Item Derivative Possible Causes Possible Consequences Action Required
Node Parameters 1A Pump Flow No 1. Blockage in pump 1. Damage to pump due to 1. Inspection/maintenance 2. Blockage in inlet overpressure of inlet/exit pipeline pipeline 2. No flow of raw materials to and pump for blockage 3. Blockage in exit reactor 2. Replacement of pipeline damaged pumps 4. Mechanical failure of 3. Installation of bypass pump line with backup pump in case of failure Less 1. Blockage in pump 1. Less flow of materials to 1. Inspection/maintenance 2. Blockage in inlet reactor – low production of inlet/exit pipeline pipeline 2. Backflow of materials to and pump for blockage 3. Blockage in exit supply tank – 2. Replacement of pipeline contamination risk inefficient pumps 4. Pump efficiency not at 3. Installation of bypass optimum line with backup pump in case of failure More 1. Damage to pump 1. Overflow of materials to 1. Replacement of blades reactor leading to level damaged pumps 2. Damage to pump problems 2. Installation of bypass controlling mechanism 2. Risk of runaway line with backup pump exothermic reaction Reverse 1. Blockage in exit 1. Backflow of materials to 1. Inspection/maintenance pipeline supply tank – of exit pipeline and contamination risk pump for blockage Pressure No 1. Blockage in pump 1. Damage to pump due to 1. Inspection/maintenance 2. Blockage in inlet overpressure of inlet/exit pipeline pipeline 2. No flow of raw materials to and pump for blockage 3. Blockage in exit reactor 2. Replacement of pipeline damaged pumps 4. Mechanical failure of 3. Installation of bypass pump line with backup pump in case of failure Less 1. Leakage of exit 1. Reaction not at peak levels 1. Inspection/maintenance pipeline 2. Potential backflow of of exit pipeline for 2. Leakage in pump materials leakage 3. Pump efficiency not at 2. Inspection/maintenance optimum of pump for leakage 4. High velocity leading 3. Replacement of to pressure drop inefficient pumps More 1. Partial blockage of exit 1. Damage to pump due to 1. Inspection/maintenance pipeline overpressure of exit pipeline for blockage