EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A. Installation
Verify that backbone cable trays and cabling are suspended from or
SAES-T-916,
A3 attached to the structural ceiling or walls with hardware or other
para 4.8.18.4
installation aids specifically designed to support their weight.
Verify that backbone cable trays and cables are not resting directly on
SAES-T-916,
A4 ceiling panels, framework (T-bars), vertical supports, or other
para 4.8.18.4
components of the suspended ceiling.
Verify that backbone cable tray is located 15 cm (6 in.) to 30 cm (12 in.) SAES-T-916,
A5
above the top surface of the cable tray side rail. para 4.8.18.4
Verify that the backbone cable trays have a minimum of 8 cm (3 in.) of SAES-T-916,
A6
clear vertical space from conduits, wires, and cables. para 4.8.18.4
Verify that the inside of backbone cable tray is free of burrs, sharp edges, SAES-T-916,
A7
or projections which can damage cable insulation. para 4.8.19.1
Verify that backbone cable tray system is not used to distribute SAES-T-916,
A8
telecommunications and power cables together. para 4.8.19.1
Verify that backbone cable trays are not installed in ceiling areas (lock SAES-T-916,
A9
tiles, drywall or plaster) that are inaccessible.. para 4.8.19.1
Verify the use of proper support for cable trays by installing cantilever SAES-T-916,
A10
brackets, trapeze supports and individual rod suspension brackets. para 4.8.19.3
Verify that cable tray fills is not exceeding the manufactures listed
SAES-T-916,
A12 capacity for the installed backbone cable tray or the maximum load
para 4.8.19.3
bearing capacity design.
Verify that during the installation that workers never use cable trays as SAES-T-916,
A13
walkways or ladders. para 4.8.19.3
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A. Installation
Verify that the backbone cable tray is readily accessible to technician and SAES-T-916,
A15
installer. para 4.8.21
Verify that backbone cable trays are marked and identified as specified in
SAES-T-916,
A16 paragraph 4.10 by EIA TIA-606, "The Administration Standard for the
para 4.8.19.4
Telecommunications Infrastructure of Commercial Buildings".
Verify that the backbone cable tray enters the TR in such a way that it SAES-T-916,
A17
does not block or cover other equipment and cabling. para 4.8.21
Verify that the backbone cable tray is secured mechanically or anchored SAES-T-916,
A18
so that movement does not occur during installation of cables. para 4.8.21
Verify that the installed backbone cable tray allows for 20% expansion of SAES-T-916,
A19
the horizontal cabling system. para 4.8.21
Verify that backbone cable trays are not house or support cable splice SAES-T-916,
A21
closures. para 4.3.5.4.3
Ensure that the fittings used to change the direction or size of a cable SAES-T-916,
A22
tray includes: Elbows, Reducers, Crossovers and Tees. para 4.8.19.2
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-T-916: Telecommunications Building Cable Systems, issued date 09 September, 2013.
2. BICSI, Chapter 5 - latest edition.
NOTES: