Professional Documents
Culture Documents
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
Operation and Maintenance of Field Office for As Submitted #REF! 5.46 month
A.1.1(16)
the Engineer As Evaluated
As Submitted #REF!
TOTAL OF PART B
As Evaluated
PART B OTHER GENERAL REQUIREMENTS
As Submitted #REF! - L.S.
B.3 Permits and Clearances
As Evaluated
As Submitted #REF! 1.00 L.S.
B.4(10) Miscellaneous Survey and Staking
As Evaluated
As Submitted #REF! 3.00 each
B.5 Project Billboard/Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S.
B.7 (2) Occupational Safety and Health Program
As Evaluated
As Submitted #REF! 1.00 L.S.
B.9 Mobilization/Demobilization
As Evaluated
As Submitted #REF! 1.00 L.S.
B.23 Staging Area
As Evaluated
As Submitted #REF!
TOTAL OF PART B
As Evaluated
BLUE BOOK VOLUME III
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART B PLAIN AND REINFORCED CONCRETE WORK
As Submitted #REF! 11,303.90 Kg
902(1)a Reinforcing Steel (Deformed), Grade 40
As Evaluated
As Submitted #REF!
TOTAL OF PART B
As Evaluated
PART J FLOOD CONTROL AND DRAINAGE
Part I-A EARTHWORK
As Submitted #REF! 633.800 sq.m.
903(2) Formworks and Falseworks
As Evaluated
As Submitted #REF! 559.50 kg
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 753.60 kg
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF!
TOTAL OF PART I-A
As Evaluated
PART I-B BANK AND SLOPE PROTECTION WORKS
CHB Non Load Bearing (Including Reinforcing As Submitted #REF! 76.20 sq. m.
1046(2)a1
Steel), 100mm As Evaluated
As Submitted #REF!
TOTAL OF PART I-B
As Evaluated
As Submitted #REF!
GRAND TOTAL
As Evaluated
Page 1 of 119
Republic of the Philippines
Department of Public Works and Hig
Region VII
CEBU 4TH DISTRICT ENGINEERING
Poblacion, Dalaguete, Cebu
EAO :
0 DA 0.0 %
0 LIP 0 % 2
1 GAA (INFRA, DOT, DTI) 2 %
EAO for Project = 2%
PROJECT LOCATION :
Loaded Trip
Speed = 30 km/hr
Unloaded Trip
Speed = 40 km/hr
= 25.00 km
JUNCTION TO
SITE (Distance)
Select Terrain = MOUNTAINOUS (Dropdown List)
Loaded Trip
Speed = 20 km/hr
Unloaded Trip
Speed = 30 km/hr
Republic of the Philippines
Department of Public Works and Highways
Region VII
BU 4TH DISTRICT ENGINEERING OFFICE
Poblacion, Dalaguete, Cebu
Check = P 0.00
0.159364000
Units Days
Mobilization Data = Prime Mover w/ Low Bed Trai = 1 6.6
Dump Truck (10 cu.m.) = 1 7
PIPES:
Select Pipe Type : Pls. Select Pipe Type (Select from Bottom to Top)
0 Galvanized Iron (G.I.) Pipes
0 High Density Polyethylene (HDPE) Pipes Pls. Select
Pipe Type
0 uPVC (Blue) Pipes
Pipes :
Total Pipe Length 0.00 m
0 0
0 0
0 0
0 0
0 0
0 0
0
0
0
0
0
0
Convergence and Special Support Program, Construction/Rehabilitation of Water Supply/Septage and S
Local Program, Local Infrastructure Program, Water Management Facilities, Water Supply
ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Againts Major Floods,
GI 1 2
HD 1
PE
UP 1
VC
P 0.00
of Water Supply/Septage and Sewerage/ Rain Water Collector Systems, Water Supply System
ies, Water Supply
s Major Floods,
INCHES MM
1.00 25.40
1.25 31.70
1.50 38.00
2.00 50.80
2.50 63.50
3.00 76.20
4.00 101.00
LIST OF EQUIPMENT ADOPTED IN
CONSTRUCTION COST ESTIMATIO
PER HOUR BASED O
0. EXTRA
Toyota Hilux Pick-up 4X4 G, 3.0 liter
0.1 Toyota
Diesel Engine
1. EARTHMOVING EQUIPMENT
1.1 Bulldozer DX175
1.2 Bulldozer with Ripper DX175
1.3 Payloader LX80-2C
1.4 Motorized Road Grader G710A 1.50 m3/1.95 yd3
1.5 Motorized Road Grader with Scarifier G710A
2. COMPACTION EQUIPMENT
2.1 Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10 mt
2.2 Vibratory Roller SD100DC 10 mt
2.3 Tandem Steel Roller HD110 10 mt
2.4 Plate Compactor 400-500 GASOLINE ENGINE
3. LIFTING EQUIPMENT
3.1 Crawler Crane All Models 21-25 mt
3.2 Crawler Crane All Models 36-40 mt
3.3 Crawler Crane with Bucket All Models 36-40 mt
3.4 Crawler Crane All Models 41-45 mt
3.5 Crawler Crane All Models 51-60 mt
3.6 Crawler Crane All Models 61-70 mt
3.7 Crawler Crane All Models 71-80 mt
3.8 Truck Mounted Crane All Models 21-25 mt
3.9 Truck Mounted Crane All Models 31-35 mt
3.10 Truck Mounted Crane All Models 41-45 mt
3.11 Truck Mounted Crane with Bucket All Models 41-45 mt
3.12 Truck Mounted Crane All Models 51-60 mt
3.13 Topless Tower Crane MDT 98-1.2M 55M x 6T/1.2T
3.14 Topless Tower Crane MDT 128 55M x 6T/1.6T
3.15 Topless Tower Crane MDT 132 G8 55M x 8T/1.6T
3.16 Topless Tower Crane MDT 162 H8 60M x 8T/1.8T
3.17 Topless Tower Crane MDT 178 60M x 8T/1.5T
3.18 Topless Tower Crane MDT 192-H12 60M x 12T/2.2T
3.19 Aerial Lift, Self Propelled, Scissor Lift GS4080 Gas/ Diesel Driven 40 ft. hts x 46 ft. Range
4. EXCAVATING EQUIPMENT
4.1 Backhoe SOLAR 220 LC-3 0.80 m³/ 1.04 yd³
4.2 Backhoe with Breaker SOLAR 220 LC-4 0.80 m³/ 1.04 yd³
4.3 Backhoe, Wheel Mounted PW60N-1 0.28 m³/ 0.37 yd³
5. FOUNDATION EQUIPMENT
5.1 Diesel Hammer K25-DSL 7500 kg-m
5.2 Vibro Hammer VIBRO FONCEUR, PTC25H1A 45000 kg-m
5.3 Vibro Hammer MHF12 w/ Hyd. Power Pack 120 kN-m
5.4 Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton
5.5 Drilling Rig C.M.V. TH18/65, 2000mm⌀ 65m depth & 18000 kh-m Drill Torque
6. ASPHALTING EQUIPMENT
6.1 Asphalt Distrtibutor ROSCO/5 ton 3000 USG
6.2 Asphalt Paver NF220BIIVDM
7. CONCRETING EQUIPMENT
7.1 Concrete Paver COMMANDER III, FOUR-TRACK
7.2 Concrete Screeder Wacker Truss Screed
7.3 One Bagger Mixer 4-6
7.4 Transit Mixer All Models 5 ft³/min
7.5 Concete Pump Diesel Driven, Trailer-Mounted Less Pipe 100 ft³/min
7.6 Grouting Machine GARNER DENVER 6x3x6, Air Driven
8. HAULING EQUIPMENT
8.1 Dump Truck All Models 12 yd³
8.2 Cargo/Service Truck All Models 2-5 mt
8.3 Boom Truck NXG1160D3ZAL1X
8.4 Cargo/Service Truck All Models 9-10 mt
8.5 Water Truck/Pump All Models 16000 L
9. AIR EQUIPMENT
9.1 Air Compressor All Models 15-35 cfm
9.2 Air Compressor All Models 126-160 cfm
9.3 Air Compressor All Models 161-185 cfm
9.4 Air Compressor All Models 356-450 cfm
9.5 Diamond Drill CP-8
9.6 Jackhammer
9.7 Pneumatic Drilling Machine
10. PUMPING EQUIPMENT
10.1 Water Pump, 100 mm suction ⌀ 1800
10.2 Water Pump, 100 mm suction ⌀ 2667 50
11. POWER GENERATION EQUIPMENT
11.1 Generator Set All Makes 6kVA
11.2 Generator Set All Makes 13kVA
11.3 Generator Set All Makes 25kVA
12. SHOP EQUIPMENT
12.1 Welding Machine Gas/Diesel Driven 300
12.2 Welding Machine Gas/Diesel Driven 500
12.3 Welding Machine Electric Driven/DC Output 500
14. MISCELLANEOUS EQUIPMENT
14.1 Portable Breaker Wacker Portable Petrol Breaker, BHF30S
14.2 Chainsaw HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard Blade
14.3 Concrete Vibrator Flexible Shaft Type 2" Head dia. With 5 Amperes Gasoline Drive Unit
14.4 Concrete Saw 14" Blade with 4 3/4" Cutting Depth
14.5 Bar Cutter 25 mm Maximum Rebar dia (Grade 40), Single Phase
14.6 Bar Bender 25 mm Maximum Rebar dia, Three Phase
14.7 Tower Lights Tower Height = 28ft, No. of Lights = 4 x 1000 watts, hp = 10.50,
Generator = 5 kW
Complete with: Cement silo and screw conveyor system. Water and
supply system. Aggregate storage bins with vibrators and conveyors
15.2 Concrete Batch Plant system. Weigh hopper with electronic loadcell for aggregates, cement,
water and admixture. Central twinshaft mixer. Hydraulic system and
Computerized Plant Control System.
18. OTHERS
18.1 Power Broom Towed Type with Engine 2m wide 6-30km /h Sweeping
Capacity
18.2 Hydroseeding Machine
18.3 Applicator Machine
18.4 Kneading Machine
18.5 Cutting Outfit
18.6 Steel Wheel with Nylon Rope
18.7 Improvised Bamboo with Bucket
18.8 Asphalt Kettle/Drum
18.9 SPT & Desanding Machine
18.10 Drop Hammer
18.11 Drop Hammer with Accessories
18.12 1 Air Compressor with 2 Jack Hammer
18.13 Bentonite Bin
18.14 Bentonite Mixer
18. OTHERS
18.15 Tremle Pipe Set
Pile Integrity Testing (Sonic) &
18.16 accessories (includes professional fee
of Structural Engineer & reports)
₱ 51,013.00 ₱ 51,013.00 0
MENT ADOPTED IN THE STANDARD DUPA FOR ROAD, BRIDGE AND BUILDING (LOW & HIGH
N COST ESTIMATION MANUALS WITH MAKE, MODEL, CAPACITY AND OPERATED RENTAL
ER HOUR BASED ON THE PREVAILING ACEL EQUIPMENT GUIDEBOOK, EDITION 26
₱ 130.54 ₱ 130.54 0 0 0 0
₱ 952.00 ₱ 952.00 0 0 0 0
₱ 93.75 ₱ 93.75 0 0 0 0
₱ 187.50 ₱ 187.50 0 0 0 0
₱ 45.45 ₱ 45.45 0 0 0 0
₱ 300.00 ₱ 300.00 0 0 0 0
₱ 200.00 ₱ 200.00 0 0 0 0
₱ 10.00 ₱ 10.00 0 0 0 0
₱ 559.00 ₱ 559.00 0 0 0 0
₱ 200.00 ₱ 200.00 0 0 0 0
₱ 5,000.00 ₱ 5,000.00 0 0 0 0
₱ 1,265.00 ₱ 1,265.00 0 0 0 0
₱ 280.00 ₱ 280.00 0 0 0 0
₱ 173.00 ₱ 173.00 0 0 0 0
MENT ADOPTED IN THE STANDARD DUPA FOR ROAD, BRIDGE AND BUILDING (LOW & HIGH
N COST ESTIMATION MANUALS WITH MAKE, MODEL, CAPACITY AND OPERATED RENTAL
ER HOUR BASED ON THE PREVAILING ACEL EQUIPMENT GUIDEBOOK, EDITION 26
₱ 320.00 ₱ 320.00 0 0 0 0
₱ 65,000.00 ₱ 65,000.00 0 0 0 0
₱ 103,000.00 ₱ 103,000.00 0 0 0 0
₱ 37,000.00 ₱ 37,000.00 0 0 0 0
₱ 75.38 ₱ 75.38 0 0 0 0
₱ 2,500.00 ₱ 2,500.00 0 0 0 0
₱ 1,249.00 ₱ 1,249.00 0 0 0 0
₱ 100.00 ₱ 100.00 0 0 0 0
BUILDING (LOW & HIGH RISE)
ND OPERATED RENTAL RATE
OK, EDITION 26
55.6
225
Republic of the Philippines
Department of Public Works and Highwa
Region VII
CEBU 4TH DISTRICT ENGINEERING O
Poblacion, Dalaguete, Cebu
Appropriation: 10,000,000.00
7887051.41
ESTIMATED DIRECT
OCM CP
COST
0 - 5M 15.00 10.00
5M - 50M 12.00 8.00
50M - 150M 10.00 8.00
150M - above 8.00 8.00
Mark-ups :
OCM = 12.00%
CP = 8.00%
VAT = 5.00%
EAO :
0 DA 0.0 %
0 LIP 0 % 2
1 ✘ GAA (INFRA, DOT, DTI) 2 %
EAO for Project = 2%
3.50% 50M - 150M
PROJECT LOCATION :
Loaded Trip
Speed = 30 km/hr
Unloaded Trip
Speed = 40 km/hr
= 25.00 km
JUNCTION TO
SITE (Distance)
Select Terrain = MOUNTAINOUS (Dropdown List)
Loaded Trip
Speed = 20 km/hr
Unloaded Trip
Speed = 30 km/hr
Republic of the Philippines
ment of Public Works and Highways
Region VII
DISTRICT ENGINEERING OFFICE
Poblacion, Dalaguete, Cebu
0 is 150.50)
Convergence and Special Support Program, Construction/Rehabilitation of Water Supply/Septage and Sew
Local Program, Local Infrastructure Program, Water Management Facilities, Water Supply
er Supply/Septage and Sewerage/ Rain Water Collector Systems, Water Supply System
ITEM NO. DESCRIPTION QUANTITY UNIT QUANTITY
5.46 month
A.1.1(16) Operation and Maintenance of Field Office for the Engineer
Provision of 4x4 Pick Up Type Service Vehicle for the Engineer 5.46 month
A.1.2(2)
on Bare Rental Basis
Operation & Maintenance of 4x4 Pick Up Type Service Vehicle 5.46 month
A.1.2(5)
for the Engineer
TOTAL OF PART A
1.00 L.S.
B.4(10) Miscellaneous Survey and Staking
3.00 each
B.5 Project Billboard/Sign Board
1.00 L.S.
B.7 (2) Occupational Safety and Health Program
1.00 L.S.
B.9 Mobilization/Demobilization
1.00 L.S.
B.23 Staging Area
TOTAL OF PART B
11,303.90 Kg
902(1)a Reinforcing Steel (Deformed), Grade 40
633.80 sq.m.
903(2) Formworks and Falseworks
TOTAL OF PART B
TOTAL OF PART C
PART D ELECTRICAL
1.00 l.s.
1102(18) Solar Panel with inverter, battery and other devices
TOTAL OF PART D
29 29
29 29
116 116
10 10
30 30
120 120
25 25
50 50
250 250
16 16 16
16 16 16
16 16 16
9 9 9
18 18 18
36 36 36
1 1
5 5
5 5
2 2 2
4 4 4
8 8 8
2 2 2
6 6 6
1 1 1
3 3 3
807 0 0 0 137 807 0
0.50 730.00 730.00 730.00 365.00 60.00 60.00
6.00 676.00 1,100.00 1,263.85 345.00 111.00 500.00
12.00000 0.93000 1.51000 1.73000 0.95000 1.85000 8.33000
9,684.00 0.00 0.00 0.00 130.15 1,492.95 0.00 27,215.49
27,215.49
SIGNAGE DESCRIPTION
ROAD AND BRIDGE WORK SITE TEMPORARY
SIGNAGE SIGN NO. Size (mm) Letters / Symbols
(Width x Height)
WORKMEN AHEAD
T1-5 900 X 600 Black
(T1-5)
Cost
(A) Angle Bar (C)
(B)
Red / Orange
- Flourescent for day
2 pcs - 6m L50 x 50
Black use (Short Term) ₱5,500.00 ₱1,360.00 ₱68.00
x 3mm
- Flourescent for
night use (Long Term)
2 pcs - 6m L50 x 50
Symbol - 600 dia. Black White Reflectorized ₱5,400.00 ₱1,360.00 ₱68.00
x 3mm
BACK - UP COMPUTATION
EARTHWORK
A.) 800 (1) - Clearing and Grubbing
2 - Tank = 82.00 m2
2 - Power Room = 32.00 m2
COLUMNS
16 mm Ø = 32.00 pcs
10 mm Ø = 64.00 pcs
BEAMS
16 mm Ø = 32.00 pcs
10 mm Ø = 74.00 pcs
SLAB
10 mm Ø = 60.00 pcs
WALL FOOTING
10 mm Ø = 34.00 pcs
BACK - UP COMPUTATION
F.) 614(2) - Waterstop
= 1.00 L.S.
K.) 1046(2)a1 - CHB Non Load Bearing (Including Reinforcing Steel), 100mm
2 - Power Room
Area = 71.40 m2
Area of slotted block
window = 4.80 m2
Total Area = 76.20 m2
N.) 1100 (10) - Conduits, Boxes, & Fittings (Conduit Works/Conduit Rough-In)
= 1.00 l.s.
BACK - UP COMPUTATION
O.) 1101 (33) - Wires and Wiring Devices
= 1.00 l.s.
P.) 1102(10) - Pole Mounted Distribution Transformer (OISC) with complete accessories, Pole Type
= 1.00 l.s.
a. Metering
Current Transformer 200:5 1.00 Unit
Pole Band, 4 way, GI, HD, 2 segments, 5'' min. dia 4.00 set
Hose, Liquid tight, 1'' Dia 12.00 mts
Connector, straight liquitight 1'' dia 2.00 mts
Wire, Insulated Copper, Stranded, #10 AWG, THW, Red 12.00 pc.
Wire, Insulated Copper, Stranded, #12 AWG, THW, White 12.00 pc.
Wire, Insulated Copper, Stranded, #10 AWG, THW, Red 15.00 pc.
Wire, Insulated Copper, Stranded, #12 AWG, THW, White 15.00 pc.
Meter Box 1.00 pc.
CT Box 1.00 pc.
b. Transformer Banking
Distribution Transformer, 13200/7620-240/120V 15kVA 1.00 pc
Hanger, Transformer, 1-Phase with Bolts, Galv, HD 2.00 pc
Cut-out Arrester comb, 100 A, 15KV 1.00 pc
Hanger, Cut-out Assembly 1.00 pc
Copper Wire, Stranded, #4, TW 6.00 pc
Clamp, Hotline, Bronze, #1/0-2/0 ACSR, AWG, with Terminal 1.00 pc
Conn. Compression YHD 300 2.00 pc
Clevis, Secondary Swinging, 1 3/4" Spool 2.00 pc
Spool Insulator 1- 3/4" 2.00 pc
Conn. Compression YHD 150 2.00 pc
Plug Terminal, Conn. Compression 6.00 pc
Q.) 1102(18) - Solar Panel with inverter, battery and other devices
= 1.00 l.s.
Mounting Structure
G.I Pipes, 2 1/2" Ø, Schedule 40 360.00 m
G.I Pipes, 3" Ø, Schedule 40 540.00 m
Welding Electrodes 20.00 kg
Gravel ¾" (w/ haulage cost) 20.00 cu.m.
Sand (w/ haulage cost) 10.00 cu.m.
Portland Cement (w/ haulage cost) 182.00 bags
Reinforcing Steel Bar Deformed Grade 40 (w/ haulage) 5,626.10 kg
Paint Red Lead 3.00 gal
Steel plate (6 mm) 459.17 kg
J - Bolts (12 mm ) 106.50 kg
Project Name : CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
Location : Municipality of Boljoon, Province of Cebu
BACK - UP COMPUTATION
R.) 1103(1) - Lighting Fixtures and Lamps
= 1.00 l.s.
= 1.00 l.s.
1.00 set
3 Hp, 230 volts, single phase, 60 cycle, 340 rpm
discharge Submersible Pump with buit-in check valve,
strainer & cable guard with accessories
1.00 set
Motor Controller RVS (reduce Voltage Starter), 3 Hp,
230V with magnetic contractor, overlay relay circuit
breaker pilot lightpush button selector switch NEMA 2
enclosure
= 1.00 l.s.
- Overflow Pipe
G.I Pipes, 2 1/2" Ø, Schedule 40 6.00 m
G.I. 2 1/2" dia. 90 deg. elbow 4.00 pcs
2 1/2" G.I. Pipe Strap 8.00 pcs
Galvanized Expansion Shield Bolt 16.00 pcs
-Drain Pipe
G.I Pipes, 3" Ø, Schedule 40 6.00 m
Gate Valve 3" Ø, Brass 2.00 pcs
-Vent Pipe
G.I Pipes, 2 1/2" Ø, Schedule 40 0.50 m
G.I. 2 1/2" dia. 90 deg. elbow 2.00 pcs
-Ladder Rung
G.I Pipes, 2 1/2" Ø, Schedule 40 50.00 m
Welding Electrods 20.00 kg
-Painting
Paint Red Lead 3.00 gal
BACK - UP COMPUTATION
U.) 1600(1) - Excavation Beneath Proposed Structures
WIDENING 1
Area (sq. m.) Volume (cu. m.)
Station Interval Remarks
1047(2)a 1047(2)a 0 0
SUB-TOTAL #VALUE! - -
WIDENING 2
Area (sq. m.) Volume (cu. m.)
Station Interval Remarks
1701(1) 1701(1) 0 0
STONE MASONRY
Area (sq. m.) Volume (cu. m.)
Station Interval Remarks
1701(1) 1711(1) 1704(1)b 1701(1) 1711(1) 1704(1)b
Prepared : Checked:
DESCRIPTION MODEL
30% add
20% add
20% add
30% add
30% add
3rd Quarter CMPD
MATERIALS
DESCRIPTION PRICE
BOULDERS = 1,000.00
SAND = 1,500.00
SELECTED BORROW =
STEEL FORMS : =
15 CM = 47.00
20 CM = 56.00
23 CM = 62.00
28 CM = 72.00
30 CM = 75.00
TARPAULIN = 32.00
THERMOPLASTIC PAINT (WHITE) = 1,848.00
THERMOPLASTIC PAINT (YELLOW = 1,700.00
TIE WIRE #16 = 95.00
FUEL - DIESEL = 55.60
READY MIXED CONCRETE CLASS "A" = 5,000.00
3mm Thick x 100 x 150 T-Bar =
Epoxy all purpose adhesive = 950.00 pioneer 1/2L set 0.11L coverage per 600x100 (0.5
ROCK = 1,100.00
BOULDERS = 920.00
GRAVEL, G1 = 1,305.00
GRAVEL, G-1½" = 1,000.00
SELECTED BORROW =
STEEL FORMS : =
15 CM = 47.00
20 CM = 56.00
23 CM = 62.00
28 CM = 72.00
30 CM = 75.00
TARPAULIN = 30.00
THERMOPLASTIC PAINT (WHITE) = 1,848.00
THERMOPLASTIC PAINT (YELLOW = 1,914.00
TIE WIRE #16 = 82.00
FUEL - DIESEL = 80.43
Corrugated Roofing, Gauge 26 (0.551mm x 2.44mm) = 378.00
Pre-Painted Flashing Ga. 24 (0.701mm) x 2.44 m = 420.00
Ordinary Flashing Ga. 24 (0.701mm) x 2.44 m = 115.00
STEEL SHEET PILE = 100.00
WATERPROOFING CEMENT = 46.00
Epoxy all purpose adhesive = 950.00 pioneer 1/2L set 0.11L coverage per 600x100
10mm SS304 Stainless Steel Hex bolt and nuts with
washer = 25.00 set
Insulation Foam = 56.00
Umbrella Nails/ Tek Screw/ J-Bolt = 8.50
Concrete Nails #4 = 100.00
Common Nails #3 = 80.00
Common Nails #4 = 80.00
Jalousie Window 500x1200 = 787.00
Door Lockset = 850.00
LABOR
DESCRIPTION MONTHLY RATE DAILY RATE HOURLY RATE
FY 2023 GAA
Republic of the Philippines
Department of Public Works and Highways
OFFICE OF THE DISTRICT ENGINEER
Cebu 4th District Engineering Office
Poblacion, Dalaguete, Cebu
EXECUTIVE SUMMARY
Program of Work
LENARD A. PANUGALINOG
OIC - Chief Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
Region VII
CEBU 4TH DISTRICT ENGINEERING OFFICE
Poblacion, Dalaguete, Cebu
NOTE: FILL UP COLORED BOXES
Sand = ₱1,800.00
Gravel 1½ = ₱1,925.00
Gravel ¾ = ₱1,875.00
Portland Cement = ₱218.00
Reinforcing Steel Bar, Deformed, Grade 40 = ₱47.00
Tie Wires # 16 = ₱70.00
Tie Wires # 12 = ₱70.00
Ready Mix, Class A, 28 days =
RC Pipes (610 mm Ø), Class II = ₱1,500.00 610₱1,500.00
RC Pipes (910 mm Ø), Class II = ₱3,248.00 910₱3,248.00
RC Pipes (1220 mm Ø), Class II = ₱5,040.00 122₱5,040.00
Boulders = ₱1,260.00
Curing Compound = ₱115.00
620
440.3333
480
620
286.6667
620
#REF!
620
#REF!
620
#REF!
620
620
#REF!
#REF!
#REF!
(Shopee - Central Visayas)
450
300
532
260
480
620
480
620
620
620
620
620
620
DERIVATION OF HAULING COST FOR AGGREGATES MATERIALS
Hauling Equiptment Used: Dumptruck 10.00 cu.m. BASED FROM RBIA INVENTORY
Total Hauling Distance = 102.192 km DESCRIPTION DISTANCE, km
Less Free Hauling Distance = 5.000 km
Net Hauling Distance = 97.192 km Source to K0057±845 via Uling, Naga 62
Loading Capacity = 10.00 cu.m. K0057±845 to N. Bacalso Ave to
Loading Time = 3.00 hr 39.2145
Junction (K0097+059)
Unloading Time = 2.00 hr Highway Junction to Project Site 0.977
Total Distance 102.1915
FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME
Source: Magdugo River, Toledo City
FORMULA: T = D/R
Where: T = Time, Time of travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
I. Labor
1.00 unit Laborer per hour 482.47 = P 482.47
Page 67 of 119
DERIVATION OF HAULING COST FOR PORTLAND CEMENT
Hauling Equiptment Used: Dumptruck 150 bags/trip BASED FROM RBIA INVENTORY
Total Hauling Distance = 14.04 km DESCRIPTION DISTANCE, km
Less Free Hauling Distance = 5.00 km K0084+000 to Dalaguete to N. Bacalso
13.059
Net Hauling Distance = 9.04 km Ave Junction (K0097+059)
Highway Junction to Project Site 0.977
Total Distance 14.036
FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME Source: Cebu 4th DEO
FORMULA: T = D/R
Where: T = Time, Time of travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
I. Labor
2.00 unit Laborer x Total Cycle Time T per day 482.47 = P 964.94
Page 68 of 119
DERIVATION OF HAULING COST FOR REINFORCING STEEL
Hauling Equiptment Used: Dumptruck 10.00 cu.m. BASED FROM RBIA INVENTORY
Total Hauling Distance = 14.04 km DESCRIPTION DISTANCE, km
Less Free Hauling Distance = 5.00 km K0084+000 to Dalaguete to N. Bacalso
13.059
Net Hauling Distance = 9.04 km Ave Junction (K0097+059)
Loading Capacity = 3,800.00 kg Highway Junction to Project Site 0.977
Manpower = 4.00 pax Total Distance 14.036
Laborer Capacity = 1,600.00 kg/man-hr
Loading/Unloading Time = 0.59 hr Source: Cebu 4th DEO
(1 Gang = 4 Laborer)
FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME
FORMULA: T = D/R
Where: T = Time, Time of travel (h)
D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)
I. Labor
4.00 unit Laborer x Total Cycle Time T per day 482.47 = P 3,448.80
Reinforcing Steel Bars Deformed Grade 40 (Based on validated CMPD for 3rd Quarter CY 2023) = P 65.00
Reinforcing Steel Bars Deformed Grade 60 (Based on validated CMPD for 3rd Quarter CY 2023) = P 67.45
Reinforcing Steel Grade 40 per KG including Hauling Cost (Base Price + Labor + Hauling Cost) = P 66.13 per kg
Reinforcing Steel Grade 60 per KG including Hauling Cost (Base Price + Labor + Hauling Cost) = P 68.58 per kg
Page 69 of 119
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU 4TH DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
Poblcion, Dalaguete, Cebu
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
Project : CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water Appropriation : 10,000,000.00
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System, Source of Fund : GAA FY 2023
Barangay El Pardo, Municipality of Boljoon, Province of Cebu Target Start Date : Upon Approval
Project ID : Total Project Duration : 142 C.D.
Location : Municipality of Boljoon, Province of Cebu
Project Description : Construction of Solar Power System and Additional Reservoir
2 - Reservoir
Solar Power System : 2 - 16kW (4.0m x 4.0m x 4.0m) : 2 - 64.00 cu.m.
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Project
PROJECT COMPONENT DESCRIPTION
Component ID
BLUE BOOK VOLUME II
PART A FACILITIES FOR THE ENGINEER 8.35% 658,704.06
PART B OTHER GENERAL REQUIREMENTS 5.33% 420,634.93
PART H MISCELLANEOUS STRUCTURES 0.58% 45,565.77
BLUE BOOK VOLUME III
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORK 0.03% 2,722.22
PART B PLAIN AND REINFORCED CONCRETE WORK (PLS. SEE FORM POW-2015-01C-00) 22.69% 1,789,312.38
PART C FINISHING AND OTHER CIVIL WORKS 6.26% 493,713.90
PART D ELECTRICAL 50.90% 4,014,494.95
PART E MECHANICAL 4.84% 381,855.93
PART I WATER SUPPLY 1.01% 80,047.27
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
SHANNEN C. MARABILES LENARD A. PANUGALINOG Name & Signature NORLANDO P. MANALO MA. CHYMBELIN D. IBAL
ENGINEER I ENGINEER II Position Title OIC - ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER
Planning & Design Section OIC - Chief Planning & Design Section Planning Division
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU 4TH DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
Poblcion, Dalaguete, Cebu
FORM ABC-2015-02-00
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Provision of 4x4 Pick Up Type Service Vehicle for the Engineer 5.46 month 278,530.98 0% - 13,926.55 13,926.55 292,457.530 53,563.65
A.1.2(2)
on Bare Rental Basis
Operation & Maintenance of 4x4 Pick Up Type Service Vehicle 5.46 month 125,572.47 20% 25,114.49 7,534.35 32,648.84 158,221.310 28,978.26
A.1.2(5)
for the Engineer
658,704.06 76,034.61 36,736.94 112,771.55 771,475.610
TOTAL OF PART A
Page 72 of 119
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU 4TH DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
Poblcion, Dalaguete, Cebu
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
APPROVED BUDGET FOR THE CONTRACT
Contract Duration : 142 Calendar Days
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST % VALUE COST
BLUE BOOK VOLUME III
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORK
114.00 sq. m. 2,722.22 20% 544.44 163.33 707.77 3,429.990 30.09
800 (1) Clearing and Grubbing
Page 73 of 119
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CEBU 4TH DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
Poblcion, Dalaguete, Cebu
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
APPROVED BUDGET FOR THE CONTRACT
Contract Duration : 142 Calendar Days
ESTIMATED TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
DIRECT COST % VALUE COST
PART D ELECTRICAL
1.00 l.s. 41,006.33 20% 8,201.27 2,460.38 10,661.65 51,667.980 51,667.98
1100 (10) Conduits, Boxes, & Fittings (Conduit Works/Conduit Rough-In)
Pole Mounted Distribution Transformer (OISC) with complete 1.00 l.s. 175,956.41 20% 35,191.28 10,557.38 45,748.66 221,705.070 221,705.07
1102(10)
accessories, Pole Type
1.00 l.s. 3,757,489.75 20% 751,497.95 225,449.39 976,947.34 4,734,437.090 4,734,437.09
1102(18) Solar Panel with inverter, battery and other devices
PART E MECHANICAL
1.00 l.s. 131,250.00 20% 26,250.00 7,875.00 34,125.00 165,375.000 165,375.00
1201(1) Water Pumping System
Page 74 of 119
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
A.1.1(3) Construction of Field Office for The Engineer 1.00 L.S. 117,179.84 117,179.84 147,646.60 1.49
A.1.1(16) Operation and Maintenance of Field Office for the Engineer 5.46 month 137,420.77 25,168.64 31,712.49 1.74
A.1.2(2) Construction of Field Office for The Engineer 5.46 month 278,530.98 51,013.00 53,563.65 3.53
A.1.2(5) Operation and Maintenance of Field Office for the Engineer 5.46 month 125,572.47 22,998.62 28,978.26 1.59
B.4(10) Miscellaneous Survey and Staking 1.00 L.S. 40,110.00 40,110.00 50,538.60 0.51
B.5 Project Billboard/Sign Board 3.00 each 14,058.24 4,686.08 5,904.46 0.18
B.7 (2) Occupational Safety and Health Program 1.00 L.S. 116,807.79 116,807.79 132,460.03 1.48
PART A EARTHWORK
800 (1) Clearing and Grubbing 114.00 sq. m. 2,722.22 23.88 30.09 0.03
900(1)c1 Structural Concrete, Class A, 28 Days 61.50 cu.m. 533,644.79 8,677.15 10,933.21 6.77
902(1)a Reinforcing Steel (Deformed), Grade 40 11,303.90 Kg 914,501.09 80.90 101.94 11.59
903(2) Formworks and Falseworks 633.80 sq.m. 322,926.49 509.51 641.98 4.09
Page 75 of 119
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
1013(1) Corrugated Metal Roofing, Gauge 26 83.40 sq. m. 50,637.67 607.17 765.03 0.64
1027(1) Cement Plaster Finish 142.80 sq. m. 33,131.25 232.01 292.33 0.42
1046(2)a1 CHB Non Load Bearing (Including Reinforcing Steel), 100mm 76.20 sq. m. 101,229.25 1,328.47 1,673.87 1.28
PART D ELECTRICAL
1100 (10) Conduits, Boxes, & Fittings (Conduit Works/Conduit Rough-In) 1.00 l.s. 41,006.33 41,006.33 51,667.98 0.52
1101(33) Wires and Wiring Devices 1.00 l.s. 36,112.52 36,112.52 45,501.77 0.46
1102(10) Pole Mounted Distribution Transformer (OISC) with complete accessories, Pole Type 1.00 l.s. 175,956.41 175,956.41 221,705.07 2.23
1102(18) Solar Panel with inverter, battery and other devices 1.00 l.s. 3,757,489.75 3,757,489.75 4,734,437.09 47.64
1103(1) Lighting Fixtures and Lamps 1.00 l.s. 3,929.94 3,929.94 4,951.73 0.05
PART E MECHANICAL
1201(1) Water Pumping System 1.00 l.s. 131,250.00 131,250.00 165,375.00 1.66
1201(12) Valves and Pipe Fittings 1.00 l.s. 250,605.93 250,605.93 315,763.48 3.18
1600(1) Excavation Beneath Proposed Structures 244.80 cu.m. 75,349.52 307.80 387.83 0.96
1601(1) Fill and Backfill 104.30 cu.m. 4,697.75 45.04 56.75 0.06
Page 76 of 119
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
FORM POW-2015-01C-00
Operation and Maintenance of Field Office for As Submitted 1.74 5.46 month - - 25,168.64 137,420.77 - - 25,168.64 137,420.77 20% 27,484.15 8,245.25 173,150.17 31,712.49
A.1.1(16)
the Engineer As Evaluated
Provision of 4x4 Pick Up Type Service Vehicle As Submitted 3.53 5.46 month - - - - 51,013.00 278,530.98 51,013.00 278,530.98 0% - 13,926.55 292,457.53 53,563.65
A.1.2(2)
for the Engineer on Bare Rental Basis As Evaluated
Operation & Maintenance of 4x4 Pick Up Type As Submitted 1.59 5.46 month 6,672.00 36,429.12 16,326.62 89,143.35 - - 22,998.62 125,572.47 20% 25,114.49 7,534.35 158,221.31 28,978.26
A.1.2(5)
Service Vehicle for the Engineer As Evaluated
As Submitted 8.35 82,855.35 241,977.32 333,871.39 658,704.06 76,034.61 36,736.94 771,475.61
TOTAL OF PART A
As Evaluated
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.51 1.00 L.S. 20,010.00 20,010.00 - - 20,100.00 20,100.00 40,110.00 40,110.00 20% 8,022.00 2,406.60 50,538.60 50,538.60
B.4(10) Miscellaneous Survey and Staking
As Evaluated
As Submitted 0.18 3.00 each 4,215.60 12,646.80 427.71 1,283.13 42.77 128.31 4,686.08 14,058.24 20% 2,811.65 843.49 17,713.38 5,904.46
B.5 Project Billboard/Sign Board
As Evaluated
As Submitted 1.48 1.00 L.S. 21,566.49 21,566.49 95,241.30 95,241.30 0.00 - 116,807.79 116,807.79 8% 9,344.62 6,307.62 132,460.03 132,460.03
B.7 (2) Occupational Safety and Health Program
As Evaluated
As Submitted 1.08 1.00 L.S. - - - - 84,938.13 84,938.13 84,938.13 84,938.13 0% - 4,246.91 89,185.04 89,185.04
B.9 Mobilization/Demobilization
As Evaluated
As Submitted 2.09 1.00 L.S. - - 137,420.77 137,420.77 27,300.00 27,300.00 164,720.77 164,720.77 20% 32,944.15 9,883.25 207,548.17 207,548.17
B.23 Staging Area
As Evaluated
As Submitted 5.33 54,223.29 233,945.20 132,466.44 420,634.93 53,122.42 23,687.87 497,445.22
TOTAL OF PART B
As Evaluated
PART H MISCELLANEOUS STRUCTURES
As Submitted 0.58 1.00 l.s. 44,650.37 44,650.37 915.40 915.40 - - 45,565.77 45,565.77 20% 9,113.15 2,733.95 57,412.87 57,412.87
614(2) Waterstop
As Evaluated
As Submitted 0.58 44,650.37 915.40 - 45,565.77 9,113.15 2,733.95 57,412.87
TOTAL OF PART H
As Evaluated
Page 77 of 119
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
FORM POW-2015-01C-00
CHB Non Load Bearing (Including Reinforcing As Submitted 1.28 76.20 sq. m. 1,200.31 91,463.62 445.64 8,877.85 44.56 887.78 1,328.47 101,229.25 20% 20,245.85 6,073.76 127,548.86 1,673.87
1046(2)a1
Steel), 100mm As Evaluated
As Submitted 0.66 559.50 kg 71.16 39,814.02 589.00 3,877.00 1,275.57 8,396.22 93.10 52,087.24 20% 10,417.45 3,125.23 65,629.92 117.30
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 0.84 753.60 kg 72.35 54,522.96 505.95 4,215.41 942.56 7,853.06 88.36 66,591.43 20% 13,318.29 3,995.49 83,905.21 111.34
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 6.26 397,957.70 73,014.70 22,741.50 493,713.90 98,742.78 29,622.84 622,079.52
TOTAL OF PART C
As Evaluated
PART D ELECTRICAL
Conduits, Boxes, & Fittings (Conduit As Submitted 0.52 1.00 l.s. 36,697.50 36,697.50 3,917.12 3,917.12 391.71 391.71 41,006.33 41,006.33 20% 8,201.27 2,460.38 51,667.98 51,667.98
1100 (10)
Works/Conduit Rough-In) As Evaluated
Page 78 of 119
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
FORM POW-2015-01C-00
As Submitted 0.46 1.00 l.s. 29,649.27 29,649.27 5,875.68 5,875.68 587.57 587.57 36,112.52 36,112.52 20% 7,222.50 2,166.75 45,501.77 45,501.77
1101(33) Wires and Wiring Devices
As Evaluated
Pole Mounted Distribution Transformer (OISC) As Submitted 2.23 1.00 l.s. 102,979.05 102,979.05 50,125.60 50,125.60 22,851.76 22,851.76 175,956.41 175,956.41 20% 35,191.28 10,557.38 221,705.07 221,705.07
1102(10)
with complete accessories, Pole Type As Evaluated
Solar Panel with inverter, battery and other As Submitted 47.64 1.00 l.s. 3,488,897.89 3,488,897.89 130,326.56 130,326.56 138,265.30 138,265.30 3,757,489.75 3,757,489.75 20% 751,497.95 225,449.39 4,734,437.09 4,734,437.09
1102(18)
devices As Evaluated
As Submitted 0.05 1.00 l.s. 2,289.00 2,289.00 1,491.76 1,491.76 149.18 149.18 3,929.94 3,929.94 20% 785.99 235.80 4,951.73 4,951.73
1103(1) Lighting Fixtures and Lamps
As Evaluated
As Submitted 50.90 3,660,512.71 191,736.72 162,245.52 4,014,494.95 802,898.99 240,869.70 5,058,263.64
TOTAL OF PART D
As Evaluated
PART E MECHANICAL
As Submitted 1.66 1.00 l.s. 131,250.00 131,250.00 - - - - 131,250.00 131,250.00 20% 26,250.00 7,875.00 165,375.00 165,375.00
1201(1) Water Pumping System
As Evaluated
As Submitted 3.18 1.00 l.s. 148,976.97 148,976.97 43,737.60 43,737.60 57,891.36 57,891.36 250,605.93 250,605.93 20% 50,121.19 15,036.36 315,763.48 315,763.48
1201(12) Valves and Pipe Fittings
As Evaluated
As Submitted 4.84 280,226.97 43,737.60 57,891.36 381,855.93 76,371.19 22,911.36 481,138.48
TOTAL OF PART E
As Evaluated
PART I WATER SUPPLY
As Submitted 0.96 244.80 cu.m. - - 289.16 3,539.32 5,866.85 71,810.20 307.80 75,349.52 20% 15,069.90 4,520.97 94,940.39 387.83
1600(1) Excavation Beneath Proposed Structures
As Evaluated
As Submitted 0.06 104.30 cu.m. - - 286.86 1,495.97 613.96 3,201.78 45.04 4,697.75 20% 939.55 281.87 5,919.17 56.75
1601(1) Fill and Backfill
As Evaluated
As Submitted 1.01 - 5,035.29 75,011.98 80,047.27 16,009.45 4,802.84 100,859.56
TOTAL OF PART I
As Evaluated
As Submitted 100.00 5,885,156.14 1,111,568.59 890,326.70 7,887,051.41 1,490,699.51 468,887.58 9,846,638.50
GRAND TOTAL
As Evaluated
Page 79 of 119
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Cargo Truck/Service Truck, All Models, 2-5 mt, 160 Hp 1
10 Cutting Oufit 1
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30 60
SUB-TOTAL 16 SUB-TOTAL
TOTAL
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
Cebu 4th District Engineering Office
Poblacion, Dalaguete, Cebu
Formula :
C.D. = ( Dh - Dl ) x ( Ap - Al)
+ Dl
( Ah - Al )
Where :
Dh = 162
Dl = 84
Ah = 20,000,000.00
Al = 5,000,000.00
Ap = 10,000,000.00
= 110
= 110 Total Working Days
8.76 kms.
26.41 kms.
DEO OFFICE
K0084+000
5.05 km from source
SOURCE : PMSC
K0089+050
42.95 kms.
PROJECT SITE
K0131+000 - K0133+000
42.95 km from source
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Rehabilitation of Water
Supply/Septage and Sewerage/Rain Water Collectors Systems - Construction of Solar Water System,
Barangay El Pardo, Municipality of Boljoon, Province of Cebu
Municipality of Boljoon, Province of Cebu
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM-POW-2015-01D-00
ITEM NO. : A.1.1(3)
DESCRIPTION : Construction of Field Office for The Engineer
Quantity : 1.00 length = 3,492.00 lm
Output per hour - As Submitted : 1 L.S.
Output per hour - As Evaluated :
No. of
A.1 Designation No. of Hours Hourly Rate Amount
Person
Labor
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Cargo Truck/Service Truck, All Models, 2-5 mt, 160 Hp 1 2.00 P 11,068.08 P 22,136.17
Dumptruck, All Models, 12 yd³, 290 Hp 1 3.00 P 20,933.99 P 62,801.96
Prepared by : Checked/Reviewed by :
Space Rental - use for the storage of construction 1 5.46 P 5,000.00 P 27,300.00
related equipment and materials such as vehicles &
stockpiles
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Reinforcing Steel Bar Deformed Grade 40 (w/ haulage) kg 1.000 P 66.13 P 66.13
#16 Galvanized Iron Wire kg 0.015 P 82.00 P 1.23
Minor Tools (5% of Material Cost) P 3.37
Prepared by : Checked/Reviewed by :
INSTALLATION:
Foreman 1 1 P 108.23 P 108.23
Skilled Laborer 2 1 P 78.24 P 156.48
Unskilled Laborer 4 1 P 60.31 P 241.24
STRIPPING:
Foreman 1 0.41 P 108.23 P 44.37
Unskilled Laborer 6 0.41 P 60.31 P 148.36
Ordinary Plywaood (1/2" x 4" x 8") - 3 uses pcs 0.35 P 750.00 P 86.75
Good Lumber - 3 uses bd-ft 7.19 P 65.00 P 155.78
Common Wire Nails Assorted kg 0.21 P 80.00 P 16.80
Consumables (5% of Material Cost) P 12.97
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Common Borrow (w/ 25% Shrinkage Factor) cu.m. 1.25 #REF! #REF!
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
F.1 Materials
Prepared by : Checked/Reviewed by :
100 mm thk CHB (Non Load Bearing) pcs 13.00 P 15.00 P 195.00
Slotted Block Concrete (0.20m x 0.20m) pcs 25.00 P 22.00 P 550.00
Portland Cement (w/ haulage cost) bag 0.53 P 248.02 P 130.21
Sand (w/ haulage cost) cu.m. 0.04 P 2,668.48 P 106.74
Reinforcing Steel Bar Deformed Grade 40 (w/ haulage) kg 3.24 P 66.13 P 214.26
#16 Galvanized Iron Wire kg 0.05 P 82.00 P 4.10
Prepared by : Checked/Reviewed by :
Erection
Skilled Laborer 3 0.49 P 78.24 P 115.01
Unskilled Laborer 3 0.49 P 60.31 P 88.66
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
F.1 Materials
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
a. Metering
Current Transformer 200:5 Unit 1.00 6,500.00 P 6,500.00
Pole Band, 4 way, GI, HD, 2 segments, 5'' min. dia set 4.00 275.00 P 1,100.00
Hose, Liquid tight, 1'' Dia mts 12.00 68.00 P 816.00
Connector, straight liquitight 1'' dia mts 2.00 73.21 P 146.42
Wire, Insulated Copper, Stranded, #10 AWG, THW, Red pc. 12.00 36.00 P 432.00
Wire, Insulated Copper, Stranded, #12 AWG, THW, White pc. 12.00 30.00 P 360.00
Wire, Insulated Copper, Stranded, #10 AWG, THW, Red pc. 15.00 36.00 P 540.00
Wire, Insulated Copper, Stranded, #12 AWG, THW, White pc. 15.00 30.00 P 450.00
b. Transformer Banking
Distribution Transformer, 13200/7620-240/120V 15kVA pc 1.00 75,400.00 P 75,400.00
Hanger, Transformer, 1-Phase with Bolts, Galv, HD pc 2.00 650.00 P 1,300.00
Cut-out Arrester comb, 100 A, 15KV pc 1.00 6,250.00 P 6,250.00
Hanger, Cut-out Assembly pc 1.00 P 640.00 P 640.00
Copper Wire, Stranded, #4, TW pc 6.00 P 72.68 P 436.08
Clamp, Hotline, Bronze, #1/0-2/0 ACSR, AWG, with Terminal pc 1.00 P 400.18 P 400.18
Conn. Compression YHD 300 pc 2.00 P 75.00 P 150.00
Clevis, Secondary Swinging, 1 3/4" Spool pc 2.00 79.17 P 158.34
Spool Insulator 1- 3/4" pc 2.00 30.00 P 60.00
Conn. Compression YHD 150 pc 2.00 45.00 P 90.00
Plug Terminal, Conn. Compression pc 6.00 366.00 P 2,196.00
Prepared by : Checked/Reviewed by :
Mounting Structure
G.I Pipes, 2 1/2" Ø, Schedule 40 m 360.00 433.83 P 156,180.00
G.I Pipes, 3" Ø, Schedule 40 m 540.00 514.17 P 277,650.00
Welding Electrodes kg 20.00 190.00 P 3,800.00
Gravel ¾" (w/ haulage cost) cu.m. 20.00 P 1,971.87 P 39,437.41
Sand (w/ haulage cost) cu.m. 10.00 P 1,996.87 P 19,968.71
Portland Cement (w/ haulage cost) bags 182.00 P 255.23 P 46,452.76
Reinforcing Steel Bar Deformed Grade 40 (w/ kg 5,626.10 P 66.13 P 372,049.00
Paint Red Lead
haulage) gal 3.00 654.00 P 1,962.00
Steel plate (6 mm) kg 459.17 P 56.00 P 25,713.32
J - Bolts (12 mm ) kg 106.50 P 37.00 P 3,940.50
Prepared by : Checked/Reviewed by :
Lightings
18 Watts LED Bulb with Vertical Downlight Fixture
Surface Type. 5", 1xE27 pcs 4.00 P 545.00 P 2,180.00
Prepared by : Checked/Reviewed by :
3 Hp, 230 volts, single phase, 60 cycle, 340 rpm set 1.00 75,000.00 P 75,000.00
discharge Submersible Pump with buit-in check valve,
strainer & cable guard with accessories
Motor Controller RVS (reduce Voltage Starter), 3 Hp, set 1.00 50,000.00 P 50,000.00
230V with magnetic contractor, overlay relay circuit
breaker pilot lightpush button selector switch NEMA 2
enclosure
Prepared by : Checked/Reviewed by :
- Overflow Pipe
G.I Pipes, 2 1/2" Ø, Schedule 40 m 6.00 771.50 P 4,629.00
G.I. 2 1/2" dia. 90 deg. elbow pcs 4.00 388.00 P 1,552.00
2 1/2" G.I. Pipe Strap pcs 8.00 15.00 P 120.00
Galvanized Expansion Shield Bolt pcs 16.00 90.00 P 1,440.00
-Drain Pipe
G.I Pipes, 3" Ø, Schedule 40 m 6.00 1,026.67 P 6,160.00
Gate Valve 3" Ø, Brass pcs 2.00 4,500.00 P 9,000.00
-Vent Pipe
G.I Pipes, 2 1/2" Ø, Schedule 40 m 0.50 771.50 P 385.75
G.I. 2 1/2" dia. 90 deg. elbow pcs 2.00 388.00 P 776.00
-Ladder Rung
G.I Pipes, 2 1/2" Ø, Schedule 40 m 50.00 771.50 P 38,575.00
Welding Electrods kg 20.00 190.00 P 3,800.00
-Painting
Paint Red Lead gal 3.00 654.00 P 1,962.00
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :
Prepared by : Checked/Reviewed by :