ACTIVITY : Conduit/Piping Installation & Wiring for VRF Power Supply (Residential Hallway Aircon) LEGENDS :

LOCATION : Lower Ground to Penthouse PENDING


DATE STARTED : Oct. 1, 2018 DEADLINE : Jan. 15, 2018 DONE

DURATION*
START DAYS DAYS MATERIALS
TASK NAME
DATE
END DATE (WORK
COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE Oct Nov Dec Jan.
DAYS)

1. Electrical 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1.1 Hanger/Support Oct. 1 Jan. 15 50 24


Chipping/Coring/Civil
1.2 Works Oct. 1 Oct. 30
Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening Oct. 1 Oct. 30 27 27

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination 0 0%

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
ACTIVITY : Auxiliary, Voice & Data Installation for Leasable @ Lower Ground LEGENDS :
LOCATION : Lower Ground TARGET :
DATE STARTED : DEADLINE : STATUS :

DURATION* DAYS DAYS MATERIALS


TASK NAME START DATE END DATE
(WORK DAYS) COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE November

1. Electrical 3 4 5 6 7 8 9 10 11 12

1.1 Hanger/Support

1.2 Chipping/Civil Works


Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
ACTIVITY : Auxiliary Grounding System LEGENDS :
LOCATION : Lower Ground TARGET : Cha
rt
Title

DATE STARTED : DEADLINE : STATUS : Cha


rt
Title

DURATION* DAYS DAYS MATERIALS


TASK NAME START DATE END DATE
(WORK DAYS) COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE November

1. Electrical 3 4 5 6 7 8 9 10 11 12

1.1 Hanger/Support
Chipping/Coring/Civil
1.2 Works
Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
ACTIVITY : Penthouse Suites Power Supply LEGENDS :
LOCATION : Penthouse TARGET
DATE STARTED : Nov. 24, 2018 DEADLINE : Nov. 28, 2018 DONE

DURATION*
START DAYS DAYS MATERIALS
TASK NAME
DATE
END DATE (WORK
COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE Nov. Dec.
DAYS)

1. Electrical 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7

1.1 Hanger/Support Nov. 22 Nov. 28 4 2 2 3 on-site


Chipping/Coring/Civil
1.2 Works Nov. 24 Nov. 28 4 2 2 3 on-site
Cable Tray Fabrication &
1.3 Installation Nov. 24 Nov. 28 4 2 2 3 on-site

1.4 Wall/Slab Opening Nov. 24 Nov. 28 4 2 2 3 on-site

1.5 Sleeve Termination Nov. 24 Nov. 28 4 2 2 3 on-site


Wire/Cable Pulling &
1.6 Termination

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.0 Response to Punchlist

2.1 Turn-over
ACTIVITY : Conduit/Piping Installation & Wiring for VRF Power Supply (Residential Hallway Aircon) LEGENDS :
LOCATION : Lower Ground to Penthouse PENDING
DATE STARTED : Oct. 1, 2018 DEADLINE : Jan. 15, 2018 DONE

DURATION*
START DAYS DAYS MATERIALS
TASK NAME
DATE
END DATE (WORK
COMPLETE* REMAINING*
MANPOWER
AVAILABILITY
% DONE Oct Nov Dec Jan.
DAYS)

1. Electrical 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1.1 Hanger/Support Oct. 1 Jan. 15 50 24


Chipping/Coring/Civil
1.2 Works Oct. 1 Oct. 30
Pull Box Fabrication &
1.3 Installation

1.4 Wall/Slab Opening Oct. 1 Oct. 30 27 27

1.5 Sleeve Termination


Wire/Cable Pulling &
1.6 Termination 0 0%

1.7 Testing

1.8 Painting/Civil Works


Punchlist
1.9

2.00 Response to Punchlist

2.10 Turn-over
Construction Form
1 Cable Tray Installation & Wiring for C-5 side @ Lower Ground ok
2 Plumbing and Sanitary Rectification @ Lower Ground ok
3 Penthouse Cable Tray Installation and Wiring for VRF power supply ok
4 Auxiliary / Voice & Data for leasable area @ Lower Ground
5 MDP for Video wall
6 Hyper-Aire letter
7 Installation of Aircon @ School Lobby

Testing & Commisioning


1 Testing of all basement exhaust fan (2 fans with issues)
2 Testing of Gensets (Friday to Saturday)
3 Fire Protection Pressure/Leak Test
4 Megger Testing
5 Water and Electricity Bill settlement
6 Water Pressure Test/Leak Test