize to project site, Contractor will conduct gate inspection to have a final check prior
to use by Subcontractor. After Pass the inspection, sticker will be attached to the
equipment/tools/vehicles. The requirements related to equipment / tools / vehicles readiness
are as follow:
• Copy of valid equipment / tools / vehicles certificates (including KEUR, STNK, BPKB);
• Equipment / tools / vehicles manual book;
• Vehicle shall have Anti-lock Brake System, Air Bag System, safety belt for all passenger,
speed sensor attached, flame arrestor and safety accessories as per HSE requirement (back
up alarm, fire extinguisher, first aid kit).
• Vehicle shall not be older than 5 years for small vehicle and 10 years for truck and other
heavy vehicles.
DOCUMENTATION READINESS
Prior to conduct work at project site, Subcontractor shall prepare several documents as a
requirements of document readiness. Those documents are as follow:
1. Project Manager, Procurement Manager and Construction Manager shall ensure that all
bidders for subcontracting passed the CSMS (Contractor Safety Management System)
before PQ (Pre-Qualification). CSMS scoring system not only based on documentation
(paper based) but also based on the scoring during shop visit in related Subcontractor
workshop. Refer to Attachment 4 CSMS Questionnaire and Flowchart of CSMS process
described in below Figure 4. CSMS Process Flow.
Page 20 of 71
Doc. No.: 26071-100-G01-GHX-00002
5. Subcontractor shall conduct HSE workshop to present their HSE management plan
including but not limited to man power plan (shall fulfil the requirements of 1 HSE
Coordinator + HSE Officer with ratio 1: 50 workers + First Aider with ratio 1:100 workers
+ Paramedic with ratio 1:250 workers).
6. Subcontractor shall provide their employees with proper equipment and skill certification
from relevant authorized government institution, provide adequate work tools and
provide all required personal protective equipment as required in the government rules
regulations and applicable industrial standard both national and international.
8. All Subcontractors and outsource parties that contribute directly with Contractor is
obliged to provide health/safety and employment insurance facility to workers, both
individually and in groups.
9. A monthly KPI audit shall be conducted to all Subcontractors to measure the HSE
performance of the Subcontractors. Subcontractor that is actively working on the project
must be audited at least once a month to measure the performance of the Subcontractor
HSE, audit results in the form of Key Performance Indicator (KPI) HSE score will determine
whether to process Monthly Progress Report or not as a prerequisite of invoicing. Audit
findings listed in the KPI must be completed well within the allocated time, if not resolved
within the specified time, then the Monthly Progress Report Subcontractor approval will
be suspended until the findings resolved.
11. Upon the submission of the progress report, Subcontractors shall achieve a compliance
score (minimum 80 of 100) without any outstanding audit or inspection item from the
Subcontractor’s HSE Key Performance Indicator (KPI).
Page 21 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 22 of 71
Doc. No.: 26071-100-G01-GHX-00002
Contractor’s activities. All vehicles shall pass an inspection. Minimum requirements for drivers
are as follows:
• The vehicle shall have Anti-lock Brake System, Air Bag System, and safety belt for all
passenger.
• Speed sensor attached in vehicle.
• Have valid gate pass.
• Completed with inspection record.
• Completed with safety accessories as per HSE requirement (reverse alarm, fire
extinguisher, first aid kit, flame arrestor).
The General Affair Department will be responsible to control driver alertness and fitness by:
• Scheduling driver’s trip plan for a week considering their enough time to rest.
• Pre- Briefing before starting work.
• Maximum duty hours of drivers shall be 15 hours.
• All driver 100 % should have attend Safe driving course provided by JO.
• Refreshment training for all driver at site will be conducted on yearly basis.
PEDESTRIAN AREA
• Contractor shall provide pedestrian walkways which capable to be used by employees to
move at site and office area by walk.
• At minimum dedicated pedestrian walkways shall provide with widths no less than 3 feet.
• Pedestrian way shall be clearly marked to show visible boundary between vehicle and
pedestrian access.
• Pedestrian crosswalk will have an interface with vehicles access. Contractor must treat
adequate control for this area such as put proper sign to stop their vehicles and give priority
to pedestrian to cross the road, provide dedicated signal man, speed limit, etc.
• Identified blind spot with potential crash between pedestrian and vehicles shall provide
with mirror and adequate safety sign. E.g. pedestrian walkways at warehouse, workshop.
Page 23 of 71
Doc. No.: 26071-100-G01-GHX-00002
Biological hazards refer to organisms or organic matters produced by these organisms that are
harmful to human health. These include parasites, viruses, bacteria, fungi and protein.
The main types of biological materials that workers were potentially exposed to in workplaces
were:
• Human bodily matter (blood, tissues, vomit, urine, faeces, saliva, breast milk)
• Animal product (meat, offal, skins, bones, blood, milk, eggs)
• Live animals (mammals, birds, fish, invertebrates and their urine or faeces)
• Biohazard waste, sewerage and rubbish
• Laboratory cultures
Occupation and workplaces where people may come into contact with biological hazards are:
Biological hazards likely to affect workers in specific workplaces will be vary according to the
type of occupation, the location, the weather, the nature of the work, species known to occur
in the region and the environment. Liaison with specialist advisors may be required to
document the type and extent of the Biohazards relevant to a workplace and to prepare a risk
assessment and mitigation plan based on that assessment.
If the contact with Biohazards cannot be prevented, the employees must use PPE and adhere
strictly to the practice of personal hygiene. PPE will be including masks, gloves, protective
clothing, eye shields (safety googles), face shields, and shoe covers.
Page 24 of 71
Doc. No.: 26071-100-G01-GHX-00002
DRINKING WATER
This provides guidance for the protection of site personnel from unsanitary and unhealthy
drinking.
• Contractor shall provide drinking water which comply with government water quality
standard for drinking water.
• It is prohibited to drink water directly from tap water, since tap water is often not
adequately treated. It is recommended to boil the water prior to drinking.
• Sampling of drinking water shall be conducted quarterly by Contractor HSE to ensure
drinking water supplies are health to consume.
Page 25 of 71
Doc. No.: 26071-100-G01-GHX-00002
As with other health and safety hazards, the greater exposure to shift work and extended hours,
the more likely the risk of some harm. The risk of working with shifts and the amount of night
work can undermine long term shifts and long hours of work and safety, those who work them.
For that there are several mitigations that need to be considered among others but not limited
to:
FITNESS TO WORK
Achieving good performance in doing the job or duty shall be equipped by fitness both physical
and mentally. Through this plan, Contractor needs to ensure that employees who working in
site area have to be in good condition to perform the job by conducting medical check-up
(MCU). Refer to attachment 1 Project HSE Policy.
The result of the medical check-up (MCU) will be reviewed by Site Doctor to determine the
fitness by considering to the job required by his/her supervisor. Only Fit to Work person shall
be obtained ID badges and enter the plant for work.
To be in line with Project HSE Policy, Contractor must conduct drug and alcohol test for the
employee. At minimum 1% of total number of employees per month shall be the target for the
test.
Page 26 of 71
Doc. No.: 26071-100-G01-GHX-00002
Drug and Alcohol test will be carried out randomly. However, employee at high risk activities
will be the priority to participate in the test.
Detail of fitness for work please refer to 26071-100-G01-GHX-00005 Health Management Plan.
• Where an employee is required to change shift from day to night shift, and vice versa,
they should be given a full 24-hour rest period prior to commencing the new shift.
• All employees shall not work more than thirteen (13) days straight without taking a day
rest.
• To effectively manage fatigue caused by on call work, consideration is to be given to:
Page 27 of 71
Doc. No.: 26071-100-G01-GHX-00002
12.5.3. HOUSEKEEPING
• Housekeeping practices and clean-up of all project facilities will be maintained by
Construction Team.
• The work area shall be maintained to a high standard of cleanliness, and supervisors will
be expected to review and rectify their respective work areas as required on a daily basis.
• Waste material shall not be burned in site and shall be segregated when disposed of in
the bins.
Noise can be Continuous, Intermittent and Impulsive. Continuous noise is constant. For
example, ventilation fans are a source of continuous noise. Intermittent noise is a mix of quiet
and noisy periods. Most manufacturing noise is intermittent. Impulse noise is a short burst of
loud noise that lasts for short duration. They are associated with such sources as explosions,
impacts, and sonic booms.
Noise assessment will be made periodically by Contractor. Employees who work in areas with
noise levels greater than 85 dB shall wear hearing protection. Contractor will ensure that these
areas are adequately marked and communicated to personnel during safety meetings,
induction training and should be detailed within the relevant work task JSA.
Contractor shall monitor ambient noise or environmental noise that potential to cause
annoyance to surrounding areas during construction work. Contractor shall conduct noise
Page 28 of 71
Doc. No.: 26071-100-G01-GHX-00002
When information indicates that any employee’s exposure may equal or exceed the Action
noise level, i.e. 8-hour TWA of 85 dB, Contractor must develop and implement noise
monitoring programs and to be carried out by Competent Person.
All personnel with potential exposure greater than the action noise level, will be enrolled in
the medical surveillance program and undergo a baseline audiogram in accordance with
current program requirements. Thereafter, annual audiograms will be compared with the
baseline exam.
All personnel enrolled in the audiometric testing portion of the medical Surveillance program
shall be identified on the “Listing of Personnel Included in the Hearing Conservation Program”.
Employee Name Employee ID # Area or Task Employee’s Supervisor
When a Standard Threshold Shift (STS) is noted between the last valid baseline and
the annual audiogram, the following steps will be taken:
1. A retest will be conducted within 30 days to confirm the STS. The employee will not be
exposed to workplace/hobby noise for 14 hours or will be provided with adequate
hearing protection prior to testing.
2. If the STS persists, ear protection will be upgraded to one with a greater Noise
Reduction Rating (NRR). The minimum NRR will be 26 dBA.
3. The employee will be counselled, and information will be obtained regarding the
employee's possible noise exposure away from the workplace or existing ear pathology.
4. Qualified medical personnel will review the audiograms. This group will determine the
need for a medical referral.
Page 29 of 71
Doc. No.: 26071-100-G01-GHX-00002
5. The employee and employee’s supervisor will be notified of the shift in hearing
threshold in writing by HSE within 21 days of determination.
6. If the employee who has experienced an STS is exposed to 85 dBA for 8 hours or 80 dBA
for 12 hours, mandatory use of ear protection is required.
7. Temporary employees will receive audiograms during their exit physicals if they have
worked around heavy equipment or have received an exposure to noise levels in excess
of 85 dBAs.
• Contractor will comply with Owner and industry standards for the specification and
provision of respiratory protection.
• Supervisor will be responsible to provide Respiratory protection base on assessment of
the job. The respiratory protection type shall be in accordance with the PPE standard.
• Any employee who requires respiratory protection to perform the work shall be trained,
medically qualified, and fit-tested.
• Contractor must ensure that respiratory protection equipment cleaned and stored
properly
• Provide special room / bunker for Radioactive storage complete with sign and according
regulation and standard radiation storage system.
• Provide Sign, Barricade, Orange & Red rotary lamp and other equipment/tools to alert
that dangerous activity being conducted.
• Provide qualified personnel to conduct radiation activity. The personnel shall be certified
by BATAN for conducting the activity.
• NDT (RT) without collimators are prohibited.
• Emergency procedure for Radioactive shall be provided.
• Radiography organization structure for Sub-Contractor shall be established. At minimum
shall describe Radiography Operator, Radiography Specialist, and Personal Protection
Radiography (PPR).
Contractor shall ensure that the following basic rules for Radiography are strictly enforced:
Page 30 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Area exposed by radioactive sources shall clearly marked at four direction (north, south,
east & west), given signs with rope or other effective means and mounted alert signs to
the radiation.
• Accepted doses for radioactive worker shall not exceed 5 Sv/H or 50 mSv/Y and, in project
site areas, the doses shall be as low as reasonably achievable and shall only be accepted
by the public not exceed 0.5 Sv/H or 5 mSv/Y.
• Contractor will ensure that radiation measuring devices in the workplace are provided.
• Ensure that all operating radiographic or X-ray equipment (inclusive survey meter)
possess a valid Government Radiographic License by The National Atomic Energy Agency
(BAPETEN). A copy of the license shall be submitted to Contractor’s HSE for review.
• Shall control that the radioactive work will not affect any system or operating process
and surrounding people, prior to commencing any radioactive work.
All project activities of Contractor in RDMP RU V Balikpapan has been included in construction
phase Environmental Impact Analysis (EIA) of Owner. The potential impacts on the environment
of the Contractor activities on this project shall be assessed and stipulated with Owner’s and
Government regulations particularly environmental regulations.
Contractor shall provide Policy, Procedure, and other document in line with Owner’s
environmental management plan and EIA of Owner in construction phase.
The following environmental plan will be developed and implemented during the project by
Contractor:
• Comply with all applicable environmental laws, regulations, rules, and codes governing
environmental requirements.
• Provide all documentation required by all levels of governing authority concerning
environmental requirements.
Provide and maintain effective planning and field control measures for the following activities:
Page 31 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Flammable
• Combustible
• Reactive
• Toxic
• Infectious
• Corrosive
• Poisonous
• Symbol and label shall be affixed on the hazardous chemical waste containers.
• The condition of the hazardous waste container/drum shall be inspected on a daily basis.
• Containers intended for hazardous waste disposal should not be used for other purpose.
• The waste should be kept at a proper temporary hazardous waste storage not more than
90 days.
• The hazardous waste temporary storage should be provided with license/permit from
authorized body.
• Contractor will provide third-party (who have license) to handle medical/clinic waste.
• Transfer of all hazardous wastes to a third-party should be accompanied by
manifest/document hazardous waste. Copies of document hazardous waste should be
maintained.
• Hazardous waste temporary storage shall comply with applied regulation and shall be
equipped with Fire extinguisher, PPE and spill kit equipment.
• Contractor shall provide Safety Data Sheet (SDS) for all waste of hazardous chemicals.
• Contractor will conduct basic waste management training periodically; this training must
be followed by personal who involved with waste of hazardous chemicals.
• Waste such as empty containers or drums with residue of flammable liquid should be
stacked in isolated area away from building and installation. Have notice displayed
forbidding smoking or naked lights. These containers should be thoroughly steam-
cleaned or washed before use.
Page 32 of 71
Doc. No.: 26071-100-G01-GHX-00002
• The Supervisor shall ensure the thickness of sand pot in good condition and inspect
periodically.
• No silica-based material will be allowed on site as storage or for use.
• Containment will be maintained at all times including during use, for 100% cleaning and
removal.
ASSURED GROUNDING
• Contractor shall ensure grounding system are provided to protect personnel and
installation against ground fault current, lightning and static discharge.
• Grounding system shall be installed and tested as per the standards.
• Only competence/certified person shall carry out electrical testing activities.
• PPE shall be used during working with electricity.
CAMERAS (SECURITY)
Detail of operational and deployment of CCTV camera is described on 26071-100-G01-GHX-
00003 Security Plan.
Page 33 of 71
Doc. No.: 26071-100-G01-GHX-00002
Lifting gears will be inspected regularly by Contractor Inspector and follow the colour
code inspection system.
Lifting plan will be applicable for critical lifting; non-critical lifting will be required
only the lifting calculation.
Rigging engineer will develop and prepare lifting plan and method statement then
submit to Contractor Sr. Rigging Engineer for review. Lifting plan and method
statement will be attached in PTW. This lifting plan would be submitted at least two
days prior to work execution.
• Contractor must ensure that all gas cylinders are to be labelled to indicate the contents of
the cylinder.
• Flammable and oxygen cylinders shall be fitted with flashback arrestor (adjacent to the
regulator) and reverse flow check valve (at the torch).
• Contractor shall develop an inspection schedule of the gas cylinder.
• All compressed cylinders must be kept clear of oil, grease or other hydrocarbons.
• Cylinders must be inspected for leaks and/or defects prior to use.
• Cylinders must not be exposed to sparks, slag, flame or other heat sources.
• Cylinders must be secured in an upright position during use and storage. They must be
secured by the use of Chain, (never use barricade tape or rope).
• Protective caps must be in place over valve stems when cylinders are in storage or when
not in use.
• Cylinders must not be taken into confined spaces.
Page 34 of 71
Doc. No.: 26071-100-G01-GHX-00002
• When cylinders are not in use, oxygen and fuel gas cylinders must be stored separately.
• Storage area for cylinders must be designated with signs stating” Oxygen Full or Empty,”
Acetylene Full or Empty,” etc.
The detail procedure related with welding and cutting activities using compressed gas cylinder
describe in Document No. 26071-100-GPP-GHX-00013 Cutting, Welding and Grinding
Procedure.
CONFINED SPACE
Confined Space means a space which:
Entry into a confined space shall only be contemplated as a last resort, after all other possible
options have been ruled out. Tasks to be carried out in a confined space shall be subject to a
Risk Assessment at the planning stage. If all other options for completing the work without
confined space entry are ruled out, task-specific controls shall be implemented to ensure it is
safe to carry out the work.
Before entering the confined space (sewer, drain, manhole, vessel, tank, or other enclosed area
with restricted entry and exit), workers must be trained and have an Entry into Confined Space
Permit.
Contractor shall identify the position(s) or person(s) responsible to coordinate entry operations
and permitting for the site(s). These people and their responsibilities shall be shown on the
Page 35 of 71
Doc. No.: 26071-100-G01-GHX-00002
Confined Space list. As a minimum confined space activity should have these following position
(s) or role (s):
• Authorized entrants.
• Standby Man/Person.
• Authorize Gas Tester.
• Entry Supervisor.
• To monitor entrants during the job and during entry & exit to ensure their safety.
• The standby person may not abandon his post for any reason while personnel are in the
space. In case he/she need to leave, he/she MUST contact their supervisor/foreman to be
replaced by another trained standby person.
• To control access to the confined space.
• To summon emergency assistance as needed.
• To assess hazards in and around the space, and act on the same.
• To keep records of confined space work, such as air test results, personnel entry/exit.
• Standby person can ONLY watch one confined space at a time and shall have no other
duties.
All workers involved in confined space entry must be adequately trained to acquire the
understanding, knowledge, and skills necessary for the safe performance of the duties and to
ensure that safe work procedures are followed.
Contractor shall identify the training required to comply with this procedure and provide
training to ensure employees have the necessary understanding, knowledge, and skills to safely
perform Confined Space duties.
Page 36 of 71
Doc. No.: 26071-100-G01-GHX-00002
The training shall develop qualified employees and shall be continually improved to address
changes in the Confined Space program.
4. Initial ventilation.
6. Continuous ventilation.
Page 37 of 71
Doc. No.: 26071-100-G01-GHX-00002
8. Rescue Plan (for high risk confined space activity based on Risk Assessment).
9. Permit to Work.
A competent Rescue Team shall be available and on alert for high risk confined space entries
(based on Risk Assessment). Rescue Team members should have ready access to Breathing
Apparatus sets or airlines, harnesses, line rescue and any other equipment necessary for safely
retrieving injured or collapsed personnel from the confined space. The Rescue Team response
time must be considered during the Risk Assessment and Planning stages of the job preparation.
Specific Confined Space procedure with project site condition shall be provided to ensure all
Confined Space activities can be carried out safely.
• Design for excavation > 1.5 m (5 feet) (including protection system) shall be developed by
Civil Engineer.
• Where the trench excavation is benched, the height between benches should not exceed
1.2 m unless designed by a consultant engineer. The overall width of the benched
excavation should not be less than the safe slope.
• Soil and materials must be kept at least 2 m from the edge of the excavation or transport
to another place to avoid landslide.
• For permanent retaining walls, check the overload capacity first.
• Support systems should only be erected, altered or dismantled by competent workmen
under supervision.
• Safe access must be provided into all excavations by means of ladders, ramps or stairs.
• Access ladders or other means of access shall be placed at regular distances (max. 7.5m) so
that workers only have to travel a short distance to escape if there any emergency
situations.
• Access ladders shall be placed at least 1 m protruding over surfaces and must be tied off to
prevent any movements.
• Climbing into or out of excavations using the waling and struts is prohibited. In narrow
trenches use vertical ladders.
• Walkways, bridges or ramps with standard guardrails must be provided where workers or
equipment are required to cross over excavations or trenches.
• At the edges of all excavations where a worker fall could occur ≥ 1.2 m, rigid barriers must
be erected or the excavation covered and clearly visible.
• Particular care is required where the public are required to cross over excavations. In a case
such as a footbridge, rigid hand railing must be provided with appropriate warning signs
advising of the hazards.
• Dewatering is necessary if the water table is less than 0.5m from the bottom of the
intended maximum depth of the excavation (i.e. more than 1.7 m depth)
Page 38 of 71
Doc. No.: 26071-100-G01-GHX-00002
• If the excavated pit or trench is deemed to be a Confined Space, the pit / trench shall be
treated as such and all Safe Working in a Confined Space shall be strictly adhered to.
ELECTRICAL SAFETY
Contractor provides a written procedure 26071-100-GPP-GHX-00006 Electrical Equipment and
Assured Grounding Procedure for detail.
• Contractor will ensure that all electrical tools such as portable tools, hand tools, and other
portable electrical apparatus, meet standard safety requirement.
• Contractor will use Ground Fault Circuit Interrupter (GFCI) and institute assured grounding
program.
• Temporary electrical installation including distribution boards, cabling, and switch gear
shall comply with the current wiring regulations. Hand lights carried into vessels shall not
exceed 12 volts, unless protection is provided by a Ground Fault Circuit Interrupter (GFCI).
• All required tests will be performed prior to first use and/or prior to the equipment is
returned to service following any repairs.
• Colour code standard will refer to Contractor standard in three months basis. Loose lifting
equipment shall be colour coded to indicate compliance with periodic inspection and / or
re-certification. The colour code will be affixed or painted onto the lifting gear.
• The following four colours, blue, orange, green and yellow will be used in rotation.
Page 39 of 71
Doc. No.: 26071-100-G01-GHX-00002
• All accidental fire on Contractor property, no matter how small, must be reported
immediately to the HSE Superintendent. The formal report should include all known or
reasonable summarized detail as an additional report may be required by government
agencies.
• The prevention of fires is of utmost importance. Good housekeeping and equipment
maintenance must be followed to keep fire hazards at a minimum.
• Contractor and Subcontractor shall provide gas detector if working in hazardous area, gas
detector that used will be calibrated annually.
• Contractor will conduct Fire Protection Training to employee. Storage and use of
flammable and combustible liquids will be per NFPA 30.
• All fire protection must be collected in designated area that are clearly identified with
appropriate marking. This equipment should be located near likely fire hazard but it must
also be accessible to operating personnel. The number type and location of extinguisher
must meet applicable standard.
• Partially used fire extinguisher must be discharger of pressure, recharged, or replace
immediately.
• All employee should be instructed in the proper use of available firefighting equipment.
Page 40 of 71
Doc. No.: 26071-100-G01-GHX-00002
and have a warning sign at the entrance indicating that no smoking or naked
lights are permitted.
• Any storage area, whether in the open or indoors, should have a portable fire
extinguisher (approved for Class B fires) available outside the entrance. This
extinguisher may be of the foam type, carbon dioxide type, dry chemical type
of liquefied gas (halon) type. Personnel must be trained in the use of the
extinguisher.
During flammable liquids are transferred from one container to another, there is a
possibility of static electricity build-up which is a dangerous ignition source. To
prevent build-up of static electricity, following requirements are required during
handling of flammable liquids:
If any personnel are splashed with a harmful or burning liquid, they must be taken
to a source of running water immediately and the splashed area should be flushed
with water for at least 15 minutes. Contaminated clothing should be removed and
medical attention sought immediately.
• Smoking shelter wall may provide however it should not fully close until the
roof. This is to ensure proper ventilation will be achieved and to prevent
flammable gas accumulation inside smoking shelter.
• Contractor must provide sufficient number of fire extinguisher at smoking
shelter.
• Minimum distance 100 m from process facility, pipe line, server, oil catcher.
• Smoking sign will be put at place.
• However, if any indication of hydrocarbon leaking, smoking will be prohibited
in smoking shelter area. Smoking sign will be replaced with No Smoking sign.
• Smoking shelter should be kept clean and tidy at any time. Contractor must
provide proper bins and periodically pick up smoking shelter rubbish. Treated
and dumped as waste.
• There will be one lighter provided on the shelter and it will be secured by
security personnel.
• This smoking shelter will be monitored by security personnel which must
standby there.
• Contractor must conduct periodical inspection of smoking shelter to ensure
the safety condition of this shelter.
Page 42 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 43 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Workers who working above 10m should check by site paramedic to ensure the fitness’s
of workers (blood pressure, height consultation & others check) before commence the
works.
• Working at heights will not be permitted without supervision from authorized persons.
• When required a permit to work shall be issued under the authorization of Construction
Manager.
• Verification of job completion will be done by Project HSE Manager/ HSE Chief/ Site Safety
Superintendent.
• Barricade tape can be used to warn of the hazard as long as personnel working on the
opening/hole attend the opening/hole.
• Permanent and temporary floor openings must have warning tags and standard guard
railing.
• Grating Removal permit shall be obtained prior to removing (for any reason) any
permanent or temporary floor openings (Grating, Checker Plate, Floor Plate, Stair Tread
or any Temporary Hole Cover) or standard guardrail, handrail system.
• Grating Removal permits shall be issued after visual inspection to the openings and assure
that the proper precautions have been taken.
• Floor holes into which persons can accidentally walk must be guarded by either a
standard railing with standard toe-boards on all exposed sides, or a floor hole cover of a
minimum 3/4” plywood if one dimension is 18” or less; otherwise 2” lumber is required.
The covering shall be secured against accidental displacement and clearly labelled “Floor
Opening — Do Not Remove”. At any time DO NOT leaving open holes without covering.
Page 44 of 71
Doc. No.: 26071-100-G01-GHX-00002
NO EQUIPMENT CERTIFICATION
1 Crane MIGAS / OIL & GAS (Government agency)
2 Truck Mounted Crane (TMC) MIGAS / OIL & GAS (Government agency)
3 Sky Lift MIGAS / OIL & GAS (Government agency)
4 Forklift MIGAS / OIL & GAS (Government agency)
5 Gondola MIGAS / OIL & GAS (Government agency)
6 Excavator DEPNAKER / MINISTRY OF MANPOWER
7 Dozer DEPNAKER / MINISTRY OF MANPOWER
8 Grader DEPNAKER / MINISTRY OF MANPOWER
9 Genset >200 KVA DEPNAKER / MINISTRY OF MANPOWER
10 Lifting gear such as webbing sling, chain, block, THIRD PARTIES
shackle, etc.
Table 7. List of Required Authority to Certify Heavy Mobile Equipment
• Vehicles shall not be older than 5 years for light vehicles and 10 years for trucks and
another heavy vehicle.
• All vehicles and heavy equipment’s must have reverse alarm installed.
• Contractor shall ensure that all vehicle drivers and heavy equipment operators are fit to
work and shall have a valid license for driving and/or operating issued by Government or
authorized institution.
• All heavy mobile equipment and vehicles must be in a safe operating condition at all
times. They are to be checked at the beginning of each shift. All heavy mobile equipment
and vehicles shall be attached by fire extinguisher, first aid equipment, seat belt and
flame/spark arrestor.
• The number of passengers of vehicles or equipment’s must follow the availability of seat
belt and it is prohibited to utilize the bed of truck and/or vehicles for passengers.
• Inspection to all heavy mobile equipment and vehicles will be done regularly. Inspection
Sticker will be attached to the heavy mobile equipment and vehicles after pass the
Inspection. With this sticker, equipment’s and/or vehicles permitted to be used at
greenfield and brownfield area.
• All heavy mobile equipment and vehicles to be used at RDMP JO will be manage to be
complied with RDMP JO Inspection procedure No. 26071-100-GPP-GHX-00026
Preventive Maintenance and Inspection Plant.
Page 45 of 71
Doc. No.: 26071-100-G01-GHX-00002
• The list of Chemical and Hazardous Materials to be used shall be available including Safety
Data Sheet (SDS).
• Required PPE as mention in SDS shall be used during handling with the chemicals.
• Required equipment and tools as mention in SDS to control any accidental release of
hazardous chemicals shall be provided.
• Before beginning a task where a hazardous substance is to be used, the risks, the
precautionary measures to be taken and the actions to be taken in the event of a spillage
(if applicable) or injury will be explained during the Pre-Job Safety Meeting (PJSM).
• It is recommended to use less harmful substances to minimise the risk to health and to
the environment.
• Only trained personnel should handle hazardous materials using the precautionary
measure that have to be taken, as instructed in the SDS.
• Used containers of hazardous substances/chemical will be disposed of as hazardous
waste.
• Hazardous chemicals will be disposed as per the instructions available in the SDS. Never
litter, or scatter used/empty chemical containers or used it for other storage purpose or
handling as it may be harmful to life and environment.
• Contractor must provide adequate eye-wash, shower and first aid boxes with medicines
at locations were hazardous chemicals are stored and handled, if deemed necessary.
Also, to ensure that it is well maintained and inspected regularly for defects or
malfunctioning.
• Employees are to be given information with regards to working with hazardous
substances and use and maintenance of applicable PPE. At minimum this shall be given
as part of the individuals Induction Training.
Page 46 of 71
Doc. No.: 26071-100-G01-GHX-00002
Page 47 of 71
Doc. No.: 26071-100-G01-GHX-00002
Contractor shall ensure to maintain portable ladders in safe condition. Ladders with the
following defects shall not be used, and shall either be tagged as unusable if kept on board, or
shall be removed from the site:
Ladders shall be inspected for defects before each day's use, and after any occurrence, such
as a fall, which could damage the ladder.
Contractor will conduct a portable equipment inspection program for portable construction
equipment used in the work, including portable ladders. Inspection Schedule will be:
Page 48 of 71
Doc. No.: 26071-100-G01-GHX-00002
Out of Service Tags (yellow colour) shall be attached to faulty equipment or out of service
equipment and shall be left attached until the equipment is repaired and ready for use.
All personnel who work in RDMP project must be worn mandatory PPE. The standard PPE that
must be worn are:
Page 49 of 71
Doc. No.: 26071-100-G01-GHX-00002
Respiratory protection All respiratory protection shall meet the requirements set out in ANSI
Z88.2 – 1992, filter respirator set out in BS EN 4275, 1997;
Airline mask BS EN 139, 1995; Self Contained Breathing Apparatus
(SCBA) BS EN 137, 1993
Hearing protection All hearing protection shall meet the requirements set out in ANSI S3.19
– 1974, all type of hearing protective shall be used
appropriately depend on noise level to protect noisy as state limit
Hand protection All hand protection shall meet the requirements set out in BS
EN 420:2003 + A1 2009 and Super Duty gloves for specific activity
Body protection One-piece coverall (grey colour) with Contractor name and personnel
name
Foot protection All foot protection shall meet the requirements set out in BS EN
345, 1993 ANSI Z.41
Fall protection All fall protection shall meet the requirements refer to ANSI
A10.14
Table 8. Personal Protective Equipment (PPE) Standard
PNEUMATIC TOOLS
Pneumatic tools include Chippers, Drills, Hammers, and Sanders. Pneumatic power tools shall
be secured by proper clamps and whip checks.
In addition to mandatory PPE, eye protection (goggles) or a face shield (with safety glasses or
goggles), and hearing protection are required for working with pneumatic tools.
Pneumatic tools may be used only by employees who are properly instructed and familiar
with these tools.
Employees must follow safe practices for operating pneumatic tools, including the following:
• Before assembling the system, check all hoses for cuts, breaks, and loose connections.
• Blow out all hoses before hooking up the equipment. If the connector has a rubber seal.
Remove it before (and replace it after) blowing.
• When possible, run air lines through areas with little traffic. If possible, avoid laying lines
across roads. Protect air lines or hoses against trucks and pedestrians either by building
Page 50 of 71
Doc. No.: 26071-100-G01-GHX-00002
runways over the hose or suspending the hose overhead with the lowest part of the hose
at least 7 feet (2 meters) above the ground.
• Tighten hammer-joint connections with a hammer. Do not tighten them by hand. Hoses
equipped with special connections require special tightening techniques or equipment.
One example is hammer-union connections, which must be tightened with a hammer.
Another example is spanner-wrench connections, who must be tightened with a spanner
wrench. Do not tighten these connections by hand.
• Do not turn on air valves until the hose connections are secure.
• Do not point an open-air hose at anyone.
• Compressed air shall not be used for cleaning purposes except where reduced to less
than 30 psi, and then only with effective chip guarding and proper personal protective
equipment.
• Unless the equipment has quick change connectors (with internal check valves), shut off
the air at the air supply valve ahead of the hose before breaking the connection.
Pedestal or bench mounted grinders shall have an emergency stop button and be fitted with
a properly adjusted tool rest. Pedestal grinders must be securely fixed to the floor to prevent
them from walking when in operation.
• Whenever possible, to secure below area of an elevated work location with barricade.
• Tools, equipment, material, etc., will be kept and arranged in an orderly manner and good
housekeeping will be practiced throughout the work day.
• Controlling/restricting the amount of material taken to the elevated work areas; only
stage/store what is needed to perform the task.
• Minimize hand carrying or handing material from person to person by hands.
• Use racks, baskets, containers, etc. to raise tools and materials.
• “Bundles” of long materials, such as scaffold tubes, will be banded together, rigged with
a minimum of two chokers/slings and will be kept horizontal.
• Loose material should be properly secured to prevent effect of wind.
• Scaffolding and work platforms shall require toe boards around the edge.
• Tools and equipment will be stored in appropriate containers/boxes to prevent dropped
objects.
Page 51 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Hot Work will not be performed overhead in areas where the potential for hot slags,
sparks or molten metal to contact employees working below without covering by fire
blanket or other similar protections.
• Tools, materials, will never be placed or stored on beams, pipes, valves unless they are
secured.
• Proper tool holsters shall be used when working at height/elevated area.
• All such facilities shall contain adequate number of suitable fire extinguisher. Contractors
must conduct periodical inspection to ensure fire extinguisher and others emergency
equipment maintained in good condition.
• Each facility shall have evacuation procedure posted at regular interval throughout. Shall
ensure that the facility evacuation procedures remain in clear view to all.
• All facility occupants shall be made aware of the evacuation procedures and the relevant
assembly/muster points for that facility.
• Lightning protection shall be provided to all such facilities. The electrical installation of
such facilities shall be approved standard and comply with the Contractor’s policy on
electrical installation.
• All emergency exits, shall be clearly marked by an A4 sized poster/notice. All emergency
exits shall remain free from obstruction at all time. Any obstruction found shall be
removed immediately.
• At no time will rubbish, refuse and combustible materials be permitted to accumulate
within any facility. All rubbish, refuse and combustible shall be removed from yard to a
designated tipping area. Open burning of rubbish, refuse and combustible material
generated by such facilities will not be permitted at any location within project boundary.
• Contractor shall provide adequate number of rubbishes, refuse and combustible
materials bins.
• Contractor shall provide all the facilities with adequate ventilation and lighting to prevent
injury or damage.
• All facilities must be kept clean and tidy at all time. Any spillage shall be cleaned
immediately.
• Contractor will provide Prayer room located at field and office area. Design and number
of Prayer room will be decided based on need at site. The Prayer room will be provided
with sufficient water for ablution tap and toilet. Cleanliness, hygiene and tap condition
must be maintained in good condition.
• Contractor must provide safe and adequate transport to pick up people from living
accommodation to the working area and vice versa.
• Contractor shall provide proper and adequate number of toilet and sanitation system.
• Contractor shall ensure the cleanliness and waste management in accordance with the
national regulation.
Page 52 of 71
Doc. No.: 26071-100-G01-GHX-00002
Such accommodation blocks shall be erected as far away from the permanent
works as possible.
Contractor must provide safe and adequate transport to pick up people from living
accommodation to the working area and vice versa.
Page 53 of 71
Doc. No.: 26071-100-G01-GHX-00002
maintained in a clean condition, at all times. Any defects found within the system
shall be rectified immediately
The user of each site ablution facilities shall discharge into a suitable designed
septic tank and soak way arrangement. All septic tank shall be designed to meet
demands from all site conditions. If at any time, septic tanks are found to be full or
overflowing they shall be pumped into a suitable tanker, immediately. The
resultant effluent shall be disposed of at an approved facility.
All Pressure Gas Cylinder (LPG) containers shall be stored outside the buildings,
except when in use.
Fly mesh shall be used at all window locations in an attempt to keep insects away
from the food preparation areas and the displayed food.
Food preparation areas shall be cleaned before and after each mealtime.
• The boundaries of critical work areas, excavation and others hazard must be clearly
delineated by visible barricade and signage.
• Hazard signage shall be posted in conspicuous place to warn workers about any hazard
that is present in the surrounding areas.
• Contractor shall ensure that employees understand with safety sign, colour coding and
barricade.
• Signage shall be well illuminated so that it could serve its purpose. Broken signage shall
be replaced immediately and maintenance of all hazard signage shall be performed
accordingly.
• Excavation and floor openings shall be barricaded with hard barricades instead of
barricade tape.
SCAFFOLDING
Detail procedure for scaffolding refers to document 26071-100-GPP-GHX-00021 Scaffolding
Procedure.
Page 54 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Work platforms must be equipped with standard guardrails, mid-rails and toe boards.
• Drop bars must be installed on all scaffolding deck/platform.
• Detail of scaffolding pipe specification and materials shall be followed Construction
Execution Plan (CEP) and in accordance with Contract.
• The uses of frame scaffolding for working at height platform are strictly prohibited.
• Movement of materials, tools, equipment, etc. to higher or lower levels will be affected
by hand line or hoist apparatus.
• Open sides and ends of platform 6 feet (1.8 meters) or more above will be guarded by
top rails, mid rails and toe boards with the top railing 42 inches (1.1 meters) above the
platform levels.
• Scaffolds must be erected plumb and on a solid foundation. Loose bricks, boxes, concrete
block, scrap lumber, etc. must not be used to level or support scaffolds or planks.
• All scaffolds must have an inspection tag placed at the point of access/egress by a
competent person.
• Employees, materials and tools must not ride on mobile scaffolds.
SIMOPS
SIMOPS is define as execution of 2 or more operations with potential interaction that could
lead to an increase of risk or introduction of new hazards to each other’s.
SIMOPS procedure and SIMOPS matrix should be established as a guideline to identify and
manage simultaneous activities. Construction will provide the SIMOPS procedure and SIMOPS
matrix with the participation of HSE and other required discipline.
Where there are major interfaces between Contractor, Sub-contractors and Operations, these
shall be managed by the Construction Management representative to ensure agreement and
clarity on SIMOPS.
Cutting Welding and Grinding or other flame or spark producing works are activities include
in hot work. All hot work activity shall be performed with hot work permit and job safety
analysis.
Hot work area shall be safe from flammable or explosive gases. Gas test shall be performed
before the job and continuously monitored until the job is completed.
Page 55 of 71
Doc. No.: 26071-100-G01-GHX-00002
Area within 10-11 meter from hot work shall be free from combustible material such as dry
woods, rubbish, fuel, and chemicals.
All personnel that perform cutting, welding, and grinding, including welder, fitter, and helper
shall be properly trained.
At green field area, most of the routine and not high-risk activities will use general work permit
with area/discipline wise, however JSA will use activity wise and shall attached to the PTW.
The details of the Contractor Work Permit System for Green Field area will be described on
document 26071-100-GPP-GHX-00001 Work Permit Procedure.
Contractor activities carried out at brownfield area will follow the Pertamina SIKA procedure
No. A-005/E15500/2016-S9.
• Contractor must ensure all workers are competent for the job assigned and completed the
training programs as per Training Matrix.
• Contractor’s Trainer are responsible to maintain the Training Program as per Training
Matrix (refer to Attachment 2.HSE Training Matrix).
• Training schedule shall be developed to ensure it complies with the minimum requirement
and in line with the construction stage (schedule).
• Training shall be conducted at classroom or practice.
Page 56 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Contractor must submit the HSE Training material to PMC for their review and approval, in
order to have alignment with Owner’s regulation.
• All training material shall be provided in dual languages which are English and Indonesia.
IIF® PROGRAMS
Incident Injury Free (IIF) programs is a commitment-based approach to addressing safety issues.
This approach has been known to transform work cultures, leading to improved relationships,
improved communication and improved safety numbers.
Basic principle of IIF program is “the relationship is the foundation of the accomplishment”, in
which the more the relationship between employees are strengthened, and the better results
can be achieved. This concept is conveyed to the individual employee via IIF orientation
programs, which also provides training for the frontline supervisors, since frontline supervisors
are strategically the key players of the programs.
The purpose of IIF is prevent harm to plant, environment and people. The focus of IIF program
is on leadership and culture. To measure the effectiveness of IIF program will be as following:
To achieve the target and maintain the focus of IIF, following programs shall be delivered:
COMPETENCY
Contractor develop HSE Training Matrix based on required HSE competencies for each Job Task
at project site. Refer to Attachment 2. HSE Training Matrix for the detail.
To increase personnel awareness on working safely, Construction Manager with HSE Manager
are responsible to ensure that all personnel have completed all training required as per Training
Matrix.
Training Sticker will be given to the participant who pass the assessment and this sticker must
be attached to their helmets. Database of employees training record shall be maintained and
used to track employee’s compliance to follow the required training.
TRAINING PROVIDER
• Since contractor will have activities at brownfield area, Owner will conduct in house
training for transfer knowledge of HSE system and requirements to Contractor.
• Contractor have responsibilities to deliver required HSE Training at project site.
Page 58 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Incident Injury Free (IIF®) Orientation is delivered by licensed third party and/or
Contractor’s HSE Trainer which hold Training of Trainer (TOT) for IIF® and
authorize/certified by licensed third party (JMJ) to conduct IIF® Training.
• Others than IIF® Orientation will be delivered by Contractor’s Competence HSE Trainer
which hold Training of Trainer (TOT).
Contractors will provide HSE Training centre to facilitate in house (at site) HSE Training. This
training centre will be located at Contractor’s temporary office and have capacity for 50
participants/trainee.
• At the end of training, training participant will be required to sign a personal declaration
which mention they are aware with the HSE matter delivered in the training and will give
their commitment to follow the HSE requirements. Trainee should pass the post-test
assessment to ensure that trainee understood.
Page 59 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Training participants who pass the assessment will be given with RDMP JO sticker to be
attached at the front side of their safety helmet.
• Training participants required to fill out the attendance list. This list will be registered to
the training database.
Direct supervisor of new & inexperience hire employee shall be responsible to the
familiarization of the project requirement include, but not limited to:
• JSA.
• Project HSE Plan.
• Safe work procedures/practice.
• Location of designated assembly point, muster point, windsock, lunch/break areas/shelter,
smoking areas, routes to and from work areas, etc.
After 30 days of mentoring program, status may be removed at the discretion of the
Construction Manager, subject to the following criteria:
Personnel who have not met the above criteria in the specified period require written approval
from the Construction Manager for continued access to the site.
16. COMMUNICATION
TOOLBOX MEETING (TBM)
Toolbox Meeting will be conducted by Contractor and Subcontractor in daily prior to the start
the activities at site. Contractor Discipline Superintendent is responsible for these meeting and
will ensure that all members of supervisor/work leader and workers are briefed on the following
prior to the start of any work activities:
Page 60 of 71
Doc. No.: 26071-100-G01-GHX-00002
• Today activities.
• Review for the tasks which have been carried out on previous day.
• Job distribution from each supervisor to all workers or team member. This is to prevent
misunderstanding and miss communication during execution of the job.
• HSE issues/concern, lesson learn, safety topics, etc. This is to remind and improve all the
members awareness concerning HSE aspects in their daily activities at site.
• Work supervisor.
• Foreman.
• Discipline superintendent.
• Engineer.
• HSE.
• Workers.
TBM could be done per group to make it effective and efficient. For example, TBM for civil
group, TBM for mechanical group, etc.
PJSM will be focus to discuss about the JSA prepared for the job/task and ensure all the
precautions mention in the JSA already in place.
Considering the number of HSE personnel and Discipline Superintendent will be not enough to
attend each PJSM, they shall prioritize to attend PJSM for high risk job/task such as:
• Job/task covered with specific PTW (not general PTW). i.e. Confined space, critical lifting,
etc.
• Job/task at brownfield area.
• Job/task with any change of working conditions, such as changes in engine conditions,
weather, personnel, execution time and work methods.
• Etc.
Page 61 of 71
Doc. No.: 26071-100-G01-GHX-00002
General Safety Talk will be done in weekly basis. Venue for General Safety Talk shall be decided
by consider Site Project condition such as availability of space to be used by staff & workers.
Basically, it is preferred to carry out General Safety Talk at one place for all staff & workers.
However, at peak project stages, it seems not practicable to do it. In this case the most effective
and efficient method will be decided. It is recommended that General Safety Talk will be divided
into several big group at several work places or every week General Safety will be scheduled to
attended by different Sub-contractors.
HSE representative from Subcontractor & Contractor (coordinator level) shall attend this
meeting. Contractor HSE Chief shall chair this meeting. The agenda and result of the meeting
will be documented and distributed to all participants.
Page 62 of 71
Doc. No.: 26071-100-G01-GHX-00002
Agenda for this meeting are as follow, but not limited to:
After the meeting, Contractor shall distribute meeting minutes to the following personnel:
Agenda of the meeting will include a communication of general HSE issues and requirements,
communication of any other pertinent information compiled from the previous month’s
activities, and sharing of lessons learned from other projects. All attendees will be required to
sign an attendance sheet for each meeting. Minutes of meeting shall be taken by Contractor.
HSE Information Boards will be used to display HSE Policy, slogans and other information as
statistics, awards, etc.
Page 63 of 71
Doc. No.: 26071-100-G01-GHX-00002
CHANNEL PURPOSE
7 Lifting Activity
9 Emergency
Table 9. HT Radio Communication Channel
Note:
The channels above can be changed and/or added depend on the situation at site
Situations that warrant a SWA may include, but are not limited to the following:
• A modification or alteration that deviates from the way the job task is normally performed
may cause unsafe work actions or conditions.
• Unscheduled or unplanned event that distracts workers from the job task being performed.
• Observation with safety impact. Whenever a worker observes a condition or situation that
has an impact on safety.
• Incomplete understanding. Whenever a worker or co-worker does not completely
understand instructions, procedures or ongoing activities.
Page 64 of 71
Doc. No.: 26071-100-G01-GHX-00002
The affected area(s) will be reopened for work by personnel with restart authority. All affected
workers and contractors will be notified of what corrective actions were implemented and that
work will recommence.
No work will resume until all issues and concerns have been addressed.
In the event of emergency, Construction Manager will be the person in charge from the
Contractor site. The project site PEHP will be aligned with Owner existing site CEHP. PEHP will
be explained more detail in Bridging Document of PEHP.
Contractor will include a process for identifying and reviewing potential emergency situation
and the mitigation and control events. In the PEHP will include as minimum, but not limited to
an emergency plan for rescuing personnel at the work site for the following events:
Train personnel by conducting regular emergency drills and exercises to test response
effectiveness.
In addition, the Emergency Response Guidelines are dynamic and must be renewed to maintain
their effectiveness in accordance with the developments and changes that exist.
Therefore, the Major Emergency Drill that involves all personnel must be carried out at least 1
(one) year. In addition, Minor Emergency Drill must be carried out at least 1 times per three
months.
Page 65 of 71
Doc. No.: 26071-100-G01-GHX-00002
Emergency Response Plan provided by Contractor shall cover all area within scope/boundary of
RDMP RU-V Project.
EMERGENCY SIREN
Below table describe emergency siren tones which informed the emergency situation.
6 minutes repetitive
2 Evacuation 6 min siren (Hi low tone)
Assembly points will be set at each point of work, if there are several work points in an area, it
will be agreed and marked as a flag with the initial’s "A" indicating the assembly point. Workers
and guests will be directed to the nearest muster point.
There are 3 muster points when an emergency occurs in the refinery area:
1. Gate V
2. Head Quarter Pertamina RU V
3. HSE Pertamina RU V Office
Page 66 of 71
Doc. No.: 26071-100-G01-GHX-00002
Contractor shall provide and socialize to all employee the location of Assembly Point, Muster
Point and Wind sock. These location (map) shall be informed at HSE Notice board located at site
and office area.
Page 67 of 71
Doc. No.: 26071-100-G01-GHX-00002
INSPECTIONS
Coordinated by Contractor HSE Chief, these inspections maybe conducted with assistance from
the Project Management team, Site Management team, Project HSE Committee team, etc.
The cause and corrective action shall be determined on e-COP report. Corrective Action
request shall be created after the audit report signed by observer. All observation and
closing status shall be registered.
Page 68 of 71
Doc. No.: 26071-100-G01-GHX-00002
Contractor Construction Manager has responsibility to ensure the audit attend by:
• Contractor & Subcontractor related discipline (refer the further topic and
schedule).
• Contractor & Subcontractor HSE.
During these programs, team members will do a walkdowns at worksite and observe
any unsafe action and condition. All team members shall take required immediate
action to close observed unsafe action and condition. Remaining issues which cannot
close at that time need to be registered into the findings list. The closing status for these
findings need to be updated to all team members regularly (e.g. every week).
Page 69 of 71
Doc. No.: 26071-100-G01-GHX-00002
Disciplinary actions shall be applied to employees who violate safety rules and
requirements up to accumulated penalty points.
Penalty point are accumulated as per type of violations classified into 3 types as follows:
Page 70 of 71
Doc. No.: 26071-100-G01-GHX-00002
21. ATTACHMENTS
Attachment 1. Project HSE Policy
Attachment 2. List of Regulations
Attachment 3. HSE Matrix Training
Attachment 4. CSMS Questionnaire
Attachment 5. HSE Program
Attachment 6. PPE Matrix
Attachment 7. Incident Process Flowchart
Attachment 8. HSE Organization Chart
Attachment 9. Change Management Request Form
Attachment 10. HIRAC Form
Attachment 11. JSA Form
Attachment 12. JHA Form
Page 71 of 71
ATTACHMENT 1. PROJECT HSE POLICY
RDMP BALIKPAPAN JO
Project Manager
ATTACHMENT 2. LIST OF REGULATIONS
HSEMS
NO REGULATIONS AND OTHER REQUIREMENTS ELEMENT/ CLAUSE
SECTION
Requirements
26070-203-G01-GHX-J0001-000 Health, Safety, Security, And
1 4.6 All
Environmental (HSSE) Plan
26070-203-G80-GAX-J0001-B01 Scope of Work and Execution
2 8.2, All
Requirements
13.9
Environment
General
Undang-Undang No. 32 / 2009 – Perlindungan dan Pengelolaan 1, 2, 3, 4, 13, 14, 20, 21, 53,
1 1 – 13 54, 57, 58, 59, 60, 67, 68, 69
Lingkungan Hidup
2 Peraturan Pemerintah No. 27 Tahun 2012 – Ijin Lingkungan 5 Pasal 53
3 PP No. 70 Tahun 2009 – Konservasi Energi 5 Pasal 7, BAB 3
Permen LH No. 13 Tahun 2010 - UKL - UPL dan Surat
4 Pernyataan Kesanggupan Pengelolaan & Pemantauan Pasal 2 - 9
Lingkungan Hidup 5
Hazardous Material
6, 8, 9, 12, 13, 15, 16, 17,
Peraturan Pemerintah No. 74/2001 – Pengelolaan Bahan
5 5, 9 18, 19, 20, 22, 23, 25, 27, 28,
Berbahaya dan Beracun 29, 30, 31, 39
Hazardous Waste
3, 4, 5, 7, 8, 9, 10, 11, 13, 14,
Peraturan Pemerintah No. 101/2014 – Pengelolaan Limbah
6 2, 5, 9 16, 29, 30, 31, 54, 55, 56, 57,
Bahan Berbahaya dan Beracun 58, 59, 60, dst.
Peraturan Menteri Lingkungan Hidup No. 14/2013 – Simbol dan
7 2, 5, 9 Poin B dan C
Label Limbah B3
Peraturan Menteri Lingkungan Hidup No. 18/2009 – Tata Cara
8 2, 5, 9 1, 2, 3, 4,
PerIjinan Pengelolaan Limbah Bahan Berbahaya dan Beracun
Keputusan Kepala Bapedal No. 01 Tahun 1995 – Tata Cara dan 1, 2, 3, 4, 5, Lampiran 1 No.
9 Persyaratan Teknis Penyimpanan dan Pengumpulan Limbah 5, 9 1, 2.1, 2.2, 3.1, 3.2, 4, 4.1,
Bahan Berbahaya dan Beracun 4.2, 4.3, 4.4,
Keputusan Kepala Bapedal No. 02 Tahun 1995 – Dokumen 1, 2, 3, 4, 5, Lampiran 1 No.
10 5, 9 1, 2, 3, 4
Limbah Bahan Berbahaya dan Beracun
Peraturan Menteri Lingkungan hidup - Simbol dan Label Limbah
11 5, 9 2, Lampiran
Bahan Berbahaya Dan Beracun
Peraturan Menteri Negara Lingkungan Hidup No. 03 Tahun
12 2008 – Tentang Tata Cara Pemberian Simbol dan Label Bahan 5, 9 2,3, 4, dan Lampiran 1 No.
B3
Surat Edaran Nomor : 08/Se/02/1997 - Penyerahan Minyak
13 Pelumas Bekas 5, 9 1 s.d. 6
Radioctive
Peraturan Pemerintah No. 61/2013 – Pengelolaan Limbah 1, 5, 6, 12, 13, 14, 15, 16, 17,
14 5, 9 20, 26, 30, 35
Radioaktif
KEPBAPETEN No. 01/Ka-BAPETEN/V-99 - Ketentuan 5
15 Keselamatan Kerja Terhadap Radiasi BAB II dan BAB IV
Water Resources
16 Undang-Undang No.07/2004 – Sumber Daya Air 1 – 13 1, 7, 8, 9, 10
Peraturan Daerah Provinsi Kalimantan Timur No. 2/2011 -
17 5, 9 BAB IV - VII
Pengelolaan Kualitas Air dan Pengendalian Pencemaran Air
Peraturan Daerah Provinsi Kalimantan Timur No. 14/2012 –
18 Pengelolaan Air Tanah di Kalimantan Timur 5 BAB II dan BAB III
Liquid Waste
Peraturan Pemerintah No. 82/2001 – Pengelolaan Kualitas Air 7,8, 9, 10, 11, 12, 16, 17, 25,
19 2, 5, 9 26, 34, 35, 37, 38, 41, 42,
dan Pengendalian Pencemaran Air
Peraturan Menteri Lingkungan Hidup No. 19/2010 - Baku Mutu
20 Air Limbah bagi Usaha dan/atau Kegiatan Migas Serta Panas 5, 9 TBA
Bumi
Keputusan Menteri Lingkungan Hidup No. 51/1995 – Baku Mutu
21 Limbah Cair Bagi Kegiatan Industri 5, 9 1, 2, 5, 6, 8, Lampiran C
Keputusan Menteri Lingkungan Hidup No. 122/2004 –
22 Perubahan Atas KepMenLH No. 51/1995 tentang Baku Mutu 5, 9 Pasal 1, 2, dan Lampiran
Limbah Cair Bagi Kegiatan Industri
KepMenLH No. 112 Tahun 2003 - Baku Mutu Air Limbah
23 Domestik 5,9 4,6,8 dan lampiran
I
N
T
S
Operator
R
Electrical / Instrument
I FREQU
Carpenter / Mason
Security Personnel
N ENCY
Heavy Equipment
Mechanical Fitter
C
Superintendent
I
Administration
General Labor
T
N
Pipe Fitter
Supervisor
Rebarman
U
Scaffolder
Inspector
Manager
Foreman
Surveyor
Engineer
G
Welder
Riggers
Painter
R
Visitor
Chief
E
1 HSE Induction for JO Daily M M M M M M M M M M M M M M M M M M M M M M M M -
Employee (Level 1) HSE Trainer
2 HSE Induction for JO As - - - - - - - - - - - - - - - - - - - - - - - - M
Visitor (Level 1) HSE Trainer required
3 Basic First Aid for JO As - O M M M M M O O O O O - - - - O O O O O O O - -
Employee Doctor/ required
(Level 2) Paramedic
4 Basic Fire Fighting JO Bi- O O M M M M M O M M O O O O O - M M M M M M O M -
(Level 1) HSE Trainer weekly
5 Hand & Power Tools JO Monthly - O - - - M M - - - - - - - - - O O O O O O - O -
(Level 1) HSE Trainer
6 Permit to Work JO As O O M M - M M - - O O M - - - - - - - - - - - - -
(PTW) HSE Trainer Required
(Level 1)
7 Hazard Identification, JO Weekly O M M M M M M - - M M M M M M O M M M M M M M M -
Risk Assessment, JSA HSE Trainer
Operator
R
Electrical / Instrument
I FREQU
Carpenter / Mason
Security Personnel
N ENCY
Heavy Equipment
Mechanical Fitter
C
Superintendent
I
Administration
General Labor
T
N
Pipe Fitter
Supervisor
Rebarman
U
Scaffolder
Inspector
Manager
Foreman
Surveyor
Engineer
G
Welder
Riggers
Painter
R
Visitor
Chief
E
Equipment (Level 1)
9 Confined Space JO As O O O O M M - - - - M - - - - M O O - O - O O -
(Level 2) HSE Trainer Required M
10 Scaffolder Training JO Weekly - - - - M O - - - - - M - - - - - - - - - - - - -
(Level 2) HSE Trainer
11 PEKA/e-Construction JO Daily M M M M M M M M M M M M M M M M M M M M M M M M -
Observation Program HSE Trainer
(Level 1)
12 Respiratory JO Daily O M M M M M M - M O O O O O O O O O O O M O O M -
Protection HSE Trainer
(Level 1)
13 Safe Driving Course JO Quarterly O O O O O O O - O O O - - - - M - - - - - - - - -
(Level 2) HSE Trainer
14 HSE Leadership JO Monthly M M M M M M M - - O O - - - - - - - - - - - - - -
(Level 1) HSEM/Chief
15 Hot Work JO Monthly - - M O O M O - - - - - - - - - M M M - M O - O -
(Level 1) HSE Trainer
16 Slinging, Rigging & JO Monthly - - M O M M - - - - - - M M M - - - - - - - - - -
Lifting Refreshment HSE Trainer
Training
(Level 2)
I
N
T
S
Operator
R
Electrical / Instrument
I FREQU
Carpenter / Mason
Security Personnel
N ENCY
Heavy Equipment
Mechanical Fitter
C
Superintendent
I
Administration
General Labor
T
N
Pipe Fitter
Supervisor
Rebarman
U
Scaffolder
Inspector
Manager
Foreman
Surveyor
Engineer
G
Welder
Riggers
Painter
R
Visitor
Chief
E
17 Incident Investigation JO Quarterly O M M M M M O - O O - - O - - - - - - - - - - - -
Training HSE Trainer
(Level 2)
18 Excavation Work JO Bi- - - M O - M M - - - - - - - - - - - - - - - - O -
(Level 1) HSE Trainer Weekly
19 Emergency JO Bi- O O M M M M M - M M M M M M M M M M M M M M M M -
Preparedness & HSE Trainer Weekly
Response
(Level 1)
20 Waste Management JO Bi- - O M O O M M - - - - - - - - - - - - - - - - - -
(Level 1) HSE Trainer Weekly
21 Electrical Safety JO Bi- - O M O O M M - - M - - - - - - - - - O M - - - -
(Level 1) HSE Trainer Weekly
22 Mechanical Safety JO Bi- - O M O O M M - - - - - - - - - - - M - - - - - -
(Level 1) HSE Trainer Weekly
23 Chemical & JO Bi- - O M O O M M - - M - - M - - - - - - - - - - - -
Hazardous Substance HSE Trainer Weekly
Handling
(Level 1)
24 Industrial Hygiene JO Quarterly - O M O O M M - - - - - - - - - - - - - - - - - -
(Level 1) Doctor/
Paramedic
25 Lock Out Tag Out JO As - O M O O M M - - - - - - - - - - - M - M - - - -
26
No
(IIF)
Note:
(LOTO)
O: Option
(Level 1)
(Level 1)
I
I
T
A
R
G
N
N
M: Mandatory
Incident Injury Free
I
E
T
T
S
R
C
R
U
U
N
3rd Party
HSE Trainer
Daily
ENCY
Required
FREQU
Manager
Chief
M M M
Superintendent
M
Engineer
M
Inspector
Supervisor
M M
Foreman
Administration
M M
Security Personnel
M
Surveyor
Scaffolder
M M
Riggers
M M
Welder
Pipe Fitter
M M
Mechanical Fitter
M
Carpenter / Mason
M
Electrical / Instrument
Rebarman
M M
Painter
M
General Labor
O
Visitor
ATTACHMENT 4. CSMS QUESTIONNAIRE
□ Perkakas Tangan / Hand Tools □ Mesin Las / Welding Machine □ Mesin Pilling / Pilling Machine
□ Alat Berat / Heavy Equipments (Dozer, Excavator, □ Tangga / Stairs □ Pompa / Pumps
Compactor, Grader)
□ Trailer, Lowboy □ Rigging/Hoisting □ Kapal Laut / Vessel
□ Truk / Truck □ Kompresor / Compressor □…
□ Crane □ Scaffolding □…
4. Material yang Digunakan / Materials Used :
Note: if more than one kind of work, you shall to attached CSMS documents as requested such as procedure , training , and certification related to each kind of work
Perwakilan Perusahaan,
Company Representative,
Nama / Name :
Tgl / Date :
ATTACHMENT 4. CSMS QUESTIONNAIRE
NO KUESIONER / QUESTIONNAIRE EVIDENCE / LAMPIRAN BUKTI NILAI / SCORE BOBOT / WEIGHT KETERANGAN / REMARK
I KEPEMIMPINAN & KEBIJAKAN K3LL / LEADERSHIP & HSE POLICY
Apakah perusahaan Anda memiliki kebijakan K3LL,
terdokumentasi & ditandatangani oleh pimpinan Salinan kebijakan K3LL perusahaan
1 perusahaan? 0 2
Does your company have HSE Policy, documented & approved
Copy of HSE policy
by Company Leader?
Who is the responsible person for implementing the HSE CV of the responsible person for implementing
management system at your company? the HSE management system at the company
Jelaskan bagaimana keterlibatan pemimpin perusahaan Notulensi rapat P2K3 mengenai peninjauan
Anda terkait dengan penerapan sistem manajemen K3LL? ulang sistem manajemen K3LL
4 0 2
Please, explain the involvement of your company leader P2K3 minutes of meeting about review of HSE
regarding HSE management system implementation? management system
NILAI TOTAL / TOTAL SCORE 0 8
II KEPATUHAN TERHADAP PERATURAN PERUNDANGAN K3LL / HSE REGULATION COMPLIANCE
Apakah perusahaan Anda memiliki organisasi P2K3 dan Struktur organisasi dilengkapi dengan
LL? nama
1 0 2
Does your company have HSE committee organization? Complete organization chart with name
Sebutkan tugas dan tanggung jawab masing-masing Tugas dan tanggung jawab masing-masing
personil dalam penerapan sistem manajemen K3LL di personil dalam penerapan sistem
perusahaan Anda? manajemen K3LL
2 0 2
Please, explain the job description of each personnel regarding Job description of each personnel in HSE
HSE management system implementation at your company? management system implementation
Apakah perusahaan Anda memiliki program Jamsostek / Salinan kartu Jamsostek / asuransi
asuransi kesehatan dan kecelakaan? kesehatan dan kecelakaan
5 0 2
Does your company have Jamsostek / health and accident Copy of Jamsostek / health and accident
insurance program? insurance card
ATTACHMENT 4. CSMS QUESTIONNAIRE
Apakah perusahaan Anda memberikan pelatihan kepada Matriks dan sertifikat pelatihan bidang
karyawan sesuai dengan lingkup pekerjaan? keahlian kerja
2 0 2
Does your company give training to employee related to the
Matrix and training certificate of work skill
scope of work?
NILAI TOTAL / TOTAL SCORE 0 6
IV MANAJEMEN SUBKONTRAKTOR / MANAGEMENT OF SUBCONTRACTOR
Apakah perusahaan Anda memiliki prosedur kerja sesuai Daftar dan salinan prosedur kerja sesuai
dengan lingkup pekerjaan? dengan lingkup pekerjaan
1 0 2
Does your company have working procedure related to the List and copy of working procedure related to
scope of work? the scope of work
Apakah perusahaan Anda memiliki prosedur identifikasi Salinan prosedur identifikasi bahaya dan
bahaya dan penilaian risiko? penilaian risiko (JSA, RA)
3 0 2
Does your company have hazard identification and risk Copy of hazard identification and risk
assesment procedure? assesment procedure (JSA, RA)
Apakah perusahaan Anda memiliki contoh JSA dan RA Contoh JSA dan RA sesuai dengan detail /
sesuai dengan detail / lingkup pekerjaan? lingkup pekerjaan
4 0 2
Does your company have an example of JSA and RA related to Example of JSA and RA related to the detail /
the detail / scope of work? scope of work
ATTACHMENT 4. CSMS QUESTIONNAIRE
1 0 2
Does your company carry out the general workplace Evidence of HSE inspection (min: 2 inspection
inspection? periods)
ATTACHMENT 4. CSMS QUESTIONNAIRE
4 0 2
Does your company do inspection for working equipments? Equipment inspection schedule and result
Apakah perusahaan Anda memiliki sarana komunikasi Contoh HSE news , HSE bulletin , HSE Alert
K3LL lainnya? (HSE news , HSE bulletin , HSE Alert dll) dll
3 0 2
Does your company have other HSE communication tool? (HSE Example of HSE news, HSE bulletin, HSE Alert
news, HSE bulletin, HSE Alert etc.) etc.
NILAI TOTAL / TOTAL SCORE 0 6
IX TANGGAP DARURAT / EMERGENCY RESPONSE
Does your company do the emergency drill regularly? Emergency drill report
2 0 3
Does your company carry out HSE internal audit? Schedule and report of HSE internal audit
0 100
Minimal Skor kelulusan Offshore 70
Minimal Skor kelulusan High Risk 60
Minimal Skor kelulusan Low Risk 50
Date:
Prepared by, Reviewed by,
(Name) (Name)
(Position) (Position)
ATTACHMENT 5. HSE PROGRAM
RDMP BALIKPAPAN JO
HEALTH & SAFETY PROGRAM
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Communicate HSEpolicy and procedures to all employees, sub-Contractors, COMPANY and other stakeholders as appropriate to ensure them
aware of their obligations with respect to Contractor’S operation.
1 Conduct orientation / induction for HSEManagement Plan and 1. Project All project Contractor Staff, Personal induction record New hire employees, CM, HSE Chief, HSEM
employees, SubContractors and visitors to CSMS Induction SubContractor Staff and visitor is maintained. Transferred
the site. Requirement Guideline. employees and visitor
2. Project Staff
Induction Record.
2 Conduct regular meetings with Contractor Project HSE Plan related Daily Tool Box A HSE discussion for each Record of Daily Tool Box Every starting of shift Site Supervisor, Discipline
staff, SubContractors and client to discuss Communication Procedure Meeting group on worker readiness, Meeting for attendance work Superintendent
HSE work plan for that day and and topics.
issues. possible JSA.
Site top management
have to attend this daily
tool box meeting
Weekly Construction progress Minutes of meeting Weekly Construction Manager
Construction coordination and discussion record with HSE as the
Meeting meeting, include HSE issues first agenda
Safety Committee Discuss HSE issues and Project Minutes of Meeting of Monthly Construction Manager
Meeting progress record and attendance
record
General safety A HSE discussion for All worker Make topics schedule and Weekly Construction Manager, HSE
talk on project record for Attendance list Manager
3 Ensure employees receive safety training Project HSE Plan Internal Training Training Nomination Form Form to signed off by Every time proposing General Superintendent /
appropriate to their task and Course must be filled out prior to any Project Manager prior to to attend a course Construction Manager
responsibility training taking place training taking place
Training Records have to be kept of all Training attendance sheet At every training Project HSE Admin. or HSE Chief
Attendance Sheet persons attending training completed course
Training Register Records have to be kept of all Training attendance sheet At every training Project HSE Admin. or HSE Chief
persons attending training completed course
4 Establish Health, Safety, and Project HSE Plan, HSE Safety Notice Display all policies, Safety Safety notice boards are Monthly Project HSE Admin. or HSE
Environmental promotional material to Communication and Board minute of meeting, review placed in each work areas Coordinator
improve the employee awareness Training Procedure result of inspection, incidents, and displaying
audits and others
RDMP BALIKPAPAN JO
4 Establish Health, Safety, and Project HSE Plan, HSE HEALTH & SAFETY PROGRAM
Environmental promotional material to Communication and
NO improve
HEALTHthe&employee
SAFETY ACTIVITY
awareness
PLAN / Training
PROCEDURE
Procedure
/ APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Safety Display project performance HSE performance board Update Weekly Project HSE Admin. or HSE
Performance review against its objective placed in front of REK Coordinator
Boards and target office and displaying
project performance
review result
Safety Alerts A Safety Alert shall be Safety Alerts produced Each occurrence PM, CM, HSE Chief or HSEM
produced for high actual or and displayed
potential incidents
Follow up all relevant Follow up action As Job condition PM, CM, HSE Chief or HSEM
corrective action of incoming incorporated into the require
safety alerts from other Project HSE Plan
projects
Cautionary and Develop and display relevant Cautionary and warning Once when it's CM, Discipline Superintendent
Warning Sign cautionary and warning sign signs developed and determined
(list of warning sign like tape displayed on the
barricade, etc.) hazardous work places
Comply with all applicable HSE laws, regulations, and statutory obligations.
5 Ensure that we are fully informed of all None Legal Gap Review all relevant legal Legal Gap Analysis is At start of project and CM, Discipline Superintendent
applicable health and safety laws, Analysis aspects project such as: developed and reviewed. as a result of any
regulations, statutory obligations and relevant statutory amendments to
Company Safety requirement and comply requirements, contractual Project procedures or legislations and client
with those laws and regulation requirements and Company working instruction may requirements
HSE requirements be developed to fill the
gap.
Ensure that health and safety management and practices are incorporated into all aspects of Contractor operations
6 We will analyze all areas of our activity Project HSE Plan and HSE JSA & Risk Identify all common hazards Conceptual Risk At start of project / Site Supervisor, Discipline
and identify the risk level Register Assessment and risks, which are associated Assessment is developed every starting of job Superintendent
with each project activity
7 Where those procedures are not Project HSE Plan and HSE Job Safety JSA must be completed for Completed JSA Prior to start of the Site Supervisor, Discipline
applicable or suitable develop, implement Register Analysis new jobs and high-risk jobs. jobs Superintendent
and maintain specific workplace
procedures to ensure operations are
conducted in such a manner that
eliminates the risk of injury, illness or
damage.
JSA Review Ensure all JSA's are suited to JSA Review report During the job in HSE Chief
jobs carried out progress
7 Where those procedures are not Project HSE Plan and HSE
applicable or suitable develop, implement Register
and maintain specific workplace
procedures to ensure operations are
conducted in such a manner that RDMP BALIKPAPAN JO
eliminates the risk of injury, illness or HEALTH & SAFETY PROGRAM
damage.
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Workplace Carry out workplace hazard Checklist of workplace As per schedule Project Supervisor and HSE
Hazard Inspection inspection for each project hazard inspection is Chief
work area completed, followed up
and closed out
Seek to achieve the personal commitment of all employees, sub-Contractors and suppliers to HSE workplace practices.
8 Investigate a workforce safety Project HSE Plan Project Safety Safety Incentive criteria is Safety Performance is Monthly CM
performance incentive scheme Incentive Scheme established and communicated monitored and reviewed
by committee
9 Involve the workforce in the Project HSE Plan Project HSE Regular meetings, which Minutes of meetings is Monthly CM
implementation of the safety program Committee attended all member of produced and
through the formation of a workplace project safety committee. communicated
safety committee
Regular inspection, which are A checklist for this Monthly HSE Chief
to carried out by all member of inspection is developed
project safety committee. and completed
10 Provide Leadership on all issues of safety Project HSE Plan Workplace Carried out a workplace hazard A checklist of this Monthly Discipline Superintendent,
management Hazard Inspection inspection for their own area inspection is completed, Project Supervisor
of responsibility followed up and closed
out by relevant
signatories, 85 % close out
action
Project HSE All signatories take a part in Signatories attended on Monthly CM
Committee Project Safety Committee, if meeting and recorded.
appointed as a member of it Take a part on inspection
Tool Box Meeting All signatories involved in this Signatories attended on Daily Site Supervisor, Discipline
meeting on their own area of meeting and recorded. Superintendent
responsibility
Safety Talks All signatories involved in this Signatories attended Weekly CM, HSE Chief
meeting. meeting and record
Weekly All signatories involved in this Signatories attended on Weekly CM
Construction meeting, with "safety" as the meeting and recorded.
Meeting first agenda of meeting.
RDMP BALIKPAPAN JO
HEALTH & SAFETY PROGRAM
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Provide HSE risk management systems and procedures that are relevant to the nature and scale of work undertaken
11 Ensuring that operations are carried out Project HSE Plan and HSE Standard Developing specific standard Standard Instruction is All works shall CM, HSEM
according to standard Contractor Register Instruction instruction or review existing developed, covered by standard
procedures or template standard communicated and instruction
instruction to be suited to the maintained
works
Permit to Work A restriction and limitation to Excavation Permit, As required CM, HSE Chief
personnel in carrying out the Working at Height Permit,
works known as a high risk Radiography Permit, Hot
Permit to Work, Entry Into
Confined Space Permit,
Electrical Permit to Work,
Crane Permit, Cold Permit
to Work
Job Safety JSA must be completed for Completed JSA (Job Safety Prior to Site Supervisor, Discipline
Analysis (JSA) new jobs, risk jobs, or jobs that Analysis) commencement of Superintendent
are not covered by SOP or the jobs
Standard Instruction prior to
commencement of the jobs
JSA Review Ensure all the jobs are carry JSA Review report, During the job in HSE Chief
out in accordance to JSA Updated JSA revision progress
number
12 Risks to health, safety and environment Project HSE Plan Pre-start Inspection of all equipment Checklist completed Before mobilize to site CM, HSE Chief
will be dealt with by elimination, or inspection must be carried out
removal, substitution, design, redesign, or
separation, administrative and personal
protection
Preventive All plant and equipment are Checklist completed As per Schedule Project GSI and Mechanical
Maintenance scheduled for maintenance Supervisor
Inspection
Workplace Carry out workplace hazard A checklist of this weekly Discipline Superintendent,
Hazard Inspection inspection regularly inspection is completed Project Supervisor
and closed out
13 Provide risk identification and Risk Register Job Safety JSA must be completed for Completed JSA Prior to Site Supervisor, Discipline
management in their work areas Analysis new jobs, risk jobs, or jobs that commencement of Superintendent
are not covered by SOP or the jobs
Standard Instruction.
RDMP BALIKPAPAN JO
13 Provide risk identification and Risk Register HEALTH & SAFETY PROGRAM
management in their work areas
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
JSA Review Ensure all the jobs are carry JSA Review report, During the job in HSE Chief
out suited to JSA Updated JSA revision progress
number
Hazard Reporting Supervisory staff to enforce Hazard report is Every Day Site Supervisor, Discipline
the reporting of hazards that produced. Superintendent, HSE
may arise before, during and Superintendent
after the works Hazard register is
maintained.
Corrective Action is
recorded.
14 Ensuring that operations are carried out Project HSE Plan Standard Developing environment Standard Instruction is All works shall CM, HSEM
according to environmental standard Instruction (SI) standard instruction or review developed, covered by standard
and Work existing or template communicated and instruction
Instruction (WI) environment standard maintained
instruction to be suited to the
works
Set measurable targets and seek to continually improve our HSE performance
15 Set the Safety Performance targets for the None To do better that the Safety Statistic Twice a Month CM
project corporate target: LTIFR <1, Performance, HSE
LTISR < 1.0, with Fatality=0, Evaluation
Medical Treatment =0
Property Damages =0,
Project Safety Environmental Damages = 0,
Performance HSE Performance min 90
Target (based on HSE Evaluation
Corporate HSE Audit Target is reviewed and As per schedule CM
compliance rate minimum 90 communicated
Audit internal project Target is reviewed and Monthly CM
minimum 1 sub- Contractor communicated
per month
RDMP BALIKPAPAN JO
HEALTH & SAFETY PROGRAM
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Periodically review and revise our HSE Policy and procedure to maintain Contractor relevance
16 Conduct assessment and review of key None Assessment HSE Formal review of the Action plan from the Every 3 months or as HSEM
personal HSE in implementing HSE Management implementation HSE review required
Management System System Checklist Management System and
performance Project Manager
or HSE Chief
17 The Project will be audited regularly Project HSE Plan Corporate HSE Corporate HSE audit shall be Corporate Audit Report As per schedule CM
Audit conducted on a regular basis
Internal Safety Every workplace shall be Internal site HSE audit Monthly CM, HSE Chief, HSEM
Audit audited against the HSE plan
by internal audit
Prepared for emergencies and response quickly, effectively and with care to incidents resulting form Contractor operation
18 Undertake and establish Emergency Project HSE Plan Emergency Develop emergency response Plans are regularly Every Six-Month CM, HSE Chief
Preparedness Response Plan plan and maintain its reviewed. The
preparedness and equipment preparedness emergency
equipment is checked
regularly
Emergency Ensure all personnel involved ERP Training will be given Before project start HSEM, Owner HSEM
Response in Emergency Response Team to Site Project Team by
Training have been trained in ERP Owner
Emergency Practice the Plan by simulating A written emergency Quarterly PM, CM, HSE Chief or HSEM
Rehearsal an emergency situation rehearsal report
Site Medical First Aid Facilities to manned Medical Kit is maintained Every Week Paramedic
Services and per day (Working Hours) by and completed
Ambulance trained medic / paramedic
Rehabilitation Ensure that rehab plan is Completed Rehab Plan Every Rehabilitation CM, HSE Chief
Plan developed and agreed to by Case
employee
Prepared for Exercise Program
19 Conduct Exercise Program None Gym or Exercise All signatories involved in this Signatories attended this Weekly CM, PM, HSE Chief
Gym or Exercise Gym or Exercise
Rules and Regulations at Site
Safety Notice All contractor Staff, Result of Monitoring Monthly CM, HSE Chief
No smoking at office site and working
Board and Project SubContractor Staff and visitor
20 area, use drug and alcohol and carry Project HSE Plan
Induction
weapon
Drug Test Random drug test Drug test result Random (Weekly) HSE Chief & CM
RDMP BALIKPAPAN JO
HEALTH & SAFETY PROGRAM
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Selection of SUBContractor
21 Conduct selection our Sub-Contractor Project HSE Plan HSE Questioner All sub-Contractor Result of questioner High Validity every 2 years Project Manager, Project
(CSMS) Risk Category > 60, 35 – Procurement Manager and
59 : Low Risk Category Project HSE Manager
In monitoring implementation HSE None HSE Report Form Implementation HSE Completed HSE Report Monthly HSE Chief
Management System at project site. Management System, Man- Form
Request project team to provide HSE Hours, Man- power, Total
Report Accident for all employee of
Contractor and All
SubContractor
Health Program of RDMP Project
25 Conduct General Medical Check-up for all Project HSE Plan General Medical All employee of Contractor Result of General Medical As required Project Manager and
new employee of Contractor Check-up Form assigned to the Project Check-up Construction Manager, Health
Coordinator
26 Conduct General Medical Check-up for Project HSE Plan General Medical All employee of Sub Contractor Result of General Medical As require CM, Medical Advisor
Sub Contractor Supervisor to Up level Check-up Form Supervisor to Up level who Check-up
assign to the Project
27 Conduct General Medical Check-up for all Project HSE Plan General Medical All employee of All Sub Result of General Medical As require CM, Medical Advisor
Sub Contractor employee Contractor Check-up
Check-up Form
employee who assign to the
Project
28 Vital Check for high risk worker Project HSE Plan Vital Check Blood pressure check for high Daily check for high risk Daily Medical Advisor & HSE Chief
risk worker worker, no indication of
high blood pressure
Incident Injury Free® Program
RDMP BALIKPAPAN JO
HEALTH & SAFETY PROGRAM
NO HEALTH & SAFETY ACTIVITY PLAN / PROCEDURE / APPENDIX TOOLS WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
29 To implement IIF® program to the entire Project HSE Plan IIF® Program Engage JMJ, start implement Activitities report as required (see PM, CM, HSE Chief or HSEM
EPC RDMP Balikpapan Project IIF ® Program at RDMP (Training attendees, attached table)
Balikpapan Project observation etc)
RDMP BALIKPAPAN JO
ENVRONMENTAL PROGRAM
NO ENVIRONMENTAL ACTIVITY PLAN / PROCEDURE / APPENDIX WHAT’S TO BE DONE? HOW DO WE CHECK? FREQUENCY PRIMARY RESPONSIBILITY
EXPECTATION REFERENCE
Control the schedule waste - Master List and inventory of As required CM, Discipline Superintendent,
management (Hazardous Chemical scheduled waste, - Storage of HSE Chief
Material) and provide MSDS at site. hazardous waste, - COMPANY
for handling waste schedule
must registered by
1 Waste Management Control Project HSE Plan
Government.
Control the non-schedule waste Weekly monitoring form Weekly HSE Chief, Discipline
through organic and non-organic completed Superintendent
waste
2 Liquid Spill Control Project HSE Plan Provide oil container and oil traps by Monitoring form completed Monthly CM, HSE Chief
the site drainage
3 Communicate Contractor Project HSE Plan All project Contractor staff, Induction record, Record As required CM, HSE Chief
Environmental Policy & Procedure SUBContractor staff and visitor daily tool box meeting,
minute of meeting and
attendance all HSE Meetings
4 Ensuring that operations are carried Project HSE Plan Developing environmental standard Standard instruction is All works shall covered Site Supervisor, HSE Chief
out according to environmental instruction or review existing or developed, communicated by standard instruction
standard template environmental standard and maintained
instruction to be suited to the work
5 Conduct accident investigation and Project HSE Plan All major and minor accident Complete accident and As per event for CM, Discipline Superintendent,
reporting investigation form investigation and 1 x 24 HSE Chief
hours for accident
reporting
6 Rules & Regulation at site: use drug Project HSE Plan All project Contractor staff, Result of monitoring Monthly CM, HSE Chief
and alcohol and carry weapon SUBContractor staff and visitor
7 Encourage behavior awareness Project HSE Plan All unsafe act and unsafe condition Complete unsafe act and Every Day All Project Team
unsafe condition form
ATTACHMENT 6. PPE MATRIX
1. VISIT SCENE 1. Check Investigator’s Safety All Wearing PPE, protect Information at scene, JSA of investigation site
Continue Collecting Evidence
1.
2. PROTECT 2. Gather evidence that might disappear from rain of work activities
2.
3.
4. Information Collection
People, Equipment, Environment, Systems:
4.
5.a Incident Description,what happened , who Injured/Involved, time of incident,
5. SEQUENCE OF
EVENTS
9. DETERMINE Must know determine which are the main factors to highlight in the report and undertake Corrective
CONTRIBUTING actions. Focus on those factors for which:
FACTORS The incident would not have happened if the factors were not present
There are practical actions to prevent recurrences
10. List actions for each contributing factors and By Who? And By When?
11. Conduct review to ensure all the facts are correct and everyone is in agreement with the findings
11. SITE REVIEW
and proposed actions
11. List names of people in review
Company/Department: Date:
Change Initiator:
No. Determine nature of the change. Does the proposed change: Y N N/A
1 Alter existing or introduce new plant and/or equipment?
2 Any change to a Contractors or Sub Contractors SoW?
3 Alter existing or introducing of a new Safe System of Work?
4 Modify material used (i.e. properties, composition, etc.)?
5 Introduction or Change to a fixed alarm and set point?
6 Alter the organisation structure, roles and responsibilities?
7 Any change to the operating controls or DCS logic philosophy?
Alter or add processes, plant or equipment requiring new skills, knowledge or
8
procedures.
9 Alter programmable electronic software and settings?
10 Alter the design/plan/layout of roads, excavations, services and facilities?
Alter the ergonomics specifications of the equipment, plant or activity (i.e. weight
11
to be lifted, pressure exerted, posture, etc.)?
12 Affect the emergency response and ability to raise alarm?
Increase levels of exposure to temperature, noise, dust, fumes, gas and/or
13
vibration generated?
14 Create new environmental emissions eg dust, noise, waste, sediment?
15 Alter land use (disturbance of mining, non-mining and rehabilitated areas)?
16 Alter energy use or greenhouse gas emissions?
17 Alter the impact to community (i.e. lighting, noise, dust, etc.)?
18 Require new or modified approvals, licenses or permits?
19 Be in conflict with any company or legislative requirements?
If one or more “yes” boxes are ticked, then the change management form is to be completed.
1 of 6
Change Management Request Form
2 of 6
Change Management Request Form
List any Technical Experts that need to be consulted on the proposed change.
List systems, policies, procedures, plans, schedules, competencies, etc this change effects.
3 of 6
Change Management Request Form
SUBMISSION
CHANGE INITIATOR:
STEP 6: APPROVAL
STAGE 6.1
TECHNICAL EXPERT (HIGH RISK)
4 of 6
Change Management Request Form
Change
Minor Serious Major
Consequence Type
Serious
Impact on safety/harm Single or multiple
Low level injury/permanent
to people Permanent loss of fatalities or
symptoms disability or
working ability, irreversible
requiring first aid impairment to one
irreversible impacts to multiple
treatment only. or more persons.
damage. Localised people.
Working conditions Serious reversible
outbreak of Widespread
causing discomfort health effects
infectious disease outbreak of
or strain. requiring medical
infectious disease.
treatment.
Localised medium
Environmental impact Wide spread /
Limited damage term damage to an
significant long Significant,
contained to a area of local value
term damage to extensive &
localised area, with reversible with
valued area, permanent impact.
no lasting impact. medium term
reversible with Loss of permit to
Nuisance local remediation.
long term operate. Loss of
impact (eg dust, Directive from
remediation. endangered
noise) with no regulator resulting
Suspension of species.
complaints. from nuisance
operations.
impacts.
Impact on Schedule < 1 day 1-4 weeks 4-12 weeks > 12 weeks
LEGEND: LOW
MEDIUM
HIGH
5 of 6
Change Management Request Form
ACTION PLAN
· All agreed actions are to be entered into Code No. for tracking.
· Each action plan is required to have an action to review the effectiveness of the change at an agreed period following the change.
# Change item Nature of item and change Action review effectiveness Who When Code No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
6 of 6
ATTACHMENT 10 HAZARD IDENTIFICATION RISK ASSESMENT & CONTROL (HIRAC)
HIRA Registration No. : Prepared by: Reviewed by: Reviewed by: Reviewed by: Approved by : Risk Category
Revision No. :
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
10
ATTACHMENT 11
Note : * : Without Control / Tanpa control *): With Control / Dengan control
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
On what conditions, job changes or distraction will this activities temporarily stop?