Professional Documents
Culture Documents
TABLE OF CONTENTS
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
1.0 SCOPE 2
2.0 REFERENCE DOCUMENTS 4
3.0 WELDING PROCESSES 5
4.0 WELDERS AND WELDING OPERATORS 7
5.0 PREHEATING 8
6.0 WELDING 12
7.0 FILLER MATERIALS FOR WELDING 24
8.0 POST WELD HEAT TREATMENT 27
9.0 WELDING QUALITY 30
10.0 TITANIUM 38
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
1.0 SCOPE
1.1. The aim of the present Welding Specification is to provide the general requirements
for the execution of welded joints on pressure equipment (vessels, heat exchangers,
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
1.2. Welding of pressure equipment shall be designed and fabricated according to the
requirements of the following Codes :
- ASME Section I;
- ASME Section VIII Division 1;
- ASME Section VIII Division 2;
- ASME B31.1;
- ASME B31.3 (shall be also considered the requirements of Spec. TEC/WEL-10);
and other Codes and contractual specifications, if any.
1.3. In case of conflicts between this specification, regulations, drawings and standards,
the Manufacturer / Subcontractor shall ask to TECHINT for clarifications before
proceeding.
Generally speaking, the most restrictive requirements shall be applied.
Any exceptions or modifications required by the Manufacturer / Subcontractor shall
obtain a written approval by TECHINT.
1.4. The references to norms, regulations, standards, codes, both national and
international, are always referred to their last edition (including upgraded,
supplements, revisions, addenda, etc.), in force at the issue date of the Purchase
Order.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
1.6. Subcontracting
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
2.2. Specifications
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
3.1. General
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
3.1.1. The Manufacturer / Subcontractor shall prepare and qualify the welding
procedure so as to cover all the welding situations including any
heterogeneous weld deposit.
3.1.2. The Manufacturer / Subcontractor shall qualify all the welders and the
welder operators.
3.1.4. All Procedure Qualification Records (PQR) shall not be older than 7 years
from the issuing data of pressure equipment (vessels, heat exchangers,
boilers, piping systems, etc.) Purchase Order.
3.1.6. Any comment or approval by TECHINT does not exempt the Manufacturer /
Subcontractor from his contractual responsibilities.
TECHINT can issue, at any moment, comments to the Welding Procedure
Specification (WPS), if divergences to the applicable provisions of Codes,
specifications, standards and construction drawings, as well as to good
engineering practice, are found.
3.2. The Welding Procedure Specifications (WPS) shall be prepared as required in the
Codes listed at paragraph 1.2.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
3.3. The specific information that shall be included in the Welding Procedure
Specifications (WPS) and/or the limits that shall be respected are the followings :
- all the essential, supplementary essential and nonessential variables listed in
paragraphs from QW-252 to QW-265 of ASME Code Section IX for the
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
3.4. For welding of Cr low alloy steel (Grade 11 and Grade 22) and for welding between
carbon steel and Cr low alloy steel (Grade 11, Grade 22), the filler material (rods
end electrodes) of PQR and that one used for the pre-fabrication and assembly shall
have the same commercial name (Trade name) and the same nominal chemical
composition.
3.5. For welding of Cr low alloy steel (Grade 11 and Grade 22), in the production welds
the heating rate, holding time and cooling rate of Post Weld Heat Treatment
(PWHT), shall not be higher than that indicated in the PQR.
3.6. TECHINT reserves to reject, without times and costs at his charge, Welding
Procedure Specifications (WPS) that are supported by more than one Procedure
Qualification Record (PQR).
This specification is applicable for welding all materials, with suitable certification
(e.g.: EN, ASTM, etc...), even if not expressly stated.
In case that base material is not clearly identified and certified, the Manufacturer /
Subcontractor shall proceed with the execution of adequate analysis including as a
minimum the chemical analysis and the “Positive Material Identification” (PMI)
testing prior to proceed with any welding operation.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
4.1. Qualification
All welders and welding operators shall be qualified according to ASME Code
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
Section IX.
The certification of qualification shall be available at site in original or with the stamp
“CONFORMS TO THE ORIGINAL” signed by the Quality Manager and the assigned
identification number or symbol must be indicated.
The Manufacturer / Subcontractor shall provide 5 days before their use, the
qualification certificate of the new welders and welding operators that are not
provided at the start of work date.
The operational staff involved in the tack welding operations (e.g.: pipe workers,
steel structure workers, etc.) shall be qualified through a test coupon carried out at
the presence of the Designated Control and by this one checked with visual
examination.
4.2. Identification
Welders and welding operators shall be identified by a number or a symbol, the same
present in the qualification certificate, that will be reported through “low stress”
punches at the sides of the weld bead.
If more welders or welding operators take part to a welding joint execution, each one
shall apply his identification number or symbol to indicate clearly the portion of the
joint that he has carried out.
The Manufacturer / Subcontractor shall keep at workplace an up to date record with
the list of the employed personnel (welders / welding operators), organized in such
way to maintain the complete traceability with the qualification certificates.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
5.0 PREHEATING
5.1. General
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
5.1.1. Welding shall not be done when the ambient temperature is lower than
-18°C.
Only the implementation of special devices, like a heated structure or a
shelter maintaining the temperature at values not lower than -18°C, will
make executable the welding activities.
5.1.2. Welding shall not be carried out when condensation occurs on metal
surface, in this case a suitable preheating shall be provided.
5.1.4. For carbon steel welding, if the environmental temperature is lower than
5°C, the base metal shall be preheated to 70°C and this shall be the
minimum temperature that shall be maintained during welding, unless a
higher temperature is specified in the following paragraphs.
5.1.6. Preheating temperature shall be reached over a band width at least 6 times
the joint thickness, with a minimum of 100 mm.
5.2.1. The minimum preheating temperature for carbon and alloy steels shall be:
a. for pressure equipment: according to Codes listed at paragraph 1.2
with the exception of carbon steel with thickness greater than 30 mm
that shall be preheated to a temperature ≥ 100°C;
b. for piping systems: according to ASME B31.1 and ASME B31.3
Codes.
The above temperature limits are to be intended as minimum values.
It will be required to Manufacturer / Subcontractor, under his complete
responsibility, to define the minimum preheating temperature according to
chemical analysis, thickness, welding process and specific heat input.
5.2.2. When required, preheating shall concern the entire thickness of the edges
to be welded and not only the material surface.
No welding, also of temporary attachments, is permitted without the
specified preheat.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
Preheating temperatures shall not be lower than those ones indicated in Table A.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
Table A
thk. < 15 mm thk. 15 ÷ 40 mm thk. > 40 mm
Steel type
preheat preheat preheat
1¼ Cr ½ Mo 150°C 200°C 220°C
2¼ Cr 1 Mo 200°C 220°C 220°C
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
Exceptions are some structures with high ferrite content (in weld and in
heat affected zone) in which some cracks (by hydrogen) can be induced, in
this case a preheat up to 150°C is recommended.
For 22 ÷ 23% Cr duplex steels, the maximum interpass temperature shall
not exceed 200°C.
For 25% Cr duplex and for super-duplex steels, the maximum interpass
temperature shall not exceed 150°C. In order to obtain optimal properties in
fused zone a maximum temperature of 100°C is recommended.
In case a solution annealing is foreseen after welding, it is not required any
restriction in the interpass temperature.
5.5.2. The Manufacturer / Subcontractor shall analyze the critical heating aspects
and highlight them in the Welding Procedure Specifications.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.0 WELDING
6.1. General
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.1.1. The welding processes to be used for the fabrication are listed in Table 1
“Acceptable welding processes”.
The use of any other welding process must be approved in writing by
TECHINT.
The fabrication shall also comply with the requirements indicated in this
Specification.
6.1.2. Unless authorized in writing by TECHINT, all the butt joints, accessible on
both sides, shall be welded with sealing run.
When the access or the wall thickness preclude the use of the butt weld
with sealing run, a weld on one side only with root weld using the process
with non-consumable tungsten electrode (GTAW) [process 141] shall be
carried out.
6.1.3. If the welded joint requires a particular root penetration, without sealing run,
the Manufacturer / Subcontractor shall prepare (providing if necessary a
suitable etch) a transversal section specimen of the joint, in order to
demonstrate that the proposed welding process reaches the required root
penetration.
TECHINT, at its judgment, can require the radiography of a test joint in
addition to the required specimen.
6.1.4. Permanent backing rings in the joints are not permitted, unless previous
written authorization by TECHINT.
Temporary backing rings shall have the same chemical composition as the
base material and after the welding shall be removed.
Fuse rings are not acceptable.
6.1.5. All welds of nozzles, manholes and their reinforcements to shells and
heads of pressure equipment shall be full penetration type.
6.1.6. All welds shall be carried out as careful as the main ones.
This includes welds for insulating support rings and connections for
ladders, platforms and pipe supports.
It is essential to use qualified welding procedures, to employ qualified
welders / welding operators as well as a suitable preheating temperature
that shall not be lower than that one used for carried out the main joints.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.1.7. It is forbidden to striking the arc on the component to be welded outside the
groove (the use of suitable small plates is allowed).
In case of accidental striking arc outside the groove, the concerned area
shall be grinded (taking care that the thickness of the material does not fail
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.2.1. Joint preparation for welding shall be carried out only by tool machining.
Excessively sharp or deep irregularities in joint edges shall be removed by
machining or grinding.
Joints edges shall be free from cracks and peelings before welding.
6.2.2. When thermal cutting is used on ferritic steels, the beveled surfaces shall
be ground approximately 1,5 mm in order to remove the hardened or
sensitized zones.
6.2.3. Thermal cutting for Cr low alloy steels (Grade 11 and Grade 22) is not
acceptable.
6.2.4. The grooves of Cr low alloy steels (Grade 11 and Grade 22) shall be
submitted to a 100% surface examination (magnetic particles or liquid
penetrant) before welding.
6.2.5. Groove preparation shall be carried out according to the Codes listed at
paragraph 1.2.
Different preparations can be used only if authorized in writing by
TECHINT.
6.2.6. Oil, grease, dirt, rust and deposits shall be removed from the surfaces of
joint and adjacent base metal within 25 mm from the edge of the joint,
before welding.
Oil and grease shall not be removed by heating with torch.
6.2.7. For welds carried out in first pass, regardless of the process, the cleaning
extension shall include also the preparation backside.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.3.1. Tack welds shall be carried out according to the applicable WPS of the
welding joint, otherwise it shall be qualified.
6.3.2. Tack welds shall be removed or re-melted during welding, in this case is
necessary to check previously that these are free from defects.
6.3.3. In case of coupling using hook bolts, those ones shall be welded with a
qualified procedure and carried out according to the applicable WPS of the
coupled joint.
Removal shall be by grinding.
After grinding the area shall be liquid penetrant examined.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.5.1. The first run in butt joints and branches, shall be carried out so that to
achieve complete and regular penetration.
Over penetration, also if localized, shall not exceed 3 mm.
6.5.2. The first run shall be free of internal undercuts, incompletely filled grooves
and defective sealing.
Stop craters shall be removed, if they present defects or irregularities that
can jeopardize a proper sealing.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.5.3. When welding is starting, and up to the joint has not been completed, it
shall be avoided that the component was subjected to movements, impacts
or vibrations that can damage the weld.
6.5.4. It is forbidden to interrupt the weld before completing the first run.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.5.6. At the end of the first run the possible visible defects, and any bead
irregularity, shall be eliminated by grinding in order not to affect the
subsequent run.
In the case of welds with SMAW [process 111], SAW [process 12] and
FCAW processes [process 136, 137 and114], the slag shall be carefully
removed.
6.5.7. In case of Cr low alloy steels (Grade 11 and Grade 22) and austenitic
stainless steels, welded without sealing run, it is always required the gas
backing shield with inert gas.
In case of Cr low alloy steels (Grade 11 and Grade 22) nitrogen cannot be
used as inert gas.
6.6.1. The filling shall be carried out, usually, immediately after the first run.
6.6.2. In case of Cr low alloy steels (Grade 11 and Grade 22) and austenitic
stainless steels, welded without sealing run, the backing shield with inert
gas shall be maintained until the completion of the second filling run.
The gas backing shall be provided also in case of welding of supports to
pipes with thickness lower than or equal to 4 mm.
6.6.3. In case of Cr low alloy steels (Grade 11 and Grade 22) is mandatory to
complete the weld without interruptions, in order to avoid the risk of
unsuccessful maintaining of the preheating (due to atmospheric events or
absence of power supply).
6.6.4. At the end of each run, the slag shall be carefully removed and eliminated,
by grinding, the possible defects, the metal excesses and the bead
irregularities, in order not to affect the execution of the subsequent runs.
When the joint has been completed, it shall be carefully cleaned to
eliminate the slag and metal spatters.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.6.5. Completed butt welds shall have a weld over thickness not higher than the
value indicated at paragraph 9.6.
The bead shall completely cover the bevels.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.6.6. At the visual examination the welds shall be free of marginal undercuts,
outcropping porosities, discontinuities or other defects and also the bead
shall be properly joined with the base metal.
6.6.7. It is forbidden to clean the bead edges with chisel or hacksaw blade.
Filing is rather acceptable in order to avoid sharp undercuts.
6.6.8. In socket joints and in slip on flanges, the weld shall be carried out with at
least two runs.
6.7.1. Only nickel alloyed filler materials with a nickel content higher than that one
of the base material shall be used.
6.7.2. The re-drying of covered electrodes and flux for submerged arc welding
SAW [process 12] shall be carried out at a temperature not lower than
300°C (unless different requirement by Manufacturer).
6.7.3. Gas containing hydrogen shall not be used for gas shield welds.
6.7.4. Backing gas shield containing hydrogen can be used only under the
complete control of the work conditions.
6.7.5. The dilution of the weld deposit on base material shall be limited to 30% for
base materials that have a poor nickel content respect that one of the filler
material.
6.7.6. The weld metal, with welding processes GTAW [process 141], shall have a
ferrite number FN included between 30 and 100 (22 ÷ 70%).
With other welding processes, or for welded joints exposed to corrosive
environment and/or in presence of diffusible hydrogen and stresses that
can spark cracks by hydrogen, the ferrite number FN shall be included
between 30 and 85 (22 ÷ 60%).
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.7.7. Welds on thin walls shall not involve their own overheating.
The arc energy shall be selected according to material composition and
involved thickness.
In these cases a cold pass technique, that includes a root run with normal
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.7.9. The Welding Procedure Specifications shall include the specific heat input
as essential variable.
6.7.10. Welds without filler metal, arc ignition and inaccurate tack welds on base
material are not acceptable.
6.7.11. For welding shall be used tools, disks, grinds and different assembly
different devices, assigned to be used exclusively for duplex and super-
duplex materials.
The pressure equipment is defined operating in hydrogen service when the partial
hydrogen pressure is higher than 6.9 bar absolutes.
In this case the following requirements shall be respected:
a. for pressure equipment and piping systems in hydrogen service all welds in
contact with the process fluid shall be full penetration type;
b. all butt welds on pressure components shall be 100% X-rays examined, the
non-butt welds shall be ultrasonically examined;
c. all reinforcement plates welded to the walls subjected to pressure shall have a
vent hole.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.9.1. If carbon steel material is used for the fabrication, it shall be killed fine grain
type supplied in normalized condition.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.9.3. Pressure equipment and piping systems, if fabricated in killed carbon steel
or in low alloy steel, shall be submitted to Post Weld Heat Treatment.
6.9.4. For pressure equipment and piping systems in wet H2S service, the
hardness of base metal, fused zone and heat affected zone shall not
exceed the values required in the NACE Standard MR0103.
Welds shall not be carried out on components protected with inorganic zinc primer
or hot dip galvanized, unless the zinc is completely removed from the area adjoining
the weld by sandblasting or grinding.
The removal of zinc rich areas by burning is not permitted.
6.11.1. Sample mock-ups of tubes to tubesheet joints shall be carried out when the
strength weld is specified and, in case of seal weld, when non-ferrous
alloys are joined.
6.11.2. Sample mock-ups shall be made by the same welders that subsequently
will carry out the production welds.
6.11.4. The Procedure Qualification Records (PQR) shall be carried out according
to EEMUA Publication N. 143 and shall include the tear test.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.12.1. Internal surface of base material shall be cleaned to remove rust, bumps,
deposits, dirt, weld spatters, etc., weld reinforcements shall be flush ground
with inside surface.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.12.3. Acceptable filler materials are the same as those used for clad restoring.
6.13.1. The weld overlay process shall be carried out and qualified according to the
requirements of ASME Code Section IX.
The Procedure Qualification Record shall contain at least the following
information :
- chemical analysis;
- result of liquid penetrant examination (PT) on first and last layer;
- result of bend tests;
- ferrite content of the overlay material;
- ferrocyanide test, when required.
Elements to be included in the chemical analysis of weld deposit shall be
the carbon and all other elements included in the filler metal with a content
higher than 1%.
Unless otherwise specified, the material sample for the chemical analysis
shall be taken at least 3 mm depth from the weld deposit surface.
The depth at which these samples have been taken shall be indicated on
the Procedure Qualification Record.
The weld deposit surface shall be relatively smooth (the wave is permitted
but without notches, indentations, etc.).
Interface between the base metal and the weld deposit shall be prepared
by machining, or grinding, whenever it is necessary to eliminate pockets,
sharp notches and other defects that can forbid the bond of weld deposit
material.
When required, the sample of the welding test shall be submitted to a heat
treatment equivalent to that one foreseen for the fabrication.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.13.2. Pressure equipment fabricated with carbon steel or alloy steel plates,
cladded or with weld deposit, shall be welded according to the following
welding sequence :
a. removal of cladded or weld deposited material for at least 10 mm on
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.13.3. Unless otherwise specified, the thickness of weld deposit shall be such to
guarantee, at 3 mm depth from the surface, the same chemical
characteristics as the required lining material.
Maximum weld deposit thickness shall not exceed 10 mm.
The surfaces with weld deposit shall be leaved in the “as deposited”
conditions with the exception of the surfaces in contact with gaskets that
will require machining.
6.13.4. Samples for chemical analysis shall be taken using the “chipping” or
“drilling” technique.
Unless otherwise specified, the sample shall be taken from the weld
deposit from at least 3 mm depth from the surface.
All the areas from which a sample for the chemical analysis has been taken
shall be repaired by Manufacturer using qualified procedures and welders.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
- for nozzles and piping systems is required that weld deposit material
will be submitted to chemical analysis, taken on the welded
component, for each welder, each Welding Procedure and each lot of
wire and/or welding flux.
6.13.7. The overlapping area between contiguous runs shall be indicated on the
WPS.
6.13.8. All procedures for heat treatment of cladded pressure equipment or piping
components shall be submitted to TECHINT for approval.
6.13.9. The ferrite content, for austenitic stainless steel weld deposits, shall be
included between FN 4 and FN 9.
The ferrite content shall be determined by the chemical composition of weld
deposit referred to the Schaeffler or De Long diagrams, or by a magnetic
gage (Severn, Magna, or equivalent).
6.13.11. Ferro cyanide test shall be carried out on all monel and copper-nickel
linings to guarantee the absence of iron and must be reported on the PQR.
The presence of iron shall be indicated with the blue color.
6.14.2. A buffer layer shall be deposited on ferritic steel, using AWS ENiCrFe2 or
3, or ERNiCr3 materials, in order to provide a suitable base material to
deposit the hard material.
In “high sulfur” service (S > 0.5%) at elevated temperature (T > 425°C), the
buffer layer material shall be E 309L or ER 309L.
6.14.3. Hard facing materials to be used are AWS ERCoCrA and ECoCrA.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
6.14.4. The particular requirements for hard facing qualification, are the followings :
- the maximum allowable width of capillary cracks shall not exceed 0,8
mm;
- the crack shall not reach the base material;
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
6.14.5. The requirements for the production tests are the followings:
- the maximum allowable width of capillary cracks shall not exceed 0,8
mm;
- the cracks shall not show abundant evidence on base material;
- the minimum hardness shall be 40 HRC.
Each weld shall be punched with the individual mark of the welder / welder operator.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
7.1. General
Electrodes and/or filler materials shall be supplied according to the requirements of
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
the Codes listed at paragraph 1.2, of ASME Code Section II Part C and shall be
selected so that :
- the strength of the deposited material by welding shall be at least equal to the
minimum tensile strength of base material;
- when similar materials are welding, the chemical composition of the deposited
material shall be as similar as possible to that one of base material.
What above does not preclude the use of welding materials containing different alloy
elements, or in different quantities, from those ones of base material, provided that
shall be evident that such elements are not harmful and that this is the only possible
way to obtain the required properties of the weld deposited material, such a suitable
tensile strength after Post Weld Heat Treatment or a suitable toughness at low
temperature.
7.1.1. Electrodes, wires and fluxes shall be conforms to what indicated in the
Welding Procedure Specifications (WPS).
7.1.2. Any box or container of weld material shall have the same reference
indications quoted in the Welding Procedure Specifications (WPS).
7.1.3. For all filler materials a certificate according to ASME Code Section II Part
C - SFA-5.01 lot classification “C1”, “S1” or “T1”, is required, unless
otherwise specified.
7.2. Storage
7.2.1. Electrodes and fluxes ready for use shall be absolutely dry.
Basic electrodes and fluxes shall be dried in suitable ovens at controlled
temperature between 350°C and 370°C for at least 1 hour and then
maintained at 120°C until they are taken (anyway, if more restrictive, the
requirement of Manufacturer shall be followed).
Electrodes not contained in the original packages or with damaged
packages, shall be rejected and segregated.
7.2.2. Electrodes that show traces of oxidation, or with coating damaged or wet,
shall be rejected and segregated.
7.2.3. After drying in oven, basic electrodes and fluxes shall be kept in suitable
containers that shall maintain them heated and protected from humidity up
to the moment of their use.
Each welder who is using basic electrodes shall have a heated quiver
(temperature ≥ 80°C) from which he will extract the electrode to be used.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
7.2.4. After 8 hours of permanence in the quiver, the unused basic electrodes
shall be put into the holding ovens.
After 15 days of permanence in the holding ovens, the unused electrodes
must be disposed.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
7.2.5. The use of electrodes or fluxes polluted by oil, grease or paint is not
permitted.
Before their use, the filler rods shall be cleaned from possible pollutions.
7.4. Austenitic stainless steels and alloys with high nickel content
7.4.1. For carbon steels and low alloy steels welded to austenitic stainless steels
with operating temperatures up to 370°C and in absence of thermal cycles
and Post Weld Heat Treatments, stainless steel type 309 or 309L shall be
used as filler material.
For these different combinations of base materials with operating
temperatures higher than 370°C, electrodes type Inconel 182 (ENiCrFe-3),
or Incoweld A (ENiCrFe-2), or TIG filler rods type Inconel 82 (ERNiCr-3)
shall be used.
These electrodes/filler materials can also be used as alternative to type 309
for welding components operating at low temperatures, unless there is
presence of sulfur.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
7.4.2. For ferritic steels welded to austenitic stainless steels (300 series), in case
that Post Weld Heat Treatment is required for the ferritic part, such
treatment shall be carried out after the deposit of ENiCrFe-3 (Inconel 182)
on the grooved surface.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
Filler materials 23% Cr duplex 22% Cr duplex 25% Cr duplex 25% Cr duplex 25% Cr
CEN classification without Mo without Cu 1.0 ÷ 2.5% Cu super-duplex
22 9 3 L (1)
25 7 2
25 9 3 CuL
25 9 4 L
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
8.1. Post Weld Heat Treatments of carbon and low alloy steels shall be in compliance
with the requirements of the following Codes :
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
- ASME Section I;
- ASME Section VIII Division 1;
- ASME Section VIII Division 2;
- ASME B31.1;
- ASME B31.3.
When components of different thickness are welded, the holding time at Post Weld
Heat Treatment temperature shall be that one concerning the greater thickness.
For base materials supplied with tempering heat treatment, the temperature of Post
Weld Heat Treatment must be at least 20°C lower than the tempering heat treatment
temperature of base material.
At this purpose, the Manufacturer / Subcontractor shall previously supply the
material certificates showing the parameters (temperature and holding time at
temperature) concerning the heat treatments undergone by materials during the
production cycle.
8.2. Post Weld Heat Treatments of austenitic stainless steel components and/or in alloys
with high nickel content shall be carried out only if specifically required.
8.3. Heat treatments can be carried out by electrical induction, electrical resistance, or
with electrical or fuel furnaces.
A suitable device shall record the entire cycle of the heat treatment on diagram
paper: heating rate, holding time at temperature, cooling rate.
This device shall be connected to thermocouples using a suitable compensated
cable, in addition shall be checked and calibrated in the place of use with type of
thermocouples and compensated cable used.
In the record diagram the references of individual thermocouples shall be clearly
distinguished.
The record diagrams of heat treatments shall report the following data :
- progressive number of diagram;
- number of weld / welds (with reference to line / isometric for piping);
- Welding Procedure Specification (WPS) used;
- number and reference of thermocouples;
- number and reference of recorders;
- date and hour of heat treatment execution;
- temperature and time scales;
- stamp and signature of the responsible of heat treatment execution.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
8.4. The thermocouples shall be located so as to avoid both the direct contact with the
heating electric elements and the burner flame.
The number of thermocouples to be applied is specified in Table B.
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
Table B
Outside pipe diameter Minimum number of Thermocouples position
thermocouples (reference in degrees)
Do ≤ 323,8 mm (12”) 2 0° - 180°
323,8 mm (12”) < Do ≤ 457,2 (18”) 3 0° - 120° - 240°
Do > 457,2 (18”) 4 0° - 90 - 180° - 270°
8.5. Possible fixing systems for thermocouples carried out by weld shall be supported by
a qualified WPS and certified welders.
Preheating temperature shall be the same required for the weld or for the material to
be heat treated.
After that heat treatment has been completed, the fixing areas of thermocouples
shall be flush ground and checked with liquid penetrant or magnetic particle
examinations.
8.6. If heating and/or cooling rate, or the temperature gaps between thermocouples,
exceeds the required limits, the joint so heat treated shall be submitted to
radiographic examination.
If maximum heat treatment temperatures, or holding time at temperature, are not
within the required limits, the heat treatment must be repeated.
8.7. The furnace configuration shall be such to avoid the direct contact of the flame with
the material surface.
8.8. All machined surfaces shall be protected against oxidation during heat treatment.
8.9. Internal and external surfaces of component to be heat treated shall be sufficiently
cleaned and free from any foreign material that can cause harmful metallurgic
effects on the material as a consequence of the heat cycle.
8.10. During heat treatment, no low melting point material, as copper or galvanized steel
wires, shall come in contact with the material to be treated.
8.11. The representative specimens of the component to be heat treated shall be heat
treated at the same time as the component itself, or, if are treated separately, they
shall be submitted to an equivalent heat treatment.
8.12. After final heat treatment, no arc ignition or repair can be made on component
unless the same is heat treated again.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
8.14. For piping welds Post Weld Heat Treatment shall be carried out, when required,
according to the requirements of Table C.
Table C
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
9.1.1. Weld repairs shall comply with the prescriptions of the applicable Code,
including preheating, Post Weld Heat Treatment and non-destructive
examination requirements.
9.1.2. Defects shall be removed by grinding and the repaired welds shall be Post
Weld Heat Treated, if it was originally required, and examined according to
the original method to guarantee the absence of defects.
9.1.4. Inspection shall be carried out on all full thickness of butt welds according
to the follows :
- For pressure equipment
Radiographic technique and acceptance standards shall be conform
to the requirements of ASME Section V, ASME Section I, ASME
Section VIII Division 1 and ASME Section VIII Division 2 Codes.
When submerged arc welding has been used for main seams, all
seam intersections and all stopping and starting points of welding
runs shall be radiographed.
Radiographic examination shall be carried out after the Post Weld
Heat Treatment, if required.
- For piping components
Radiographic technique and acceptance standards shall be conform
to the requirements of ASME Section V, ASME B31.1 and ASME
B31.3 Codes.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
9.2.1. For pressure equipment and piping components, not operating in wet H2S
service, the hardness of base material, weld and heat affected zone shall
not exceed the following values :
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
Material Hardness
Carbon steel
225 HB
(only for thicknesses greater than 25 mm)
1Cr and 1¼Cr alloy steel 225 HB
2¼Cr alloy steel 241 HB
400 series stainless steel 241 HB
For Cr low alloy steel (Grade 11 and Grade 22) a ferritic-bainitic structure
shall be ensured.
For Cr low alloy steels (Grade 11 and Grade 22), hardness shall be
checked in fused zone, in heat affected zone and in base material near the
heat affected zone at 40 mm distance from the same (on both sides).
9.2.3. If two different materials are welded, the maximum hardness of the weld
shall not exceed the lesser required value for the involved base materials.
Hardness of each affected zone shall not exceed the hardness required for
the contiguous base material.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
specification :
- corrosion test in heat affected zone;
- micrographic examination for search of chromium carbide
precipitation in heat affected zone;
- measurement of ferrite content in fused zone, this value shall
be included between FN 4 and FN 9.
9.4. The Procedure Qualification Records (PQR) shall include the results of additional
tests (hardness, impact test, etc.), when required.
9.6. Workings
Reinforcements of butt welds, on pressure equipment plate joints, shall not exceed
the following values:
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
9.7.3. Surface examination with magnetic particles (MT) or liquid penetrant (PT)
A surface examination (MT or PT) shall be carried out at 100% on welds
after Post Weld Heat Treatment.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
Limitations
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
111 - with covered electrodes SMAW - Shielded Metal Arc (14), (15), (18)
141 - with non-consumable GTAW - Gas Tungsten Arc (TIG) (1), (11), (18)
tungsten electrode,
TIG weld
131 - in inert gas with GMAW - Gas Metal Arc (1), (2), (3), (7),
consumable electrode wire, (10), (11), (16)
MIG weld
135 - in active shielding gas with (1), (2), (3), (7),
consumable electrode wire, (10), (11), (16)
MAG weld
136 - in active shielding gas with FCAW - Flux-Cored Arc (5), (9), (16)
cored electrode
137 - in inert gas with cored (5), (9), (16)
electrode wire
114 - with cored electrode wire (5), (9), (12), (16)
without shielding gas
12 - submerged with electrode SAW - Submerged Arc (4), (5), (6), (8),
wire (9), (17), (18)
Limitations
(1) An internal washing with inert gas is required for weld consumable inserts of all materials,
for root and second run of single welds for butt joints in materials with alloy content
greater than 3%.
In order to guarantee a proper shielding for gas backing, it is necessary to introduce the
necessary amount of gas before welding.
During welding, the gas backing flow rate shall be that one qualified.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
(3) Short Arc or Pulsed Arc automatic welding is permitted for full thickness butt welds, for
piping components of any dimension, with the following limitations :
- PA position only;
- for thicknesses larger than 9 mm, but not over 25 mm, is permitted to use an
automatic weaving arc and a minimum current of 170 ampere is required for all runs
after root run;
- not permitted when a big thermal dissipating mass can compromise the weld
integrity (slip-on and socket flange welds, fillet welds, branches, weldolets, etc.) and
whenever the thickness of both materials of the joint exceeds 9 mm;
- not permitted for piping components with nominal diameter lower than 75 mm;
- permitted only if the feed direction is indicated in the Welding Procedure
Specification;
- not permitted to deposit filling or covering in descending;
- the percentage of the welds to be radiographed shall be increased as regards than
one required by applicable Code, by 5% for welds on thicknesses up to 9 mm and
by 10% for those ones on larger thicknesses.
(4) The use of neutral flux (non-sensitive) is required for Submerged Arc Welding [process
12] of carbon steels with thicknesses larger than 25 mm and for all materials other than
carbon steel.
If a sensitive flux is used, each production welding shall have a maximum hardness of 200
HB.
(5) The use of alloyed wire and of neutral flux is required for alloy weld deposits.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
(8) Run on and run off plates, shall be of the same material as the base material on all
longitudinal welds.
(9) The wire-flux combinations used for production welds, shall be the same as used in the
Procedure Qualification Record (PQR).
(11) If this process is used for field welding, suitable precautions shall be taken to shelter the
welding area from wind, or air flows that can compromise the efficiency of shielding gas.
(12) This welding process is not permitted for execution of welds on carbon or alloy steel
components, submitted to pressure or vibrations.
(13) The single runs, carried out with automatic standard processes, shall not deposit more
than 6,35 mm.
(14) For Cr low alloy steels (Grade 11 and Grade 22) welding, basic electrodes shall be special
type at low hydrogen absorption (4 ml H2 / 100 g) with certificate according to ASME Code
Section II Part C - SFA-5.01, lot classification “C4” or “S3”, with inspection / testing level
“I”.
(15) For Cr low alloy steels (Grade 11 and Grade 22) welding, the joint filling shall be carried
out using electrodes with 2,5 mm or 3,25 mm diameter.
The use of electrodes with larger diameter than that one required shall be previously
agreed with TECHINT.
(16) This welding process is not permitted for Cr low alloy steels (Grade 11 and Grade 22)
welding.
(17) For Cr low alloy steels (Grade 11 and Grade 22) welding, the use of this process is
accepted for the execution of filling runs of butt joints and for fillet joints of piping
components positioned with rolling horizontal axis and only for diameters larger than or
equal to 150 mm and thicknesses larger than 5 mm.
Multipass technique shall be used (at stretched beads).
The use of this process shall be previously approved by TECHINT.
(18) For Cr low alloy steels (Grade 11 and Grade 22) welding, the welding filler materials shall
be supplied with certificate according to ASME Code Section II Part C - SFA-5.01, lot
classification “C4” or “S3”, inspection / testing level “I”.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
10.0 TITANIUM
10.1.2. The shears cut can only be used as roughing out cut and edges shall than
be submitted to machine tool working (milling).
10.1.3. Cut oils, greases or emulsions containing sulphur or halogens, are not
permitted.
The recommended cooling liquids are :
- 5% solution of sodium nitride (Na3N) in water;
- 5% to 10% solution of soluble oil in water.
10.1.4. All tools shall be carefully cleaned before their use and shall be employed
for titanium and its alloys only.
10.2.1. The area concerning fusion and contiguous surfaces to edges (25 mm
minimum on both sides) that will be interested by welding, as fused or
however heated at a temperature over 300°C, shall be always prepared as
required in the following points.
10.2.2. Cleaning shall be made using austenitic stainless steel or titanium brushes,
in order to remove scales, paints, trapped dirt, silvery metal, abrasives, dust
and any foreign substances that could react with titanium surfaces.
The use of steel wool, glass paper or coated ceramic paper, is not
permitted.
10.2.4. In presence of a thin oxide layer, this one shall be removed by pickling (see
paragraph 10.3).
If the oxide layer is thicker, as the one that is formed at temperatures over
600°C, this shall be removed by sandblasting or mechanical work followed
by pickling (see paragraph 10 .3).
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
10.2.5. Surfaces submitted to pickling shall anyway be rekindled by filing with fine
file before the washing with solvents (ethyl alcohol, acetone, methyl ethyl
ketone, etc.), that shall be carried out immediately before welding.
Use of chlorinated, sulphide and sulphur-chlorinated solvents is not
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
10.2.6. Use of textile fabrics with naps, wool or cloths is not permitted.
10.2.7. After cleaning, the welding joint shall be kept fully free from contaminations,
including fingerprints, until the welding begin.
10.3. Pickling
10.3.2. The nitric acid content shall be anyway maintained over 20% to minimize
the absorption of hydrogen and the consequent embrittlement (brittleness
by pickling or by hydrogen).
10.3.3. After pickling a washing with alcohol or warm water (with chloride content
not over 100 ppm) shall be carried out, followed by a careful drying to avoid
water evaporation.
10.4.1 General
During welding the fused zone and each contiguous area, on welding and
back sides, that can reach the temperature of 300°C, shall be protected
against the contamination of atmospheric gases (oxygen, nitrogen and
hydrogen).
This protection shall be provided by an inert gas atmosphere (argon or
helium), or by the execution of the under vacuum welding at a pressure not
larger than 10-5 bar absolutes.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
10.6. Welding
10.6.1. The acceptable welding processes for welding titanium and its alloys are :
- TIG (GTAW) [process 141];
- plasma (PAW) [process 15];
- electron beam (EBW) [process 51];
- laser (LBW) [process 52].
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
0,25 ÷ 2
2÷6
6 ÷ 10
> 10
10.7.3. For non-automatic welding processes and for butt welds up to 4,5 mm
thickness, wires with diameter up to 1,6 mm shall be used.
Over 4,5 mm thickness, 2,4 mm, 3,2 mm and 4 mm diameter wires can be
used.
MOD/GEN-02e Rev 01
GENERAL WELDING SPECIFICATION
FOR PRESSURE EQUIPMENT
ACCORDING TO ASME CODE
10.7.4. For GTAW automatic welding process [process 141], wires with diameter
0,8 mm, 1,1 mm and 1,6 mm shall be used.
10.8. Preheating
THIS DOCUMENT IS PROPERTY OF TECHINT AND MAY NOT BE PARTLY OR WHOLLY REPRODUCED WITHOUT PRIOR WRITTEN PERMISSION FROM TECHINT
In butt weld joints, the temperature of base material shall always be maintained over
16°C.
Root run and intermediate runs, shall have a temperature lower than 150°C before
starting the subsequent run.
10.10.3. Procedure Qualification Reports (PQR) shall be carried out with the same
materials used in production (base material, welding filler material, shield
gas, etc.).
MOD/GEN-02e Rev 01