Meeting Chaired by: PROJECT DIRECTOR , IDAP Location: Conference Room at Site
Discussion about the submittal submission status 200 Beeded Mother & Child Hospital,Layyah
Participants
(A) Attendees:
1.1 Steel grated door with 1/16" sheeting and angle iron frame) (C- 26), Contractor CCECC-SALMAN JV
will submit the shop drawings by tomorrow. 04 August 2023
th
Laminated wooden Floor (Floor & Skirting) (C-32), Contractor needs to submit the CCECC-SALMAN JV
1.2 Polished Sample for approval by tomorrow. 04 August 2023
th
Accoustical Panel for ceiling (C-45), Contractor will discuss with vendor and re-Submit CCECC-SALMAN JV
the submittal with sample with in 1 week.
1.3 10 August 2023
th
Laminated wooden wall (C-48), Contractor will re-submit the submittal by tomorrow. CCECC-SALMAN JV
1.4 04 August 2023
th
Wash Terrazzo on walls (C-49), Contractor will arrange the sample by tomorrow. CCECC-SALMAN JV
1.5 04 August 2023
th
M.S Louvered doors (C-61), Contractor will submit the shop drawings by tomorrow and CCECC-SALMAN JV
prepare one sample with actual size and get Approval.
1.6 04 August 2023
th
2" thick asphalt (Bitumen, Stone dust and aggregate) (C-71), CCECC-SALMAN JV
Contractor will re-Submit the submittal including sample by today.
1.7 03 August 2023
th
Steel Window openable glazed pannel (C-81), This item is deleted and contractor CCECC-SALMAN JV
neede to use Aluminium instead of Steel as per RFI Response.
1.8
UPVC /phenolic Door, Contractor will submit the Submittal with sample within one week. CCECC-SALMAN JV
1.9 10 August 2023
th
2-HVAC
Round Insulated Flexible Duct (H-04), Contractor will submit the submittal within one CCECC-SALMAN JV
2.1 week. 10 August 2023
th
Exhaust Flue duct 3" (H-05), thick foil-faced rock wool thermal insulation, Contractor CCECC-SALMAN JV
will submit the submittal with in one week.
2.2 10 August 2023
th
Aluminium cladding (H-09), over exposed ducting /piping & Plant room Piping (0.5mm CCECC-SALMAN JV
thick), Contractor will submit the submittal by tomorrow.
2.3 04 August 2023
th
Flexible duct connector (H-10) , of Robust Polyester with PVC coating 6" wide, CCECC-SALMAN JV
2.4 Contractor will submit the submittal by tomrrow. 04 August 2023
th
Terminal HEPA filter (H-25), Contractor will re-submit the submittal within one week. CCECC-SALMAN JV
2.5 10 August 2023
th
3-Plumbing
3.1 PVC Floor Cleanouts (P06), Contractor will Re-submit by tomorrow. 04 August 2023
th
CCECC-SALMAN JV
3.2 RO Plant to produce 1.0 m3/hr product water as per WHO standardsfountain (P- CCECC-SALMAN JV
11), Contractor instructed to review the highlighted issue and re-Submit it with in 2 days. 05 August 2023
th
3.3 Ductile Iron Pipe 8" dia (P-67), Contractor will submit the submittal by tomorrow. 04 August 2023
th
CCECC-SALMAN JV
Fiber Glass Shed using Fiber Glass double ply sheet and M.S square pipe of CCECC-SALMAN JV
3.4 section 1-1/2"x1-1/2" of 18 SWG (P-68)" Contractor confimed that they will Re-submit 07 August 2023
th
with in 3 days.
3.5 Garden Type Hydrants, (P-70), Contractor Required to submit the required 10 August 2023
th
CCECC-SALMAN JV
documentation for approval.
4-Electrical
4.1 Wiring Accessories (E-04), Contractor will re-submit the submittal by tomorrow. 04 August 2023
th
CCECC-SALMAN JV
4.2 UPS (10 kva.30 kva and 60 kva) (E-14), Contractor will confirm the status within one 10 August 2023
th
CCECC-SALMAN JV
week.
4.3 Elevators (Dumb Waiter) (E-18), ), Contractor will confirm the status within one week. 10 August 2023
th
CCECC-SALMAN JV
4.4 Public Address System (Hospital Building) (E-24), Contractor will confirm the status 10 August 2023
th
CCECC-SALMAN JV
within one week.
4.5 Public Address System (Lecture Hall), Contractor will confirm the status within one 10 August 2023
th
CCECC-SALMAN JV
week.
4.6 ENCLOSED BUS ASSEMBLIES (E-35), Contractor will Re-submit submittal for source 04 August 2023
th
CCECC-SALMAN JV
approval by tomorrow.
5-Fire Fighting
5.1 FM 200 (FF-17), Contractor will re-submitt the submittal within one week. 10 August 2023
th
CCECC-SALMAN JV
5.2 Fire Protection Pumps (FF-02), Contractor will confirm the status within one week. 10 August 2023
th
CCECC-SALMAN JV
Meeting ended with a vote of thanks to and from all the participants.
Distribution:
1. All participants
2. File
Issued by:
Uzair Ahmad
Planning & Project Control Engr