ITP Steel Structure Work Rev.0 - WTL - P.pea - PP Comment
ITP Steel Structure Work Rev.0 - WTL - P.pea - PP Comment
Item
Acticity Characteristic to be verified INSPECTION FOR REFERENCE DOCUMENT REPORT FORMAT REMARKS
1 of 4
Inspection and Test Plan for Steel Structure Work
Item
Acticity Characteristic to be verified INSPECTION FOR REFERENCE DOCUMENT REPORT FORMAT REMARKS
1.3.2 Surface Preparation 1.Surface check and remove all grease and oil contamination before blasting H S R
2.Check compressor air free from water & oil H S R
3.Surface condition shall be over Sa 2.5 after blasting H S R
1.3.3 Painting 1.Check the paint mix rate and condition H S R
Manufacturer recommends Supplier
2.Check the temperature and humility<85% H S R
3.Check the paint dry and curing time H S R
4.Check Final DFT H W R
1.3.4 Material storage 1.Material storage control list H R R
1.3.5 Release to Site 1.Check document concern to steel structure fabrication and MEMBER marking for identify H R R FM-118
Complied with engineering DWG
2.Notification to WTL/SCOT before 24 days H R R FM-100
2 of 4
Inspection and Test Plan for Steel Structure Work
Item
Acticity Characteristic to be verified INSPECTION FOR REFERENCE DOCUMENT REPORT FORMAT REMARKS
3 of 4
Inspection and Test Plan for Steel Structure Work
Item
Acticity Characteristic to be verified INSPECTION FOR REFERENCE DOCUMENT REPORT FORMAT REMARKS
Documentation
3.1 QA/QC Documentation 1.Submit as-built DWg H R R
2.Final document submit all of inspection records & mill certificate whole package H R R
Complied with engineering DWG
3.Clear all outstanding punchlist H W R
4.Turnover pack preparation and handover to shell for system mechanical complition H R R
4 of 4