Project:- Saving Houses B+G+8 Typology Revis Block Type:- New B+G+8

Client:- Addis Ababa Saving Houses Developme Block No.____________


Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Timizing Dimension Qty Description

SUB-STRUCTURE
Excavation and Earth Work
Site Clearing and Removing Top soil 200mm
1 1 1 738.43 (allowing 1.50m working space)
1.00 738.43
738.43 Total
Bulk excavation up to 150cm
(allowing 1.00m top & 0.25cm bottom working space both side)
1 1 1 729.68 from autocad
1.50 1,094.52
1,094.52 Total
ditto but from 150 to 300cm
1 1 1 729.43 from autocad
1.50 1,094.15
1,094.15 Total

ditto but from 300 to 450cm


1 1 1 729.43 from autocad
1.50 1,094.15
1,094.15 Total
ditto but from 450 to 600cm
1 1 1 729.43 from autocad
1.50 1094.15

1 1 -1 12.10 Deduct 15cm thick slab


4.90 Axis A-C/1-2
0.95 -56.33

1 1 -1 6.17 Axis E-F/1-2


4.90
0.95 -28.72
1 1 -1 5.43 Axis F-G/2-5
14.90
0.95 -76.86
1 1 1 6.30 Lift area
5.65 Av.W-(7.8+4.8)/2=6.30
1.50 53.39 Av.W-(6.8+4.5)/2=5.65
985.63 Total
Pit Excavation up to 150cm
(allowing 0.25m working space)
1 1 4 2.20 F-1
2.20
1.50 29.04
29.04 Total
ditto but from 150 to 300cm
(allowing 0.25m working space)
1 1 4 2.20 F-1
2.20
1.50 29.04
29.04 Total
Trench Excavation up to 150cm
1 1 1 38.65 Peripherial
1.00
1.20 46.38

46.38 Total to Item 1.8

Fill around isolated footing with selected material from quarry waste
and compact in layers not exceeding 200mm thick.
1 2 1 29.04 Pit Excavation
58.08
1 -4 1 1.70 DDT (Lean & Concrete under Pad)
1.70
0.05 -0.58
1 -4 1 1.70
1.70
0.25 -2.89
54.61 Total
Backfill under mat foundation with non expansive selected material from
quary
1 1 1 700.96
0.60
420.58
1 1 -1 11.25 Deduct 15cm thick slab
4.05 Axis A-C/1-2
0.60 -27.34

1 1 -1 5.32 Axis E-F/1-2


4.05
0.60 -12.93
1 1 -1 4.65 Axis F-G/2-5
13.20
0.60 -36.83
343.48 Total
Back fill Under Hardcore (solid slab)
1 1 1 11.25 Axis A-C/1-2
4.05
0.40 18.23
1 1 1 5.32 Axis E-F/1-2
4.05
0.40 8.62
1 1 1 13.15 Axis F-G/2-5
4.65
0.40 24.46
51.31 Total
Back fill under strip foundation
1 1 1 12.20 axis 1 b/n A,B & B'
1.05
0.50 0.53
1 1 1 6.17 axis 1 b/n E & F
1.05
0.50 0.53
1 1 1 5.43 axis 2 b/n F & G
1.05
0.50 0.53
1 1 1 5.43 axis 5 b/n F & G
1.05
0.50 0.53
1 1 2 4.90 axis A & F b/n 1 & 1'
1.05
0.50 0.53
1 1 1 13.20 axis G b/n 2,3,4 & 5
1.05
0.50 0.53
3.18 Total

=BOQ!$B$40
1 1 1 738.43
0.20 147.69
1,094.52 Bulk excavation up to 150cm
1,094.15 Bulk excavation from 150 to 300cm
1,094.15 Bulk excavation from 300 to 450cm
985.63 Bulk excavation from 450 to 600cm
Bulk excavation from 600 to 750cm
29.04 Pit excavation from up to 150 from NGL
29.04 Pit excavation from 150 to 300 cm
4,474.22 Total

250mm thick basaltic stone hardcore well rolled, consolidated and


blinded with crushed stone.
@ elev. +0.00m( verenda)
1 1 1 17.45 axis B-E/5-6
3.60 62.82
In ramp interance
1 1 1 3.46 Axis F-G/5-6
5.08 17.58
1 1 1 5.03 axis F-G/2-5
13.15 66.14
@ elev. -3.30m
1 1 1 11.25 axis A-C/1-2
4.05 45.56
1 1 1 5.25 axis E-F/1-2
4.05 21.26
213.36 Total
Concrete Work
50mm Lean concrete quality c-5
Basement floor
A. Under footing Pad
allowing 10cm width addition
1 1 4 1.80 F-1
1.80 12.96

12.96 Total
B. Under mat foundation
allowing 5cm width addition
1 1 1 573.70
1.00 573.70

573.70 Total
C. Under strip foundation
1 1 1 12.10 axis 1 b/n A-B'
0.95 11.50 m²
1 1 1 6.17 axis 1 b/n E & F
0.95 5.86 m²
1 1 1 5.50 axis 2 b/n F & G
0.95 5.23 m²
1 1 1 5.50 axis 5 b/n F & G
0.95 5.23 m²
1 1 2 4.05 axis A & F b/n 1 & 1'
0.95 7.70 m²
1 1 1 13.20 axis G b/n 2-5
0.95 12.54 m²

48.06 m² Total
E. under 15cm thick basement slab
Axis A-C/1-2
1 1 1 11.25
4.05 45.56 m²
Axis E-F/1-2
1 1 1 5.32
4.05 21.55 m²
Axis E-G/2-5
1 1 1 13.20
4.65 61.38 m²

128.49 m² Total
F. under Ground floor Slab
1 1 1 17.35 b/n axis B-E & 5-6
3.60
62.46 m²

62.46 m² Total
G. Under Ground floor beam

1 1 1 17.25 GB-4
0.25 On axis 6/B-E
4.31 m²
1 1 2 3.55 GB-5
0.25 On axis B & E/5 - 6
1.78 m²
1 1 1 3.55 GB-7
0.30 On axis D'/5 - 6
1.07 m²
1 1 1 3.55 GB-13
0.30 On axis C/5-6
1.07 m²
8.23 m² Total
Reinforced concrete (C-25)
A. In footing pad
1 1 4 1.70 F-1
1.70
0.25 2.89

2.89 Total
B. In 110mm thick mat foundation
1 1 1 573.70 Mat
1.10 631.07
1 0.5 1 7.80 Triangle lift area
1.50 Y-direction
1.50 8.78
1 0.5 1 7.80
0.76
0.76 2.25
1 0.5 2 6.30 X-direction
1.50
1.50 14.18
1 1 1 4.08 Rectangle lift area
1.50 Y-direction
4.80 29.38
1 1 -1 1.80
0.40
4.80 -3.46
1 1 1 4.36 X-direction
1.50
4.47 29.23
1 1 -1 1.80
0.40
4.47 -3.22

708.21 Total
C. In strip foundation
1 1 1 12.10 axis 1 b/n A - B'
0.95
0.25 2.87
1 1 1 6.17 axis 1 b/n E & F
0.95
0.25 1.47
1 1 1 5.50 axis 2 b/n F & G
0.95
0.25 1.31
1 1 1 5.50 axis 5 b/n F & G
0.95
0.25 1.31

1 1 2 4.05 axis A & F b/n 1 & 1'


0.95
0.25 1.92
1 1 1 13.20 axis G b/n 2 - 5
0.95
0.25 3.14

12.02 Total
D. In 15cm thick basement slab
1 1 1 11.20 Axis A-C/1-2
4.35 48.72
1 1 1 5.32
4.05 21.55 Axis E-F/1-2
1 1 1 13.20
4.65 61.38
Axis E-G/2-5
131.65 Total
E. In foundation column
1 1 4 0.30 C-1
0.30
2.42 0.87

0.87 Total
F. In Basement column
1 1 4 0.30 C-1
0.30
2.80
1.01
1 1 15 0.60 C-2
0.60
2.80
15.12
1 1 7 0.80 C-3
0.80
2.80
12.54
1 1 8 0.40
0.40
2.80 3.58
At slab,beam & coll coniction
1 1 15 0.35 C-2
0.35
0.34 0.62
1 1 7 0.55 C-3
0.55
0.34 0.72
1 1 8 0.15
0.15
0.34 0.06
33.65 Total
G. In shear wall for lift
Basement floor
1 1 2 2.60 W-2
0.25
2.70 3.51
1 1 1 1.80 W-3
0.25
2.70 1.22
1 1 1 1.80 W-4
0.25
2.70 1.22
1 1 -1 1.00
2.10
0.25 -0.53

5.42 Total
H. In retaining wall
1 1 1 32.53 W-1
0.25
2.80 22.77
1 1 1 5.03 W-2
0.25
2.80 3.52
1 1 1 28.20 W-3
0.25
2.80 19.74
1 1 -2 3.00 Ddt Opening
0.25
0.25 -0.38
1 1 1 18.80 W-4
0.25
2.80 13.16
1 1 -2 3.00 Ddt Opening
0.25
0.25 -0.38
1 1 1 6.70 W-5
0.25
2.80 4.69
1 1 1 12.70 W-6
0.25
2.96 9.40

72.52 Total
I. In Grade beam
1 1 2 27.00 GB-1
0.50
0.25 6.75
1 1 1 9.68 GB-2
0.50
0.25 1.21
1 1 1 15.32 GB-3
0.50
0.25 1.92
1 1 1 17.25 GB-4
0.50
0.25 2.16
1 1 2 22.45 GB-5
0.50
0.25 5.61
1 1 1 15.65 GB-6
0.50
0.25 1.96
1 1 1 6.65 GB-7
0.50
0.25 0.83
1 1 1 15.65 GB-8
0.50
0.25 1.96
1 1 1 7.80 GB-9
0.50
0.25 0.98
1 1 1 3.10 GB-10
0.50
0.25 0.39
1 1 1 6.75 GB-11
0.50
0.25 0.84
1 1 1 1.05 GB-12
0.50
0.25 0.13
1 1 1 3.55 GB-13
0.50
0.25 0.44

25.18 Total
J. In ramp beam
1 1 1 5.40 FB-1
0.50
0.25 0.68
1 1 1 10.43 FB-1
0.50
0.25 1.30
1 1 1 12.05 FB-2
0.50
0.25 1.51
1 1 1 5.03 FB-3
0.50
0.25 0.63

4.12 Total
K In Ground floor slab (16cm thick)
Ground Floor
1 1 1 1 26.65 On Axis 1-2, A-F
6.75

1 1 1 1 23.35 On Axis 2-3, A-E


4.95

1 1 1 1 29.10 On Axis 3-4, A-F


4.95

1 1 1 1 28.85 On Axis 4-5, A-F


3.45

1 1 -1 1 2.35 Deductions
2.05 lift shaft area

1 1 -1 1 0.80 Duct Area


1.40

Columns
1 1 -3 1 0.05 Axis 1
0.05

1 1 -3 1 0.35
0.35

1 1 -5 1 0.35 Axis 2
0.35

1 1 -6 1 0.35 Axis 3
0.35

1 1 -4 1 0.35 Axis 4
0.35

1 1 -1 1 0.35
0.60

1 1 -3 1 0.05 Axis 5
0.05

1 1 -2 1 0.35
0.35

1 1 -1 1 3.45 Deduct Stair case-1 area


2.95

Total
M. In 10cm thick Ground Floor Solid Slab
1 1 1 17.35 Axis B-C/5-6
3.60
62.46 m²
62.46 m² Total
N. In ramp (20cm thick)
1 1 1 5.98 Axis E-F/2-3
4.93 29.48 m²

1 1 1 4.90 Axis F-G/2-5


5.08 24.89 m²
1 1 1 4.95
5.08 25.15 m²
1 1 1 3.40
5.08 17.27 m²
Deduct Column Area
1 1 -1 0.70 Axis 2
0.53 -0.37 m²
1 1 -1 0.58 Axis 3
0.41 -0.24 m²
1 1 -2 0.05 Axis 4 & 5
0.05 -0.01 m²
96.17 m² Total
P. Stair case & Landing
Main stair with two landing
Basement floor
SECTION A-A
1 1 0.5 6 1.03 riser
0.28
0.17

1 1 1 1 1.95 sofit
1.03
0.22

1 1 1 1 1.15 Landing 1
1.03
0.22

1 1 1 1 0.40 ddt
0.40
0.22

SECTION B-B
1 1 0.5 5 1.03 riser
0.28
0.17

1 1 1 1 1.93 sofit
1.03
0.22

1 1 1 1 1.15 Landing 1
1.03
0.22

SECTION C-C
1 1 1 6 1.03 riser
0.5 0.29
0.17

1 1 1 1 1.93 sofit
1.15
0.22

Total
Formwork
A. To footing pad
F-1
1 1 4 6.80 P=1.70*4=6.80m
0.25 6.80

6.80 Total to Item 2.03 A


B. In Mat foundation
Mat
1 1 1 105.80 P=2*(31.1+21.8)=105.80m
1.10 116.38 60.28
Lift
1 1 1 7.80 P=2*(2.1+1.8)=7.80m
1.50 11.70

128.08 Total to Item 2.03 B


C. In strip foundation
1 1 1 23.25 axis 1 b/n A - B'
0.25 5.81 P=12.05+11.20=23.25m
1 1 1 11.49 axis 1 b/n E & F
0.25 2.87 P=6.17+5.32=11.49m
1 1 1 10.08 axis 2 b/n F & G
0.25 2.52 P=5.43+4.65=10.08m
1 1 1 0.61 axis 5 b/n F & G
0.25 0.15 P=5.73+4.88=10.61m
1 1 2 8.95 axis A & F b/n 1 & 1'
0.25 4.48 P=4.90+4.05=8.85m
1 1 1 28.10 axis G b/n 2 - 5
0.25 7.03 P=14.90+13.2=28.1m

22.86 Total to Item 2.03 C


E. In foundation column
1 1 4 1.20 C-1
2.42 11.62 P=0.3*4=1.20m

11.62 Total to Item 2.03 E


F. In Basement column
1 1 12 1.20 C-1
2.80 40.32 P=0.3*4=1.20m
1 -1 12 0.50 deduct shear wall side
2.80 -16.80 P=0.25*2=0.50m

1 1 12 2.40 C-2
2.80 80.64 P=0.6*4=2.40m
1 -1 9 0.50 deduct shear wall side
2.80 -12.60 P=0.25*2=0.50m

1 1 10 3.20 C-3
2.80 89.60 P=0.8*4=3.20m
At slab,beam & coll coniction
1 1 12 0.70 C-2
0.34 2.86 P=0.35*2=0.70m

1 1 10 2.20 C-3
0.34 7.48 P=0.55*4=2.20m

191.50 Total to Item 2.03 F


G. In shear wall for lift
For Pad
1 1 2 2.10 W-2
1.50 6.30 P=2.1=2.10m

1 1 1 1.80 W-3
1.50 2.70 P=1.8=1.80m

1 1 1 1.80 W-4
1.50 2.70 P=1.8=1.80m
Basement floor
1 1 2 4.70 W-2
2.70 25.38 P=2.6+2.1=4.70m

1 1 1 4.10 W-3
2.70 11.07 P=2.3+1.8=4.10m

1 1 1 2.30 W-4
2.70 6.21 P=(0.65+0.25+0.4)*2=2.60m

1 1 1 1.80 p=2.3+1.8=4.10m
2.70 4.86
1 1 -1 1.00 deduct open area
2.10 -2.10
1 1 1 0.25 p=0.25m
2.10 0.53

57.65 Total to item 2.03 G


H. In retaining wall
Internal & External
1 2 1 32.53 W-1
0.25 16.27
1 2 -2 3.00 Ddt Opening
0.25 -3.00
1 2 1 5.03 W-2
0.25 2.52
1 2 1 28.20 W-3
0.25 14.10
1 2 -2 3.00 Ddt Opening
0.25 -3.00
1 2 1 18.80 W-4
0.25 9.40
1 2 -2 3.00 Ddt Opening
0.25 -3.00
1 2 1 6.70 W-5
0.25 3.35
1 2 1 12.70 W-6
0.25 6.35
1 2 -1 4.40 Ddt Opening
0.80 -7.04
35.95 Total to item 2.03 H
I. To Ground floor beam
Internal & Bottom
1 2 1 27.00 GB-1
0.70 37.80
1 1 2 27.00
0.25 13.50
1 1 2 9.68 GB-2
0.35 6.78
1 1 1 9.68
0.25 2.42
1 1 2 15.32 GB-3
0.35 10.72
1 1 1 15.32
0.25 3.83
1 1 2 17.25 GB-4
0.35 12.08
1 1 1 17.25
0.25 4.31
1 2 2 22.45 GB-5
0.70 62.86
1 1 1 22.45
0.25 5.61
1 1 1 15.65 GB-6
0.70 10.96
1 1 1 15.65
0.25 3.91
1 1 1 6.65 GB-7
0.70 4.66
1 1 1 6.65
0.25 1.66
1 1 1 15.65 GB-8
0.70 10.96
1 1 1 15.65
0.25 3.91
1 1 1 7.80 GB-9
0.70 5.46
1 1 1 7.80
0.25 1.95
1 1 1 3.10 GB-10
0.70 2.17
1 1 1 3.10
0.25 0.78
1 1 1 6.75 GB-11
0.50 3.38
1 1 1
0.25 0.25
1 1 1 1.05 GB-12
0.70 0.74
1 1 1 1.05
0.25 0.26
1 1 1 3.55 GB-13
0.70 2.49
1 1 1 3.55
0.25 0.89

214.34 Total to item 2.03 I


J. To ramp beam
Internal & Bottom
1 1 2 5.40 FB-1
0.50 5.40
1 1 1 5.40
0.25 1.35
1 1 2 10.43 FB-1
0.50 10.43
1 1 1 10.43
0.25 2.61
1 1 2 12.05 FB-2
0.50 12.05
1 1 1 12.05
0.25 3.01
1 1 2 5.03 FB-3
0.50 5.03
1 1 1 5.03
0.25 1.26

41.14 Total to item 2.03 J


K. To Ground floor slab
Bottom
1 1 1 1 26.65 On Axis 1-2, A-F
6.75

1 1 1 1 23.35 On Axis 2-3, A-E


4.95

1 1 1 1 29.10 On Axis 3-4, A-F


4.95

1 1 1 1 28.85 On Axis 4-5, A-F


3.45

1 1 -1 1 2.35 Deductions
2.05 lift shaft area

1 1 -1 1 0.80 Duct Area


1.40

Columns
1 1 -3 1 0.05 Axis 1
0.05

1 1 -3 1 0.35
0.35

1 1 -5 1 0.35 Axis 2
0.35

1 1 -6 1 0.35 Axis 3
0.35

1 1 -4 1 0.35 Axis 4
0.35

1 1 -1 1 0.35
0.60

1 1 -3 1 0.05 Axis 5
0.05

1 1 -2 1 0.35
0.35

1 1 -1 1 3.45 Deduct Stair case-1 area


2.95

Total to item 2.03 K


M. In ramp slab

1 1 1 5.98 Axis E-F/2-3


4.93 29.48

1 1 1 13.15 Axis F-G/2-5


5.03 66.14
Deduct Column Area
1 1 -1 0.70 Axis 2
0.53 -0.37
1 1 -1 0.58 Axis 3
0.41 -0.24
1 1 -2 0.05 Axis 4 & 5
0.05 -0.01

95.00 Total to item 2.03 M


O. Stair case & Landing
Main stair with two landing
Basement floor
SECTION A-A
1 1 1 6 1.03 riser
0.17

1 1 1 1 1.95 sofit
1.03

1 1 1 1 1.03 Landing 1
1.15

1 1 1 1 1.86 side formwork


0.22

SECTION B-B
1 1 1 4 1.03 riser
0.17

1 1 1 1 1.30 sofit
1.03

1 1 1 1 1.15 Landing 1
1.03

1 1 1 1 1.86 side formwork


0.22

1 1 1 6 1.03 SECTION C-C


0.17 riser

1 1 1 1 1.93 sofit
1.15

1 1 1 1 1.45 side formwork


0.22

Mild steel reinforcement according to structural drawings. Price


Total to item
includes 2.03bending,
cutting, O placing in position and tying wire and
concrete spacers.
0,000.00 kg a) Dia 6 mm deformed bar
9,125.30 kg b) Dia 8 mm deformed bar
8,549.26 kg c) Dia 10 mm deformed bar
1,379.76 kg d) Dia 12 mm deformed bar
4,073.03 kg e) Dia 14 mm deformed bar
23,374.55 kg f) Dia 16 mm deformed bar
23,866.78 kg g) Dia 20 mm deformed bar
- h) Dia 24 mm deformed bar
10mm thick and 100mm high Styrofoam expansion joint between
ground slab and grade beam
At ground floor slab & beam
B/n Axis C-E/5-6
1 1 6 3.60 On Axis B, C, D & E
1.00
21.60 m²
1 1 2 17.45 On Axis 5 & 6
1.00
34.90 m²
56.50 m² Total to item 2.05
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Project:- Saving Houses B+G+8 Typology Rev Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Developm Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Timizing Dimension Qty Descreption
SUPER-STRUCTURE
CONCRETE WORKS
Reinforced concrete in class C-25 (with a 28-day 15cm cube crushing strength of 25MPa "Type of
cement to be ordinary portland cement (OPC)"

A. In Elevation Columns
Ground floor
1 13 1 2.80 ON AXIS 2G,3G,4G,5G,5B,5E,5F,5C',5A,6B,6C,6D',6F
0.30 C1
0.30
3.28 m³
1 21 1 2.80 ON AXIS 1C,2A,3A,2B,2C,2E,2F,3B,3C,3E,3F,4A,4B,4D',4E,4F,5D',1D,1E,2D,3D
0.60 C2
0.60
21.17 m³
1 1 1 2.80 ON AXIS 5 B'
0.60 C3
0.60
1.01 m³

FIRST FLOOR

ON AXIS 1 C,1 D, 1E, 2 A, 3A,2 B,2C,2D,2E,2F,3B,3C,3D,3E,3F, 4A,4B,4D',4E,4F,5D'


1 21 1 2.80
0.60 C2
0.60
21.17 m³
1 1 1 2.80 ON AXIS 5C'
0.30 C1
0.30
0.25 m³
1 1 1 2.80 ON AXIS 5B'
0.40 C4
0.40
0.45 m³
SECOND-THIRD FLOOR

ON AXIS 1 C,1 D, 1E, 2 A,2 B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F, 4A,4B,4D',4E,4F,5D'


2 21 1 2.80
0.60 C2
0.60
42.34 m³
2 1 1 2.80 ON AXIS 5C'
0.30 C1
0.30
0.50 m³
2 1 1 2.80 ON AXIS 5B'
0.40 C4
0.40
0.90 m³
FOURTH- EIGHT FLOOR

ON AXIS 1 C,1 D, 1E, 2A, 2B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F,4A,4B,4D',4E,4F,5B',5C',5D'


5 22 1 2.80
0.40 C6
0.40
49.28 m³
5 1 1 2.80 ON AXIS 5C'
0.30 C1
0.30
1.26 m³
water tanker
1 1 1 0.30 ON AXIS 5C'
0.30 C1
4.00
0.36 m³
1 2 1 0.40 ON AXIS 5B',4D'
0.40 C4
4.00
1.28 m³
1 1 1 0.40 ON AXIS 5 D'
0.40 C2
4.00
0.64 m³ 2.28 m³
143.89 m³ Total To Item 1.01.A
B. In floor & top tie beam
Intermediate beam
First floor
1 1 1 12.60 ON XIS 1-(C-E)
0.50 FB-1
0.25
1.58 m³
1 1 1 35.93 ON AXIS-2 (A-G)
0.50 FB-2
0.25
4.49
1 1 1 35.92 ON AXIS -3 (A-G)
0.50 FB-3
0.25
4.49 m³
1 1 1 10.88 ON AXIS 4-(A-B')
0.50 FB-4
0.25
1.36 m³
1 1 1 16.81 ON AXIS 4 -(D'-G)
0.50 FB-5
0.25
2.1
1 1 1 5.64 ON AXIS 4 -(B'-D')
0.50 FB-5
0.25
0.71
1 1 1 35.93 ON AXIS 5 - (A-G)
0.50 FB-6
0.25
4.49 m³
1 1 1 18.42 ON AXIS 6 -(B-E )
0.50 FB-7
0.25
2.30 m³
1 1 1 13.30 ON AXIS A -(5-2 )
0.50 FB-8
0.25
1.66 m³
1 1 1 16.90 ON AXIS B -(6-2)
0.50 FB-9
0.25
2.11 m³
1 1 1 4.93 ON AXIS C -(6-5)
0.50 FB-10
0.25
0.62 m³
1 1 1 16.60 ON AXIS C (4-1)
0.50 FB-11
0.25
2.08 m³
1 2 1 6.75 b/n axis C-C'& (2-1)
0.50 FB-12
0.25
1.69 m³
1 1 1 16.60 ON AXIS D -(4-1)
0.50 FB-13
0.25
2.08 m³
1 1 1 23.65 ON AXIS E-(6-1)
0.50 FB-14
0.25
2.96 m³
1 1 1 7.05 ON AXIS D'-E & (6 -4)
0.50 FB-15
0.25
0.88 m³
1 1 1 3.45 ON AXIS C' (5-4)
0.50 FB-16
0.25
0.43 m³
1 1 1 3.60 ON XIS C ( 6-5)
0.50 FB-17
0.25
0.45 m³
1 1 1 3.45 ON AXIS B' (5-4)
0.50 FB-18
0.25
0.43 m³

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Second- 8th floor
7 1 1 12.60 ON AXIS 1-(C-E)
0.50 FB-1
0.25
11.03 m³
7 1 1 30.60 ON AXIS-2 (A-F)
0.50 FB-2
0.25
26.78
7 1 1 30.60 ON AXIS 3 (A-F)
0.50 FB-3
0.25
26.78 m³
7 1 1 10.88 ON AXIS 4-(A-B')
0.50 FB-4
0.25
9.52 m³
7 1 1 11.48 ON AXIS 4 -(D'-F)
0.50 FB-5
0.25
10.05 m³
7 1 1 5.64 ON AXIS 4 -(B'-D')
0.50 FB-5
0.25
4.94 m³
7 1 1 8.84 ON AXIS -5 (B'-D')
0.50 FB-6
0.25
7.74 m³
7 2 1 9.85 ON AXIS A and F (4-2 )
0.50 FB-7
0.25
17.24 m³
7 1 1 9.85 ON AXIS B -(4-2 )
0.50 FB-8
0.25
8.62 m³ 16.6
7 2 1 16.60 ON AXIS C & E (4-1)
0.50 FB-9
0.25
29.05 m³
7 1 1 16.60 ON AXIS D-(4-1)
0.50 FB-10
0.25
14.53 m³
7 1 1 3.45 ON AXIS D' (5-4)
0.50 FB-11
0.25
3.02 m³
7 1 1 3.45 ON AXIS B' (5-4)
0.50 FB-12
0.25
3.02 m³
7 1 1 3.45 ON AXIS C' (5-4)
0.50 FB-13
0.25
3.02 m³
TOP TIE BEAM
1 1 1 12.60 ON AXIS 1 (C-E)
0.40 RB-2
0.25
1.26 m³
1 1 1 30.60 ON AXIS -2 (A-F)
0.40 RB-3
0.25
3.06 m³
1 1 1 30.60 ON AXIS 3 -(A-F)
0.40 RB-5
0.25
3.06 m³
1 1 1 10.88 ON AXIS 4 (A-B' )
0.40 RB-4
0.25
1.09 m³
1 1 1 10.88 ON AXIS 4 (B'-D' )
0.40 RB-5
0.25
1.09 m³
1 1 1 8.84 ON AXIS 5 (B'-D')
0.40 RB-10
0.25
0.88 m³
1 1 1 9.85 ON AXIS A (4-2)
0.40 RB-6
0.25
0.99 m³
1 2 1 9.85 ON AXIS B & F (4-2)
0.40 RB-7
0.25
1.97 m³
1 2 1 16.60 ON AXIS C & D-(4-1)
0.40 RB-8
0.25
3.32 m³
1 1 1 3.45 ON AXIS C' (5-4)
0.40 RB-1
0.25
0.35 m³
1 1 1 3.45
0.40 ON AXIS B' & D' (5-4)
0.25 RB-9

0.35 m³
1 1 1 16.60 ON AXIS E (4-1 )
0.40 RB-10
0.25
1.66 m³
WATER TANKER BEAM
1 1 1 8.84 ON AXIS 5 (B'-D')
0.40 RB-11
0.25
0.88 m³
1 1 1 8.84 ON AXIS 4 (B'-D')
0.40 RB-12
0.25
0.88 m³
1 1 1 3.45 ON AXIS B' (4-5)
0.40 RB-13
0.25
0.35 m³
1 1 1 3.45 ON AXIS (4-5)
0.40 RB-14
0.25
0.35 m³
1 1 1 3.45 ON AXIS D' (4-5)
0.40 RB-15
0.25
0.35 m³
2.81 m³
234.14 m³ Total To Item 1.1.B

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


C. Stair case & Landing
Grnd-8th Floor
main stair case
SECTION A-A
9 0.5 6 1.03 riser
0.28
0.17
1.32 m³
9 1 1 1.95 sofit
1.03
0.22
3.98 m³
9 1 1 1.15 Landing 1
1.03
0.22
2.35 m³
9 1 1 0.40 ddt
0.40
0.22
-0.32 m³
SECTION B-B
9 0.5 5 1.03 riser
0.28
0.17
1.07 m³
9 1 1 1.93 sofit
1.03
0.22
3.94 m³
9 1 1 1.15 Landing 1
1.03
0.22
2.35 m³
SECTION C-C
9 1 6 1.03 riser
0.5 0.29
0.17
1.33 m³
9 1 1 1.93 sofit
1.15
0.22
4.39 m³ 20.41
SHOP STAIR
Ground Floor
SECTION E-E
1 0.5 11 1.05 riser
0.30
0.15
0.26 m³
1 1 1 3.75 sofit
1.05
0.22
0.87 m³
1 1 1 1.98 Landing 1
1.05
0.22
0.46 m³
SECTION F-F
1 0.5 11 1.05 riser
0.30
0.15
0.26 m³
1 1 1 3.30 sofit
1.05
0.22
0.76 m³
1 1 1 1.98 Landing 1
1.05
0.22
0.46 m³

23.48 m³ Total To Item 1.1.C

D) In Shear wall for lift shaft


GROUND FLOOR
1 2 1 2.60 W2
3.30
0.25
4.29 m³
1 1 1 1.80 W3
3.30
0.25
1.49 m³
1 1 1 1.80 W4
3.30
0.25
1.49 m³
1 1 -1 2.10 DDT
1.00 OPENING
0.25
-0.53 m³
1st to 8th
8 2 1 2.60 W2
3.30
0.25
34.32 m³
8 1 1 1.80 W3
3.30
0.25

11.88 m³
8 1 1 1.80 W4
3.30
0.25
11.88 m³
8 1 -1 2.10 DDT
1.00 OPENING
0.25
-4.20 m³
ABOVE 8TH FLOOR
1 1 1 2.60 W2
2.50
0.25
1.63 m³
1 1 1 2.60 W2
0.70
0.25
0.46 m³
1 1 1 1.80 W3
0.70
0.25
0.32 m³
1 1 1 1.80 W4
0.70
0.25
0.32 m³
1 1 1 1.00 DDT LIFT DOOR
1.30
0.25
-0.33 m³
2.40 m³
63.02 m³ Total To Item 1.1.E

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption

E. In RC Gutter
1 1 1 23.25 On Axis 1'-2' / A-C
0.15
0.90
3.14 m³
1 1 1 15.00 On Axis 1'-2' / E-F
0.15
0.90
2.03 m³
1 1 1 12.38 On Axis 4 / E-F
0.15
0.90 0.91
1.67 m³

6.84 m³ Total To Item 1.1E

F. 15cm thick solid slab


FIRST FLOOR
1 1 1 5.93 B/ N Axis 4-5 & A-B
3.45
20.46 m²
1 1 1 4.46 B/ N Axis B-B' & 4-5
3.45
15.37 m²
1 1 1 2.84 B/ N Axis C-C' & 4-5
3.40
9.66 m²
1 1 1 4.63 B/ N Axis D'-E & 4-5
3.45
15.97 m²
1 1 1 5.75 B/ N Axis E-F & 4-5
3.45
19.84 m²
1 1 1 5.08 B/ N Axis F-G & 4-5
3.45
17.53 m²
1 1 1 5.08 B/ N Axis F-G & 2-3
4.93
25.04 m²
1 1 1 5.08 B/ N Axis F-G & 3-4
4.93
25.04 m²
1 1 1 5.58 B/ N Axis B-C & 5-6
3.60
20.09 m²
1 1 1 3.60 B/ N Axis C-D' & 5-6
7.22
25.99 m²
1 1 1 4.63 B/ N Axis D'-E & 5-6
3.60
16.67 m²
1 -13 1 0.05 Deduct Column Contact Area
0.05 Axis 2G, 3G 4G, 5A, 5B, 5C', 5E, 5F,5G,6B,6C,6D,6E
-0.03 m²
SECOND- EIGHTH FLOOR
7 1 1 6.55 ON Axis 1 B/N C-D
1.05
48.14 m²
7 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.10
68.22 m²
7 1 1 3.45 ON Axis 4-5 B/N B'-C'
2.84
68.59 m²
7 1 1 1.45 ON Axis 4-5 B/N B'-C'
1.40
14.21 m²
Deduct Column Contact Area
7 -1 1 0.35
0.17
-0.42 m²
410.37 m² Total To Item 1.1.E
F'. In 15 cm thick Roof Slab
1 1 1 6.50 ON Axis 1 B/N C-D
1.05
6.83 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20
10.63 m²
1 1 1 3.45 ON Axis 4-5 B/N B'-D

2.90
10.01 m²
1 1 1 2.84 ON Axis 4-5 B/N B'-D
3.45
9.80 m²
1 1 1 2.35
1.40
3.29 m²
1 -2 1 0.15 Deduct column contact area
0.15
-0.05 m² 40.51 m²
WATER TANKER SLAB
1 1 1 5.19 b/n Axis 4-5 & B'-D'
3.45
17.91 m²

1 1 1 2.90
3.45
10.01 m²
1 -2 1 0.15 Deduct column contact area
0.15
-0.05 m² 27.87 m²

68.38 m² Total To Item 1.1.F

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


G. 6cm thick concrete on toilet area
1St Floor
1 1 1 5.03 B/ N Axis A'-B & 2-3
4.65
23.39 m²
1 -1 1 1.95 Deduct HCB Area
0.20
-0.39 m²
1 -1 1 7.45
0.10
-0.75 m²
1 -1 1 1.87
0.10
-0.19 m²
1 -1 1 0.63
1.20
-0.76 m²
2nd-8th floor
7 2 1 1.47 B/ N Axis C-D & 1-1'
2.20
45.28 m²
7 -1 1 0.35
0.60
-1.47 m²
7 1 1 1.78 Axis 2-3 b/n B-B'
2.07
25.79 m²
7 1 2 2.90 B/ N Axis E-F &A-B , 2'-3'
2.58
104.75 m²
7 -2 1 0.63
1.20
-10.58 m²

185.07 m² Total Area To Item 1.01 G


H. Extra 6cm thick concrete on Bathroom
1St Floor
1 1 1 5.03 B/ N Axis A'-B & 2-3
4.65
23.39 m²
1 -1 1 1.95 Deduct HCB Area
0.20
-0.39 m²
1 -1 1 7.45
0.10
-0.75 m²
1 -1 1 1.87
0.10
-0.19 m²
1 -1 1 0.63
1.20
-0.76 m²
2nd-8th floor
7 2 1 1.47 B/ N Axis C-D & 1-1'
2.20
45.28 m²
7 -1 1 0.35
0.60
-1.47 m²
7 1 1 1.78 Axis 2-3 b/n B-B'
2.07
25.79 m²
7 1 2 2.90 B/ N Axis E-F &A-B , 2'-3'
2.58
104.75 m²
7 -2 1 0.63
1.20
-10.58 m²

185.07 m² Total Area To Item 1.01 H


11.10 m³ Total Volume To Item 1.01 H
I. Concrete fillers around columns & beam
connection at floor levels
1st - 4th floor
At slab, beam & column conection
4 1 1 0.05 C-1
0.05
0.34
0.00 m³
4 1 22 0.35 C-2
0.35
0.34
3.67 m³
5th - 8th floor
4 1 1 0.05 At slab, beam & column conection
0.05 C-1
0.34
0.00 m³
4 1 22 0.15
0.15 C-2
0.34
0.67 m³
At Roof Level
1 1 1 0.05 At slab, beam & column conection
0.05 C-1
0.40
0.00 m³
1 1 22 0.15
0.15 C-2
0.40
0.20 m³

4.54 m³ Total Item 1.01i

Ribbed slab for suspended floor slab made of 60 mm


thick concrete slab in C-25,60x240 mm one way concrete
girder with c/c spacing of 400mm including 200x400x240mm
hollow concrete ribbed block and all according to the detail
structural drawing.
FIRST FLOOR
1 2 1 5.93 B/ N Axis A - B & 2-3 ,3-4
4.93
58.47 m²
1 1 1 3.13 B/ N Axis B-B' & 2-3
4.93
15.43 m²
1 1 1 5.58 B/ N Axis B-B' & 3-4
4.93
27.51 m²
1 1 1 5.67 B/ N Axis C - D & 1-2
6.75
38.27 m²
1 2 1 5.92 B/ N Axis C - D & 2-3 & 3-4
4.93
58.37 m²
1 1 1 5.67 B/N Axis D-E & 1-2
6.75
38.27 m²
1 2 1 5.92 B/N Axis D-E & 2-3, 3-4
4.93
58.37 m²
1 2 1 5.75 B/N Axis E-F & 2-3,3-4
4.93
56.70 m²
SECOND-THIRED FLOOR
2 2 1 5.93 B/ N Axis A - B & 2-3 ,3-4
4.93
116.94 m²
2 2 1 5.58 B/ N Axis B-C & 2-3 , 3-4
4.93
110.04 m²
2 1 1 6.75 B/ N Axis C - D & 1-2
5.67
76.55 m²
2 2 1 5.92 B/ N Axis C - D & 2-3 & 3-4
4.93
116.74 m²
2 1 1 5.68 B/N Axis D-E & 1-2
6.75
76.68 m²
2 2 1 5.92 B/N Axis D-E & 2-3, 3-4
4.93
116.74 m²
2 2 1 5.75 B/N Axis E-F & 2-3,3-4
4.93
113.39 m²
FOURTH -EIGHTH FLOOR

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


5 2 1 5.93 B/ N Axis A - B & 2-3 ,3-4
4.93
292.35 m²
5 2 1 5.58 B/ N Axis B-B' & 2-3 , 3-4
4.93
275.09 m²
5 1 1 6.75 B/ N Axis C - D & 1-2
5.67
191.36 m²
5 2 1 5.92 B/ N Axis C - D & 2-3 & 3-4
4.93
291.86 m²

5 1 1 5.68 B/N Axis D-E & 1-2

6.75
191.70 m²
5 2 1 5.92 B/N Axis D-E & 2-3, 3-4
4.93
291.86 m²
5 2 1 5.75 B/N Axis E-F & 2-3,3-4
4.93

283.48 m² 2896.16 m²

Deduct column edge contact area


FIRST-THIRD FLOOR
3 -3 1 0.35 Axis 1
0.35
-1.10 m²
3 -6 1 0.35 Axis 2
0.35
-2.21 m²
3 -1 1 0.05
0.05
-0.01 m²
3 -6 1 0.35 Axis 3
0.35
-2.21 m²
3 -1 1 0.05
0.05
-0.01 m²
3 -5 1 0.35 Axis 4
0.35
-1.84 m²
3 -1 1 0.05
0.05
-0.01 m²
3 -1 1 0.35 Axis 5
0.18
-0.19 m² -7.60 m²
3 -5 1 0.05
0.05
-0.04 m²
5 -20 1 0.15 FOURTH -EIGHTH FLOOR
0.15
-2.25 m²
2886.31 m² Total Item 1.3

Provide, Cut and Fix in position Sawn zigba wood form


work for:

A) Elevation columns
Basement floor
1 11 1 2.80 ON AXIS 1 A,1 B,1F,2G,3G,4G,5A,5B,5E,5F,5G
0.60
18.48 m²
1 11 1 2.80
0.10
3.08 m²
1 17 1 2.80 ON AXIS 1 C,1D,1E,2A,3A,2F,3B,3C,3E,3F,4A,4B,4D',4E,4F,5B',5D'
2.40
114.24 m²
1 5 1 2.80 1 C,1D,1E,5B',5D'
0.70
9.80 m²
1 12 1 2.80 ON AXIS 2A,3A,2F,3B,3C,3E,3F,4A,4B,4D',4E,4F
1.20
40.32 m²
1 7 1 2.80 ON AXIS 2B-E,3B-D
3.20
62.72 m²
Ground floor

1 12 1 2.80 ON AXIS 2G,3G,4G,5A,5B,5E,5F,5G,6B,6C,6D',6E


1.20
40.32 m²
1 19 1 2.80 ON AXIS 1 C,2A,3A,2 B,2C,2E,2F,3B,3C,3E,3F,4A,4B,4D',4E,4F,5B',5C',5D'
2.40
127.68 m²
1 4 1 2.80 ON AXIS 1D,1E,2D,3D
2.40
26.88 m²
FIRST FLOOR

ON AXIS 1 C,1 D, 1E, 2 A, 3A,2 B,2C,2D,2E,2F,3B,3C,3D,3E,3F, 4A,4B,4D',4E,4F,5B',5D'


1 22 1 2.80
2.40
147.84 m²
1 1 1 2.80 ON AXIS 5C'
1.20
3.36 m²

SECOND-THIRD FLOOR

ON AXIS 1 C,1 D, 1E, 2 A,2 B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F, 4A,4B,4D',4E,4F,5C',5D'


2 22 1 2.80
2.40
295.68 m²
2 1 1 2.80 ON AXIS 5C'
1.20
6.72 m²
FOURTH- EIGHT FLOOR
ON AXIS 1 C,1 D, 1E, 2A, 2B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F,4A,4B,4D',4E,4F,5B',5C',5D'
5 22 1 2.80
1.60
492.80 m²
2 1 1 2.80 ON AXIS 5C'
1.20
6.72 m²
water tanker
1 3 1 2.10 ON AXIS 5B',5D',4D'
1.60
10.08 m²

1406.72 m² Total To Item 1.04.A

B) In Floor & Top Tie beam


1) intermediate beam
First floor
External
1 1 1 12.60 ON AXIS 1-(C-E)
0.50 FB-1
6.30 m²
Internal
1 1 1 10.80 ON AXIS 1-(C-E)
0.22 FB-1
2.38 m²
Bottom
1 1 1 10.80 ON AXIS 1-(C-E)
0.25 FB-1
2.70 m²
External
1 1 1 23.33 ON AXIS-2 (A-G)
0.50 FB-2
11.67 m²
Internal
1 1 1 10.80 ON AXIS-2 (A-C)
0.22 FB-2
2.38 m²
1 2 1 10.80 ON AXIS-2 (C-E)
0.22 FB-2
4.75 m²
1 1 1 10.80 ON AXIS-2 (E-G)
0.22 FB-2
2.38 m²
Bottom
1 1 1 32.03 ON AXIS-2 (A-G)
0.25 FB-2
8.01 m²
Internal
1 2 1 32.03 ON AXIS -3 (A-G)
0.22 FB-3
14.09 m²
Bottom
1 1 1 32.03 ON AXIS -3 (A-G)
0.25 FB-3
8.01 m²
Internal
1 2 1 9.68 ON AXIS 4-(A-B')
0.22 FB-4
4.26 m²
bottom
1 1 1 9.68 ON AXIS 4-(A-B')
0.25 FB-4
2.42 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Internal
1 2 1 20.05 ON AXIS 4 -(C-G)
0.22 FB-5
8.82 m²
bottom
1 1 1 20.05 ON AXIS 4 -(D'-G)
0.25 FB-5
5.01 m²
External
1 1 1 17.47 ON AXIS 5 - (A-B AND E-G)
0.50 FB-6
8.74 m²
Internal
1 1 1 32.93 ON AXIS 5 - (A-G)
0.22 FB-6
7.24 m²
bottom
1 1 1 32.93 ON AXIS 5 - (A-G)
0.25 FB-6
8.23 m²
Internal
1 1 1 17.20 ON AXIS 6 -(B-E )
0.22 FB-7
3.78 m²
External
1 1 1 18.42 ON AXIS 6 -(B-E )
0.50 FB-7
9.21 m²
Bottom
1 1 1 17.20 ON AXIS 6 -(B-E )
0.25 FB-7
4.30 m²
Internal
1 1 2 12.20 ON AXIS F (5-2 )
0.22 FB-8
5.37 m²
Internal
1 1 2 12.60 ON AXIS G & A -(5-2 )
0.22 FB-8
5.54 m²
External
1 2 1 14.30 ON AXIS A & G -(5-2 )
0.50 FB-8
14.30 m²
Bottom
1 3 1 12.60 ON AXIS A & G-(5-2 )
0.25 FB-8
9.45 m²
1 3 1 12.20 ON AXIS F -(5-2 )
0.25 FB-8
9.15 m²
Internal
1 1 2 8.80 ON AXIS B -(2-5)
0.22 FB-9
3.87 m²
Internal
1 1 1 3.55 ON AXIS B -(6-5)
0.22 FB-9
0.78 m²
External
1 1 1 3.85 ON AXIS B -(6-5)
0.50 FB-9
1.93 m²
Bottom
1 1 1 15.75 ON AXIS B -(6-2)
0.25 FB-9
3.94 m²
Internal
1 1 1 4.93 ON AXIS -(3-2)
0.22 FB-10
1.08 m²
External
1 1 1 4.93 ON AXIS B-B'-(3-2)
0.50 FB-10
2.47 m²
Bottom
1 1 1 4.93 ON AXIS B-B'-(3-2)
0.25 FB-10
1.23 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Internal
1 1 1 10.79 ON AXIS C (3-1)
0.22 FB-11
2.37 m²
1 1 1 4.76 ON AXIS C (4-3)
0.22 FB-11
1.05 m²
External
1 1 1 11.92 ON AXIS C (2-1)
0.50 FB-11
5.96 m²

Bottom
1 1 1 15.55 ON AXIS C (4-1)
0.25 FB-11
3.89 m²
Internal
1 2 2 6.75 b/n axis C-C'& D'-E (2-1)
0.22 FB-12
5.94 m²
Bottom
1 2 1 6.75 b/n axis C-C'& D'-E (2-1)
0.25 FB-12
3.38 m²
Internal
1 1 1 15.15 ON AXIS D -(4-1)
0.22 FB-13
3.33 m²
Bottom
1 1 1 15.15 ON AXIS D -(4-1)
0.25 FB-13
3.79 m²
Internal
1 1 1 21.70 ON AXIS E-(6-1)
0.22 FB-14
4.77 m²
External
1 1 1 10.85 ON AXIS E-(2-1 )
0.50 FB-14
5.43 m²
Bottom
1 1 1 22.15 ON AXIS E-(6-1)
0.25 FB-14
5.54 m²
Internal
1 1 2 6.95 ON AXIS D' (6 -4)
0.22 FB-15
3.06 m²
Bottom
1 1 1 6.95 ON AXIS D' (6 -4)
0.25 FB-15
1.74 m²
Internal
1 1 2 3.10 ON AXIS C' (5-4)
0.22 FB-16
1.36 m²
Bottom
1 1 1 3.40 ON AXIS C' (5-4)
0.25 FB-16
0.85 m²
Internal
1 1 2 3.55 ON XIS C ( 6-5)
0.22 FB-17
1.56 m²
Bottom
1 1 1 3.55 ON XIS C ( 6-5)
0.25 FB-17
0.89 m²
Internal
1 1 2 1.25 ON AXIS B' (5-4)
0.22 FB-18
0.55 m²
Bottom
1 1 1 1.25 ON AXIS B' (5-4)
0.25 FB-18
0.31 m²
Second- Third floor
Internal
2 1 1 10.80 ON AXIS 1-(C-E)
0.22 FB-1
4.75 m²
External
2 1 1 12.60 ON AXIS 1-(C-E)
0.50 FB-1
12.60 m²
Bottom
2 1 1 10.80 ON AXIS 1-(C-E)
0.25 FB-1
5.40 m²
Internal
2 1 1 10.80 ON AXIS-2 (C-E)
0.22 FB-2
4.75 m²
2 1 1 16.20 ON AXIS-2 (A-F)
0.22 FB-2
7.13 m²
External
2 1 1 18.00 ON AXIS-2 (A-F)
0.50 FB-2
18.00 m²
Bottom
2 1 1 27.00 ON AXIS-2 (A-F)
0.25 FB-2
13.50 m²
Internal
2 1 1 27.00 ON AXIS 3 (A-F)
0.22 FB-3
11.88 m²
Bottom
2 1 1 27.00 ON AXIS 3 (A-F)
0.25 FB-3
13.50 m²
Internal
2 1 1 9.68 ON AXIS 4-(A-B')
0.22 FB-4
4.26 m²
External
2 1 1 10.88 ON AXIS 4-(A-B')
0.50 FB-4
10.88 m²
2 1 1 -4.43 ON AXIS 4-(A-B')
0.50 deduct balcony side
-4.43 m²
Bottom
2 1 1 9.68 ON AXIS 4-(A-B')
0.25 FB-4
4.84 m²
Internal
2 1 1 9.68 ON AXIS 4 -(C-F)
0.22 FB-5
4.26 m²
2 1 1 5.39 ON AXIS 4 -(C-F)
0.22 FB-5
2.37 m²
External
2 1 1 10.88 ON AXIS 4 -(D'-F)
0.50 FB-5
10.88 m²
2 1 1 -4.43 ON AXIS 4 -(D'-F)
0.50 deduct balcony
-4.43 m²
Bottom
2 1 1 15.32 ON AXIS 4 -(D'-F)
0.25 FB-5
7.66 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


External
2 1 1 8.84 ON AXIS -5 (B'-D')
0.22 FB-6
3.89 m²
Internal
2 1 1 7.34 ON AXIS -5 (B'-D')
0.22 FB-6
3.23 m²
Bottom
2 1 1 7.34 ON AXIS -5 (B'-D')
0.25 FB-6
3.67 m²
External
2 2 1 10.60 ON AXIS A & F (4-2 )
0.50 FB-7
21.20 m²
Internal
2 2 1 8.80 ON AXIS A & F (4-2 )
0.22 FB-7
7.74 m²
Bottom
2 2 1 8.80 ON AXIS A & F (4-2 )
0.25 FB-7
8.80 m²

2 1 2 8.80 Internal
0.22 ON AXIS B -(4-2 )
7.74 m² FB-8
Bottom
2 1 1 8.80 ON AXIS B -(4-2 )
0.25 FB-8
4.40 m²
Internal
2 2 1 15.20 ON AXIS C & E (4-1)
0.22 FB-9
13.38 m²
Internal
2 2 1 15.20 ON AXIS C & E (4-1)
0.22 FB-9
13.38 m²
External
2 2 1 7.00 ON AXIS C (4-1)
0.50 FB-9
14.00 m²
Bottom
2 1 1 15.20 ON AXIS C (4-1)
0.25 FB-9
7.60 m²
Internal
2 1 2 15.20 ON AXIS D -(4-1)
0.22 FB-10
13.38 m²
Bottom
2 1 1 15.20 ON AXIS D -(4-1)
0.25 FB-10
7.60 m²
Internal
2 1 1 3.10 ON AXIS D' (5-4)
0.22 FB-11
1.36 m²
External
2 1 1 3.70 ON AXIS D' (5-4)
0.50 FB-11
3.70 m²
Bottom
2 1 1 3.10 ON AXIS D' (5-4)
0.25 FB-11
1.55 m²
Internal
2 1 1 1.25 ON AXIS B' (5-4)
0.22 FB-12
0.55 m²
2 1 1 1.25 Bottom
0.25 ON AXIS B' (5-4)
0.63 m² FB-12
External
2 1 1 1.55 ON AXIS B' (5-4)
0.50 FB-12
1.55 m²
Internal
2 1 2 3.10 ON AXIS C' (5-4)
0.22 FB-13
2.73 m²
Bottom
2 1 1 3.10 ON AXIS C' (5-4)
0.25 FB-13
1.55 m²
Internal
1 2 2 6.75 b/n axis C-C' & D'-E (2-1)
0.22 FB-12'
5.94 m²
Bottom
1 2 1 6.75 b/n axis C-C' & D'-E (2-1)
0.25 FB-12'
3.38 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Fourth- Eighth floor
Internal
2 1 1 11.00 ON AXIS 1-(C-E)
0.22 FB-1
4.84 m²
External
2 1 1 12.60 ON AXIS 1-(C-E)
0.50 FB-1
12.60 m²
Bottom
2 1 1 11.00 ON AXIS 1-(C-E)
0.25 FB-1
5.50 m²
Internal
2 1 1 11.00 ON AXIS-2 (C-E)
0.22 FB-2
4.84 m²
2 1 1 16.80 ON AXIS-2 (A-F)
0.22 FB-2
7.39 m²
External
2 1 1 18.00 ON AXIS-2 (A-F)
0.50 FB-2
18.00 m²
Bottom
2 1 1 27.80 ON AXIS-2 (A-F)
0.25 FB-2
13.90 m²
Internal
2 1 1 27.80 ON AXIS 3 (A-F)
0.22 FB-3
12.23 m²
Bottom
2 1 1 27.80 ON AXIS 3 (A-F)
0.25 FB-3
13.90 m²
Internal
2 1 1 9.88 ON AXIS 4-(A-B')
0.22 FB-4
4.35 m²
External
2 1 1 10.88 ON AXIS 4-(A-B')
0.50 FB-4
10.88 m²
2 1 1 -4.43 ON AXIS 4-(A-B')
0.50 deduct balcony side
-4.43 m²
Bottom
2 1 1 9.88 ON AXIS 4-(A-B')
0.25 FB-4
4.94 m²
Internal
2 1 1 10.08 ON AXIS 4 -(C-F)
0.22 FB-5
4.44 m²
2 1 1 5.39 ON AXIS 4 -(C-F)
0.22 FB-5
2.37 m²
External
2 1 1 10.88 ON AXIS 4 -(D'-F)
0.50 FB-5
10.88 m²
2 1 1 -4.43 ON AXIS 4 -(D'-F)
0.50 deduct balcony
-4.43 m²
Bottom
2 1 1 15.72 ON AXIS 4 -(D'-F)
0.25 FB-5
7.86 m²
External
2 1 1 8.84 ON AXIS -5 (B'-D')
0.22 FB-6
3.89 m²
Internal
2 1 1 7.74 ON AXIS -5 (B'-D')
0.22 FB-6
3.41 m²
Bottom
2 1 1 7.74 ON AXIS -5 (B'-D')
0.25 FB-6
3.87 m²
External
2 2 1 10.60 ON AXIS A & F (4-2 )
0.50 FB-7
21.20 m²

2 2 1 9.40 Internal
0.22 ON AXIS A & F (4-2 )
8.27 m² FB-7
Bottom
2 2 1 9.40 ON AXIS A & F (4-2 )
0.25 FB-7
9.40 m²
Internal
2 1 2 9.00 ON AXIS B -(4-2 )
0.22 FB-8
7.92 m²
Bottom
2 1 1 9.00 ON AXIS B -(4-2 )
0.25 FB-8
4.50 m²
Internal
2 2 1 15.60 ON AXIS C & E (4-1)
0.22 FB-9
13.73 m²
Internal
2 2 1 15.40 ON AXIS C & E (4-1)
0.22 FB-9
13.55 m²
External
2 2 1 7.00 ON AXIS C (4-1)
0.50 FB-9
14.00 m²
Bottom
2 1 1 15.60 ON AXIS C (4-1)
0.25 FB-9
7.80 m²
Internal
2 1 2 15.60 ON AXIS D -(4-1)
0.22 FB-10
13.73 m²
Bottom
2 1 1 15.60 ON AXIS D -(4-1)
0.25 FB-10
7.80 m²
Internal
2 1 1 3.10 ON AXIS D' (5-4)
0.22 FB-11
1.36 m²
External
2 1 1 3.70 ON AXIS D' (5-4)
0.50 FB-11
3.70 m²
Bottom
2 1 1 3.10 ON AXIS D' (5-4)
0.25 FB-11
1.55 m²
Internal
2 1 1 1.25 ON AXIS B' (5-4)
0.22 FB-12
0.55 m²
2 1 1 1.25 Bottom
0.25 ON AXIS B' (5-4)
0.63 m² FB-12
External
2 1 1 1.55 ON AXIS B' (5-4)
0.50 FB-12
1.55 m²
Internal
2 1 2 3.10 ON AXIS C' (5-4)
0.22 FB-13
2.73 m²
Bottom
2 1 1 3.10 ON AXIS C' (5-4)
0.25 FB-13
1.55 m²
Internal
1 2 2 6.75 b/n axis C-C' & D'-E (2-1)
0.22 FB-12'
5.94 m²
Bottom
1 2 1 6.75 b/n axis C-C' & D'-E (2-1)
0.25 FB-12'
3.38 m²

TOP TIE BEAM


Internal
1 1 2 3.45 ON AXIS C' (5-4)
0.40 RB-1
2.76 m²
bottom
1 1 1 3.45 ON AXIS C' (5-4)
0.25 RB-1
0.86 m²
Internal
1 1 1 11.40 ON AXIS 1 (C-E)
0.40 RB-2
4.56 m²
External
1 1 1 12.60 ON AXIS 1 (C-E)
0.40 RB-2
5.04 m²
Bottom
1 1 1 11.40 ON AXIS 1 (C-E)
0.25 RB-2
2.85 m²
External
1 1 1 18.00 ON AXIS -2 (A-C) AND E-F
0.40 RB-3
7.20 m²
Internal
1 1 1 11.40 ON AXIS -2 (C-E)
0.40 RB-3
4.56 m²
Internal
1 1 1 25.65 ON AXIS -2 (A-F)
0.40 RB-3
10.26 m²
Bottom
1 1 1 27.40 ON AXIS -2 (A-F)
0.25 RB-3
6.85 m²
External
1 1 1 10.88 ON AXIS 4-(A-B)
0.40 RB-4
4.35 m²
1 -1 1 4.43 DEDUCT BALCONY SIDE
0.40
-1.77 m²
Internal

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


1 1 1 10.08 ON AXIS 4-(A-B)
0.40 RB-4
4.03 m²
Bottom
1 1 1 10.08 ON AXIS 4-(A-B)
0.25 RB-4
2.52 m²
External
1 1 1 10.88 ON AXIS 4 -(C-F)
0.40 RB-4
4.35 m²
1 -1 1 4.43 DEDUCT BALCONY SIDE
0.40
-1.77 m²
Internal
1 1 1 15.67 ON AXIS 4 -(C-F)
0.40 RB-5
6.27 m²
1 1 1 5.59 ON AXIS 4 -(C-F)
0.40 RB-5
2.24 m²
Bottom
1 1 1 15.42 ON AXIS 4 -(C-F)
0.25 RB-5
3.86 m²
External
1 1 1 10.60 ON AXIS A- (4-2)
0.40 RB-6
4.24 m²
Internal
1 1 1 9.40 ON AXIS A- (4-2)
0.40 RB-6
3.76 m²
Bottom
1 1 1 9.40 ON AXIS A- (4-2)
0.25 RB-6
2.35 m²
Internal
1 1 2 9.40 ON AXIS B & F(4-2)
0.40 RB-7
7.52 m²
Bottom
1 1 1 9.40 ON AXIS B & F(4-2)
0.25 RB-7
2.35 m²
External
1 1 1 7.00 ON AXIS C & D (1-4 )
0.40 RB-8
2.80 m²
Internal
1 2 1 6.60 ON AXIS C & D (1-4 )
0.40 RB-8
5.28 m²
1 1 1 9.55 ON AXIS C & D (1-4 )
0.40 RB-8
3.82 m²
Bottom
1 1 1 15.95 ON AXIS C & D (1-4 )
0.25 RB-8
3.99 m²
External
1 1 1 1.65 ON AXIS B' (4-5)
0.40 RB-9
0.66 m²
Internal
1 1 1 1.25 ON AXIS B' (4-5)
0.40 RB-9
0.50 m²
Bottom
1 1 1 1.25 ON AXIS B' (4-5)
0.25 RB-9
0.31 m²
External
1 1 1 3.70 ON AXIS D' (4-5)
0.40 RB-9
1.48 m²
Internal
1 1 1 3.30 ON AXIS D' (4-5)
0.40 RB-9
1.32 m²
Bottom
1 1 1 3.30 ON AXIS D' (4-5)
0.25 RB-9
0.83 m²
External
1 1 1 8.84 ON AXIS 5 (B'-D')
0.40 RB-10
3.54 m²
Internal
1 1 1 7.79 ON AXIS 5 (B'-D')
0.40 RB-10
3.12 m²
Bottom
1 1 1 8.04 ON AXIS 5 (B'-D')
0.25 RB-10
2.01 m²
External
1 1 1 7.00 ON AXIS E (4-1)
0.40 RB-10
2.80 m²
Internal
1 1 2 9.40 ON AXIS E (4-1)
0.40 RB-10
7.52 m²
1 1 1 6.60 ON AXIS E (4-1)
0.40 RB-10
2.64 m²
Bottom
1 1 1 15.95 ON AXIS E (4-1)
0.25 RB-10
3.99 m²
Internal
1 1 1 16.31 ON AXIS (5-1)
0.40 RB-11
6.52 m²
WATER TANKER BEAM
External
1 1 1 8.84 ON AXIS 5 (B'-D')
0.40 RB-11
3.54 m²
Internal
1 1 1 7.79 ON AXIS 5 (B'-D')
0.40 RB-11
3.12 m²
Bottom
1 1 1 7.79 ON AXIS 5 (B'-D')
0.25 RB-11
1.95 m²
External
1 1 2 5.86 ON AXIS 4 (B'-D')
0.40 RB-12
4.69 m²
Internal
1 1 2 5.61 ON AXIS 4 (B'-D')
0.40 RB-12
4.49 m²
Bottom
1 1 1 5.61 ON AXIS 4 (B'-D')
0.25 RB-12
1.40 m²
External
1 1 1 3.70 ON AXIS B' (4-5)
0.40 RB-13
1.48 m²
Internal
1 1 1 3.30 ON AXIS B' (4-5)
0.40 RB-13
1.32 m²
Bottom
1 1 1 3.30 ON AXIS B' (4-5)
0.25 RB-13
0.83 m²
Internal
1 1 2 3.45 ON AXIS (4-5)
0.40 RB-14
2.76 m²
Bottom
1 1 1 3.45 ON AXIS (4-5)
0.25 RB-14
0.86 m²
External
1 1 1 3.70 ON AXIS B' (4-5)
0.40 RB-13
1.48 m²
Internal
1 1 1 3.30 ON AXIS D' (4-5)
0.40 RB-15
1.32 m²
Bottom
1 1 2 3.30 ON AXIS D' (4-5)
0.25 RB-15
1.65 m²
979.64
979.64 m² Total To Item 1.04.B

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption

C) Stair case & Landing

Main stair case


Ground-8th floor
SECTION A-A

9 1 6 1.03 riser

0.17

9.46 m²
9 1 1 1.95 sofit
1.03

18.08 m³
9 1 1 1.03 Landing 1
1.15

10.66 m³
9 1 1 1.86 side formwork
0.22
3.68 m³

SECTION B-B
9 1 4 1.03 riser
0.17
6.12 m³
9 1 1 1.30 sofit
1.03
12.05 m³
9 1 1 1.15 Landing 1
1.03
10.66 m³
9 1 1 1.86 side formwork
0.22
3.68 m³
SECTION C-C
9 1 6 1.03 riser
0.17
9.18 m³
9 1 1 1.93 sofit
1.15
19.98 m³
9 1 1 1.45 side formwork
0.22
2.87 m³
SHOP STAIR
SECTION E-E

1 1 11 0.15 riser

0.30

0.50 m³
1 1 1 3.75 sofit

1.05
3.94 m³
1 1 1 3.02 side formwork
0.22
0.66 m³
SECTION F-F
1 1 11 0.15 riser
0.30
0.50 m³
1 1 1 3.02 side formwork
0.22
0.66 m³
1 1 1 3.30 sofit
1.05
3.47 m³
1 1 1 1.98 Landing 1
2.20
4.36 m³
1 1 2 1.98 side Landing formwork
0.22
0.87 m³

121.38 m² Total To Item 1.04.C

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption

D) Shear wall

GROUND FLOOR
external
1 1 1 2.60 W2
3.30
8.58 m³
Internal
1 1 1 2.10 W2
3.30
6.93 m³
external
1 1 1 2.30 W3
3.30
7.59 m³
Internal
1 1 1 1.80 W3
3.30

5.94 m³
external

1 1 1 2.30 W4

3.30

7.59 m³
Internal

1 1 1 1.80 W4
3.30
5.94 m³
1 1 -2 2.10 DDT
1.00 OPENING
-4.20 m³
1st to 8th
external
8 1 1 2.60 W2
3.30
68.64 m³
Internal
8 1 1 2.10 W2
3.30
55.44 m³
external
8 1 1 2.30 W3
3.30
60.72 m³
Internal
8 1 1 1.80 W3
3.30
47.52 m³
external
8 1 1 2.30 W4
3.30
60.72 m³
Internal
8 1 1 1.80 W4
3.30
47.52 m³
8 1 -2 2.10 DDT
1.00 OPENING
-33.60 m³
ABOVE 8TH FLOOR
external
1 1 1 2.60 W2
2.50
6.50 m³
Internal
1 1 1 2.10 W2
2.50
5.25 m³
external
1 1 1 2.60 W2
0.70
1.82 m³
Internal
1 1 1 2.10 W2
0.70
1.47 m³
external
1 1 1 2.30 W3
0.70
1.61 m³
Internal
1 1 1 1.80 W3
0.70
1.26 m³
external
1 1 1 2.30 W4
0.70
1.61 m³

1 1 1 1.80 Internal
0.70 W4
1.26 m³
20.78
366.11 m² Total To Item 1.04.D

E). In Concrete gutter


External
1 1 1 23.85 on axis A'-C b/n 1'-2'
0.84
20.03 m² internal
1 1 1 23.25 on axis A'-C b/n 1'-2'
0.78
18.14 m² bottom
1 1 1 23.85 on axis A'-C b/n 1'-2'
0.25
5.96 m²
External
1 1 1 15.86 on axis E'-F' b/n 1'-2'
0.84
13.32 m² internal
1 1 1 15.00 on axis E'-F' b/n 1'-2'
0.84
12.60 m² bottom
1 1 1 15.86 on axis E'-F' b/n 1'-2'
0.25
3.97 m²
External
1 1 1 12.98 on axis 4 b/n 1D'-F'
0.84
10.90 m² Internal
1 1 1 12.38 on axis 4 b/n 1D'-F'
0.84
10.40 m² Bottom
1 1 1 12.98 on axis 4 b/n 1D'-F'
0.25
3.25 m²

98.57 m² Total To Item 1.1d

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


F) 15cm thick solid slab
AROUND CIRCULATION
FIRST FLOOR
1 1 1 5.93 B/ N Axis 4-5 & A-B
3.45
20.46 m²
1 1 1 4.46 B/ N Axis B-B' & 4-5
3.45
15.37 m²
1 1 1 2.84 B/ N Axis C-C' & 4-5
3.40
9.66 m²
1 1 1 4.63 B/ N Axis D'-E & 4-5
3.45
15.97 m²
1 1 1 5.75 B/ N Axis E-F & 4-5
3.45
19.84 m²
1 1 1 5.08 B/ N Axis F-G & 4-5
3.45
17.53 m²
1 1 1 5.08 B/ N Axis F-G & 2-3
4.93
25.04 m²
1 1 1 5.08 B/ N Axis F-G & 3-4
4.93
25.04 m²
1 1 1 5.58 B/ N Axis B-C & 5-6
3.60
20.09 m²
1 1 1 3.60 B/ N Axis C-D' & 5-6
7.22
25.99 m²
1 1 1 4.63 B/ N Axis D'-E & 5-6
3.60
16.67 m²
1 -13 1 0.05 Deduct Column Contact Area
0.05 Axis 2G, 3G 4G, 5A, 5B, 5C', 5E, 5F,5G,6B,6C,6D,6E
-0.03 m²
SECOND- EIGHTH FLOOR
7 1 1 6.55 ON Axis 1 B/N C-D
1.05
48.14 m²
7 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.10
68.22 m²
7 1 1 3.45 ON Axis 4-5 B/N B'-C'
2.84
68.59 m²
7 1 1 1.45 ON Axis 4-5 B/N B'-C'
1.40
14.21 m²

410.79 m² Total To Item 1.2.F


G) In 15 cm thick Roof Slab
1 1 1 6.50 ON Axis 1 B/N C-D
1.05
6.83 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20
10.63 m²
1 1 1 3.45 ON Axis 4-5 B/N B'-D
2.90

10.01 m²
1 1 1 2.84 ON Axis 4-5 B/N B'-D
3.45
9.80 m²
1 1 1 2.35
1.40
3.29 m²
1 -2 1 0.15 Deduct column contact area
0.15
-0.05 m²
WATER TANKER SLAB
1 1 1 5.19 b/n Axis 4-5 & B'-D'
3.45
17.91 m²

1 1 1 2.90
3.45
10.01 m²
1 -2 1 0.15 Deduct column contact area
0.15
-0.05 m²

68.38 m² Total To Item 1.2.G

Precast Beam Elements (PB) to the sizes given below.

FIRST FLOOR
a) Pre-cast rib unit PB 1 of size (293 X 120 X 80mm) consisting of 15 kg of reinforcing
1 1 1 40.00 bar and 0.04m3 of C-25 concrete (Price shall include transportation and placing in
position)
40 Pcs
b) Pre-cast rib unit PB 2 of size (503X 120 X 80mm) consisting of 12 kg of
1 1 1 95.00 reinforcing bar and 0.03m3 of C-25 concrete (Price shall include transportation and
placing in position)
95 Pcs
SECOND- EIGHTH FLOOR
a) Pre-cast rib unit PB 1 of size (293 X 120 X 80mm) consisting of 15 kg of reinforcing
7 1 1 40.00 bar and 0.04m3 of C-25 concrete (Price shall include transportation and placing in
position)
280 Pcs
b) Pre-cast rib unit PB 2 of size (503X 120 X 80mm) consisting of 12 kg of
7 1 1 100.00 reinforcing bar and 0.03m3 of C-25 concrete (Price shall include transportation and
placing in position)
700 Pcs
320 Pcs Total Item of 293x120x80mm Precast Beam
795 Pcs Total Item of 293x120x80mm Precast Beam
Steel reinforcement according to structural drawing. Price includes cutting,
bending, placing in position and tying wires:
3,965.32 kg a) dia. 6mm plain bar
15,179.07 kg b) dia. 8mm deformed bar
11,298.72 kg c) dia. 10mm deformed bar
8,886.61 kg d) dia. 12mm deformed bar
7,595.44 kg e) dia. 14mm deformed bar
13,370.36 kg f) dia. 16mm deformed bar
14,787.62 kg g) dia. 20mm deformed bar
1,072.67 kg g) dia. 24mm deformed bar

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Project:- Saving Houses B+G+8 Typolog Block Type:- New B+G+8


Client:- Addis Ababa Saving Houses De Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Timizing Dimension Qty Descreption
SUPER-STRUCTURE
BLOCK WORK
20cm thick Class B external HCB wall which can
satisfy the designed strength, bedded in cement
mortar (1:3).
Basement floor
1 1 1 5.30 On axis 4 b/n E - F
2.80
14.84 m²
1 1 2 5.30 On axis 2,3 b/n E - F
2.50
26.50 m²
1 1 1 6.91 On axis E b/n 1 - 2 & 4 -5
2.80
19.35 m²
1 1 1 4.24 On axis 4 b/n C - D'
2.80
11.87 m²
1 1 1 3.10 On axis D' b/n 4-5
2.80
8.68 m² 81.24 m²
Gnd Floor
1 1 1 10.80 On axis 1 b/n C-E
2.80
30.24 m²
1 1 1 10.80 On axis 2 b/n A-B'
2.80
30.24 m²
Deduction
1 -1 1 4.20 W1
1.80
-7.56 m²
1 -1 1 2.75 TW-2
0.80
-2.20 m²
1 -1 1 1.10 W-11
1.80
-1.98 m²
On axis 2 b/n E-G
1 1 1 10.43
2.80
29.20 m²
1 1 -1 4.50 DDT TW-5
0.80
-3.60 m²
1 1 -1 5.40 DDT TW-4
0.80
-4.32 m²
1 1 1 3.25 On axis 3 b/n A-B'
2.80
9.10 m²
1 1 1 10.80 On axis 3 b/n D-F
2.80
30.24 m²
1 1 1 5.64 On axis 4 b/n C-D'
2.80
15.79 m²
1 1 1 7.64 On axis 5 b/n B'-D'
2.80
21.39 m²
Deduction
1 -1 1 2.40 W-4
1.80
-4.32 m²
1 -1 1 2.74 WD-2
2.80
-7.67 m²
1 1 1 1.40 b/n axis A/ 2-3
2.80
3.92 m²
1 1 1 5.02 b/n axis A-B/2-3
3.00
15.06 m²
1 1 1 5.23 b/n axis B-B'/2-3
2.80
14.64 m²
1 1 1 4.39 b/n axis C & 2-3
2.80
12.29 m²
1 1 1 13.33 On axis D b/n 1-4
2.80
37.32 m²
1 1 1 3.10 On axis D' b/n 4-5
2.80
8.68 m²
1 -1 1 3.10 W-4
0.50
-1.55 m²
1 1 1 8.80 On axis E b/n 2-4
2.80
24.64 m²
1 1 1 4.40 On axisd F b/n 3-4
2.80
12.32 m²
1 1 1 13.10 On axisd G b/n 2-5
2.80
36.68 m²
1 2 -1 4.50 DDT TW-5
0.80
-7.20 m²
1 1 -1 2.70 DDT TW-6
0.80
-2.16 m² 289.21 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc
Timizing Dimension Qty Descreption
FIRST FLOOR
1 1 1 10.80 On axis 1 b/n C-E
2.80
30.24 m²
1 1 1 10.80 On axis 2 b/n A-B'
2.80
30.24 m²
Deduction
1 -1 1 4.20 W1
1.80
-7.56 m²
1 -1 1 2.75 TW-2
0.80
-2.20 m²
1 -1 1 1.10 W-11
1.80
-1.98 m²
1 1 1 3.25 On axis 3 b/n A-B
2.80
9.10 m²
1 1 1 5.40 On axis 3 b/n E-F
2.80
15.12 m²
1 1 1 5.64 On axis 4 b/n C-D'
2.80
15.79 m²
1 1 1 7.54 On axis 5 b/n B'-D'
2.80
21.11 m²
Deduction
1 -1 1 2.40 W-4
1.80
-4.32 m²
1 -1 1 2.59 W-2
1.80
-4.66 m²
1 1 1 1.40 b/n axis A & 2-4
2.80
3.92 m²
1 1 1 5.03 b/n axis A-b & 2-3
3.02
15.19 m²
1 1 1 3.21 b/n axis B & 3-4
2.80
8.99 m²
1 1 1 5.23 b/n axis B-B' & 2-3
2.80
14.64 m²
1 1 1 4.39 b/n axis C & 2-3
2.80
12.29 m²
1 1 1 5.15 b/n axis C - D & 3-4
3.02
15.55 m²
1 1 1 8.57 On axis D b/n 1-3
2.80
24.00 m²
1 1 1 3.10 On axis D' b/n 4-5
2.80
8.68 m²
1 -1 1 3.10 W-4
0.50
-1.55 m²
1 1 1 2.17 On axis E b/n 2-3
2.80
6.08 m²
1 1 1 3.30 On Axis A, 4-5
0.60
1.98 m²
1 1 1 0.40 On Axis A, 4-5
0.40
0.16 m²
1 1 1 5.10 On Axis 5 , A-B
0.60
3.06 m²
1 1 1 1.20 On Axis 5 , A-B
0.40
0.48 m²
1 1 2 3.31 On Axis B & E ,5-6
0.60
3.97 m²
1 1 2 0.80 On Axis B & E ,5-6
0.40
0.64 m²
1 1 1 15.60 On Axis 6 ,B-E
0.60
9.36 m²
1 1 1 2.40 On Axis 6 ,B-E
0.40
0.96 m²
1 1 1 9.93 On Axis 5 ,E-G
0.60
5.96 m²
1 1 1 1.80 On Axis 5 ,E-G
0.40
0.72 m²
1 1 1 12.00 On Axis G ,2-5
0.60
7.20 m²
1 1 1 2.00 On Axis G ,2-5
0.40
0.80 m²
1 1 1 4.63 On Axis 2 ,F-G
0.60
2.78 m²
1 1 1 0.80 On Axis 2 ,F-G
0.40
0.32 m² 247.06 m²
Second- Third floor
2 1 1 6.55 On axis 1 b/n C-D
3.02
39.56 m² Deduction
2 -1 2 0.80 TW-3
0.60
-1.92 m²
2 1 1 5.40 On axis 1 b/n D-E
2.80
30.24 m²
Deduction
2 -1 2 2.00 W-5
1.80
-14.40 m²
2 1 1 12.08 b/n axis 1-2 & C-E
3.00
72.48 m²
2 1 1 12.33 On axis 2 b/n A-C
2.80
69.05 m²
Deduction
2 -1 1 0.80 W-8
1.80
-2.88 m²
2 -1 1 2.00 W-5
1.80
-7.20 m²
2 -1 1 0.60 TW-3
0.80
-0.96 m²
2 -1 1 1.10 W-11
1.80
-3.96 m²
On axis 2 b/n E-F
2 1 1 5.40
2.80
30.24 m²
Deduction
2 -1 1 0.80 W-8
1.80
-2.88 m²
On axis 2-3 b/n A-F
2 1 1 5.03
3.00
30.18 m²
2 1 1 10.80 On axis 3 b/n B-C & D-E
2.80
60.48 m²
2 1 1 9.68 On axis 4 b/n A-B'
2.80
54.21 m²
2 1 1 9.68 On axis 4 b/n D'-F
2.80
54.21 m²
Deduction
2 -1 2 2.00 W-5
1.80
-14.40 m²
2 -1 2 1.80 WD-16
2.80
-20.16 m²
2 -1 2 1.43 WD-17
2.80
-16.02 m²
2 -1 2 2.05 W-6
1.80
-14.76 m²
2 1 1 7.54 On axis 5 b/n B'-D'
2.80
42.22 m²
Deduction
2 -1 1 2.69 W-2
1.80
-9.68 m²
2 -1 1 2.40 W-4'
1.80
-8.64 m²
2 1 1 8.80 On axis A b/n 2-4
2.80
49.28 m²
2 -1 1 2.90 Deduction
1.80 W-7
-10.44 m²
2 -2 1 0.60 TW-3
0.80
-1.92 m²
2 1 1 4.39 On axis B b/n 2-3
2.80
24.58 m²
2 1 1 1.25 On axis B' b/n 4-5
2.80
7.00 m²
2 1 1 5.65 b/n axis C & 1-2
2.80
31.64 m²
2 1 1 1.49 b/n axis C & 2-3
2.80
8.34 m²
Deduction
2 -1 1 1.95 W-10
1.80
-7.02 m²
2 -1 1 1.85 W-9
1.80
-6.66 m²
2 -1 1 1.49 W-12
0.80
-2.38 m²
2 1 1 3.45 b/n axis C & 3-4
2.80
19.32 m²
2 1 1 9.40 On axis D b/n 1-4
2.80
52.64 m²
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


2 1 1 3.10 On axis D' b/n 4-5
2.80
17.36 m²
Deduction
2 -1 1 3.10 W-4
0.50
-3.10 m²
2 1 1 9.00 On axis E b/n 1-3
2.80
50.40 m²
Deduction
2 -1 1 2.00 W-5
1.80
-7.20 m²
2 1 1 8.80 On axisd F b/n 2-4
2.80
49.28 m²
Deduction
2 -1 1 2.90 W-7
1.80
-10.44 m²
2 -2 1 0.60 TW-3
0.80
-1.92 m²
2 1 1 1.42 On Axis E b/n 1-2
0.60 BALCONY
1.70 m²
2 1 1 1.40 On Axis C b/n 1-2
0.60 BALCONY
1.68 m²
627.16 m²
4th-8th Floor
5 1 1 6.55 On axis 1 b/n C-D
3.02
98.91 m² Deduction
5 -1 2 0.80 TW-3
0.60
-4.80 m²
5 1 1 5.60 On axis 1 b/n D-E
2.80
78.40 m²
Deduction
5 -1 2 2.00 W-5
1.80
-36.00 m²
5 1 1 12.08 b/n axis 1-2 & C-E
3.00
181.20 m²
5 1 1 12.73 On axis 2 b/n A-C
2.80
178.22 m²
Deduction
5 -1 1 0.80 W-8
1.80
-7.20 m²
5 -1 1 2.00 W-5
1.80
-18.00 m²
5 -1 1 0.60 TW-3
0.80
-2.40 m²
5 -1 1 1.10 W-11
1.80
-9.90 m²
On axis 2 b/n E-F
5 1 1 5.60
2.80
78.40 m²
Deduction
5 -1 1 0.80 W-8
1.80
-7.20 m²
On axis 2-3 b/n A-F
5 1 1 5.03
3.00
75.45 m²
5 1 1 11.10 On axis 3 b/n B-C & D-E
2.80
155.40 m²
5 1 1 10.08 On axis 4 b/n A-B'
2.80
141.12 m²
5 1 1 10.08 On axis 4 b/n D'-F
2.80
141.12 m²
Deduction
5 -1 2 2.00 W-5
1.80
-36.00 m²
5 -1 2 1.80 WD-16
2.80
-50.40 m²
5 -1 2 1.43 WD-17
2.80
-40.04 m²
5 -1 2 2.05 W-6
1.80
-36.90 m²
5 1 1 7.74 On axis 5 b/n B'-D'
2.80
108.36 m²
Deduction
5 -1 1 2.69 W-2
1.80
-24.21 m²
5 -1 1 2.40 W-4'
1.80
-21.60 m²
5 1 1 9.40 On axis A b/n 2-4
2.80
131.60 m²
5 -1 1 2.90 Deduction
1.80 W-7
-26.10 m²
5 -2 1 0.60 TW-3
0.80
-4.80 m²
5 1 1 4.69 On axis B b/n 2-3
2.80
65.66 m²
5 1 1 1.25 On axis B' b/n 4-5
2.80
17.50 m²
5 1 1 5.85 b/n axis C & 1-2
2.80
81.90 m²
5 -1 1 1.95 Deduction
1.80 W-10
-17.55 m²
5 -1 1 1.85 W-9
1.80
-16.65 m²
5 1 1 1.59 b/n axis C & 2-3
2.80
22.26 m²
5 -1 1 1.49 Deduction
0.80 W-12
-5.96 m²
5 1 1 3.55 b/n axis C & 3-4
2.80
49.70 m²
5 1 1 9.90 On axis D b/n 1-4
2.80
138.60 m²
5 1 1 3.30 On axis D' b/n 4-5
2.80
46.20 m²
Deduction
5 -1 1 3.10 W-4
0.50
-7.75 m²
5 1 1 9.50 On axis E b/n 1-3
2.80
133.00 m²
Deduction
5 -1 1 2.00 W-5
1.80
-18.00 m²
5 1 1 9.40 On axisd F b/n 2-4
2.80
131.60 m²
Deduction
5 -1 1 2.90 W-7
1.80
-26.10 m²
5 -2 1 0.60 TW-3
0.80
-4.80 m²
5 1 1 1.42 On Axis E b/n 1-2
0.60 BALCONY
4.26 m²
5 1 1 1.40 On Axis C b/n 1-2
0.60 BALCONY
4.20 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Above Top tie Beam
1 1 1 10.68 On axis 4 b/n A-B'
2.00
21.36 m²
1 1 0.5 12.60 On axis 1 b/N C-E
2.00
12.60 m²
1 2 0.5 5.00 On axis F b/n 2-4
2.00
10.00 m²
1 1 0.5 10.60 On axis A b/n 2-4
2.00
10.60 m²
1 1 0.5 4.39 On axis B b/n 2-3
0.90
1.98 m²
1 1 1 5.40 On axis 3 b/n B-C

0.90

4.86 m²
1 1 1 5.00 On axis D b/n 3-4

2.00

10.00 m²

1 1 1 6.40 On axis D b/n 2'-3

2.00

12.80 m²

1 1 0.5 4.40 On axis E b/n 2-3

2.00

4.40 m²
1 1 1 5.40 On axis 3 b/n D-E
2.00
10.80 m²
LOBBY
1 1 0.5 5.22 On axis C-D b/n 2-3
2.00
5.22 m²
1 1 0.5 3.56 On axis C b/n 3-4
2.00
3.56 m²
1 1 1 7.54 WATER TANKER
3.00 FRONT ELEVATION
22.62 m²
1 -1 1 2.59 Deduction
1.80 W-2
-4.66 m²
1 -1 1 2.40 W-4
0.80
-1.92 m²
1 1 1 3.10 RIGHT SIDE ELEVATION
3.00
9.30 m²
1 1 1 3.30 LEFT SIDE ELEVATION
3.00
9.90 m²
143.41 m²
3028.77 m² Total To Item 2.01

Ditto as item 2.01 but for 100mm HCB wall.


Basement floor
1 1 1 1.40 At Garbage & Sanitary Ducts
2.80 On Axis 4-5 , C-D
3.92 m²
1 1 1 1.25
2.80
3.50 m²
1 1 1 0.70
2.80
1.96 m²
1 1 1 0.50
2.80
1.40 m² 10.78 m²
GROUND FLOOR
1 1 1 7.30 On Axis a-b & 2-3
3.00 toilet area horizontally
21.90 m²
1 1 1 3.72 On Axis a-b & 2-3
3.02 toilet area vertically
11.23 m²
1 1 1 1.30 DUCT (Pipe cover at toilet)
3.02
3.93 m²
1 1 1 3.90 On Axis C b/n 4-5
3.02 duct area
11.78 m²
1 1 1 1.00 On Axis A,3
2.80 DUCT (Pipe cover at toilet)
2.80 m²
1 1 1 0.80 On Axis 1, C-D
3.02 DUCT (Pipe cover)
2.42 m²
1 1 1 1.15 On Axis 4, B'
3.02 DUCT (Pipe cover)
3.47 m²
1 1 1 0.80 On Axis 4, D'
3.02 DUCT (Pipe cover)
2.42 m²
1 1 2 0.55 On Axis F around axis 3
3.02 DUCT (Pipe cover)
3.32 m² 63.27 m²
FIRST FLOOR

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


1 1 1 7.30 On Axis a-b & 2-3
3.02 toilet area horizontally
22.05 m²
1 1 1 3.72 On Axis a-b & 2-3
3.02 toilet area vertically
11.23 m²
1 1 1 1.30 DUCT (Pipe cover at toilet)
3.02
3.93 m²
1 1 1 3.90 On Axis C b/n 4-5
3.02 duct area
11.78 m²
1 1 1 1.00 On Axis A,3
2.80 DUCT (Pipe cover at toilet)
2.80 m²
1 1 1 0.80 On Axis 1, C-D
3.02 DUCT (Pipe cover)
2.42 m²
1 1 1 1.15 On Axis 4, B'
3.02 DUCT (Pipe cover)
3.47 m²
1 1 1 0.80 On Axis 4, D'
3.02 DUCT (Pipe cover)
2.42 m²
1 1 2 0.55 On Axis F around axis 3
3.02 DUCT (Pipe cover)
3.32 m² 63.41 m²
SECOND- THIRD FLOOR
2 1 1 1.53 On Axis 1-2 C-E

3.02 TOILET
9.24 m²
2 1 1 4.60
3.02
27.78 m²
2 1 1 6.28 On Axis 1-2 C-E
3.02 BED ROOM-1
37.93 m²
2 1 1 2.05
2.80
11.48 m²
2 1 1 6.89 KITCHEN
3.02
41.62 m²
2 1 1 1.75 BED ROOM-1
3.02
10.57 m²
2 1 1 3.46 On Axis 2-3 & A-F
3.02 TOILET (B/N A-B)
20.90 m²
2 1 1 5.72 BED ROOMS
3.02
34.55 m²
2 1 1 3.38 TOILET (B/N B-D)
3.02
20.42 m²
2 1 1 6.92 KITCHEN
3.02
41.80 m²
2 1 1 4.13 Store
3.02
24.95 m²
2 1 1 5.35 BED ROOM 2 (B/N E-F)
3.02
32.31 m²
2 1 1 3.63 TOILET (B/N E-F)
3.02
21.93 m²
2 1 2 2.18 On Axis 3 & A-F
2.80 TOILET
24.42 m²
2 1 2 3.21 On Axis 3 A & F
3.02 TOILET
38.78 m²
2 1 2 3.58
3.02 BED ROOM-1
43.25 m²
2 1 2 6.04 KITCHEN
3.02
72.96 m²
2 1 1 3.05 On Axis C b/n 4-5
3.02 DUCT
18.42 m²
2 2 2 0.50 On Axis A & F around axis 3
3.02 DUCT (Pipe cover at toilet)
12.08 m²
2 1 1 0.50 On Axis 2 B-B'
3.02 DUCT (Pipe cover at toilet)
3.02 m²
2 1 2 0.80 On Axis 4, B'&D'
3.02 DUCT (Pipe cover at kitchen)
9.66 m²
2 1 1 1.20 On Axis 1, C-D
3.02 DUCT (Pipe cover at toilet)
7.25 m²
2 1 1 4.83 On Axis 4 b/n A-B'
0.60 BALCONY
5.80 m²
2 1 1 5.03 On Axis 4 b/n D'-E
0.60 BALCONY
6.04 m² 577.13 m²
4TH-8TH Floor

5 1 1 1.53 On Axis 1-2 C-E

3.02 TOILET
23.10 m²
5 1 1 4.60
3.02
69.46 m²
5 1 1 6.28 On Axis 1-2 C-E
3.02 BED ROOM-1
94.83 m²
5 1 1 2.25
2.80
31.50 m²
5 1 1 6.89 KITCHEN
3.02
104.04 m²
5 1 1 1.75 BED ROOM-1
3.02
26.43 m²
5 1 1 3.46 On Axis 2-3 & A-F
3.02 TOILET (B/N A-B)
52.25 m²
5 1 1 5.72 BED ROOMS
3.02
86.37 m²
5 1 1 3.38 TOILET (B/N B-D)
3.02
51.04 m²
5 1 1 6.92 KITCHEN
3.02
104.49 m²
5 1 1 4.13 Store
3.02
62.36 m²
5 1 1 5.35 BED ROOM 2 (B/N E-F)
3.02
80.79 m²
5 1 1 3.63 TOILET (B/N E-F)
3.02
54.81 m²
5 1 2 2.38 On Axis 3 & A-F
2.80 TOILET
66.64 m²
5 1 2 3.21 On Axis 3 A & F
3.02 TOILET
96.94 m²
5 1 2 3.58
3.02 BED ROOM-1
108.12 m²
5 1 2 6.04 KITCHEN
3.02
182.41 m²
5 1 1 3.05 On Axis C b/n 4-5
3.02 DUCT
46.06 m²
5 2 2 0.50 On Axis A & F around axis 3
3.02 DUCT (Pipe cover at toilet)
30.20 m²
5 1 1 0.50 On Axis 2 B-B'
3.02 DUCT (Pipe cover at toilet)
7.55 m²
5 1 2 0.80 On Axis 4, B'&D'
3.02 DUCT (Pipe cover at kitchen)
24.16 m²
5 1 1 1.20 On Axis 1, C-D
3.02 DUCT (Pipe cover at toilet)
18.12 m²
5 1 1 4.83 On Axis 4 b/n A-B'
0.60 BALCONY
14.49 m²
5 1 1 5.03 On Axis 4 b/n D'-E
0.60 BALCONY
15.09 m²
2165.83 m² Total To Item 2.02

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Ent Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC

Timizing Dimension Qty Description


SUPER-STRUCTURE
Supply and fix toch applied water proofing membrane of 4mm thick
which passes (ASTM D6222) and granular finish for roof water
proofing system(minimum slope 1/20).
ROOF LEVEL
1 1 1 6.45 ON Axis 1 B/N C-D
1.25
8.06 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E'
1.20 Balcony
10.63 m²
WATER TANKER SLAB
1 1 1 8.84
3.95
34.92 m²
53.61 m² Total item

Supply and Apply Cementious Damp Proofing for upper floor


wet areas to a height of 300mm on walls and column.

a. all upper wet rooms


Ground floor Verenda
1 1 1 12.00 B/N axis 1-2 & A-B'
7.00
84.00 m²
1 1 1 6.00 B/N axis 1-2 & E-F
7.00
42.00 m²
Grnd &1st Floor
2 1 1 1.65 B/N axis 2-3 & B-B'
1.28 Toilet
3.89 m²
2 1 1 1.65 >>
0.90
2.97 m²
2 1 1 1.65 >>
1.09
3.48 m²
2 1 1 1.31 >>
1.65
4.32 m²
2 1 1 2.85 >>
2.63
14.85 m²
2 1 1 1.70 >>
2.60
8.84 m²
2 -1 1 0.40 deduct for column Area
0.60
-0.48 m²
2 -1 1 0.25
0.60
-0.30 m²
2ND-3RD FLOOR
2 1 1 2.07 Toilet
1.78 B/N axis 2 & B-B'
7.28 m²
2 1 1 2.58
1.48 B/N axis 3 & A-B'
7.55 m²
2 1 1 2.58
1.42
7.33 m²
2 -1 1 0.40 deduct for column area
0.20
-0.16 m²
2 -1 1 0.40
0.30
-0.24 m²
2 1 1 2.20 B/N axis 1 & C-D'
1.47
6.47 m²
2 1 1 2.20
1.47
6.26 m²
2 -1 1 0.60 Deduct for column area
0.35
-0.42 m²
2 1 1 2.58 B/N axis 3 & E-F
1.43
7.18 m²
2 1 1 2.58
1.47
7.59 m²
2 -2 1 0.40 Deduct for column area
0.25
-0.40 m²
212.01 m² Total item
4TH-8TH Floor
2 1 1 2.07 Toilet
1.78 B/N axis 2 & B-B'
7.28 m²
2 1 1 2.58
1.48 B/N axis 3 & A-B'
7.55 m²
2 1 1 2.58
1.42
7.33 m²
2 -1 1 0.20 deduct for column area
0.20
-0.08 m²
2 -1 1 0.20
0.10
-0.04 m²
2 1 1 2.20 B/N axis 1 & C-D'
1.47
6.47 m²
2 1 1 2.20
1.47
6.26 m²
2 -1 1 0.40 Deduct for column area
0.15
-0.12 m²
2 1 1 2.58 B/N axis 3 & E-F
1.43
7.18 m²
2 1 1 2.58
1.47
7.59 m²
2 -2 1 0.20 Deduct for column area
0.15
-0.12 m²
49.30 m² Total item
261.31 m² Total item to 3.02.a

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Description


b) Concrete Retaining Wall
1 1 1 114.65 Basement floor
3.00
343.95
343.95 Total to Item 3.02b
C) CAFETERIA TERRACE
1 2 1 6.10 B/N axis 4-5 & A-B & E-F
3.55
43.31 m²
1 2 1 7.45 B/N axis 4-6 & B-B' & D'-E
4.63
68.99 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 14.00 B/N axis 2-5 & F-G
5.28
73.92 m²
1 1 1 66.80 SKIRTING
0.10
6.68 m² 226.05 m²
226.05 m² Total item
Average 70mm thick light weight concrete in mix (1:2:5) cement,
pumice and sand laid over RC roof slab
ROOF LEVEL
1 1 1 6.45 ON Axis 1 B/N C-D
1.25
8.06 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20 Balcony
10.63 m²
WATER TANKER SLAB
1 1 1 8.84
3.95
34.92 m²
53.61 m² Total To Item
Apply 30 mm thick smooth finished cement sand screed laid on top
of light weight concrete area in mortar mix (1:3) with proper slope
towards down pipe.
ROOF LEVEL
1 1 1 6.45 ON Axis 1 B/N C-D
1.25
8.06 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20 Balcony
10.63 m²
WATER TANKER SLAB
1 1 1 8.84
3.95
34.92 m²
53.61 m² Total To Item
Roof cover in prepainted EGA - 500
1 1 1 11.91 Axis b/n A -C & 2-4
10.25
122.08 m²
1 1 1 10.25 Axis b/n C-D, 2-4
0.5 6.07
31.11 m²
1 1 1 10.00 Axis b/n C-D, 2-4
0.5 6.10
30.50 m²
1 1 1 6.10 Axis b/n C-D, 1-2
6.85
41.79 m²
1 1 1 6.05 Axis b/n D-E & 1-2
6.85
41.44 m²
1 1 1 6.10 Axis b/n D-E & 2-3
0.5 5.07
15.46 m²
1 1 1 6.00 Axis b/n D-E & 2-3
0.5 5.10
15.30 m²
1 1 1 5.88 Axis b/n E-F & 2-3
5.10
29.99 m²
1 1 1 12.00 Axis b/N D-F & 3-4
5.10
61.20 m²
1 -1 1 1.10 Axis b/N D-F & 3-4
1.97
-2.17 m²
386.70 m²Total To Item 3..05
G-28 galvanized flat metal sheet gutter
1 1 1 50.63
50.63 m²
50.63 mlTotal To Item
Roof Ridge cover dev. Length=67cm
1 1 1 19.59
19.59 mlTotal To Item
Copping
1 1 1 68.58
68.58 ml
Supply and fix 110mm PVC Downpipe including elbow and other
necessary materials and accessories to complete the work
Down PIPE
1 1 10 30.00
300.00 mlTotal To Item

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc
Project:- Saving Houses B+G+8 Typolog Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses D Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Timizing Dimension Qty Descreption
SUPER-STRUCTURE
FINISHING
Wall finishing
50mm thick cement sand screed smoothly finished flooring in mortar mix
(1:3) at basement garage.
2nd- 3rd floor
3-bed room (C-E)
2 1 1 3.60 M.B.ROOM
3.00
21.60 m²
2 1 1 1.60
1.30
4.16 m²
2 -1 1 0.40 deduction for column in MB
0.40
-0.32 m²
2 1 1 2.73 B.ROOM 1
3.30
18.02 m²
2 -1 1 0.18 deduction for column in BR1
0.40
-0.14 m²
2 1 1 3.15 B.ROOM 2
2.00
12.60 m²
2 -1 1 0.40 deduction for column in BR2
0.40
-0.32 m²
2 1 1 7.03 LIVING & DINING ROOM
5.98
84.08 m²
2 -2 1 0.40 deduction for Balcony and column in Living dining column
0.23 on Axis 3
-0.37 m²
2 -1 1 0.40 on Axis 2
0.60
-0.48 m²
2 -1 1 0.40
0.32
-0.26 m² Balcony
2 -1 1 1.18
2.08
-4.91 m²
2 1 1 3.55 CORRIDOR
1.37
9.73 m²
2 1 1 2.98
1.50
8.94 m²
2 1 1 2.90
0.80
4.64 m²
3-bed room (A-B')
2 1 1 4.02 B.ROOM 2
2.20
17.69 m²
2 -1 1 0.40 Deduct column contact area
0.18
-0.14 m²
2 1 1 3.52 M.B.ROOM
3.68
25.91 m²
2 1 1 1.00
0.50
1.00 m²
2 -1 1 0.40 Deduct for column in MB
0.40
-0.32 m²
2 1 1 2.50 CORRIDOR
3.30
16.50 m²
2 1 1 6.00
1.37
16.44 m²
2 -1 1 0.78 Deduct column contact area
0.77
-1.20 m²
2 1 1 3.48 B.ROOM 1
3.48
24.22 m²
2 -1 1 0.40 deduction for column in BR1
0.40
-0.32 m²
2 1 1 4.95 LIVING & DINING ROOM
3.62
35.84 m²
2 -1 1 0.40 deduction for column in Living dining column
0.60
-0.48 m²
2-bed room
2 1 1 5.10 LIVING & DINING ROOM
4.10
41.82 m²
2 -1 1 0.23 deduction for column in Living dining column
0.60
-0.28 m²
2 1 1 5.13 CORRIDOR
0.93
9.54 m²
2 1 1 2.52 M.B.ROOM
5.03
25.35 m²
2 -1 1 0.23 deduction for column in MB
0.23
-0.11 m²
2 -1 1 0.23
0.40
-0.18 m²
2 1 1 4.50 B.ROOM 1
2.15
19.35 m²
2 1 1 3.00 store
1.83
10.98 m²
3-bed room (D'-F)
2 1 1 2.00 B.ROOM 2
4.05
16.20 m²
2 1 1 3.70 M.B.ROOM
3.52
26.05 m²
2 -1 1 0.40 deduction for column in MB
0.40
-0.32 m²
2 1 1 3.12 CORRIDOR
2.48
15.48 m²
2 1 1 6.38
1.57
20.03 m²
2 -1 1 0.38 deduction for column in corridor
0.17
-0.13 m²
2 -1 1 0.60
0.17
-0.20 m²
2 1 1 3.48 B.ROOM 1
3.47
24.15 m²
2 -1 1 0.40 deduction for column in BR1
0.40
-0.32 m²
2 1 1 5.13 LIVING & DINING ROOM
3.61
37.04 m²
2 -1 1 0.40 deduction for column in Living dining
0.60
-0.48 m²
2 1 1 2.69 B/N axis 4-5 & C-D
3.45 ENTRANCE LOBBY
18.56 m²
2 1 1 1.14 B/N axis 4-5 & C-D

0.53 ENTRANCE LOBBY


1.21 m²
4th-8th floor
3-bed room (C-E)
5 1 1 3.60 M.B.ROOM
3.00
54.00 m²
5 1 1 1.60
1.30
10.40 m²
5 -1 1 0.27 deduction for column in MB
0.27
-0.36 m²
5 1 1 2.73 B.ROOM 1
3.30
45.05 m²
5 -1 1 0.12 deduction for column in BR1
0.30
-0.18 m²
5 1 1 3.15 B.ROOM 2
2.00
31.50 m²
5 -1 1 0.30 deduction for column in BR2
0.30
-0.45 m²
5 1 1 7.03 LIVING & DINING ROOM
5.98
210.20 m²
5 -2 1 0.30 deduction for Balcony and column in Living dining column
0.23 on Axis 3
-0.69 m²
5 -1 1 0.27 on Axis 2
0.40
-0.54 m²
5 -1 1 0.27
0.21
-0.28 m² Balcony
5 -1 1 1.18
2.08
-12.27 m²
5 1 1 3.55 CORRIDOR
1.37
24.32 m²
5 1 1 2.98
1.50
22.35 m²
5 1 1 2.90
0.80
11.60 m²
3-bed room (A-B')
5 1 1 4.02 B.ROOM 2
2.20
44.22 m²
5 -1 1 0.27 Deduct column contact area
0.12
-0.16 m²
5 1 1 3.52 M.B.ROOM
3.68
64.77 m²
5 1 1 1.00
0.50
2.50 m²
5 -1 1 0.27 Deduct for column in MB
0.27
-0.36 m²
5 1 1 2.50 CORRIDOR
3.30
41.25 m²
5 1 1 6.00
1.37
41.10 m²
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


5 -1 1 0.78 Deduct column contact area
0.77
-3.00 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


5 1 1 3.48 B.ROOM 1
3.48
60.55 m²
5 -1 1 0.27 deduction for column in BR1
0.27
-0.36 m²
5 1 1 4.95 LIVING & DINING ROOM
3.62
89.60 m²
5 -1 1 0.27 deduction for column in Living dining column
0.40
-0.54 m²
2-bed room
5 1 1 5.10 LIVING & DINING ROOM
4.10
104.55 m²
5 -1 1 0.23 deduction for column in Living dining column
0.40
-0.46 m²
5 1 1 5.13 CORRIDOR
0.93
23.85 m²
5 1 1 2.52 M.B.ROOM
5.03
63.38 m²
5 -1 1 0.23 deduction for column in MB
0.23
-0.26 m²
5 -1 1 0.23
0.40
-0.46 m²
5 1 1 4.50 B.ROOM 1
2.15
48.38 m²
5 1 1 3.00 store
1.83
27.45 m²
3-bed room (D'-F)
5 1 1 2.00 B.ROOM 2
4.05
40.50 m²
5 1 1 3.70 M.B.ROOM
3.52
65.12 m²
5 -1 1 0.27 deduction for column in MB
0.27
-0.36 m²
5 1 1 3.12 CORRIDOR
2.48
38.69 m²
5 1 1 6.38
1.57
50.08 m²
5 -1 1 0.38 deduction for column in corridor
0.17
-0.32 m²
5 -1 1 0.60
0.17
-0.51 m²
5 1 1 3.48 B.ROOM 1
3.47
60.38 m²
5 -1 1 0.27 deduction for column in BR1
0.27
-0.36 m²
5 1 1 5.13 LIVING & DINING ROOM
3.61
92.60 m²
5 -1 1 0.27 deduction for column in Living dining
0.40
-0.54 m²
5 1 1 2.69 B/N axis 4-5 & C-D
3.45 ENTRANCE LOBBY
46.40 m²
5 1 1 1.14 B/N axis 4-5 & C-D

0.53 ENTRANCE LOBBY


3.02 m²
1951.20 m² Total item 7.01
280x30mm Terrazo window sill cut to appropriate size, weathered and mounted on

GROUND FLOOR
1 1 1 4.20 W-1
4.20 ml
1 1 1 2.75 TW-2
2.75 ml
1 1 1 1.10 W-11
1.10 ml
1 1 1 2.40 W-4
2.40 ml
1 1 1 3.10
3.10 ml
FIRST FLOOR
1 1 1 4.20 W-1
4.20 ml
1 1 1 2.75 TW-2
2.75 ml
1 1 1 1.10 W-11
1.10 ml
1 1 1 2.40 W-4
2.40 ml
1 1 1 3.10
3.10 ml
1 1 1 2.59 W-2
2.59 ml
2ND- 8TH FLOOR
7 1 2 2.00 on axis 1 W-5
28.00 ml
7 1 2 0.60 on axis 1' TW-3
8.40 ml
7 1 1 2.00 on axis 2 W-5
14.00 ml
7 1 2 0.80 W-8
11.20 ml
7 1 1 0.60 TW-3
4.20 ml
7 1 1 1.10 W-11
7.70 ml
7 1 2 2.00 on axis 4 W-5
28.00 ml
7 1 2 2.03 W-6
28.42 ml
on axis 5
7 1 1 2.59 W-2
18.13 ml
7 1 1 2.40 W-4'
16.80 ml
on axis A
7 1 1 2.90 W-7
20.30 ml
7 1 2 0.60 TW-3
8.40 ml
on axis C
7 1 1 1.95 W-10
13.65 ml
7 1 1 1.85 W-9
12.95 ml
on axis D'
7 1 1 3.10 W-4
21.70 ml
on axis E
7 1 1 2.00 W-5
14.00 ml
on axis F
7 1 1 2.90 W-7
20.30 ml
7 1 2 0.60 TW-3
8.40 ml
314.24 ml Total item 7.02
20mm thick white terazzo tile bull nosed window sill
bedded in cement mortar 1:3
1ST Floor on Terrace
On Axis A, 4-5
1 1 1 3.30
3.30 ml
On Axis A, 4-5
1 1 1 0.40
0.40 ml
On Axis 5 , A-B
1 1 1 0.60
0.60 ml
On Axis 5 , A-B
1 1 1 1.00
1.00 ml
On Axis B & E ,5-6
1 1 2 3.10
6.20 ml
On Axis B & E ,5-6
1 1 2 0.80
1.60 ml
On Axis 6 ,B-E
1 1 1 15.80
15.80 ml
On Axis 6 ,B-E
1 1 1 2.60
2.60 ml
On Axis 5 ,E-G
1 1 1 9.73
9.73 ml
On Axis 5 ,E-G
1 1 1 1.80
1.80 ml
On Axis G ,2-5
1 1 1 12.30

12.30 ml

On Axis G ,2-5
1 1 1 2.00
2.00 ml
On Axis 2 ,F-G
1 1 1 5.43
5.43 ml
62.76 ml Total item 7.12

377.00 ml Total item 7.02 & 7.12

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


B. Terrazzo copping on verendah, balcony & roof parapet of
size 180*30mm
On Axis 4 b/n A-B'
7 1 1 4.83 BALCONY
33.81 ml
On Axis 4 b/n D'-E
7 1 1 5.03 BALCONY
35.21 ml
On Axis E b/n 1-2
7 1 1 1.42 BALCONY
9.94 ml
On Axis C b/n 1-2
7 1 1 1.40 BALCONY
9.80 ml

88.76 ml Total item 7.02B

Marble flooring to stair case bedded on and including cement sand mortar mix
1:3 and jointsgrouted in appropriate color filler setting coat mortar. Pattern and color of the
tile shall be approved by the architect.

20mm thick to landing.

Basement floor
1 1 1 1.09 STAIR 1
1.14
1.24 m²
1 -1 1 0.45 deduct column area
0.80
-0.36 m²

1 1 1 1.42
1.08
1.53 m²
GRD-8TH FLOOR
9 1 1 1.09 STAIR 1
1.14
11.18 m²
9 -1 1 0.45 deduct column area
0.80
-3.24 m²
9 1 1 1.42
1.08
13.80 m²

1 1 2 2.20 GRD- FLOOR


1.98 STAIR 2
8.71 m²
32.86 m² Total item 20mm thick landing

SHOP STAIR
GRD- FLOOR
1 2 10 1.05 - Tread size 30x340mm
0.34
7.14
Main stair
Basement floor
0.34 - Tread size 30x340mm
1 1 7 1.10 section A-A
2.62
0.34
1 1 5 1.10 section B-B
1.87
0.34
1 1 12 1.15 section C-C
4.69 9.18
GRD-8TH FLOOR
0.34 - Tread size 30x340mm
9 1 7 1.09 section A-A
23.35
0.34
9 1 5 1.10 section B-B
16.83
0.34
9 1 7 1.15 section C-C
24.63 64.81
81.13 Total item tread size 30x340mm

Border marble
0.15 ground floor
1 1 2 3.70 WD-6
1.11
0.15 WD-7
1 1 2 6.40
1.92
0.15 First floor
1 1 2 6.40 WD-7
1.92
0.15
1 1 1 5.40 WD-4
0.81
0.15
1 1 2 3.70 WD-6
1.11
6.87 Total item Boarder Marble

SHOP STAIR
GRD- FLOOR
1 2 10 0.14 Riser size 20x10mm
1.15
3.22
Main Stair
Basement floor
0.34 Riser size 20x10mm
1 1 7 1.10 section A-A
2.62
0.34
1 1 5 1.10 section B-B
1.87
0.34
1 1 12 1.15 section C-C
4.69 9.18

GRD-8TH FLOOR
0.14 Riser size 20x10mm
9 1 7 1.10 section A-A
9.70
0.14
9 1 5 1.10 section B-B
6.93
0.14
9 1 7 1.15 section C-C
10.14
#REF!
39.17 Total item of Riser 20x10mm

Supply and fix 200x150x6 mm white glazed Ceramic wall tiles stuck to wall with
cement mortar mix (1:2) backing and 2 mm joints to be grouted in white cement.

Grd- First floor


2 1 1 5.35 G. TOILET
2.00
21.40 m³
2 1 1 3.57
2.00
14.28 m³
2 1 1 6.60
2.00
26.40 m³
2 1 1 6.35 L. TOILET
2.00
25.40 m³
2 1 1 5.21
2.00
20.84 m³
2 1 1 4.78
2.00
19.12 m³
2nd- 8TH floor
7 1 1 7.00 On axis 2 b/n B-B'
1.80
88.20 m³
7 1 1 7.51 On axis 3 around A-B
1.80
94.63 m³
7 1 1 7.51
1.80
94.63 m³
7 1 1 6.67 On axis 1 around C-D
1.80
84.04 m³
7 1 1 7.30
1.80
91.98 m³
7 1 1 7.51 On axis 3 around E-F
1.80
94.63 m³
7 1 1 7.51
1.80
94.63 m³
KITCHEN
7 1 1 1.10 B/N axis 2 & B-C
1.50
11.55 m²
7 1 1 2.05 B/N axis 3-4 & B-C
1.50
21.53 m²
7 1 1 1.58 B/N axis 3-4 & D-E
1.50
16.59 m²
7 1 1 2.00 B/N axis 1-2 & D'-E
1.50
21.00 m²
840.85 m² Total item 7.04
Ditto but for lift shaft
GRANITE WALL CLADDING
Ground
1 1 1 2.10 W4
3.00
6.30 m²
1 1 -1 2.10 DDT OPENING
1.00
-2.10 m²
first
1 1 1 2.10 W4
3.00
6.30 m²
1 1 -1 2.10 DDT OPENING
1.00
-2.10 m²
2nd to 8th
7 1 1 2.30 W4
3.00
48.30 m²
7 1 -1 2.10 DDT OPENING
1.00
-14.70 m²
42.00 m² Total item 7.05

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


100mm thick precast concrete pavement in concrete class C-15 around the
building open jointed on and including 400mm selected material compacted
fill and 100mm thick redash or equivalent bedding material.
1 1 1 127.77 Around the Building
1.00
127.77 m²
1 -2 1 4.00 deduct ramp area
1.00
-8.00 m²
119.77 m² Total item 7.06 a

half ditch
1 1 1 119.77
119.77 ml

119.77 ml Total item 7.06 b

Apply 42mm thick cement screed in 1:3 cement mortar ratio


to receive porceline ceramic tile, Marble and ceramic tiles.
GRD FLOOR
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 2
56.94 m²
1 -2 1 0.40 deduction for column in GRD floor
0.60
-0.48 m²
1 -2 1 0.40
0.21
-0.17 m²
1 1 1 11.98 B/N axis 1-2' & D'-E
6.00 SHOP 3
71.88 m²
1 -2 1 0.40 deduction for column
0.19
-0.15 m²
1 -2 1 0.20
0.60
-0.24 m²
1 -2 1 0.40
0.18
-0.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 SHOP 1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 6.03
5.02
30.27 m²

1 1 1 5.80 B/N axis 3-4 & E-F


5.15 SHOP 4
29.87 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 6.03 B/N axis 3-4 & D'-E
5.14 SHOP 5
30.99 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.23
0.22
-0.05 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 5.01 B/N axis 3-4 & C-D
3.99 SHOP 6
19.99 m²
1 -1 1 0.25 deduction for column
0.18
-0.05 m²
FIRST FLOOR
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 7
56.94 m²
1 -2 1 0.40 deduction for column
0.60
-0.48 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 9.49 B/N axis 1-2' & D'-E
6.00 SHOP 8
56.94 m²
1 -2 1 0.60 deduction for column
0.20
-0.24 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 2.69
6.00
16.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 Café & Restaurant #1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 5.92 B/N axis 2-3 & E-F
5.15 SHOP 9
30.49 m²
1 -2 1 0.60 deduction for column
0.60
-0.72 m²
1 1 1 15.72 B/N axis 3-4 & C'-F
5.01 Café & Restaurant #2
78.76 m²
1 -2 1 0.25 deduction for column
0.60
-0.30 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -2 1 0.50
0.60
-0.60 m²
1 -1 1 0.17
0.40
-0.07 m²
1 1 1 2.91 B/N axis 3-4 & B-C'
8.18 SHOP 10
23.80 m²
1 -1 1 0.18
0.60
-0.11 m²
CORRIDOR
1 1 1 6.06 FOR GROUND FLOOR
2.49
15.09 m²
1 1 1 5.18
1.00
5.18 m²
1 1 1 7.84 Entrance lobby
4.76
37.32 m²
1 1 1 1.50
0.29
0.44 m²
1 -1 1 0.26 Deduction for column
0.40
-0.10 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.35
0.17
-0.06 m²
1 -1 1 0.60
0.29
-0.17 m²
Verenda 1-3
1 1 1 3.55 B/N axis 4-5 & A-B
6.15
21.83 m²
1 1 1 4.63 B/N axis 4-6 & B-B'
7.45
34.49 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 4.63 B/N axis 4-6 & D'-E
7.45
34.49 m²
1 1 1 11.53 B/N axis 4-5 & E-G
3.55
40.93 m²
1 1 1 10.45 B/N axis 2-4 & F-G
5.28
55.18 m²
1 1 1 3.45 B/N axis 4-5 & C-D
2.69 APARTMENT ENTRANCE LOBBY
9.28 m²
1 1 1 1.14 B/N axis 4-5 & C-D
0.53 APARTMENT ENTRANCE LOBBY
0.60 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


1 1 1 12.26 FOR FIRST FLOOR
2.49
30.53 m²
1 1 1 8.18 lobby
1.93
15.79 m²
1 -1 1 0.60 Deduction for column
0.27
-0.16 m²
1 -2 1 0.46
0.27
-0.25 m²
1 1 1 3.45 B/N axis 4-5 & C-D
2.69 APARTMENT ENTRANCE LOBBY
9.28 m²
1 1 1 1.14 B/N axis 4-5 & C-D
0.53 APARTMENT ENTRANCE LOBBY
0.60 m²
CAFETERIA TERACE
1 1 1 3.55 B/N axis 4-5 & A-B
6.15
21.83 m²
1 1 1 4.63 B/N axis 4-6 & B-B'
7.45
34.49 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 4.63 B/N axis 4-6 & D'-E
7.45
34.49 m²
1 1 1 11.53 B/N axis 4-5 & E-G
3.55
40.93 m²
1 1 1 10.45 B/N axis 2-4 & F-G
5.28
55.18 m²
1172.19 m² Total item 7.07

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Supply and fix 8mm thick non slippery porcelain ceramic floor tiles. Price includes tiles,
adhesives glue, cross spacers, sealant, and all accessories. Size, pattern, quality and color
shall be approved by the architect.
GRD FLOOR
Verendah
1 1 1 12.00 B/N axis 1-2 & A-B
7.00
84.00 m²
1 1 1 6.00 B/N axis 1-2 & E-F
7.00
42.00 m²
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 2
56.94 m²
1 -2 1 0.40 deduction for column in GRD floor
0.60
-0.48 m²
1 -2 1 0.40
0.21
-0.17 m²
1 1 1 11.98 B/N axis 1-2' & D'-E
6.00 SHOP 3
71.88 m²
1 -2 1 0.40 deduction for column
0.19
-0.15 m²
1 -2 1 0.20
0.60
-0.24 m²
1 -2 1 0.40
0.18
-0.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 SHOP 1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 6.03
5.02
30.27 m²

1 1 1 5.80 B/N axis 3-4 & E-F


5.15 SHOP 4
29.87 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 6.03 B/N axis 3-4 & D'-E
5.14 SHOP 5
30.99 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.23
0.22
-0.05 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 5.01 B/N axis 3-4 & C-D
3.99 SHOP 6
19.99 m²
1 -1 1 0.25 deduction for column
0.18
-0.05 m²
CORRIDOR
1 1 1 6.06 FOR GROUND FLOOR
2.49
15.09 m²
1 1 1 5.18
1.00
5.18 m²
1 1 1 7.84 Entrance lobby
4.76
37.32 m²
1 1 1 1.50
0.29
0.44 m²
1 -1 1 0.26 Deduction for column
0.40
-0.10 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.35
0.17
-0.06 m²
1 -1 1 0.60
0.29
-0.17 m² 476.86 m²

FIRST FLOOR
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 7
56.94 m²
1 -2 1 0.40 deduction for column
0.60
-0.48 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 9.49 B/N axis 1-2' & D'-E
6.00 SHOP 8
56.94 m²
1 -2 1 0.60 deduction for column
0.20
-0.24 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 2.69
6.00
16.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 Café & Restaurant #1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 5.92 B/N axis 2-3 & E-F
5.15 SHOP 9
30.49 m²
1 -2 1 0.60 deduction for column
0.60
-0.72 m²
1 1 1 15.72 B/N axis 3-4 & C'-F
5.01 Café & Restaurant #2
78.76 m²
1 -2 1 0.25 deduction for column
0.60
-0.30 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -2 1 0.50
0.60
-0.60 m²
1 -1 1 0.17
0.40
-0.07 m²
1 1 1 2.91 B/N axis 3-4 & B-C'
8.18 SHOP 10
23.80 m²
1 -1 1 0.18
0.60
-0.11 m²
CORRIDOR
1 1 1 12.26 FOR FIRST FLOOR
2.49
30.53 m²
1 1 1 8.18 lobby
1.93
15.79 m²
1 -1 1 0.60 Deduction for column
0.27
-0.16 m²
1 -2 1 0.46
0.27
-0.25 m² 361.43 m²
CAFETERIA TERACE
1 1 1 3.55 B/N axis 4-5 & A-B
6.15
21.83 m²
1 1 1 4.63 B/N axis 4-6 & B-B'
7.45
34.49 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 4.63 B/N axis 4-6 & D'-E
7.45
34.49 m²
1 1 1 11.53 B/N axis 4-5 & E-G
3.55
40.93 m²
1 1 1 10.45 B/N axis 2-4 & F-G
5.28
55.18 m²
1 1 -1 5.25 ddt column
1.00
-5.25 m² 214.82 m²

1053.11 m² Total item 7.08

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Supply and fix 10cm high porcelain skirting
Ground floor
B/N axis 1-2' & C-D
1 1 1 20.03 SHOP 2
20.03 ml
B/N axis 1-2' & D'-E
1 1 1 28.85 SHOP 3
28.85 ml
B/N axis 2-3 & A-B
1 1 1 12.77 SHOP 1
12.77 ml
B/N axis 3-4 & E-F
1 1 1 16.49 SHOP 4
16.49 ml
B/N axis 3-4 & D'-E
1 1 1 19.35 SHOP 5
19.35 ml
B/N axis 3-4 & C-D
1 1 1 9.17 SHOP 6
9.17 ml
1 1 1 11.76 CORRIDOR
11.76 ml
VERENDA
1 1 1 12.60 On Axis 1-2 & A-B
12.60 ml
1 1 1 6.60 On Axis 1-2 & E-F
6.60 ml
First floor
B/N axis 1-2' & C-D
1 1 1 20.03 SHOP 7
20.03 ml
B/N axis 1-2' & D'-E
1 1 1 20.03 SHOP 8
20.03 ml
B/N axis 2-3 & A-B
1 1 1 15.92 Café & Restaurant #1
15.92 ml
B/N axis 2-3 & E-F
1 1 1 9.64 SHOP 9
9.64 ml
B/N axis 3-4 & C-F
1 1 1 22.86 Café & Restaurant #2
22.86 ml
B/N axis 3-4 & B-C
1 1 1 11.35 SHOP 10
11.35 ml
1 1 1 6.88 CORRIDOR
6.88 ml

CAFETERIA TERACE
1 1 1 9.65 on axis A,5 b/n 4-5 , A-B
9.65 ml
B/N axis 5-6 & B'-D'
1 1 1 25.90
25.90 ml
B/N axis 5-6 & B'-D'
1 1 1 30.81
30.81 ml 66.36 ml
1 1 1 16.24 B/N axis 4-5 & B'-D'
16.24 ml
189.31 ml
326.93 ml Total item 7.08
Supply and fix 8mm thick non slippery ceramic floor tiles. Price includes tiles, adhesives
glue, cross spacers, sealant, and all accessories. Size, pattern, quality and color shall be
approved by the architect.

Grnd- 1st Floor


Gent's Toilet
2 1 1 1.70 B/N axis 2-3 & B-B'
1.27
4.32 m²
2 1 1 1.70
0.90
3.06 m²
2 1 1 2.85
2.33
13.28 m²
2 -1 1 0.40 Deduct Column and HCB Contact Area
0.60
-0.48 m²
2 -1 1 0.30
0.30
-0.18 m²
2 -1 1 0.30
0.40
-0.24 m²
2 -1 1 0.40
0.10
-0.08 m²
2 1 1 1.70 Lent's Toilet
1.09
3.71 m²
2 1 1 1.31
1.70
4.45 m²
2 1 1 1.70
2.60
8.84 m²
2 -1 1 0.60 Deduct Column Contact Area
0.25
-0.30 m² 36.38 m²
2ND-8TH FLOOR
7 1 1 2.07 BATHROOM
1.78 B/N axis 2 & B-B'
25.79 m²
7 -1 1 0.30 Deduct pipe area
0.20
-0.42 m²
7 1 1 2.58 B/N axis 3 & A-B'
1.48
26.73 m²
7 1 1 2.58
1.42
25.65 m²
7 -1 1 0.50 Deduct column and pipe area
0.40
-1.40 m²
7 -2 1 0.30
0.30
-1.26 m²
7 1 1 2.20 B/N axis 1 & C-D'
1.47
22.64 m²
7 1 1 2.20
1.47
. 22.64 m²
7 -1 1 0.50 Deduct column and pipe area
0.35
-1.23 m²
7 -2 1 0.40
0.15
-0.84 m²
7 1 1 2.58 B/N axis 3 & E-F
1.42
25.65 m²
7 1 1 2.58
1.47
26.55 m²
7 -1 1 0.50 Deduct column and pipe area
0.40
-1.40 m²
7 -2 1 0.30
0.30
-1.26 m²
KITCHEN
7 1 1 3.15 B/N axis 2 & B-C
2.07
45.64 m²
7 -2 1 0.60 Deduct Column Contact Area
0.40
-3.36 m²
7 1 1 3.23 B/N axis 3-4 & B-C
3.50
79.14 m²
7 -1 1 0.40 Deduct Pipe Area
0.35
-0.98 m²
7 1 1 3.18 B/N axis 3-4 & D-E
3.46
77.02 m²
7 1 1 0.60 Deduct column and pipe area
0.35
1.47 m²
7 -1 1 0.40
0.30
-0.84 m²
7 1 1 2.25 B/N axis 1-2 & D'-E
2.70
42.53 m²
BALCONY
7 1 2 4.23 B/N axis 4-5 & A-C , D'-F
1.10
65.14 m²
7 1 1 1.75 B/N axis 1-2 & C-C'
1.80
22.05 m²
7 1 1 1.10 B/N axis 1-2 & D'-E
1.80
13.86 m²
7 1 1 0.70
0.20
0.98 m²
510.49 m²
546.87 m² Total item 7.08
Supply and fix 10cm high ceramic skirting
2ND-8TH FLOOR
BALCONY
7 1 2 5.83 B/N axis 4-5 & A-C , D'-F
81.62
7 1 1 4.90 B/N axis 1-2 & C-C'
34.30
7 1 1 3.02 B/N axis 1-2 & D'-E
21.14
KITCHEN
7 1 1 10.45 B/N axis 2 & B-C
73.15
7 1 1 13.33 B/N axis 3-4 & B-C
93.31
7 1 1 13.92 B/N axis 3-4 & D-E
97.44
7 1 1 9.20 B/N axis 1-2 & D'-E
64.40
465.36 Total item 7.09

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Supply and fix 20mm thick marble floor tiles. Price shall include cement
screed, mirror polishing and all necessary works.
GROUND FLOOR
1 1 1 2.91 B/N axis 4-5 & C-D
3.45 APARTMENT ENTRANCE LOBBY
10.04 m²
1 1 1 1.40 B/N axis 4-5 & C-D
0.85 APARTMENT ENTRANCE LOBBY
1.19 m²
VERENDA
1 1 1 10.78 B/N axis 4-5 & A-C

3.60
38.81 m²
1 1 1 10.78 B/N axis 4-5 & D'-F

3.60
38.81 m²
1 1 1 18.22 B/N axis 5-6 & B-E

3.70
67.41 m² 156.26 m²
First floor
1 1 1 2.91 B/N axis 4-5 & C-D

3.45 APARTMENT ENTRANCE LOBBY


10.04 m²
1 1 1 1.40 B/N axis 4-5 & C-D

0.85 APARTMENT ENTRANCE LOBBY


1.19 m² 167.49 m²
2nd- 8TH floor
7 1 1 2.91 B/N axis 4-5 & C-D

3.45 ENTRANCE LOBBY


70.28 m²
7 1 1 1.40 B/N axis 4-5 & C-D

0.85
8.33 m²
7 1 1 5.92 B/N axis 2'-4 & C-D

6.85 LOBBY
283.86 m²
7 1 -1 0.58 DDT COL

0.60
-2.44 m²
360.03 m²
527.52 m² Total item 7.10
Supply and fix 10cm high Marble skirting
GROUND FLOOR
B/N axis 4-5 & C-D
1 1 1 6.03 APARTMENT ENTRANCE LOBBY
6.03
VERENDA
1 1 1 5.70 B/N axis 4-5 & A-C
5.70
1 1 1 17.44 B/N axis 4-5 & D'-F
17.44
1 1 1 5.70 B/N axis 5-6 & B-E
5.70
1ST FOOR
1 1 1 6.03 APARTMENT ENTRANCE LOBBY
6.03
2nd- 8TH floor
7 1 1 19.46
136.22

Staircase Skirting
Shop Stair
1 1 1 6.00 Ground floor
6.00 Staircase skirting
1 1 1 6.16
6.16 landing skirting
Main Stair
1 1 1 5.25 Basement floor
5.25 Staircase skirting
1 1 1 4.44
4.44 landing skirting
Gnd-8th floor
9 1 1 5.36 Staircase skirting
48.24
9 1 1 4.24 landing skirting
38.16
285.37 Total item 7.11

Ditto but 30x3cm marble threshold bedded on cement mortar (1:3) ratio. Price shall
include cement screed, mirror polishing and all necessary works.

7 1 4 0.30 2nd- 8TH floor


1.20
10.08 Total item 7.13

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Gypsum Plastering
Finishing for Lobby and Corridor at Residential Houses
a) Internal Plastered vertical surface
2nd- 3rd floor
2 1 1 6.25 On axis C b/N 2'-4
2.80
35.00 m²
2 -1 1 2.80 Deduction
1.20 D-6
-6.72 m²
2 -1 1 1.50 W-12
0.80
-2.40 m²
2 1 1 6.02 On axis 2' b/N C-D
3.02
36.36 m²
2 -1 1 2.90 Deduction
1.20 D-6
-6.96 m²
2 1 1 6.25 On axis D b/N 2'-4
2.80
35.00 m²
2 -1 1 2.80 Deduction
1.20 D-6
-6.72 m²
2 -1 1 2.80 Deduction
D-7
1.20
-6.72 m²
2 1 1 5.96 On axis 4 b/N B'-D'
2.80
33.38 m²
2 -1 1 5.64
2.80
-31.58 m²
2 -2 1 2.69 Deduction
2.80 WD-2
-30.13 m²
2 1 1 3.10 On axis D'/4-5
2.80
17.36 m²
2 -1 1 3.10 Deduction
1.50 W-4
-9.30 m²
2 1 1 5.34 On axis 5 b/N B'-D'
2.80
29.90 m²
2 -1 1 2.69 Deduction
1.80 W-2
-9.68 m²
2 1 1 3.65 Around duct
2.80
20.44 m²
4th- 8TH floor
5 1 1 6.45 On axis C b/N 2'-4
2.80
90.30 m²
5 -1 1 2.80 Deduction
1.20 D-6
-16.80 m²
5 -1 1 1.50 W-12
0.80
-6.00 m²
5 1 1 6.02 On axis 2' b/N C-D
3.02
90.90 m²
5 -1 1 2.90 Deduction
1.20 D-6
-17.40 m²
5 1 1 6.45 On axis D b/N 2'-4
2.80
90.30 m²
5 -1 1 2.80 Deduction
1.20 D-6
-16.80 m²
5 -1 1 2.80 Deduction
D-7
1.20
-16.80 m²
5 1 1 5.96 On axis 4 b/N B'-D'
2.80
83.44 m²
5 -1 1 5.64
2.80
-78.96 m²
5 -2 1 2.69 Deduction
2.80 WD-2
-75.32 m²
5 1 1 3.10 On axis D'/4-5
2.80
43.40 m²
5 -1 1 3.10 Deduction
1.50 W-4
-23.25 m²
5 1 1 5.54 On axis 5 b/N B'-D'
2.80
77.56 m²
5 -1 1 2.69 Deduction
1.80 W-2
-24.21 m²
5 1 1 3.65 Around duct
2.80
51.10 m²
348.69 m²
Exposed Columns
Second- Third Floor
2 2 1 2.80 ON AXIS 3 C & D
2.80
31.36 m²
2 2 1 1.30
0.20
1.04 m²
2 1 1 0.45 ON AXIS 4 & D'
2.80
2.52 m²
2 1 1 0.40
0.20
0.16 m²
2 1 1 0.95 On axis 5 C'-D'
2.80
5.32 m²
2 1 1 0.80
0.20
0.32 m²
Fourth- Eigth Floor
5 2 1 1.60 ON AXIS 3 C & D
2.80
44.80 m²
5 2 1 0.70
0.20
1.40 m²
5 1 1 0.25 ON AXIS 4 & D'
2.80
3.50 m²
5 1 1 0.20
0.20
0.20 m²
5 1 1 0.55 On axis 5 C'-D'
2.80
7.70 m²
5 1 1 0.40
0.20
0.40 m²
98.72 m² Total item
447.41 m² Total item of 7.16A

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


b) Plastered Soffit
lobby
6 1 1 5.92 on Axis 2'-4, C-D
6.60
234.43 m³ on Axis 4-5, C-D
6 1 1 2.69
3.45
55.68 m³
6 1 1 0.53
1.14
3.63 m³ 293.74 m³
Deduction For Columns
2nd- 3rd Floor
2 -2 1 0.35 On axis 3 b/N C-D
0.60
-0.84 m²
2 -1 1 0.05 On axis 5 b/N B'-D'
0.05
-0.01 m²
2 -1 1 0.35 On axis 5 D'
0.35
-0.25 m²
4th - 8th floor
2 -2 1 0.15 On axis 3 b/N C-D
0.40
-0.24 m²
2 -1 1 0.05 On axis 5 b/N B'-D'
0.05
-0.01 m²
2 -1 1 0.15 On axis 5 D'
0.15
-0.05 m²
Balcony
7 1 1 4.43 On Axis 4 b/n A-B'
1.10
34.11 m²
7 1 1 4.43 On Axis 4 b/n D'-E
1.10
34.11 m²
Balcony @ roof level
1 1 1 4.43 On Axis 4 b/n A-B'
1.10
4.87 m²
1 1 1 4.43 On Axis 4 b/n D'-E
1.10
4.87 m²
main stair case
Basement-8th Floor
10 1 1 2.40 SECTION A-A
1.03 sofit
24.72 m³
10 1 1 1.03 Landing 1
1.27
13.08 m³
10 1 1 2.40 side
0.22
5.28 m³
1 7 0.5 0.29 Riser side
0.15
0.15 m³
SECTION B-B
10 1 1 1.93 sofit
1.03
19.88 m³
10 1 1 1.27 Landing 1
1.03
13.08 m³
10 1 1 1.93 side
0.22
4.25 m³
1 7 0.5 0.29 Riser side
0.15
0.15 m³
SECTION C-C
10 1 1 2.00 sofit
1.15
23.00 m³
10 1 1 2.00 side
0.22
4.40 m³
1 5 0.5 0.29 Riser side
0.15
0.11 m³

478.40 m² Total to item of 7.16 B


Finishing for Lobby and Corridor at Shops
a) Internal Plastered vertical surface
Grnd FLOOR
1 1 1 10.80 On axis 1 b/n C-E
2.80
30.24 m²
1 1 1 4.20 On axis 2 b/n A-B
2.80
11.76 m²
1 -1 1 4.20 Deduction
1.80 W-1
-7.56 m²
1 1 1 2.20 On axis 2 b/n B-C
2.80
6.16 m²
1 -1 1 1.10 Deduction
1.80 W-11
-1.98 m²
1 1 1 10.43 On axis 2 b/n E-G
2.80
29.20 m²
1 2 1 10.80 On axis 3 b/n D-F
2.80
60.48 m²
1 1 1 7.54 On axis 4 b/n B'-D'
2.80
21.11 m²
1 1 1 5.64
2.80
15.79 m²
1 1 1 6.74 On axis 5 b/n B'-D'
2.80
18.87 m²
1 -1 1 2.40 Deduction
1.80 W-4
-4.32 m²
1 1 1 1.40 On axis A b/n 2-4
2.80
3.92 m²
1 1 2 4.39 b/n axis C & 2-3
2.80
24.58 m²
1 1 2 13.33 On axis D b/N 1-4
2.80
74.65 m²
1 1 1 3.10 On axis D' b/N 4-5
2.80
8.68 m²
1 -1 1 3.10 Deduction
1.50 W-4'
-4.65 m²
1 1 1 8.80 On axis E b/n 1-4
2.80
24.64 m²
1 1 1 4.40 On axis F b/n 3-4
2.80
12.32 m²
1 1 1 13.10 On axis G b/n 2-4
2.80
36.68 m²
1 1 1 5.23 On Axis B-B' & 2-3
3.02 toilet area
15.79 m²
1 1 1 2.85 On Axis C b/n 4-5
3.02 duct area
8.61 m²
1 1 1 1.55
2.80
4.34 m²
Exposed Columns
1 1 1 2.45 On axis 1 b/n C-E
2.80
6.86 m²
1 1 1 0.54
2.80
1.51 m²
1 1 1 6.05 On axis 2 b/n A-G
2.80
16.94 m²
1 1 1 0.95
2.80
2.66 m²
1 1 1 6.09 On axis 3 b/n A-G
2.80
17.05 m²
1 1 1 1.20
2.80
3.36 m²
1 1 1 7.05 On axis 4 b/n A-G
2.80
19.74 m²
1 1 1 2.97
2.80
8.32 m²
1 1 1 2.30 On axis 5 b/n A-G
2.80
6.44 m²
1 1 1 1.10
2.80
3.08 m²
1 1 1 0.50 On axis 6 b/n B-E
2.80
1.40 m²
1 1 1 0.50
2.80
1.40 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


FIRST FLOOR
1 1 1 10.80 On axis 1 b/n C-E
2.80
30.24 m²
1 1 1 4.20 On axis 2 b/n A-B
2.80
11.76 m²
1 -1 1 4.20 Deduction
1.80 W-1
-7.56 m²
1 1 1 2.20 On axis 2 b/n B-C
2.80
6.16 m²
1 -1 1 1.10 Deduction
1.80 W-11
-1.98 m²
1 2 1 5.40 On axis 3 b/n E-F
2.80
30.24 m²
1 1 1 3.65
2.80
10.22 m²
1 1 1 8.07 On axis 4 b/n B'-D'
2.80
22.60 m²
1 1 1 5.67
2.80
15.88 m²
1 1 1 6.74 On axis 5 b/n B'-D'
2.80
18.87 m²
1 -1 1 2.40 Deduction
1.80 W-4
-4.32 m²
1 -1 1 2.59
1.80 W-2
-4.66 m²
1 1 1 1.40 On axis A b/n 2-4
2.80
3.92 m²
1 2 1 3.21 On axis B b/n 3-4
2.80
17.98 m²
1 2 1 4.39 b/n axis C & 2-3
2.80
24.58 m²
1 2 1 5.15 b/n axis C - D & 3-4
3.00
30.90 m²
1 2 1 8.57 b/n axis D & 1-3
2.80
47.99 m²
7 1 1 3.10 On axis D' b/N 4-5
2.80
60.76 m²
1 -1 1 3.10 Deduction
1.50 W-4
-4.65 m²
1 2 1 2.17 b/n axis E & 2-3
2.80
12.15 m²
1 1 1 1.40 On axis F b/n 2-4
2.80
3.92 m²
1 1 2 5.23 On Axis B-B' & 2-3
3.00 toilet area
31.38 m²
1 1 1 2.85 On Axis C b/n 4-5
3.02 duct area
8.61 m²
1 1 1 1.55
2.80
4.34 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Exposed Columns
1 1 1 2.45 On axis 1 b/n C-E
2.80
6.86 m²
1 1 1 0.54
2.80
1.51 m²
1 1 1 5.60 On axis 2 b/n A-F
3.00
16.80 m²
1 1 1 0.80
2.80
2.24 m²
1 1 1 5.64 On axis 3 b/n A-F
2.80
15.79 m²
1 1 1 1.05
2.80
2.94 m²
1 1 1 5.15 On axis 4 b/n A-F
2.80
14.42 m²
1 1 1 1.80
2.80
5.04 m²
1 1 1 0.85 On axis 5 b/n B'-D'
2.80
2.38 m²
1 1 1 0.25
2.80
0.70 m²
916.09 m² Total item 7.16 a

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


b) Plastered Soffit
Ceilling gypsum plastering
GROUND FLOOR
Solid Slab
1 1 1 5.93 B/ N Axis 4-5 & A-B
3.45
20.44 m²
1 1 1 4.25 B/ N Axis B-B' & 4-5
3.45
14.66 m²
1 1 1 2.91 B/ N Axis C-C' & 4-5
1.08
3.14 m²
1 1 1 3.22
1.09
3.51 m²
1 1 1 3.00
1.28
3.84 m²
1 1 1 4.46 B/ N Axis D'-E & 4-5
3.45
15.37 m²
1 1 1 5.93 B/ N Axis E-F & 4-5
3.45
20.44 m²
1 1 1 12.70 B/ N Axis F-G & 2-5
5.08
64.52 m²
1 1 1 5.76 B/ N Axis B-C & 5-6
3.60
20.72 m²
1 1 1 3.60 B/ N Axis C-D & 5-6
6.00
21.60 m²
1 1 1 5.74 B/ N Axis D-E & 5-6
3.54
20.32 m²
Ribbed Slab
1 1 1 5.87 B/N axis 1-2' & C-D
7.10 SHOP 2
41.68 m³
1 1 1 2.17
5.80
12.59 m³
1 1 1 5.86 B/N axis 1-3 & D-E
7.10 SHOP 3
41.61 m³
1 1 1 5.75
4.46
25.62 m³
1 1 1 5.85 B/N axis 2-4 & A-B
4.84 SHOP 1
28.31 m³
1 1 1 5.10
4.47
22.80 m³
1 1 1 4.95 B/N axis 3-4 & E-F
5.75 SHOP 4
28.46 m³
1 1 1 4.95 B/N axis 3-4 & D-E
5.93 SHOP 5
29.35 m³
1 1 1 3.99 B/N axis 3-4 & C-D
4.76 SHOP 6
18.99 m³
CORRIDOR
FOR GROUND FLOOR
1 1 1 5.92 B/n axis 2-3 & C-D
2.40
14.21 m³
1 1 1 1.68 B/n axis 3-4 & C-D
4.80
8.04 m³
1 1 1 7.34 Entrance lobby
4.81 B/n axis 3-4 & B-C
35.27 m³
Ramp
1 1 1 4.88 B/n axis 2-3 & E-F
12.95
63.20 m³
VERENDA
1 1 1 3.35 B/N axis 4-5 & A-C
10.63
35.61 m³
1 1 1 3.35 B/N axis 4-5 & D'-F
10.63
35.61 m³
1 1 1 17.45 B/N axis 5-6 & B-E
3.60
62.82 m³
Toilet
1 1 1 1.40 B/N axis 2-3 & A'-B
4.48
6.28 m³
1 1 1 1.00 B/N axis 2-3 & B-B'
2.75
2.75 m³
1 1 1 2.85
2.33
6.64 m³
1 1 1 1.70
2.60
4.42 m³
Exposed beam
Internal
1 1 1 10.80 ON XIS 1-(C-E)
0.22 FB-1
2.38 m²
Bottom
1 1 1 10.80 ON XIS 1-(C-E)
0.05 FB-1
0.54 m²
Internal
1 1 1 10.55 ON AXIS-2 (A-C)
0.22 FB-2
2.32 m²
1 2 1 10.80 ON AXIS-2 (C-E)
0.22 FB-2
4.75 m²
1 1 1 5.40 ON AXIS-2 (E-F)
0.22 FB-2
1.19 m²
1 1 1 5.03 ON AXIS-2 (F-G)
0.22 FB-2
1.11 m²
Bottom
1 1 1 8.65 ON AXIS-2 (A-C)
0.25 FB-2
2.16 m²
1 1 1 10.80 ON AXIS-2 (C-E)
0.25 FB-2
2.70 m²
1 1 1 10.43 ON AXIS-2 (E-G)
0.05 FB-2
0.52 m²
Internal
1 2 1 31.78 ON AXIS -3 (A-G)
0.22 FB-3
13.98 m²
1 2 1 5.03 ON AXIS -3 (A-G)
0.22 FB-3
2.21 m²
Bottom
1 1 1 17.83 ON AXIS -3 (A-G)
0.25 FB-3
4.46 m²
1 1 1 13.95 ON AXIS -3 (A-G)
0.05 FB-3
0.70 m²
Internal
1 1 1 9.68 ON AXIS 4-(A-B')
0.22 FB-4
2.13 m²
bottom
1 1 1 9.68 ON AXIS 4-(A-B')
0.25 FB-4
2.42 m²
Internal
1 2 1 5.44 ON AXIS 4 -(C'-D')
0.22 FB-5
2.39 m²
1 2 1 9.68 ON AXIS 4 -(D'-G)
0.22 FB-5
4.26 m²
1 2 1 5.03 ON AXIS 4 -(D'-G)
0.22 FB-5
2.21 m²
bottom
1 1 1 14.71 ON AXIS 4 -(D'-G)
0.25 FB-5
3.68 m²
1 1 1 5.44 ON AXIS 4 -(D'-G)
0.05 FB-5
0.27 m²
Internal
1 1 1 29.88 ON AXIS 5 - (A-G)
0.22 FB-6
6.57 m²
1 1 1 9.01 ON AXIS 5 - (A-G)
0.22 FB-6
1.98 m²
bottom
1 1 1 30.93 ON AXIS 5 - (A-G)
0.25 FB-6
7.73 m²
1 1 1 3.35 ON AXIS 5 - (A-G)
0.05 FB-6
0.17 m²
Internal
1 1 1 17.53 ON AXIS 6 -(B-E )
0.22 FB-7
3.86 m²
Bottom
1 1 1 17.53 ON AXIS 6 -(B-E )
0.25 FB-7
4.38 m²
Internal
1 1 1 12.20 ON AXIS A -(5-2 )
0.22 FB-8
2.68 m²
1 1 1 13.10 ON AXIS G -(5-2 )
0.22 FB-8
2.88 m²
Internal
1 2 1 4.40 ON AXIS F -(3-2 )
0.22 FB-8
1.94 m²
1 2 1 8.10 ON AXIS F -(3-5 )
0.22 FB-8
3.56 m²
Bottom
1 1 1 10.40 ON AXIS A-(5-2 )
0.25 FB-8
2.60 m²
1 1 1 1.40 ON AXIS A-(5-2 )
0.05 FB-8
0.07 m²
1 1 1 7.80 ON AXIS F - (5-2 )
0.25 FB-8
1.95 m²
1 1 1 4.40 ON AXIS F - (5-2 )
0.05 FB-8
0.22 m²
1 1 1 11.70 ON AXIS G-(5-2 )
0.25 FB-8
2.93 m²
1 1 1 1.40 ON AXIS G-(5-2 )
0.05 FB-8
0.07 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc
Timizing Dimension Qty Descreption
Internal
1 2 1 8.35 ON AXIS B -(4-2)
0.22 FB-9
3.67 m²
1 2 1 3.40 ON AXIS B -(5-4)
0.22 FB-9
1.50 m²
1 2 1 6.95 ON AXIS B -(6-4)
0.22 FB-9
3.06 m² 11.75
Bottom
1 1 1 15.30 ON AXIS B -(6-2)
0.25 FB-9
3.83 m²
Internal
1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.50 FB-10
2.47 m²
Bottom
1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.05 FB-10
0.25 m²
Internal
1 1 1 6.40 ON AXIS C -(1-2)
0.22 FB-11
1.41 m²
1 2 1 4.39 ON AXIS C -(3-2)
0.22 FB-11
1.93 m²
1 2 1 4.76 ON AXIS C -(3-4)
0.22 FB-11
2.09 m²
Bottom
1 1 1 11.16 ON AXIS C -(1-2 & 3-4)
0.25 FB-11
2.79 m²
1 1 1 4.40 ON AXIS C -(2-3)
0.05 FB-11
0.22 m²
Internal
1 2 2 6.75 b/n axis C-D and D-E & (2-1)
0.22 FB-12
5.94 m²
Bottom
1 2 1 6.75 b/n axis C-D and D-E & (2-1)
0.25 FB-12
3.38 m²
Internal
1 1 2 15.55 ON AXIS D -(4-1)
0.22 FB-13
6.84 m²
Bottom
1 1 1 2.22 ON AXIS D -(4-1)
0.25 FB-13
0.56 m²
1 1 1 13.33 ON AXIS D -(4-1)
0.05 FB-13
0.67 m²
Internal
1 1 1 21.70 ON AXIS E-(6-1)
0.22 FB-14
4.77 m²
Internal
1 1 1 6.40 ON AXIS E-(1-2)
0.22 FB-14
1.41 m²
1 1 2 8.80 ON AXIS E-(2-4)
0.22 FB-14
3.87 m²
1 1 2 3.40 ON AXIS E-(4-5)
0.22 FB-14
1.50 m²
1 1 2 3.55 ON AXIS E-(5-6)
0.22 FB-14
1.56 m²
Bottom
1 1 1 13.35 ON AXIS E-(1-2 & 4-6)
0.25 FB-14
3.34 m²
1 1 1 8.80 ON AXIS E-(2-4)
0.05 FB-14
0.44 m²
Internal
1 1 2 6.65 ON AXIS D' - (6 -4)
0.22 FB-15
2.93 m²
Bottom
1 1 1 6.65 ON AXIS D' - (6 -4)
0.25 FB-15
1.66 m²
1 1 1 3.10 ON AXIS D' - (6 -4)
0.05 FB-15
0.16 m²
Internal
1 1 2 3.40 ON AXIS C' (5-4)
0.22 FB-16
1.50 m²
Bottom
1 1 1 3.40 ON AXIS C' (5-4)
0.25 FB-16
0.85 m²
Internal
1 1 2 3.55 ON AXIS C ( 6-5)
0.22 FB-17
1.56 m²
Bottom
1 1 1 3.55 ON AXIS C( 6-5)
0.25 FB-17
0.89 m²
Internal
1 1 2 1.25 ON AXIS C (5-4)
0.22 FB-18
0.55 m²
Internal
1 1 1 1.25 ON AXIS C (5-4)
0.05 FB-18
0.06 m²

Deduct for Columns contact Areas


Ground Floor
1 20 -1 0.35
0.35
-2.45 m³
1 16 -1 0.05
0.05
-0.040 m³
First Floor
Solid Slab
1 1 1 5.95 ON Axis 1 B/N C-D
0.85
5.06 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20
10.63 m²
1 1 1 3.45 ON Axis 4-5 B/N B'-C'
2.69
9.28 m²
1 1 1 1.14 ON Axis 4-5 B/N B'-C'
0.53
0.60 m²
Ribbed Slab
1 1 1 5.78 B/N axis 1-2' & C-D
6.80 SHOP 7
39.27 m³
1 1 1 5.78
2.15
12.42 m³
1 1 1 5.78 B/N axis 1-2' & D-E

SHOP 8
6.80
39.27 m³

1 1 1 5.78
2.15
12.42 m³
1 1 1 4.47 B/N axis 2-4 & A-B
4.98 Café & Restaurant #1
22.24 m³
1 1 1 5.78
4.84
27.95 m³
1 1 1 5.67 B/N axis 2-3 & E-F
4.90 SHOP 9
27.78 m³
1 1 1 8.13 B/N axis 3-4 & B-C'
2.91 SHOP 10
23.66 m³
1 1 1 4.84 B/N axis 3-4 & C'-F
15.10 Café & Restaurant #2
73.06 m³
CORRIDOR
1 1 1 5.78 B/n axis 2-3 & D-E
2.37
13.66 m³
1 1 1 5.85 B/n axis 2-3 & C-D
2.37
13.84 m³
1 1 1 1.93 lobby
7.93 B/n axis 3-4 & B-C'
15.30 m³
Toilet
1 1 1 1.40 B/N axis 2-3 & A'-B
4.48
6.28 m³
1 1 1 1.00 B/N axis 2-3 & B-B'
2.75
2.75 m³
1 1 1 2.85
2.33
6.64 m³
1 1 1 1.70
2.60
4.42 m³
Exposed beam
Internal
1 1 1 10.60 ON AXIS 1-(C-E)
0.22 FB-1
2.33 m²
1 1 1 5.20 ON AXIS 1-(C-D)
0.22 FB-1
1.14 m²
Bottom
1 1 1 9.20 ON AXIS 1-(C-E)
0.25 FB-1
2.30 m²
1 1 1 1.31 ON AXIS 1-(C-E)
0.05 FB-1
0.07 m²
Internal
1 1 1 16.20 ON AXIS-2 (A-F)
0.22 FB-2
3.56 m²
1 2 1 10.80
0.22
4.75 m²
Bottom
1 1 1 14.57 ON AXIS-2 (A-F)
0.25 FB-2
3.64 m²
1 1 1 7.38
0.05
0.37 m²
Internal
1 1 2 27.00 ON AXIS 3 (A-F)
0.22 FB-3
11.88 m²
Bottom
1 1 1 11.64 ON AXIS 3 (A-F)
0.25 FB-3
2.91 m²
1 1 1 10.70 ON AXIS 3 (A-F)
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


0.05 FB-3
0.54 m²
1 1 1 4.36 ON AXIS 3 (A-F)
0.15 FB-3
0.65 m²
Internal
1 1 1 9.68 ON AXIS 4-(A-B')
0.22 FB-4
2.13 m²
Bottom
1 1 1 7.28 ON AXIS 4-(A-B')
0.25 FB-4
1.82 m²
1 1 1 2.19 ON AXIS 4-(A-B')
0.05 FB-4
0.11 m²
Internal
1 1 1 14.92 ON AXIS 4 -(C-F)
0.22 FB-5
3.28 m²
1 1 1 5.64 ON AXIS 4 -(C-F)
0.22 FB-5
1.24 m²
Bottom
1 1 1 9.80 ON AXIS 4 -(C-F)
0.25 FB-5
2.45 m²
1 1 1 5.13 ON AXIS 4 -(C-F)
0.05 FB-5
0.26 m²
Internal
1 1 1 7.54 ON AXIS -5 (B'-D')
0.22 FB-6
1.66 m²
Bottom
1 1 1 4.99 ON AXIS -5 (B'-D')
0.25 FB-6
1.25 m²
1 1 1 2.55 ON AXIS -5 (B'-D')
0.05 FB-6
0.13 m²
Internal
1 2 1 8.80 ON AXIS A & F (4-2 )
0.22 FB-7
3.87 m²
Bottom
1 2 1 4.10 ON AXIS A & F (4-2 )
0.25 FB-7
2.05 m²
1 2 1 4.30 ON AXIS A & F (4-2 )
0.05 FB-7
0.43 m²
Internal
1 1 2 8.70 ON AXIS B -(4-2 )
0.22 FB-8
3.83 m²
Bottom
1 1 1 4.40 ON AXIS B -(4-2 )
0.05 FB-8
0.22 m²
1 1 1 4.40 ON AXIS B -(4-2 )
0.25 FB-8
1.10 m²
Internal
1 1 1 14.75 ON AXIS C (4-1)
0.22 FB-9
3.25 m²
1 1 1 8.85
0.22
1.95 m²
Bottom
1 1 1 3.71 ON AXIS C (4-1)
0.05 FB-9
0.19 m²
1 1 1 9.09 ON AXIS C (4-1)
0.25 FB-9
2.27 m²
Internal
1 1 1 6.40 ON AXIS E (4-1)
0.22 FB-9
1.41 m²
1 2 1 8.70
0.22
3.83 m²
Bottom
1 1 1 8.20 ON AXIS E (4-1)
0.25 FB-9
2.05 m²
1 1 1 6.70 ON AXIS E (4-1)
0.05 FB-9
0.34 m²
Internal
1 1 2 15.55 ON AXIS D -(4-1)
0.22 FB-10
6.84 m²
Bottom
1 1 1 7.95 ON AXIS D -(4-1)
0.05 FB-10
0.40 m²
1 1 1 2.05 ON AXIS D -(4-1)
0.15 FB-10
0.31 m²
1 1 1 4.65 ON AXIS D -(4-1)
0.25 FB-10
1.16 m²
Internal
1 1 2 6.75 Beam around C-D b/n 1-2
0.22
2.97 m²
Bottom
1 1 1 5.26 Beam around C-D b/n 1-2
0.25
1.32 m²
1 1 1 0.85
0.15
0.13 m²
Internal
1 1 2 6.75 Beam around D-E b/n 1-2
0.22
2.97 m²
Bottom
1 1 1 6.65 Beam around D-E b/n 1-2
0.25
1.66 m²
Internal
1 1 1 3.10 ON AXIS D' (5-4)
0.22 FB-11
0.68 m²
Bottom
1 1 1 3.10 ON AXIS D' (5-4)
0.25 FB-11
0.78 m²
Internal
1 1 1 1.25 ON AXIS B' (5-4)
0.22 FB-12
0.28 m²
Bottom
1 1 1 1.25 ON AXIS B' (5-4)
0.05 FB-12
0.06 m²
Internal
1 1 1 3.10 ON AXIS C' (5-4)
0.22 FB-13
0.68 m²
1 1 1 3.10 ON AXIS C' (5-4)
0.22 FB-13
0.68 m²
Bottom
1 1 1 3.10 ON AXIS C' (5-4)
0.25 FB-13
0.78 m²

Deduct for Columns contact Areas


1 21 -1 0.35 1st-Floor
0.35
-2.57 m³
1 2 -1 0.05
0.05
-0.01 m³
SHOP STAIR
Ground floor
SECTION E-E
1 1 1 3.75 sofit
1.05
3.94 m³
1 1 1 3.75 Side Flight
0.22
0.83 m³
1 11 0.5 0.30 Riser side
0.15
0.25 m³
SECTION F-F
1 1 1 3.30 Side Flight
0.22
0.73 m³
1 11 0.5 0.30 Riser side
0.15
0.25 m³
1 1 1 3.30 sofit
1.05
3.47 m³
1 1 1 1.99 Landing 1
2.20
4.38 m³
1 1 1 0.06 side Landing
0.22
0.01 m³ 13.86
1372.73 m² Total item 7.16b

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

1
Project:- Saving Houses B+G+8 Typolog Block Type:- New B+G+8
2
Client:- Addis Ababa Saving Houses De Block No.____________
3
Contractor: ______________________ Payment No.__________
4
Consultant: K2N Architecture and Engineering Consultancy PLC
5

6 Timizing Dimension Qty Descreption

7
SUPER-STRUCTURE
8
CARPENTRY AND JOINERY

9
Supply and fix 3.4mm thick patterned MDF Wooden
Door.
10 7 1 1 1.20 Type D6 SIZE 1200x2950mm
11
2.95 24.78 m²
12

13 7 3 1 1.20 Type D6 SIZE 1200x2750mm


14
2.75 69.30 m²
15

16 7 4 1 0.70 Type D4 SIZE 700x2950mm


17
2.95 57.82 m²
18

19 7 4 1 0.80 Type D5 SIZE 800x2950mm


20
2.95 66.08 m²
21
217.98 m² Total Area
22
6. Plastering & Pointing
23
Apply two coats of plastering with cement mortar 1:3
mix ratio.
24
a. To all internal wall surface
25
20 HCB
26
Basement floor
27 1 2 1 5.30 On axis 4 b/n E - F
28 2.80
29
29.68 m²
30 1 4 2 5.30 On axis 2,3 b/n E - F
31 2.50
32
106.00 m²
33 1 2 1 6.91 On axis E b/n 1 - 2 & 4 -5
34 2.80
35
38.70 m²
36 1 2 1 4.24 On axis 4 b/n C - D'
37 2.80
38
23.74 m²
39 1 2 1 3.10 On axis D' b/n 4-5
40 2.80
41
17.36 m²
42
Grd FLOOR
43 1 1 1 10.80 On axis 1 b/n C-E
44 2.80
45
30.24 m²
46 1 1 1 10.80 On axis 2 b/n A-B'
47 2.80
48
30.24 m²
49 1 1 1 8.80 On axis 2 b/n A-B'edge
50 0.20
51
1.76 m²
52 Deduction
53 1 -1 1 4.20 W1
54 1.80
55
-7.56 m²
56 1 -1 1 2.75 TW-2
57 0.80
58
-2.20 m²
59 1 -1 1 1.10 W-11
60 1.80
61
-1.98 m²
62 On axis 2 b/n E-G
63 1 1 1 10.43
64 2.80
65
29.20 m²
66 On axis 2 b/n E-G edge
67 1 1 1 3.20
68 0.20
69
0.64 m²
70 1 1 -1 4.50 DDT TW-5
71 0.80
72
-3.60 m²
73 1 1 -1 5.40 DDT TW-4
74 0.80
75
-4.32 m²
76 1 2 1 3.25 On axis 3 b/n A-B'
77 2.80
78
18.20 m²
79 1 1 2 10.80 On axis 3 b/n D-F
80 2.80
81
60.48 m²
82 1 1 2 5.64 On axis 4 b/n C-D'
83 2.80
84
31.58 m²
85 1 1 1 7.64 On axis 5 b/n B'-D'
86 2.80
87
21.39 m²
88 1 1 1 7.20 On axis 5 b/n B'-D' edge
89 0.20
90
1.44 m²
91 1 -1 1 2.40 W-4'
92 0.80
93
-1.92 m²
94 1 -1 1 2.74 WD-2
95 2.80
96
-7.67 m²
97 1 1 1 1.40 b/n axis A/ 2-3
98 2.80
99
3.92 m²
100 1 1 1 5.60
101 0.20
102
1.12 m²
103 1 2 1 5.02 b/n axis A-B/2-3
104 3.00
105
30.12 m²
106 1 2 1 5.23 b/n axis B-B'/2-3
107 2.80
108
29.29 m²
109 1 1 1 3.00 b/n axis B-B'/2-3 edge
110 0.20
111
0.60 m²
112 1 2 1 4.39 b/n axis C & 2-3
113 2.80
114
24.58 m²
115 1 2 1 13.33 On axis D b/n 1-4
116 2.80
117
74.65 m²
118 1 1 1 5.60 On axis D b/n 1-4 Edge
119 0.20
120
1.12 m²
121 1 1 1 3.10 On axis D' b/n 4-5
122 2.80
123
8.68 m²
124 1 -1 1 3.10 W-4
125 0.50
126
-1.55 m²
127 1 1 1 1.00 On axis D' b/n 4-5 edge
128 0.20
129
0.20 m²
130 1 2 1 8.80 On axis E b/n 2-4
131 2.80
132
49.28 m²
133 1 2 1 4.40 On axisd F b/n 3-4
134 2.80
135
24.64 m²
136 1 1 1 13.10 On axisd G b/n 2-4
137 2.80
138
36.68 m²
139 1 2 -1 4.50 DDT TW-5
140 0.80
141
-7.20 m²
142 1 1 -1 2.70 DDT TW-6
143 0.80
144
-2.16 m²
145 1 1 1 3.20
146 0.20
147
0.64 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


148 FIRST FLOOR
149 1 1 1 10.80 On axis 1 b/n C-E
150 2.80
151
30.24 m²
152 1 1 1 10.80 On axis 2 b/n A-B'
153 2.80
154
30.24 m²
155 Deduction
156 1 -1 1 4.20 W1
157 1.80
158
-7.56 m²
159 1 -1 1 2.75 TW-2
160 0.80
161
-2.20 m²
162 1 -1 1 1.10 W-11
163 1.80
164
-1.98 m²
165 1 1 1 8.80 On axis 2 b/n A-B' Edge
166 0.20
167
1.76 m²
168 1 2 1 3.25 On axis 3 b/n A-B
169 2.80
170
18.20 m²
171 1 2 1 5.40 On axis 3 b/n E-F
172 2.80
173
30.24 m²
174 1 2 1 5.64 On axis 4 b/n C-D'
175 2.80
176
31.58 m²
177 1 1 1 7.54 On axis 5 b/n B'-D'
178 2.80
179
21.11 m²
180 Deduction
181 1 -1 1 2.40 W-4
182 1.80
183
-4.32 m²
184 1 -1 1 2.59 W-2
185 1.80
186
-4.66 m²
187 1 1 1 7.20 On axis 5 b/n B'-D' Edge
188 0.20
189
1.44 m²
190 1 1 1 1.40 b/n axis A & 2-4
191 2.80
192
3.92 m²
193 1 1 1 5.60 b/n axis A & 2-4 Edge
194 0.20
195
1.12 m²
196 1 2 1 5.03 b/n axis A-B & 2-3
197 3.02
198
30.38 m²
199 1 2 1 3.21 b/n axis B & 3-4
200 2.80
201
17.98 m²
202 1 1 1 5.60 b/n axis B & 3-4 Edge
203 0..2
204
5.60 m²
205 1 2 1 5.23 b/n axis B-B' & 2-3
206 2.80
207
29.29 m²
208 1 1 1 3.00 b/n axis B-B' & 2-3 edge
209 0.20
210
0.60 m²
211 1 2 1 4.39 b/n axis C & 2-3
212 2.80
213
24.58 m²
214 1 2 1 5.15 b/n axis C - D & 3-4
215 3.02
216
31.11 m²
217 1 1 1 3.00 b/n axis C - D & 3-4 edge
218 0.20
219
0.60 m²
220 1 2 1 8.57 On axis D b/n 1-3
221 2.80
222
47.99 m²
223 1 1 1 2.80 On axis D b/n 1-3 edge
224 0.20
225
0.56 m²
226 1 1 1 3.10 On axis D' b/n 4-5
227 2.80
228
8.68 m²
229 1 -1 1 3.10 W-4
230 0.50
231
-1.55 m²
232 1 1 1 1.00 On axis D' b/n 4-5 edge
233 0.20
234
0.20 m²
235 1 2 1 2.17 On axis E b/n 2-3
236 2.80
237
12.15 m²
238 1 1 1 2.80 On axis E b/n 2-3 edge
239 0.20
240
0.56 m²
241
Around Terrace
242 1 1 1 3.30 On Axis A, 4-5
243 0.60
244
1.98 m²
245 1 1 1 0.40 On Axis A, 4-5
246 0.40
247
0.16 m²
248 1 1 1 5.10 On Axis 5 , A-B
249 0.60
250
3.06 m²
251 1 1 1 1.20 On Axis 5 , A-B
252 0.40
253
0.48 m²
254 1 1 2 3.31 On Axis B & E ,5-6
255 0.60
256
3.97 m²
257 1 1 2 0.80 On Axis B & E ,5-6
258 0.40
259
0.64 m²
260 1 1 1 15.60 On Axis 6 ,B-E
261 0.60
262
9.36 m²
263 1 1 1 2.40 On Axis 6 ,B-E
264 0.40
265
0.96 m²
266 1 1 1 9.93 On Axis 5 ,E-G
267 0.60
268
5.96 m²
269 1 1 1 1.80 On Axis 5 ,E-G
270 0.40
271
0.72 m²
272 1 1 1 12.00 On Axis G ,2-5
273 0.60
274
7.20 m²
275 1 1 1 2.00 On Axis G ,2-5
276 0.40
277
0.80 m²
278 1 1 1 4.63 On Axis 2 ,F-G
279 0.60
280
2.78 m²
281 1 1 1 0.80 On Axis 2 ,F-G
282 0.40
283
0.32 m² 38.39 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption

284
Second- Third floor
285 2 1 1 6.55 On axis 1 b/n C-D
286 3.02
287
39.56 m²
288 2 -1 2 0.80 Deduction
289 0.60 TW-3
290
-1.92 m²
291 2 1 1 3.20 On axis 1 b/n C-D edge
292 0.20
293
1.28 m²
294 2 1 1 5.40 On axis 1 b/n D-E
295 2.80
296
30.24 m²
297 Deduction
298 2 -1 2 2.00 W-5
299 1.80
300
-14.40 m²
301 2 1 1 7.20 On axis 1 b/n D-E edge
302 0.20
303
2.88 m²
304 2 2 1 12.08 b/n axis 1-2 & C-E
305 3.00
306
144.96 m²
307 2 1 1 12.33 On axis 2 b/n A-C
308 2.80
309
69.05 m²
310 Deduction
311 2 -1 1 0.80 W-8
312 1.80
313
-2.88 m²
314 2 -1 1 2.00 W-5
315 1.80
316
-7.20 m²
317 2 -1 1 0.60 TW-3
318 0.80
319
-0.96 m²
320 2 -1 1 1.10 W-11
321 1.80
322
-3.96 m²
323 2 1 1 12.40 On axis 2 b/n A-C
324 0.20
325
4.96 m²
326 2 1 1 5.40 On axis 2 b/n E-F
327 2.80
328
30.24 m²
329

330 2 -1 1 0.80 Deduction


331 1.80 W-8
332
-2.88 m²
333 2 1 1 3.60 On axis 2 b/n E-F edge
334 0.20
335
1.44 m²
336 2 2 1 5.03 On axis 2-3 b/n A-F
337 3.00
338
60.36 m²
339 2 2 1 10.80 On axis 3 b/n B-C & D-E
340 2.80
341
120.96 m²
342 2 1 1 9.68 On axis 4 b/n A-B'
343 2.80
344
54.21 m²
345 2 1 1 18.40 On axis 4 b/n A-B' edge
346 0.20
347
7.36 m²
348 2 1 1 9.68 On axis 4 b/n D'-F
349 2.80
350
54.21 m²
351 Deduction
352 2 -1 2 2.00 W-5
353 1.80
354
-14.40 m²
355 2 -1 2 1.80 WD-16
356 2.80
357
-20.16 m²
358 2 -1 2 1.43 WD-17
359 2.80
360
-16.02 m²
361 2 -1 2 2.05 W-6
362 1.80
363
-14.76 m²
364 2 1 1 18.40 On axis 4 b/n D'-F edge
365 0.20
366
7.36 m²
367 2 1 1 7.54 On axis 5 b/n B'-D'
368 2.80
369
42.22 m²
370 Deduction
371 2 -1 1 2.69 W-2
372 1.80
373
-9.68 m²
374 2 -1 1 2.40 W-4'
375 1.80
376
-8.64 m²
377 2 1 1 7.20 On axis 5 b/n B'-D' edge
378 0.20
379
2.88 m²
380 2 1 1 8.80 On axis A b/n 2-4
381 2.80
382
49.28 m²
383 Deduction
384 2 -1 1 2.90 W-7
385 1.80
386
-10.44 m²
387 2 -2 1 0.60 TW-3
388 0.80
389
-1.92 m²
390 2 1 1 6.80 On axis A b/n 2-4
391 0.20
392
2.72 m²
393 2 2 1 4.39 On axis B b/n 2-3
394 2.80
395
49.17 m²
396 2 1 1 1.25 On axis B' b/n 4-5
397 2.80
398
7.00 m²
399 2 1 1 5.65 b/n axis C & 1-2
400 2.80
401
31.64 m²
402 2 -1 1 1.95 Deduction
403 1.80 W-10
404
-7.02 m²
405 2 -1 1 1.85 W-9
406 1.80
407
-6.66 m²
408 2 1 1 7.20 b/n axis C & 1-2 edge
409 0.20
410
2.88 m²
411 2 2 1 1.49 b/n axis C & 2-3
412 2.80
413
16.69 m²
414 2 -1 1 1.49 Deduction
415 0.80 W-12
416
-2.38 m²
417 2 1 1 1.60 b/n axis C & 2-3 edge
418 0.20
419
0.64 m²
420 2 2 1 3.45 b/n axis C & 3-4
421 2.80
422
38.64 m²
423 2 2 1 9.40 On axis D b/n 1-4
424 2.80
425
105.28 m²
426 2 1 1 3.10 On axis D' b/n 4-5
427 2.80
428
17.36 m²
429 Deduction
430 2 -1 1 3.10 W-4
431 0.50
432
-3.10 m²
433 2 1 1 1.00 On axis D' b/n 4-5
434 0.20
435
0.40 m²
436 2 1 1 9.00 On axis E b/n 1-3
437 2.80
438
50.40 m²
439 2 -1 1 2.00 Deduction
440 1.80 W-5
441
-7.20 m²
442 2 1 1 3.60 On axis E b/n 1-3 edge
443 0.20
444
1.44 m²
445 2 1 1 8.80 On axisd F b/n 2-4
446 2.80
447
49.28 m²
448 2 -1 1 2.90 Deduction
449 1.80 W-7
450
-10.44 m²
451 2 -2 1 0.60 TW-3
452 0.80
453
-1.92 m²
454 2 1 1 6.80 On axisd F b/n 2-4 edge
455 0.20
456
2.72 m²
457 2 1 1 1.42 On Axis E b/n 1-2
458 0.60 BALCONY
459
1.70 m²
460 2 1 1 1.40 On Axis C b/n 1-2
461 0.60 BALCONY
462
1.68 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption

463
4th-8th Floor
464 5 1 1 6.55 On axis 1 b/n C-D
465 3.02
466
98.91 m²
467 5 -1 2 0.80 Deduction
468 0.60 TW-3
469
-4.80 m²
470 5 1 1 3.20 On axis 1 b/n C-D edge
471 0.20
472
3.20 m²
473 5 1 1 5.60 On axis 1 b/n D-E
474 2.80
475
78.40 m²
476 Deduction
477 5 -1 2 2.00 W-5
478 1.80
479
-36.00 m²
480 5 1 1 7.20 On axis 1 b/n D-E edge
481 0.20
482
7.20 m²
483 5 2 1 12.08 b/n axis 1-2 & C-E
484 3.00
485
362.40 m²
486 5 1 1 12.73 On axis 2 b/n A-C
487 2.80
488
178.22 m²
489 Deduction
490 5 -1 1 0.80 W-8
491 1.80
492
-7.20 m²
493 5 -1 1 2.00 W-5
494 1.80
495
-18.00 m²
496 5 -1 1 0.60 TW-3
497 0.80
498
-2.40 m²
499 5 -1 1 1.10 W-11
500 1.80
501
-9.90 m²
502 5 1 1 12.40 On axis 2 b/n A-C
503 0.20
504
12.40 m²
505 5 1 1 5.60 On axis 2 b/n E-F
506 2.80
507
78.40 m²
508

509 5 -1 1 0.80 Deduction


510 1.80 W-8
511
-7.20 m²
512 5 1 1 3.60 On axis 2 b/n E-F edge
513 0.20
514
3.60 m²
515 5 2 1 5.03 On axis 2-3 b/n A-F
516 3.00
517
150.90 m²
518 5 2 1 11.30 On axis 3 b/n B-C & D-E
519 2.80
520
316.40 m²
521 5 1 1 10.08 On axis 4 b/n A-B'
522 2.80
523
141.12 m²
524 5 1 1 18.40 On axis 4 b/n A-B' edge
525 0.20
526
18.40 m²
527 5 1 1 10.08 On axis 4 b/n D'-F
528 2.80
529
141.12 m²
530 Deduction
531 5 -1 2 2.00 W-5
532 1.80
533
-36.00 m²
534 5 -1 2 1.80 WD-16
535 2.80
536
-50.40 m²
537 5 -1 2 1.43 WD-17
538 2.80
539
-40.04 m²
540 5 -1 2 2.05 W-6
541 1.80
542
-36.90 m²
543 5 1 1 18.40 On axis 4 b/n D'-F edge
544 0.20
545
18.40 m²
546 5 1 1 7.74 On axis 5 b/n B'-D'
547 2.80
548
108.36 m²
549 Deduction
550 5 -1 1 2.69 W-2
551 1.80
552
-24.21 m²
553 5 -1 1 2.40 W-4'
554 1.80
555
-21.60 m²
556 5 1 1 7.20 On axis 5 b/n B'-D' edge
557 0.20
558
7.20 m²
559 5 1 1 9.40 On axis A b/n 2-4
560 2.80
561
131.60 m²
562 Deduction
563 5 -1 1 2.90 W-7
564 1.80
565
-26.10 m²
566 5 -2 1 0.60 TW-3
567 0.80
568
-4.80 m²
569 5 1 1 6.80 On axis A b/n 2-4
570 0.20
571
6.80 m²
572 5 2 1 4.69 On axis B b/n 2-3
573 2.80
574
131.32 m²
575 5 1 1 1.25 On axis B' b/n 4-5
576 2.80
577
17.50 m²
578 5 1 1 5.85 b/n axis C & 1-2
579 2.80
580
81.90 m²
581 5 -1 1 1.95 Deduction
582 1.80 W-10
583
-17.55 m²
584 5 -1 1 1.85 W-9
585 1.80
586
-16.65 m²
587 5 1 1 7.20 b/n axis C & 1-2 edge
588 0.20
589
7.20 m²
590 5 2 1 1.59 b/n axis C & 2-3
591 2.80
592
44.52 m²
593 5 -1 1 1.49 Deduction
594 0.80 W-12
595
-5.96 m²
596 5 1 1 1.60 b/n axis C & 2-3 edge
597 0.20
598
1.60 m²
599 5 2 1 3.55 b/n axis C & 3-4
600 2.80
601
99.40 m²
602 5 2 1 9.90 On axis D b/n 1-4
603 2.80
604
277.20 m²
605 5 1 1 3.30 On axis D' b/n 4-5
606 2.80
607
46.20 m²
608 Deduction
609 5 -1 1 3.10 W-4
610 0.50
611
-7.75 m²
612 5 1 1 1.00 On axis D' b/n 4-5
613 0.20
614
1.00 m²
615 5 1 1 9.50 On axis E b/n 1-3
616 2.80
617
133.00 m²
618 5 -1 1 2.00 Deduction
619 1.80 W-5
620
-18.00 m²
621 5 1 1 3.60 On axis E b/n 1-3 edge
622 0.20
623
3.60 m²
624 5 1 1 9.40 On axisd F b/n 2-4
625 2.80
626
131.60 m²
627 5 -1 1 2.90 Deduction
628 1.80 W-7
629
-26.10 m²
630 5 -2 1 0.60 TW-3
631 0.80
632
-4.80 m²
633 5 1 1 6.80 On axisd F b/n 2-4 edge
634 0.20
635
6.80 m²
636 5 1 1 1.42 On Axis E b/n 1-2
637 0.60 BALCONY
638
4.26 m²
639 5 1 1 1.40 On Axis C b/n 1-2
640 0.60 BALCONY
641
4.20 m²
642 WATER TANKER
643 1 1 1 7.54 FRONT ELEVATION
644 3.00 On Axis 5 B'-D*
645
22.62 m²
646 1 -1 1 2.59 Deduction
647 1.80 W-2
648
-4.66 m²
649 1 -1 1 2.40 W-4
650 0.80
651
-1.92 m²
652 1 1 1 5.20 On Axis 5 B'-D* Edge
653 0.20
654
1.04 m²
655 1 1 1 3.10 RIGHT SIDE ELEVATION
656 3.00 On Axis F 2-4
657
9.30 m²
658 1 1 1 3.30 LEFT SIDE ELEVATION
659 3.00 On Axis A 2-4
660
9.90 m² 2468.243
661
4484.66 m² Total To Item

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption

662
Ditto as item 6.1 but for 100mm HCB wall.
663
Basement floor
664 1 2 1 1.40 At Garbage & Sanitary Ducts
665 2.80 On Axis 4-5 , C-D
666
7.84 m²
667 1 2 1 1.25
668 2.80
669
7.00 m²
670 1 2 1 0.70
671 2.80
672
3.92 m²
673 1 2 1 0.50
674 2.80
675
2.80 m²
676 GROUND FLOOR
677 1 2 1 7.30 On Axis a-b & 2-3
678 3.02 toilet area horizontally
679
44.09 m²
680 1 2 1 3.72 On Axis a-b & 2-3
681 3.02 toilet area vertically
682
22.47 m²
683 1 1 1 1.30 DUCT (Pipe cover at toilet)
684 3.02
685
3.93 m²
686 1 1 1 3.90 On Axis C b/n 4-5
687 3.02 duct area
688
11.78 m²
689 1 1 1 1.00 On Axis A,3
690 2.80 DUCT (Pipe cover at toilet)
691
2.80 m²
692 1 1 1 0.80 On Axis 1, C-D
693 3.02 DUCT (Pipe cover)
694
2.42 m²
695 1 1 1 1.15 On Axis 4, B'
696 3.02 DUCT (Pipe cover)
697
3.47 m²
698 1 1 1 0.80 On Axis 4, D'
699 3.02 DUCT (Pipe cover)
700
2.42 m²
701 1 1 2 0.55 On Axis F around axis 3
702 3.02 DUCT (Pipe cover)
703
3.32 m²
704 FIRST FLOOR
705 1 2 1 7.30 On Axis a-b & 2-3
706 3.02 toilet area horizontally
707
44.09 m²
708 1 2 1 3.72 On Axis a-b & 2-3
709 3.02 toilet area vertically
710
22.47 m²
711 1 1 1 1.30 DUCT (Pipe cover at toilet)
712 3.02
713
3.93 m²
714 1 1 1 3.90 On Axis C b/n 4-5
715 3.02 duct area
716
11.78 m²
717 1 1 1 1.00 On Axis A,3
718 2.80 DUCT (Pipe cover at toilet)
719
2.80 m²
720 1 1 1 0.80 On Axis 1, C-D
721 3.02 DUCT (Pipe cover)
722
2.42 m²
723 1 1 1 1.15 On Axis 4, B'
724 3.02 DUCT (Pipe cover)
725
3.47 m²
726 1 1 1 0.80 On Axis 4, D'
727 3.02 DUCT (Pipe cover)
728
2.42 m²
729 1 1 2 0.55 On Axis F around axis 3
730 3.02 DUCT (Pipe cover)
731
3.32 m²
732 SECOND- THIRD FLOOR
733 2 2 1 1.53 On Axis 1-2 C-E
734 3.02 TOILET
735
18.48 m²
736 2 2 1 4.60
737 3.02
738
55.57 m²
739 2 1 4 3.00 On Axis 1-2 C-E edge
740 0.10
741
2.40 m²
742 2 2 1 6.28 On Axis 1-2 C-E
743 3.02 BED ROOM-1
744
75.86 m²
745 2 2 1 2.05
746 2.80
747
22.96 m²
748 2 1 1 3.00 On Axis 1-2 C-E edge
749 0.10
750
0.60 m²
751 2 2 1 6.89 KITCHEN
752 3.02
753
83.23 m²
754 2 2 1 3.00 KITCHEN edge
755 0.10
756
1.20 m²
757 2 2 1 1.75 BED ROOM-1
758 3.02
759
21.14 m²
760 2 1 1 0.10 BED ROOM-1 edge
761 3.02
762
0.60 m²
763 2 2 1 3.46 On Axis 2-3 & A-F
764 3.02 TOILET (B/N A-B)
765
41.80 m²
766 2 1 2 0.10 On Axis 2-3 & A-F edge
767 3.02
768
1.21 m²
769 2 2 1 5.72 BED ROOMS
770 3.02
771
69.10 m²
772 2 1 3 0.10 BED ROOMS edge
773 3.02
774
1.81 m²
775 2 2 1 3.38 TOILET (B/N B-D)
776 3.02
777
40.83 m²
778 2 1 1 0.10 TOILET (B/N B-D) edge
779 3.02
780
0.60 m²
781 2 2 1 6.92 KITCHEN
782 3.02
783
83.59 m²
784 2 1 2 0.10 KITCHEN
785 3.02
786
1.21 m²
787 2 2 1 4.13 Store
788 3.02
789
49.89 m²
790 2 1 1 0.10 Store edge
791 3.02
792
0.60 m²
793 2 2 1 5.35 BED ROOM 2 (B/N E-F)
794 3.02
795
64.63 m²
796 2 1 1 0.20 BED ROOM 2 (B/N E-F) edge
797 3.02
798
1.21 m²
799 2 2 1 3.63 TOILET (B/N E-F)
800 3.02
801
43.85 m²
802 2 1 3 0.10 TOILET (B/N E-F) edge
803 3.02
804
1.81 m²
805 2 2 2 2.18 On Axis 3 A & F
806 2.80 TOILET
807
48.83 m²
808 2 2 2 3.21 On Axis 3 A & F
809 3.02 TOILET
810
77.55 m²
811 2 1 2 0.20 On Axis 3 A & F edge
812 3.02 TOILET
813
2.42 m²
814 2 2 2 3.58 BED ROOM-1
815 3.02
816
86.49 m²
817 2 1 2 0.20 BED ROOM-1 edge
818 3.02
819
2.42 m²
820 2 2 2 6.04 KITCHEN
821 3.02
822
145.93 m²
823 2 1 2 0.20 KITCHEN edge
824 3.02
825
2.42 m²
826 2 2 1 3.05 On Axis C b/n 4-5
827 3.02 DUCT
828
36.84 m²
829 2 2 2 0.50 On Axis A & F around axis 3
830 3.02 DUCT (Pipe cover at toilet)
831
12.08 m²
832 2 1 1 0.50 On Axis 2 B-B'
833 3.02 DUCT (Pipe cover at toilet)
834
3.02 m²
835 2 1 2 0.80 On Axis 4, B'&D'
836 3.02 DUCT (Pipe cover at kitchen)
837
9.66 m²
838 2 1 1 1.20 On Axis 1, C-D
839 3.02 DUCT (Pipe cover at toilet)
840
7.25 m²
841 2 1 1 4.83 On Axis 4 b/n A-B'
842 0.60 BALCONY
843
5.80 m²
844 2 1 1 5.03 On Axis 4 b/n D'-E
845 0.60 BALCONY
846
6.04 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE B C D E F TYPOLOGY :B+G+8 G CONSULTANT:K2N Architecture and Engineering Consultancy plc
6 Timizing Dimension Qty Descreption

847 4TH- 8TH FLOOR


848 5 2 1 1.53 On Axis 1-2 C-E
849 3.02 TOILET
850
46.21 m²
851 5 2 1 4.60
852 3.02
853
138.92 m²
854 5 1 4 3.00 On Axis 1-2 C-E edge
855 0.10
856
6.00 m²
857 5 2 1 6.28 On Axis 1-2 C-E
858 3.02 BED ROOM-1
859
189.66 m²
860 5 2 1 2.25
861 2.80
862
63.00 m²
863 5 1 1 3.00 On Axis 1-2 C-E edge
864 0.10
865
1.50 m²
866 5 2 1 6.89 KITCHEN
867 3.02
868
208.08 m²
869 5 2 1 3.00 KITCHEN edge
870 0.10
871
3.00 m²
872 5 2 1 1.75 BED ROOM-1
873 3.02
874
52.85 m²
875 5 1 1 0.10 BED ROOM-1 edge
876 3.02
877
1.51 m²
878 5 2 1 3.46 On Axis 2-3 & A-F
879 3.02 TOILET (B/N A-B)
880
104.49 m²
881 5 1 2 0.10 On Axis 2-3 & A-F edge
882 3.02
883
3.02 m²
884 5 2 1 5.72 BED ROOMS
885 3.02
886
172.74 m²
887 5 1 3 0.10 BED ROOMS edge
888 3.02
889
4.53 m²
890 5 2 1 3.38 TOILET (B/N B-D)
891 3.02
892
102.08 m²
893 5 1 1 0.10 TOILET (B/N B-D) edge
894 3.02
895
1.51 m²
896 5 2 1 6.92 KITCHEN
897 3.02
898
208.98 m²
899 5 1 2 0.10 KITCHEN
900 3.02
901
3.02 m²
902 5 2 1 4.13 Store
903 3.02
904
124.73 m²
905 5 1 1 0.10 Store edge
906 3.02
907
1.51 m²
908 5 2 1 5.35 BED ROOM 2 (B/N E-F)
909 3.02
910
161.57 m²
911 5 1 1 0.20 BED ROOM 2 (B/N E-F) edge
912 3.02
913
3.02 m²
914 5 2 1 3.63 TOILET (B/N E-F)
915 3.02
916
109.63 m²
917 5 1 3 0.10 TOILET (B/N E-F) edge
918 3.02
919
4.53 m²
920 5 2 2 2.38 On Axis 3 A & F
921 2.80 TOILET
922
133.28 m²
923 5 2 2 3.21 On Axis 3 A & F
924 3.02 TOILET
925
193.88 m²
926 5 1 2 0.20 On Axis 3 A & F edge
927 3.02 TOILET
928
6.04 m²
929 5 2 2 3.58 BED ROOM-1
930 3.02
931
216.23 m²
932 5 1 2 0.20 BED ROOM-1 edge
933 3.02
934
6.04 m²
935 5 2 2 6.04 KITCHEN
936 3.02
937
364.82 m²
938 5 1 2 0.20 KITCHEN edge
939 3.02
940
6.04 m²
941 5 2 1 3.05 On Axis C b/n 4-5
942 3.02 DUCT
943
92.11 m²
944 5 2 2 0.50 On Axis A & F around axis 3
945 3.02 DUCT (Pipe cover at toilet)
946
30.20 m²
947 5 1 1 0.50 On Axis 2 B-B'
948 3.02 DUCT (Pipe cover at toilet)
949
7.55 m²
950 5 1 2 0.80 On Axis 4, B'&D'
951 3.02 DUCT (Pipe cover at kitchen)
952
24.16 m²
953 5 1 1 1.20 On Axis 1, C-D
954 3.02 DUCT (Pipe cover at toilet)
955
18.12 m²
956 5 1 1 4.83 On Axis 4 b/n A-B'
957 0.60 BALCONY
958
14.49 m²
959 5 1 1 5.03 On Axis 4 b/n D'-E
960 0.60 BALCONY
961
15.09 m²
962
4190.01 m² Total To Item 6.01a
963
8674.66 m² Total Area of Internal Plastering
964
820.56 m² Deduct Plastering to receive ceramic wall
965
7854.10 m² Total Item 6.01a
966
b. To external wall surfaces
967
GROUND FLOOR
968 1 1 1 12.60 On axis 1 b/n C-E
969 3.30
970
41.58 m²
971 1 1 1 12.00 On axis 2 b/n A-B'
972 3.30
973
39.60 m²
974 Deduction
975 1 -1 1 4.20 W1
976 1.80
977
-7.56 m²
978 1 -1 1 2.75 TW-2
979 0.80
980
-2.20 m²
981 1 -1 1 1.10 W-11
982 1.80
983
-1.98 m²
984 On axis 2 b/n E-G
985 1 1 1 11.33
986 3.30
987
37.39 m²
988 1 1 1 10.60 On axis A b/n 2-4
989 3.30
990
34.98 m²
991 1 -1 1 7.40 Deduct WD-6
992 2.80
993
-20.72 m²
994 1 1 2 7.00 On axis C & E b/n 1-2
995 3.30
996
46.20 m²
997 1 -1 2 6.40 Deduct open area
998 2.80
999
-35.84 m²
1000 1 1 1 14.30 On axisd G b/n 2-4
1001 3.30
1002
47.19 m²
1003 1 2 -1 4.50 DDT TW-5
1004 0.80
1005
-7.20 m²
1006 1 1 -1 2.70 DDT TW-6
1007 0.80
1008
-2.16 m²
1009
FIRST FLOOR
1010 1 1 1 12.60 On axis 1 b/n C-E
1011 3.30
1012
41.58 m²
1013 1 1 1 12.00 On axis 2 b/n A-B'
1014 3.30
1015
39.60 m²
1016 Deduction
1017 1 -1 1 4.20 W1
1018 1.80
1019
-7.56 m²
1020 1 -1 1 2.75 TW-2
1021 0.80
1022
-2.20 m²
1023 1 -1 1 1.10 W-11
1024 1.80
1025
-1.98 m²
1026 1 1 1 6.00 On axis 2 b/n E-F
1027 3.30
1028
19.80 m²
1029 Deduction
1030 1 -1 1 5.40 WD4
1031 2.80
1032
-15.12 m²
1033 1 1 1 21.50 On axis 4 b/n A-B' & D'-F
1034 3.30
1035
70.95 m²
1036 1 -2 1 5.40 Deduction
1037 2.80 WD4'
1038
-30.24 m²
1039 1 -1 1 4.24 Deduction
1040 2.80 WD-8
1041
-11.87 m²
1042 1 -1 1 4.28 Deduction
1043 2.80 WD-9
1044
-11.98 m²
1045 1 1 1 8.84
1046 3.30 On axis 5 b/n B'-D'
1047
29.17 m²
1048

1049 1 -1 1 2.40 Deduction


1050 0.80 W-4
1051
-1.92 m²
1052 1 -1 1 2.59 W-2
1053 1.80
1054
-4.66 m²
1055 1 1 2 10.60 On axis A & F b/n 2-4
1056 3.30
1057
69.96 m²
1058 Deduction
1059 1 -1 2 7.40 WD-6
1060 2.80
1061
-41.44 m²
1062 1 1 2 3.70 On axis B' & D' b/n 4-5
1063 3.30
1064
24.42 m²
1065 Deduction
1066 1 -1 1 3.10 W-4
1067 0.50
1068
-1.55 m²
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


1069 1 1 2 7.00 On axis C & E b/n 1-2
1070 3.30
1071
46.20 m²
1072 Deduction
1073 1 -1 2 6.40 WD-7
1074 2.80
1075
-35.84 m²
1076
Around Terrace
1077 1 1 1 3.30 On Axis A, 4-5
1078 0.80
1079
2.64 m²
1080 1 1 1 0.40 On Axis A, 4-5
1081 0.60
1082
0.24 m²
1083 1 1 1 5.10 On Axis 5 , A-B
1084 0.80
1085
4.08 m²
1086 1 1 1 1.20 On Axis 5 , A-B
1087 0.60
1088
0.72 m²
1089 1 1 2 3.31 On Axis B & E ,5-6
1090 0.80
1091
5.30 m²
1092 1 1 2 0.80 On Axis B & E ,5-6
1093 0.60
1094
0.96 m²
1095 1 1 1 15.60 On Axis 6 ,B-E
1096 0.80
1097
12.48 m²
1098 1 1 1 2.40 On Axis 6 ,B-E
1099 0.60
1100
1.44 m²
1101 1 1 1 9.93 On Axis 5 ,E-G
1102 0.80
1103
7.94 m²
1104 1 1 1 1.80 On Axis 5 ,E-G
1105 0.60
1106
1.08 m²
1107 1 1 1 12.00 On Axis G ,2-5
1108 0.80
1109
9.60 m²
1110 1 1 1 2.00 On Axis G ,2-5
1111 0.60
1112
1.20 m²
1113 1 1 1 4.63 On Axis 2 ,F-G
1114 0.80
1115
3.70 m²
1116 1 1 1 0.80 On Axis 2 ,F-G
1117 0.60
1118
0.48 m² 51.86 m²
1119
Second- Eighth Floor
1120 7 1 1 6.55 On axis 1' b/n C-D
1121 3.30
1122
151.31 m²
1123 Deduction
1124 7 -1 2 0.80 TW-3
1125 0.60
1126
-6.72 m²
1127 7 1 1 6.00 On axis 1 b/n D-E
1128 3.30
1129
138.60 m²
1130 Deduction
1131 7 -1 2 2.00 W-5
1132 1.80
1133
-50.40 m²
1134 7 1 1 12.00 On axis 2 b/n A-C
1135 3.30
1136
277.20 m²
1137 Deduction
1138 7 -1 1 0.80 W-8
1139 1.80
1140
-10.08 m²
1141 7 -1 1 2.00 W-5
1142 1.80
1143
-25.20 m²
1144 7 -1 1 0.60 TW-3
1145 0.80
1146
-3.36 m²
1147 7 -1 1 1.10 W-11
1148 1.80
1149
-13.86 m²
1150 7 1 1 6.00 On axis 2 b/n E-F
1151 3.30
1152
138.60 m²
1153 7 -1 1 0.80 Deduction
1154 1.80 W-8
1155
-10.08 m²
1156 7 1 1 21.76 On axis 4 b/n A-F
1157 3.30
1158
502.66 m²
1159 7 -1 2 2.00 Deduction
1160 1.80 W-5
1161
-50.40 m²
1162 7 -1 2 1.80 WD-16
1163 2.80
1164
-70.56 m²
1165 7 -1 2 1.43 WD-17
1166 2.80
1167
-56.06 m²
1168 7 -1 2 2.03 W-6
1169 1.80
1170
-51.16 m²
1171 7 1 1 4.83 On Axis 4 b/n A-B'
1172 0.80 BALCONY
1173
27.05 m²
1174 7 1 1 5.03 On Axis 4 b/n D'-E
1175 0.80 BALCONY
1176
28.17 m²
1177 7 1 1 8.84 On axis 5 b/n B'-D'
1178 3.30
1179
204.20 m²
1180 Deduction
1181 7 -1 1 2.59 W-2
1182 1.80
1183
-32.63 m²
1184 7 -1 1 2.40 W-4'
1185 0.80
1186
-13.44 m²
1187 7 1 1 10.60 On axis A b/n 2-4
1188 3.30
1189
244.86 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


1190 Deduction
1191 7 -1 1 2.90 W-7
1192 1.80
1193
-36.54 m²
1194 7 -2 1 0.60 TW-3
1195 0.80
1196
-6.72 m²
1197 7 1 1 3.70 On axis B' b/n 4-5
1198 3.30
1199
85.47 m²
1200 7 1 1 6.25 b/n axis C & 1-2
1201 3.30
1202
144.38 m²
1203 Deduction
1204 7 -1 1 1.95 W-10
1205 1.80
1206
-24.57 m²
1207 7 -1 1 1.85 W-9
1208 1.80
1209
-23.31 m²
1210 7 2 1 1.40 On Axis C & E 1-2
1211 0.80 Balcony
1212
15.68 m²
1213 7 1 1 3.70 On axis D' b/n 4-5
1214 3.30
1215
85.47 m²
1216 Deduction
1217 7 -1 1 3.10 W-4
1218 0.50
1219
-10.85 m²
1220 7 1 1 5.20 On axis E b/n 1-2
1221 3.30
1222
120.12 m²
1223 Deduction
1224 7 -1 1 2.00 W-5
1225 1.80
1226

1227 7 1 1 10.60 On axis F b/n 2-4


1228 3.30
1229
244.86 m²
1230 Deduction
1231 7 -1 1 2.90 W-7
1232 1.80
1233
-36.54 m²
1234 7 -2 1 0.60 TW-3
1235 0.80
1236
-6.72 m²
1237
Above Top tie Beam
1238 1 1 1 10.68 On axis 4 b/n A-B'
1239 2.00
1240
21.36 m²
1241 1 1 0.5 12.60 On axis 1 b/N C-E
1242 2.00
1243
12.60 m²
1244 1 2 0.5 5.00 On axis F b/n 2-4
1245 2.00
1246
10.00 m²
1247 1 1 0.5 10.60 On axis A b/n 2-4
1248 2.00
1249
10.60 m²
1250 1 1 1 7.54 WATER TANKER
1251 3.00 FRONT ELEVATION
1252
22.62 m²
1253 1 -1 1 2.59 Deduction
1254 1.80 W-2
1255
-4.66 m²
1256 1 -1 1 2.40 W-4
1257 0.80
1258
-1.92 m²
1259 1 1 1 3.10 RIGHT SIDE ELEVATION
1260 3.00
1261
9.30 m²
1262 1 1 1 3.30 LEFT SIDE ELEVATION
1263 3.00
1264
9.90 m²
1265
Gutter Plastering
1266 1 1 1 2.06 On Axis A-C / 1'-2'
1267 23.25
1268
48.01 m²
1269 1 1 1 2.06 On Axis E-F / 1-2'
1270 15.00
1271
30.97 m²
1272 1 1 1 2.06 On Axis 4 / D'-F
1273 12.38
1274
25.56 m² 2063.76
1275
2460.22 m² Total Item 6.01 b
1276
C. To Suspended slab & stair case
1277 SOLID SLAB
1278 GROUND FLOOR CEILING
1279 1 1 1 5.93 B/ N Axis 4-5 & A-B
1280 3.45
1281
20.44 m²
1282 1 1 1 4.25 B/ N Axis B-B' & 4-5
1283 3.45
1284
14.66 m²
1285 1 1 1 2.91 B/ N Axis C-C' & 4-5
1286 1.08
1287
3.14 m²
1288 1 1 1 3.22
1289 1.09
1290
3.51 m²
1291 1 1 1 3.00
1292 1.28
1293
3.84 m²
1294 1 1 1 4.46 B/ N Axis D'-E & 4-5
1295 3.45
1296
15.37 m²
1297 1 1 1 5.93 B/ N Axis E-F & 4-5
1298 3.45
1299
20.44 m²
1300 1 1 1 12.70 B/ N Axis F-G & 2-5
1301 5.08
1302
64.52 m²
1303 1 1 1 5.76 B/ N Axis B-C & 5-6
1304 3.60
1305
20.72 m²
1306 1 1 1 3.60 B/ N Axis C-D & 5-6
1307 6.00
1308
21.60 m²
1309 1 1 1 5.74 B/ N Axis D-E & 5-6
1310 3.54
1311
20.32 m²
1312 FIRST-SEVENTH FLOOR CEILING
1313 7 1 1 5.95 ON Axis 1 B/N C-D
1314 0.85
1315
35.40 m²
1316 7 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1317 1.20
1318
74.42 m²
1319 7 1 1 3.45 ON Axis 4-5 B/N B'-C'
1320 2.69
1321
64.96 m²
1322 7 1 1 1.14 ON Axis 4-5 B/N B'-C'
1323 0.53
1324
4.23 m²
1325
Roof slab
1326 1 1 1 6.05 ON Axis 1 B/N C-D
1327 1.05
1328
6.35 m²
1329 1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1330 1.20
1331
10.63 m²
1332 1 1 1 3.45 ON Axis 4-5 B/N B'-C'
1333 2.69
1334
9.28 m²
1335 1 1 1 1.14 ON Axis 4-5 B/N B'-C'
1336 0.53
1337
0.60 m²
1338

1339 1 1 1 8.44
1340 3.55
1341
29.96 m² 235.83 m²
1342
main stair case
1343 9 1 1 2.40 SECTION A-A
1344 1.03 sofit
1345
22.25 m³
1346 9 1 1 1.03 Landing 1
1347 1.27
1348
11.77 m³
1349 9 1 1 2.40 side
1350 0.22
1351
4.75 m³
1352 1 7 0.5 0.29 Riser side
1353 0.15
1354
0.15 m³
1355 SECTION B-B
1356 9 1 1 1.93 sofit
1357 1.03
1358
17.89 m³
1359 9 1 1 1.27 Landing 1
1360 1.03
1361
11.77 m³
1362 9 1 1 1.93 side
1363 0.22
1364
3.82 m³
1365 1 7 0.5 0.29 Riser side
1366 0.15
1367
0.15 m³
1368 SECTION C-C
1369 9 1 1 2.00 sofit
1370 1.15
1371
20.70 m³
1372 9 1 1 2.00 side
1373 0.22
1374
3.96 m³
1375 1 5 0.5 0.29 Riser side
1376 0.15
1377
0.11 m³
1378 SHOP STAIR
1379 SECTION E-E
1380 1 1 1 3.75 sofit
1381 1.05
1382
3.94 m³
1383 1 1 1 3.75 Side Flight
1384 0.22
1385
0.83 m³
1386 1 11 0.5 0.30 Riser side
1387 0.15
1388
0.25 m³
1389 SECTION F-F
1390 1 1 1 3.30 Side Flight
1391 0.22
1392
0.73 m³
1393 1 11 0.5 0.30 Riser side
1394 0.15
1395
0.25 m³
1396 1 1 1 3.30 sofit
1397 1.05
1398
3.47 m³
1399 1 1 1 1.99 Landing 1
1400 2.20
1401
4.38 m³
1402 1 1 1 0.06 side Landing
1403 0.22
1404
0.01 m³
1405

1406
555.57 m² Total to item

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


1407 Ribbed CEILING PLASTERING
1408 GROUND FLOOR CEILING (1st floor slab)
1409
1 1 1 5.87 B/N axis 1-2' & C-D
1410
7.10 SHOP 2
1411
41.68 m³
1412
1 1 1 2.17
1413
5.80
1414
12.59 m³
1415
1 1 1 5.86 B/N axis 1-3 & D-E
1416
7.10 SHOP 3
1417
41.61 m³
1418
1 1 1 5.75
1419
4.46
1420
25.62 m³
1421
1 1 1 5.85 B/N axis 2-4 & A-B
1422
4.84 SHOP 1
1423
28.31 m³
1424
1 1 1 5.10
1425
4.47
1426
22.80 m³
1427
1 1 1 4.95 B/N axis 3-4 & E-F
1428
5.75 SHOP 4
1429
28.46 m³
1430
1 1 1 4.95 B/N axis 3-4 & D-E
1431
5.93 SHOP 5
1432
29.35 m³
1433
1 1 1 3.99 B/N axis 3-4 & C-D
1434
4.76 SHOP 6
1435
18.99 m³
1436 CORRIDOR
1437 FOR GROUND FLOOR
1438 1 1 1 5.92 B/n axis 2-3 & C-D
1439
2.40
1440
14.21 m³
1441 1 1 1 1.68 B/n axis 3-4 & C-D
1442
4.80
1443
8.04 m³
1444 1 1 1 7.34 Entrance lobby
1445
4.81 B/n axis 3-4 & B-C
1446
35.27 m³
1447 Ramp
1448 1 1 1 4.88 B/n axis 2-3 & E-F
1449
12.95
1450
63.20 m³
1451 VERENDA
1452 1 1 1 3.35 B/N axis 4-5 & A-C
1453
10.63
1454
35.61 m³
1455 1 1 1 3.35 B/N axis 4-5 & D'-F
1456
10.63
1457
35.61 m³
1458 1 1 1 17.45 B/N axis 5-6 & B-E
1459
3.60
1460
62.82 m³
1461
Toilet
1462 1 1 1 1.40 B/N axis 2-3 & A'-B
1463
4.48
1464
6.28 m³
1465 1 1 1 1.00 B/N axis 2-3 & B-B'
1466
2.75
1467
2.75 m³
1468 1 1 1 2.85
1469 2.33
1470
6.64 m³
1471 1 1 1 1.70
1472
2.60
1473
4.42 m³
1474
First Floor ceiling (2nd floor slab)
1475
1 1 1 5.78 B/N axis 1-2' & C-D
1476
6.80 SHOP 7
1477
39.27 m³
1478
1 1 1 5.78
1479
2.15
1480
12.42 m³
1481
1 1 1 5.78 B/N axis 1-2' & D-E
1482
6.80 SHOP 8
1483
39.27 m³
1484
1 1 1 5.78

2.15
1485

1486
12.42 m³
1487
1 1 1 4.47 B/N axis 2-4 & A-B
1488
4.98 Café & Restaurant #1
1489
22.24 m³
1490
1 1 1 5.78
1491
4.84
1492
27.95 m³
1493
1 1 1 5.67 B/N axis 2-3 & E-F
1494
4.90 SHOP 9
1495
27.78 m³
1496
1 1 1 8.13 B/N axis 3-4 & B-C'
1497
2.91 SHOP 10
1498
23.66 m³
1499
1 1 1 4.84 B/N axis 3-4 & C'-F
1500
15.10 Café & Restaurant #2
1501
73.06 m³
1502 CORRIDOR
1503 1 1 1 5.78 B/n axis 2-3 & D-E
1504
2.37
1505
13.66 m³
1506 1 1 1 5.85 B/n axis 2-3 & C-D
1507
2.37
1508
13.84 m³
1509 1 1 1 1.93 lobby
1510
7.93 B/n axis 3-4 & B-C'
1511
15.30 m³
1512
Toilet
1513 1 1 1 1.40 B/N axis 2-3 & A'-B
1514
4.48
1515
6.28 m³
1516 1 1 1 1.00 B/N axis 2-3 & B-B'
1517
2.75
1518
2.75 m³
1519 1 1 1 2.85
1520
2.33
1521
6.64 m³
1522 1 1 1 1.70
1523
2.60
1524
4.42 m³

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption

1525
2nd- 7th floor Ceiling (3rd-8th floor slab)
1526
3-bed room (C-E)
1527
6 1 1 3.60 M.B.ROOM
1528
3.00
1529
64.80 m³
1530
6 1 1 1.60
1531
1.30
1532
12.48 m³
1533
6 1 1 2.73 B.ROOM 1
1534
3.30
1535
54.05 m³
1536
6 1 1 3.15 B.ROOM 2
1537
2.00
1538
37.80 m³
1539
6 1 1 5.93 LIVING & DINING ROOM including Balcony
1540
6.66
1541
236.78 m³
1542
6 1 1 1.40 CORRIDOR
1543
0.80
1544
6.72 m³
1545
6 1 1 4.90
1546
1.50
1547
44.10 m³
1548
6 1 1 2.16
1549
1.40
1550
18.14 m³
1551 6 1 1 2.20 TOILET
1552
1.50
1553
. 19.80 m³
1554 6 1 1 2.20
1555
1.50
1556
. 19.80 m³
1557 6 1 1 2.25 KITCHEN
1558
2.70
1559
36.45 m³
1560
3-bed room (A-B')
1561
6 1 1 3.56 M.B.ROOM
1562
3.48
1563
74.23 m³
1564
6 1 1 1.00
1565
0.50
1566
3.00 m³
1567
6 1 1 3.89 B.ROOM 2
1568
2.20
1569
51.41 m³
1570
6 1 1 2.25 CORRIDOR
1571
3.30
1572
44.55 m³
1573
6 1 1 5.88
1574
1.37
1575
48.29 m³
1576
6 1 1 3.43 B.ROOM 1
1577
3.43
1578
70.59 m³
1579
6 1 1 4.70 LIVING & DINING ROOM
1580
3.53
1581
99.55 m³
1582 6 1 1 2.53 TOILET
1583
1.43
1584
21.71 m³
1585 6 1 1 2.53
1586
1.35
1587
20.49 m³
1588 6 1 1 3.23 KITCHEN
1589
3.45
1590
66.86 m³
1591 2-bed room (A-D)
1592
6 1 1 4.85 LIVING & DINING ROOM
1593
4.05
1594
117.86 m³
1595
6 1 1 4.88 CORRIDOR
1596
0.93
1597
27.23 m³
1598
6 1 1 2.47 M.B.ROOM
1599
4.98
1600
73.80 m³
1601
6 1 1 4.45 B.ROOM 1
1602
2.15
1603
57.41 m³
1604
6 1 1 3.00 store
1605
1.78
1606
32.04 m³
1607 6 1 1 2.02 TOILET
1608
1.78
1609
21.57 m³
1610 6 1 1 2.90 KITCHEN
1611
2.02
1612
35.15 m³
1613 6 1 1 1.85 Balcony
1614
1.80
1615
19.98 m³
1616 3-bed room (D'-F)
1617
6 1 1 2.00 B.ROOM 2
1618
4.00
1619
48.00 m³
1620
6 1 1 3.65 M.B.ROOM
1621 3.47
1622
75.99 m³
1623 6 1 1 1.02
1624
0.56
1625
3.43 m³
1626
6 1 1 3.30 CORRIDOR
1627
2.23
1628
44.09 m³
1629
6 1 1 5.80
1630
1.37
1631
47.68 m³
1632
6 1 1 3.42 B.ROOM 1
1633
3.43
1634
70.38 m³
1635
6 1 1 4.88 LIVING & DINING ROOM
1636
3.56
1637
104.24 m³
1638 6 1 1 2.53 TOILET
1639
1.30
1640
19.66 m³
1641 6 1 1 2.53
1642
1.30
1643
19.66 m³
1644 6 1 1 3.18 KITCHEN
1645
3.46
1646
66.02 m³
1647 6 1 1 5.92 lobby
1648
6.60 on Axis 2'-4, C-D
1649
234.43 m³
1650 6 1 1 2.69 on Axis 4-5, C-D
1651
3.45
1652
55.68 m³
1653 6 1 1 0.53
1654
1.14
1655
3.63 m³ 2229.53 m³
1656
Deduct column contact areas
1657 Ground
1658
1 21 -1 0.35
1659
0.35
1660
-2.57 m³
1661
1 15 -1 0.05
1662
0.05
1663
-0.040 m³
1664
3 21 -1 0.35 1st-3rd
1665
0.35
1666
-7.72 m³
1667
3 2 -1 0.05
1668
0.05
1669
-0.02 m³
1670
4 22 -1 0.15 4th-7th
1671
0.15
1672
-1.98 m³
1673
4 1 -1 0.05
1674
0.05 2217.19
1675
-0.01 m³ -12.34 m³
1676
3082.41 m²
1677

1678
3637.98 m² Total Item 6.01 C

STANDARD TAKEOFF SHEET


CLIENT : AASHDE B C D E F TYPOLOGY :B+G+8 G CONSULTANT:K2N Architecture and Engineering Consultancy plc
6 Timizing Dimension Qty Descreption

1679
D. To exposed beams, columns & stair case
1680
First floor Beams
1681 Internal
1682 1 1 1 10.80 ON XIS 1-(C-E)
1683
0.22 FB-1
1684
2.38 m²
1685 Bottom
1686 1 1 1 10.80 ON XIS 1-(C-E)
1687
0.05 FB-1
1688
0.54 m²
1689 Internal
1690 1 1 1 10.55 ON AXIS-2 (A-C)
1691
0.22 FB-2
1692
2.32 m²
1693 1 2 1 10.80 ON AXIS-2 (C-E)
1694
0.22 FB-2
1695
4.75 m²
1696 1 1 1 5.40 ON AXIS-2 (E-F)
1697
0.22 FB-2
1698
1.19 m²
1699 1 1 1 5.03 ON AXIS-2 (F-G)
1700
0.22 FB-2
1701
1.11 m²
1702 Bottom
1703 1 1 1 8.65 ON AXIS-2 (A-C)
1704
0.25 FB-2
1705
2.16 m²
1706 1 1 1 10.80 ON AXIS-2 (C-E)
1707
0.25 FB-2
1708
2.70 m²
1709 1 1 1 10.43 ON AXIS-2 (E-G)
1710
0.05 FB-2
1711
0.52 m²
1712 Internal
1713 1 2 1 31.78 ON AXIS -3 (A-G)
1714
0.22 FB-3
1715
13.98 m²
1716 1 2 1 5.03 ON AXIS -3 (A-G)
1717
0.22 FB-3
1718
2.21 m²
1719 Bottom
1720 1 1 1 17.83 ON AXIS -3 (A-G)
1721
0.25 FB-3
1722
4.46 m²
1723 1 1 1 13.95 ON AXIS -3 (A-G)
1724
0.05 FB-3
1725
0.70 m²
1726 Internal
1727 1 1 1 9.68 ON AXIS 4-(A-B')
1728
0.22 FB-4
1729
2.13 m²
1730 bottom
1731 1 1 1 9.68 ON AXIS 4-(A-B')
1732
0.25 FB-4
1733
2.42 m²
1734 Internal
1735 1 2 1 5.44 ON AXIS 4 -(C'-D')
1736
0.22 FB-5
1737
2.39 m²
1738 1 2 1 9.68 ON AXIS 4 -(D'-G)
1739 0.22 FB-5
1740
4.26 m²
1741 1 2 1 5.03 ON AXIS 4 -(D'-G)
1742
0.22 FB-5
1743
2.21 m²
1744 bottom
1745 1 1 1 14.71 ON AXIS 4 -(D'-G)
1746
0.25 FB-5
1747
3.68 m²
1748 1 1 1 5.44 ON AXIS 4 -(D'-G)
1749
0.05 FB-5
1750
0.27 m²
1751 Internal
1752 1 1 1 29.88 ON AXIS 5 - (A-G)
1753
0.22 FB-6
1754
6.57 m²
1755 1 1 1 9.01 ON AXIS 5 - (A-G)
1756
0.22 FB-6
1757
1.98 m²
1758 bottom
1759 1 1 1 30.93 ON AXIS 5 - (A-G)
1760
0.25 FB-6
1761
7.73 m²
1762 1 1 1 3.35 ON AXIS 5 - (A-G)
1763
0.05 FB-6
1764
0.17 m²
1765 Internal
1766 1 1 1 17.53 ON AXIS 6 -(B-E )
1767
0.22 FB-7
1768
3.86 m²
1769 Bottom
1770 1 1 1 17.53 ON AXIS 6 -(B-E )
1771
0.25 FB-7
1772
4.38 m²
1773 Internal
1774 1 1 1 12.20 ON AXIS A -(5-2 )
1775
0.22 FB-8
1776
2.68 m²
1777 1 1 1 13.10 ON AXIS G -(5-2 )
1778
0.22 FB-8
1779
2.88 m²
1780 Internal
1781 1 2 1 4.40 ON AXIS F -(3-2 )
1782
0.22 FB-8
1783
1.94 m²
1784 1 2 1 8.10 ON AXIS F -(3-5 )
1785
0.22 FB-8
1786
3.56 m²
1787 Bottom
1788 1 1 1 10.40 ON AXIS A-(5-2 )
1789
0.25 FB-8
1790
2.60 m²
1791 1 1 1 1.40 ON AXIS A-(5-2 )
1792
0.05 FB-8
1793
0.07 m²
1794 1 1 1 7.80 ON AXIS F - (5-2 )
1795
0.25 FB-8
1796
1.95 m²
1797 1 1 1 4.40 ON AXIS F - (5-2 )
1798
0.05 FB-8
1799
0.22 m²
1800 1 1 1 11.70 ON AXIS G-(5-2 )
1801
0.25 FB-8
1802
2.93 m²
1803 1 1 1 1.40 ON AXIS G-(5-2 )
1804
0.05 FB-8
1805
0.07 m²
1806 Internal
1807 1 2 1 8.35 ON AXIS B -(4-2)
1808
0.22 FB-9
1809
3.67 m²
1810 1 2 1 3.40 ON AXIS B -(5-4)
1811
0.22 FB-9
1812
1.50 m²
1813 1 2 1 6.95 ON AXIS B -(6-4)
1814
0.22 FB-9
1815
3.06 m² 11.75
1816 Bottom
1817 1 1 1 15.30 ON AXIS B -(6-2)
1818 0.25 FB-9
1819
3.83 m²
1820
Internal
1821 1 1 1 4.93 ON AXIS b/n B-C & 2-3
1822
0.50 FB-10
1823
2.47 m²
1824 Bottom
1825 1 1 1 4.93 ON AXIS b/n B-C & 2-3
1826
0.05 FB-10
1827
0.25 m²
1828
Internal
1829 1 1 1 6.40 ON AXIS C -(1-2)
1830
0.22 FB-11
1831
1.41 m²
1832 1 2 1 4.39 ON AXIS C -(3-2)
1833
0.22 FB-11
1834
1.93 m²
1835 1 2 1 4.76 ON AXIS C -(3-4)
1836
0.22 FB-11
1837
2.09 m²
1838 Bottom
1839 1 1 1 11.16 ON AXIS C -(1-2 & 3-4)
1840
0.25 FB-11
1841
2.79 m²
1842 1 1 1 4.40 ON AXIS C -(2-3)
1843
0.05 FB-11
1844
0.22 m²
1845
Internal
1846 1 2 2 6.75 b/n axis C-D and D-E & (2-1)
1847
0.22 FB-12
1848
5.94 m²
1849 Bottom
1850 1 2 1 6.75 b/n axis C-D and D-E & (2-1)
1851
0.25 FB-12
1852
3.38 m²
1853
Internal
1854 1 1 2 15.55 ON AXIS D -(4-1)
1855
0.22 FB-13
1856
6.84 m²
1857 Bottom
1858 1 1 1 2.22 ON AXIS D -(4-1)
1859
0.25 FB-13
1860
0.56 m²
1861 1 1 1 13.33 ON AXIS D -(4-1)
1862
0.05 FB-13
1863
0.67 m²
1864
Internal
1865 1 1 1 21.70 ON AXIS E-(6-1)
1866
0.22 FB-14
1867
4.77 m²
1868
Internal
1869 1 1 1 6.40 ON AXIS E-(1-2)
1870
0.22 FB-14
1871
1.41 m²
1872 1 1 2 8.80 ON AXIS E-(2-4)
1873
0.22 FB-14
1874
3.87 m²
1875 1 1 2 3.40 ON AXIS E-(4-5)
1876
0.22 FB-14
1877
1.50 m²
1878 1 1 2 3.55 ON AXIS E-(5-6)
1879
0.22 FB-14
1880
1.56 m²
1881 Bottom
1882 1 1 1 13.35 ON AXIS E-(1-2 & 4-6)
1883
0.25 FB-14
1884
3.34 m²
1885 1 1 1 8.80 ON AXIS E-(2-4)
1886
0.05 FB-14
1887
0.44 m²
1888
Internal
1889 1 1 2 6.65 ON AXIS D' - (6 -4)
1890
0.22 FB-15
1891
2.93 m²
1892 Bottom
1893 1 1 1 6.65 ON AXIS D' - (6 -4)
1894
0.25 FB-15
1895
1.66 m²
1896 1 1 1 3.10 ON AXIS D' - (6 -4)
1897
0.05 FB-15
1898
0.16 m²
1899
Internal
1900 1 1 2 3.40 ON AXIS C' (5-4)
1901
0.22 FB-16
1902
1.50 m²
1903 Bottom
1904 1 1 1 3.40 ON AXIS C' (5-4)
1905
0.25 FB-16
1906
0.85 m²
1907
Internal
1908 1 1 2 3.55 ON AXIS C ( 6-5)
1909
0.22 FB-17
1910
1.56 m²
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


1911 Bottom
1912 1 1 1 3.55 ON AXIS C( 6-5)
1913
0.25 FB-17
1914
0.89 m²
1915
Internal
1916 1 1 2 1.25 ON AXIS C (5-4)

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


1917
0.22 FB-18
1918
0.55 m²
1919
Internal
1920 1 1 1 1.25 ON AXIS (5-4)
1921
0.05 FB-18
1922
0.06 m²
1923
2nd- 7th Floor Beams

STANDARD TAKEOFF SHEET


CLIENT : AASHDE B C D E F TYPOLOGY :B+G+8 G CONSULTANT:K2N Architecture and Engineering Consultancy plc
6 Timizing Dimension Qty Descreption
1924
Internal
1925 6 1 1 10.60 ON AXIS 1-(C-E)
1926
0.22 FB-1
1927
13.99 m²
1928 6 1 1 5.20 ON AXIS 1-(C-D)
1929
0.22 FB-1
1930
6.86 m²
1931 Bottom
1932 6 1 1 9.20 ON AXIS 1-(C-E)
1933
0.25 FB-1
1934
13.80 m²
1935 6 1 1 1.31 ON AXIS 1-(C-E)
1936
0.05 FB-1
1937
0.39 m²
1938 Internal
1939 6 1 1 16.20 ON AXIS-2 (A-F)
1940
0.22 FB-2
1941
21.38 m²
1942 6 2 1 10.80
1943
0.22
1944
28.51 m²
1945 Bottom
1946 6 1 1 14.57 ON AXIS-2 (A-F)
1947
0.25 FB-2
1948
21.86 m²
1949 6 1 1 7.38
1950
0.05
1951
2.21 m²
1952
Internal
1953 6 1 2 27.00 ON AXIS 3 (A-F)
1954
0.22 FB-3
1955
71.28 m²
1956 Bottom
1957 6 1 1 11.64 ON AXIS 3 (A-F)
1958
0.25 FB-3
1959
17.46 m²
1960 6 1 1 10.70 ON AXIS 3 (A-F)
1961
0.05 FB-3
1962
3.21 m²
1963 6 1 1 4.36 ON AXIS 3 (A-F)
1964
0.15 FB-3
1965
3.92 m²
1966
Internal
1967 6 1 1 9.68 ON AXIS 4-(A-B')
1968
0.22 FB-4
1969
12.78 m²
1970 Bottom
1971 6 1 1 7.28 ON AXIS 4-(A-B')
1972
0.25 FB-4
1973
10.92 m²
1974 6 1 1 2.19 ON AXIS 4-(A-B')
1975
0.05 FB-4
1976
0.66 m²
1977
Internal
1978 6 1 1 14.92 ON AXIS 4 -(C-F)
1979
0.22 FB-5
1980
19.69 m²
1981 6 1 1 5.64 ON AXIS 4 -(C-F)
1982
0.22 FB-5
1983
7.44 m²
1984 Bottom
1985 6 1 1 9.80 ON AXIS 4 -(C-F)
1986
0.25 FB-5
1987
14.70 m²
1988 6 1 1 5.13 ON AXIS 4 -(C-F)
1989
0.05 FB-5
1990
1.54 m²
1991
Internal
1992 6 1 1 7.54 ON AXIS -5 (B'-D')
1993
0.22 FB-6
1994
9.95 m²
1995 Bottom
1996 6 1 1 4.99 ON AXIS -5 (B'-D')
1997
0.25 FB-6
1998
7.49 m²
1999 6 1 1 2.55 ON AXIS -5 (B'-D')
2000
0.05 FB-6
2001
0.77 m²
2002
Internal
2003 6 2 1 8.80 ON AXIS A & F (4-2 )
2004
0.22 FB-7
2005
23.23 m²
2006 Bottom
2007 6 2 1 4.10 ON AXIS A & F (4-2 )
2008
0.25 FB-7
2009
12.30 m²
2010 6 2 1 4.30 ON AXIS A & F (4-2 )
2011
0.05 FB-7
2012
2.58 m²
2013
Internal
2014 6 1 2 8.70 ON AXIS B -(4-2 )
2015
0.22 FB-8
2016
22.97 m²
2017 Bottom
2018 6 1 1 4.40 ON AXIS B -(4-2 )
2019
0.05 FB-8
2020
1.32 m²
2021 6 1 1 4.40 ON AXIS B -(4-2 )
2022
0.25 FB-8
2023
6.60 m²
2024
Internal
2025 6 1 1 14.75 ON AXIS C (4-1)
2026
0.22 FB-9
2027
19.47 m²
2028 6 1 1 8.85
2029
0.22
2030
11.68 m²
2031 Bottom
2032 6 1 1 3.71 ON AXIS C (4-1)
2033
0.05 FB-9
2034
1.11 m²
2035 6 1 1 9.09 ON AXIS C (4-1)
2036
0.25 FB-9
2037
13.64 m²
2038
Internal
2039 6 1 1 6.40 ON AXIS E (4-1)
2040
0.22 FB-9
2041
8.45 m²
2042 6 2 1 8.70
2043
0.22
2044
22.97 m²
2045 Bottom
2046 6 1 1 8.20 ON AXIS E (4-1)
2047
0.25 FB-9
2048
12.30 m²
2049 6 1 1 6.70 ON AXIS E (4-1)
2050
0.05 FB-9
2051
2.01 m²
2052
Internal
2053 6 1 2 15.55 ON AXIS D -(4-1)
2054
0.22 FB-10
2055
41.05 m²
2056 Bottom
2057 6 1 1 7.95 ON AXIS D -(4-1)
2058
0.05 FB-10
2059
2.39 m²
2060 6 1 1 2.05 ON AXIS D -(4-1)
2061
0.15 FB-10
2062
1.85 m²
2063 6 1 1 4.65 ON AXIS D -(4-1)
2064
0.25 FB-10
2065
6.98 m²
2066
Internal
2067 6 1 2 6.75 Beam around C-D b/n 1-2
2068
0.22
2069
17.82 m²
2070 Bottom
2071 6 1 1 5.26 Beam around C-D b/n 1-2
2072
0.25
2073
7.89 m²
2074 6 1 1 0.85
2075
0.15
2076
0.77 m²
2077
Internal
2078 6 1 2 6.75 Beam around D-E b/n 1-2
2079
0.22
2080
17.82 m²
2081 Bottom
2082 6 1 1 6.65 Beam around D-E b/n 1-2
2083
0.25
2084
9.98 m²
2085
Internal
2086 6 1 1 3.10 ON AXIS D' (5-4)
2087
0.22 FB-11
2088
4.09 m²
2089 Bottom
2090 6 1 1 3.10 ON AXIS D' (5-4)
2091
0.25 FB-11
2092
4.65 m²
2093
Internal
2094 6 1 1 1.25 ON AXIS B' (5-4)
2095
0.22 FB-12
2096
1.65 m²
2097 Bottom
2098 6 1 1 1.25 ON AXIS B' (5-4)
2099
0.05 FB-12
2100
0.38 m²
2101
Internal
2102 6 1 1 3.10 ON AXIS C' (5-4)
2103
0.22 FB-13
2104
4.09 m²
2105 6 1 1 3.10 ON AXIS C' (5-4)
2106
0.32 FB-13
2107
5.95 m²
2108 Bottom
2109 6 1 1 3.10 ON AXIS C' (5-4)
2110
0.25 FB-13
2111
4.65 m²
2112
TOP TIE BEAM
2113
Internal
2114 1 1 2 3.45 ON XIS C' (5-4)
2115
0.22 RB-1
2116
1.52 m² .
2117
bottom
2118 1 1 1 3.45 ON XIS C' (5-4)
2119
0.25 RB-1
2120
0.86 m²
2121
Internal
2122 1 1 1 11.40 ON AXIS 1 - (C-E)
2123
0.22 RB-2
2124
2.51 m²
2125
Bottom
2126 1 1 1 9.20 ON AXIS 1 (C-E)
2127
0.25 RB-2
2128
2.30 m²
2129 1 1 1 1.31 ON AXIS (D-E)
2130
0.05 RB-2
2131
0.07 m²
2132
Internal
2133 1 1 1 16.20 ON AXIS -2 (A-F)
2134
0.22 RB-3
2135
3.56 m²
2136 1 1 2 10.80 ON AXIS -2 (C-E)
2137
0.22 RB-3
2138
4.75 m²
2139
Bottom
2140 1 1 1 14.57 ON AXIS -2 (A-F)
2141
0.25 RB-3
2142
3.64 m²
2143 1 1 1 7.38 ON AXIS -2 (A-F)
2144
0.05 RB-3
2145
0.37 m²
2146
Internal
2147 1 1 2 27.00 ON AXIS -3 (A-F)
2148
0.22 RB-3
2149
11.88 m²
2150
Bottom
2151 1 1 1 11.64 ON AXIS -3 (A-F)
2152
0.25 RB-3
2153
2.91 m²
2154 1 1 1 4.36 ON AXIS -3 (A-F)
2155
0.15 RB-3
2156
0.65 m²
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc
B C D E F G

6 Timizing Dimension Qty Descreption


2157 1 1 1 10.70 ON AXIS -3 (A-F)
2158
0.05 RB-3
2159
0.54 m²
2160
Internal
2161 1 1 1 9.68 ON AXIS 4-(A-B')
2162
0.22 RB-4
2163
2.13 m²
2164
Bottom
2165 1 1 1 7.28 ON AXIS 4-(A-B')
2166
0.25 RB-4
2167
1.82 m²
2168 1 1 1 2.19 ON AXIS 4-(A-B')
2169
0.05 RB-4
2170
0.11 m²
2171
Internal
2172 1 1 1 14.92 ON AXIS 4 -(C-F)
2173
0.22 RB-5
2174
3.28 m²
2175 1 1 1 5.64 ON AXIS 4 -(C-F)
2176
0.22 RB-5
2177
1.24 m²
2178
Bottom
2179 1 1 1 9.80 ON AXIS 4 -(C-F)
2180
0.25 RB-5
2181
2.45 m²
2182 1 1 1 5.13 ON AXIS 4 -(C-F)
2183
0.05 RB-5
2184
0.26 m²
2185
Internal
2186 1 1 1 8.80 ON AXIS -A- (4-2)
2187
0.22 RB-6
2188
1.94 m²
2189
Bottom
2190 1 1 1 4.10 ON AXIS -A- (4-2)
2191
0.25 RB-6
2192
1.03 m²
2193 1 1 1 4.30 ON AXIS -A- (4-2)
2194
0.05 RB-6
2195
0.22 m²
2196
Internal
2197 1 1 2 8.70 ON AXIS -B- (4-2 )
2198
0.22 RB-7
2199
3.83 m²
2200
Bottom
2201 1 1 1 4.40 ON AXIS -B- (4-2 )
2202
0.25 RB-7
2203
1.10 m²
2204 1 1 1 4.40 ON AXIS -B- (4-2 )
2205
0.05 RB-7
2206
0.22 m²
2207
Internal
2208 1 1 1 8.80 ON AXIS -F- (4-2)
2209
0.22 RB-7
2210
1.94 m²
2211
Bottom
2212 1 1 1 4.10 ON AXIS -F- (4-2)
2213
0.25 RB-7
2214
1.03 m²
2215 1 1 1 4.30 ON AXIS -F- (4-2)
2216
0.05 RB-7
2217
0.22 m²
2218
Internal
2219 1 1 1 14.75 ON AXIS -C- (2-1)
2220
0.22 RB-8
2221
3.25 m²
2222 1 1 1 8.85 ON AXIS -C- (4-2)
2223
0.22 RB-8
2224
1.95 m²
2225
Bottom
2226 1 1 1 9.09 ON AXIS C (4-1)
2227
0.25 RB-8
2228
2.27 m²
2229 1 1 1 3.71 ON AXIS C (4-1)
2230
0.05 RB-8
2231
0.19 m²
2232
Internal
2233 1 1 2 15.55 ON AXIS D -(4-1)
2234
0.22 RB-8
2235
6.84 m²
2236 Bottom
2237 1 1 1 7.95 ON AXIS D -(4-1)
2238
0.05 RB-8
2239
0.40 m²
2240 1 1 1 4.65 ON AXIS D -(4-1)
2241
0.25 RB-8
2242
1.16 m²
2243 1 1 1 2.05 ON AXIS D -(4-1)
2244
0.15 RB-8
2245
0.31 m²
2246
Internal
2247 1 1 1 1.25 ON AXIS B' - (4-5)
2248
0.22 RB-9
2249
0.28 m²
2250
Bottom
2251 1 1 1 1.25 ON AXIS B' - (4-5)
2252
0.05 RB-9
2253
0.06 m²
2254
Internal
2255 1 1 1 3.10 ON AXIS C' - (4-5)
2256
0.22 RB-9
2257
0.68 m²
2258
Bottom
2259 1 1 1 3.10 ON AXIS C' - (4-5)
2260
0.25 RB-9
2261
0.78 m²
2262
Internal
2263 1 1 1 7.54 ON AXIS -5- (B'-D')
2264
0.22 RB-10
2265
1.66 m²
2266
Bottom
2267 1 1 1 4.99 ON AXIS -5- (B'-D')
2268
0.25 RB-10
2269
1.25 m²
2270 1 1 1 2.55 ON AXIS -5- (B'-D')
2271
0.05 RB-10
2272
0.13 m²
2273
Internal
2274 1 1 1 6.40 ON AXIS E (4-1)
2275
0.22 RB-11
2276
1.41 m²
2277 1 1 2 8.70
2278
0.22
2279
3.83 m²
2280 Bottom
2281 1 1 1 8.20 ON AXIS E (4-1)
2282
0.25 RB-11
2283
2.05 m²
2284 1 1 1 6.70 ON AXIS E (4-1)
2285
0.05 RB-11
2286
0.34 m²
2287
WATER TANKER BEAM
2288 1 1 1 7.79 Internal
2289
0.22 ON AXIS 5 (B'-D')
2290
1.71 m² RB-11
2291 1 1 1 7.79 Bottom
2292
0.05 ON AXIS 5 (B'-D')
2293
0.39 m² RB-11
2294 1 1 1 5.84 Internal
2295
0.22 ON AXIS 4 (B'-D')
2296
1.28 m² RB-12
2297 1 1 1 5.84 Bottom
2298
0.05 ON AXIS 4 (B'-D')
2299
0.29 m² RB-12
2300 1 1 1 3.30 Internal
2301
0.22 ON AXIS B' (4-5)
2302
0.73 m² RB-13
2303 1 1 1 3.30 Bottom
2304
0.05 ON AXIS B' (4-5)
2305
0.17 m² RB-13
2306 1 1 1 3.30 Internal
2307
0.22 ON AXIS (4-5)
2308
0.73 m² RB-14
2309 1 1 1 3.30 Bottom
2310
0.05 ON AXIS (4-5)
2311
0.17 m² RB-14
2312 1 1 1 3.30 Internal
2313
0.22 ON AXIS D' (4-5)
2314
0.73 m² RB-15
2315 1 1 1 3.30 Bottom
2316
0.05 ON AXIS D' (4-5)
2317
0.17 m² RB-15
2318
844.67 m³
2319 COLUMN
2320
A) Elevation columns
2321
Ground floor
2322
1 1 1 3.20 ON AXIS 1
2323
2.80
2324
8.96 m³
2325
1 1 1 2.45
2326
0.20
2327
0.49 m³
2328
1 1 1 10.40 ON AXIS 2
2329
2.80
2330
29.12 m³
2331
1 1 1 7.10
2332
0.20
2333
1.42 m³
2334
1 1 1 11.27 ON AXIS 3
2335
2.80
2336
31.56 m³
2337
1 1 1 8.02
2338
0.20
2339
1.60 m³
2340
1 1 1 10.50 ON AXIS 4
2341
2.80
2342
29.40 m³
2343
1 1 1 6.80
2344
0.20
2345
1.36 m³
2346
1 1 1 8.90 ON AXIS 5
2347
2.80
2348
24.92 m³
2349
1 1 1 2.40
2350
0.20
2351
0.48 m³
2352
1 1 1 3.00 ON AXIS 6
2353
2.80
2354
8.40 m³
2355
1 1 1 0.50
2356
0.20
2357
0.10 m³
2358
First floor
2359
1 1 1 3.20 ON AXIS 1
2360
2.80
2361
8.96 m³
2362
1 1 1 2.45
2363
0.20
2364
0.49 m³
2365
1 1 1 10.00 ON AXIS 2
2366
2.80
2367
28.00 m³
2368
1 1 1 6.65
2369
0.20
2370
1.33 m³
2371
1 1 1 11.17 ON AXIS 3
2372
2.80
2373
31.28 m³
2374
1 1 1 7.52
2375
0.20
2376
1.50 m³
2377
1 1 1 7.80 ON AXIS 4
2378
2.80
2379
21.84 m³
2380
1 1 1 4.90
2381
0.20
2382
0.98 m³
2383
1 1 1 1.90 ON AXIS 5
2384
2.80
2385
5.32 m³
2386
1 1 1 1.15
2387
0.20
2388
0.23 m³

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption

2389
Second- Fourth Floor

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption


2390
3 1 1 4.10 ON AXIS 1
2391
2.80
2392
34.44 m³
2393
3 1 1 3.25
2394
0.20
2395
1.95 m³
2396
3 1 1 8.80 ON AXIS 2
2397
2.80
2398
73.92 m³
2399
3 1 1 6.65
2400
0.20
2401
3.99 m³
2402
3 1 1 10.80 ON AXIS 3
2403
2.80
2404
90.72 m³
2405
3 1 1 7.70
2406
0.20
2407
4.62 m³
2408
3 1 1 6.20 ON AXIS 4
2409
2.80
2410
52.08 m³
2411
3 1 1 4.90
2412
0.20
2413
2.94 m³
2414
3 1 1 1.90 ON AXIS 5
2415
2.80
2416
15.96 m³
2417
3 1 1 1.15
2418
0.20
2419
0.69 m³
2420
Fifth- Eight Floor
2421
4 1 1 2.30 ON AXIS 1
2422
2.80
2423
25.76 m³
2424
4 1 1 1.45
2425
0.20
2426
1.16 m³
2427
4 1 1 5.00 ON AXIS 2
2428
2.80
2429
56.00 m³
2430
4 1 1 2.85
2431
0.20
2432
2.28 m³
2433
4 1 1 6.00 ON AXIS 3
2434
2.80
2435
67.20 m³
2436
4 1 1 3.30
2437
0.20
2438
2.64 m³
2439
4 1 1 3.40 ON AXIS 4
2440
2.80
2441
38.08 m³
2442
4 1 1 2.10
2443
0.20
2444
1.68 m³
2445
4 1 1 0.60 ON AXIS 5
2446
2.80
2447
6.72 m³
2448
4 1 1 0.30
2449
0.20
2450
0.24 m³ #REF!
2451
720.81 m³
2452
1565.48 m³ Total To Item 6.01 D
2453
E. To exposed lift wall and retaining wall
2454
` BASEMENT FOOR
2455
1 1 1 2.60 lift wall
2456
3.15 W2
2457
8.19 m³
2458
1 1 1 2.30
2459
3.15
2460
7.25 m³
2461
1 1 1 2.30 lift wall
2462
3.15 W3
2463
7.25 m³
2464
1 1 1 1.10 lift wall
2465
3.15 W4
2466
3.47 m³
2467 Grd- first floor
2468
lift wall
2469
1 1 1 2.30 W3 (at Ground Floor)
2470
3.12
2471
7.18 m³
2472
2 1 1 2.60 w2
2473
3.12
2474
16.22 m³
2475
2 1 1 2.30 w2
2476
3.12
2477
14.35 m³
2478
2 1 1 2.30 w3
2479
3.12
2480
14.35 m³
2481
1 1 1 2.10 W4
2482
3.12
2483
6.55 m³
2484
1 -1 1 1.00 DDT
2485
2.10
2486
-2.10 m³
2487 second-eight floor
2488
7 1 1 2.10 w2
2489
3.12
2490
45.86 m³
2491
7 1 1 2.40 w2
2492
3.12
2493
52.42 m³
2494
7 1 1 2.30 w3
2495
3.12
2496
50.23 m³
2497
7 1 1 2.10 W4
2498
3.12
2499
45.86 m³
2500
1 -1 1 1.00 DDT
2501
2.10
2502
-2.10 m³
274.98 m² Total to item 6.01 E
F. To all internal wall to receive ceramic
2503

2504

wall tile,

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

B C D E F G

6 Timizing Dimension Qty Descreption

2505
Grd- FIRST floor
2506
2 1 1 5.35 G. TOILET
2507
2.00
2508
21.40 m³
2509
2 1 1 3.57
2510
2.00
2511
14.28 m³
2512
2 1 1 6.60
2513
2.00
2514
26.40 m³
2515
2 1 1 6.35 L. TOILET
2516
2.00
2517
25.40 m³
2518
2 1 1 5.21
2519
2.00
2520
20.84 m³
2521
2 1 1 4.78
2522
2.00
2523
19.12 m³
2524
2nd- 8TH floor
2525
Toilet
2526
7 1 1 7.00 On axis 2 b/n B-B'
2527
2.00
2528
98.00 m³
2529
7 1 1 7.51 On axis 3 around A-B
2530
2.00
2531
105.14 m³
2532
7 1 1 7.51
2533
2.00
2534
105.14 m³
2535
7 1 1 6.67 On axis 1 around C-D
2536
2.00
2537
93.38 m³
2538
7 1 1 7.30
2539
2.00
2540
102.20 m³
2541
7 1 1 7.51 On axis 3 around E-F
2542
1.80
2543
94.63 m³
2544
7 1 1 7.51
2545
1.80
2546
94.63 m³
2547

820.56 m² Total item 6.01F


G) To all lift shaft shear wall to receive
2548

2549

2550 Granite
BASEMENT wallFOORtile,
2551
1 1 1 2.10 lift wall
2552
3.15 W4
2553
6.62 m³
2554
1 1 1 0.25
2555
2.10
2556
0.53 m³
2557
1 1 1 1.00
2558
0.25
2559
0.25 m³
2560
1 -1 1 1.00 DDT
2561
2.10
2562
-2.10 m³
2563
5.30 m² TOTAL ITEM
2564
Grd- first floor
2565
2 1 1 2.10 lift wall
2566
3.12 W4
2567
13.10 m³
2568
2 1 1 0.25
2569
2.10
2570
1.05 m³
2571
2 1 1 1.00
2572
0.25
2573
0.50 m³
2574
2 -1 1 1.00 DDT
2575
2.10
2576
-4.20 m³
2577
second-eight floor
2578
7 1 1 2.10 lift wall
2579
3.12 W4
2580
45.86 m³
2581
7 1 1 0.25
2582
2.10
2583
3.68 m³
2584
7 1 1 1.00
2585
0.25
2586
1.75 m³
2587
7 -1 1 1.00 DDT
2588
2.10
2589
-14.70 m³
2590

2591
52.34 m² Total item 6.01G
2592

STANDARD TAKEOFF SHEET


OTT G+7 LINEAR RESIDENCE

Project:- Saving Houses B+G+8 Ty Block Type:- New B+G+8


Client:- Addis Ababa Saving Hous Block No.____________
Contractor: _____________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Timizing Dimension Qty Description

SUPER-STRUCTURE
Apply kadisco or equivalent type Quartz paint to
external plaster wall Surface according to complete
manufacturing instruction
GROUND application.
FLOOR
1 1 1 12.60 On axis 1 b/n C-E
3.30
41.58 m²
1 1 1 12.00 On axis 2 b/n A-B'
3.30
39.60 m²
Deduction
1 -1 1 4.20 W1
1.80
-7.56 m²
1 -1 1 2.75 TW-2
0.80
-2.20 m²
1 -1 1 1.10 W-11
1.80
-1.98 m²
On axis 2 b/n E-G
1 1 1 11.33
3.30
37.39 m²
1 1 1 10.60 On axis A b/n 2-4
3.30
34.98 m²
1 -1 1 7.40 Deduct WD-6
2.80
-20.72 m²
1 1 2 7.00 On axis C & E b/n 1-2
3.30
46.20 m²
1 -1 2 6.40 Deduct open area
2.80
-35.84 m²
1 1 1 14.30 On axisd G b/n 2-4
3.30
47.19 m²
1 2 -1 4.50 DDT TW-5
0.80
-7.20 m²
1 1 -1 2.70 DDT TW-6
0.80
-2.16 m²
FIRST FLOOR
1 1 1 12.60 On axis 1 b/n C-E
3.30
41.58 m²
1 1 1 12.00 On axis 2 b/n A-B'
3.30
39.60 m²
Deduction
1 -1 1 4.20 W1
1.80
-7.56 m²
1 -1 1 2.75 TW-2
0.80
-2.20 m²
1 -1 1 1.10 W-11
1.80
-1.98 m²
1 1 1 6.00 On axis 2 b/n E-F
3.30
19.80 m²
Deduction
1 -1 1 5.40 WD4
2.80
-15.12 m²
1 1 1 21.50 On axis 4 b/n A-B' & D'-F
3.30
70.95 m²
1 -2 1 5.40 Deduction
2.80 WD4'
-30.24 m²
1 -1 1 4.24 Deduction
2.80 WD-8
-11.87 m²
1 -1 1 4.28 Deduction
2.80 WD-9
-11.98 m²
1 1 1 8.84
3.30 On axis 5 b/n B'-D'
29.17 m²

1 -1 1 2.40 Deduction
0.80 W-4
-1.92 m²
1 -1 1 2.59 W-2
1.80
-4.66 m²
1 1 2 10.60 On axis A & F b/n 2-4
3.30
69.96 m²
Deduction
1 -1 2 7.40 WD-6
2.80
-41.44 m²
1 1 2 3.70 On axis B' & D' b/n 4-5
3.30
24.42 m²
Deduction
1 -1 1 3.10 W-4
0.50
-1.55 m²
1 1 2 7.00 On axis C & E b/n 1-2
3.30
46.20 m²
Deduction
1 -1 2 6.40 WD-7
2.80
-35.84 m²
Around Terrace
External
1 1 1 3.30 On Axis A, 4-5
0.80
2.64 m²
1 1 1 0.40 On Axis A, 4-5
0.60
0.24 m²
1 1 1 5.10 On Axis 5 , A-B
0.80
4.08 m²
1 1 1 1.20 On Axis 5 , A-B
0.60
0.72 m²
1 1 2 3.31 On Axis B & E ,5-6
0.80
5.30 m²
1 1 2 0.80 On Axis B & E ,5-6
0.60
0.96 m²
1 1 1 15.60 On Axis 6 ,B-E
0.80
12.48 m²
1 1 1 2.40 On Axis 6 ,B-E
0.60
1.44 m²
1 1 1 9.93 On Axis 5 ,E-G
0.80
7.94 m²
1 1 1 1.80 On Axis 5 ,E-G
0.60
1.08 m²
1 1 1 12.00 On Axis G ,2-5
0.80
9.60 m²
1 1 1 2.00 On Axis G ,2-5
0.60
1.20 m²
1 1 1 4.63 On Axis 2 ,F-G
0.80
3.70 m²
1 1 1 0.80 On Axis 2 ,F-G
0.60
0.48 m²

CONTRACTOR RESIDIENT ENGINEER QUANTITY SURVIOUR 67


OTT G+7 LINEAR RESIDENCE

Timizing Dimension Qty Description


INTERNAL
1 1 1 3.30 On Axis A, 4-5
0.60
1.98 m²
1 1 1 0.40 On Axis A, 4-5
0.40
0.16 m²
1 1 1 5.10 On Axis 5 , A-B
0.60
3.06 m²
1 1 1 1.20 On Axis 5 , A-B
0.40
0.48 m²
1 1 2 3.31 On Axis B & E ,5-6
0.60
3.97 m²
1 1 2 0.80 On Axis B & E ,5-6
0.40
0.64 m²
1 1 1 15.60 On Axis 6 ,B-E
0.60
9.36 m²
1 1 1 2.40 On Axis 6 ,B-E
0.40
0.96 m²
1 1 1 9.93 On Axis 5 ,E-G
0.60
5.96 m²
1 1 1 1.80 On Axis 5 ,E-G
0.40
0.72 m²
1 1 1 12.00 On Axis G ,2-5
0.60
7.20 m²
1 1 1 2.00 On Axis G ,2-5
0.40
0.80 m²
1 1 1 4.63 On Axis 2 ,F-G
0.60
2.78 m²
1 1 1 0.80 On Axis 2 ,F-G
0.40
0.32 m² 38.39 m²

CONTRACTOR RESIDIENT ENGINEER QUANTITY SURVIOUR 68


OTT G+7 LINEAR RESIDENCE

Timizing Dimension Qty Description


Second- eighth Floor
7 1 1 6.55 On axis 1' b/n C-D
3.30
151.31 m²
Deduction
7 -1 2 0.80 TW-3
0.60
-6.72 m²
7 1 1 6.00 On axis 1 b/n D-E
3.30
138.60 m²
Deduction
7 -1 2 2.00 W-5
1.80
-50.40 m²
7 1 1 12.00 On axis 2 b/n A-C
3.30
277.20 m²
Deduction
7 -1 1 0.80 W-8
1.80
-10.08 m²
7 -1 1 2.00 W-5
1.80
-25.20 m²
7 -1 1 0.60 TW-3
0.80
-3.36 m²
7 -1 1 1.10 W-11
1.80
-13.86 m²
7 1 1 6.00 On axis 2 b/n E-F
3.30
138.60 m²
7 -1 1 0.80 Deduction
1.80 W-8
-10.08 m²
7 1 1 21.76 On axis 4 b/n A-F
3.30
502.66 m²
Deduction
7 -1 2 2.00 W-5
1.80
-50.40 m²
7 -1 2 1.80 WD-16
2.80
-70.56 m²
7 -1 2 1.43 WD-17
2.80
-56.06 m²
7 -1 2 2.03 W-6
1.80

-51.16 m²
7 1 1 4.83 On Axis 4 b/n A-B'
0.80 BALCONY
27.05 m²
7 1 1 5.03 On Axis 4 b/n D'-E
0.80 BALCONY
28.17 m²
7 1 1 8.84 On axis 5 b/n B'-D'
3.30
204.20 m²
Deduction
7 -1 1 2.59 W-2
1.80
-32.63 m²
7 -1 1 2.40 W-4'
0.80
-13.44 m²
7 1 1 10.60 On axis A b/n 2-4
3.30
244.86 m²
Deduction
7 -1 1 2.90 W-7
1.80
-36.54 m²
7 -2 1 0.60 TW-3
0.80
-6.72 m²
7 1 1 3.70 On axis B' b/n 4-5
3.30
85.47 m²
7 1 1 6.25 b/n axis C & 1-2
3.30
144.38 m²
Deduction
7 -1 1 1.95 W-10
1.80
-24.57 m²
7 -1 1 1.85 W-9
1.80
-23.31 m²
7 2 1 1.40 On Axis C & E 1-2
0.80 Balcony
15.68 m²
7 1 1 3.70 On axis D' b/n 4-5
3.30
85.47 m²
Deduction
7 -1 1 3.10 W-4
0.50
-10.85 m²
7 1 1 5.20 On axis E b/n 1-2
3.30
120.12 m²

7 -1 1 2.00 Deduction
1.80 W-5
-25.20 m²
7 1 1 10.60 On axis F b/n 2-4
3.30
244.86 m²
Deduction
7 -1 1 2.90 W-7
1.80
-36.54 m²
7 -2 1 0.60 TW-3
0.80
-6.72 m²

CONTRACTOR RESIDIENT ENGINEER QUANTITY SURVIOUR 69


OTT G+7 LINEAR RESIDENCE

Timizing Dimension Qty Description


Above Top tie Beam
1 1 1 10.68 On axis 4 b/n A-B'
2.00
21.36 m²
1 1 0.5 12.60 On axis 1 b/N C-E
2.00
12.60 m²
1 2 0.5 5.00 On axis F b/n 2-4
2.00
10.00 m²
1 1 0.5 10.60 On axis A b/n 2-4
2.00
10.60 m² 54.56 m²
1 1 1 7.54 WATER TANKER
4.25 FRONT ELEVATION
32.05 m² On axis 5 b/n B'-D'
1 -1 1 2.59 Deduction
1.80 W-2
-4.66 m²
1 -1 1 2.40 W-4
0.80
-1.92 m²
1 1 1 3.10 RIGHT SIDE ELEVATION
4.25 On axis D', 4-5
13.18 m²
1 1 1 3.30 LEFT SIDE ELEVATION
4.25 On axis B', 4-5
14.03 m² 52.663
Balcony
7 1 1 4.83 Internal
0.60 On Axis 4 b/n A-B'
20.29 m²
Internal
7 1 1 5.03 On Axis 4 b/n D'-E
0.60
21.13 m²
Internal
7 1 1 1.40 On Axis C b/n 1-2
0.60
5.88 m²
7 1 1 1.40 Internal
0.60 On Axis E b/n 1-2
5.88 m² 53.17 m²
Concrete Gutter
1 1 1 0.84 on Axis A-C/1'-2'
22.55
18.94 m²
on Axis D'-F/1-4
1 1 1 0.84
35.98
30.22 m² 2488.63

2488.63 m² Total item 9.01

Apply three coats of approved type


plastic emulsion
Finishing paint
for Lobby andto
Corridor at
Residential Houses
a) Internal Plastered vertical surface
2nd- 3rd floor
2 1 1 6.25 On axis C b/N 2'-4
2.80
35.00 m²
2 -1 1 2.80 Deduction
1.20 D-6
-6.72 m²
2 -1 1 1.50 W-12
0.80
-2.40 m²
2 1 1 6.02 On axis 2' b/N C-D
3.00
36.12 m²
2 -1 1 2.90 Deduction
1.20 D-6
-6.96 m²
2 1 1 6.25 On axis D b/N 2'-4
2.80
35.00 m²
2 -1 1 2.80 Deduction
1.20 D-6
-6.72 m²
2 -1 1 2.80 Deduction

1.20 D-7
-6.72 m²
2 1 1 5.96 On axis 4 b/N B'-D'
2.80
33.38 m²
2 -1 1 5.64
2.80
-31.58 m²
2 -2 1 2.69 Deduction
2.80 WD-2
-30.13 m²
2 1 1 3.10 On axis D'/4-5
2.80
17.36 m²
2 -1 1 3.10 Deduction
1.50 W-4
-9.30 m²
2 1 1 5.34 On axis 5 b/N B'-D'
2.80
29.90 m²
2 -1 1 2.69 Deduction
1.80 W-2
-9.68 m²
2 1 1 0.70 Around duct
2.80
3.92 m²
4th- 8TH floor
5 1 1 6.45 On axis C b/N 2'-4
2.80
90.30 m²
5 -1 1 2.80 Deduction
1.20 D-6
-16.80 m²
5 -1 1 1.50 W-12
0.80
-6.00 m²
5 1 1 6.02 On axis 2' b/N C-D
3.00
90.30 m²
5 -1 1 2.90 Deduction
1.20 D-6
-17.40 m²
5 1 1 6.45 On axis D b/N 2'-4
2.80
90.30 m²
5 -1 1 2.80 Deduction
1.20 D-6
-16.80 m²
5 -1 1 2.80 Deduction

1.20 D-7
-16.80 m²
5 1 1 5.96 On axis 4 b/N B'-D'
2.80
83.44 m²
5 -1 1 5.64
2.80
-78.96 m²
5 -2 1 2.69 Deduction
2.80 WD-2
-75.32 m²
5 1 1 3.10 On axis D'/4-5
2.80
43.40 m²
5 -1 1 3.10 Deduction
1.50 W-4
-23.25 m²
5 1 1 5.54 On axis 5 b/N B'-D'
2.80
77.56 m²
5 -1 1 2.69 Deduction
1.80 W-2
-24.21 m²
5 1 1 0.70 Around duct
2.80
9.80 m²
290.03 m² Total item 9.02a

CONTRACTOR RESIDIENT ENGINEER QUANTITY SURVIOUR 70


OTT G+7 LINEAR RESIDENCE

Timizing Dimension Qty Description

B) exposed beams, columns and Staircases


Intermediate & Top Tie beam
Second- Third floor
2 1 2 5.40 Internal
0.22 ON AXIS 3 -(C-D)
4.75 m² FB-3

2 1 1 5.40 Bottom
0.25 ON AXIS 3 -(C-D)
2.70 m² FB-3

2 1 1 5.64 Internal
0.22 ON AXIS 4 -(C-D')
2.48 m² FB-5
2 1 1 4.75
0.22
2.09 m²
2 1 1 2.95 Bottom
0.05 ON AXIS 4 -(C-D')
0.30 m² FB-5
2 1 1 2.69
0.25
1.35 m²
2 1 1 5.34 Internal
0.22 ON AXIS 5-(B'-D')
2.35 m²
2 1 1 5.34 Bottom
0.05 ON AXIS 5-(B'-D')
0.53 m²
2 1 1 5.09
0.10
1.02 m²
2 1 1 6.25 Internal
0.22 ON AXIS C (4-2')
2.75 m² FB-9
2 1 1 3.56 Bottom
0.05 ON AXIS C (4-1)
0.36 m² FB-9
2 1 1 1.20
0.10
0.24 m²
2 1 1 1.49 W-12
0.10
0.30 m²
2 1 1 6.25 Internal
0.22 ON AXIS D -(4-2')
2.75 m² FB-10
2 1 1 3.85 Bottom
0.05 ON AXIS D -(4-1)
0.39 m² FB-10
2 1 1 2.40
0.10
0.48 m²
4TH- 7th floor
4 1 2 5.80 Internal
0.22 ON AXIS 3 -(C-D)
10.21 m² FB-3

4 1 1 5.80 Bottom
0.25 ON AXIS 3 -(C-D)
5.80 m² FB-3

4 1 1 5.84 Internal
0.22 ON AXIS 4 -(C-D')
5.14 m² FB-5
4 1 1 4.75
0.22
4.18 m²
4 1 1 3.15 Bottom
0.05 ON AXIS 4 -(C-D')
0.63 m² FB-5
4 1 1 2.89
0.25
2.89 m²
4 1 1 5.54 Internal
0.22 ON AXIS 5-(B'-D')

4.88 m²
4 1 1 5.54 Bottom
0.05 ON AXIS 5-(B'-D')
1.11 m²
4 1 1 5.09
0.10
2.04 m²
4 1 1 6.45 Internal
0.22 ON AXIS C (4-2')
5.68 m² FB-9
4 1 1 3.76 Bottom
0.05 ON AXIS C (4-2')
0.75 m² FB-9
4 1 1 1.20 WD-6
0.10
0.48 m²
4 1 1 1.49 W-12
0.10
0.60 m²
4 1 1 6.45 Internal
0.22 ON AXIS D -(4-2')
5.68 m² FB-10
4 1 1 4.05 Bottom
0.05 ON AXIS D -(4-1)
0.81 m² FB-10
4 1 1 2.40
0.10
0.96 m²
TOP TIE BEAM @ top of 8th floor
1 1 1 5.59 Internal
0.22 ON AXIS 4 -(C-D')
1.23 m² RB-5
1 1 1 4.69
0.22
1.03 m²
1 1 1 2.69 Bottom
0.25 ON AXIS 4 -(C-D')
0.67 m² RB-5
1 1 1 5.21
0.05
0.26 m²
Internal
1 1 1 6.45 ON AXIS C (4-2')
0.22 RB-8
1.42 m² Bottom
ON AXIS C (4-2')
1 1 1 2.69 RB-8
0.10
0.27 m² Internal
1 1 1 6.45 ON AXIS D (4-2')
0.22 RB-8
1.42 m²
Bottom
1 1 1 2.40 ON AXIS D (4-2')
0.10 RB-8
0.24 m²
1 1 1 4.05
0.05 Internal
ON AXIS C-D (5-4)
1 1 2 3.45 RB-1
0.22
1.52 m² Bottom
ON AXIS C-D (5-4)
1 1 1 3.45 RB-1
0.25
0.86 m² Internal
ON AXIS 4-5 (B'-D')
1 1 1 3.10 RB-9
0.22
0.68 m² Bottom
ON AXIS 4-5 (B'-D')
1 1 1 3.10 RB-9
0.05
0.16 m²
1 1 1 5.59 Internal
0.22 ON AXIS 5 (B'-D')
1.23 m²
1 1 1 5.09 Bottom
0.25 ON AXIS 5 (B'-D')
1.27 m²
1 1 1 0.50
0.05
0.03 m²
88.97 m²

CONTRACTOR RESIDIENT ENGINEER QUANTITY SURVIOUR 71


OTT G+7 LINEAR RESIDENCE

Timizing Dimension Qty Description


EXPOSED COLUMNS
A) Elevation columns
Ground floor
1 1 1 0.60 On axis 6 b/n B-E
2.80
1.68 m²
1 1 1 1.60 ON AXIS 4 & 5, C' & D
2.80
4.48 m²
1 1 1 1.60 FIRST FLOOR
2.80 ON AXIS 4 & 5, C' & D
4.48 m²
Second- Third Floor
2 2 1 2.80 ON AXIS 3 C & D
2.80
31.36 m²
2 2 1 1.30
0.20
1.04 m²
2 1 1 0.45 ON AXIS 4 & D'
2.80
2.52 m²
2 1 1 0.40
0.20
0.16 m²
2 1 1 0.95 On axis 5 C'-D'
2.80
5.32 m²
2 1 1 0.80
0.20
0.32 m²
Fourth- Eigth Floor
5 2 1 1.60 ON AXIS 3 C & D
2.80
44.80 m²
5 2 1 0.70
0.20
1.40 m²
5 1 1 0.25 ON AXIS 4 & D'
2.80
3.50 m²
5 1 1 0.20
0.20
0.20 m²
5 1 1 0.55 On axis 5 C'-D'
2.80
7.70 m²
5 1 1 0.40
0.20
0.40 m²
109.36 m² Total To Item 9.02b
main stair case
Ground-8th Floor
9 1 1 2.40 SECTION A-A
1.03 sofit
22.25 m³
9 1 1 1.03 Landing 1
1.27
11.77 m³
9 1 1 2.40 side
0.22
4.75 m³
1 7 0.5 0.29 Riser side
0.15
0.15 m³
SECTION B-B
9 1 1 1.93 sofit
1.03
17.89 m³
9 1 1 1.27 Landing 1
1.03
11.77 m³
9 1 1 1.93 side
0.22
3.82 m³
1 7 0.5 0.29 Riser side
0.15
0.15 m³
SECTION C-C
9 1 1 2.00 sofit
1.15
20.70 m³
9 1 1 2.00 side
0.22
3.96 m³
1 5 0.5 0.29 Riser side
0.15
0.11 m³
97.32 m²
295.65 m² Total Item to Exposed Beam & Column

C. Internal Lift wall and Retaining Wall


Ground Floor
1 1 0.5 2.30 On Axis B'/4-5
3.30
3.80 m²
1 1 0.5 2.60 On Axis 4/B-C'
3.30
4.29 m²

First Floor
1 1 0.5 2.60 On Axis 4/B-C'
3.30
4.29 m²

2nd-8th floor
1 1 0.5 2.40 On Axis 4/B-C'
3.30
3.96 m²

16.34 m² Total Item to 9.02.C

CONTRACTOR RESIDIENT ENGINEER QUANTITY SURVIOUR 72


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc
Project:- Saving Houses B+G+8 Typolog Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses D Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Timizing Dimension Qty Descreption
SUPER-STRUCTURE
FINISHING
Wall finishing
50mm thick cement sand screed smoothly finished flooring in mortar mix
(1:3) at basement garage.
2nd- 3rd floor
3-bed room (C-E)
2 1 1 3.60 M.B.ROOM
3.00
21.60 m²
2 1 1 1.60
1.30
4.16 m²
2 -1 1 0.40 deduction for column in MB
0.40
-0.32 m²
2 1 1 2.73 B.ROOM 1
3.30
18.02 m²
2 -1 1 0.18 deduction for column in BR1
0.40
-0.14 m²
2 1 1 3.15 B.ROOM 2
2.00
12.60 m²
2 -1 1 0.40 deduction for column in BR2
0.40
-0.32 m²
2 1 1 7.03 LIVING & DINING ROOM
5.98
84.08 m²
2 -2 1 0.40 deduction for Balcony and column in Living dining column
0.23 on Axis 3
-0.37 m²
2 -1 1 0.40 on Axis 2
0.60
-0.48 m²
2 -1 1 0.40
0.32
-0.26 m² Balcony
2 -1 1 1.18
2.08
-4.91 m²
2 1 1 3.55 CORRIDOR
1.37
9.73 m²
2 1 1 2.98
1.50
8.94 m²
2 1 1 2.90
0.80
4.64 m²
3-bed room (A-B')
2 1 1 4.02 B.ROOM 2
2.20
17.69 m²
2 -1 1 0.40 Deduct column contact area
0.18
-0.14 m²
2 1 1 3.52 M.B.ROOM
3.68
25.91 m²
2 1 1 1.00
0.50
1.00 m²
2 -1 1 0.40 Deduct for column in MB
0.40
-0.32 m²
2 1 1 2.50 CORRIDOR
3.30
16.50 m²
2 1 1 6.00
1.37
16.44 m²
2 -1 1 0.78 Deduct column contact area
0.77
-1.20 m²
2 1 1 3.48 B.ROOM 1
3.48
24.22 m²
2 -1 1 0.40 deduction for column in BR1
0.40
-0.32 m²
2 1 1 4.95 LIVING & DINING ROOM
3.62
35.84 m²
2 -1 1 0.40 deduction for column in Living dining column
0.60
-0.48 m²
2-bed room
2 1 1 5.10 LIVING & DINING ROOM
4.10
41.82 m²
2 -1 1 0.23 deduction for column in Living dining column
0.60
-0.28 m²
2 1 1 5.13 CORRIDOR
0.93
9.54 m²
2 1 1 2.52 M.B.ROOM
5.03
25.35 m²
2 -1 1 0.23 deduction for column in MB
0.23
-0.11 m²
2 -1 1 0.23
0.40
-0.18 m²
2 1 1 4.50 B.ROOM 1
2.15
19.35 m²
2 1 1 3.00 store
1.83
10.98 m²
3-bed room (D'-F)
2 1 1 2.00 B.ROOM 2
4.05
16.20 m²
2 1 1 3.70 M.B.ROOM
3.52
26.05 m²
2 -1 1 0.40 deduction for column in MB
0.40
-0.32 m²
2 1 1 3.12 CORRIDOR
2.48
15.48 m²
2 1 1 6.38
1.57
20.03 m²
2 -1 1 0.38 deduction for column in corridor
0.17
-0.13 m²
2 -1 1 0.60
0.17
-0.20 m²
2 1 1 3.48 B.ROOM 1
3.47
24.15 m²
2 -1 1 0.40 deduction for column in BR1
0.40
-0.32 m²
2 1 1 5.13 LIVING & DINING ROOM
3.61
37.04 m²
2 -1 1 0.40 deduction for column in Living dining
0.60
-0.48 m²
2 1 1 2.69 B/N axis 4-5 & C-D
3.45 ENTRANCE LOBBY
18.56 m²
2 1 1 1.14 B/N axis 4-5 & C-D

0.53 ENTRANCE LOBBY


1.21 m²
4th-8th floor
3-bed room (C-E)
5 1 1 3.60 M.B.ROOM
3.00
54.00 m²
5 1 1 1.60
1.30
10.40 m²
5 -1 1 0.27 deduction for column in MB
0.27
-0.36 m²
5 1 1 2.73 B.ROOM 1
3.30
45.05 m²
5 -1 1 0.12 deduction for column in BR1
0.30
-0.18 m²
5 1 1 3.15 B.ROOM 2
2.00
31.50 m²
5 -1 1 0.30 deduction for column in BR2
0.30
-0.45 m²
5 1 1 7.03 LIVING & DINING ROOM
5.98
210.20 m²
5 -2 1 0.30 deduction for Balcony and column in Living dining column
0.23 on Axis 3
-0.69 m²
5 -1 1 0.27 on Axis 2
0.40
-0.54 m²
5 -1 1 0.27
0.21
-0.28 m² Balcony
5 -1 1 1.18
2.08
-12.27 m²
5 1 1 3.55 CORRIDOR
1.37
24.32 m²
5 1 1 2.98
1.50
22.35 m²
5 1 1 2.90
0.80
11.60 m²
3-bed room (A-B')
5 1 1 4.02 B.ROOM 2
2.20
44.22 m²
5 -1 1 0.27 Deduct column contact area
0.12
-0.16 m²
5 1 1 3.52 M.B.ROOM
3.68
64.77 m²
5 1 1 1.00
0.50
2.50 m²
5 -1 1 0.27 Deduct for column in MB
0.27
-0.36 m²
5 1 1 2.50 CORRIDOR
3.30
41.25 m²
5 1 1 6.00
1.37
41.10 m²
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


5 -1 1 0.78 Deduct column contact area
0.77
-3.00 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


5 1 1 3.48 B.ROOM 1
3.48
60.55 m²
5 -1 1 0.27 deduction for column in BR1
0.27
-0.36 m²
5 1 1 4.95 LIVING & DINING ROOM
3.62
89.60 m²
5 -1 1 0.27 deduction for column in Living dining column
0.40
-0.54 m²
2-bed room
5 1 1 5.10 LIVING & DINING ROOM
4.10
104.55 m²
5 -1 1 0.23 deduction for column in Living dining column
0.40
-0.46 m²
5 1 1 5.13 CORRIDOR
0.93
23.85 m²
5 1 1 2.52 M.B.ROOM
5.03
63.38 m²
5 -1 1 0.23 deduction for column in MB
0.23
-0.26 m²
5 -1 1 0.23
0.40
-0.46 m²
5 1 1 4.50 B.ROOM 1
2.15
48.38 m²
5 1 1 3.00 store
1.83
27.45 m²
3-bed room (D'-F)
5 1 1 2.00 B.ROOM 2
4.05
40.50 m²
5 1 1 3.70 M.B.ROOM
3.52
65.12 m²
5 -1 1 0.27 deduction for column in MB
0.27
-0.36 m²
5 1 1 3.12 CORRIDOR
2.48
38.69 m²
5 1 1 6.38
1.57
50.08 m²
5 -1 1 0.38 deduction for column in corridor
0.17
-0.32 m²
5 -1 1 0.60
0.17
-0.51 m²
5 1 1 3.48 B.ROOM 1
3.47
60.38 m²
5 -1 1 0.27 deduction for column in BR1
0.27
-0.36 m²
5 1 1 5.13 LIVING & DINING ROOM
3.61
92.60 m²
5 -1 1 0.27 deduction for column in Living dining
0.40
-0.54 m²
5 1 1 2.69 B/N axis 4-5 & C-D
3.45 ENTRANCE LOBBY
46.40 m²
5 1 1 1.14 B/N axis 4-5 & C-D

0.53 ENTRANCE LOBBY


3.02 m²
1951.20 m² Total item 7.01
280x30mm Terrazo window sill cut to appropriate size, weathered and mounted on

GROUND FLOOR
1 1 1 4.20 W-1
4.20 ml
1 1 1 2.75 TW-2
2.75 ml
1 1 1 1.10 W-11
1.10 ml
1 1 1 2.40 W-4
2.40 ml
1 1 1 3.10
3.10 ml
FIRST FLOOR
1 1 1 4.20 W-1
4.20 ml
1 1 1 2.75 TW-2
2.75 ml
1 1 1 1.10 W-11
1.10 ml
1 1 1 2.40 W-4
2.40 ml
1 1 1 3.10
3.10 ml
1 1 1 2.59 W-2
2.59 ml
2ND- 8TH FLOOR
7 1 2 2.00 on axis 1 W-5
28.00 ml
7 1 2 0.60 on axis 1' TW-3
8.40 ml
7 1 1 2.00 on axis 2 W-5
14.00 ml
7 1 2 0.80 W-8
11.20 ml
7 1 1 0.60 TW-3
4.20 ml
7 1 1 1.10 W-11
7.70 ml
7 1 2 2.00 on axis 4 W-5
28.00 ml
7 1 2 2.03 W-6
28.42 ml
on axis 5
7 1 1 2.59 W-2
18.13 ml
7 1 1 2.40 W-4'
16.80 ml
on axis A
7 1 1 2.90 W-7
20.30 ml
7 1 2 0.60 TW-3
8.40 ml
on axis C
7 1 1 1.95 W-10
13.65 ml
7 1 1 1.85 W-9
12.95 ml
on axis D'
7 1 1 3.10 W-4
21.70 ml
on axis E
7 1 1 2.00 W-5
14.00 ml
on axis F
7 1 1 2.90 W-7
20.30 ml
7 1 2 0.60 TW-3
8.40 ml
314.24 ml Total item 7.02
20mm thick white terazzo tile bull nosed window sill
bedded in cement mortar 1:3
1ST Floor on Terrace
On Axis A, 4-5
1 1 1 3.30
3.30 ml
On Axis A, 4-5
1 1 1 0.40
0.40 ml
On Axis 5 , A-B
1 1 1 0.60
0.60 ml
On Axis 5 , A-B
1 1 1 1.00
1.00 ml
On Axis B & E ,5-6
1 1 2 3.10
6.20 ml
On Axis B & E ,5-6
1 1 2 0.80
1.60 ml
On Axis 6 ,B-E
1 1 1 15.80
15.80 ml
On Axis 6 ,B-E
1 1 1 2.60
2.60 ml
On Axis 5 ,E-G
1 1 1 9.73
9.73 ml
On Axis 5 ,E-G
1 1 1 1.80
1.80 ml
On Axis G ,2-5
1 1 1 12.30

12.30 ml

On Axis G ,2-5
1 1 1 2.00
2.00 ml
On Axis 2 ,F-G
1 1 1 5.43
5.43 ml
62.76 ml Total item 7.12

377.00 ml Total item 7.02 & 7.12

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


B. Terrazzo copping on verendah, balcony & roof parapet of
size 180*30mm
On Axis 4 b/n A-B'
7 1 1 4.83 BALCONY
33.81 ml
On Axis 4 b/n D'-E
7 1 1 5.03 BALCONY
35.21 ml
On Axis E b/n 1-2
7 1 1 1.42 BALCONY
9.94 ml
On Axis C b/n 1-2
7 1 1 1.40 BALCONY
9.80 ml

88.76 ml Total item 7.02B

Marble flooring to stair case bedded on and including cement sand mortar mix
1:3 and jointsgrouted in appropriate color filler setting coat mortar. Pattern and color of the
tile shall be approved by the architect.

20mm thick to landing.

Basement floor
1 1 1 1.09 STAIR 1
1.14
1.24 m²
1 -1 1 0.45 deduct column area
0.80
-0.36 m²

1 1 1 1.42
1.08
1.53 m²
GRD-8TH FLOOR
9 1 1 1.09 STAIR 1
1.14
11.18 m²
9 -1 1 0.45 deduct column area
0.80
-3.24 m²
9 1 1 1.42
1.08
13.80 m²
GRD- FLOOR
STAIR 2
1 1 2 2.20
1.98
8.71 m²
32.86 m² Total item 20mm thick landing

SHOP STAIR
GRD- FLOOR
1 2 10 1.05 - Tread size 30x340mm
0.34
7.14
Main stair
Basement floor
0.34 - Tread size 30x340mm
1 1 7 1.10 section A-A
2.62
0.34
1 1 5 1.10 section B-B
1.87
0.34
1 1 12 1.15 section C-C
4.69 9.18
GRD-8TH FLOOR
0.34 - Tread size 30x340mm
9 1 7 1.09 section A-A
23.35
0.34
9 1 5 1.10 section B-B
16.83
0.34
9 1 7 1.15 section C-C
24.63 64.81
81.13 Total item tread size 30x340mm

Border marble
0.15 ground floor
1 1 2 3.70 WD-6
1.11
0.15 WD-7
1 1 2 6.40
1.92
0.15 First floor
1 1 2 6.40 WD-7
1.92
0.15
1 1 1 5.40 WD-4
0.81
0.15
1 1 2 3.70 WD-6
1.11
6.87 Total item Boarder Marble

SHOP STAIR
GRD- FLOOR
1 2 10 0.14 Riser size 20x10mm
1.15
3.22
Main Stair
Basement floor
0.34 Riser size 20x10mm
1 1 7 1.10 section A-A
2.62
0.34
1 1 5 1.10 section B-B
1.87
0.34
1 1 12 1.15 section C-C
4.69 9.18

GRD-8TH FLOOR
0.14 Riser size 20x10mm
9 1 7 1.10 section A-A
9.70
0.14
9 1 5 1.10 section B-B
6.93
0.14
9 1 7 1.15 section C-C
10.14
#REF!
39.17 Total item of Riser 20x10mm

Supply and fix 200x150x6 mm white glazed Ceramic wall tiles stuck to wall with
cement mortar mix (1:2) backing and 2 mm joints to be grouted in white cement.

Grd- First floor


2 1 1 5.35 G. TOILET
2.00
21.40 m³
2 1 1 3.57
2.00
14.28 m³
2 1 1 6.60
2.00
26.40 m³
2 1 1 6.35 L. TOILET
2.00
25.40 m³
2 1 1 5.21
2.00
20.84 m³
2 1 1 4.78
2.00
19.12 m³
2nd- 8TH floor
7 1 1 7.00 On axis 2 b/n B-B'
1.80
88.20 m³
7 1 1 7.51 On axis 3 around A-B
1.80
94.63 m³
7 1 1 7.51
1.80
94.63 m³
7 1 1 6.67 On axis 1 around C-D
1.80
84.04 m³
7 1 1 7.30
1.80
91.98 m³
7 1 1 7.51 On axis 3 around E-F
1.80
94.63 m³
7 1 1 7.51
1.80
94.63 m³
KITCHEN
7 1 1 1.10 B/N axis 2 & B-C
1.50
11.55 m²
7 1 1 2.05 B/N axis 3-4 & B-C
1.50
21.53 m²
7 1 1 1.58 B/N axis 3-4 & D-E
1.50
16.59 m²
7 1 1 2.00 B/N axis 1-2 & D'-E
1.50
21.00 m²
840.85 m² Total item 7.04
Ditto but for lift shaft
GRANITE WALL CLADDING
Ground
1 1 1 2.10 W4
3.00
6.30 m²
1 1 -1 2.10 DDT OPENING
1.00
-2.10 m²
first
1 1 1 2.10 W4
3.00
6.30 m²
1 1 -1 2.10 DDT OPENING
1.00
-2.10 m²
2nd to 8th
7 1 1 2.30 W4
3.00
48.30 m²
7 1 -1 2.10 DDT OPENING
1.00
-14.70 m²
42.00 m² Total item 7.05

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


100mm thick precast concrete pavement in concrete class C-15 around the
building open jointed on and including 400mm selected material compacted
fill and 100mm thick redash or equivalent bedding material.
1 1 1 127.77 Around the Building
1.00
127.77 m²
1 -2 1 4.00 deduct ramp area
1.00
-8.00 m²
119.77 m² Total item 7.06 a

half ditch
1 1 1 119.77
119.77 ml

119.77 ml Total item 7.06 b

Apply 42mm thick cement screed in 1:3 cement mortar ratio


to receive porceline ceramic tile, Marble and ceramic tiles.
GRD FLOOR
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 2
56.94 m²
1 -2 1 0.40 deduction for column in GRD floor
0.60
-0.48 m²
1 -2 1 0.40
0.21
-0.17 m²
1 1 1 11.98 B/N axis 1-2' & D'-E
6.00 SHOP 3
71.88 m²
1 -2 1 0.40 deduction for column
0.19
-0.15 m²
1 -2 1 0.20
0.60
-0.24 m²
1 -2 1 0.40
0.18
-0.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 SHOP 1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 6.03
5.02
30.27 m²

1 1 1 5.80 B/N axis 3-4 & E-F


5.15 SHOP 4
29.87 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 6.03 B/N axis 3-4 & D'-E
5.14 SHOP 5
30.99 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.23
0.22
-0.05 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 5.01 B/N axis 3-4 & C-D
3.99 SHOP 6
19.99 m²
1 -1 1 0.25 deduction for column
0.18
-0.05 m²
FIRST FLOOR
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 7
56.94 m²
1 -2 1 0.40 deduction for column
0.60
-0.48 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 9.49 B/N axis 1-2' & D'-E
6.00 SHOP 8
56.94 m²
1 -2 1 0.60 deduction for column
0.20
-0.24 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 2.69
6.00
16.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 Café & Restaurant #1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 5.92 B/N axis 2-3 & E-F
5.15 SHOP 9
30.49 m²
1 -2 1 0.60 deduction for column
0.60
-0.72 m²
1 1 1 15.72 B/N axis 3-4 & C'-F
5.01 Café & Restaurant #2
78.76 m²
1 -2 1 0.25 deduction for column
0.60
-0.30 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -2 1 0.50
0.60
-0.60 m²
1 -1 1 0.17
0.40
-0.07 m²
1 1 1 2.91 B/N axis 3-4 & B-C'
8.18 SHOP 10
23.80 m²
1 -1 1 0.18
0.60
-0.11 m²
CORRIDOR
1 1 1 6.06 FOR GROUND FLOOR
2.49
15.09 m²
1 1 1 5.18
1.00
5.18 m²
1 1 1 7.84 Entrance lobby
4.76
37.32 m²
1 1 1 1.50
0.29
0.44 m²
1 -1 1 0.26 Deduction for column
0.40
-0.10 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.35
0.17
-0.06 m²
1 -1 1 0.60
0.29
-0.17 m²
Verenda 1-3
1 1 1 3.55 B/N axis 4-5 & A-B
6.15
21.83 m²
1 1 1 4.63 B/N axis 4-6 & B-B'
7.45
34.49 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 4.63 B/N axis 4-6 & D'-E
7.45
34.49 m²
1 1 1 11.53 B/N axis 4-5 & E-G
3.55
40.93 m²
1 1 1 10.45 B/N axis 2-4 & F-G
5.28
55.18 m²
1 1 1 3.45 B/N axis 4-5 & C-D
2.69 APARTMENT ENTRANCE LOBBY
9.28 m²
1 1 1 1.14 B/N axis 4-5 & C-D
0.53 APARTMENT ENTRANCE LOBBY
0.60 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


1 1 1 12.26 FOR FIRST FLOOR
2.49
30.53 m²
1 1 1 8.18 lobby
1.93
15.79 m²
1 -1 1 0.60 Deduction for column
0.27
-0.16 m²
1 -2 1 0.46
0.27
-0.25 m²
1 1 1 3.45 B/N axis 4-5 & C-D
2.69 APARTMENT ENTRANCE LOBBY
9.28 m²
1 1 1 1.14 B/N axis 4-5 & C-D
0.53 APARTMENT ENTRANCE LOBBY
0.60 m²
CAFETERIA TERACE
1 1 1 3.55 B/N axis 4-5 & A-B
6.15
21.83 m²
1 1 1 4.63 B/N axis 4-6 & B-B'
7.45
34.49 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 4.63 B/N axis 4-6 & D'-E
7.45
34.49 m²
1 1 1 11.53 B/N axis 4-5 & E-G
3.55
40.93 m²
1 1 1 10.45 B/N axis 2-4 & F-G
5.28
55.18 m²
1172.19 m² Total item 7.07

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Supply and fix 8mm thick non slippery porcelain ceramic floor tiles. Price includes tiles,
adhesives glue, cross spacers, sealant, and all accessories. Size, pattern, quality and color
shall be approved by the architect.
GRD FLOOR
Verendah
1 1 1 12.00 B/N axis 1-2 & A-B
7.00
84.00 m²
1 1 1 6.00 B/N axis 1-2 & E-F
7.00
42.00 m²
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 2
56.94 m²
1 -2 1 0.40 deduction for column in GRD floor
0.60
-0.48 m²
1 -2 1 0.40
0.21
-0.17 m²
1 1 1 11.98 B/N axis 1-2' & D'-E
6.00 SHOP 3
71.88 m²
1 -2 1 0.40 deduction for column
0.19
-0.15 m²
1 -2 1 0.20
0.60
-0.24 m²
1 -2 1 0.40
0.18
-0.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 SHOP 1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 6.03
5.02
30.27 m²

1 1 1 5.80 B/N axis 3-4 & E-F


5.15 SHOP 4
29.87 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 6.03 B/N axis 3-4 & D'-E
5.14 SHOP 5
30.99 m²
1 -1 1 0.40 deduction for column
0.22
-0.09 m²
1 -1 1 0.23
0.22
-0.05 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.40
0.50
-0.20 m²
1 1 1 5.01 B/N axis 3-4 & C-D
3.99 SHOP 6
19.99 m²
1 -1 1 0.25 deduction for column
0.18
-0.05 m²
CORRIDOR
1 1 1 6.06 FOR GROUND FLOOR
2.49
15.09 m²
1 1 1 5.18
1.00
5.18 m²
1 1 1 7.84 Entrance lobby
4.76
37.32 m²
1 1 1 1.50
0.29
0.44 m²
1 -1 1 0.26 Deduction for column
0.40
-0.10 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -1 1 0.35
0.17
-0.06 m²
1 -1 1 0.60
0.29
-0.17 m² 476.86 m²

FIRST FLOOR
1 1 1 9.49 B/N axis 1-2' & C-D
6.00 SHOP 7
56.94 m²
1 -2 1 0.40 deduction for column
0.60
-0.48 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 9.49 B/N axis 1-2' & D'-E
6.00 SHOP 8
56.94 m²
1 -2 1 0.60 deduction for column
0.20
-0.24 m²
1 -2 1 0.40
0.20
-0.16 m²
1 1 1 2.69
6.00
16.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
4.72 Café & Restaurant #1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²
1 1 1 5.92 B/N axis 2-3 & E-F
5.15 SHOP 9
30.49 m²
1 -2 1 0.60 deduction for column
0.60
-0.72 m²
1 1 1 15.72 B/N axis 3-4 & C'-F
5.01 Café & Restaurant #2
78.76 m²
1 -2 1 0.25 deduction for column
0.60
-0.30 m²
1 -1 1 0.35
0.60
-0.21 m²
1 -2 1 0.50
0.60
-0.60 m²
1 -1 1 0.17
0.40
-0.07 m²
1 1 1 2.91 B/N axis 3-4 & B-C'
8.18 SHOP 10
23.80 m²
1 -1 1 0.18
0.60
-0.11 m²
CORRIDOR
1 1 1 12.26 FOR FIRST FLOOR
2.49
30.53 m²
1 1 1 8.18 lobby
1.93
15.79 m²
1 -1 1 0.60 Deduction for column
0.27
-0.16 m²
1 -2 1 0.46
0.27
-0.25 m² 361.43 m²
CAFETERIA TERACE
1 1 1 3.55 B/N axis 4-5 & A-B
6.15
21.83 m²
1 1 1 4.63 B/N axis 4-6 & B-B'
7.45
34.49 m²
1 1 1 8.84 B/N axis 5-6 & B'-D'
3.75
33.15 m²
1 1 1 4.63 B/N axis 4-6 & D'-E
7.45
34.49 m²
1 1 1 11.53 B/N axis 4-5 & E-G
3.55
40.93 m²
1 1 1 10.45 B/N axis 2-4 & F-G
5.28
55.18 m²
1 1 -1 5.25 ddt column
1.00
-5.25 m² 214.82 m²

1053.11 m² Total item 7.08

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Supply and fix 10cm high porcelain skirting
Ground floor
B/N axis 1-2' & C-D
1 1 1 20.03 SHOP 2
20.03 ml
B/N axis 1-2' & D'-E
1 1 1 28.85 SHOP 3
28.85 ml
B/N axis 2-3 & A-B
1 1 1 12.77 SHOP 1
12.77 ml
B/N axis 3-4 & E-F
1 1 1 16.49 SHOP 4
16.49 ml
B/N axis 3-4 & D'-E
1 1 1 19.35 SHOP 5
19.35 ml
B/N axis 3-4 & C-D
1 1 1 9.17 SHOP 6
9.17 ml
1 1 1 11.76 CORRIDOR
11.76 ml
VERENDA
1 1 1 12.60 On Axis 1-2 & A-B
12.60 ml
1 1 1 6.60 On Axis 1-2 & E-F
6.60 ml
First floor
B/N axis 1-2' & C-D
1 1 1 20.03 SHOP 7
20.03 ml
B/N axis 1-2' & D'-E
1 1 1 20.03 SHOP 8
20.03 ml
B/N axis 2-3 & A-B
1 1 1 15.92 Café & Restaurant #1
15.92 ml
B/N axis 2-3 & E-F
1 1 1 9.64 SHOP 9
9.64 ml
B/N axis 3-4 & C-F
1 1 1 22.86 Café & Restaurant #2
22.86 ml
B/N axis 3-4 & B-C
1 1 1 11.35 SHOP 10
11.35 ml
1 1 1 6.88 CORRIDOR
6.88 ml
CAFETERIA TERACE
on axis A,5 b/n 4-5 , A-B
1 1 1 9.65
9.65 ml
B/N axis 5-6 & B'-D'
1 1 1 25.90
25.90 ml
B/N axis 5-6 & B'-D'
1 1 1 30.81
30.81 ml 66.36 ml
1 1 1 16.24 B/N axis 4-5 & B'-D'
16.24 ml
189.31 ml
326.93 ml Total item 7.08
Supply and fix 8mm thick non slippery ceramic floor tiles. Price includes tiles, adhesives
glue, cross spacers, sealant, and all accessories. Size, pattern, quality and color shall be
approved by the architect.

Grnd- 1st Floor


Gent's Toilet
2 1 1 1.70 B/N axis 2-3 & B-B'
1.27
4.32 m²
2 1 1 1.70
0.90
3.06 m²
2 1 1 2.85
2.33
13.28 m²
2 -1 1 0.40 Deduct Column and HCB Contact Area
0.60
-0.48 m²
2 -1 1 0.30
0.30
-0.18 m²
2 -1 1 0.30
0.40
-0.24 m²
2 -1 1 0.40
0.10
-0.08 m²
2 1 1 1.70 Lent's Toilet
1.09
3.71 m²
2 1 1 1.31
1.70
4.45 m²
2 1 1 1.70
2.60
8.84 m²
2 -1 1 0.60 Deduct Column Contact Area
0.25
-0.30 m² 36.38 m²
2ND-8TH FLOOR
7 1 1 2.07 BATHROOM
1.78 B/N axis 2 & B-B'
25.79 m²
7 -1 1 0.30 Deduct pipe area
0.20
-0.42 m²
7 1 1 2.58 B/N axis 3 & A-B'
1.48
26.73 m²
7 1 1 2.58
1.42
25.65 m²
7 -1 1 0.50 Deduct column and pipe area
0.40
-1.40 m²
7 -2 1 0.30
0.30
-1.26 m²
7 1 1 2.20 B/N axis 1 & C-D'
1.47
22.64 m²
7 1 1 2.20
1.47
. 22.64 m²
7 -1 1 0.50 Deduct column and pipe area
0.35
-1.23 m²
7 -2 1 0.40
0.15
-0.84 m²
7 1 1 2.58 B/N axis 3 & E-F
1.42
25.65 m²
7 1 1 2.58
1.47
26.55 m²
7 -1 1 0.50 Deduct column and pipe area
0.40
-1.40 m²
7 -2 1 0.30
0.30
-1.26 m²
KITCHEN
7 1 1 3.15 B/N axis 2 & B-C
2.07
45.64 m²
7 -2 1 0.60 Deduct Column Contact Area
0.40
-3.36 m²
7 1 1 3.23 B/N axis 3-4 & B-C
3.50
79.14 m²
7 -1 1 0.40 Deduct Pipe Area
0.35
-0.98 m²
7 1 1 3.18 B/N axis 3-4 & D-E
3.46
77.02 m²
7 1 1 0.60 Deduct column and pipe area
0.35
1.47 m²
7 -1 1 0.40
0.30
-0.84 m²
7 1 1 2.25 B/N axis 1-2 & D'-E
2.70
42.53 m²
BALCONY
7 1 2 4.23 B/N axis 4-5 & A-C , D'-F
1.10
65.14 m²
7 1 1 1.75 B/N axis 1-2 & C-C'
1.80
22.05 m²
7 1 1 1.10 B/N axis 1-2 & D'-E
1.80
13.86 m²
7 1 1 0.70
0.20
0.98 m²
510.49 m²
546.87 m² Total item 7.08
Supply and fix 10cm high ceramic skirting
2ND-8TH FLOOR
BALCONY
7 1 2 5.83 B/N axis 4-5 & A-C , D'-F
81.62
7 1 1 4.90 B/N axis 1-2 & C-C'
34.30
7 1 1 3.02 B/N axis 1-2 & D'-E
21.14
KITCHEN
7 1 1 10.45 B/N axis 2 & B-C
73.15
7 1 1 13.33 B/N axis 3-4 & B-C
93.31
7 1 1 13.92 B/N axis 3-4 & D-E
97.44
7 1 1 9.20 B/N axis 1-2 & D'-E
64.40
465.36 Total item 7.09

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Supply and fix 20mm thick marble floor tiles. Price shall include cement
screed, mirror polishing and all necessary works.
GROUND FLOOR
1 1 1 2.91 B/N axis 4-5 & C-D
3.45 APARTMENT ENTRANCE LOBBY
10.04 m²
1 1 1 1.40 B/N axis 4-5 & C-D
0.85 APARTMENT ENTRANCE LOBBY
1.19 m²
VERENDA
1 1 1 10.78 B/N axis 4-5 & A-C

3.60
38.81 m²
1 1 1 10.78 B/N axis 4-5 & D'-F

3.60
38.81 m²
1 1 1 18.22 B/N axis 5-6 & B-E

3.70
67.41 m² 156.26 m²
First floor
1 1 1 2.91 B/N axis 4-5 & C-D

3.45 APARTMENT ENTRANCE LOBBY


10.04 m²
1 1 1 1.40 B/N axis 4-5 & C-D

0.85 APARTMENT ENTRANCE LOBBY


1.19 m² 167.49 m²
2nd- 8TH floor
7 1 1 2.91 B/N axis 4-5 & C-D

3.45 ENTRANCE LOBBY


70.28 m²
7 1 1 1.40 B/N axis 4-5 & C-D

0.85
8.33 m²
7 1 1 5.92 B/N axis 2'-4 & C-D

6.85 LOBBY
283.86 m²
7 1 -1 0.58 DDT COL

0.60
-2.44 m²
360.03 m²
527.52 m² Total item 7.10
Supply and fix 10cm high Marble skirting
GROUND FLOOR
B/N axis 4-5 & C-D
1 1 1 6.03 APARTMENT ENTRANCE LOBBY
6.03
VERENDA
1 1 1 5.70 B/N axis 4-5 & A-C
5.70
1 1 1 17.44 B/N axis 4-5 & D'-F
17.44
1 1 1 5.70 B/N axis 5-6 & B-E
5.70
1ST FOOR
1 1 1 6.03 APARTMENT ENTRANCE LOBBY
6.03
2nd- 8TH floor
7 1 1 19.46
136.22

Staircase Skirting
Shop Stair
1 1 1 6.00 Ground floor
6.00 Staircase skirting
1 1 1 6.16
6.16 landing skirting
Main Stair
1 1 1 5.25 Basement floor
5.25 Staircase skirting
1 1 1 4.44
4.44 landing skirting
Gnd-8th floor
9 1 1 5.36 Staircase skirting
48.24
9 1 1 4.24 landing skirting
38.16
285.37 Total item 7.11

Ditto but 30x3cm marble threshold bedded on cement mortar (1:3) ratio. Price shall
include cement screed, mirror polishing and all necessary works.

7 1 4 0.30 2nd- 8TH floor


1.20
10.08 Total item 7.13

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Gypsum Plastering
Finishing for Lobby and Corridor at Residential Houses
a) Internal Plastered vertical surface
2nd- 3rd floor
2 1 1 6.25 On axis C b/N 2'-4
2.80
35.00 m²
2 -1 1 2.80 Deduction
1.20 D-6
-6.72 m²
2 -1 1 1.50 W-12
0.80
-2.40 m²
2 1 1 6.02 On axis 2' b/N C-D
3.02
36.36 m²
2 -1 1 2.90 Deduction
1.20 D-6
-6.96 m²
2 1 1 6.25 On axis D b/N 2'-4
2.80
35.00 m²
2 -1 1 2.80 Deduction
1.20 D-6
-6.72 m²
2 -1 1 2.80 Deduction
D-7
1.20
-6.72 m²
2 1 1 5.96 On axis 4 b/N B'-D'
2.80
33.38 m²
2 -1 1 5.64
2.80
-31.58 m²
2 -2 1 2.69 Deduction
2.80 WD-2
-30.13 m²
2 1 1 3.10 On axis D'/4-5
2.80
17.36 m²
2 -1 1 3.10 Deduction
1.50 W-4
-9.30 m²
2 1 1 5.34 On axis 5 b/N B'-D'
2.80
29.90 m²
2 -1 1 2.69 Deduction
1.80 W-2
-9.68 m²
2 1 1 3.65 Around duct
2.80
20.44 m²
4th- 8TH floor
5 1 1 6.45 On axis C b/N 2'-4
2.80
90.30 m²
5 -1 1 2.80 Deduction
1.20 D-6
-16.80 m²
5 -1 1 1.50 W-12
0.80
-6.00 m²
5 1 1 6.02 On axis 2' b/N C-D
3.02
90.90 m²
5 -1 1 2.90 Deduction
1.20 D-6
-17.40 m²
5 1 1 6.45 On axis D b/N 2'-4
2.80
90.30 m²
5 -1 1 2.80 Deduction
1.20 D-6
-16.80 m²
5 -1 1 2.80 Deduction
D-7
1.20
-16.80 m²
5 1 1 5.96 On axis 4 b/N B'-D'
2.80
83.44 m²
5 -1 1 5.64
2.80
-78.96 m²
5 -2 1 2.69 Deduction
2.80 WD-2
-75.32 m²
5 1 1 3.10 On axis D'/4-5
2.80
43.40 m²
5 -1 1 3.10 Deduction
1.50 W-4
-23.25 m²
5 1 1 5.54 On axis 5 b/N B'-D'
2.80
77.56 m²
5 -1 1 2.69 Deduction
1.80 W-2
-24.21 m²
5 1 1 3.65 Around duct
2.80
51.10 m²
348.69 m²
Exposed Columns
Second- Third Floor
2 2 1 2.80 ON AXIS 3 C & D
2.80
31.36 m²
2 2 1 1.30
0.20
1.04 m²
2 1 1 0.45 ON AXIS 4 & D'
2.80
2.52 m²
2 1 1 0.40
0.20
0.16 m²
2 1 1 0.95 On axis 5 C'-D'
2.80
5.32 m²
2 1 1 0.80
0.20
0.32 m²
Fourth- Eigth Floor
5 2 1 1.60 ON AXIS 3 C & D
2.80
44.80 m²
5 2 1 0.70
0.20
1.40 m²
5 1 1 0.25 ON AXIS 4 & D'
2.80
3.50 m²
5 1 1 0.20
0.20
0.20 m²
5 1 1 0.55 On axis 5 C'-D'
2.80
7.70 m²
5 1 1 0.40
0.20
0.40 m²
98.72 m² Total item
447.41 m² Total item of 7.16A

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


b) Plastered Soffit
lobby
6 1 1 5.92 on Axis 2'-4, C-D
6.60
234.43 m³ on Axis 4-5, C-D
6 1 1 2.69
3.45
55.68 m³
6 1 1 0.53
1.14
3.63 m³ 293.74 m³
Deduction For Columns
2nd- 3rd Floor
2 -2 1 0.35 On axis 3 b/N C-D
0.60
-0.84 m²
2 -1 1 0.05 On axis 5 b/N B'-D'
0.05
-0.01 m²
2 -1 1 0.35 On axis 5 D'
0.35
-0.25 m²
4th - 8th floor
2 -2 1 0.15 On axis 3 b/N C-D
0.40
-0.24 m²
2 -1 1 0.05 On axis 5 b/N B'-D'
0.05
-0.01 m²
2 -1 1 0.15 On axis 5 D'
0.15
-0.05 m²
Balcony
7 1 1 4.43 On Axis 4 b/n A-B'
1.10
34.11 m²
7 1 1 4.43 On Axis 4 b/n D'-E
1.10
34.11 m²
Balcony @ roof level
1 1 1 4.43 On Axis 4 b/n A-B'
1.10
4.87 m²
1 1 1 4.43 On Axis 4 b/n D'-E
1.10
4.87 m²
main stair case
Basement-8th Floor
10 1 1 2.40 SECTION A-A
1.03 sofit
24.72 m³
10 1 1 1.03 Landing 1
1.27
13.08 m³
10 1 1 2.40 side
0.22
5.28 m³
1 7 0.5 0.29 Riser side
0.15
0.15 m³
SECTION B-B
10 1 1 1.93 sofit
1.03
19.88 m³
10 1 1 1.27 Landing 1
1.03
13.08 m³
10 1 1 1.93 side
0.22
4.25 m³
1 7 0.5 0.29 Riser side
0.15
0.15 m³
SECTION C-C
10 1 1 2.00 sofit
1.15
23.00 m³
10 1 1 2.00 side
0.22
4.40 m³
1 5 0.5 0.29 Riser side
0.15
0.11 m³

478.40 m² Total to item of 7.16 B


Finishing for Lobby and Corridor at Shops
a) Internal Plastered vertical surface
Grnd FLOOR
1 1 1 10.80 On axis 1 b/n C-E
2.80
30.24 m²
1 1 1 4.20 On axis 2 b/n A-B
2.80
11.76 m²
1 -1 1 4.20 Deduction
1.80 W-1
-7.56 m²
1 1 1 2.20 On axis 2 b/n B-C
2.80
6.16 m²
1 -1 1 1.10 Deduction
1.80 W-11
-1.98 m²
1 1 1 10.43 On axis 2 b/n E-G
2.80
29.20 m²
1 2 1 10.80 On axis 3 b/n D-F
2.80
60.48 m²
1 1 1 7.54 On axis 4 b/n B'-D'
2.80
21.11 m²
1 1 1 5.64
2.80
15.79 m²
1 1 1 6.74 On axis 5 b/n B'-D'
2.80
18.87 m²
1 -1 1 2.40 Deduction
1.80 W-4
-4.32 m²
1 1 1 1.40 On axis A b/n 2-4
2.80
3.92 m²
1 1 2 4.39 b/n axis C & 2-3
2.80
24.58 m²
1 1 2 13.33 On axis D b/N 1-4
2.80
74.65 m²
1 1 1 3.10 On axis D' b/N 4-5
2.80
8.68 m²
1 -1 1 3.10 Deduction
1.50 W-4'
-4.65 m²
1 1 1 8.80 On axis E b/n 1-4
2.80
24.64 m²
1 1 1 4.40 On axis F b/n 3-4
2.80
12.32 m²
1 1 1 13.10 On axis G b/n 2-4
2.80
36.68 m²
1 1 1 5.23 On Axis B-B' & 2-3
3.02 toilet area
15.79 m²
1 1 1 2.85 On Axis C b/n 4-5
3.02 duct area
8.61 m²
1 1 1 1.55
2.80
4.34 m²
Exposed Columns
1 1 1 2.45 On axis 1 b/n C-E
2.80
6.86 m²
1 1 1 0.54
2.80
1.51 m²
1 1 1 6.05 On axis 2 b/n A-G
2.80
16.94 m²
1 1 1 0.95
2.80
2.66 m²
1 1 1 6.09 On axis 3 b/n A-G
2.80
17.05 m²
1 1 1 1.20
2.80
3.36 m²
1 1 1 7.05 On axis 4 b/n A-G
2.80
19.74 m²
1 1 1 2.97
2.80
8.32 m²
1 1 1 2.30 On axis 5 b/n A-G
2.80
6.44 m²
1 1 1 1.10
2.80
3.08 m²
1 1 1 0.50 On axis 6 b/n B-E
2.80
1.40 m²
1 1 1 0.50
2.80
1.40 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption

1 1 1 10.80 FIRST FLOOR


2.80 On axis 1 b/n C-E
30.24 m²
1 1 1 4.20 On axis 2 b/n A-B
2.80
11.76 m²
1 -1 1 4.20 Deduction
1.80 W-1
-7.56 m²
1 1 1 2.20 On axis 2 b/n B-C
2.80
6.16 m²
1 -1 1 1.10 Deduction
1.80 W-11
-1.98 m²
1 2 1 5.40 On axis 3 b/n E-F
2.80
30.24 m²
1 1 1 3.65
2.80
10.22 m²
1 1 1 8.07 On axis 4 b/n B'-D'
2.80
22.60 m²
1 1 1 5.67
2.80
15.88 m²
1 1 1 6.74 On axis 5 b/n B'-D'
2.80
18.87 m²
1 -1 1 2.40 Deduction
1.80 W-4
-4.32 m²
1 -1 1 2.59
1.80 W-2
-4.66 m²
1 1 1 1.40 On axis A b/n 2-4
2.80
3.92 m²
1 2 1 3.21 On axis B b/n 3-4
2.80
17.98 m²
1 2 1 4.39 b/n axis C & 2-3
2.80
24.58 m²
1 2 1 5.15 b/n axis C - D & 3-4
3.00
30.90 m²
1 2 1 8.57 b/n axis D & 1-3
2.80
47.99 m²
7 1 1 3.10 On axis D' b/N 4-5
2.80
60.76 m²
1 -1 1 3.10 Deduction
1.50 W-4
-4.65 m²
1 2 1 2.17 b/n axis E & 2-3
2.80
12.15 m²
1 1 1 1.40 On axis F b/n 2-4
2.80
3.92 m²
1 1 2 5.23 On Axis B-B' & 2-3
3.00 toilet area
31.38 m²
1 1 1 2.85 On Axis C b/n 4-5
3.02 duct area
8.61 m²
1 1 1 1.55
2.80
4.34 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


Exposed Columns
1 1 1 2.45 On axis 1 b/n C-E
2.80
6.86 m²
1 1 1 0.54
2.80
1.51 m²
1 1 1 5.60 On axis 2 b/n A-F
3.00
16.80 m²
1 1 1 0.80
2.80
2.24 m²
1 1 1 5.64 On axis 3 b/n A-F
2.80
15.79 m²
1 1 1 1.05
2.80
2.94 m²
1 1 1 5.15 On axis 4 b/n A-F
2.80
14.42 m²
1 1 1 1.80
2.80
5.04 m²
1 1 1 0.85 On axis 5 b/n B'-D'
2.80
2.38 m²
1 1 1 0.25
2.80
0.70 m²
916.09 m² Total item 7.16 a

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


b) Plastered Soffit
Ceilling gypsum plastering
GROUND FLOOR
Solid Slab
1 1 1 5.93 B/ N Axis 4-5 & A-B
3.45
20.44 m²
1 1 1 4.25 B/ N Axis B-B' & 4-5
3.45
14.66 m²
1 1 1 2.91 B/ N Axis C-C' & 4-5
1.08
3.14 m²
1 1 1 3.22
1.09
3.51 m²
1 1 1 3.00
1.28
3.84 m²
1 1 1 4.46 B/ N Axis D'-E & 4-5
3.45
15.37 m²
1 1 1 5.93 B/ N Axis E-F & 4-5
3.45
20.44 m²
1 1 1 12.70 B/ N Axis F-G & 2-5
5.08
64.52 m²
1 1 1 5.76 B/ N Axis B-C & 5-6
3.60
20.72 m²
1 1 1 3.60 B/ N Axis C-D & 5-6
6.00
21.60 m²
1 1 1 5.74 B/ N Axis D-E & 5-6
3.54
20.32 m²
Ribbed Slab
1 1 1 5.87 B/N axis 1-2' & C-D
7.10 SHOP 2
41.68 m³
1 1 1 2.17
5.80
12.59 m³
1 1 1 5.86 B/N axis 1-3 & D-E
7.10 SHOP 3
41.61 m³
1 1 1 5.75
4.46
25.62 m³
1 1 1 5.85 B/N axis 2-4 & A-B
4.84 SHOP 1
28.31 m³
1 1 1 5.10
4.47
22.80 m³
1 1 1 4.95 B/N axis 3-4 & E-F
5.75 SHOP 4
28.46 m³
1 1 1 4.95 B/N axis 3-4 & D-E
5.93 SHOP 5
29.35 m³
1 1 1 3.99 B/N axis 3-4 & C-D
4.76 SHOP 6
18.99 m³
CORRIDOR
FOR GROUND FLOOR
1 1 1 5.92 B/n axis 2-3 & C-D
2.40
14.21 m³
1 1 1 1.68 B/n axis 3-4 & C-D
4.80
8.04 m³
1 1 1 7.34 Entrance lobby
4.81 B/n axis 3-4 & B-C
35.27 m³
Ramp
1 1 1 4.88 B/n axis 2-3 & E-F
12.95
63.20 m³
VERENDA
1 1 1 3.35 B/N axis 4-5 & A-C
10.63
35.61 m³
1 1 1 3.35 B/N axis 4-5 & D'-F
10.63
35.61 m³
1 1 1 17.45 B/N axis 5-6 & B-E
3.60
62.82 m³
Toilet
1 1 1 1.40 B/N axis 2-3 & A'-B
4.48
6.28 m³
1 1 1 1.00 B/N axis 2-3 & B-B'
2.75
2.75 m³
1 1 1 2.85
2.33
6.64 m³
1 1 1 1.70
2.60
4.42 m³
Exposed beam
Internal
1 1 1 10.80 ON XIS 1-(C-E)
0.22 FB-1
2.38 m²
Bottom
1 1 1 10.80 ON XIS 1-(C-E)
0.05 FB-1
0.54 m²
Internal
1 1 1 10.55 ON AXIS-2 (A-C)
0.22 FB-2
2.32 m²
1 2 1 10.80 ON AXIS-2 (C-E)
0.22 FB-2
4.75 m²
1 1 1 5.40 ON AXIS-2 (E-F)
0.22 FB-2
1.19 m²
1 1 1 5.03 ON AXIS-2 (F-G)
0.22 FB-2
1.11 m²
Bottom
1 1 1 8.65 ON AXIS-2 (A-C)
0.25 FB-2
2.16 m²
1 1 1 10.80 ON AXIS-2 (C-E)
0.25 FB-2
2.70 m²
1 1 1 10.43 ON AXIS-2 (E-G)
0.05 FB-2
0.52 m²
Internal
1 2 1 31.78 ON AXIS -3 (A-G)
0.22 FB-3
13.98 m²
1 2 1 5.03 ON AXIS -3 (A-G)
0.22 FB-3
2.21 m²
Bottom
1 1 1 17.83 ON AXIS -3 (A-G)
0.25 FB-3
4.46 m²
1 1 1 13.95 ON AXIS -3 (A-G)
0.05 FB-3
0.70 m²
Internal
1 1 1 9.68 ON AXIS 4-(A-B')
0.22 FB-4
2.13 m²
bottom
1 1 1 9.68 ON AXIS 4-(A-B')
0.25 FB-4
2.42 m²
Internal
1 2 1 5.44 ON AXIS 4 -(C'-D')
0.22 FB-5
2.39 m²
1 2 1 9.68 ON AXIS 4 -(D'-G)
0.22 FB-5
4.26 m²
1 2 1 5.03 ON AXIS 4 -(D'-G)
0.22 FB-5
2.21 m²
bottom
1 1 1 14.71 ON AXIS 4 -(D'-G)
0.25 FB-5
3.68 m²
1 1 1 5.44 ON AXIS 4 -(D'-G)
0.05 FB-5
0.27 m²
Internal
1 1 1 29.88 ON AXIS 5 - (A-G)
0.22 FB-6
6.57 m²
1 1 1 9.01 ON AXIS 5 - (A-G)
0.22 FB-6
1.98 m²
bottom
1 1 1 30.93 ON AXIS 5 - (A-G)
0.25 FB-6
7.73 m²
1 1 1 3.35 ON AXIS 5 - (A-G)
0.05 FB-6
0.17 m²
Internal
1 1 1 17.53 ON AXIS 6 -(B-E )
0.22 FB-7
3.86 m²
Bottom
1 1 1 17.53 ON AXIS 6 -(B-E )
0.25 FB-7
4.38 m²
Internal
1 1 1 12.20 ON AXIS A -(5-2 )
0.22 FB-8
2.68 m²
1 1 1 13.10 ON AXIS G -(5-2 )
0.22 FB-8
2.88 m²
Internal
1 2 1 4.40 ON AXIS F -(3-2 )
0.22 FB-8
1.94 m²
1 2 1 8.10 ON AXIS F -(3-5 )
0.22 FB-8
3.56 m²
Bottom
1 1 1 10.40 ON AXIS A-(5-2 )
0.25 FB-8
2.60 m²
1 1 1 1.40 ON AXIS A-(5-2 )
0.05 FB-8
0.07 m²
1 1 1 7.80 ON AXIS F - (5-2 )
0.25 FB-8
1.95 m²
1 1 1 4.40 ON AXIS F - (5-2 )
0.05 FB-8
0.22 m²
1 1 1 11.70 ON AXIS G-(5-2 )
0.25 FB-8
2.93 m²
1 1 1 1.40 ON AXIS G-(5-2 )
0.05 FB-8
0.07 m²

STANDARD TAKEOFF SHEET


CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc
Timizing Dimension Qty Descreption
Internal
1 2 1 8.35 ON AXIS B -(4-2)
0.22 FB-9
3.67 m²
1 2 1 3.40 ON AXIS B -(5-4)
0.22 FB-9
1.50 m²
1 2 1 6.95 ON AXIS B -(6-4)
0.22 FB-9
3.06 m² 11.75
Bottom
1 1 1 15.30 ON AXIS B -(6-2)
0.25 FB-9
3.83 m²
Internal
1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.50 FB-10
2.47 m²
Bottom
1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.05 FB-10
0.25 m²
Internal
1 1 1 6.40 ON AXIS C -(1-2)
0.22 FB-11
1.41 m²
1 2 1 4.39 ON AXIS C -(3-2)
0.22 FB-11
1.93 m²
1 2 1 4.76 ON AXIS C -(3-4)
0.22 FB-11
2.09 m²
Bottom
1 1 1 11.16 ON AXIS C -(1-2 & 3-4)
0.25 FB-11
2.79 m²
1 1 1 4.40 ON AXIS C -(2-3)
0.05 FB-11
0.22 m²
Internal
1 2 2 6.75 b/n axis C-D and D-E & (2-1)
0.22 FB-12
5.94 m²
Bottom
1 2 1 6.75 b/n axis C-D and D-E & (2-1)
0.25 FB-12
3.38 m²
Internal
1 1 2 15.55 ON AXIS D -(4-1)
0.22 FB-13
6.84 m²
Bottom
1 1 1 2.22 ON AXIS D -(4-1)
0.25 FB-13
0.56 m²
1 1 1 13.33 ON AXIS D -(4-1)
0.05 FB-13
0.67 m²
Internal
1 1 1 21.70 ON AXIS E-(6-1)
0.22 FB-14
4.77 m²
Internal
1 1 1 6.40 ON AXIS E-(1-2)
0.22 FB-14
1.41 m²
1 1 2 8.80 ON AXIS E-(2-4)
0.22 FB-14
3.87 m²
1 1 2 3.40 ON AXIS E-(4-5)
0.22 FB-14
1.50 m²
1 1 2 3.55 ON AXIS E-(5-6)
0.22 FB-14
1.56 m²
Bottom
1 1 1 13.35 ON AXIS E-(1-2 & 4-6)
0.25 FB-14
3.34 m²
1 1 1 8.80 ON AXIS E-(2-4)
0.05 FB-14
0.44 m²
Internal
1 1 2 6.65 ON AXIS D' - (6 -4)
0.22 FB-15
2.93 m²
Bottom
1 1 1 6.65 ON AXIS D' - (6 -4)
0.25 FB-15
1.66 m²
1 1 1 3.10 ON AXIS D' - (6 -4)
0.05 FB-15
0.16 m²
Internal
1 1 2 3.40 ON AXIS C' (5-4)
0.22 FB-16
1.50 m²
Bottom
1 1 1 3.40 ON AXIS C' (5-4)
0.25 FB-16
0.85 m²
Internal
1 1 2 3.55 ON AXIS C ( 6-5)
0.22 FB-17
1.56 m²
Bottom
1 1 1 3.55 ON AXIS C( 6-5)
0.25 FB-17
0.89 m²
Internal
1 1 2 1.25 ON AXIS C (5-4)
0.22 FB-18
0.55 m²
Internal
1 1 1 1.25 ON AXIS C (5-4)
0.05 FB-18
0.06 m²

Deduct for Columns contact Areas


Ground Floor
1 20 -1 0.35
0.35
-2.45 m³
1 16 -1 0.05
0.05
-0.040 m³
First Floor
Solid Slab
1 1 1 5.95 ON Axis 1 B/N C-D
0.85
5.06 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20
10.63 m²
1 1 1 3.45 ON Axis 4-5 B/N B'-C'
2.69
9.28 m²
1 1 1 1.14 ON Axis 4-5 B/N B'-C'
0.53
0.60 m²
Ribbed Slab
1 1 1 5.78 B/N axis 1-2' & C-D
6.80 SHOP 7
39.27 m³
1 1 1 5.78
2.15
12.42 m³
1 1 1 5.78 B/N axis 1-2' & D-E

SHOP 8
6.80
39.27 m³

1 1 1 5.78
2.15
12.42 m³
1 1 1 4.47 B/N axis 2-4 & A-B
4.98 Café & Restaurant #1
22.24 m³
1 1 1 5.78
4.84
27.95 m³
1 1 1 5.67 B/N axis 2-3 & E-F
4.90 SHOP 9
27.78 m³
1 1 1 8.13 B/N axis 3-4 & B-C'
2.91 SHOP 10
23.66 m³
1 1 1 4.84 B/N axis 3-4 & C'-F
15.10 Café & Restaurant #2
73.06 m³
CORRIDOR
1 1 1 5.78 B/n axis 2-3 & D-E
2.37
13.66 m³
1 1 1 5.85 B/n axis 2-3 & C-D
2.37
13.84 m³
1 1 1 1.93 lobby
7.93 B/n axis 3-4 & B-C'
15.30 m³
Toilet
1 1 1 1.40 B/N axis 2-3 & A'-B
4.48
6.28 m³
1 1 1 1.00 B/N axis 2-3 & B-B'
2.75
2.75 m³
1 1 1 2.85
2.33
6.64 m³
1 1 1 1.70
2.60
4.42 m³
Exposed beam
Internal
1 1 1 10.60 ON AXIS 1-(C-E)
0.22 FB-1
2.33 m²
1 1 1 5.20 ON AXIS 1-(C-D)
0.22 FB-1
1.14 m²
Bottom
1 1 1 9.20 ON AXIS 1-(C-E)
0.25 FB-1
2.30 m²
1 1 1 1.31 ON AXIS 1-(C-E)
0.05 FB-1
0.07 m²
Internal
1 1 1 16.20 ON AXIS-2 (A-F)
0.22 FB-2
3.56 m²
1 2 1 10.80
0.22
4.75 m²
Bottom
1 1 1 14.57 ON AXIS-2 (A-F)
0.25 FB-2
3.64 m²
1 1 1 7.38
0.05
0.37 m²
Internal
1 1 2 27.00 ON AXIS 3 (A-F)
0.22 FB-3
11.88 m²
Bottom
1 1 1 11.64 ON AXIS 3 (A-F)
0.25 FB-3
2.91 m²
1 1 1 10.70 ON AXIS 3 (A-F)
STANDARD TAKEOFF SHEET
CLIENT : AASHDE TYPOLOGY :B+G+8 CONSULTANT:K2N Architecture and Engineering Consultancy plc

Timizing Dimension Qty Descreption


0.05 FB-3
0.54 m²
1 1 1 4.36 ON AXIS 3 (A-F)
0.15 FB-3
0.65 m²
Internal
1 1 1 9.68 ON AXIS 4-(A-B')
0.22 FB-4
2.13 m²
Bottom
1 1 1 7.28 ON AXIS 4-(A-B')
0.25 FB-4
1.82 m²
1 1 1 2.19 ON AXIS 4-(A-B')
0.05 FB-4
0.11 m²
Internal
1 1 1 14.92 ON AXIS 4 -(C-F)
0.22 FB-5
3.28 m²
1 1 1 5.64 ON AXIS 4 -(C-F)
0.22 FB-5
1.24 m²
Bottom
1 1 1 9.80 ON AXIS 4 -(C-F)
0.25 FB-5
2.45 m²
1 1 1 5.13 ON AXIS 4 -(C-F)
0.05 FB-5
0.26 m²
Internal
1 1 1 7.54 ON AXIS -5 (B'-D')
0.22 FB-6
1.66 m²
Bottom
1 1 1 4.99 ON AXIS -5 (B'-D')
0.25 FB-6
1.25 m²
1 1 1 2.55 ON AXIS -5 (B'-D')
0.05 FB-6
0.13 m²
Internal
1 2 1 8.80 ON AXIS A & F (4-2 )
0.22 FB-7
3.87 m²
Bottom
1 2 1 4.10 ON AXIS A & F (4-2 )
0.25 FB-7
2.05 m²
1 2 1 4.30 ON AXIS A & F (4-2 )
0.05 FB-7
0.43 m²
Internal
1 1 2 8.70 ON AXIS B -(4-2 )
0.22 FB-8
3.83 m²
Bottom
1 1 1 4.40 ON AXIS B -(4-2 )
0.05 FB-8
0.22 m²
1 1 1 4.40 ON AXIS B -(4-2 )
0.25 FB-8
1.10 m²
Internal
1 1 1 14.75 ON AXIS C (4-1)
0.22 FB-9
3.25 m²
1 1 1 8.85
0.22
1.95 m²
Bottom
1 1 1 3.71 ON AXIS C (4-1)
0.05 FB-9
0.19 m²
1 1 1 9.09 ON AXIS C (4-1)
0.25 FB-9
2.27 m²
Internal
1 1 1 6.40 ON AXIS E (4-1)
0.22 FB-9
1.41 m²
1 2 1 8.70
0.22
3.83 m²
Bottom
1 1 1 8.20 ON AXIS E (4-1)
0.25 FB-9
2.05 m²
1 1 1 6.70 ON AXIS E (4-1)
0.05 FB-9
0.34 m²
Internal
1 1 2 15.55 ON AXIS D -(4-1)
0.22 FB-10
6.84 m²
Bottom
1 1 1 7.95 ON AXIS D -(4-1)
0.05 FB-10
0.40 m²
1 1 1 2.05 ON AXIS D -(4-1)
0.15 FB-10
0.31 m²
1 1 1 4.65 ON AXIS D -(4-1)
0.25 FB-10
1.16 m²
Internal
1 1 2 6.75 Beam around C-D b/n 1-2
0.22
2.97 m²
Bottom
1 1 1 5.26 Beam around C-D b/n 1-2
0.25
1.32 m²
1 1 1 0.85
0.15
0.13 m²
Internal
1 1 2 6.75 Beam around D-E b/n 1-2
0.22
2.97 m²
Bottom
1 1 1 6.65 Beam around D-E b/n 1-2
0.25
1.66 m²
Internal
1 1 1 3.10 ON AXIS D' (5-4)
0.22 FB-11
0.68 m²
Bottom
1 1 1 3.10 ON AXIS D' (5-4)
0.25 FB-11
0.78 m²
Internal
1 1 1 1.25 ON AXIS B' (5-4)
0.22 FB-12
0.28 m²
Bottom
1 1 1 1.25 ON AXIS B' (5-4)
0.05 FB-12
0.06 m²
Internal
1 1 1 3.10 ON AXIS C' (5-4)
0.22 FB-13
0.68 m²
1 1 1 3.10 ON AXIS C' (5-4)
0.22 FB-13
0.68 m²
Bottom
1 1 1 3.10 ON AXIS C' (5-4)
0.25 FB-13
0.78 m²

Deduct for Columns contact Areas


1 21 -1 0.35 1st-Floor
0.35
-2.57 m³
1 2 -1 0.05
0.05
-0.01 m³
SHOP STAIR
Ground floor
SECTION E-E
1 1 1 3.75 sofit
1.05
3.94 m³
1 1 1 3.75 Side Flight
0.22
0.83 m³
1 11 0.5 0.30 Riser side
0.15
0.25 m³
SECTION F-F
1 1 1 3.30 Side Flight
0.22
0.73 m³
1 11 0.5 0.30 Riser side
0.15
0.25 m³
1 1 1 3.30 sofit
1.05
3.47 m³
1 1 1 1.99 Landing 1
2.20
4.38 m³
1 1 1 0.06 side Landing
0.22
0.01 m³ 13.86
1372.73 m² Total item 7.16b

STANDARD TAKEOFF SHEET


B-

avg off set auto cad in mm area in m2


Site cleri 5.77 0.750 0.25 1.000 9756144 975.6144
Bulk 5.57 0.724 0.25 0.974 8790535 879.0535
4.07 0.529 0.25 0.779 8548400 854.84
2.57 0.334 0.25 0.584 8309308 830.9308
1.07 0.139 0.25 0.389 8073257 807.3257
0.00 - 0.25 0.25 7906852 790.6852

fill
0.60 0.09 0.25 0.34 6260508 626.051
0 0 0.25 7906852 790.685
area in m3
9756144 1
8790535 0.9739978
866.947 1300.420125 Exca. 0 - 1.5 8548400 0.7789816
842.885 1264.3281 Exca. 1.5 - 3 8309308 0.5839653
819.128 1228.692375 Exca. 3 - 4.5 8073257 0.3889491
799.005 853.9370746875 Exca. 4.5 - 6 7906852 0.25

708.368 425.02
Project:- Saving Houses B+G+8 Typology Revision

Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________

Contractor____________________ Payment No._final payment_

Consultant:- K2N Architecture and Engineering consultancy

TOTAL EXCAV. DEPTH


Height from profile Concret worek

MAT FOUNDATION
LEAN CONCRET
AFTTER BULCK

F
GRADE BEAM
UNDER MAT

O
HEIGHT OF
BASEMENT
FILL

(BULK)

COLLUMN

O
thickness
axis

PR
thckness
To NGL
UNDER MAT

DEPTH

depth
FFL

ER
FOUND.

AT
W
1 2 3 4=2-3 5 6 7 9 10=[3-(1+5+6+7+8+9)] 11=[3-(5+6+7)]+0.10

1 A-1 -0.7 0.9 6.45 5.55 0.60 0.05 1.10 0.50 4.10 3.80

2 C-1' -0.7 0.66 6.45 5.79 0.60 0.05 1.10 0.50 4.10 4.04

3 C-1 -0.7 0.7 6.45 5.75 0.60 0.05 1.10 0.50 4.10 4.00

4 E-1 -0.7 0.33 6.45 6.12 0.60 0.05 1.10 0.50 4.10 4.37

5 E-1' -0.7 0.3 6.45 6.15 0.60 0.05 1.10 0.50 4.10 4.40

6 F-1' -0.7 0.24 6.45 6.21 0.60 0.05 1.10 0.50 4.10 4.46

7 E-5 -0.7 0.87 6.45 5.58 0.60 0.05 1.10 0.50 4.10 3.83

8 A-5 -0.7 1.45 6.45 5.00 0.60 0.05 1.10 0.50 4.10 3.25

avg (0.70) 0.68 6.45 5.77 0.60 0.05 1.10 0.50 4.10 4.12
sump pit 5.12 retaining wall 4.42 10+0.50-0.16
foundation column 2.18 (2+3m)+1-6-9-0.25

CONTRACTOR Checked by OE VERIFIED BY R.E Approved by COORDINATER


Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC

ITEM No Discription Contract QUANTITY Contract Amount Executed Amount

A. SUB-STRUCTURE
1 Excavation & Earth Works 16,830.35 1,277,563.56 861,832.74
2 Concrete Works 94,124.63 1,853,810.70 1,802,182.20
3 Masonary Work 12.51 8,854.71
SUB TOTAL-A 110,967.49 3,140,228.97 2,664,014.94
B. SUPER-STRUCTURE
1 Concrete Works 92,344.56 2,884,609.13 2,634,816.91
2 Walling works 5,008.05 276,215.28 290,009.26
3 Roofing works 4,685.01 529,374.35 487,064.47
4 Metal Works - -
5 Carpentry & Joinery 217.98 928,267.76 943,995.67
6 Plastering and Pointing 14,331.33 1,078,826.54 1,253,025.18
7 Finishing works 16,364.70 2,713,341.54 1,580,786.28
8 Glazing works 1,241.24 19,859.84
9 Painting works 16,675.35 1,114,025.42 461,024.14
10 Sanitary Installation - 90,835.45
11 Electrical installation - 102,630.92
12 DEWATERING WATER SUMP PIT - 849,809.64
SUB TOTAL-B 150,868.22 10,587,795.86 7,650,721.90
GRAND TOTAL = A+B 261,835.71 13,728,024.83 10,314,736.84
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_
1.21Fill aroundDescription
retaining wall with

Ite.

Ite.
x Dim. Qty Description x Dim. Qty
selected material from quarry waste and
compact in layers not exceeding 200mm
A. SUB-STRUCTURE
0 1 1 723.97 thick.
Excavation and Earth Work 3.00 Peripherial
Site Clearing and Removing Top soil 200mm 0.80
(allowing 1.0m working space) -
1 1 1 975.61 - Total to Item 1.8
1.00 1 2 1 29.04 Fill around isolated footing with selected
975.61 58.08 material from quarry waste and compact in
Pit Excavation
layers not exceeding 200mm thick.
975.61 -1 1 1 12.96
1 1 1 866.95 Bulk excavation
(allowing 1.00m top up to 150cm
& 0.25cm bottom (12.96) DDT (Lean under Pad)
1.50 working space both side) -1 1 1 2.89
1,300.42 from autocad (2.89) DDT (Footing Pad)
1,300.42
1 1 1 842.89 ditto but from 150 to 300cm -1 1 1 0.79
1.50 from autocad (0.79) DDT (Foundation column)
1,264.33
1,264.33 Total 41.44 Total
Backfill under mat foundation with non
1 1 1 819.13 ditto but from 300 to 450cm 1 1 1 708.37 expansive selected material from quary
1.50 from autocad 0.60
1,228.69 425.02
1,228.69 Total 1 1 -1 11.25 Deduct 15cm thick slab
ditto but from 450 to 600cm 4.05 Axis A-C/1-2
1 1 1 799.01 from autocad 0.60
1.07 -27.34
853.94 1 1 -1 5.32 Axis E-F/1-2
1 1 -1 12.10 Deduct 15cm thick slab 4.05
4.90 Axis A-C/1-2 0.60
0.95 -12.93
-56.33 1 1 -1 4.65 Axis F-G/2-5
1 1 -1 6.17 Axis E-F/1-2 13.20
4.90 0.60
0.95 -36.83
-28.72 Axis F-G/2-5 347.92 Total
1 1 -1 5.43 Back fill Under Hardcore (solid slab)
14.90 1 1 1 11.25 Axis A-C/1-2
0.95 Lift area 4.05
-76.86 Av.W-(7.8+4.8)/2=6.30 0.40
1 1 1 6.30 Av.W-(6.8+4.5)/2=5.65 18.23
5.65 1 1 1 5.32 Axis E-F/1-2
0.30 4.05
10.68 0.40
702.71 Total 8.62
ditto but from 600 to 750cm 1 1 1 17.45 Axis b/n 5-6/B-E
1 1 1 6.30 Av.W-(7.8+4.8)/2=6.30 4.60
5.65 Av.W-(6.8+4.5)/2=5.65 0.10
1.20 8.03
42.71
650.52 Total
1 1 4 2.20 Pit Excavation up to 150cm 1 1 1 13.15 Axis F-G/2-5
2.20 (allowing 0.25m working space) 4.65
1.50 F-1 0.40
29.04 24.46
29.04 Total 59.34 Total
1 1 4 2.20 ditto but from 150 to 300cm Back fill under strip foundation
2.20 (allowing 0.25m working space) 1 1 1 12.20 axis 1 b/n A,B & B'
1.50 F-1 0.95
29.04 0.50
29.04 Total 5.80

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 6.17 axis 1 b/n E & F Concrete Work


0.95 50mm Lean concrete quality c-5
0.50 Basement floor
2.93 A. Under footing Pad
1 1 1 5.43 axis 2 b/n F & G allowing 10cm width addition
0.95 1 1 4 1.80 F-1
0.50 1.80
2.58 12.96
1 1 1 5.43 axis 5 b/n F & G 12.96 m² Total
0.95 B. Under mat foundation
0.50 allowing 5cm width addition
2.58 1 1 1 598.45
1.00
598.45
1 1 1 6.80 Triangular Area for lift
2.10
14.28
1 1 1 6.80
1.07
7.28
1 2 1 4.80
2.10
1 1 2 4.90 axis A & F b/n 1 & 1' 20.16
0.95
0.50 640.17 m² Total
4.66 C. Under strip foundation

1 1 1 13.20 axis G b/n 2,3,4 & 5 1 1 1 12.10 axis 1 b/n A-B'


0.95 0.95
0.50 11.50 m²
6.27 1 1 1 6.17 axis 1 b/n E & F
24.82 Total 0.95
5.86 m²
1 1 1 975.61 Site clearance 1 1 1 5.50 axis 2 b/n F & G
0.20 195.12 0.95
1,300.42 Bulk excavation up to 150cm 5.23 m²
1,264.33 Bulk excavation from 150 to 300cm 1 1 1 5.50 axis 5 b/n F & G
1,228.69 Bulk excavation from 300 to 450cm 0.95
702.71 Bulk excavation from 450 to 600cm 5.23 m²
42.70 Bulk excavation from 600 to 750cm 1 1 2 4.05 axis A & F b/n 1 & 1'
29.04 Pit excavation from up to 150 from NGL 0.95
29.04 Pit excavation from 150 to 300 cm 7.70 m²
4,792.05 Total 1 1 1 13.20 axis G b/n 2-5
0.95
250mm thick basaltic stone hardcore well 12.54 m²
rolled,
@ elev.consolidated and blinded with
+0.00m( verenda) 48.06 m² Total
crushed stone.
1 1 1 17.45 axis B-E/5-6 E. under 15cm thick basement slab
3.60 1 1 1 11.25 Axis A-C/1-2
62.82 4.05
1 1 1 3.46 In ramp interance 45.56
5.08 Axis F-G/5-6 1 1 1 5.32 Axis E-F/1-2
17.58 4.05
1 1 1 5.03 axis F-G/2-5 21.55
13.15 1 1 1 13.2 Axis E-G/2-5
66.14 4.65
1 1 1 11.25 @ elev. -3.30m 61.38
4.05 axis A-C/1-2 128.49 m² Total
45.56 F. under Ground floor Slab
1 1 1 5.25 axis E-F/1-2 1 1 1 17.35 b/n axis B-E & 5-6
4.05 3.60
21.26 62.46 m²
213.36 m² Total 62.46 m² Total

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

G. Under Ground floor beam 1 1 -1 1.80


0.40
1 1 1 17.25 GB-4 4.47
0.25 On axis 6/B-E -3.22
4.31 729.58 Total
1 1 2 3.55 GB-5 C. In strip foundation
0.25 On axis B & E/5 - 6 1 1 1 12.10 axis 1 b/n A - B'
1.78 0.95
1 1 1 3.55 GB-7 0.25
0.3 On axis D'/5 - 6 2.87
1.07 1 1 1 6.17 axis 1 b/n E & F
1 1 1 3.55 GB-13 0.95
0.3 On axis C/5-6 0.25
1.07 1.47
8.23 m² Total 1 1 1 5.50 axis 2 b/n F & G
Reinforced concrete (C-25) 0.95

A. In footing pad 0.25


1 1 4 1.7 F-1 1.31
1.7 1 1 1 5.50 axis 5 b/n F & G
0.25 0.95
2.89 0.25
2.89 Total 1.31
B. In 110mm thick mat foundation
1 1 1 593.13 Mat 1 1 2 4.05 axis A & F b/n 1 & 1'
1.10 0.95
652.44 0.25
1 0.5 1 7.80 Triangle lift area 1.92
1.50 Y-direction 1 1 1 13.20 axis G b/n 2 - 5
1.50 0.95
8.78 0.25
1 0.5 1 7.80 3.14
0.76 12.02 Total
0.76 D. In 15cm thick basement slab
2.25 1 1 1 11.20 Axis A-C/1-2
1 0.5 2 6.30 X-direction 4.35
1.50 48.72
1.50 1 1 1 5.32 Axis E-F/1-2
14.18 4.05
1 1 1 4.08 Rectangle lift area 21.55
1.50 Y-direction 1 1 1 13.20 Axis E-G/2-5
4.80 4.65
29.38 61.38
1 1 -1 1.80 131.65 Total
0.40 E. In foundation column
4.80 1 1 4 0.30 C-1
-3.46 0.30
1 1 1 4.36 X-direction 2.18
1.50 0.79
4.47 0.79 Total
29.23

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

F. In Basement column
1 1 12 0.30 C-1 1 1 -1 4.40 Ddt Opening
0.30 0.25
4.10 0.80
4.43 -0.88
1 1 12 0.60 C-2 1 1 1 5.03 W-2
0.60 0.25
4.10 4.60
17.71 5.78
1 1 10 0.80 C-3 1 1 1 28.20 W-3
0.80 0.25
4.10 4.42
26.24 31.16
At slab,beam & coll coniction 1 1 -2 3.00 Ddt Opening
1 1 12 0.35 C-2 0.25
0.35 0.25

0.34 -0.38
0.50 1 1 1 19.00 W-4
1 1 10 0.55 C-3 0.25
0.55 4.42
0.34 21.00
1.03 1 1 -2 3.00 Ddt Opening
1 1 8 0.15 0.25
0.15 0.25
0.34 -0.38
0.06 1 1 1 6.70 W-5
49.97 Total 0.25
G. In shear wall for lift 4.42
Basement floor 7.40
1 1 2 2.60 W-2 1 1 1 12.70 W-6
0.25 0.25
4.60 4.60
5.98 14.61
1 1 1 1.80 W-3 115.14 Total
0.25 I. In Grade beam
4.60 1 1 2 27.00 GB-1
2.07 0.50
1 1 1 1.80 W-4 0.25
0.25 6.75
4.60 1 1 1 9.68 GB-2
2.07 0.50
1 1 -1 1.00 0.25
2.10 1.21
0.25 1 1 1 15.32 GB-3
-0.53 0.50
12.90 Total 0.25
H. In retaining wall 1.92
1 1 1 33.33 W-1 1 1 1 17.25 GB-4
0.25 0.50
4.42 0.25
36.83 2.16

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 2 22.45 GB-5 1 1 1 5.03 FB-3


0.50 0.50
0.25 0.25
5.61 0.63
1 1 1 15.65 GB-6 4.12 Total
0.50 1 1 1 29.10 K In Ground floor slab (16cm thick)
0.25 6.75 Ground Floor
1.96 196.43 On Axis 1-2, A-F
1 1 1 6.65 GB-7 1 1 1 23.35 On Axis 2-3, A-E
0.50 4.95
0.25 115.58
0.83 1 1 1 29.10 On Axis 3-4, A-F
1 1 1 15.65 GB-8 4.95
0.50 144.05
0.25 1 1 1 29.10 On Axis 4-5, A-F
1.96 3.45

1
1 1 7.80 GB-9 100.40
0.50 1 -1 1 2.60 Deductions
0.25 2.05 lift shaft area
0.98 -5.33
1 1 1 3.10 GB-10 1 -1 1 0.80 Duct Area
0.50 1.40
0.25 -1.12
0.39 Columns
1 1 1 6.75 GB-11 1 -3 1 0.05 Axis 1
0.50 0.05
0.25 -0.01
0.84 1 -3 1 0.35
1 1 1 1.05 GB-12 0.35
0.50 -0.37
0.25 1 -5 1 0.35 Axis 2
0.13 0.35
1 1 1 3.55 GB-13 -0.61
0.50 1 -6 1 0.35 Axis 3
0.25 0.35
0.44 -0.74
25.18 Total 1 -4 1 0.35 Axis 4
J. In ramp beam 0.35
1 1 1 5.40 FB-1 -0.49
0.50 1 -1 1 0.35
0.25 0.60
0.68 -0.21
1 1 1 10.43 FB-1 1 -3 1 0.05
0.50 0.05
0.25 -0.01
1.30 1 -2 1 0.35
1 1 1 12.05 FB-2 0.35
0.50 -0.25
0.25 1 -1 1 3.45 Deduct Stair case-1 area
1.51 2.95
-10.18
537.14 Total

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

M. In 10cm thick Ground Floor Solid Slab SECTION C-C


1 1 1 17.35 Axis B-C/5-6 1 1 6 1.03 riser
3.60 0.5 0.29
62.46 m² 0.17
62.46 m² Total 0.15
N. In ramp (20cm thick) 1 1 1 1.93 sofit
1 1 1 5.98 Axis E-F/2-3 1.15
4.93 0.22
29.48 m² 0.49
1 1 1 4.90 Axis F-G/2-5
5.08
24.89 m² 1 0.5 5 1.03 SECTION D-D
1 1 1 4.95 0.28 riser
5.08 0.165
25.15 m² 0.12
1 1 1 3.40 1 0.5 1 3.1 Landing BEAM

5.08 0.5
17.27 m² 0.25
1 1 -1 0.70 Deduct Column Area 0.19
0.53 Axis 2 1 1 1 1.93 sofit
-0.37 m² 1.03
1 1 -1 0.58 Axis 3 0.22
0.41 0.44
-0.24 m² 1 1 1 1.15 Landing 1
1 1 -2 0.05 1.03
0.05 Axis 4 & 5 0.22
-0.01 m² 0.26

96.17 m² Total 3.55 Total


1 0.5 6 1.03 P. Stair case & Landing A. To footing pad
0.28 Main stair with two landing F-1
0.17 Basement floor 1 1 4 6.80 P=1.70*4=6.80m
0.15 SECTION A-A 0.25
1 1 1 1.95 riser 6.80
1.03 6.80 Total to Item 2.03 A
0.22 sofit B. In Mat foundation
0.44 Mat
1 1 1 1.15 1 1 1 105.80 P=2*(31.1+21.8)=105.80m
1.03 Landing 1 1.10 60.28
0.22 116.38 Lift
0.26 1 1 1 7.80 P=2*(2.1+1.8)=7.80m
1 1 1 0.40 1.50
0.40 ddt 11.70
0.22 128.08 Total to Item 2.03 B
0.04 C. In strip foundation
1 1 1 23.25 axis 1 b/n A - B'
1 0.5 5 1.03 SECTION B-B 0.25 P=12.05+11.20=23.25m
0.28 riser 5.81
0.17 1 1 1 11.49 axis 1 b/n E & F
0.12 0.25 P=6.17+5.32=11.49m
1 0.5 1 3.10 Landing BEAM 2.87
0.50 1 1 1 10.08 axis 2 b/n F & G
0.25 0.25 P=5.43+4.65=10.08m
0.19 2.52
1 1 1 1.93 sofit 1 1 1 0.61 axis 5 b/n F & G
1.03 0.25 P=5.73+4.88=10.61m
0.22 0.15
0.44 1 1 2 8.95 axis A & F b/n 1 & 1'
1 1 1 1.15 Landing 1 0.25 P=4.90+4.05=8.85m
1.03 4.48
0.22
0.26
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 28.10 axis G b/n 2 - 5 1 1 1 2.60 W-4


0.25 P=14.90+13.2=28.1m 4.60 P=(0.65+0.25+0.4)*2=2.60m
7.03 11.96
22.86 Total to Item 2.03 C 1 1 1 1.80 p=2.3+1.8=4.10m
E. In foundation column 4.60
1 1 4 1.20 C-1 8.28
2.18 P=0.3*4=1.20m 1 1 -1 1.00 deduct open area
10.47 2.10

10.47 Total to Item 2.03 E -2.10


F. In Basement column 1 1 2 0.25 p=0.25m
1 1 16 1.20 C-1 2.10
4.10 P=0.3*4=1.20m 1.05
78.72
1 -1 16 0.50 deduct shear wall side 92.99 Total to item 2.03 G
4.10 P=0.25*2=0.50m H. In retaining wall
-32.80 Internal & External
1 1 12 2.40 C-2 1 2 1 32.53 W-1
4.10 P=0.6*4=2.40m 4.42
118.08 287.57
1 -1 8 0.50 deduct shear wall side 1 2 -1 4.40 Ddt Opening
4.10 P=0.25*2=0.50m 0.80
-16.40 -7.04
1 1 10 3.20 C-3 1 2 1 5.03 W-2
4.10 P=0.8*4=3.20m 4.60
131.20 46.28
At slab,beam & coll coniction 1 2 1 28.20 W-3
1 1 12 0.70 C-2 4.42
0.34 P=0.35*2=0.70m 249.29
2.86 1 2 -2 3.00 Ddt Opening
1 1 10 2.20 C-3 0.25
0.34 P=0.55*4=2.20m -3.00
7.48 1 2 1 18.80 W-4
4.42
289.14 Total to Item 2.03 F 166.19
G. In shear wall for lift 1 2 -2 3.00 Ddt Opening
For Pad 0.25
1 1 2 2.10 W-2 -3.00
1.50 P=2.1=2.10m 1 2 1 6.70 W-5
6.30 4.42
1 1 1 1.80 W-3 59.23
1.50 P=1.8=1.80m 1 2 1 12.70 W-6
2.70 4.60
1 1 1 1.80 W-4 116.84
1.50 P=1.8=1.80m 0 2 -1 4.40 Ddt Opening
2.70 0.80
Basement floor 0.00
1 1 2 4.70 W-2 912.36 Total to item 2.03 H
4.60 P=2.6+2.1=4.70m I. To Ground floor beam

43.24 Internal & Bottom


1 1 1 4.10 W-3 1 2 1 21.00 GB-1
4.60 P=2.3+1.8=4.10m 0.68
18.86 28.56
1 2 1 5.40
0.84
9.07

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 2 26.20 1 1 1 3.10 GB-10


0.25 0.70
13.10 2.17
1 1 2 9.68 GB-2 1 1 1 3.10
0.35 0.25
6.78 0.78
1 1 1 9.68 1 1 1 6.75 GB-11
0.25 0.50

2.42 3.38
1 1 2 15.32 GB-3 1 1 1 6.75
0.35 0.25
10.72 1.69
1 1 1 15.32 1 1 1 1.05 GB-12
0.25 0.70
3.83 0.74
1 1 2 17.25 GB-4 1 1 1 1.05
0.35 0.25
12.08 0.26
1 1 1 17.25 1 1 1 3.55 GB-13
0.25 0.70
4.31 2.49
1 2 2 22.45 GB-5 1 1 1 3.55
0.70 0.25
62.86 0.89
1 1 1 22.45
0.25 215.21 Total to item 2.03 I
5.61 1 1 2 5.40 J. To ramp beam
1 1 1 15.65 GB-6 0.50 Internal & Bottom
0.70 5.40 FB-1
10.96 1 1 1 5.40
1 1 1 15.65 0.25
0.25 1.35
3.91 1 1 2 10.43 FB-1
1 1 1 6.65 GB-7 0.50
0.70 10.43
4.66 1 1 1 10.43
1 1 1 6.65 0.25
0.25 2.61
1.66 1 1 2 12.05 FB-2
1 1 1 15.65 GB-8 0.50
0.70 12.05
10.96 1 1 1 12.05
1 1 1 15.65 0.25
0.25 3.01
3.91 1 1 2 5.03 FB-3
1 1 1 7.80 GB-9 0.50
0.70 5.03
5.46 1 1 1 5.03
1 1 1 7.80 0.25
0.25 1.26
1.95 41.14 Total to item 2.03 J

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

K. To Ground floor slab M. In ramp slab


Bottom
1 1 1 29.10 On Axis 1-2, A-F 1 1 1 5.98 Axis E-F/2-3
6.75 4.93
196.43 29.48
1 1 1 23.35 On Axis 2-3, A-E 1 1 1 13.15 Axis F-G/2-5
4.95 5.03
115.58 66.14 Deduct Column Area

1 1 1 29.10 On Axis 3-4, A-F 1


1 -1 0.70 Axis 2
4.95 0.53
144.05 -0.37
1 1 1 29.10 On Axis 4-5, A-F 1 1 -1 0.58 Axis 3
3.45 0.41
100.40 -0.24
1 1 1 115.0 Side 1 1 -2 0.05 Axis 4 & 5
0.16 0.05
18.40 -0.01
1 -1 1 2.60 Deductions 95.00 Total to item 2.03 M
2.05 lift shaft area O. Stair case & Landing
-5.33 Main stair with two landing
1 -1 1 0.80 Duct Area Basement floor
1.40 SECTION A-A
-1.12 1 1 6 1.03 riser
Columns 0.17
1 -3 1 0.05 Axis 1 1.05
0.05 1 1 1 1.95 sofit
-0.01 1.03
1 -3 1 0.35 2.01
0.35 1 1 1 1.03 Landing 1
-0.37 1.15
1 -5 1 0.35 Axis 2 1.18
0.35 1 1 2 1.86 side formwork
-0.61 0.39
1 -6 1 0.35 Axis 3 1.45
0.35 SECTION B-B
-0.74 1 1 4 1.03 riser
1 -4 1 0.35 Axis 4 0.17
0.35 0.68
-0.49 1 1 1 1.30 sofit
1 -1 1 0.35 1.03
0.60 1.34
-0.21 1 1 1 1.15 Landing 1
1 -3 1 0.05 Axis 5 1.03
0.05 1.18
-0.01 1 1 1 1.86 side formwork
1 -2 1 0.35 0.39
0.35 0.73
-0.25 1 1 6 1.03 SECTION C-C
1 -1 1 3.45 Deduct Stair case-1 area 0.17 riser
2.95 1.02
-10.18 1 1 1 1.93 sofit
555.54 Total to item 2.03 K 1.15 1.93

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 2 1.45 side formwork


0.39
1.13
1 1 1 3.10 Landing beam
1.09
Mild steel reinforcement according to
3.38
structural drawings. Price includes
17.08 Total to item
cutting, 2.03 O
bending, placing in position
and tying wire and concrete spacers.
0,000.00 kg a) Dia 6 mm deformed bar
10,012.49 kg b) Dia 8 mm deformed bar
11,129.33 kg c) Dia 10 mm deformed bar

3,941.50 kg
d) Dia 12 mm deformed bar
5,408.65 kg e) Dia 14 mm deformed bar
25,838.36 kg f) Dia 16 mm deformed bar
24,009.03 kg g) Dia 20 mm deformed bar
0,000.00 kg 10mm
h) Dia 24 mm
thick deformed
and 100mm bar
high
Styrofoam expansion joint between
groundAt slab andfloor
ground gradeslab
beam& beam
B/n Axis C-E/5-6
1 1 6 3.60 On Axis B, C, D & E
1.00
21.60
1 1 2 17.45 On Axis 5 & 6
1.00
34.90
56.50 m² Total to item 2.05

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

B- SUPER STRUCTURE water tanker


1. CONCRETE WORKS 1 1 1 0.30 ON AXIS 5C'
Reinforced concrete in class C-25 0.30 C1
(with a 28-day 15cm cube crushing 2.75
strength of 25MPa "Type of cement to
1 13 1 2.80 A. In Elevation Columns 0.25 m³
be ordinary portland cement (OPC)"
0.30 Ground floor 1 2 1 0.40 ON AXIS 5B',4D'
0.30 ON AXIS 2G,3G,4G,5G,5B,5E,5F,5C',5A,6B,6C,6D',6F 0.40 C4
3.28 m³ C1 AXIS
ON 2.75
1C,2A,3A,2B,2C,2E,2F,3B,3C,3E,3F,4A,
1 21 1 2.80 4B,4D',4E,4F,5D',1D,1E,2D,3D 0.88 m³
0.60 C2 1 1 1 0.40 ON AXIS 5 D'
0.60 0.40 C2
21.17 m³ 2.75
1 1 1 2.80 ON AXIS 5 B' 0.44 m³ 1.57 m³
0.60 C3 194.49 m³ Total To Item 1.01.A
0.60 B. In floor & top tie beam
1.01 m³ Intermediate beam
First floor
FIRST-THIRD FLOOR
ON AXIS 1 C,1 D, 1E, 2 A, 3A,2 1 1 1 12.60 ON XIS 1-(C-E)
3 21 1 2.80 B,2C,2D,2E,2F,3B,3C,3D,3E,3F, 0.50 FB-1
0.60 4A,4B,4D',4E,4F,5D'
C2 0.25
0.60 1.58 m³
63.50 m³ 1 1 1 35.93 ON AXIS-2 (A-G)
3 1 1 2.80 ON AXIS 5C' 0.50 FB-2
0.30 C1 0.25
0.30 4.49
0.76 m³ 1 1 1 35.92 ON AXIS -3 (A-G)
3 1 1 2.80 ON AXIS 5B' 0.50 FB-3
0.60 C4 0.25
0.60 4.49 m³
3.02 m³ 1 1 1 10.88 ON AXIS 4-(A-B')
FOURTH-
ON AXIS 1 SEVENTH
C,1 D, 1E, 2FLOOR
A,2 0.50 FB-4
4 21 1 2.80 B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F, 0.25
0.60 4A,4B,4D',4E,4F,5D'
C2 1.36 m³
0.60 1 1 1 16.81 ON AXIS 4 -(D'-G)
84.67 m³ 0.50 FB-5
4 1 1 2.80 ON AXIS 5C' 0.25
0.30 C1 2.1
0.30 1 1 1 5.64 ON AXIS 4 -(B'-D')
1.01 m³ 0.50 FB-5
4 1 1 2.80 ON AXIS 5B' 0.25
0.60 C4 0.71
0.60 1 1 1 35.93 ON AXIS 5 - (A-G)
4.03 m³ 0.50 FB-6
EIGHT
ON AXISFloor
1 C,1 D, 1E, 2A, 0.25
1 22 1 2.90 2B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F,4A, 4.49 m³
4B,4D',4E,4F,5B',5C',5D'
0.40 C6 1 1 1 18.42 ON AXIS 6 -(B-E )
0.40 0.50 FB-7
10.21 m³ 0.25
1 1 1 2.90 ON AXIS 5C' 2.30 m³
0.30 C1
0.30
0.26 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 3 1 13.30 ON AXIS A -(5-2 ) 7 1 1 30.60 ON AXIS-2 (A-F)


0.50 FB-8 0.50 FB-2
0.25 0.25
4.99 m³ 26.78
1 1 1 16.90 ON AXIS B -(6-2) 7 1 1 30.60 ON AXIS 3 (A-F)
0.50 FB-9 0.50 FB-3
0.25 0.25
2.11 m³ 26.78 m³

1 1 1 7 1 1
4.93 ON AXIS C -(6-5) 10.88 ON AXIS 4-(A-B')
0.50 FB-10 0.50 FB-4
0.25 0.25
0.62 m³ 9.52 m³
1 1 1 16.60 ON AXIS C (4-1) 7 1 1 11.48 ON AXIS 4 -(D'-F)
0.50 FB-11 0.50 FB-5
0.25 0.25
2.08 m³ 10.05 m³
1 2 1 6.75 b/n axis C-C'& (2-1) 7 1 1 5.64 ON AXIS 4 -(B'-D')
0.50 FB-12 0.50 FB-5
0.25 0.25
1.69 m³ 4.94 m³
1 1 1 16.60 ON AXIS D -(4-1) 7 1 1 8.84 ON AXIS -5 (B'-D')
0.50 FB-13 0.50 FB-6
0.25 0.25
2.08 m³ 7.74 m³
1 1 1 23.65 ON AXIS E-(6-1) 7 2 1 9.85 ON AXIS A and F (4-2 )
0.50 FB-14 0.50 FB-7
0.25 0.25
2.96 m³ 17.24 m³
1 1 1 7.05 ON AXIS D'-E & (6 -4) 7 1 1 9.85 ON AXIS B -(4-2 )
0.50 FB-15 0.50 FB-8
0.25 0.25
0.88 m³ 8.62 m³ 16.6
1 1 1 3.45 ON AXIS C' (5-4) 7 2 1 16.60 ON AXIS C & E (4-1)
0.50 FB-16 0.50 FB-9
0.25 0.25
0.43 m³ 29.05 m³
1 1 1 3.60 ON XIS C ( 6-5) 7 1 1 16.60 ON AXIS D-(4-1)
0.50 FB-17 0.50 FB-10
0.25 0.25
0.45 m³ 14.53 m³
1 1 1 3.45 ON AXIS B' (5-4) 7 1 1 3.45 ON AXIS D' (5-4)
0.50 FB-18 0.50 FB-11
0.25 0.25
0.43 m³ 3.02 m³
Second- 8th floor 7 1 1 3.45 ON AXIS B' (5-4)
7 1 1 12.60 ON AXIS 1-(C-E) 0.50 FB-12
0.50 FB-1 0.25
0.25 3.02 m³
11.03 m³ 7 1 1 3.45 ON AXIS C' (5-4)

0.50 FB-13
0.25
3.02 m³
7 2 1 6.75 ON AXIS C & E (1-2)
0.50
0.25
11.81 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

TOP TIE BEAM WATER TANKER BEAM


1 1 1 12.60 ON AXIS 1 (C-E) 1 1 1 8.84 ON AXIS 5 (B'-D')
0.40 RB-2 0.40 RB-11
0.25 0.25
1.26 m³ 0.88 m³
1 1 1 30.60 ON AXIS -2 (A-F) 1 1 1 8.84 ON AXIS 4 (B'-D')
0.40 RB-3 0.40 RB-12
0.25 0.25

3.06 m³ 0.88 m³
1 1 1 30.60 ON AXIS 3 -(A-F) 1 1 1 3.45 ON AXIS B' (4-5)
0.40 RB-5 0.40 RB-13
0.25 0.25
3.06 m³ 0.35 m³
1 1 1 10.88 ON AXIS 4 (A-B' ) 1 1 1 3.45 ON AXIS (4-5)
0.40 RB-4 0.40 RB-14
0.25 0.25
1.09 m³ 0.35 m³
1 1 1 10.88 ON AXIS 4 (B'-D' ) 1 1 1 3.45 ON AXIS D' (4-5)
0.40 RB-5 0.40 RB-15
0.25 0.25
1.09 m³ 0.35 m³
1 1 1 8.84 ON AXIS 5 (B'-D') 2.81 m³
0.40 RB-10 249.28 m³ Total To Item 1.1.B
0.25 C. Stair case & Landing
0.88 m³ Grnd-8th Floor
1 1 1 9.85 ON AXIS A (4-2) main stair case
0.40 RB-6 SECTION A-A
0.25 9 0.5 7 1.03 riser
0.99 m³ 0.28
1 2 1 9.85 ON AXIS B & F (4-2) 0.17
0.40 RB-7 1.54 m³
0.25 9 1 1 1.95 sofit
1.97 m³ 1.03
1 2 1 16.60 ON AXIS C & D-(4-1) 0.22
0.40 RB-8 3.98 m³
0.25 9 1 1 1.15 Landing 1
3.32 m³ 1.03
1 1 1 3.45 ON AXIS C' (5-4) 0.22
0.40 RB-1 2.35 m³
0.25 9 1 1 0.40 ddt
0.35 m³ 0.40
1 1 1 3.45 0.22
0.40 ON AXIS B' & D' (5-4) -0.32 m³
0.25 RB-9 SECTION B-B
0.35 m³ 9 0.5 5 1.03 riser
1 1 1 16.60 ON AXIS E (4-1 ) 0.28
0.40 RB-10 0.17
0.25 1.07 m³
1.66 m³ 9 1 1 1.93 sofit
1.03
0.22
3.94 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

9 1 1 1.15 Landing 1 1 1 1 1.80 W3


1.03 3.30
0.22 0.25
2.35 m³ 1.49 m³
SECTION C-C 1 1 1 1.80 W4
9 0.5 7 1.03 riser 3.30
0.29 0.25
0.17 1.49 m³
1.55 m³ 1 1 -1 2.10 DDT
9 1 1 1.93 sofit 1.00 OPENING
1.15 0.25
0.22 -0.53 m³

4.39 m³
1st to 8th
9 1 1 3.10 landing beam
0.50
0.25
3.49 m³
SHOP STAIR 8 2 1 2.60 W2
Ground Floor 3.30
SECTION E-E 0.25
1 0.5 11 1.05 riser 34.32 m³
0.30 8 1 1 1.80 W3
0.15 3.30
0.26 m³ 0.25
1 1 1 3.75 sofit 11.88 m³
1.05 8 1 1 1.80 W4
0.22 3.30
0.87 m³ 0.25
1 1 1 1.98 Landing 1 11.88 m³
1.05 8 1 -1 2.10 DDT
0.22 1.00 OPENING
0.46 m³ 0.25
SECTION F-F -4.20 m³
1 0.5 11 1.05 riser ABOVE 8TH FLOOR
0.30 1 1 1 2.60 W2
0.15 0.70
0.26 m³ 0.25
1 1 1 3.30 sofit 0.46 m³
1.05 1 1 1 2.60 W2
0.22 0.70
0.76 m³ 0.25
1 1 1 1.98 Landing 1 0.46 m³
1.05 1 1 1 1.80 W3
0.22 0.70
0.46 m³ 0.25
0.32 m³
27.41 m³ Total To Item 1.1.C 1 1 1 1.80 W4
D) In Shear wall for lift shaft 0.70
GROUND FLOOR 0.25
1 2 1 2.60 W2 0.32 m³
3.30 1 1 1 1.00 DDT LIFT DOOR
0.25 1.30
4.29 m³ 0.25
-0.33 m³
1.23 m³
61.85 m³ Total To Item 1.1.E

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

E. In RC Gutter 1 -13 1 0.05 Deduct Column Contact Area


1 1 1 23.25 On Axis 1'-2' / A-C 0.05 Axis 2G, 3G 4G, 5A, 5B, 5C', 5E, 5F,5G,6B,6C,6D,6E
0.15 -0.03 m²
0.90 SECOND- EIGHTH FLOOR
3.14 m³ 7 1 1 6.55 ON Axis 1 B/N C-D
1 1 1 15.00 On Axis 1'-2' / E-F 1.05
0.15 48.14 m²
0.90 7 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E

2.03 m³ 1.20

1 1 1 12.38 On Axis 4 / E-F 74.42 m²


0.15 7 1 1 3.45 ON Axis 4-5 B/N B'-C'
0.90 0.91 2.84
1.67 m³ 68.59 m²
7 1 1 1.45 ON Axis 4-5 B/N B'-C'
6.84 m³ Total To Item 1.1E 1.40
F. 15cm thick solid slab 14.21 m²
FIRST FLOOR Deduct Column Contact Area
1 1 1 5.93 B/ N Axis 4-5 & A-B 7 -1 1 0.35
3.45 0.17
20.46 m² -0.42 m²
1 1 1 4.46 B/ N Axis B-B' & 4-5 1 1 1 6.50 ON Axis 1 B/N C-D
3.45 1.05
15.37 m² 6.83 m²
1 1 1 2.84 B/ N Axis C-C' & 4-5 1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
3.45 1.20
9.80 m² 10.63 m²
1 1 1 4.63 B/ N Axis D'-E & 4-5 1 1 1 3.45 ON Axis 4-5 B/N B'-D
3.45 2.90
15.97 m² 10.01 m²
1 1 1 5.75 B/ N Axis E-F & 4-5 1 1 1 2.84 ON Axis 4-5 B/N B'-D
3.45 3.45
19.84 m² 9.80 m²
1 1 1 5.08 B/ N Axis F-G & 4-5 1 1 1 2.35
3.45 1.40
17.53 m² 3.29 m²
1 1 1 5.08 B/ N Axis F-G & 2-3 1 -2 1 0.15 Deduct column contact area
4.93 0.15
25.04 m² -0.05 m² 40.51 m²
1 1 1 5.08 B/ N Axis F-G & 3-4
4.93 459.25 m² Total To Item 1.1.G
25.04 m² Roof slab
1 1 1 5.58 B/ N Axis B-C & 5-6 1 1 1 5.19 WATER TANKER SLAB
3.60 3.45 b/n Axis 4-5 & B'-D'
20.09 m² 17.91 m²
1 1 1 3.60 B/ N Axis C-D' & 5-6
7.22 1 1 1 2.90
25.99 m² 3.45

1 1 1 4.63 B/ N Axis D'-E & 5-6 10.01 m²


3.60 1 -2 1 0.15 Deduct column contact area
16.67 m² 0.15
1 1 1 1.45 ON Axis 4-5 B/N B'-C' -0.05 m² 27.87 m²
1.40
2.03 m² 27.87 m² Total To Item 1.1.F

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description
H. Extra 6cm thick concrete on
Bathroom
1St Floor 5th - 8th floor
1 1 1 5.03 B/ N Axis A'-B & 2-3 4 1 1 0.05 At slab, beam & column conection
4.65 0.05 C-1
23.39 m² 0.34
0 -1 1 1.95 Deduct HCB Area 0.00 m³
0.20 4 1 22 0.15
0.00 m² 0.15 C-2

0 -1 1 7.45 0.34

0.10 0.67 m³
0.00 m² At Roof Level
0 -1 1 1.87 1 1 1 0.05 At slab, beam & column conection
0.10 0.05 C-1
0.00 m² 0.40
0 -1 1 0.63 0.00 m³
1.20 1 1 22 0.15
0.00 m² 0.15 C-2
2nd-8th floor 0.40
7 2 1 1.47 B/ N Axis C-D & 1-1' 0.20 m³
2.20
45.28 m² 4.54 m³ Total Item 1.01i
7 -1 1 0.35
0.60
-1.47 m²
7 1 1 1.78 Axis 2-3 b/n B-B'
2.07
25.79 m²
7 1 2 2.90 B/ N Axis E-F &A-B , 2'-3'
2.58
104.75 m²
7 -2 1 0.63
1.20
-10.58 m²

187.16 m² Total Area To Item 1.01 H


11.23 m³ Total Volume To Item 1.01 H

I. Concrete fillers around columns &


beam connection at floor levels
1st - 4th floor
At slab, beam & column conection
4 1 1 0.05 C-1
0.05
0.34

0.00 m³

4 1 22 0.35 C-2
0.35
0.34
3.67 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Ribbed slab for suspended floor Payment No._final payment_
slab made of 60 mm thick concrete

Ite.

Ite.
x Dim. Qty Description
slab in C-25,60x240 mm one way x Dim. Qty Description
concrete girder with c/c spacing of
5 2 1 5.58 B/ N Axis B-B' & 2-3 , 3-4
400mm including 200x400x240mm
FIRST
hollow concrete FLOOR
ribbed block and all 4.93
1 2 1 5.93 B/ N
according toAxis A-B&
the detail 2-3 ,3-4
structural 275.09 m²
4.93 drawing. 5 1 1 6.75 B/ N Axis C - D & 1-2
58.47 m² 5.67
1 1 1 3.13 B/ N Axis B-B' & 2-3 191.36 m²
4.93 5 2 1 5.92 B/ N Axis C - D & 2-3 & 3-4
15.43 m² 4.93

1 1 1 5.58 B/ N Axis B-B' & 3-4 291.86 m²

4.93 5 1 1 5.68 B/N Axis D-E & 1-2


27.51 m² 6.75
1 1 1 5.67 B/ N Axis C - D & 1-2 191.70 m²
6.75 5 2 1 5.92 B/N Axis D-E & 2-3, 3-4
38.27 m² 4.93
1 2 1 5.92 B/ N Axis C - D & 2-3 & 3-4 291.86 m²
4.93 5 2 1 5.75 B/N Axis E-F & 2-3,3-4
58.37 m² 4.93
1 1 1 5.67 B/N Axis D-E & 1-2 283.48 m² 1525.34 m²
6.75 Deduct column edge contact area
38.27 m² FIRST-THIRD FLOOR
1 2 1 5.92 B/N Axis D-E & 2-3, 3-4 3 -3 1 0.35 Axis 1
4.93 0.35
58.37 m² -1.10 m²
1 2 1 5.75 B/N Axis E-F & 2-3,3-4 3 -6 1 0.35 Axis 2
4.93 0.35
56.70 m² -2.21 m²
SECOND-THIRED FLOOR 3 -1 1 0.05
2 2 1 5.93 B/ N Axis A - B & 2-3 ,3-4 0.05
4.93 -0.01 m²
116.94 m² 3 -6 1 0.35 Axis 3
2 2 1 5.58 B/ N Axis B-C & 2-3 , 3-4 0.35
4.93 -2.21 m²
110.04 m² 3 -1 1 0.05
2 1 1 6.75 B/ N Axis C - D & 1-2 0.05
5.67 -0.01 m²
76.55 m² 3 -5 1 0.35 Axis 4
2 2 1 5.92 B/ N Axis C - D & 2-3 & 3-4 0.35
4.93 -1.84 m²
116.74 m² 3 -1 1 0.05
2 1 1 5.68 B/N Axis D-E & 1-2 0.05
6.75 -0.01 m²
76.68 m² 3 -1 1 0.35 Axis 5
2 2 1 5.92 B/N Axis D-E & 2-3, 3-4 0.18
4.93 -0.19 m² -7.60 m²
116.74 m² 3 -5 1 0.05
2 2 1 5.75 B/N Axis E-F & 2-3,3-4 0.05

4.93 -0.04 m²

113.39 m² 5 -20 1 0.15 FOURTH -EIGHTH FLOOR


FOURTH -EIGHTH FLOOR 0.15
5 2 1 5.93 B/ N Axis A - B & 2-3 ,3-4 -2.25 m²
4.93 2886.31 m² Total Item 1.3
292.35 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Provide, Cut and Fix in position


Sawn zigba wood form work for: 1 1 1 2.80 ON AXIS 5C'
A) Elevation columns 1.20
3.36 m²
water tanker
1 3 1 2.10 ON AXIS 5B',5D',4D'
1.60
10.08 m²

1368.80 m² Total To Item 1.04.A


B) In Floor & Top Tie beam
1) intermediate beam
First floor
External
1 1 1 12.60 ON AXIS 1-(C-E)
0.50 FB-1
6.30 m²
Internal
1 1 1 10.80 ON AXIS 1-(C-E)
0.22 FB-1
2.38 m²
Bottom
Ground floor 1 1 1 10.80 ON AXIS 1-(C-E)
0.25 FB-1
1 12 1 2.80 ON AXIS 2G,3G,4G,5A,5B,5E,5F,5G,6B,6C,6D',6E 2.70 m²
1.20 External
ON AXIS 1 C,2A,3A,2
40.32 m² B,2C,2E,2F,3B,3C,3E,3F,4A,4B,4D',4E,4 1 1 1 23.33 ON AXIS-2 (A-G)
1 19 1 2.80 F,5B',5C',5D' 0.50 FB-2
2.40 11.67 m²
127.68 m² Internal
1 4 1 2.80 ON AXIS 1D,1E,2D,3D 1 1 1 10.80 ON AXIS-2 (A-C)
2.40 0.22 FB-2
26.88 m² 2.38 m²
1 2 1 10.80 ON AXIS-2 (C-E)
ON AXISFIRST-THIRD
1 C,1 D, 1E, 2 FLOOR
A, 3A,2 0.22 FB-2
3 22 1 2.80 B,2C,2D,2E,2F,3B,3C,3D,3E,3F, 4.75 m²
2.40 4A,4B,4D',4E,4F,5B',5D' 1 1 1 10.80 ON AXIS-2 (E-G)
443.52 m² 0.22 FB-2
3 1 1 2.80 ON AXIS 5C' 2.38 m²
1.20 Bottom
10.08 m² 1 1 1 32.03 ON AXIS-2 (A-G)
FOURTH- SEVENTH FLOOR 0.25 FB-2
ON AXIS 1 C,1 D, 1E, 2 A,2 8.01 m²
4 22 1 2.80 B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F, Internal
2.40 4A,4B,4D',4E,4F,5C',5D' 1 2 1 27.00 ON AXIS -3 (A-f)
591.36 m² 0.22 FB-3

4 1 1 2.80 ON AXIS 5C' 11.88 m²


1.20 1 2 1 5.03 ON AXIS -3 (A-G)
13.44 m² 0.34 FB-3
EIGHT
ON AXIS 1 C,1 D, 1E,Floor
2A, 3.42 m²
1 22 1 2.90 2B,2C,2D,2E,2F,3A,3B,3C,3D,3E,3F,4A, 1 1 1 32.03 Bottom
1.60 4B,4D',4E,4F,5B',5C',5D' 0.25 ON AXIS -3 (A-G)
102.08 m² 8.01 m² FB-3

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal Bottom
1 1 1 9.68 ON AXIS 4-(A-B') 1 3 1 12.60 ON AXIS A & G-(5-2 )
0.22 FB-4 0.25 FB-8
2.13 m² 9.45 m²
1 1 1 9.68
0.34
3.29 m²
bottom 1 2 1 12.20 ON AXIS F -(5-2 )
1 1 1 9.68 ON AXIS 4-(A-B') 0.34 FB-8
0.25 FB-4 8.30 m²
2.42 m² Internal
Internal 1 2 1 8.80 ON AXIS B -(2-5)
1 1 1 15.32 ON AXIS 4 -(C-F) 0.22 FB-9
0.22 FB-5 3.87 m²
3.37 m² Internal
1 1 1 12.52 ON AXIS 4 -(C-F) 1 2 1 3.40 ON AXIS B -(4-5)
0.34 0.34 FB-9
4.26 m² 2.31 m²
1 1 1 2.55 ON AXIS 4 -(C'-D')
0.50

1.28 m²
1 1 2 5.03 ON AXIS 4 -(F-G)
0.34
3.42 m²
bottom 1 1 1 3.55 ON AXIS B -(6-5)
1 1 1 20.05 ON AXIS 4 -(D'-G) 0.34 FB-9
0.25 FB-5 1.21 m²
5.01 m² External
External 1 1 1 3.85 ON AXIS B -(6-5)
1 1 1 19.13 ON AXIS 5 - (A-B AND E-G) 0.50 FB-9
0.50 FB-6 1.93 m²
9.57 m² Bottom
Internal 1 1 1 15.75 ON AXIS B -(6-2)
1 2 1 16.32 ON AXIS 5 - (B-E) 0.25 FB-9
0.34 FB-6 3.94 m²
11.10 m² Internal
1 1 1 16.58 ON AXIS 5 - (A-B,E-G)
0.34 FB-6
5.64 m²
bottom 1 1 1 4.93 ON AXIS -(3-2)
1 1 1 32.93 ON AXIS 5 - (A-G) 0.22 FB-10
0.25 FB-6 1.08 m²
8.23 m² External
Internal 1 1 1 4.93 ON AXIS B-B'-(3-2)
1 1 1 17.20 ON AXIS 6 -(B-E ) 0.50 FB-10
0.34 FB-7 2.47 m²
5.85 m² Bottom
External 1 1 1 4.93 ON AXIS B-B'-(3-2)
1 1 1 18.42 ON AXIS 6 -(B-E ) 0.25 FB-10
0.50 FB-7 1.23 m²
9.21 m² Internal
Bottom 1 1 1 10.79 ON AXIS C (3-1)
1 1 1 17.20 ON AXIS 6 -(B-E ) 0.22 FB-11
0.25 FB-7 2.37 m²
4.30 m² 1 1 1 4.76 ON AXIS C (4-3)
Internal 0.22 FB-11
1 1 1 12.20 ON AXIS F (5-2 ) 1.05 m²
0.34 FB-8 External
4.15 m² 1 1 1 11.92 ON AXIS C (2-1)
1 1 2 3.40 ON AXIS F (5-4 )
0.34 FB-8
2.31 m²
Internal 0.50 FB-11
1 1 1 12.80 ON AXIS G & A -(5-2 ) 5.96 m²
0.34 FB-8 Bottom
4.35 m² 1 1 1 15.55 ON AXIS C (4-1)
External 0.25 FB-11
1 2 1 14.30 ON AXIS A & G -(5-2 ) 3.89 m²
0.50 FB-8
14.30 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal Internal
1 2 2 6.75 b/n axis C-C'& D'-E (2-1) 1 1 2 1.25 ON AXIS B' (5-4)
0.22 FB-12 0.34 FB-18
5.94 m² 0.85 m²
Bottom Bottom
1 2 1 6.75 b/n axis C-C'& D'-E (2-1) 1 1 1 1.25 ON AXIS B' (5-4)
0.25 FB-12 0.25 FB-18
3.38 m² 0.31 m²
Internal Second- Third floor
1 1 1 15.15 ON AXIS D -(4-1) Internal
0.22 FB-13 2 1 1 10.80 ON AXIS 1-(C-E)
3.33 m² 0.22 FB-1
Bottom 4.75 m²
1 1 1 15.15 ON AXIS D -(4-1)
0.25 FB-13 2 1 1 5.15 ON AXIS 1-(C-E)
3.79 m² 0.34 FB-1
3.50 m²
Internal External
1 1 1 16.85 ON AXIS D -(4-1) 2 1 1 6.00 ON AXIS 1-(C-E)
0.22 FB-14 0.50 FB-1
3.71 m² 6.00 m²
1 1 1 6.95 ON AXIS D -(6-4)
0.34 FB-14
2.36 m²
1 1 1 3.40 ON AXIS D -(5-4) Bottom
0.34 FB-14 2 1 1 10.80 ON AXIS 1-(C-E)
1.16 m² 0.25 FB-1
External 5.40 m²
1 1 1 6.40 ON AXIS E-(2-1 ) Internal
0.50 FB-14 2 2 1 10.80 ON AXIS-2 (C-E)
3.20 m² 0.22 FB-2
1 1 1 3.55 ON AXIS D -(5-6) 9.50 m²
0.34 FB-14
1.21 m²
Bottom
1 1 1 22.15 ON AXIS E-(6-1) 2 1 1 16.20 ON AXIS-2 (A-F)
0.25 FB-14 0.22 FB-2
5.54 m² 7.13 m²
Internal External
1 1 2 6.95 ON AXIS D' (6 -4) 2 1 1 18.00 ON AXIS-2 (A-F)
0.34 FB-15 0.50 FB-2
4.73 m² 18.00 m²
Bottom Bottom
1 1 1 6.95 ON AXIS D' (6 -4) 2 1 1 27.00 ON AXIS-2 (A-F)
0.25 FB-15 0.25 FB-2
1.74 m² 13.50 m²
Internal Internal
1 1 2 3.10 ON AXIS C' (5-4) 2 2 1 27.00 ON AXIS 3 (A-F)
0.34 FB-16 0.22 FB-3
2.11 m² 23.76 m²
Bottom Bottom
1 1 1 3.10 ON AXIS C' (5-4) 2 1 1 27.00 ON AXIS 3 (A-F)
0.25 FB-16 0.25 FB-3
0.78 m² 13.50 m²
Internal Internal
1 1 2 3.55 ON XIS C ( 6-5) 2 1 1 9.68 ON AXIS 4-(A-B')
0.22 FB-17 0.22 FB-4
1.56 m² 4.26 m²
Bottom External
1 1 1 3.55 ON XIS C ( 6-5) 2 1 1 10.88 ON AXIS 4-(A-B')
0.25 FB-17 0.50 FB-4
0.89 m² 10.88 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 0 1 -4.43 ON AXIS 4-(A-B') Bottom


0.50 dedu 2 1 1 8.80 ON AXIS B -(4-2 )
0.00 m² 0.25 FB-8
Bottom 4.40 m²
2 1 1 9.68 ON AXIS 4-(A-B') Internal
0.25 FB-4 2 2 1 15.20 ON AXIS C & E (4-1)
4.84 m² 0.22 FB-9
Internal 13.38 m²

2 1 1
2.84 ON AXIS 4 -(C-F) Internal
0.22 FB-5 2 2 1 15.20 ON AXIS C & E (4-1)
1.25 m² 0.22 FB-9
2 1 1 15.18 ON AXIS 4 -(C'-F) 13.38 m²
0.22 FB-5 External
6.68 m² 2 2 1 7.00 ON AXIS C (4-1)
2 1 1 2.55 ON AXIS 4 -(C-F) 0.50 FB-9
0.50 FB-5 14.00 m²
2.55 m² Bottom
External 2 2 1 15.20 ON AXIS C (4-1)
2 1 1 10.88 ON AXIS 4 -(D'-F) 0.25 FB-9
0.50 FB-5 15.20 m²
10.88 m² Internal
Bottom 2 1 2 15.20 ON AXIS D -(4-1)
2 1 1 15.32 ON AXIS 4 -(D'-F) 0.22 FB-10
0.25 FB-5 13.38 m²
7.66 m² Bottom
External 2 1 1 15.20 ON AXIS D -(4-1)
2 1 1 8.84 ON AXIS -5 (B'-D') 0.25 FB-10
0.50 FB-6 7.60 m²
8.84 m² Internal
Internal 2 1 1 3.10 ON AXIS D' (5-4)
2 1 1 6.94 ON AXIS -5 (B'-D') 3.34 FB-11
0.34 FB-6 20.71 m²
4.72 m² External
Bottom 2 1 1 3.70 ON AXIS D' (5-4)
2 1 1 7.34 ON AXIS -5 (B'-D') 0.50 FB-11
0.25 FB-6 3.70 m²
3.67 m² Bottom
External 2 1 1 3.10 ON AXIS D' (5-4)
2 2 1 10.60 ON AXIS A & F (4-2 ) 0.25 FB-11
0.50 FB-7 1.55 m²
21.20 m² Internal
Internal 2 1 1 1.25 ON AXIS B' (5-4)
2 2 1 8.80 ON AXIS A & F (4-2 ) 0.34 FB-12
0.22 FB-7 0.85 m²
7.74 m² 2 1 1 1.25 Bottom
Bottom 0.25 ON AXIS B' (5-4)
2 2 1 8.80 ON AXIS A & F (4-2 ) 0.63 m² FB-12
0.25 FB-7 External
8.80 m² 2 1 1 1.55 ON AXIS B' (5-4)
2 1 2 8.80 Internal 0.50 FB-12
0.22 ON AXIS B -(4-2 ) 1.55 m²
7.74 m² FB-8

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal Internal
2 1 2 3.10 ON AXIS C' (5-4) 5 1 1 9.88 ON AXIS 4-(A-B')
0.34 FB-13 0.22 FB-4
4.22 m² 10.87 m²
Bottom External
2 1 1 3.10 ON AXIS C' (5-4) 5 1 1 10.88 ON AXIS 4-(A-B')
0.25 FB-13 0.50 FB-4
1.55 m² 27.20 m²

5 0 1
Internal -4.43 ON AXIS 4-(A-B')
1 2 2 6.75 b/n axis C-C' & D'-E (2-1) 0.50 deduct balcony side
0.22 FB-12' 0.00 m²
5.94 m² Bottom
Bottom 5 1 1 9.88 ON AXIS 4-(A-B')
1 2 1 6.75 b/n axis C-C' & D'-E (2-1) 0.25 FB-4
0.25 FB-12' 12.35 m²
3.38 m² Internal
Fourth- Eighth floor 5 1 1 9.68 ON AXIS 4 -(C-F)
Internal 0.22 FB-5
5 1 1 10.80 ON AXIS 1-(C-E) 10.65 m²
0.22 FB-1 5 1 1 2.84 ON AXIS 4 -(C-F)
11.88 m² 0.22 FB-5
5 1 1 5.15 ON AXIS 1-(C-E) 3.12 m²
0.34 FB-1 5 1 1 2.55 ON AXIS 4 -(C-F)
8.76 m² 0.50 FB-5
External 6.38 m²
5 1 1 12.60 ON AXIS 1-(C-E) 5 1 1 15.08 ON AXIS 4 -(C-F)
0.50 FB-1 0.22 FB-5
31.50 m² 16.59 m²
Bottom External
5 1 1 11.00 ON AXIS 1-(C-E) 5 1 1 10.88 ON AXIS 4 -(D'-F)
0.25 FB-1 0.50 FB-5
13.75 m² 27.20 m²
Internal Bottom
5 2 1 11.00 ON AXIS-2 (C-E) 5 1 1 15.72 ON AXIS 4 -(D'-F)
0.22 FB-2 0.25 FB-5
24.20 m² 19.65 m²
5 1 1 16.80 ON AXIS-2 (A-F) External
0.22 FB-2 5 1 1 8.84 ON AXIS -5 (B'-D')
18.48 m² 0.50 FB-6
External 22.10 m²
5 1 1 18.00 ON AXIS-2 (A-F) Internal
0.50 FB-2 5 1 1 7.74 ON AXIS -5 (B'-D')
45.00 m² 0.34 FB-6
Bottom 13.16 m²
5 1 1 27.80 ON AXIS-2 (A-F) Bottom
0.25 FB-2 5 1 1 7.74 ON AXIS -5 (B'-D')
34.75 m² 0.25 FB-6
Internal 9.68 m²
5 1 1 27.80 ON AXIS 3 (A-F) External
0.22 FB-3 5 2 1 10.60 ON AXIS A & F (4-2 )
30.58 m² 0.50 FB-7
Bottom 53.00 m²
5 1 1 27.80 ON AXIS 3 (A-F) 5 2 1 9.40 Internal
0.25 FB-3 0.22 ON AXIS A & F (4-2 )
34.75 m² 20.68 m² FB-7

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Bottom 5 1 1 1.25 Bottom


5 2 1 9.40 ON AXIS A & F (4-2 ) 0.25 ON AXIS B' (5-4)
0.25 FB-7 1.56 m² FB-12
23.50 m² External
Internal 5 1 1 1.55 ON AXIS B' (5-4)
5 1 2 9.00 ON AXIS B -(4-2 ) 0.50 FB-12
0.22 FB-8 3.88 m²
19.80 m² Internal

Bottom 5 1 2
3.10 ON AXIS C' (5-4)
5 1 1 9.00 ON AXIS B -(4-2 ) 0.22 FB-13
0.25 FB-8 6.82 m²
11.25 m² Bottom
Internal 5 1 1 3.10 ON AXIS C' (5-4)
5 2 1 15.60 ON AXIS C & E (4-1) 0.34 FB-13
0.22 FB-9 5.27 m²
34.32 m² Internal
Internal 5 2 2 6.75 b/n axis C-C' & D'-E (2-1)
5 2 1 15.40 ON AXIS C & E (4-1) 0.22 FB-12'
0.22 FB-9 29.70 m²
33.88 m² Bottom
External 5 2 1 6.75 b/n axis C-C' & D'-E (2-1)
5 2 1 7.00 ON AXIS C (4-1) 0.25 FB-12'
0.50 FB-9 16.88 m²
35.00 m² 1446.63 m² Total To Item 1.04.B
Bottom TOP TIE BEAM
5 2 1 15.60 ON AXIS C (4-1) Internal
0.25 FB-9 1 1 2 3.45 ON AXIS C' (5-4)
39.00 m² 0.40 RB-1
Internal 2.76 m²
5 1 2 15.60 ON AXIS D -(4-1) bottom
0.22 FB-10 1 1 1 3.45 ON AXIS C' (5-4)
34.32 m² 0.25 RB-1
Bottom 0.86 m²
5 1 1 15.60 ON AXIS D -(4-1) Internal
0.25 FB-10 1 1 1 11.40 ON AXIS 1 (C-E)
19.50 m² 0.40 RB-2
Internal 4.56 m²
5 1 1 3.10 ON AXIS D' (5-4) External
0.34 FB-11 1 1 1 12.60 ON AXIS 1 (C-E)
5.27 m² 0.40 RB-2
External 5.04 m²
5 1 1 3.70 ON AXIS D' (5-4) Bottom
0.50 FB-11 1 1 1 11.40 ON AXIS 1 (C-E)
9.25 m² 0.25 RB-2
Bottom 2.85 m²
5 1 1 3.10 ON AXIS D' (5-4) External
0.25 FB-11 1 1 1 18.00 ON AXIS -2 (A-C) AND E-F
3.88 m² 0.40 RB-3
Internal 7.20 m²
5 1 1 1.25 ON AXIS B' (5-4)
0.22 FB-12
1.38 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal Internal
1 1 1 11.40 ON AXIS -2 (C-E) 1 1 1 9.40 ON AXIS A- (4-2)
0.40 RB-3 0.40 RB-6
4.56 m² 3.76 m²
Internal Bottom
1 1 1 25.65 ON AXIS -2 (A-F) 1 1 1 9.40 ON AXIS A- (4-2)
0.40 RB-3 0.25 RB-6
10.26 m² 2.35 m²

Bottom Internal
1 1 1 27.40 ON AXIS -2 (A-F) 1 1 2 9.40 ON AXIS B & F(4-2)
0.25 RB-3 0.40 RB-7
6.85 m² 7.52 m²
External Bottom
1 1 1 10.88 ON AXIS 4-(A-B) 1 1 1 9.40 ON AXIS B & F(4-2)
0.40 RB-4 0.25 RB-7
4.35 m² 2.35 m²
1 -1 1 4.43 DEDUCT BALCONY SIDE External
0.40 1 1 1 7.00 ON AXIS C & D (1-4 )
-1.77 m² 0.40 RB-8
Internal 2.80 m²
1 1 1 10.08 ON AXIS 4-(A-B) Internal
0.40 RB-4 1 2 1 6.60 ON AXIS C & D (1-4 )
4.03 m² 0.40 RB-8
Bottom 5.28 m²
1 1 1 10.08 ON AXIS 4-(A-B) 1 1 1 9.55 ON AXIS C & D (1-4 )
0.25 RB-4 0.40 RB-8
2.52 m² 3.82 m²
External Bottom
1 1 1 10.88 ON AXIS 4 -(C-F) 1 1 1 15.95 ON AXIS C & D (1-4 )
0.40 RB-4 0.25 RB-8
4.35 m² 3.99 m²
1 -1 1 4.43 DEDUCT BALCONY SIDE External
0.40 1 1 1 1.65 ON AXIS B' (4-5)
-1.77 m² 0.40 RB-9
Internal 0.66 m²
1 1 1 15.67 ON AXIS 4 -(C-F) Internal
0.40 RB-5 1 1 1 1.25 ON AXIS B' (4-5)
6.27 m² 0.40 RB-9
1 1 1 5.59 ON AXIS 4 -(C-F) 0.50 m²
0.40 RB-5 Bottom
2.24 m² 1 1 1 1.25 ON AXIS B' (4-5)
Bottom 0.25 RB-9
1 1 1 15.42 ON AXIS 4 -(C-F) 0.31 m²
0.25 RB-5 External
3.86 m² 1 1 1 3.70 ON AXIS D' (4-5)

External 0.40 RB-9


1 1 1 10.60 ON AXIS A- (4-2) 1.48 m²
0.40 RB-6 Internal
4.24 m² 1 1 1 3.30 ON AXIS D' (4-5)
0.40 RB-9
1.32 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Bottom Internal
1 1 1 3.30 ON AXIS D' (4-5) 1 1 2 5.61 ON AXIS 4 (B'-D')
0.25 RB-9 0.40 RB-12
0.83 m² 4.49 m²
External Bottom
1 1 1 8.84 ON AXIS 5 (B'-D') 1 1 1 5.61 ON AXIS 4 (B'-D')
0.40 RB-10 0.25 RB-12
3.54 m² 1.40 m²

Internal External
1 1 1 7.79 ON AXIS 5 (B'-D') 1 1 1 3.70 ON AXIS B' (4-5)
0.40 RB-10 0.40 RB-13
3.12 m² 1.48 m²
Bottom Internal
1 1 1 8.04 ON AXIS 5 (B'-D') 1 1 1 3.30 ON AXIS B' (4-5)
0.25 RB-10 0.40 RB-13
2.01 m² 1.32 m²
External Bottom
1 1 1 7.00 ON AXIS E (4-1) 1 1 1 3.30 ON AXIS B' (4-5)
0.40 RB-10 0.25 RB-13
2.80 m² 0.83 m²
Internal Internal
1 1 2 9.40 ON AXIS E (4-1) 1 1 2 3.45 ON AXIS (4-5)
0.40 RB-10 0.40 RB-14
7.52 m² 2.76 m²
1 1 1 6.60 ON AXIS E (4-1) Bottom
0.40 RB-10 1 1 1 3.45 ON AXIS (4-5)
2.64 m² 0.25 RB-14
Bottom 0.86 m²
1 1 1 15.95 ON AXIS E (4-1) External
0.25 RB-10 1 1 1 3.70 ON AXIS B' (4-5)
3.99 m² 0.40 RB-13
Internal 1.48 m²
1 1 1 16.31 ON AXIS (5-1) Internal
0.40 RB-11 1 1 1 3.30 ON AXIS D' (4-5)
6.52 m² 0.40 RB-15
WATER TANKER BEAM 1.32 m²
External Bottom
1 1 1 8.84 ON AXIS 5 (B'-D') 1 1 2 3.30 ON AXIS D' (4-5)
0.40 RB-11 0.25 RB-15
3.54 m² 1.65 m²
Internal 9268.25090000001
1 1 1 7.79 ON AXIS 5 (B'-D') 173.26 m² Total To Item 1.04.B
0.40 RB-11 C) Stair case & Landing
3.12 m² Main stair case
Bottom Ground-8th floor
1 1 1 7.79 ON AXIS 5 (B'-D') SECTION A-A
0.25 RB-11 9 1 7 1.03 riser
1.95 m² 0.17
External 11.03 m²
1 1 2 5.86 ON AXIS 4 (B'-D')
0.40 RB-12
4.69 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

9 1 1 1.95 sofit 1 1 2 3.02 side formwork


1.03 0.39
18.08 m³ 2.36 m³
9 1 1 1.03 Landing 1 1 1 1 3.30 sofit
1.15 1.05
10.66 m³ 3.47 m³
9 1 2 1.86 side formwork 1 1 1 1.98 Landing 1
0.39 2.20

13.06 m³ 4.36 m³

1 1 2 1.98 side Landing formwork


SECTION B-B 0.22
9 1 5 1.03 riser 0.87 m³
0.17
7.65 m³ 185.89 m² Total To Item 1.04.C
9 1 1 1.30 sofit D) Shear wall
1.03 GROUND FLOOR
12.05 m³ external
9 1 1 1.15 Landing 1 1 1 2 2.60 W2
1.03 3.30
10.66 m³ 17.16 m³
9 1 2 1.86 side formwork Internal
0.39 1 1 2 2.10 W2
13.06 m³ 3.30
SECTION C-C 13.86 m³
9 1 7 1.03 riser external
0.17 1 1 1 2.30 W3
10.71 m³ 3.30
9 1 1 1.93 sofit 7.59 m³
1.15 Internal
19.98 m³ 1 1 1 1.80 W3
9 1 2 1.45 side formwork 3.30
0.39 5.94 m³
10.18 m³ external
9 1 1 3.10 side formwork 1 1 1 2.30 W4
1.09 3.30
30.41 m³ 7.59 m³

SHOP STAIR Internal


SECTION E-E 1 1 1 1.80 W4
1 1 11 0.15 riser 3.30
0.30 5.94 m³
0.50 m³ 1 1 -2 2.10 DDT
1 1 1 3.75 sofit 1.00 OPENING
1.05 -4.20 m³
3.94 m³ Side formwork
1 1 2 0.25
2.10
1.05 m²
1 1 1 0.25
1.00
0.25 m² 1st to 8th
1 1 2 3.02 side formwork external
0.39 8 1 2 2.60 W2
2.36 m³ 3.30
SECTION F-F 137.28 m²
1 1 11 0.15 riser Internal
0.30 8 1 2 2.10 W2
0.50 m³ 3.30
110.88 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

external E). In Concrete gutter


8 1 1 2.30 W3 External
3.30 1 1 1 23.85 on axis A'-C b/n 1'-2'
60.72 m³ 0.84
Internal 20.03 m² internal
8 1 1 1.80 W3 1 1 1 23.25 on axis A'-C b/n 1'-2'
3.30 0.78
47.52 m³ 18.14 m² bottom

external 1 1 1 23.85
on axis A'-C b/n 1'-2'
8 1 1 2.30 W4 0.25
3.30 5.96 m²
60.72 m³ External
Internal 1 1 1 15.86 on axis E'-F' b/n 1'-2'
8 1 1 1.80 W4 0.84
3.30 13.32 m² internal
47.52 m³ 1 1 1 15.00 on axis E'-F' b/n 1'-2'
8 1 -2 2.10 DDT 0.84
1.00 OPENING 12.60 m² bottom
-33.60 m³ 1 1 1 15.86 on axis E'-F' b/n 1'-2'
Side formwork 0.25
8 1 2 0.25 3.97 m²
2.10
8.40 m²
8 1 1 0.25
1.00
2.00 m²
ABOVE 8TH FLOOR
external
1 1 1 2.60 W2 External
0.70 1 1 1 12.98 on axis 4 b/n 1D'-F'
1.82 m³ 0.84
Internal 10.90 m² Internal
1 1 1 2.10 W2 1 1 1 12.38 on axis 4 b/n 1D'-F'
0.70 0.84
1.47 m³ 10.40 m² Bottom
external 1 1 1 12.98 on axis 4 b/n 1D'-F'
1 1 1 2.60 W2 0.25
0.70 3.25 m²
1.82 m³
Internal
1 1 1 2.10 W2 98.57 m² Total To Item 1.1d
0.70 G) In 16 cm thick Roof Slab
1.47 m³ AROUND CIRCULATION
external FIRST FLOOR
1 1 1 2.30 W3 1 1 1 5.93 B/ N Axis 4-5 & A-B
0.70 3.45
1.61 m³ 20.46 m²
Internal 1 1 1 4.46 B/ N Axis B-B' & 4-5
1 1 1 1.80 W3 3.45
0.70 15.37 m²
1.26 m³ 1 1 1 2.84 B/ N Axis C-C' & 4-5
external 3.40
1 1 1 2.30 W4 9.66 m²
0.70 1 1 1 4.63 B/ N Axis D'-E & 4-5
1.61 m³ 3.45
1 1 1 1.80 Internal 15.97 m²
0.70 W4 1 1 1 1.45 B/ N Axis E-F & 4-5
1.26 m³ 1.40
508.94 m² Total To Item 1.04.D 2.03 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 5.75 B/ N Axis E-F & 4-5 1 1 1 2.35


3.45 1.40
19.84 m² 3.29 m²
1 1 1 5.08 B/ N Axis F-G & 4-5 1 -2 1 0.15 Deduct column contact area
3.45 0.15
17.53 m² -0.05 m²
1 1 1 5.08 B/ N Axis F-G & 2-3 453.33 m² Total To Item 1.2.F
4.93 WATER TANKER SLAB

25.04 m² 1 1 1 5.19 b/n Axis 4-5 & B'-D'

1 1 1 5.08 B/ N Axis F-G & 3-4 3.45


4.93 17.91 m²
25.04 m²
1 1 1 5.58 B/ N Axis B-C & 5-6 1 1 1 2.90
3.60 3.45
20.09 m² 10.01 m²
1 1 1 3.60 B/ N Axis C-D' & 5-6 1 -2 1 0.15 Deduct column contact area
7.22 0.15
25.99 m² -0.05 m²
1 1 1 4.63 B/ N Axis D'-E & 5-6 27.87 m² Total To Item 1.2.G
Precast Beam Elements (PB) to the
3.60
sizes given below.
a) Pre-cast rib unit PB 1 of size (293 X
16.67 m² FIRST FLOOR
120 X 80mm) consisting of 15 kg of
1 -13 1 0.05 Deduct Column Contact Area 1 1 1 40.00 reinforcing bar and 0.04m3 of C-25
concrete
b) (Price
Pre-cast shall PB
rib unit include
2 of size (503X
0.05 Axis 2G, 3G 4G, 5A, 5B, 5C', 5E, 5F,5G,6B,6C,6D,6E 40 Pcs
transportation
120 and placing
X 80mm) consisting in kg
of 12 position)
of
-0.03 m² 1 1 1 95.00 reinforcing bar and 0.03m3 of C-25
concrete (Price shall include
SECOND- EIGHTH FLOOR 95 Pcs
transportation and placing in position)
7 1 1 6.55 ON Axis 1 B/N C-D a) Pre-cast
SECOND-rib unit PB 1 ofFLOOR
EIGHTH size (293 X
120 X 80mm) consisting of 15 kg of
1.05 7 1 1 40.00 reinforcing bar and 0.04m3 of C-25
b) Pre-cast
concrete rib unit
(Price shall PB 2 of size (503X
include
48.14 m² 280 Pcs 120 X 80mm) consisting
transportation of 12
and placing in kg of
position)
7 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E 7 1 1 100.0 reinforcing bar and 0.03m3 of C-25
1.10 700 Pcs concrete (Price shall include
Total Item of 293x120x80mm
transportation and placing inPrecast
position)
68.22 m² 320 Pcs
Beam
Total reinforcement
Item of 293x120x80mm
7 1 1 3.45 ON Axis 4-5 B/N B'-C' 795 Pcs Steel accordingPrecast
to
Beam
structural drawing. Price includes
2.84
cutting, bending, placing in position
68.59 m² 5,207.79 kg and tyinga)wires:
dia. 6mm plain bar
7 1 1 1.45 ON Axis 4-5 B/N B'-C' 14,748.96 kg b) dia. 8mm deformed bar
1.40 10,926.73 kg c) dia. 10mm deformed bar
14.21 m² 8,793.40 kg d) dia. 12mm deformed bar
10,613.67 kg e) dia. 14mm deformed bar
13,487.96 kg f) dia. 16mm deformed bar
G) In 15 cm thick Roof Slab 15,057.61 kg g) dia. 20mm deformed bar
1 1 1 6.50 ON Axis 1 B/N C-D 1,078.71 kg g) dia. 24mm deformed bar
1.05
6.83 m²
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
1.20
10.63 m²
1 1 1 3.45 ON Axis 4-5 B/N B'-D

2.90

10.01 m²
1 1 1 2.84 ON Axis 4-5 B/N B'-D
3.45
9.80 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

I. Concrete fillers around


columns & beam connection at
floor
1st levels
- 4th floor
At slab, beam & column conection
4 4 1 0.05 C-1
0.34
0.00 m²
4 4 22 0.35 C-2
0.34
41.89 m²
5th - 8th floor
4 4 1 0.05 At slab, beam & column conection
0.34 C-1
0.27 m²
4 4 22 0.15 C-2
0.34
17.95 m²
At Roof Level
1 4 4 0.05 At slab, beam & column conection
0.40 C-1
0.32 m²
1 4 22 0.15 C-2
0.40
5.28 m²

65.71 m² Total Item 1.01i

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

BLOCK WORK 1 1 1 5.64 On axis 4 b/n C-D'


20cm thick Class B external HCB 2.80
wall whichBasement
can satisfy the designed
floor 15.79 m²
strength, bedded in cement mortar
1 1 1 5.30 On axis 4 b/n E - F 1 1 1 7.64 On axis 5 b/n B'-D'
(1:3).
3.22 2.80
17.07 m² 21.39 m²
1 1 2 5.30 On axis 2,3 b/n E - F Deduction
2.50 1 -1 1 2.40 W-4

26.50 m² 1.80

1 1 1 6.91 On axis E b/n 1 - 2 & 4 -5 -4.32 m²


3.22 1 -1 1 2.74 WD-2
22.25 m² 2.80
1 1 1 4.24 On axis 4 b/n C - D' -7.67 m²
3.22 1 1 1 1.40 b/n axis A/ 2-3
13.65 m² 2.80
1 1 1 3.10 On axis D' b/n 4-5 3.92 m²
3.22 1 1 1 5.02 b/n axis A-B/2-3
9.98 m² 3.00
-12.72 m² TW- (5.30*0.8*3) 15.06 m²
Gnd Floor 1 1 1 5.23 b/n axis B-B'/2-3
1 1 1 10.80 On axis 1 b/n C-E 2.80
2.80 14.64 m²
30.24 m² 1 1 1 4.39 b/n axis C & 2-3
1 1 1 10.80 On axis 2 b/n A-B' 2.80
2.80 12.29 m²
30.24 m² 1 1 1 13.33 On axis D b/n 1-4
Deduction 2.80
1 -1 1 4.20 W1 37.32 m²
1.80 1 1 1 3.10 On axis D' b/n 4-5
-7.56 m² 2.80
1 -1 1 2.75 TW-2 8.68 m²
0.80 1 -1 1 3.10 W-4
-2.20 m² 0.50
1 -1 1 1.10 W-11 -1.55 m²
1.80 1 1 1 8.80 On axis E b/n 2-4
-1.98 m² 2.80
On axis 2 b/n E-G 24.64 m²
1 1 1 10.43 1 1 1 4.40 On axisd F b/n 3-4
2.80 2.80
29.20 m² 12.32 m²
1 1 -1 4.50 DDT TW-5 1 1 1 13.10 On axisd G b/n 2-5
0.80 2.80
-3.60 m² 36.68 m²
1 1 -1 5.40 DDT TW-4 1 2 -1 4.50 DDT TW-5
0.80 0.80
-4.32 m² -7.20 m²
1 1 1 3.25 On axis 3 b/n A-B' 1 1 -1 2.70 DDT TW-6
2.80 0.80
9.10 m² -2.16 m² 82189.6654916667
1 1 1 10.80 On axis 3 b/n D-F 1 1 1 1.35 On axisd B' b/n 4-5
2.80 2.80
30.24 m² 3.78 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

FIRST FLOOR 1 1 1 5.15 b/n axis C - D & 3-4


1 1 1 10.80 On axis 1 b/n C-E 3.02
2.80 15.55 m²
30.24 m² 1 1 1 8.57 On axis D b/n 1-3
1 1 1 10.80 On axis 2 b/n A-B' 2.80
2.80 24.00 m²
30.24 m² 1 1 1 3.10 On axis D' b/n 4-5
Deduction 2.80

1 -1 1 4.20 W1 8.68 m²

1.80 1 -1 1 3.10 W-4


-7.56 m² 0.50
1 -1 1 2.75 TW-2 -1.55 m²
0.80 1 1 1 2.17 On axis E b/n 2-3
-2.20 m² 2.80
1 -1 1 1.10 W-11 6.08 m²
1.80 1 1 1 3.30 On Axis A, 4-5
-1.98 m² 0.60
1 1 1 3.25 On axis 3 b/n A-B 1.98 m²
2.80 1 1 1 0.40 On Axis A, 4-5
9.10 m² 0.40
1 1 1 5.40 On axis 3 b/n E-F 0.16 m²
2.80 1 1 1 5.10 On Axis 5 , A-B
15.12 m² 0.60
1 1 1 5.64 On axis 4 b/n C-D' 3.06 m²
2.80 1 1 1 1.20 On Axis 5 , A-B
15.79 m² 0.40
1 1 1 7.54 On axis 5 b/n B'-D' 0.48 m²
2.80 1 1 2 3.31 On Axis B & E ,5-6
21.11 m² 0.60
Deduction 3.97 m²
1 -1 1 2.40 W-4 1 1 2 0.80 On Axis B & E ,5-6
1.80 0.40
-4.32 0.64 m²
1 -1 1 2.59 W-2 1 1 1 15.60 On Axis 6 ,B-E
1.80 0.60
-4.662 9.36 m²
1 2 1 1.40 b/n axis A & F b/n 2-4 1 1 1 2.40 On Axis 6 ,B-E
2.80 0.40
7.84 0.96 m²
1 1 1 5.03 b/n axis A-b & 2-3 1 1 1 9.93 On Axis 5 ,E-G
3.02 0.60
15.1906 5.96 m²
1 1 1 3.21 b/n axis B & 3-4 1 1 1 1.80 On Axis 5 ,E-G
2.80 0.40
8.988 0.72 m²
1 1 1 5.23 b/n axis B-B' & 2-3 1 1 1 12.00 On Axis G ,2-5
2.80 0.60
14.644 7.20 m²
1 1 1 4.39 b/n axis C & 2-3 1 1 1 2.00 On Axis G ,2-5
2.80 0.40
12.292 0.80 m²
1 1 1 1.35 On axisd B' b/n 4-5
2.80
3.78 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 4.63 On Axis 2 ,F-G 2 1 1 10.80 On axis 3 b/n B-C & D-E


0.60 2.80
2.78 m² 60.48 m²
1 1 1 0.80 On Axis 2 ,F-G 2 1 1 9.68 On axis 4 b/n A-B'
0.40 2.80
0.32 m² 305.4586 54.21 m²
Second- Third floor 2 1 1 9.68 On axis 4 b/n D'-F
2 1 1 6.55 On axis 1 b/n C-D 2.80

3.14 54.21 m²

41.13 m² Deduction Deduction


2 -1 2 0.80 TW-3 2 -1 2 2.00 W-5
0.60 1.80
-1.92 m² -14.40 m²
2 1 1 5.40 On axis 1 b/n D-E 2 -1 2 1.80 WD-16
2.80 2.80
30.24 m² -20.16 m²
Deduction 2 -1 2 1.43 WD-17
2 -1 2 2.00 W-5 2.80
1.80 -16.02 m²
-14.40 m² 2 -1 2 2.05 W-6
2 1 1 12.08 b/n axis 1-2 & C-E 1.80
3.00 -14.76 m²
72.48 m² 2 1 1 7.54 On axis 5 b/n B'-D'
2 1 1 12.33 On axis 2 b/n A-C 2.80
2.80 42.22 m²
69.05 m² Deduction
Deduction 2 -1 1 2.69 W-2
2 -1 1 0.80 W-8 1.80
1.80 -9.68 m²
-2.88 m² 2 -1 1 2.40 W-4'
2 -1 1 2.00 W-5 1.80
1.80 -8.64 m²
-7.20 m² 2 1 1 8.80 On axis A b/n 2-4
2 -1 1 0.60 TW-3 2.80
0.80 49.28 m²
-0.96 m² 2 -1 1 2.90 Deduction
2 -1 1 1.10 W-11 1.80 W-7
1.80 -10.44 m²
-3.96 m² 2 -2 1 0.60 TW-3
On axis 2 b/n E-F 0.80
2 1 1 5.40 -1.92 m²
2.80 2 1 1 4.39 On axis B b/n 2-3
30.24 m² 2.80
Deduction 24.58 m²
2 -1 1 0.80 W-8 2 1 1 1.25 On axis B' b/n 4-5
1.80 2.80
-2.88 m² 7.00 m²
On axis 2-3 b/n A-F 2 1 1 5.65 b/n axis C & 1-2
2 1 1 5.03 2.80
3.00 31.64 m²
30.18 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 1 1 1.49 b/n axis C & 2-3 4th-8th Floor


2.80 5 1 1 6.55 On axis 1 b/n C-D
8.34 m² 3.02
Deduction 98.91 m² Deduction
2 -1 1 1.95 W-10 5 -1 2 0.80 TW-3
1.80 0.60
-7.02 m² -4.80 m²
2 -1 1 1.85 W-9 5 1 1 5.60 On axis 1 b/n D-E

1.80 2.80

-6.66 m² 78.40 m²
2 -1 1 1.49 W-12 Deduction
0.80 5 -1 2 2.00 W-5
-2.38 m² 1.80
2 1 1 3.45 b/n axis C & 3-4 -36.00 m²
2.80 5 1 1 12.08 b/n axis 1-2 & C-E
19.32 m² 3.00
2 1 1 9.40 On axis D b/n 1-4 181.20 m²
2.80 5 1 1 12.73 On axis 2 b/n A-C
52.64 m² 2.80
2 1 1 3.10 On axis D' b/n 4-5 178.22 m²
2.80 Deduction
17.36 m² 5 -1 1 0.80 W-8
Deduction 1.80
2 -1 1 3.10 W-4 -7.20 m²
0.50 5 -1 1 2.00 W-5
-3.10 m² 1.80
2 1 1 9.00 On axis E b/n 1-3 -18.00 m²
2.80 5 -1 1 0.60 TW-3
50.40 m² 0.80
Deduction -2.40 m²
2 -1 1 2.00 W-5 5 -1 1 1.10 W-11
1.80 1.80
-7.20 m² -9.90 m²
2 1 1 8.80 On axisd F b/n 2-4 On axis 2 b/n E-F
2.80 5 1 1 5.60
49.28 m² 2.80
Deduction 78.40 m²
2 -1 1 2.90 W-7 Deduction
1.80 5 -1 1 0.80 W-8
-10.44 m² 1.80
2 -2 1 0.60 TW-3 -7.20 m²
0.80 On axis 2-3 b/n A-F
-1.92 m² 5 1 1 5.03
2 1 1 1.42 On Axis E b/n 1-2 3.00
0.60 BALCONY 75.45 m²
1.70 m² 5 1 1 11.10 On axis 3 b/n B-C & D-E
2 1 1 1.40 On Axis C b/n 1-2 2.80
0.60 BALCONY 155.40 m²
1.68 m² 5 1 1 10.08 On axis 4 b/n A-B'
2.80
141.12 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

5 1 1 10.08 On axis 4 b/n D'-F 5 1 1 1.59 b/n axis C & 2-3


2.80 2.80
141.12 m² 22.26 m²
Deduction 5 -1 1 1.49 Deduction
5 -1 2 2.00 W-5 0.80 W-12
1.80 -5.96 m²
-36.00 m² 5 1 1 3.55 b/n axis C & 3-4
5 -1 2 1.80 WD-16 2.80

2.80 49.70 m²

-50.40 m² 5 1 1 9.90 On axis D b/n 1-4


5 -1 2 1.43 WD-17 2.80
2.80 138.60 m²
-40.04 m² 5 1 1 3.30 On axis D' b/n 4-5
5 -1 2 2.05 W-6 2.80
1.80 46.20 m²
-36.90 m² Deduction
5 1 1 7.74 On axis 5 b/n B'-D' 5 -1 1 3.10 W-4
2.80 0.50
108.36 m² -7.75 m²
Deduction 5 1 1 9.50 On axis E b/n 1-3
5 -1 1 2.69 W-2 2.80
1.80 133.00 m²
-24.21 m² Deduction
5 -1 1 2.40 W-4' 5 -1 1 2.00 W-5
1.80 1.80
-21.60 m² -18.00 m²
5 1 1 9.40 On axis A b/n 2-4 5 1 1 9.40 On axisd F b/n 2-4
2.80 2.80
131.60 m² 131.60 m²
5 -1 1 2.90 Deduction Deduction
1.80 W-7 5 -1 1 2.90 W-7
-26.10 m² 1.80
5 -2 1 0.60 TW-3 -26.10 m²
0.80 5 -2 1 0.60 TW-3
-4.80 m² 0.80
5 1 1 4.69 On axis B b/n 2-3 -4.80 m²
2.80 5 1 1 1.42 On Axis E b/n 1-2
65.66 m² 0.60 BALCONY
5 1 1 1.25 On axis B' b/n 4-5 4.26 m²
2.80 5 1 1 1.40 On Axis C b/n 1-2
17.50 m² 0.60 BALCONY
5 1 1 5.85 b/n axis C & 1-2 4.20 m²
2.80 Above Top tie Beam
81.90 m² 1 1 1 10.68 On axis 4 b/n A-B'
5 -1 1 1.95 Deduction 2.00
1.80 W-10 21.36 m²
-17.55 m² 1 1 0.5 12.60 On axis 1 b/N C-E
5 -1 1 1.85 W-9 2.00
1.80 12.60 m²
-16.65 m² 1 2 0.5 5.00 On axis F b/n 2-4
2.00
10.00 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 0.5 10.60 On axis A b/n 2-4 1 1 1 1.25


2.00 3.22
10.60 m² 4.03 m²
1 1 0.5 4.39 On axis B b/n 2-3 1 1 1 0.70
0.90 3.22
1.98 m² 2.25 m²
1 1 1 5.40 On axis 3 b/n B-C 1 1 1 0.50
0.90 3.22

4.86 m² 1.61 m² 7.89 m²

1 1 1 5.00 On axis D b/n 3-4 GROUND FLOOR


2.00 1 1 1 7.30 On Axis a-b & 2-3
10.00 m² 3.00 toilet area horizontally
1 1 1 6.40 On axis D b/n 2'-3 21.90 m²
2.00 1 1 1 3.72 On Axis a-b & 2-3
12.80 m² 3.02 toilet area vertically
1 1 0.5 4.40 On axis E b/n 2-3 11.23 m²
2.00 1 1 1 1.30 DUCT (Pipe cover at toilet)
4.40 m² 3.02
1 1 1 5.40 On axis 3 b/n D-E 3.93 m²
2.00 1 1 1 3.90 On Axis C b/n 4-5
10.80 m² 3.02 duct area
LOBBY 11.78 m²
1 1 0.5 5.22 On axis C-D b/n 2-3 1 1 1 1.00 On Axis A,3
2.00 2.80 DUCT (Pipe cover at toilet)
5.22 m² 2.80 m²
1 1 0.5 3.56 On axis C b/n 3-4 1 1 1 0.80 On Axis 1, C-D
2.00 3.02 DUCT (Pipe cover)
3.56 m² 2.42 m²
1 1 1 7.54 WATER TANKER 1 1 1 1.15 On Axis 4, B'
3.00 FRONT ELEVATION 3.02 DUCT (Pipe cover)
22.62 m² 3.47 m²
1 -1 1 2.59 Deduction 1 1 1 0.80 On Axis 4, D'
1.80 W-2 3.02 DUCT (Pipe cover)
-4.66 m² 2.42 m²
1 -1 1 2.40 W-4 1 1 2 0.55 On Axis F around axis 3
0.80 3.02 DUCT (Pipe cover)
-1.92 m² 3.32 m² 63.27 m²
1 1 1 3.10 RIGHT SIDE ELEVATION FIRST FLOOR
3.00 1 1 1 7.30 On Axis a-b & 2-3
9.30 m² 3.02 toilet area horizontally
1 1 1 3.30 LEFT SIDE ELEVATION 22.05 m²
3.00 1 1 1 3.72 On Axis a-b & 2-3
9.90 m² 3.02 toilet area vertically
1 1 1 33.33 at the top level and balcony 11.23 m²
0.20
6.67 m² 1 1 1 1.30 DUCT (Pipe cover at toilet)
1 1 1 5.00 On Axis D b/n 3-4 3.02
0.40 3.93 m²
2.00 m² 1 1 1 3.90 On Axis C b/n 4-5
1 1 1 2.41 around stair case 3.02 duct area
3.00 11.78 m²
7.23 m²

3053.21 m² Total To Item 2.01

Ditto as item 2.01 but for 100mm HCB wall.

Basement floor
1 1 1 1.40 At Garbage & Sanitary Ducts
3.22 On Axis 4-5 , C-D
4.51 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 1.00 On Axis A,3 2 1 1 3.63 TOILET (B/N E-F)


2.80 DUCT (Pipe cover at toilet) 3.02
2.80 m² 21.93 m²
1 1 1 0.80 On Axis 1, C-D 2 1 2 2.18 On Axis 3 & A-F
3.02 DUCT (Pipe cover) 2.80 TOILET
2.42 m² 24.42 m²
1 1 1 1.15 On Axis 4, B' 2 1 2 3.21 On Axis 3 A & F
3.02 DUCT (Pipe cover) 3.02 TOILET

3.47 m² 38.78 m²

1 1 1 0.80 On Axis 4, D' 2 1 2 3.58


3.02 DUCT (Pipe cover) 3.02 BED ROOM-1
2.42 m² 43.25 m²
1 1 2 0.55 On Axis F around axis 3 2 1 2 6.04 KITCHEN
3.02 DUCT (Pipe cover) 3.02
3.32 m² 3072.15 m² 72.96 m²
SECOND- THIRD FLOOR 2 1 1 3.05 On Axis C b/n 4-5
2 1 1 1.53 On Axis 1-2 C-E 3.02 DUCT
3.02 TOILET 18.42 m²
9.24 m² 2 2 2 0.50 On Axis A & F around axis 3
2 1 1 5.00 3.02 DUCT (Pipe cover at toilet)
3.02 12.08 m²
30.20 m² 2 1 1 0.50 On Axis 2 B-B'
2 1 1 6.28 On Axis 1-2 C-E 3.02 DUCT (Pipe cover at toilet)
3.02 BED ROOM-1 3.02 m²
37.93 m² 2 1 2 0.80 On Axis 4, B'&D'
2 1 1 2.05 3.02 DUCT (Pipe cover at kitchen)
2.80 9.66 m²
11.48 m² 2 1 1 1.20 On Axis 1, C-D
2 1 1 6.89 KITCHEN 3.02 DUCT (Pipe cover at toilet)
3.02 7.25 m²
41.62 m² 2 1 1 4.83 On Axis 4 b/n A-B'
2 1 1 1.75 BED ROOM-1 0.60 BALCONY
3.02 5.80 m²
10.57 m² 2 1 1 5.03 On Axis 4 b/n D'-E
2 1 1 3.46 On Axis 2-3 & A-F 0.60 BALCONY
3.02 TOILET (B/N A-B) 6.04 m² 338.78 m²
20.90 m² 4TH-8TH Floor
2 1 1 5.72 BED ROOMS 5 1 1 1.53 On Axis 1-2 C-E
3.02 3.02 TOILET
34.55 m² 23.10 m²
2 1 1 3.38 TOILET (B/N B-D) 5 1 1 4.60
3.02 3.02
20.42 m² 69.46 m²
2 1 1 6.92 KITCHEN 5 1 1 6.28 On Axis 1-2 C-E
3.02 3.02 BED ROOM-1
41.80 m² 94.83 m²
2 1 1 4.13 Store 5 1 1 2.25
3.02 2.80
24.95 m² 31.50 m²
2 1 1 5.35 BED ROOM 2 (B/N E-F) 5 1 1 6.89 KITCHEN
3.02 3.02
32.31 m² 104.04 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

5 1 1 1.75 BED ROOM-1 5 1 1 4.83 On Axis 4 b/n A-B'


3.02 0.60 BALCONY
26.43 m² 14.49 m²
5 1 1 3.46 On Axis 2-3 & A-F 5 1 1 5.03 On Axis 4 b/n D'-E
3.02 TOILET (B/N A-B) 0.60 BALCONY
52.25 m² 15.09 m²
5 1 1 5.72 BED ROOMS 2169.86 m² Supply and fix toch
Total applied
To Item 2.02water
proofing membrane of 4mm thick
3.02 3. ROOFING AND(ASTM
which passes WATER PROOFING
D6222) and WORK
granular finish for roof water proofing
86.37 m²
system(minimum slope 1/20).
5 1 1 3.38 TOILET (B/N B-D) ROOF LEVEL
3.02 1 6.85 ON Axis 1 B/N C-D
51.04 m² 1.05
5 1 1 6.92 KITCHEN 7.19 m²
3.02 2 4.43 ON Axis 4 B/N A'-B' & D'-E'
104.49 m² 2.05 Balcony
5 1 1 4.13 Store 18.16 m²
3.02 WATER TANKER SLAB
62.36 m² 1 9.64
5 1 1 5.35 BED ROOM 2 (B/N E-F) 4.75
3.02 45.79 m²
80.79 m² 71.14 m² Total Cementious
Supply and Apply item Damp
5 1 1 3.63 TOILET (B/N E-F) Proofing for upper floor wet areas to a
3.02 height of 300mm
a. all upper on walls and column.
wet rooms
54.81 m² Ground floor Verenda
5 1 2 2.38 On Axis 3 & A-F 1 12.00 B/N axis 1-2 & A-B'
2.80 TOILET 7.00
66.64 m² 84.00 m²
5 1 2 3.21 On Axis 3 A & F 1 6.00 B/N axis 1-2 & E-F
3.02 TOILET 7.00
96.942 42.00 m²
5 1 2 3.58 Grnd &1st Floor
3.02 BED ROOM-1 1 2 1 1.65 B/N axis 2-3 & B-B'
108.116 1.28 Toilet
5 1 2 6.04 KITCHEN 3.89 m²
3.02 1 2 1 1.65 >>
182.408 0.90
5 1 1 3.05 On Axis C b/n 4-5 2.97 m²
3.02 DUCT 1 2 1 1.65 >>
46.055 1.09
5 2 2 0.50 On Axis A & F around axis 3 3.48 m²
3.02 DUCT (Pipe cover at toilet) 1 2 1 1.31 >>
30.2 1.65
5 1 1 0.50 On Axis 2 B-B' 4.32 m²
3.02 DUCT (Pipe cover at toilet) 1 2 1 2.85 >>
7.55 m² 2.63
5 1 2 0.80 On Axis 4, B'&D' 14.85 m²
3.02 DUCT (Pipe cover at kitchen) 1 2 1 1.70 >>
24.16 m² 2.60
5 1 1 1.20 On Axis 1, C-D 8.84 m²
3.02 DUCT (Pipe cover at toilet) 1 2 1 0.40 deduct for column Area
18.12 m² 0.60
0.48 m²
38.832
______________ ______________ ______________
Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 2 1 0.25 5 1 1 0.20
0.60 0.10
0.30 m² 0.10 m²
2ND-3RD FLOOR 5 1 1 2.20 B/N axis 1 & C-D'
1 2 1 2.07 Toilet 1.47
1.78 B/N axis 2 & B-B' 16.17 m²
7.28 m² 5 1 1 2.20
1 2 1 2.58 1.47

1.48 B/N axis 3 & A-B' 15.96 m²

7.55 m² 5 1 1 0.40 Deduct for column area


1 2 1 2.58 0.15
1.42 0.30 m²
7.33 m² 5 1 1 2.58 B/N axis 3 & E-F
1 2 1 0.40 deduct for column area 1.43
0.20 18.25 m²
0.16 m² 5 1 1 2.58
1 2 1 0.40 1.47
0.30 18.96 m²
0.24 m² 5 1 1 0.20 Deduct for column area
0.15
0.15 m²
7 1 1 54.60 on the wall surface
1 2 1 2.20 B/N axis 1 & C-D' 0.30
1.47 114.66 m²
6.47 m² 240.40 m² Total item
1 2 1 2.20 456.21 m² Total item to 3.02.a
1.47 b) Concrete Retaining Wall
6.26 m² 1 1 1 114.65 Basement floor
1 2 1 0.60 Deduct for column area 3.00
0.35 343.95 m²
0.42 m² 1 1 1 5.03
1 2 1 2.58 B/N axis 3 & E-F 1.14 5.73 m²
1.43 349.68 m² Total to Item 3.02b
7.18 m² F) CAFETERIA TERRACE
1 2 1 2.58 1 1 2 6.10 B/N axis 4-5 & A-B & E-F
1.47 3.55
7.59 m² 43.31 m²
1 2 1 0.40 Deduct for column area 1 1 2 7.45 B/N axis 4-6 & B-B' & D'-E
0.25 4.63
0.20 m² 68.99 m²
215.81 m² total 1 1 1 8.84 B/N axis 5-6 & B'-D'
4TH-8TH Floor 3.75
1 5 1 2.07 Toilet 33.15 m²
1.78 B/N axis 2 & B-B' 1 1 1 14.00 B/N axis 2-5 & F-G
18.33 m² 5.28
1 5 1 2.58 73.92 m²
1.48 B/N axis 3 & A-B' 1 1 1 66.80 SKIRTING
19.00 m² 0.10
1 5 1 2.58 6.68 m² 226.05
1.42 226.05 m² Total item
18.32 m² Average 70mm thick light weight
1 5 1 0.20 deduct for column area concrete in mix (1:2:5) cement, pumice
and sand laid over RC roof slab
0.20 1 1 1 6.85 ROOF LEVEL
0.20 m² 1.05 ON Axis 1 B/N C-D
7.19 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 2 4.43 ON Axis 4 B/N A'-B' & D'-E 5. CARPENTRY AND JOINERY


2.05 Balcony Supply and fix 3.4mm thick patterned
18.16 m² 7 1 1 1.20 MDF Wooden Door.
WATER TANKER SLAB 2.95 Type D6 SIZE 1200x2950mm
1 1 1 9.65 24.78
4.75 7 3 1 1.20 Type D6 SIZE 1200x2750mm

45.84 m² 2.75

71.19 m² Apply 30 mm Total Tosmooth


thick Item finished 69.3
cement sand screed laid on top of
light weight concrete area in mortar 7 4 1 0.70 Type D4 SIZE 700x2950mm
mix (1:3) with proper slope towards
down pipe. ROOF LEVEL 2.95
1 1 1 6.85 ON Axis 1 B/N C-D
1.05 7 4 1 0.80 57.82 Type D5 SIZE 800x2950mm
7.19 m² 2.95
1 1 2 4.43 ON Axis 4 B/N A'-B' & D'-E 66.08 Total Area
2.05 Balcony 217.98 m²
18.16 m² Plastic Celling
Lobby
WATER TANKER SLAB 1 1 1 5.92 b/n 2'-4 & C-D
1 1 1 9.64 1.49
4.75 8.82
45.79 m² 1 1 1 5.92
71.14 m² Total To Item 5.36
Roof cover in prepainted EGA - 500 31.73
1 1 1 12.80 Axis b/n C-E & 1-2 1 1 -1 0.18 DDt Coll
7.00 0.18
89.60 m² -0.0324
1 1 1 30.60 Axis b/n A-F , 2-4 1 1 -1 0.35
10.70 0.18
327.42 m² -0.063
417.02 m² Total To Item 3..05 40.46 m²
G-28 galvanized flat metal sheet
1 1 1 51.83 Gutter
51.83 m²
51.83 ml Total To Item 6. Plastering & Pointing
Roof Ridge cover dev. Length=67cm Apply two coats of plastering with
1 1 1 19.59 cement mortar 1:3 mix ratio.
19.59 ml Total To Item a. To all internal wall surface
Copping 20 HCB
1 1 1 68.58 1 2 1 5.30 Basement floor
68.58 ml 2.80 On axis 4 b/n E - F
Supply and fix 110mm PVC 29.68 m²
Downpipe including elbow and 1 4 2 5.30 On axis 2,3 b/n E - F
other necessary materials and
accessories to complete the work 2.80
118.72 m²
Down PIPE 1 2 1 6.91 On axis E b/n 1 - 2 & 4 -5
1 1 11 29.70 2.80
326.70 ml Total To Item 38.70 m²
1 2 1 4.24 On axis 4 b/n C - D'
2.80
23.74 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 2 1 3.10 On axis D' b/n 4-5 1 -1 1 2.40 W-4'


3.20 0.80
19.84 m² -1.92 m²
Grd FLOOR 1 -1 1 2.74 WD-2
1 1 1 10.80 On axis 1 b/n C-E 2.80

2.80 -7.67 m²

30.24 m² 1 1 1 1.40 b/n axis A/ 2-3


1 1 1 10.80 On axis 2 b/n A-B' 2.80
2.80 3.92 m²
30.24 m² 1 1 1 5.60
1 1 1 8.80 On axis 2 b/n A-B'edge 0.20
0.20 1.12 m²
1.76 m² 1 2 1 5.02 b/n axis A-B/2-3
Deduction 3.00
1 -1 1 4.20 W1 30.12 m²
1.80 1 2 1 5.23 b/n axis B-B'/2-3
-7.56 m² 2.80
1 -1 1 2.75 TW-2 29.29 m²
0.80 1 1 1 3.00 b/n axis B-B'/2-3 edge
-2.20 m² 0.20
1 -1 1 1.10 W-11 0.60 m²
1.80 1 2 1 4.39 b/n axis C & 2-3
-1.98 m² 2.80
On axis 2 b/n E-G 24.58 m²
1 1 1 10.43 1 2 1 13.33 On axis D b/n 1-4
2.80 2.80
29.20 m² 74.65 m²
On axis 2 b/n E-G edge 1 1 1 5.60 On axis D b/n 1-4 Edge
1 1 1 3.20 0.20
0.20 1.12 m²
0.64 m² 1 1 1 3.10 On axis D' b/n 4-5
1 1 -1 4.50 DDT TW-5 2.80
0.80 8.68 m²
-3.60 m² 1 -1 1 3.10 W-4
1 1 -1 5.40 DDT TW-4 0.50
0.80 -1.55 m²
-4.32 m² 1 1 1 1.00 On axis D' b/n 4-5 edge
1 2 1 3.25 On axis 3 b/n A-B' 0.20
2.80 0.20 m²
18.20 m² 1 2 1 8.80 On axis E b/n 2-4
1 1 2 10.80 On axis 3 b/n D-F 2.80
2.80 49.28 m²
60.48 m² 1 2 1 4.40 On axisd F b/n 3-4
1 1 2 5.64 On axis 4 b/n C-D' 2.80
2.80 24.64 m²
31.58 m² 1 1 1 13.10 On axisd G b/n 2-4
1 1 1 7.64 On axis 5 b/n B'-D' 2.80
2.80 36.68 m²
21.39 m² 1 2 -1 4.50 DDT TW-5
1 1 1 7.20 On axis 5 b/n B'-D' edge 0.80
0.20 -7.20 m²
1.44 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 -1 2.70 DDT TW-6 1 1 1 5.60 b/n axis A & 2-4 Edge


0.80 0.20
-2.16 m² 1.12 m²
1 1 1 3.20 1 2 1 5.03 b/n axis A-B & 2-3
0.20 3.02

0.64 m² 30.38 m²

FIRST FLOOR 1 2 1 3.21 b/n axis B & 3-4


1 1 1 10.80 On axis 1 b/n C-E 2.80
2.80 17.98 m²
30.24 m² 1 1 1 5.60 b/n axis B & 3-4 Edge
1 1 1 10.80 On axis 2 b/n A-B' 0..2
2.80 5.60 m²
30.24 m² 1 2 1 5.23 b/n axis B-B' & 2-3
Deduction 2.80
1 -1 1 4.20 W1 29.29 m²
1.80 1 1 1 3.00 b/n axis B-B' & 2-3 edge
-7.56 m² 0.20
1 -1 1 2.75 TW-2 0.60 m²
0.80 1 2 1 4.39 b/n axis C & 2-3
-2.20 m² 2.80
1 -1 1 1.10 W-11 24.58 m²
1.80 1 2 1 5.15 b/n axis C - D & 3-4
-1.98 m² 3.02
1 1 1 8.80 On axis 2 b/n A-B' Edge 31.11 m²
0.20 1 1 1 3.00 b/n axis C - D & 3-4 edge
1.76 m² 0.20
1 2 1 3.25 On axis 3 b/n A-B 0.60 m²
2.80 1 2 1 8.57 On axis D b/n 1-3
18.20 m² 2.80
1 2 1 5.40 On axis 3 b/n E-F 47.99 m²
2.80 1 1 1 2.80 On axis D b/n 1-3 edge
30.24 m² 0.20
1 2 1 5.64 On axis 4 b/n C-D' 0.56 m²
2.80 1 1 1 3.10 On axis D' b/n 4-5
31.58 m² 2.80
1 1 1 7.54 On axis 5 b/n B'-D' 8.68 m²
2.80 1 -1 1 3.10 W-4
21.11 m² 0.50
Deduction -1.55 m²
1 -1 1 2.40 W-4 1 1 1 1.00 On axis D' b/n 4-5 edge
0.80 0.20
-1.92 m² 0.20 m²
1 -1 1 2.59 W-2 1 2 1 2.17 On axis E b/n 2-3
1.80 2.80
-4.66 m² 12.15 m²
1 1 1 7.20 On axis 5 b/n B'-D' Edge 1 1 1 2.80 On axis E b/n 2-3 edge
0.20 0.20
1.44 m² 0.56 m²
1 1 1 1.40 b/n axis A & 2-4 Around Terrace
2.80 1 1 1 3.30 On Axis A, 4-5
3.92 m² 0.60
1.98 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 0.40 On Axis A, 4-5 Deduction


0.40 2 -1 2 2.00 W-5
0.16 m² 1.80
1 1 1 5.10 On Axis 5 , A-B -14.40 m²
0.60 2 1 1 7.20 On axis 1 b/n D-E edge

3.06 m² 0.20

1 1 1 1.20 On Axis 5 , A-B 2.88 m²


0.40 2 2 1 12.08 b/n axis 1-2 & C-E
0.48 m² 3.00
1 1 2 3.31 On Axis B & E ,5-6 144.96 m²
0.60 2 1 1 12.33 On axis 2 b/n A-C
3.97 m² 2.80
1 1 2 0.80 On Axis B & E ,5-6 69.05 m²
0.40 Deduction
0.64 m² 2 -1 1 0.80 W-8
1 1 1 15.60 On Axis 6 ,B-E 1.80
0.60 -2.88 m²
9.36 m² 2 -1 1 2.00 W-5
1 1 1 2.40 On Axis 6 ,B-E 1.80
0.40 -7.20 m²
0.96 m² 2 -1 1 0.60 TW-3
1 1 1 9.93 On Axis 5 ,E-G 0.80
0.60 -0.96 m²
5.96 m² 2 -1 1 1.10 W-11
1 1 1 1.80 On Axis 5 ,E-G 1.80
0.40 -3.96 m²
0.72 m² 2 1 1 12.40 On axis 2 b/n A-C
1 1 1 12.00 On Axis G ,2-5 0.20
0.60 4.96 m²
7.20 m² 2 1 1 5.40 On axis 2 b/n E-F
1 1 1 2.00 On Axis G ,2-5 2.80
0.40 30.24 m²
0.80 m²
1 1 1 4.63 On Axis 2 ,F-G 2 -1 1 0.80 Deduction
0.60 1.80 W-8
2.78 m² -2.88 m²
1 1 1 0.80 On Axis 2 ,F-G 2 1 1 3.60 On axis 2 b/n E-F edge
0.40 0.20
0.32 m² 36.41 m² 1.44 m²
Second- Third floor 2 2 1 5.03 On axis 2-3 b/n A-F
2 1 1 6.55 On axis 1 b/n C-D 3.00
3.02 60.36 m²
39.56 m² 2 2 1 10.80 On axis 3 b/n B-C & D-E
2 -1 2 0.80 Deduction 2.80
0.60 TW-3 120.96 m²
-1.92 m² 2 1 1 9.68 On axis 4 b/n A-B'
2 1 1 3.20 On axis 1 b/n C-D edge 2.80
0.20 54.21 m²
1.28 m² 2 1 1 18.40 On axis 4 b/n A-B' edge
2 1 1 5.40 On axis 1 b/n D-E 0.20
2.80 7.36 m²
30.24 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 1 1 9.68 On axis 4 b/n D'-F 2 1 1 5.65 b/n axis C & 1-2


2.80 2.80
54.21 m² 31.64 m²
Deduction 2 -1 1 1.95 Deduction
2 -1 2 2.00 W-5 1.80 W-10

1.80 -7.02 m²

-14.40 m² 2 -1 1 1.85 W-9


2 -1 2 1.80 WD-16 1.80
2.80 -6.66 m²
-20.16 m² 2 1 1 7.20 b/n axis C & 1-2 edge
2 -1 2 1.43 WD-17 0.20
2.80 2.88 m²
-16.02 m² 2 2 1 1.49 b/n axis C & 2-3
2 -1 2 2.05 W-6 2.80
1.80 16.69 m²
-14.76 m² 2 -1 1 1.49 Deduction
2 1 1 18.40 On axis 4 b/n D'-F edge 0.80 W-12
0.20 -2.38 m²
7.36 m² 2 1 1 1.60 b/n axis C & 2-3 edge
2 1 1 7.54 On axis 5 b/n B'-D' 0.20
2.80 0.64 m²
42.22 m² 2 2 1 3.45 b/n axis C & 3-4
Deduction 2.80
2 -1 1 2.69 W-2 38.64 m²
1.80 2 2 1 9.40 On axis D b/n 1-4
-9.68 m² 2.80
2 -1 1 2.40 W-4 105.28 m²
0.80 2 1 1 3.10 On axis D' b/n 4-5
-3.84 m² 2.80
2 1 1 7.20 On axis 5 b/n B'-D' edge 17.36 m²
0.20 Deduction
2.88 m² 2 -1 1 3.10 W-4
2 1 1 8.80 On axis A b/n 2-4 0.50
2.80 -3.10 m²
49.28 m² 2 1 1 1.00 On axis D' b/n 4-5
Deduction 0.20
2 -1 1 2.90 W-7 0.40 m²
1.80 2 1 1 9.00 On axis E b/n 1-3
-10.44 m² 2.80
2 -2 1 0.60 TW-3 50.40 m²
0.80 2 -1 1 2.00 Deduction
-1.92 m² 1.80 W-5
2 1 1 6.80 On axis A b/n 2-4 -7.20 m²
0.20 2 1 1 3.60 On axis E b/n 1-3 edge
2.72 m² 0.20
2 2 1 4.39 On axis B b/n 2-3 1.44 m²
2.80 2 1 1 8.80 On axisd F b/n 2-4
49.17 m² 2.80
2 1 1 1.25 On axis B' b/n 4-5 49.28 m²
2.80
7.00 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 -1 1 2.90 Deduction 5 -1 1 1.10 W-11


1.80 W-7 1.80
-10.44 m² -9.90 m²
2 -2 1 0.60 TW-3 5 1 1 12.40 On axis 2 b/n A-C
0.80 0.20

-1.92 m² 12.40 m²

2 1 1 6.80 On axisd F b/n 2-4 edge 5 1 1 5.60 On axis 2 b/n E-F


0.20 2.80
2.72 m² 78.40 m²
2 1 1 1.42 On Axis E b/n 1-2
0.60 BALCONY 5 -1 1 0.80 Deduction
1.70 m² 1.80 W-8
2 1 1 1.40 On Axis C b/n 1-2 -7.20 m²
0.60 BALCONY 5 1 1 3.60 On axis 2 b/n E-F edge
1.68 m² 0.20
4th-8th Floor 3.60 m²
5 1 1 6.55 On axis 1 b/n C-D 5 2 1 5.03 On axis 2-3 b/n A-F
3.02 3.00
98.91 m² 150.90 m²
5 -1 2 0.80 Deduction 5 2 1 11.30 On axis 3 b/n B-C & D-E
0.60 TW-3 2.80
-4.80 m² 316.40 m²
5 1 1 3.20 On axis 1 b/n C-D edge 5 1 1 10.08 On axis 4 b/n A-B'
0.20 2.80
3.20 m² 141.12 m²
5 1 1 5.60 On axis 1 b/n D-E 5 1 1 18.40 On axis 4 b/n A-B' edge
2.80 0.20
78.40 m² 18.40 m³
Deduction 5 1 1 10.08 On axis 4 b/n D'-F
5 -1 2 2.00 W-5 2.80
1.80 141.12 m³
-36.00 m² Deduction
5 1 1 7.20 On axis 1 b/n D-E edge 5 -1 2 2.00 W-5
0.20 1.80
7.20 m² -36.00 m²
5 2 1 12.08 b/n axis 1-2 & C-E 5 -1 2 1.80 WD-16
3.00 2.80
362.40 m² -50.40 m²
5 1 1 12.73 On axis 2 b/n A-C 5 -1 2 1.43 WD-17
2.80 2.80
178.22 m² -40.04 m²
Deduction 5 -1 2 2.05 W-6
5 -1 1 0.80 W-8 1.80
1.80 -36.90 m²
-7.20 m² 5 1 1 18.40 On axis 4 b/n D'-F edge
5 -1 1 2.00 W-5 0.20
1.80 18.40 m²
-18.00 m² 5 1 1 7.74 On axis 5 b/n B'-D'
5 -1 1 0.60 TW-3 2.80
0.80 108.36 m²
-2.40 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Deduction 5 2 1 3.55 b/n axis C & 3-4


5 -1 1 2.69 W-2 2.80
1.80 99.40 m²
-24.21 m² 5 2 1 9.90 On axis D b/n 1-4
5 -1 1 2.40 W-4 2.80

0.80 277.20 m²

-9.60 m² 5 1 1 3.30 On axis D' b/n 4-5


5 1 1 7.20 On axis 5 b/n B'-D' edge 2.80
0.20 46.20 m²
7.20 m² Deduction
5 1 1 9.40 On axis A b/n 2-4 5 -1 1 3.10 W-4
2.80 0.50
131.60 m² -7.75 m²
Deduction 5 1 1 1.00 On axis D' b/n 4-5
5 -1 1 2.90 W-7 0.20
1.80 1.00 m²
-26.10 m² 5 1 1 9.50 On axis E b/n 1-3
5 -2 1 0.60 TW-3 2.80
0.80 133.00 m²
-4.80 m² 5 -1 1 2.00 Deduction
5 1 1 6.80 On axis A b/n 2-4 1.80 W-5
0.20 -18.00 m²
6.80 m² 5 1 1 3.60 On axis E b/n 1-3 edge
5 2 1 4.69 On axis B b/n 2-3 0.20
2.80 3.60 m²
131.32 m² 5 1 1 9.40 On axisd F b/n 2-4
5 1 1 1.25 On axis B' b/n 4-5 2.80
2.80 131.60 m²
17.50 m² 5 -1 1 2.90 Deduction
5 1 1 5.85 b/n axis C & 1-2 1.80 W-7
2.80 -26.10 m²
81.90 m² 5 -2 1 0.60 TW-3
5 -1 1 1.95 Deduction 0.80
1.80 W-10 -4.80 m²
-17.55 m² 5 1 1 6.80 On axisd F b/n 2-4 edge
5 -1 1 1.85 W-9 0.20
1.80 6.80 m²
-16.65 m² 5 1 1 1.42 On Axis E b/n 1-2
5 1 1 7.20 b/n axis C & 1-2 edge 0.60 BALCONY
0.20 4.26 m²
7.20 m² 5 1 1 1.40 On Axis C b/n 1-2
5 2 1 1.59 b/n axis C & 2-3 0.60 BALCONY
2.80 4.20 m²
44.52 m² WATER TANKER
5 -1 1 1.49 Deduction 1 1 1 7.54 FRONT ELEVATION
0.80 W-12 3.00 On Axis 5 B'-D*
-5.96 m² 22.62 m²
5 1 1 1.60 b/n axis C & 2-3 edge 1 -1 1 2.59 Deduction
0.20 1.80 W-2
1.60 m² -4.66 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 -1 1 2.40 W-4 1 1 2 0.55 On Axis F around axis 3


0.80 3.02 DUCT (Pipe cover)
-1.92 m² 3.32 m²
1 1 1 5.20 On Axis 5 B'-D* Edge FIRST FLOOR
0.20 1 2 1 7.30 On Axis a-b & 2-3

1.04 m² 3.02 toilet area horizontally

1 1 1 3.10 RIGHT SIDE ELEVATION 44.09 m³


3.00 On Axis F 2-4 1 2 1 3.72 On Axis a-b & 2-3
9.30 m² 3.02 toilet area vertically
1 1 1 3.30 LEFT SIDE ELEVATION 22.47 m³
3.00 On Axis A 2-4 1 1 1 1.30 DUCT (Pipe cover at toilet)
9.90 m² 1189.861 3.02
4519.06 m² Sub Total To Item 3.93 m³

Ditto as item 6.1 but for 100mm HCB wall. 1 1 1 3.90 On Axis C b/n 4-5

Basement floor 3.02 duct area


1 2 1 1.40 At Garbage & Sanitary Ducts 11.78 m³
2.80 On Axis 4-5 , C-D 1 1 1 1.00 On Axis A,3
7.84 m² 2.80 DUCT (Pipe cover at toilet)
1 2 1 1.25 2.80 m²
2.80 1 1 1 0.80 On Axis 1, C-D
7.00 m² 3.02 DUCT (Pipe cover)
1 2 1 0.70 2.42 m²
2.80 1 1 1 1.15 On Axis 4, B'
3.92 m² 3.02 DUCT (Pipe cover)
1 2 1 0.50 3.47 m²
2.80 1 1 1 0.80 On Axis 4, D'
2.80 m² 3.02 DUCT (Pipe cover)
GROUND FLOOR 2.42 m²
1 2 1 7.30 On Axis a-b & 2-3 1 1 2 0.55 On Axis F around axis 3
3.02 toilet area horizontally 3.02 DUCT (Pipe cover)
44.09 m² 3.32 m²
1 2 1 3.72 On Axis a-b & 2-3 SECOND- THIRD FLOOR
3.02 toilet area vertically 2 2 1 1.53 On Axis 1-2 C-E
22.47 m² 3.02 TOILET
1 1 1 1.30 DUCT (Pipe cover at toilet) 18.48 m²
3.02 2 2 1 4.60
3.93 m² 3.02
1 1 1 3.90 On Axis C b/n 4-5 55.57 m²
3.02 duct area 2 1 4 3.00 On Axis 1-2 C-E edge
11.78 m² 0.10
1 1 1 1.00 On Axis A,3 2.40 m²
2.80 DUCT (Pipe cover at toilet) 2 2 1 6.28 On Axis 1-2 C-E
2.80 m² 3.02 BED ROOM-1
1 1 1 0.80 On Axis 1, C-D 75.86 m²
3.02 DUCT (Pipe cover) 2 2 1 2.05
2.42 m² 2.80
1 1 1 1.15 On Axis 4, B' 22.96 m²
3.02 DUCT (Pipe cover) 2 1 1 3.00 On Axis 1-2 C-E edge
3.47 m² 0.10
1 1 1 0.80 On Axis 4, D' 0.60 m²
3.02 DUCT (Pipe cover)
2.42 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 2 1 6.89 KITCHEN 2 1 3 0.10 TOILET (B/N E-F) edge


3.02 3.02
83.23 m² 1.81 m²
2 2 1 3.00 KITCHEN edge 2 2 2 2.18 On Axis 3 A & F
0.10 2.80 TOILET

1.20 m² 48.83 m²

2 2 1 1.75 BED ROOM-1 2 2 2 3.21 On Axis 3 A & F


3.02 3.02 TOILET
21.14 m² 77.55 m²
2 1 1 0.10 BED ROOM-1 edge 2 1 2 0.20 On Axis 3 A & F edge
3.02 3.02 TOILET
0.60 m² 2.42 m²
2 2 1 3.46 On Axis 2-3 & A-F 2 2 2 3.58 BED ROOM-1
3.02 TOILET (B/N A-B) 3.02
41.80 m² 86.49 m²
2 1 2 0.10 On Axis 2-3 & A-F edge 2 1 2 0.20 BED ROOM-1 edge
3.02 3.02
1.21 m² 2.42 m²
2 2 1 5.72 BED ROOMS 2 2 2 6.04 KITCHEN
3.02 3.02
69.10 m² 145.93 m²
2 1 3 0.10 BED ROOMS edge 2 1 2 0.20 KITCHEN edge
3.02 3.02
1.81 m² 2.42 m²
2 2 1 3.38 TOILET (B/N B-D) 2 2 1 3.05 On Axis C b/n 4-5
3.02 3.02 DUCT
40.83 m² 36.84 m²
2 1 1 0.10 TOILET (B/N B-D) edge 2 2 2 0.50 On Axis A & F around axis 3
3.02 3.02 DUCT (Pipe cover at toilet)
0.60 m² 12.08 m²
2 2 1 6.92 KITCHEN 2 1 1 0.50 On Axis 2 B-B'
3.02 3.02 DUCT (Pipe cover at toilet)
83.59 m² 3.02 m²
2 1 2 0.10 KITCHEN 2 1 2 0.80 On Axis 4, B'&D'
3.02 3.02 DUCT (Pipe cover at kitchen)
1.21 m² 9.66 m²
2 2 1 4.13 Store 2 1 1 1.20 On Axis 1, C-D
3.02 3.02 DUCT (Pipe cover at toilet)
49.89 m² 7.25 m²
2 1 1 0.10 Store edge 2 1 1 4.83 On Axis 4 b/n A-B'
3.02 0.60 BALCONY
0.60 m² 5.80 m²
2 2 1 5.35 BED ROOM 2 (B/N E-F) 2 1 1 5.03 On Axis 4 b/n D'-E
3.02 0.60 BALCONY
64.63 m² 6.04 m²
2 1 1 0.20 BED ROOM 2 (B/N E-F) edge 4TH- 8TH FLOOR
3.02 5 2 1 1.53 On Axis 1-2 C-E
1.21 m² 3.02 TOILET
2 2 1 3.63 TOILET (B/N E-F) 46.21 m²
3.02
43.85 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

5 2 1 4.60 5 2 1 4.13 Store


3.02 3.02
138.92 m² 124.73 m²
5 1 4 3.00 On Axis 1-2 C-E edge 5 1 1 0.10 Store edge
0.10 3.02

6.00 m² 1.51 m²

5 2 1 6.28 On Axis 1-2 C-E 5 2 1 5.35 BED ROOM 2 (B/N E-F)


3.02 BED ROOM-1 3.02
189.66 m² 161.57 m²
5 2 1 2.25 5 1 1 0.20 BED ROOM 2 (B/N E-F) edge
2.80 3.02
63.00 m² 3.02 m²
5 1 1 3.00 On Axis 1-2 C-E edge 5 2 1 3.63 TOILET (B/N E-F)
0.10 3.02
1.50 m² 109.63 m²
5 2 1 6.89 KITCHEN 5 1 3 0.10 TOILET (B/N E-F) edge
3.02 3.02
208.08 m² 4.53 m²
5 2 1 3.00 KITCHEN edge 5 2 2 2.38 On Axis 3 A & F
0.10 2.80 TOILET
3.00 m² 133.28 m²
5 2 1 1.75 BED ROOM-1 5 2 2 3.21 On Axis 3 A & F
3.02 3.02 TOILET
52.85 m² 193.88 m²
5 1 1 0.10 BED ROOM-1 edge 5 1 2 0.20 On Axis 3 A & F edge
3.02 3.02 TOILET
1.51 m² 6.04 m²
5 2 1 3.46 On Axis 2-3 & A-F 5 2 2 3.58 BED ROOM-1
3.02 TOILET (B/N A-B) 3.02
104.49 m² 216.23 m²
5 1 2 0.10 On Axis 2-3 & A-F edge 5 1 2 0.20 BED ROOM-1 edge
3.02 3.02
3.02 m² 6.04 m²
5 2 1 5.72 BED ROOMS 5 2 2 6.04 KITCHEN
3.02 3.02
172.74 m² 364.82 m²
5 1 3 0.10 BED ROOMS edge 5 1 2 0.20 KITCHEN edge
3.02 3.02
4.53 m² 6.04 m²
5 2 1 3.38 TOILET (B/N B-D) 5 2 1 3.05 On Axis C b/n 4-5
3.02 3.02 DUCT
102.08 m² 92.11 m²
5 1 1 0.10 TOILET (B/N B-D) edge 5 2 2 0.50 On Axis A & F around axis 3
3.02 3.02 DUCT (Pipe cover at toilet)
1.51 m² 30.20 m²
5 2 1 6.92 KITCHEN 5 1 1 0.50 On Axis 2 B-B'
3.02 3.02 DUCT (Pipe cover at toilet)
208.98 m² 7.55 m²
5 1 2 0.10 KITCHEN 5 1 2 0.80 On Axis 4, B'&D'
3.02 3.02 DUCT (Pipe cover at kitchen)
3.02 m² 24.16 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

5 1 1 1.20 On Axis 1, C-D 1 2 -1 4.50 DDT TW-5


3.02 DUCT (Pipe cover at toilet) 0.80
18.12 m² -7.20 m²
5 1 1 4.83 On Axis 4 b/n A-B' 1 1 -1 2.70 DDT TW-6
0.60 BALCONY 0.80

14.49 m² -2.16 m²

5 1 1 5.03 On Axis 4 b/n D'-E FIRST FLOOR


0.60 BALCONY 1 1 1 12.60 On axis 1 b/n C-E
15.09 m² 3.30
4190.01 m² Total To Item 6.01a 41.58 m²
8709.06 m² Total Area of Internal Plastering 1 1 1 12.00 On axis 2 b/n A-B'
820.56 m² Ddt Plastering to receive ceramic wall 3.30
7888.50 m² Total Item to 6.01a 39.60 m²
b. To external wall surfaces Deduction
GROUND FLOOR 1 -1 1 4.20 W1
1 1 1 12.60 On axis 1 b/n C-E 1.80
3.30 -7.56 m²
41.58 m² 1 -1 1 2.75 TW-2
1 1 1 12.00 On axis 2 b/n A-B' 0.80
3.30 -2.20 m²
39.60 m² 1 -1 1 1.10 W-11
Deduction 1.80
1 -1 1 4.20 W1 -1.98 m²
1.80 1 1 1 6.00 On axis 2 b/n E-F
-7.56 m³ 3.30
1 -1 1 2.75 TW-2 19.80 m²
0.80 Deduction
-2.20 m³ 1 -1 1 5.40 WD4
1 -1 1 1.10 W-11 2.80
1.80 -15.12 m²
-1.98 m³ 1 1 1 21.50 On axis 4 b/n A-B' & D'-F
On axis 2 b/n E-G 3.30
1 1 1 11.33 70.95 m²
3.30 1 -2 1 5.40 Deduction
37.39 m² 2.80 WD4'
1 1 1 10.60 On axis A b/n 2-4 -30.24 m²
3.30 1 -1 1 4.24 Deduction
34.98 m² 2.80 WD-8
1 -1 1 7.40 Deduct WD-6 -11.87 m²
2.80 1 -1 1 4.28 Deduction
-20.72 m² 2.80 WD-9
1 1 2 7.00 On axis C & E b/n 1-2 -11.98 m²
3.30 1 1 1 8.84
46.20 m² 3.30 On axis 5 b/n B'-D'
1 -1 2 6.40 Deduct open area 29.172
2.80
-35.84 m² 1 -1 1 2.40 Deduction
1 1 1 14.30 On axisd G b/n 2-4 0.80 W-4
3.30 -1.92 m²
47.19

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 -1 1 2.59 W-2 1 1 1 1.80 On Axis 5 ,E-G


1.80 0.60
-4.66 m² 1.08 m²
1 1 2 10.60 On axis A & F b/n 2-4 1 1 1 12.00 On Axis G ,2-5
3.30 0.80

69.96 m² 9.60 m²

Deduction 1 1 1 2.00 On Axis G ,2-5


1 -1 2 7.40 WD-6 0.60
2.80 1.20 m²
-41.44 m³ 1 1 1 4.63 On Axis 2 ,F-G
1 1 2 3.70 On axis B' & D' b/n 4-5 0.80
3.30 3.70 m²
24.42 m³ 1 1 1 0.80 On Axis 2 ,F-G
Deduction 0.60
1 -1 1 3.10 W-4 0.48 m² 45.05 m²
0.50 Second- Eighth Floor
-1.55 m² 7 1 1 6.55 On axis 1' b/n C-D
1 1 2 7.00 On axis C & E b/n 1-2 3.30
3.30 151.31 m²
46.20 m² Deduction
Deduction 7 -1 2 0.80 TW-3
1 -1 2 6.40 WD-7 0.60
2.80 -6.72 m²
-35.84 m² 7 1 1 6.00 On axis 1 b/n D-E
Around Terrace 3.30
1 1 1 3.30 On Axis A, 4-5 138.60 m²
0.80 Deduction
2.64 m² 7 -1 2 2.00 W-5
1 1 1 0.40 On Axis A, 4-5 1.80
0.60 -50.40 m²
0.24 m² 7 1 1 12.00 On axis 2 b/n A-C
1 1 1 5.10 On Axis 5 , A-B 3.30
0.80 277.20 m²
4.08 m² Deduction
1 1 1 1.20 On Axis 5 , A-B 7 -1 1 0.80 W-8
0.60 1.80
0.72 m² -10.08 m²
1 1 2 3.31 On Axis B & E ,5-6 7 -1 1 2.00 W-5
0.80 1.80
5.30 m² -25.20 m²
1 1 2 0.80 On Axis B & E ,5-6 7 -1 1 0.60 TW-3
0.60 0.80
0.96 m² -3.36 m²
1 1 1 15.60 On Axis 6 ,B-E 7 -1 1 1.10 W-11
0.80 1.80
12.48 m² -13.86 m²
1 1 1 2.40 On Axis 6 ,B-E 7 1 1 6.00 On axis 2 b/n E-F
0.60 3.30
1.44 m² 138.60 m²
1 1 1 9.93 On Axis 5 ,E-G 7 -1 1 0.80 Deduction
0.80 1.80 W-8
7.94 m² -10.08 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

7 1 1 21.76 On axis 4 b/n A-F 7 -1 1 1.85 W-9


3.30 1.80
502.66 m² -23.31 m²
7 -1 2 2.00 Deduction 7 2 1 1.40 On Axis C & E 1-2
1.80 W-5 0.80 Balcony

-50.40 m² 15.68 m²

7 -1 2 1.80 WD-16 7 1 1 3.70 On axis D' b/n 4-5


2.80 3.30
-70.56 m² 85.47 m²
7 -1 2 1.43 WD-17 Deduction
2.80 7 -1 1 3.10 W-4
-56.06 m² 0.50
7 -1 2 2.03 W-6 -10.85 m²
1.80 7 1 1 5.20 On axis E b/n 1-2
-51.16 m² 3.30
7 1 1 4.83 On Axis 4 b/n A-B' 120.12 m²
0.80 BALCONY Deduction
27.05 m² 7 -1 1 2.00 W-5
7 1 1 5.03 On Axis 4 b/n D'-E 1.80
0.80 BALCONY -25.20 m²
28.17 m² 7 1 1 10.60 On axis F b/n 2-4
7 1 1 8.84 On axis 5 b/n B'-D' 3.30
3.30 244.86 m²
204.20 m² Deduction
Deduction 7 -1 1 2.90 W-7
7 -1 1 2.59 W-2 1.80
1.80 -36.54 m²
-32.63 m² 7 -2 1 0.60 TW-3
7 -1 1 2.40 W-4' 0.80
0.80 -6.72 m²
-13.44 m² Above Top tie Beam
7 1 1 10.60 On axis A b/n 2-4 1 1 1 10.68 On axis 4 b/n A-B'
3.30 2.00
244.86 m² 21.36 m²
Deduction 1 1 0.5 12.60 On axis 1 b/N C-E
7 -1 1 2.90 W-7 2.00
1.80 12.60 m²
-36.54 m² 1 2 0.5 5.00 On axis F b/n 2-4
7 -2 1 0.60 TW-3 2.00
0.80 10.00 m²
-6.72 m² 1 1 0.5 10.60 On axis A b/n 2-4
7 1 1 3.70 On axis B' b/n 4-5 2.00
3.30 10.60 m²
85.47 m² 1 1 1 7.54 WATER TANKER
7 1 1 6.25 b/n axis C & 1-2 2.75 FRONT ELEVATION
3.30 20.74 m²
144.38 m² 1 -1 1 2.59 Deduction
Deduction 1.80 W-2
7 -1 1 1.95 W-10 -4.66 m²
1.80
-24.57 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 -1 1 2.40 W-4 1 1 1 3.60 B/ N Axis C-D & 5-6


0.80 6.00
-1.92 m² 21.60 m²
1 1 1 3.10 RIGHT SIDE ELEVATION 1 1 1 5.74 B/ N Axis D-E & 5-6
3.00 3.54

9.30 m² 20.32 m²

1 1 1 3.30 LEFT SIDE ELEVATION FIRST-SEVENTH FLOOR CEILING

3.00 7 1 1 5.95 ON Axis 1 B/N C-D


9.90 m² 0.85
Gutter Plastering 35.40 m²
1 1 1 2.06 On Axis A-C / 1'-2' 7 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
23.25 1.20
48.01 m² 74.42 m²
1 1 1 2.06 On Axis E-F / 1-2' 7 1 1 3.45 ON Axis 4-5 B/N B'-C'
17.50 2.69
36.13 m² 64.96 m²
1 1 1 2.06 On Axis 4 / D'-F 7 1 1 1.14 ON Axis 4-5 B/N B'-C'
12.38 0.53
25.56 m² 1221.79 4.23 m²
2438.29 m² Total Item 6.01 b Roof slab
C. To Suspended slab & stair case 1 1 1 6.05 ON Axis 1 B/N C-D
SOLID SLAB 1.05
GROUND FLOOR CEILING 6.35 m²
1 1 1 5.93 B/ N Axis 4-5 & A-B 1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E
3.45 1.20
20.44 m² 10.63 m³
1 1 1 4.25 B/ N Axis B-B' & 4-5 1 1 1 3.45 ON Axis 4-5 B/N B'-C'
3.45 2.69
14.66 m² 9.28 m³
1 1 1 2.91 B/ N Axis C-C' & 4-5 1 1 1 1.14 ON Axis 4-5 B/N B'-C'
1.08 0.53
3.14 m² 0.60 m³
1 1 1 3.22 1 1 1 8.44
1.09 3.55
3.51 29.96 m² 235.83 m²
1 1 1 3.00 main stair case
1.28 Ground - 8th floor
3.84 9 1 1 2.40 SECTION A-A
1 1 1 4.46 B/ N Axis D'-E & 4-5 1.03 sofit
3.45 22.25 m²
15.37 m² 9 1 1 1.03 Landing 1
1 1 1 5.93 B/ N Axis E-F & 4-5 1.27
3.45 11.77 m²
20.44 m² 9 1 1 2.40 side
1 1 1 12.70 B/ N Axis F-G & 2-5 0.22
5.08 4.75 m²
64.52 m² 1 7 0.5 0.29 Riser side
1 1 1 5.76 B/ N Axis B-C & 5-6 0.15
3.60 0.15 m²
20.72 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

SECTION B-B Ribbed CEILING PLASTERING


9 1 1 1.93 sofit GROUND FLOOR CEILING (1st floor
1.03 1 1 1 5.87 slab)
17.89 m² 7.10 B/N axis 1-2' & C-D
9 1 1 1.27 Landing 1 41.68 m² SHOP 2

1.03 1 1 1 2.17

11.77 m² 5.80
9 1 1 1.93 side 12.59 m²
0.22 1 1 1 5.86 B/N axis 1-3 & D-E
3.82 m² 7.10 SHOP 3
1 7 0.5 0.29 Riser side 41.61 m²
0.15 1 1 1 5.75
0.15 m² 4.46
SECTION C-C 25.62 m²
9 1 1 2.00 sofit 1 1 1 5.85 B/N axis 2-4 & A-B
1.15 4.84 SHOP 1
20.70 m² 28.31 m²
9 1 1 2.00 side 1 1 1 5.10
0.22 4.47
3.96 m² 22.80 m²
1 5 0.5 0.29 Riser side 1 1 1 4.95 B/N axis 3-4 & E-F
0.15 5.75 SHOP 4
0.11 m² 28.46 m²
SHOP STAIR 1 1 1 4.95 B/N axis 3-4 & D-E
SECTION E-E 5.93 SHOP 5
1 1 1 3.75 sofit 29.35 m²
1.05 1 1 1 3.99 B/N axis 3-4 & C-D
3.94 m² 4.76 SHOP 6
1 1 1 3.75 Side Flight 18.99 m²
0.22 CORRIDOR
0.83 m² FOR GROUND FLOOR
1 11 0.5 0.30 Riser side 1 1 1 5.92 B/n axis 2-3 & C-D
0.15 2.40
0.25 m² 14.21 m²
SECTION F-F 1 1 1 1.68 B/n axis 3-4 & C-D
1 1 1 3.30 Side Flight 4.80
0.22 8.04 m²
0.73 m² 1 1 1 7.34 Entrance lobby
1 11 0.5 0.30 Riser side 4.81 B/n axis 3-4 & B-C
0.15 35.27 m²
0.25 m² Ramp
1 1 1 3.30 sofit 1 1 1 4.88 B/n axis 2-3 & E-F
1.05 12.95
3.47 m² 63.20 m²
1 1 1 1.99 Landing 1 VERENDA
2.20 1 1 1 3.35 B/N axis 4-5 & A-C
4.38 m² 10.63
1 1 1 0.06 side Landing 35.61 m²
0.22 1 1 1 3.35 B/N axis 4-5 & D'-F
0.01 m² 10.63
35.61 m²
555.57 m² Total to item

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 17.45 B/N axis 5-6 & B-E 1 1 1 1.93 lobby


3.60 7.93 B/n axis 3-4 & B-C'
62.82 m² 15.30 m²
Toilet Toilet
1 1 1 1.40 B/N axis 2-3 & A'-B 1 1 1 1.40 B/N axis 2-3 & A'-B

4.48 4.48

6.28 m² 6.28 m²
1 1 1 1.00 B/N axis 2-3 & B-B' 1 1 1 1.00 B/N axis 2-3 & B-B'
2.75 2.75
2.75 m² 2.75 m²
1 1 1 2.85 1 1 1 2.85
2.33 2.33
6.64 m² 6.64 m²
1 1 1 1.70 1 1 1 1.70
2.60 2.60
4.42 m² 4.42 m²
2nd- 7th floor Ceiling (3rd-8th floor
First Floor ceiling (2nd floor slab)
slab)
1 1 1 5.78 B/N axis 1-2' & C-D 3-bed room (C-E)
6.80 SHOP 7 6 1 1 3.60 M.B.ROOM
39.27 m² 3.00
1 1 1 5.78 64.80 m²
2.15 6 1 1 1.60
12.42 m² 1.30
1 1 1 5.78 B/N axis 1-2' & D-E 12.48 m²
6.80 SHOP 8 6 1 1 2.73 B.ROOM 1
39.27 m² 3.30
1 1 1 5.78 54.05 m²
2.15 6 1 1 3.15 B.ROOM 2
12.42 m² 2.00
1 1 1 4.47 B/N axis 2-4 & A-B 37.80 m²
4.98 Café & Restaurant #1 6 1 1 5.93 LIVING & DINING ROOM including Balcony
22.24 m² 6.66
1 1 1 5.78 236.78 m²
4.84 6 1 1 1.40 CORRIDOR
27.95 m² 0.80
1 1 1 5.67 B/N axis 2-3 & E-F 6.72 m²
4.90 SHOP 9 6 1 1 4.90
27.78 m² 1.50
1 1 1 8.13 B/N axis 3-4 & B-C' 44.10 m²
2.91 SHOP 10 6 1 1 2.16
23.66 m² 1.40
1 1 1 4.84 B/N axis 3-4 & C'-F 18.14 m²
15.10 Café & Restaurant #2 6 1 1 2.20 TOILET
73.06 m² 1.50
CORRIDOR . 19.80 m²
1 1 1 5.78 B/n axis 2-3 & D-E 6 1 1 2.20
2.37 1.50
13.66 m³ . 19.80 m²
1 1 1 5.85 B/n axis 2-3 & C-D 6 1 1 2.25 KITCHEN
2.37 2.70
13.84 m³ 36.45 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

3-bed room (A-B') 6 1 1 2.90 KITCHEN


6 1 1 3.56 M.B.ROOM 2.02
3.48 35.15 m²
74.23 m² 6 1 1 1.85 Balcony
6 1 1 1.00 1.80

0.50 19.98 m²

3.00 m² 3-bed room (D'-F)


6 1 1 3.89 B.ROOM 2 6 1 1 2.00 B.ROOM 2
2.20 4.00
51.41 m² 48.00 m²
6 1 1 2.25 CORRIDOR 6 1 1 3.65 M.B.ROOM
3.30 3.47
44.55 m² 75.99 m²
6 1 1 5.88 6 1 1 1.02
1.37 0.56
48.29 m² 3.43 m²
6 1 1 3.43 B.ROOM 1 6 1 1 3.30 CORRIDOR
3.43 2.23
70.59 m² 44.09 m²
6 1 1 4.70 LIVING & DINING ROOM 6 1 1 5.80
3.53 1.37
99.55 m² 47.68 m²
6 1 1 2.53 TOILET 6 1 1 3.42 B.ROOM 1
1.43 3.43
21.71 m² 70.38 m²
6 1 1 2.53 6 1 1 4.88 LIVING & DINING ROOM
1.35 3.56
20.49 m² 104.24 m²
6 1 1 3.23 KITCHEN 6 1 1 2.53 TOILET
3.45 1.30
66.86 m² 19.66 m²
2-bed room (A-D) 6 1 1 2.53
6 1 1 4.85 LIVING & DINING ROOM 1.30
4.05 19.66 m²
117.86 m² 6 1 1 3.18 KITCHEN
6 1 1 4.88 CORRIDOR 3.46
0.93 66.02 m²
27.23 m² 6 1 1 5.92 lobby
6 1 1 2.47 M.B.ROOM 6.60 on Axis 2'-4, C-D
4.98 234.43 m²
73.80 m² 6 1 1 2.69 on Axis 4-5, C-D
6 1 1 4.45 B.ROOM 1 3.45
2.15 55.68 m²
57.41 m² 6 1 1 0.53
6 1 1 3.00 store 1.14
1.78 3.63 m² 1626.27 m³
32.04 m² Deduct column contact areas
6 1 1 2.02 TOILET Ground
1.78 1 21 -1 0.35
21.57 m² 0.35
-2.57 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 15 -1 0.05 Internal
0.05 1 2 1 31.78 ON AXIS -3 (A-G)
-0.04 m² 0.22 FB-3
3 21 -1 0.35 1st-3rd 13.98 m²
0.35 1 2 1 5.03 ON AXIS -3 (A-G)

-7.72 m² 0.22
FB-3
3 2 -1 0.05 2.21 m²
0.05 Bottom
-0.02 m² 1 1 1 17.83 ON AXIS -3 (A-G)
4 22 -1 0.15 4th-7th 0.25 FB-3
0.15 4.46 m²
-1.98 m² 1 1 1 13.95 ON AXIS -3 (A-G)
4 1 -1 0.05 0.05 FB-3
0.05 -9.77 0.70 m²
-0.01 m² -9.77 Internal
3082.41 m² Sub Total (m2) to item 1 1 1 9.68 ON AXIS 4-(A-B')
3637.98 m² Total Item 6.01 C 0.22 FB-4
D. To exposed beams, columns & 2.13 m²
stair case bottom
First floor Beams 1 1 1 9.68 ON AXIS 4-(A-B')
Internal 0.25 FB-4
1 1 1 10.80 ON XIS 1-(C-E) 2.42 m²
0.22 FB-1 Internal
2.38 m² 1 2 1 5.44 ON AXIS 4 -(C'-D')
Bottom 0.22 FB-5
1 1 1 10.80 ON XIS 1-(C-E) 2.39 m²
0.05 FB-1 1 2 1 9.68 ON AXIS 4 -(D'-G)
0.54 m² 0.22 FB-5
Internal 4.26 m²
1 1 1 10.55 ON AXIS-2 (A-C) 1 2 1 5.03 ON AXIS 4 -(D'-G)
0.22 FB-2 0.22 FB-5
2.32 m² 2.21 m²
1 2 1 10.80 ON AXIS-2 (C-E) bottom
0.22 FB-2 1 1 1 14.71 ON AXIS 4 -(D'-G)
4.75 m² 0.25 FB-5
1 1 1 5.40 ON AXIS-2 (E-F) 3.68 m²
0.22 FB-2 1 1 1 5.44 ON AXIS 4 -(D'-G)
1.19 m² 0.05 FB-5
1 1 1 5.03 ON AXIS-2 (F-G) 0.27 m²
0.22 FB-2 Internal
1.11 m² 1 1 1 29.88 ON AXIS 5 - (A-G)
Bottom 0.22 FB-6
1 1 1 8.65 ON AXIS-2 (A-C) 6.57 m²
0.25 FB-2 1 1 1 9.01 ON AXIS 5 - (A-G)
2.16 m² 0.22 FB-6
1 1 1 10.80 ON AXIS-2 (C-E) 1.98 m²
0.25 FB-2 bottom
2.70 m² 1 1 1 30.93 ON AXIS 5 - (A-G)
1 1 1 10.43 ON AXIS-2 (E-G) 0.25 FB-6
0.05 FB-2 7.73 m²
0.52 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 3.35 ON AXIS 5 - (A-G) 1 2 1 6.95 ON AXIS B -(6-4)


0.05 FB-6 0.22 FB-9
0.17 m² 3.06 m² 11.75
Internal Bottom
1 1 1 17.53 ON AXIS 6 -(B-E ) 1 1 1 15.30 ON AXIS B -(6-2)

0.22 0.25
FB-7 FB-9
3.86 m² 3.83 m²
Bottom Internal
1 1 1 17.53 ON AXIS 6 -(B-E ) 1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.25 FB-7 0.50 FB-10
4.38 m² 2.47 m²
Internal Bottom
1 1 1 12.20 ON AXIS A -(5-2 ) 1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.22 FB-8 0.05 FB-10
2.68 m² 0.25 m²
1 1 1 13.10 ON AXIS G -(5-2 ) Internal
0.22 FB-8 1 1 1 6.40 ON AXIS C -(1-2)
2.88 m² 0.22 FB-11
Internal 1.41 m²
1 2 1 4.40 ON AXIS F -(3-2 ) 1 2 1 4.39 ON AXIS C -(3-2)
0.22 FB-8 0.22 FB-11
1.94 m² 1.93 m²
1 2 1 8.10 ON AXIS F -(3-5 ) 1 2 1 4.76 ON AXIS C -(3-4)
0.22 FB-8 0.22 FB-11
3.56 m² 2.09 m²
Bottom Bottom
1 1 1 10.40 ON AXIS A-(5-2 ) 1 1 1 11.16 ON AXIS C -(1-2 & 3-4)
0.25 FB-8 0.25 FB-11
2.60 m² 2.79 m²
1 1 1 1.40 ON AXIS A-(5-2 ) 1 1 1 4.40 ON AXIS C -(2-3)
0.05 FB-8 0.05 FB-11
0.07 m² 0.22 m²
1 1 1 7.80 ON AXIS F - (5-2 ) Internal
0.25 FB-8 1 2 2 6.75 b/n axis C-D and D-E & (2-1)
1.95 m² 0.22 FB-12
1 1 1 4.40 ON AXIS F - (5-2 ) 5.94 m²
0.05 FB-8 Bottom
0.22 m² 1 2 1 6.75 b/n axis C-D and D-E & (2-1)
1 1 1 11.70 ON AXIS G-(5-2 ) 0.25 FB-12
0.25 FB-8 3.38 m²
2.93 m² Internal
1 1 1 1.40 ON AXIS G-(5-2 ) 1 1 2 15.55 ON AXIS D -(4-1)
0.05 FB-8 0.22 FB-13
0.07 m² 6.84 m²
Internal Bottom
1 2 1 8.35 ON AXIS B -(4-2) 1 1 1 2.22 ON AXIS D -(4-1)
0.22 FB-9 0.25 FB-13
3.67 m² 0.56 m²
1 2 1 3.40 ON AXIS B -(5-4) 1 1 1 13.33 ON AXIS D -(4-1)
0.22 FB-9 0.05 FB-13
1.50 m² 0.67 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal Internal
1 1 1 21.70 ON AXIS E-(6-1) 1 1 2 1.25 ON AXIS C (5-4)
0.22 FB-14 0.22 FB-18
4.77 m² 0.55 m²
Internal Internal

1 1 1 6.40 1 1 1 1.25
ON AXIS E-(1-2) ON AXIS (5-4)
0.22 FB-14 0.05 FB-18
1.41 m² 0.06 m²
1 1 2 8.80 ON AXIS E-(2-4) 2nd- 7th Floor Beams
0.22 FB-14 Internal
3.87 m² 7 1 1 10.60 ON AXIS 1-(C-E)
1 1 2 3.40 ON AXIS E-(4-5) 0.22 FB-1
0.22 FB-14 16.32 m²
1.50 m² 7 1 1 5.20 ON AXIS 1-(C-D)
1 1 2 3.55 ON AXIS E-(5-6) 0.22 FB-1
0.22 FB-14 8.01 m²
1.56 m² Bottom
Bottom 7 1 1 9.20 ON AXIS 1-(C-E)
1 1 1 13.35 ON AXIS E-(1-2 & 4-6) 0.25 FB-1
0.25 FB-14 16.10 m²
3.34 m² 7 1 1 1.31 ON AXIS 1-(C-E)
1 1 1 8.80 ON AXIS E-(2-4) 0.05 FB-1
0.05 FB-14 0.46 m²
0.44 m² Internal
Internal 7 1 1 16.20 ON AXIS-2 (A-F)
1 1 2 6.65 ON AXIS D' - (6 -4) 0.22 FB-2
0.22 FB-15 24.95 m³
2.93 m² 7 2 1 10.80
Bottom 0.22
1 1 1 6.65 ON AXIS D' - (6 -4) 33.26 m³
0.25 FB-15 Bottom
1.66 m² 7 1 1 14.57 ON AXIS-2 (A-F)
1 1 1 3.10 ON AXIS D' - (6 -4) 0.25 FB-2
0.05 FB-15 25.50 m²
0.16 m² 7 1 1 7.38
Internal 0.05
1 1 2 3.40 ON AXIS C' (5-4) 2.58 m²
0.22 FB-16 Internal
1.50 m² 7 1 2 27.00 ON AXIS 3 (A-F)
Bottom 0.22 FB-3
1 1 1 3.40 ON AXIS C' (5-4) 83.16 m²
0.25 FB-16 Bottom
0.85 m² 7 1 1 11.64 ON AXIS 3 (A-F)
Internal 0.25 FB-3
1 1 2 3.55 ON AXIS C ( 6-5) 20.37 m²
0.22 FB-17 7 1 1 10.70 ON AXIS 3 (A-F)
1.56 m² 0.05 FB-3
Bottom 3.75 m²
1 1 1 3.55 ON AXIS C( 6-5) 7 1 1 4.36 ON AXIS 3 (A-F)
0.25 FB-17 0.15 FB-3
0.89 m² 4.58 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal Bottom
7 1 1 9.68 ON AXIS 4-(A-B') 7 1 1 4.40 ON AXIS B -(4-2 )
0.22 FB-4 0.05 FB-8
14.91 m² 1.54 m²
Bottom 7 1 1 4.40 ON AXIS B -(4-2 )

7 1 1 7.28 0.25
ON AXIS 4-(A-B') FB-8
0.25 FB-4 7.70 m²
12.74 m² Internal
7 1 1 2.19 ON AXIS 4-(A-B') 7 1 1 14.75 ON AXIS C (4-1)
0.05 FB-4 0.22 FB-9
0.77 m² 22.72 m²
Internal 7 1 1 8.85
7 1 1 14.92 ON AXIS 4 -(C-F) 0.22
0.22 FB-5 13.63 m²
22.98 m² Bottom
7 1 1 5.64 ON AXIS 4 -(C-F) 7 1 1 3.71 ON AXIS C (4-1)
0.22 FB-5 0.05 FB-9
8.69 m² 1.30 m²
Bottom 7 1 1 9.09 ON AXIS C (4-1)
7 1 1 9.80 ON AXIS 4 -(C-F) 0.25 FB-9
0.25 FB-5 15.91 m²
17.15 m² Internal
7 1 1 5.13 ON AXIS 4 -(C-F) 7 1 1 6.40 ON AXIS E (4-1)
0.05 FB-5 0.22 FB-9
1.80 m² 9.86 m²
Internal 7 2 1 8.70
7 1 1 7.54 ON AXIS -5 (B'-D') 0.22
0.22 FB-6 26.80 m²
11.61 m² Bottom
Bottom 7 1 1 8.20 ON AXIS E (4-1)
7 1 1 4.99 ON AXIS -5 (B'-D') 0.25 FB-9
0.25 FB-6 14.35 m²
8.73 m² 7 1 1 6.70 ON AXIS E (4-1)
7 1 1 2.55 ON AXIS -5 (B'-D') 0.05 FB-9
0.05 FB-6 2.35 m²
0.89 m² Internal
Internal 7 1 2 15.55 ON AXIS D -(4-1)
7 2 1 8.80 ON AXIS A & F (4-2 ) 0.22 FB-10
0.22 FB-7 47.89 m²
27.10 m² Bottom
Bottom 7 1 1 7.95 ON AXIS D -(4-1)
7 2 1 4.10 ON AXIS A & F (4-2 ) 0.05 FB-10
0.25 FB-7 2.78 m²
14.35 m² 7 1 1 2.05 ON AXIS D -(4-1)
7 2 1 4.30 ON AXIS A & F (4-2 ) 0.15 FB-10
0.05 FB-7 2.15 m²
3.01 m² 7 1 1 4.65 ON AXIS D -(4-1)
Internal 0.25 FB-10
7 1 2 8.70 ON AXIS B -(4-2 ) 8.14 m²
0.22 FB-8
26.80 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal bottom
7 1 2 6.75 Beam around C-D b/n 1-2 1 1 1 3.45 ON AXIS C' (5-4)
0.22 0.25 RB-1
20.79 m² 0.86 m²
Bottom Internal

7 1 1 5.26 1 1 1 11.40
Beam around C-D b/n 1-2 ON AXIS 1 - (C-E)
0.25 0.22 RB-2
9.21 m² 2.51 m²
7 1 1 0.85 Bottom
0.15 1 1 1 9.20 ON AXIS 1 (C-E)
0.89 m² 0.25 RB-2
Internal 2.30 m²
7 1 2 6.75 Beam around D-E b/n 1-2 1 1 1 1.31 ON AXIS (D-E)
0.22 0.05 RB-2
20.79 m² 0.07 m²
Bottom Internal
7 1 1 6.65 Beam around D-E b/n 1-2 1 1 1 16.20 ON AXIS -2 (A-F)
0.25 0.22 RB-3
11.64 m² 3.56 m²
Internal 1 1 2 10.80 ON AXIS -2 (C-E)
7 1 1 3.10 ON AXIS D' (5-4) 0.22 RB-3
0.22 FB-11 4.75 m²
4.77 m³ Bottom
Bottom 1 1 1 14.57 ON AXIS -2 (A-F)
7 1 1 3.10 ON AXIS D' (5-4) 0.25 RB-3
0.25 FB-11 3.64 m²
5.43 m² 1 1 1 7.38 ON AXIS -2 (A-F)
Internal 0.05 RB-3
7 1 1 1.25 ON AXIS B' (5-4) 0.37 m²
0.22 FB-12 Internal
1.93 m³ 1 1 2 27.00 ON AXIS -3 (A-F)
Bottom 0.22 RB-3
7 1 1 1.25 ON AXIS B' (5-4) 11.88 m²
0.05 FB-12 Bottom
0.44 m² 1 1 1 11.64 ON AXIS -3 (A-F)
Internal 0.25 RB-3
7 1 1 3.10 ON AXIS C' (5-4) 2.91 m²
0.22 FB-13 1 1 1 4.36 ON AXIS -3 (A-F)
4.77 m² 0.15 RB-3
7 1 1 3.10 ON AXIS C' (5-4) 0.65 m²
0.32 FB-13 1 1 1 10.70 ON AXIS -3 (A-F)
6.94 m² 0.05 RB-3
Bottom 0.54 m²
7 1 1 3.10 ON AXIS C' (5-4) Internal
0.25 FB-13 1 1 1 9.68 ON AXIS 4-(A-B')
5.43 m² 0.22 RB-4
TOP TIE BEAM 2.13 m²
Internal Bottom
1 1 2 3.45 ON XIS C' (5-4) 1 1 1 7.28 ON AXIS 4-(A-B')
0.22 RB-1 0.25 RB-4
1.52 m² . 1.82 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 2.19 ON AXIS 4-(A-B') Internal


0.05 RB-4 1 1 1 14.75 ON AXIS -C- (2-1)
0.11 m² 0.22 RB-8
Internal 3.25 m²
1 1 1 14.92 ON AXIS 4 -(C-F) 1 1 1 8.85 ON AXIS -C- (4-2)

0.22 0.22
RB-5 RB-8
3.28 m² 1.95 m²
1 1 1 5.64 ON AXIS 4 -(C-F) Bottom
0.22 RB-5 1 1 1 9.09 ON AXIS C (4-1)
1.24 m² 0.25 RB-8
Bottom 2.27 m²
1 1 1 9.80 ON AXIS 4 -(C-F) 1 1 1 3.71 ON AXIS C (4-1)
0.25 RB-5 0.05 RB-8
2.45 m² 0.19 m²
1 1 1 5.13 ON AXIS 4 -(C-F) Internal
0.05 RB-5 1 1 2 15.55 ON AXIS D -(4-1)
0.26 m² 0.22 RB-8
Internal 6.84 m²
1 1 1 8.80 ON AXIS -A- (4-2) Bottom
0.22 RB-6 1 1 1 7.95 ON AXIS D -(4-1)
1.94 m² 0.05 RB-8
Bottom 0.40 m²
1 1 1 4.10 ON AXIS -A- (4-2) 1 1 1 4.65 ON AXIS D -(4-1)
0.25 RB-6 0.25 RB-8
1.03 m² 1.16 m²
1 1 1 4.30 ON AXIS -A- (4-2) 1 1 1 2.05 ON AXIS D -(4-1)
0.05 RB-6 0.15 RB-8
0.22 m² 0.31 m²
Internal Internal
1 1 2 8.70 ON AXIS -B- (4-2 ) 1 1 1 1.25 ON AXIS B' - (4-5)
0.22 RB-7 0.22 RB-9
3.83 m² 0.28 m²
Bottom Bottom
1 1 1 4.40 ON AXIS -B- (4-2 ) 1 1 1 1.25 ON AXIS B' - (4-5)
0.25 RB-7 0.05 RB-9
1.10 m² 0.06 m²
1 1 1 4.40 ON AXIS -B- (4-2 ) Internal
0.05 RB-7 1 1 1 3.10 ON AXIS C' - (4-5)
0.22 m² 0.22 RB-9
Internal 0.68 m²
1 1 1 8.80 ON AXIS -F- (4-2) Bottom
0.22 RB-7 1 1 1 3.10 ON AXIS C' - (4-5)
1.94 m² 0.25 RB-9
Bottom 0.78 m²
1 1 1 4.10 ON AXIS -F- (4-2) Internal
0.25 RB-7 1 1 1 7.54 ON AXIS -5- (B'-D')
1.03 m² 0.22 RB-10
1 1 1 4.30 ON AXIS -F- (4-2) 1.66 m²
0.05 RB-7 Bottom
0.22 m² 1 1 1 4.99 ON AXIS -5- (B'-D')
0.25 RB-10
1.25 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 2.55 ON AXIS -5- (B'-D') COLUMN


0.05 RB-10 A) Elevation columns
0.13 m² Ground floor
Internal 1 1 1 3.20 ON AXIS 1
1 1 1 6.40 ON AXIS E (4-1) 2.80

0.22 8.96 m²
RB-11
1.41 m² 1 1 1 2.45
1 1 2 8.70 0.20
0.22 0.49 m²
3.83 m² 1 1 1 10.40 ON AXIS 2
Bottom 2.80
1 1 1 8.20 ON AXIS E (4-1) 29.12 m²
0.25 RB-11 1 1 1 7.10
2.05 m² 0.20
1 1 1 6.70 ON AXIS E (4-1) 1.42 m²
0.05 RB-11 1 1 1 11.27 ON AXIS 3
0.34 m² 2.80
WATER TANKER BEAM 31.56 m²
1 1 1 7.79 Internal 1 1 1 8.02
0.22 ON AXIS 5 (B'-D') 0.20
1.71 m² RB-11 1.60 m²
1 1 1 7.79 Bottom 1 1 1 10.50 ON AXIS 4
0.05 ON AXIS 5 (B'-D') 2.80
0.39 m² RB-11 29.40 m²
1 1 1 5.84 Internal 1 1 1 6.80
0.22 ON AXIS 4 (B'-D') 0.20
1.28 m² RB-12 1.36 m²
1 1 1 5.84 Bottom 1 1 1 8.90 ON AXIS 5
0.05 ON AXIS 4 (B'-D') 2.80
0.29 m² RB-12 24.92 m²
1 1 1 3.30 Internal 1 1 1 2.40
0.22 ON AXIS B' (4-5) 0.20
0.73 m² RB-13 0.48 m²
1 1 1 3.30 Bottom 1 1 1 3.00 ON AXIS 6
0.05 ON AXIS B' (4-5) 2.80
0.17 m² RB-13 8.40 m²
1 1 1 3.30 Internal 1 1 1 0.50
0.22 ON AXIS (4-5) 0.20
0.73 m² RB-14 0.10 m²
1 1 1 3.30 Bottom First floor
0.05 ON AXIS (4-5) 1 1 1 3.20 ON AXIS 1
0.17 m² RB-14 2.80
1 1 1 3.30 Internal 8.96 m³
0.22 ON AXIS D' (4-5) 1 1 1 2.45
0.73 m² RB-15 0.20
1 1 1 3.30 Bottom 0.49 m³
0.05 ON AXIS D' (4-5) 1 1 1 10.00 ON AXIS 2
0.17 m² RB-15 2.80
941.94 m³ 28.00 m³

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 6.65 Fifth- Eight Floor


0.20 4 1 1 2.30 ON AXIS 1
1.33 m² 2.80
1 1 1 11.17 ON AXIS 3 25.76 m²
2.80 4 1 1 1.45

31.28 m² 0.20

1 1 1 7.52 1.16 m²
0.20 4 1 1 5.00 ON AXIS 2
1.50 m² 2.80
1 1 1 7.80 ON AXIS 4 56.00 m²
2.80 4 1 1 2.85
21.84 m² 0.20
1 1 1 4.90 2.28 m²
0.20 4 1 1 6.00 ON AXIS 3
0.98 m² 2.80
1 1 1 1.90 ON AXIS 5 67.20 m²
2.80 4 1 1 3.30
5.32 m² 0.20
1 1 1 1.15 2.64 m²
0.20 4 1 1 3.40 ON AXIS 4
0.23 m² 2.80
Second- Fourth Floor 38.08 m²
3 1 1 4.10 ON AXIS 1 4 1 1 2.10
2.80 0.20
34.44 m² 1.68 m²
3 1 1 3.25 4 1 1 0.60 ON AXIS 5
0.20 2.80
1.95 m² 6.72 m²
3 1 1 8.80 ON AXIS 2 4 1 1 0.30
2.80 0.20
73.92 m² 0.24 m²
3 1 1 6.65 water tanker level
0.20 1 1 1 1.30 ON AXIS 5
3.99 m² 2.60
3.38 m²
1 1 1 2.10 ON AXIS 4
2.60
5.46 m²

729.65 m³ sub total (m2) to item


1671.59 m³ Total To Item 6.01 D
E. To exposed lift wall and retaining
3 1 1 10.80 ON AXIS 3 ` wall
2.80 1 1 1 2.60 BASEMENT FOOR
90.72 m² 4.22 lift wall
3 1 1 7.70 10.97 m² W2
0.20 1 1 1 2.30
4.62 m² 4.22
3 1 1 6.20 ON AXIS 4 9.71 m²
2.80 1 1 1 2.30 lift wall
52.08 m² 4.22 W3
3 1 1 4.90 9.71 m²
0.20 1 1 1 1.10 lift wall
2.94 m² 4.22 W4
3 1 1 1.90 ON AXIS 5 4.64 m²
2.80 Grd- first floor
15.96 m² lift wall
3 1 1 1.15 1 1 1 2.30 W3 (at Ground Floor)
0.20 3.12
0.69 m² 7.18 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 1 1 2.60 w2 2nd- 8TH floor


3.12 Toilet
16.22 m² 7 1 1 7.00 On axis 2 b/n B-B'
2 1 1 2.30 w2 2.00
3.12 98.00 m²

14.35 m² 7 1 1 7.51 On axis 3 around A-B

2 1 1 2.30 w3 2.00
3.12 105.14 m²
14.35 m² 7 1 1 7.51
1 1 1 2.10 W4 2.00
3.12 105.14 m²
6.55 m² 7 1 1 6.67 On axis 1 around C-D
1 -1 1 1.00 DDT 2.00
2.10 93.38 m²
-2.10 m² 7 1 1 7.30
second-eight floor 2.00
7 1 1 2.10 w2 102.20 m²
3.12 7 1 1 7.51 On axis 3 around E-F
45.86 m² 1.80
7 1 1 2.40 w2 94.63 m²
3.12 7 1 1 7.51
52.42 m² 1.80
7 1 1 2.30 w3 94.63 m²
3.12
50.23 m² 820.56 m² Total item 6.01F
7 1 1 2.10 W4 G) To all lift shaft shear wall to
3.12 receive Granite wall tile,
45.86 m² 1 1 1 2.10 BASEMENT FOOR
1 -1 1 1.00 DDT 4.22 lift wall
2.10 8.86 m² W4
-2.10 m² 1 1 1 0.25
283.84 m² Total to item 6.01 E 2.10
F. To all internal wall to receive 0.53 m²
ceramic wall tile, 1 1 1 1.00
2 1 1 5.35 Grd- FIRST floor 0.25
2.00 G. TOILET 0.25 m²
21.40 m² 1 -1 1 1.00 DDT
2 1 1 3.57 2.10
2.00 -2.10 m²
14.28 m² 7.54 m² TOTAL ITEM
2 1 1 6.60 Grd- first floor
2.00 2 1 1 2.10 lift wall
26.40 m² 3.12 W4
2 1 1 6.35 L. TOILET 13.10 m²
2.00 2 1 1 0.25
25.40 m² 2.10
2 1 1 5.21 1.05 m²
2.00 2 1 1 1.00
20.84 m² 0.25
2 1 1 4.78 0.50 m²
2.00
19.12 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 -1 1 1.00 DDT
2.10
-4.20 m²
Second-Eight floor
7 1 1 2.10 lift wall

3.12 W4

45.86 m²
7 1 1 0.25
2.10
3.68 m²
7 1 1 1.00
0.25
1.75 m²
7 -1 1 1.00 DDT
2.10
-14.70 m²

54.58 m² Total item 6.01G

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

7. FINISHING 3-bed room (A-B')


50mm thickWall finishing
cement sand screed 2 1 1 4.02 B.ROOM 2
smoothly finished flooring in mortar 2.20
mix (1:3) at basement garage.
2nd- 3rd floor 17.69 m²
3-bed room (C-E) 2 -1 1 0.40 Deduct column contact area

2 1 1 3.60 M.B.ROOM 0.18

3.00 -0.14 m²
21.60 m² 2 1 1 3.52 M.B.ROOM
2 1 1 1.60 3.68
1.30 25.91 m²
4.16 m² 2 1 1 1.00
2 -1 1 0.40 deduction for column in MB 0.50
0.40 1.00 m²
-0.32 m² 2 -1 1 0.40 Deduct for column in MB
2 1 1 2.73 B.ROOM 1 0.40
3.30 -0.32 m²
18.02 m² 2 1 1 2.50 CORRIDOR
2 -1 1 0.18 deduction for column in BR1 3.30
0.40 16.50 m²
-0.14 m² 2 1 1 6.00
2 1 1 3.15 B.ROOM 2 1.37
2.00 16.44 m²
12.60 m² 2 -1 1 0.78 Deduct column contact area
2 -1 1 0.40 deduction for column in BR2 0.77
0.40 -1.20 m²
-0.32 m² 2 1 1 3.48 B.ROOM 1
2 1 1 7.03 LIVING & DINING ROOM 3.48
5.98 24.22 m²
84.08 m² 2 -1 1 0.40 deduction for column in BR1
2 -2 1 0.40 deduction for Balcony and column in Living dining column 0.40
0.23 on Axis 3 -0.32 m²
-0.37 m² 2 1 1 4.95 LIVING & DINING ROOM
2 -1 1 0.40 on Axis 2 3.62
0.60 35.84 m²
-0.48 m² 2 -1 1 0.40 deduction for column in Living dining column
2 -1 1 0.40 0.60
0.32 -0.48 m²
-0.26 m² Balcony 2-bed room
2 -1 1 1.18 2 1 1 5.10 LIVING & DINING ROOM
2.08 4.10
-4.91 m² 41.82 m²
2 1 1 3.55 CORRIDOR 2 -1 1 0.23 deduction for column in Living dining column
1.37 0.60
9.73 m² -0.28 m²
2 1 1 2.98 2 1 1 5.13 CORRIDOR
1.50 0.93
8.94 m² 9.54 m²
2 1 1 2.90 2 1 1 2.52 M.B.ROOM
0.80 5.03
4.64 m² 25.35 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 -1 1 0.23 deduction for column in MB 4th-8th floor


0.23 3-bed room (C-E)
-0.11 m² 5 1 1 3.60 M.B.ROOM
2 -1 1 0.23 3.00
0.40 54.00 m²

-0.18 m² 5 1 1 1.60

2 1 1 4.50 B.ROOM 1 1.30


2.15 10.40 m²
19.35 m² 5 -1 1 0.27 deduction for column in MB
2 1 1 3.00 store 0.27
1.83 -0.36 m²
10.98 m² 5 1 1 2.73 B.ROOM 1
3-bed room (D'-F) 3.30
2 1 1 2.00 B.ROOM 2 45.05 m²
4.05 5 -1 1 0.12 deduction for column in BR1
16.20 m² 0.30
2 1 1 3.70 M.B.ROOM -0.18 m²
3.52 5 1 1 3.15 B.ROOM 2
26.05 m² 2.00
2 -1 1 0.40 deduction for column in MB 31.50 m²
0.40 5 -1 1 0.30 deduction for column in BR2
-0.32 m² 0.30
2 1 1 3.12 CORRIDOR -0.45 m²
2.48 5 1 1 7.03 LIVING & DINING ROOM
15.48 m² 5.98
2 1 1 6.38 210.20 m²
1.57 5 -2 1 0.30 deduction for Balcony and column in
20.03 m² 0.23 Living dining column
2 -1 1 0.38 deduction for column in corridor -0.69 m² on Axis 3
0.17 5 -1 1 0.27 on Axis 2
-0.13 m² 0.40
2 -1 1 0.60 -0.54 m²
0.17 5 -1 1 0.27
-0.20 m² 0.21
2 1 1 3.48 B.ROOM 1 -0.28 m² Balcony
3.47 5 -1 1 1.18
24.15 m² 2.08
2 -1 1 0.40 deduction for column in BR1 -12.27 m²
0.40 5 1 1 3.55 CORRIDOR
-0.32 m² 1.37
2 1 1 5.13 LIVING & DINING ROOM 24.32 m²
3.61 5 1 1 2.98
37.04 m² 1.50
2 -1 1 0.40 deduction for column in Living dining 22.35 m²
0.60 5 1 1 2.90
-0.48 m² 0.80
11.60 m²
3-bed room (A-B')
5 1 1 4.02 B.ROOM 2
2.20
44.22 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

5 -1 1 0.27 Deduct column contact area 5 1 1 4.50 B.ROOM 1


0.12 2.15
-0.16 m² 48.38 m²
5 1 1 3.52 M.B.ROOM 5 1 1 3.00 store
3.68 1.83

64.77 m² 27.45 m²

5 1 1 1.00 3-bed room (D'-F)


0.50 5 1 1 2.00 B.ROOM 2
2.50 m² 4.05
5 -1 1 0.27 Deduct for column in MB 40.50 m²
0.27 5 1 1 3.70 M.B.ROOM
-0.36 m² 3.52
5 1 1 2.50 CORRIDOR 65.12 m²
3.30 5 -1 1 0.27 deduction for column in MB
41.25 m² 0.27
5 1 1 6.00 -0.36 m²
1.37 5 1 1 3.12 CORRIDOR
41.10 m² 2.48
5 -1 1 0.78 Deduct column contact area 38.69 m²
0.77 5 1 1 6.38
-3.00 m² 1.57
5 1 1 3.48 B.ROOM 1 50.08 m²
3.48 5 -1 1 0.38 deduction for column in corridor
60.55 m² 0.17
5 -1 1 0.27 deduction for column in BR1 -0.32 m²
0.27 5 -1 1 0.60
-0.36 m² 0.17
5 1 1 4.95 LIVING & DINING ROOM -0.51 m²
3.62 5 1 1 3.48 B.ROOM 1
89.60 m² 3.47
5 -1 1 0.27 deduction for column in Living dining column 60.38 m²
0.40 5 -1 1 0.27 deduction for column in BR1
-0.54 m² 0.27
2-bed room -0.36 m²
5 1 1 5.10 LIVING & DINING ROOM 5 1 1 5.13 LIVING & DINING ROOM
4.10 3.61
104.55 m² 92.60 m²
5 -1 1 0.23 deduction for column in Living 5 -1 1 0.27 deduction for column in Living dining
0.40 dining column 0.40
-0.46 m² -0.54 m²
5 1 1 5.13 CORRIDOR 1 1 1 5.09 Machin Room
0.93 3.55 18.07 m²
23.85 m² 1 1 -1 2.10 DDT Lift shaft
5 1 1 2.52 M.B.ROOM 2.40
5.03 -5.04 m²
63.38 m²
5 -1 1 0.23 deduction for column in MB 1895.04 m² Total item 7.01
0.23 280x30mm Terrazo window sill cut to
appropriate size, weathered and
-0.26 m² mounted on
5 -1 1 0.23 1 1 1 4.25 GROUND FLOOR
0.40 4.25 m² W-1
-0.46 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 2.80 TW-2 7 1 1 1.90 W-9


2.80 ml 13.30 ml
1 1 1 1.15 W-11 on axis D'
1.15 ml 2 1 1 3.15 W-4
1 1 1 2.45 W-4 6.30 ml
2.45 ml on axis D'
1 1 1 3.15 5 1 1 3.35 W-4
3.15 ml 16.75 ml
1 1 1 5.45 TW-4 on axis E
5.45 ml 7 1 1 2.05 W-5
1 1 3 4.55 TW-5 14.35 ml
13.65 ml on axis F
1 1 1 2.75 TW-6 7 1 1 2.95 W-7
2.75 ml 20.65 ml
FIRST FLOOR 7 1 2 0.65 TW-3

4.25 W-1 9.10 ml


1 1 1
4.25 ml 1 1 2 3.05 top tie beam ( lift house)
1 1 1 2.80 TW-2 6.10 ml TW-7
2.80 ml 1 1 1 2.45 W-4
1 1 1 1.15 W-11 2.45 ml
1.15 ml 1 1 1 2.64
1 1 1 2.45 W-4 2.64 ml
2.45 ml
1 1 1 3.15 W-4' 357.58 ml Total item 7.02
3.15 ml 20mm thick white terazzo tile bull
1 1 1 2.64 W-2 nosed window sill bedded in cement
mortar 1:3
2.64 ml 1ST Floor on Terrace
2ND- 8TH FLOOR 1 1 1 3.30 On Axis A, 4-5
7 1 2 2.05 on axis 1 W-5 3.30 ml
28.70 ml On Axis A, 4-5
7 1 2 0.65 on axis 1' TW-3 1 1 1 0.40
9.10 ml 0.40 ml
7 1 1 2.05 on axis 2 W-5 On Axis 5 , A-B
14.35 ml 1 1 1 0.60
7 1 2 0.85 W-8 0.60 ml
11.90 ml On Axis 5 , A-B
7 1 1 0.65 TW-3 1 1 1 5.65
4.55 ml 5.65 ml
7 1 1 1.15 W-11 On Axis B & E ,5-6
8.05 ml 1 1 2 3.10
7 1 2 2.05 on axis 4 W-5 6.20 ml
28.70 ml On Axis B & E ,5-6
7 1 2 2.08 W-6 1 1 2 0.80
29.12 ml 1.60 ml
on axis 5 On Axis 6 ,B-E
7 1 1 2.64 W-2 1 1 1 15.80
18.48 ml 15.80 ml
7 1 1 2.45 W-4' On Axis 6 ,B-E
17.15 ml 1 1 1 2.60
on axis A 2.60 ml
7 1 1 2.95 W-7 On Axis 5 ,E-G
20.65 ml 1 1 1 9.73
7 1 2 0.65 TW-3 9.73 ml
9.10 ml On Axis 5 ,E-G
on axis C 1 1 1 1.80
7 1 1 2.00 W-10 1.80 ml
14.00 ml On Axis G ,2-5
1 1 1 12.30
12.30 ml

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

On Axis G ,2-5 SHOP STAIR


1 1 1 2.00 GRD- FLOOR
2.00 ml 1 2 10 1.05 - Tread size 30x340mm
On Axis 2 ,F-G 0.34
1 1 1 5.43 7.14 m²

5.43 ml Main stair

67.41 ml Total item 7.12 Basement floor


0.34 - Tread size 30x340mm
424.99 ml Total item 7.02 & 7.12 1 1 7 1.10 section A-A
B. Terrazzo copping on verendah,
balcony & roof parapet of size 2.62 m²
180*30mm
0.34
On Axis 4 b/n A-B' 1 2 5 1.10 section B-B & section D-D
7 1 1 4.83 BALCONY 3.74 m²
33.81 ml 0.34
On Axis 4 b/n D'-E section C-C
1 1 12 1.15
7 1 1 5.03 BALCONY 4.69 m² 11.05
35.21 ml GRD-8TH FLOOR
On Axis E b/n 1-2 0.34 - Tread size 30x340mm
7 1 1 1.42 BALCONY 9 1 7 1.09 section A-A
9.94 ml 23.35 m²
On Axis C b/n 1-2 0.34
7 1 1 1.40 BALCONY 9 1 5 1.10 section B-B
9.80 ml 16.83 m²
Marble flooring to stair case 0.34
bedded on and including cement
88.76 ml Total item 7.02B 9 1 7 1.15 section C-C
sand mortar mix 1:3 and
jointsgrouted in appropriate color 24.63 m² 64.81
filler setting coat mortar. Pattern and
20mm thick to landing. 83.00 Total item tread size 30x340mm
color of the tile shall be approved by
Basement floor
the architect. Border marble
1 1 1 1.09 STAIR 1 0.15 ground floor
1.14 1 1 2 3.70 WD-6
1.24 m² 1.11 m²
1 -1 1 0.45 deduct column area 0.15 WD-7
0.80 1 1 2 6.40
-0.36 m² 1.92 m²
0.15 First floor
1 1 1 1.42 1 1 2 6.40 WD-7
1.08 1.92 m²
1.53 m² 0.15
GRD-8TH FLOOR 1 1 1 5.40 WD-4
9 1 1 1.09 STAIR 1 0.81 m²
1.14 0.15
11.18 m² 1 1 2 3.70 WD-6

9 -1 1 0.45 deduct column area 1.11 m²


0.80 6.87 Total item Boarder Marble
-3.24 m² SHOP STAIR
9 1 1 1.42 GRD- FLOOR
1.08 1 2 10 0.14 Riser size 20x10mm
13.80 m² 1.15
1 1 2 2.20 GRD- FLOOR 3.22 m²
1.98 STAIR 2
8.71 m²
32.86 m² Total item 20mm thick landing

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Main Stair 7 1 1 7.51


Basement floor 1.80
0.34 Riser size 20x10mm 94.63 m²
1 1 7 1.10 section A-A 7 1 1 6.67 On axis 1 around C-D
2.62 m² 1.80

0.34 84.04 m²

1 2 5 1.10 section B-B & section D-D 7 1 1 7.30


3.74 m² 1.80
0.34 91.98 m²
1 1 12 1.15 section C-C 7 1 1 7.51 On axis 3 around E-F
4.69 m² 11.05 1.80
94.63 m²
GRD-8TH FLOOR 7 1 1 7.51
0.14 Riser size 20x10mm 1.80
9 1 7 1.10 section A-A 94.63 m² 642.74
9.70 m² KITCHEN
0.14 7 1 1 1.10 B/N axis 2 & B-C
9 1 5 1.10 section B-B 1.50
6.93 m² 11.55 m²
0.14 7 1 1 2.05 B/N axis 3-4 & B-C
9 1 7 1.15 section C-C 1.50
10.14 m² 21.53 m²
7 1 1 1.58 B/N axis 3-4 & D-E
47.91 Supply
Totaland
itemfix 200x150x6
of Riser mm
20x10mm 1.50
white glazed Ceramic wall tiles
stuck to wall with cement mortar mix 16.59 m²
(1:2) backing and 2 mm joints to be
Grd- First
grouted in white floor
cement. 7 1 1 2.00 B/N axis 1-2 & D'-E
2 1 1 5.35 G. TOILET 1.50
2.00 21.00 m²
21.40 m² 840.85 m² Total item 7.04
2 1 1 3.57 Ditto but for lift shaft
2.00 GRANITE WALL CLADDING
14.28 m² Basement
2 1 1 6.60 1 1 1 2.10 W4
2.00 4.22
26.40 m² 8.86 m²
2 1 1 6.35 L. TOILET 1 1 -1 2.10 DDT OPENING
2.00 1.00
25.40 m² -2.10 m²
2 1 1 5.21 Grond & first
2.00 1 2 1 2.10 W4
20.84 m² 3.14
2 1 1 4.78 13.19 m²

2.00 1 2 -1 2.10 DDT OPENING


19.12 m² 1.00
2nd- 8TH floor -4.20 m²
7 1 1 7.00 On axis 2 b/n B-B' 2nd to 8th
1.80 7 1 1 2.30 W4
88.20 m² 3.14
7 1 1 7.51 On axis 3 around A-B 50.55 m²
1.80
94.63 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

7 1 -1 2.10 DDT OPENING 1 -2 1 0.60 deduction for column


1.00 0.50
-14.70 m² -0.60 m²
51.60 m² Total item 7.05 1 -1 1 0.60
100mm thick precast concrete 0.40
pavement in concrete class C-15
Pavement
around Aroundopen
the building the Building
jointed on -0.24 m²
1 1 1 131.76
and including 400mm selected
1.00 1 -1 1 0.60
131.76 m² 0.18
1 -2 1 4.00 deduct ramp area -0.11 m²
1.00 1 -1 1 0.17
-8.00 m² 0.18
123.76 m² Total item 7.06 a -0.03 m²
half ditch & Curvestone 1 1 1 6.03
1 1 1 136.75 5.02
136.75 30.27 m²
136.75 ml Total
Apply 42mm itemcement
thick 7.06 b screed to
receive porceline ceramic tile, Marble 1 1 1 5.80 B/N axis 3-4 & E-F
and ceramic tiles in 1:3 cement mortar 5.15 SHOP 4
GRDratio.
FLOOR 29.87 m²
1 1 1 12.00 Verendah 1 -1 1 0.40 deduction for column
7.00 B/N axis 1-2 & A-B 0.22
84.00 m² -0.09 m²
1 1 1 6.00 B/N axis 1-2 & E-F 1 -1 1 0.40
7.00 0.50
42.00 m² -0.20 m²
1 1 1 9.49 1 1 1 6.03 B/N axis 3-4 & D'-E
6.00 B/N axis 1-2' & C-D 5.14 SHOP 5
56.94 m² SHOP 2 30.99 m²
1 -2 1 0.40 deduction for column in GRD floor 1 -1 1 0.40 deduction for column
0.60 0.22
-0.48 m² -0.09 m²
1 -2 1 0.40 1 -1 1 0.23
0.21 0.22
-0.17 m² -0.05 m²
1 1 1 11.98 B/N axis 1-2' & D'-E 1 -1 1 0.35
6.00 SHOP 3 0.60
71.88 m² -0.21 m²
1 -2 1 0.40 deduction for column 1 -1 1 0.40
0.19 0.50
-0.15 m² -0.20 m²
1 -2 1 0.20 1 1 1 5.01 B/N axis 3-4 & C-D
0.60 3.99 SHOP 6
-0.24 m² 19.99 m²
1 -2 1 0.40 1 -1 1 0.25 deduction for column
0.18 0.18
-0.14 m² -0.05 m²
1 1 1 5.22 B/N axis 2-4 & A-B FIRST FLOOR
4.72 SHOP 1 1 1 1 9.49 B/N axis 1-2' & C-D
24.64 m² 6.00 SHOP 7
1 1 1 5.22 56.94 m²
6.10
31.84 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 -2 1 0.40 deduction for column 1 -2 1 0.50


0.60 0.60
-0.48 m² -0.60 m²
1 -2 1 0.40 1 -1 1 0.17
0.20 0.40

-0.16 m² -0.07 m²

1 1 1 2.91 B/N axis 3-4 & B-C'


1 1 1 9.49 B/N axis 1-2' & D'-E 8.18 SHOP 10
6.00 SHOP 8 23.80 m²
56.94 m² 1 -1 1 0.18
1 -2 1 0.60 deduction for column 0.60
0.20 -0.11 m²
-0.24 m² CORRIDOR
1 -2 1 0.40 1 1 1 6.06 FOR GROUND FLOOR
0.20 2.49
-0.16 m² 15.09 m²
1 1 1 2.69 1 1 1 5.18
6.00 1.00
16.14 m² 5.18 m²
1 1 1 5.22 B/N axis 2-4 & A-B 1 1 1 7.84 Entrance lobby
4.72 Café & Restaurant #1 4.76
24.64 m² 37.32 m²
1 1 1 5.22 1 1 1 1.50
6.10 0.29
31.84 m² 0.44 m²
1 -2 1 0.60 deduction for column 1 -1 1 0.26 Deduction for column
0.50 0.40
-0.60 m² -0.10 m²
1 -1 1 0.60 1 -1 1 0.35
0.40 0.60
-0.24 m² -0.21 m²
1 -1 1 0.60 1 -1 1 0.35
0.18 0.17
-0.11 m² -0.06 m²
1 -1 1 0.17 1 -1 1 0.60
0.18 0.29
-0.03 m² -0.17 m²
1 1 1 5.92 B/N axis 2-3 & E-F CORRIDOR
5.15 SHOP 9 FOR FIRST FLOOR
30.49 m² 1 1 1 12.26
1 -2 1 0.60 deduction for column 2.49
0.60 30.53 m²
-0.72 m² 1 1 1 8.18 Lobby
1 1 1 15.72 B/N axis 3-4 & C'-F 1.93
5.01 Café & Restaurant #2 15.79 m²
78.76 m² 1 -1 1 0.60 Deduction for column
1 -2 1 0.25 deduction for column 0.27
0.60 -0.16 m²
-0.30 m² 1 -2 1 0.46
1 -1 1 0.35 0.27
0.60 -0.25 m²
-0.21 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

CAFETERIA TERACE 1 1 1 6.00 B/N axis 1-2 & E-F


1 1 1 3.55 B/N axis 4-5 & A-B 7.00
6.15 42.00 m²
21.83 m² 1 1 1 9.49 B/N axis 1-2' & C-D
1 1 1 4.63 B/N axis 4-6 & B-B' 6.00 SHOP 2

56.94 m²
7.45
34.49 m² 1 -2 1 0.40 deduction for column in GRD floor
1 1 1 8.84 B/N axis 5-6 & B'-D' 0.60
3.75 -0.48 m²
33.15 m² 1 -2 1 0.40
1 1 1 4.63 B/N axis 4-6 & D'-E 0.21
7.45 -0.17 m²
34.49 m² 1 1 1 11.98 B/N axis 1-2' & D'-E
1 1 1 11.53 B/N axis 4-5 & E-G 6.00 SHOP 3
3.55 71.88 m²
40.93 m² 1 -2 1 0.40 deduction for column
1 1 1 10.45 B/N axis 2-4 & F-G 0.19
5.28 -0.15 m²
55.18 m² 1 -2 1 0.20
1 1 -1 5.25 ddt column 0.60
1.00 -0.24 m²
-5.25 m² 1 -2 1 0.40
0.18
1053.11 m² Total item -0.14 m²
1 1 1 5.22 B/N axis 2-4 & A-B
1053.11 m² Total item 7.07 (Receive ceramic Tile) 4.72 SHOP 1
24.64 m²
1 1 1 5.22
6.10
31.84 m²
1 -2 1 0.60 deduction for column
0.50
-0.60 m²
1 -1 1 0.60
0.40
-0.24 m²
1 -1 1 0.60
0.18
-0.11 m²
1 -1 1 0.17
0.18
-0.03 m²

1 1 1 6.03
5.02
Supply and fix 8mm thick non 30.27 m²
slippery porcelain ceramic floor tiles. 1 1 1 5.80 B/N axis 3-4 & E-F
Price includes tiles, adhesives glue, SHOP 4
5.15
cross spacers, sealant, and all
accessories. Size, pattern, quality and 29.87 m²
GRD
color shall be FLOOR
approved by the 1 -1 1 0.40 deduction for column
1 1 1 12.00 architect. Verendah 0.22
7.00 B/N axis 1-2 & A-B -0.09 m²
84.00 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 -1 1 0.40 FIRST FLOOR


0.50 1 1 1 9.49 B/N axis 1-2' & C-D
-0.20 m² 6.00 SHOP 7
1 1 1 6.03 B/N axis 3-4 & D'-E 56.94 m²
5.14 SHOP 5 1 -2 1 0.40 deduction for column

30.99 m²
0.60
1 -1 1 0.40 deduction for column -0.48 m²
0.22 1 -2 1 0.40
-0.09 m² 0.20
1 -1 1 0.23 -0.16 m²
0.22 1 1 1 9.49 B/N axis 1-2' & D'-E
-0.05 m² 6.00 SHOP 8
1 -1 1 0.35 56.94 m²
0.60 1 -2 1 0.60 deduction for column
-0.21 m² 0.20
1 -1 1 0.40 -0.24 m²
0.50 1 -2 1 0.40
-0.20 m² 0.20
1 1 1 5.01 B/N axis 3-4 & C-D -0.16 m²
3.99 SHOP 6 1 1 1 2.69
19.99 m² 6.00
1 -1 1 0.25 deduction for column 16.14 m²
0.18 1 1 1 5.22 B/N axis 2-4 & A-B
-0.05 m² 4.72 Café & Restaurant #1
CORRIDOR 24.64 m²
1 1 1 6.06 FOR GROUND FLOOR 1 1 1 5.22
2.49 6.10
15.09 m² 31.84 m²
1 1 1 5.18 1 -2 1 0.60 deduction for column
1.00 0.50
5.18 m² -0.60 m²
1 1 1 7.84 Entrance lobby 1 -1 1 0.60
4.76 0.40
37.32 m² -0.24 m²
1 1 1 1.50 1 -1 1 0.60
0.29 0.18
0.44 m² -0.11 m²
1 -1 1 0.26 Deduction for column 1 -1 1 0.17
0.40 0.18
-0.10 m² -0.03 m²
1 -1 1 0.35 1 1 1 5.92 B/N axis 2-3 & E-F
0.60 5.15 SHOP 9
-0.21 m² 30.49 m²
1 -1 1 0.35 1 -2 1 0.60 deduction for column
0.17 0.60
-0.06 m² -0.72 m²
1 -1 1 0.60 1 1 1 15.72 B/N axis 3-4 & C'-F
0.29 5.01 Café & Restaurant #2
-0.17 m² 1244.78 m² 78.76 m²
1 -2 1 0.25 deduction for column
0.60
-0.30 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 -1 1 0.35 Supply and fix 10cm high porcelain


0.60 skirting
-0.21 m² Ground floor
1 -2 1 0.50 1 1 1 20.17 B/N axis 1-2' & C-D
0.60 20.17 SHOP 2

-0.60 m² B/N axis 1-2' & D'-E

1 -1 1 0.17 1 1 1 28.85 SHOP 3


0.40 28.85
-0.07 m² B/N axis 2-3 & A-B
1 1 1 2.91 B/N axis 3-4 & B-C' 1 1 1 12.77 SHOP 1
8.18 SHOP 10 12.77
23.80 m² B/N axis 3-4 & E-F
1 -1 1 0.18 1 1 1 16.49 SHOP 4
0.60 16.49
-0.11 m² B/N axis 3-4 & D'-E
CORRIDOR 1 1 1 19.35 SHOP 5
1 1 1 12.26 FOR FIRST FLOOR 19.35
2.49 B/N axis 3-4 & C-D
30.53 m² 1 1 1 9.17 SHOP 6
1 1 1 8.18 lobby 9.17
1.93 1 1 1 11.76 CORRIDOR
15.79 m² 11.76
1 -1 1 0.60 Deduction for column VERENDA
0.27 1 1 1 13.20 On Axis 1-2 & A-B
-0.16 m² 13.2
1 -2 1 0.46 1 1 1 6.60 On Axis 1-2 & E-F
0.27 6.6
-0.25 m² 176.59 m² First floor
CAFETERIA TERACE B/N axis 1-2' & C-D
1 1 1 3.55 B/N axis 4-5 & A-B 1 1 1 20.03 SHOP 7
6.15 20.03
21.83 m² B/N axis 1-2' & D'-E
1 1 1 4.63 B/N axis 4-6 & B-B' 1 1 1 20.03 SHOP 8
7.45 20.03
34.49 m² B/N axis 2-3 & A-B
1 1 1 8.84 B/N axis 5-6 & B'-D' 1 1 1 15.92 Café & Restaurant #1
3.75 15.92
33.15 m² B/N axis 2-3 & E-F
1 1 1 4.63 B/N axis 4-6 & D'-E 1 1 1 9.64 SHOP 9
7.45 9.64
34.49 m² B/N axis 3-4 & C-F
1 1 1 11.53 B/N axis 4-5 & E-G 1 1 1 22.86 Café & Restaurant #2

3.55 22.86
40.93 m² B/N axis 3-4 & B-C
1 1 1 10.45 B/N axis 2-4 & F-G 1 1 1 11.35 SHOP 10
5.28 11.35
55.18 m² 1 1 1 6.88 CORRIDOR
1 1 -1 5.25 ddt column 6.88
1.00 CAFETERIA TERACE
-5.25 m² 1 1 1 9.65 on axis A,5 b/n 4-5 , A-B
1053.11 m² Total item 7.08 9.65

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

B/N axis 5-6 & B'-D' 7 -1 1 0.30 Deduct pipe area


1 1 1 25.90 0.20
25.9 -0.42 m²
B/N axis 5-6 & B'-D' 7 1 1 2.58 B/N axis 3 & A-B'
1 1 1 30.81 1.48

56.71 26.73 m²
30.81
1 1 1 16.24 B/N axis 4-5 & B'-D' 7 1 1 2.58
16.24 1.42
1340.88 ml 25.65 m²
327.67 ml Total item 7.08 7 -1 1 0.50 Deduct column and pipe area
Supply and fix 8mm thick non 0.40
slippery ceramic floor tiles. Price -1.40 m²
includes tiles, adhesives glue, cross
7 -2 1 0.30
spacers, sealant, and all accessories.
2 1 1 1.70 Grnd- 1st Floor 0.30
1.27 Gent's Toilet -1.26 m²
4.32 m² B/N axis 2-3 & B-B' 7 1 1 2.20 B/N axis 1 & C-D'
2 1 1 1.70 1.47
0.90 22.64 m²
3.06 m² 7 1 1 2.20
2 1 1 2.85 1.47
2.33 . 22.64 m²
13.28 m² 7 -1 1 0.50 Deduct column and pipe area
2 -1 1 0.40 Deduct Column and HCB Contact Area 0.35
0.60 -1.23 m²
-0.48 m² 7 -2 1 0.40
2 -1 1 0.30 0.15
0.30 -0.84 m²
-0.18 m² 7 1 1 2.58 B/N axis 3 & E-F
2 -1 1 0.30 1.42
0.40 25.65 m²
-0.24 m² 7 1 1 2.58
2 -1 1 0.40 1.47
0.10 26.55 m²
-0.08 m² 7 -1 1 0.50 Deduct column and pipe area
2 1 1 1.70 Lent's Toilet 0.40
1.09 -1.40 m²
3.71 m² 7 -2 1 0.30
2 1 1 1.31 0.30
1.70 -1.26 m²
4.45 m² KITCHEN
2 1 1 1.70 7 1 1 3.15 B/N axis 2 & B-C
2.60 2.07
8.84 m² 45.64 m²
2 -1 1 0.60 Deduct Column Contact Area 7 -2 1 0.60 Deduct Column Contact Area
0.25 0.40
-0.30 m² 36.38 m² -3.36 m²
2ND-8TH FLOOR 7 1 1 3.23 B/N axis 3-4 & B-C
7 1 1 2.07 BATHROOM 3.50
1.78 B/N axis 2 & B-B' 79.14 m²
25.79 m² 7 -1 1 0.40 Deduct Pipe Area
0.35
-0.98 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

7 1 1 3.18 B/N axis 3-4 & D-E 1 1 1 1.40 B/N axis 4-5 & C-D
3.46 0.85 APARTMENT ENTRANCE LOBBY
77.02 m² 1.19 m²
7 1 1 0.60 Deduct column and pipe area VERENDA
0.35 1 1 1 10.88 B/N axis 4-5 & A-C

1.47 m²
3.70
7 -1 1 0.40 40.26 m²
0.30 1 1 1 10.88 B/N axis 4-5 & D'-F
-0.84 m² 3.70
7 1 1 2.25 B/N axis 1-2 & D'-E 40.26 m²
2.70 1 1 1 18.42 B/N axis 5-6 & B-E
42.53 m² 3.85
BALCONY 70.92 m² 151.44 m²
7 1 2 4.23 B/N axis 4-5 & A-C , D'-F First floor
1.10 1 1 1 2.91 B/N axis 4-5 & C-D
65.14 m² 3.75 APARTMENT ENTRANCE LOBBY
7 1 1 1.75 B/N axis 1-2 & C-C' 10.91 m²
1.80 1 1 1 1.40 B/N axis 4-5 & C-D
22.05 m² 0.85 APARTMENT ENTRANCE LOBBY
7 1 1 1.10 B/N axis 1-2 & D'-E 1.19 m² 164.73 m²
1.80 2nd- 8TH floor
13.86 m² 7 1 1 2.91 B/N axis 4-5 & C-D
7 1 1 0.70 3.75 ENTRANCE LOBBY
0.20 76.39 m²
0.98 m² 7 1 1 1.40 B/N axis 4-5 & C-D
685.00 m² 0.85
546.87 m² Total item 7.08 8.33 m²
Supply and fix 10cm high ceramic 7 1 1 5.92 B/N axis 2'-4 & C-D
skirting 6.85 LOBBY
2ND-8TH FLOOR 283.86 m²
7 1 2 5.83 BALCONY 7 1 -1 0.58 DDT COL
81.62 B/N axis 4-5 & A-C , D'-F 0.60
7 1 1 4.90 B/N axis 1-2 & C-C' -2.44 m²
34.30 378.24 m²
7 1 1 3.02 B/N axis 1-2 & D'-E 540.91 m² Total item 7.10
Supply and fix 10cm high Marble
21.14
skirting
KITCHEN GROUND FLOOR
7 1 1 10.45 B/N axis 2 & B-C B/N axis 4-5 & C-D
73.15 1 1 1 6.03 APARTMENT ENTRANCE LOBBY
7 1 1 13.33 B/N axis 3-4 & B-C 6.03
93.31 VERENDA
7 1 1 13.92 B/N axis 3-4 & D-E 1 1 1 5.70 B/N axis 4-5 & A-C
97.44 5.7
7 1 1 9.20 B/N axis 1-2 & D'-E 1 1 1 17.44 B/N axis 4-5 & D'-F
64.40 17.44
465.36 Supply andTotal
fix 20mm
item thick
7.09 marble 1 1 1 5.70 B/N axis 5-6 & B-E
floor tiles. Price shall include cement
5.7
screed, mirror polishing and all
necessaryGROUND
works. FLOOR 1ST FOOR
1 1 1 2.91 B/N axis 4-5 & C-D 1 1 1 6.03 APARTMENT ENTRANCE LOBBY
3.45 APARTMENT ENTRANCE LOBBY 6.03
10.04 m²

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2nd- 8TH floor 2 1 1 5.77 On axis 4 b/N B'-D'


7 1 1 19.46 2.80
136.22 32.31 m²
Staircase Skirting 2 -1 1 2.69 Deduction
Shop Stair 2.80 WD-2
1 1 1 6.00 Ground floor -15.06
6.00 Staircase skirting 2 1 1 3.10 On axis D'/4-5
1 1 1 6.16 2.80
6.16 landing skirting 17.36
Main Stair 2 -1 1 3.10 Deduction
1 1 1 5.25 Basement floor 0.50 W-4
5.25 Staircase skirting -3.1
1 1 1 4.44 2 -1 1 1.55 W-4'
4.44 landing skirting 0.80

Gnd-8th floor
-2.48
9 1 1 5.36 Staircase skirting 2 1 1 5.34 On axis 5 b/N B'-D'
48.24 2.80
9 1 1 4.24 landing skirting 29.9
38.16 250.50 2 -1 1 2.69 Deduction
285.37 Total item 7.11 1.80 W-2
30x3cm marble threshold bedded on
cement mortar (1:3) ratio. -9.68
7 1 4 0.30 2nd- 8TH floor 2 1 1 0.70 Around duct
1.20 2.80
10.08 Total item 7.13 3.92
Gypsum Plastering 2 1 1 2.95 on axis 4 c'-d'
Finishing for Lobby and Corridor at
Residential Houses 2.80
a) Internal Plastered vertical surface 16.52
2nd- 3rd floor 4th- 8TH floor
2 1 1 6.25 On axis C b/N 2'-4 5 1 1 6.45 On axis C b/N 2'-4
2.80 2.80
35.00 90.3
2 -1 1 2.80 Deduction 5 -1 1 2.80 Deduction
1.20 D-6 1.20 D-6
-6.72 -16.8
2 -1 1 1.50 W-12 5 -1 1 1.50 W-12
0.80 0.80
-2.4 -6.00
2 1 1 5.92 On axis 2' b/N C-D 5 1 1 6.02 On axis 2' b/N C-D
3.02 3.02
35.76 90.9
2 -1 1 2.80 Deduction 5 -1 1 2.80 Deduction
1.20 D-6 1.20 D-6
-6.72 -16.8
2 1 1 6.25 On axis D b/N 2'-4 5 1 1 6.45 On axis D b/N 2'-4
2.80 2.80
35.00 90.3
2 -1 1 2.80 Deduction 5 -1 1 2.80 Deduction
1.20 D-6 1.20 D-6
-6.72 -16.8
2 -1 1 2.80 Deduction 5 -1 1 2.80 Deduction
1.20 D-7 1.20 D-7
-6.72 -16.8

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

5 1 1 5.77 On axis 4 b/N B'-D' 5 1 1 0.25 ON AXIS 4 & D'


2.80 2.80
80.78 3.5
5 -1 1 2.69 Deduction 5 1 1 0.20
2.80 WD-2 0.20

-37.66 0.2
5 1 1 3.10 On axis D'/4-5 5 1 1 0.55 On axis 5 C'-D'
2.80 2.80
43.4 7.7
5 -1 1 3.30 Deduction 5 1 1 0.40
0.50 W-4 0.20
-8.25 0.4
5 1 1 5.54 On axis 5 b/N B'-D' 98.72 m² Total item
2.80 656.02 m² Total item of 7.16A
77.56 b) Plastered Soffit
5 -1 1 2.69 Deduction lobby
1.80 W-2 6 1 1 5.92 on Axis 2'-4, C-D

-24.21 6.60
5 -1 1 1.55 W-4' 234.43 on Axis 4-5, C-D
0.80 7 1 1 2.69
-6.2 3.55
5 1 1 0.70 Around duct 66.85
2.80 7 1 1 0.53
9.8 1.14
5 1 1 2.95 on axis 4 c'-d' 4.23 305.51 m³
2.80 7 1 1 0.55 On axis 5 C'-D'
41.3 Around roof level lift shaft area 2.80
1 1 1 5.54 On axis 5 b/N B'-D' 10.78
2.80 7 1 1 0.40
15.51 0.20
1 -1 1 2.69 Deduction 0.56
1.80 W-2 1 1 1 8.44 at roof level
-4.84 3.55
1 -1 1 1.55 W-4' 29.96
0.80 Deduction For Columns
-1.24 2nd- 3rd Floor
1 1 1 5.84 on axis 4 c'-d' 2 -2 1 0.35 On axis 3 b/N C-D
2.80 0.60
16.35 -0.84
1 1 1 3.10 On axis D'/4-5 2 -1 1 0.05 On axis 5 b/N B'-D'
2.80 0.05
8.68 -0.01
1 -1 1 3.30 Deduction 2 -1 1 0.35 On axis 5 D'
0.50 W-4 0.35
-1.65 -0.25
1 1 1 1.25 Around roof level lift shaft area 4th - roof level floor
2.80 5 -2 1 0.15 On axis 3 b/N C-D
3.5 0.40
36.31 m² -0.6
557.30 m² 6 -1 1 0.05 On axis 5 b/N B'-D'
Exposed Columns 0.05
Second- Third Floor -0.02
2 2 1 2.80 ON AXIS 3 C & D 6 -1 1 0.15 On axis 5 D'
2.80 0.15
31.36 -0.14
2 2 1 1.30 Balcony
0.20 7 1 1 4.43 On Axis 4 b/n A-B'
1.04 1.10
2 1 1 0.45 ON AXIS 4 & D' 34.11
2.80 7 1 1 4.43 On Axis 4 b/n D'-E
2.52 1.10
2 1 1 0.40 34.11
0.20 Exposed beam
0.16 7 1 1 6.85 SECOND- Eigth Floor
2 1 1 0.95 On axis 5 C'-D' 0.22 FB -9 On Axis C b/n 2'-4
2.80 10.55
5.32 7 1 1 6.85 FB - 10 On Axis D b/n 2'-4
2 1 1 0.80 0.22

0.20 10.55

5.40 FB - 3 On Axis 3 b/n C-D


0.32 7 1 1
Fourth- Eigth Floor 0.69
5 2 1 1.60 ON AXIS 3 C & D 26.08
2.80 7 1 1 5.97 FB - 5 On Axis 4 b/n C-D
44.8 0.22
5 2 1 0.70 9.19
0.20 7 1 1 2.69 FB - 5 On Axis 4 b/n C-D
1.4 0.25
4.71

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

7 1 1 5.64 FB - 5 On Axis 4 b/n C-D Finishing for Lobby and Corridor at


0.34 Shops
13.42 a) Internal Plastered vertical surface
7 1 1 3.10 FB - 13 On Axis C' b/n 4-5 BASEMENT FLOOR (RAMP
0.93 RETAINING)
20.18 1 1 1 14.30 On axis G b/n 2-5
7 1 1 3.10 FB - 11 On Axis D' b/n 4-5 3.33
0.34 47.619
7.38 1 1 1 8.85
7 1 1 7.04 FB - 6 On Axis 5 b/n B'-D' 1.14
0.34 10.089
16.76
1 1 1 8.19 WATER TANKER LEVEL
0.34 RB -12 On Axis 4 b/n B'-D'
2.78

1 1 1 3.30 RB -13 On Axis B' b/n 4-5


0.34
1.12 1 1 1 5.43 On axis 2 b/n G-F
1 1 1 3.30 RB -14 On Axis C' b/n 4-5 2.80
0.93 15.204
3.07 1 1 1 5.30 On axis 2 b/n E-F
1 1 1 3.30 RB -15 On Axis D' b/n 4-5 2.80
0.34 14.84 30.044
1.12 Grnd FLOOR
1 1 1 8.04 RB -11 On Axis 5 b/n B'-D' 1 1 1 10.80 On axis 1 b/n C-E
0.34 2.80
2.73 30.24
Balcony @ roof level 1 1 1 4.20 On axis 2 b/n A-B
1 1 1 4.43 On Axis 4 b/n A-B' 2.80
1.10 11.76
4.87 1 -1 1 4.20 Deduction
1 1 1 4.43 On Axis 4 b/n D'-E 1.80 W-1
1.10 -7.56
4.87 1 1 1 2.20 On axis 2 b/n B-C
main stair case 2.80
ground-8th Floor 6.16
10 1 1 2.40 SECTION A-A 1 -1 1 1.10 Deduction
1.03 sofit 1.80 W-11
24.72 -1.98
10 1 1 1.03 Landing 1 1 1 1 10.43 On axis 2 b/n E-G

1.27 2.80
13.08 29.204
10 1 1 2.40 side 1 2 1 10.80 On axis 3 b/n D-F
0.22 2.80
5.28 60.48
10 7 0.5 0.29 Riser side 1 1 1 7.54 On axis 4 b/n B'-D'
0.15 2.80
1.52 21.112
SECTION B-B 1 1 1 5.64
10 1 1 1.93 sofit 2.80
1.03 15.792
19.88 1 1 1 6.74 On axis 5 b/n B'-D'
10 1 1 1.27 Landing 1 2.80
1.03 18.872
13.08 1 -1 1 2.40 Deduction
10 1 1 1.93 side 1.80 W-4
0.22 -4.32
4.25 1 1 1 1.40 On axis A b/n 2-4
10 7 0.5 0.29 Riser side 2.80
0.15 3.92
1.52 1 1 2 4.39 b/n axis C & 2-3
SECTION C-C 2.80

10 1 1 2.00 sofit 24.584


1.15 1 1 2 13.33 On axis D b/N 1-4
23 2.80
10 1 1 2.00 side 74.648
0.22 1 1 1 3.10 On axis D' b/N 4-5
4.4 2.80
10 5 0.5 0.29 Riser side 8.68
0.15 1 -1 1 2.40 Deduction
1.09 0.80 W-4'
664.37 m² Total to item of 7.16 B -1.92

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 2 1 8.80 On axis E b/n 1-4 1 1 1 0.50


2.80 2.80
49.28 1.4
1 2 1 4.40 On axis F b/n 3-4 FIRST FLOOR
2.80 1 1 1 10.80 On axis 1 b/n C-E

24.64 2.80
1 1 1 13.10 On axis G b/n 2-4 30.24
2.80 1 1 1 4.20 On axis 2 b/n A-B
36.68 2.80
1 1 1 5.23 On Axis B-B' & 2-3 11.76
3.02 toilet area 1 -1 1 4.20 Deduction
15.7946 1.80 W-1
1 1 1 2.85 On Axis C b/n 4-5 -7.56
3.02 duct area 1 1 1 2.20 On axis 2 b/n B-C
8.607 2.80
1 1 1 1.55 6.16
2.80 1 -1 1 1.10 Deduction
4.34 1.80 W-11
Exposed Columns -1.98
1 1 1 2.45 On axis 1 b/n C-E 1 2 1 5.40 On axis 3 b/n E-F
2.80 2.80
6.86 30.24
1 1 1 0.54 1 1 1 3.65
2.80 2.80
1.512 10.22
1 1 1 6.05 On axis 2 b/n A-G 1 1 1 8.07 On axis 4 b/n B'-D'
2.80 2.80
16.94 22.596
1 1 1 0.95 1 1 1 5.67
2.80 2.80
2.66 15.876
1 1 1 6.09 On axis 3 b/n A-G 1 1 1 6.74 On axis 5 b/n B'-D'
2.80 2.80
17.052 18.872
1 1 1 1.20 1 -1 1 2.40 Deduction
2.80 1.80 W-4
3.36 -4.32
1 1 1 7.05 On axis 4 b/n A-G 1 -1 1 2.59
2.80 1.80 W-2
19.74 -4.662
1 1 1 2.97 1 1 1 1.40 On axis A b/n 2-4
2.80 2.80

8.316 3.92
1 1 1 2.30 On axis 5 b/n A-G 1 2 1 3.21 On axis B b/n 3-4
2.80 2.80
6.44 17.976
1 1 1 1.10 1 2 1 4.39 b/n axis C & 2-3
2.80 2.80
3.08 24.584
1 2 1 5.15 b/n axis C - D & 3-4
3.00
30.9

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 2 1 8.57 b/n axis D & 1-3 1 1 1 0.25


2.80 2.80
47.992 0.7
7 1 1 3.10 On axis D' b/N 4-5 984.42 m² Total item 7.16 a
2.80 b) Plastered Soffit

Ceilling gypsum plastering


60.76
1 -1 1 3.10 Deduction GROUND FLOOR
1.50 W-4 Solid Slab
-4.65 1 1 1 5.93 B/ N Axis 4-5 & A-B
1 2 1 2.17 b/n axis E & 2-3 3.45
2.80 20.44
12.152 1 1 1 4.25 B/ N Axis B-B' & 4-5
1 1 1 1.40 On axis F b/n 2-4 3.45
2.80 14.66
3.92 1 1 1 2.91 B/ N Axis C-C' & 4-5
1 1 2 5.23 On Axis B-B' & 2-3 1.08
3.00 toilet area 3.14
31.38 1 1 1 3.22
1 1 1 2.85 On Axis C b/n 4-5 1.09
3.02 duct area 3.51
8.607 1 1 1 3.00
1 1 1 1.55 1.28
2.80 3.84
4.34 1 1 1 4.46 B/ N Axis D'-E & 4-5
Exposed Columns 3.45
1 1 1 2.45 On axis 1 b/n C-E 15.37
2.80 1 1 1 5.93 B/ N Axis E-F & 4-5
6.86 3.45
1 1 1 0.54 20.44
2.80 1 1 1 12.70 B/ N Axis F-G & 2-5
1.512 5.08
1 1 1 5.60 On axis 2 b/n A-F 64.52
3.00 1 1 1 5.76 B/ N Axis B-C & 5-6
16.8 3.60
1 1 1 0.80 20.72
2.80 1 1 1 3.60 B/ N Axis C-D & 5-6
2.24 6.00
1 1 1 5.64 On axis 3 b/n A-F 21.6
2.80 1 1 1 5.74 B/ N Axis D-E & 5-6
15.792 3.54
1 1 1 1.05 20.32 208.56
2.80 Ribbed Slab

2.94 1 1 1 5.87 B/N axis 1-2' & C-D


1 1 1 5.15 On axis 4 b/n A-F 7.10 SHOP 2
2.80 41.68
14.42 1 1 1 2.17
1 1 1 1.80 5.80
2.80 12.59
5.04 1 1 1 5.86 B/N axis 1-3 & D-E
1 1 1 0.85 On axis 5 b/n B'-D' 7.10 SHOP 3
2.80 41.61
2.38

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 1 1 5.75 1 1 1 2.85
4.46 2.33
25.62 6.64
1 1 1 5.85 B/N axis 2-4 & A-B 1 1 1 1.70
4.84 SHOP 1 2.60

28.31 4.42
1 1 1 5.10 Exposed beam
4.47 Internal
22.8 1 1 1 10.80 ON XIS 1-(C-E)
1 1 1 4.95 B/N axis 3-4 & E-F 0.22 FB-1
5.75 SHOP 4 2.38
28.46 Bottom
1 1 1 4.95 B/N axis 3-4 & D-E 1 1 1 10.80 ON XIS 1-(C-E)
5.93 SHOP 5 0.05 FB-1
29.35 0.54
1 1 1 3.99 B/N axis 3-4 & C-D Internal
4.76 SHOP 6 1 1 1 10.55 ON AXIS-2 (A-C)
18.99 0.22 FB-2
CORRIDOR 2.32
FOR GROUND FLOOR 1 2 1 10.80 ON AXIS-2 (C-E)
1 1 1 5.92 B/n axis 2-3 & C-D 0.22 FB-2
2.40 4.75
14.21 1 1 1 5.40 ON AXIS-2 (E-F)
1 1 1 1.68 B/n axis 3-4 & C-D 0.22 FB-2
4.80 1.19
8.04 1 1 1 5.03 ON AXIS-2 (F-G)
1 1 1 7.34 Entrance lobby 0.22 FB-2
4.81 B/n axis 3-4 & B-C 1.11
35.27 Bottom
Ramp 1 1 1 8.65 ON AXIS-2 (A-C)
1 1 1 4.88 B/n axis 2-3 & E-F 0.25 FB-2
12.95 2.16
63.2 1 1 1 10.80 ON AXIS-2 (C-E)
VERENDA 0.25 FB-2
1 1 1 3.35 B/N axis 4-5 & A-C 2.7
10.63 1 1 1 10.43 ON AXIS-2 (E-G)
35.61 0.05 FB-2
1 1 1 3.35 B/N axis 4-5 & D'-F 0.52
10.63 Internal
35.61 1 2 1 31.78 ON AXIS -3 (A-G)
1 1 1 17.45 B/N axis 5-6 & B-E 0.22 FB-3
3.60 13.98

62.82 1 2 1 5.03 ON AXIS -3 (A-G)


Toilet 0.22 FB-3
1 1 1 1.40 B/N axis 2-3 & A'-B 2.21
4.48 Bottom
6.28 1 1 1 17.83 ON AXIS -3 (A-G)
1 1 1 1.00 B/N axis 2-3 & B-B' 0.25 FB-3
2.75 4.46
2.75 1 1 1 13.95 ON AXIS -3 (A-G)
0.05 FB-3
0.7

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal 1 1 1 13.10 ON AXIS G -(5-2 )


1 1 1 9.68 ON AXIS 4-(A-B') 0.22 FB-8
0.22 FB-4 2.88
2.13 Internal
bottom 1 2 1 4.40 ON AXIS F -(3-2 )

9.68
1 1 1 ON AXIS 4-(A-B') 0.22 FB-8
0.25 FB-4 1.94
2.42 1 2 1 8.10 ON AXIS F -(3-5 )
Internal 0.22 FB-8
1 2 1 5.44 ON AXIS 4 -(C'-D') 3.56
0.22 FB-5 Bottom
2.39 1 1 1 10.40 ON AXIS A-(5-2 )
1 2 1 9.68 ON AXIS 4 -(D'-G) 0.25 FB-8
0.22 FB-5 2.6
4.26 1 1 1 1.40 ON AXIS A-(5-2 )
1 2 1 5.03 ON AXIS 4 -(D'-G) 0.05 FB-8
0.22 FB-5 0.07
2.21 1 1 1 7.80 ON AXIS F - (5-2 )
bottom 0.25 FB-8
1 1 1 14.71 ON AXIS 4 -(D'-G) 1.95
0.25 FB-5 1 1 1 4.40 ON AXIS F - (5-2 )
3.68 0.05 FB-8
1 1 1 5.44 ON AXIS 4 -(D'-G) 0.22
0.05 FB-5 1 1 1 11.70 ON AXIS G-(5-2 )
0.27 0.25 FB-8
Internal 2.93
1 1 1 29.88 ON AXIS 5 - (A-G) 1 1 1 1.40 ON AXIS G-(5-2 )
0.22 FB-6 0.05 FB-8
6.57 0.07
1 1 1 9.01 ON AXIS 5 - (A-G) Internal
0.22 FB-6 1 2 1 8.35 ON AXIS B -(4-2)
1.98 0.22 FB-9
bottom 3.67
1 1 1 30.93 ON AXIS 5 - (A-G) 1 2 1 3.40 ON AXIS B -(5-4)
0.25 FB-6 0.22 FB-9
7.73 1.5
1 1 1 3.35 ON AXIS 5 - (A-G) 1 2 1 6.95 ON AXIS B -(6-4)
0.05 FB-6 0.22 FB-9
0.17 3.06 11.75
Internal Bottom
1 1 1 17.53 ON AXIS 6 -(B-E ) 1 1 1 15.30 ON AXIS B -(6-2)
0.22 FB-7 0.25 FB-9

3.86 3.83
Bottom Internal
1 1 1 17.53 ON AXIS 6 -(B-E ) 1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.25 FB-7 0.50 FB-10
4.38 2.47
Internal Bottom
1 1 1 12.20 ON AXIS A -(5-2 ) 1 1 1 4.93 ON AXIS b/n B-C & 2-3
0.22 FB-8 0.05 FB-10
2.68 0.25

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Internal 1 1 2 3.55 ON AXIS E-(5-6)


1 1 1 6.40 ON AXIS C -(1-2) 0.22 FB-14
0.22 FB-11 1.56
1.41 Bottom
1 2 1 4.39 ON AXIS C -(3-2) 1 1 1 13.35 ON AXIS E-(1-2 & 4-6)

0.22 FB-11 0.25 FB-14


1.93 3.34
1 2 1 4.76 ON AXIS C -(3-4) 1 1 1 8.80 ON AXIS E-(2-4)
0.22 FB-11 0.05 FB-14
2.09 0.44
Bottom Internal
1 1 1 11.16 ON AXIS C -(1-2 & 3-4) 1 1 2 6.65 ON AXIS D' - (6 -4)
0.25 FB-11 0.22 FB-15
2.79 2.93
1 1 1 4.40 ON AXIS C -(2-3) Bottom
0.05 FB-11 1 1 1 6.65 ON AXIS D' - (6 -4)
0.22 0.25 FB-15
Internal 1.66
1 2 2 6.75 b/n axis C-D and D-E & (2-1) 1 1 1 3.10 ON AXIS D' - (6 -4)
0.22 FB-12 0.05 FB-15
5.94 0.16
Bottom Internal
1 2 1 6.75 b/n axis C-D and D-E & (2-1) 1 1 2 3.40 ON AXIS C' (5-4)
0.25 FB-12 0.22 FB-16
3.38 1.5
Internal Bottom
1 1 2 15.55 ON AXIS D -(4-1) 1 1 1 3.40 ON AXIS C' (5-4)
0.22 FB-13 0.25 FB-16
6.84 0.85
Bottom Internal
1 1 1 2.22 ON AXIS D -(4-1) 1 1 2 3.55 ON AXIS C ( 6-5)
0.25 FB-13 0.22 FB-17
0.56 1.56
1 1 1 13.33 ON AXIS D -(4-1) Bottom
0.05 FB-13 1 1 1 3.55 ON AXIS C( 6-5)
0.67 0.25 FB-17
Internal 0.89
1 1 1 21.70 ON AXIS E-(6-1) Internal
0.22 FB-14 1 1 2 1.25 ON AXIS C (5-4)
4.77 0.22 FB-18
Internal 0.55
1 1 1 6.40 ON AXIS E-(1-2) Internal

0.22 FB-14 1 1 1 1.25 ON AXIS C (5-4)


1.41 0.05 FB-18
1 1 2 8.80 ON AXIS E-(2-4) 0.06
0.22 FB-14 Deduct for Columns contact Areas
3.87 Ground Floor
1 1 2 3.40 ON AXIS E-(4-5) 1 20 -1 0.35
0.22 FB-14 0.35
1.5 -2.45

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1 16 -1 0.05 1 1 1 1.93 lobby


0.05 7.93 B/n axis 3-4 & B-C'
-0.04 15.3
First Floor Toilet
Solid Slab 1 1 1 1.40 B/N axis 2-3 & A'-B

5.95 ON Axis 1 B/N C-D


1 1 1 4.48
0.85 6.28
5.06 1 1 1 1.00 B/N axis 2-3 & B-B'
1 2 1 4.43 ON Axis 4 B/N A'-B' & D'-E 2.75
1.20 2.75
10.63 1 1 1 2.85
1 1 1 3.45 ON Axis 4-5 B/N B'-C' 2.33
2.69 6.64
9.28 1 1 1 1.70
1 1 1 1.14 ON Axis 4-5 B/N B'-C' 2.60
0.53 4.42
0.6 Exposed beam
Ribbed Slab Internal
1 1 1 5.78 B/N axis 1-2' & C-D 1 1 1 10.60 ON AXIS 1-(C-E)
6.80 SHOP 7 0.22 FB-1
39.27 2.33
1 1 1 5.78 1 1 1 5.20 ON AXIS 1-(C-D)
2.15 0.22 FB-1
12.42 1.14
1 1 1 5.78 B/N axis 1-2' & D-E Bottom
6.80 SHOP 8 1 1 1 9.20 ON AXIS 1-(C-E)
39.27 0.25 FB-1
1 1 1 5.78 2.3
2.15 1 1 1 1.31 ON AXIS 1-(C-E)
12.42 0.05 FB-1
1 1 1 4.47 B/N axis 2-4 & A-B 0.07
4.98 Café & Restaurant #1 Internal
22.24 1 1 1 16.20 ON AXIS-2 (A-F)
1 1 1 5.78 0.22 FB-2
4.84 3.56
27.95 1 2 1 10.80
1 1 1 5.67 B/N axis 2-3 & E-F 0.22
4.90 SHOP 9 4.75
27.78 Bottom
1 1 1 8.13 B/N axis 3-4 & B-C' 1 1 1 14.57 ON AXIS-2 (A-F)
2.91 SHOP 10 0.25 FB-2
23.66 3.64

1 1 1 4.84 B/N axis 3-4 & C'-F 1 1 1 7.38


15.10 Café & Restaurant #2 0.05
73.06 0.37
CORRIDOR Internal
1 1 1 5.78 B/n axis 2-3 & D-E 1 1 2 27.00 ON AXIS 3 (A-F)
2.37 0.22 FB-3
13.66 11.88
1 1 1 5.85 B/n axis 2-3 & C-D
2.37
13.84

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Bottom Bottom
1 1 1 11.64 ON AXIS 3 (A-F) 1 2 1 4.10 ON AXIS A & F (4-2 )
0.25 FB-3 0.25 FB-7
2.91 2.05
1 1 1 10.70 ON AXIS 3 (A-F) 1 2 1 4.30 ON AXIS A & F (4-2 )

0.05 FB-3 0.05 FB-7


0.54 0.43
1 1 1 4.36 ON AXIS 3 (A-F) Internal
0.15 FB-3 1 1 2 8.70 ON AXIS B -(4-2 )
0.65 0.22 FB-8
Internal 3.83
1 1 1 9.68 ON AXIS 4-(A-B') Bottom
0.22 FB-4 1 1 1 4.40 ON AXIS B -(4-2 )
2.13 m² 0.05 FB-8
Bottom 0.22
1 1 1 7.28 ON AXIS 4-(A-B') 1 1 1 4.40 ON AXIS B -(4-2 )
0.25 FB-4 0.25 FB-8
1.82 1.1
1 1 1 2.19 ON AXIS 4-(A-B') Internal
0.05 FB-4 1 1 1 14.75 ON AXIS C (4-1)
0.11 0.22 FB-9
Internal 3.25
1 1 1 14.92 ON AXIS 4 -(C-F) 1 1 1 8.85
0.22 FB-5 0.22
3.28 1.95
1 1 1 5.64 ON AXIS 4 -(C-F) Bottom
0.22 FB-5 1 1 1 3.71 ON AXIS C (4-1)
1.24 0.05 FB-9
Bottom 0.19
1 1 1 9.80 ON AXIS 4 -(C-F) 1 1 1 9.09 ON AXIS C (4-1)
0.25 FB-5 0.25 FB-9
2.45 2.27
1 1 1 5.13 ON AXIS 4 -(C-F) Internal
0.05 FB-5 1 1 1 6.40 ON AXIS E (4-1)
0.26 0.22 FB-9
Internal 1.41
1 1 1 7.54 ON AXIS -5 (B'-D') 1 2 1 8.70
0.22 FB-6 0.22
1.66 3.83
Bottom Bottom
1 1 1 4.99 ON AXIS -5 (B'-D') 1 1 1 8.20 ON AXIS E (4-1)
0.25 FB-6 0.25 FB-9

1.25 2.05
1 1 1 2.55 ON AXIS -5 (B'-D') 1 1 1 6.70 ON AXIS E (4-1)
0.05 FB-6 0.05 FB-9
0.13 0.34
Internal Internal
1 2 1 8.80 ON AXIS A & F (4-2 ) 1 1 2 15.55 ON AXIS D -(4-1)
0.22 FB-7 0.22 FB-10
3.87 6.84

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Bottom Bottom
1 1 1 7.95 ON AXIS D -(4-1) 1 1 1 3.10 ON AXIS C' (5-4)
0.05 FB-10 0.25 FB-13
0.4 0.78
1 1 1 2.05 ON AXIS D -(4-1)

Deduct for Columns contact Areas


0.15 FB-10
0.31 1 21 -1 0.35 1st-Floor
1 1 1 4.65 ON AXIS D -(4-1) 0.35
0.25 FB-10 -2.57
1.16 1 2 -1 0.05
Internal 0.05
1 1 2 6.75 Beam around C-D b/n 1-2 -0.01
0.22 SHOP STAIR
2.97 Ground floor
Bottom SECTION E-E
1 1 1 5.26 Beam around C-D b/n 1-2 1 1 1 3.75 sofit
0.25 1.05
1.32 3.94
1 1 1 0.85 1 1 1 3.75 Side Flight
0.15 0.22
0.13 0.83
Internal 1 11 0.5 0.30 Riser side
1 1 2 6.75 Beam around D-E b/n 1-2 0.15
0.22 0.25
2.97 SECTION F-F
Bottom 1 1 1 3.30 Side Flight
1 1 1 6.65 Beam around D-E b/n 1-2 0.22
0.25 0.73
1.66 1 11 0.5 0.30 Riser side
Internal 0.15
1 1 1 3.10 ON AXIS D' (5-4) 0.25
0.22 FB-11 1 1 1 3.30 sofit
0.68 1.05
Bottom 3.47
1 1 1 3.10 ON AXIS D' (5-4) 1 1 1 1.99 Landing 1
0.25 FB-11 2.20
0.78 4.38
Internal 1 1 1 0.06 side Landing
1 1 1 1.25 ON AXIS B' (5-4) 0.22
0.22 FB-12 0.01 13.86
0.28 1372.73 m² Total item 7.16b
Bottom

1 1 1 1.25 ON AXIS B' (5-4)


0.05 FB-12
0.06
Internal
1 1 1 3.10 ON AXIS C' (5-4)
0.22 FB-13
0.68
1 1 1 3.10 ON AXIS C' (5-4)
0.22 FB-13
0.68

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

9. PAINTING Deduction
Apply kadisco or equivalent type
Quartz paint to external plaster wall
Surface according to complete
GROUND FLOOR 1 -1 1 4.20 W1
manufacturing instruction
1 1 1 13.80 On axis 1 b/n C-E 1.80
3.30 -7.56
45.54 1 -1 1 2.75 TW-2

12.00 On axis 2 b/n A-B'


1 1 1 0.80
3.30 -2.2
39.6 1 -1 1 1.10 W-11
Deduction 1.80
1 -1 1 4.20 W1 -1.98
1.80 1 1 1 6.00 On axis 2 b/n E-F
-7.56 3.30
1 -1 1 2.75 TW-2 19.8
0.80 Deduction
-2.2 1 -1 1 5.40 WD4
1 -1 1 1.10 W-11 2.80
1.80 -15.12
-1.98 1 1 1 21.50 On axis 4 b/n A-B' & D'-F
On axis 2 b/n E-G 3.30
1 1 1 11.33 70.95
3.30 1 -2 1 5.40 Deduction
37.389 2.80 WD4'
1 1 1 10.60 On axis A b/n 2-4 -30.24
3.30 1 -1 1 4.24 Deduction
34.98 2.80 WD-8
1 -1 1 7.40 Deduct WD-6 -11.872
2.80 1 -1 1 4.28 Deduction
-20.72 2.80 WD-9
1 1 2 7.00 On axis C & E b/n 1-2 -11.984
3.30 1 1 1 8.84
46.2 3.30 On axis 5 b/n B'-D'
1 -1 2 6.40 Deduct open area 29.172
2.80
-35.84 1 -1 1 2.40 Deduction
1 1 1 14.30 On axisd G b/n 2-4 0.80 W-4
3.30 -1.92
47.19 1 -1 1 2.59 W-2
1 2 -1 4.50 DDT TW-5 1.80
0.80 -4.662
-7.2 1 1 2 10.60 On axis A & F b/n 2-4
1 1 -1 2.70 DDT TW-6 3.30

0.80 69.96
-2.16 Deduction
FIRST FLOOR 1 -1 2 7.40 WD-6
1 1 1 12.60 On axis 1 b/n C-E 2.80
3.30 -41.44
41.58 1 1 2 3.70 On axis B' & D' b/n 4-5
1 1 1 12.00 On axis 2 b/n A-B' 3.30
3.30 24.42
39.6

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Deduction 1 1 1 0.80 On Axis 2 ,F-G


1 -1 1 3.10 W-4 0.60
0.50 0.48
-1.55 INTERNAL
1 1 2 7.00 On axis C & E b/n 1-2 1 1 1 3.30 On Axis A, 4-5

3.30 0.60
46.2 1.98
Deduction 1 1 1 0.40 On Axis A, 4-5
1 -1 2 6.40 WD-7 0.40
2.80 0.16
-35.84 1 1 1 5.10 On Axis 5 , A-B
Around Terrace 0.60
External 3.06
1 1 1 3.30 On Axis A, 4-5 1 1 1 1.20 On Axis 5 , A-B
0.60 0.40
1.98 0.48
1 1 1 0.40 On Axis A, 4-5 1 1 2 3.31 On Axis B & E ,5-6
0.60 0.60
0.24 3.972
1 1 1 5.10 On Axis 5 , A-B 1 1 2 0.80 On Axis B & E ,5-6
0.60 0.40
3.06 0.64
1 1 1 1.20 On Axis 5 , A-B 1 1 1 15.60 On Axis 6 ,B-E
0.60 0.60
0.72 9.36
1 1 2 3.31 On Axis B & E ,5-6 1 1 1 2.40 On Axis 6 ,B-E
0.60 0.40
3.972 0.96
1 1 2 0.80 On Axis B & E ,5-6 1 1 1 9.93 On Axis 5 ,E-G
0.60 0.60
0.96 5.958
1 1 1 15.60 On Axis 6 ,B-E 1 1 1 1.80 On Axis 5 ,E-G
0.80 0.40
12.48 0.72
1 1 1 2.40 On Axis 6 ,B-E 1 1 1 12.00 On Axis G ,2-5
0.60 0.60
1.44 7.2
1 1 1 9.93 On Axis 5 ,E-G 1 1 1 2.00 On Axis G ,2-5
0.80 0.40
7.944 0.8
1 1 1 1.80 On Axis 5 ,E-G 1 1 1 4.63 On Axis 2 ,F-G
0.60 0.60

1.08 2.778
1 1 1 12.00 On Axis G ,2-5 1 1 1 0.80 On Axis 2 ,F-G
0.80 0.40
9.6 0.32 38.39 m²
1 1 1 2.00 On Axis G ,2-5 Second- eighth Floor
0.60 7 1 1 6.55 On axis 1' b/n C-D
1.2 3.30
1 1 1 4.63 On Axis 2 ,F-G 151.305
0.80
3.704

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

Deduction 7 1 1 5.03 On Axis 4 b/n D'-E


7 -1 2 0.80 TW-3 0.80 BALCONY
0.60 28.168
-6.72 7 1 1 8.84 On axis 5 b/n B'-D'
7 1 1 6.00 On axis 1 b/n D-E 3.30

3.30 204.204
138.6 Deduction
Deduction 7 -1 1 2.59 W-2
7 -1 2 2.00 W-5 1.80
1.80 -32.634
-50.40 m² 7 -1 1 2.40 W-4'
7 1 1 12.00 On axis 2 b/n A-C 0.80
3.30 -13.44
277.20 m² 7 1 1 10.60 On axis A b/n 2-4
Deduction 3.30
7 -1 1 0.80 W-8 244.86
1.80 Deduction
-10.08 7 -1 1 2.90 W-7
7 -1 1 2.00 W-5 1.80
1.80 -36.54
-25.2 7 -2 1 0.60 TW-3
7 -1 1 0.60 TW-3 0.80
0.80 -6.72
-3.36 7 1 1 3.70 On axis B' b/n 4-5
7 -1 1 1.10 W-11 3.30
1.80 85.47
-13.86 7 1 1 6.25 b/n axis C & 1-2
7 1 1 6.00 On axis 2 b/n E-F 3.30
3.30 144.375
138.6 Deduction
7 -1 1 0.80 Deduction 7 -1 1 1.95 W-10
1.80 W-8 1.80
-10.08 -24.57
7 1 1 21.76 On axis 4 b/n A-F 7 -1 1 1.85 W-9
3.30 1.80
502.656 -23.31
Deduction 7 2 1 1.40 On Axis C & E 1-2
7 -1 2 2.00 W-5 0.80 Balcony
1.80 15.68
-50.4 7 1 1 3.70 On axis D' b/n 4-5
7 -1 2 1.80 WD-16 3.30
2.80 85.47

-70.56 Deduction
7 -1 2 1.43 WD-17 7 -1 1 3.10 W-4
2.80 0.50
-56.056 -10.85
7 -1 2 2.03 W-6 7 1 1 5.20 On axis E b/n 1-2
1.80 3.30
-51.156 120.12
7 1 1 4.83 On Axis 4 b/n A-B' 7 -1 1 2.00 Deduction
0.80 BALCONY 1.80 W-5
27.048 -25.2

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

7 1 1 10.60 On axis F b/n 2-4 7 1 1 1.40 Internal


3.30 0.60 On Axis E b/n 1-2

100.80 m²
244.86 5.88
Deduction Concrete Gutter
7 -1 1 2.90 W-7 1 1 1 0.84 on Axis A-C/1'-2'

22.55
1.80
-36.54 18.942
7 -2 1 0.60 TW-3 on Axis D'-F/1-4
0.80 1 1 1 0.84
-6.72 35.98
Above Top tie Beam 30.2232 1085.63
1 1 1 10.68 On axis 4 b/n A-B' Total item 9.01
2.00
21.36
1 1 0.5 12.60 On axis 1 b/N C-E
2.00 Ground floor remaing parts
12.6 1 1 1 3.20 Coln On Axis A,3,4,5
1 2 0.5 5.00 On axis F b/n 2-4 3.30
2.00 10.56
10 1 1 2 6.20 Beam On axisd C&E
1 1 0.5 10.60 On axis A b/n 2-4 0.50 b/n 1-2
2.00 6.2
10.6 54.56 m² 1 1 1 24.33 Beam On axis 6 b/n& B-E&
1 1 1 7.54 WATER TANKER 0.25 Axis B&E b/n 5-6 Bottom part
4.25 FRONT ELEVATION 6.0825
32.045 On axis 5 b/n B'-D' 1 1 1 16.25 Beam On axis 5 b/n A-B&
1 -1 1 2.59 Deduction 0.25 E-G Bottom part
1.80 W-2 4.0625
-4.662 1 1 1 10.80 Beam On axisd A b/n 2-5
1 -1 1 2.40 W-4 0.25
0.80 2.7
-1.92 1 1 1 2.40 Coln On axis B5,E5&5F
1 1 1 3.10 RIGHT SIDE ELEVATION 2.80
4.25 On axis D', 4-5 6.72
13.175 1 1 4 0.90 Coln On axis B6,C6,D6&E6
1 1 1 3.30 LEFT SIDE ELEVATION 2.80
4.25 On axis B', 4-5 10.08 At Window Eges
14.025 52.663 W1
Balcony 1 1 1 7.8 L=4.2+1.8*2=7.8
7 1 1 4.83 Internal 0.1 w=0.1m
0.60 On Axis 4 b/n A-B' 0.78
20.286 1 1 1 4.7 W-11
Internal 0.1 L=1.1+1.8*2=4.7

7 1 1 5.03 On Axis 4 b/n D'-E 0.47


0.60 1 1 1 4.35 TW-2
21.126 0.1 L=2.75+0.8*2=4.35
Internal 0.435
7 1 1 1.40 On Axis C b/n 1-2 TW-4
0.60 1 1 1 7
5.88 0.1
0.7 TW-5
1 3 1 6.1 L=4.5+0.8*2=6.1
0.1
______________ ______________ ______________
Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

1.83 1 8 1 6.29 W-2


1 1 1 4.35 TW-6 0.10 L=2.69+1.8*2=6.29
0.1 L=2.75+0.8*2=4.35 5.032
0.435 First Floor window ege W-4'
1 1 1 4.35 TW-2 1 8 1 5.15 L=1.55+1.8*2=5.15
0.10 L=2.75+0.8*2=4.35 0.10
0.435 4.12 w-4
1 1 1 67.26 Terrace beam 1 8 1 6.70 L=3.1+1.8*2=6.7
0.50 0.10
33.63 5.36
W-11
1 1 1 4.70 L=1.1+1.8*2=4.7
0.10
0.47 W-1
1 1 1 7.80 L=4.2+1.8*2=7.8 2677.02 m² Total item 9.01
0.10 Apply three coats of approved type
Finishing for Lobby
plastic emulsion paintand
to Corridor at
0.78
Residential Houses
1 1 1 6.19 W-2 a) Internal Plastered vertical surface
0.10 L=2.59+1.8*2=6.19 2nd- 3rd floor
0.619 2 1 1 6.25 On axis C b/N 2'-4
1 1 1 3.15 W-4 2.80
0.10 L=1.55+1.8*2=3.15 35.00
0.315 2 -1 1 2.80 Deduction
3.15 W-4' 1.20 D-6
1 1 1 0.10 L=1.55+1.8*2=3.15 -6.72
0.315 Second -Eight Floor window ege 2 -1 1 1.50 W-12
1 7 2 4.40 At window edges 0.80

W-8
0.10 -2.40
6.16 L=0.8+1.8*2=4.4 2 1 1 6.02 On axis 2' b/N C-D
1 7 6 5.60 W-5 3.00
0.10 L=2+1.8*2=5.6 36.12
23.52 2 -1 1 2.80 Deduction
1 7 7 2.20 TW-3 1.20 D-6
0.10 L=0.6+0.8*2=2.2 -6.72
10.78 2 1 1 6.25 On axis D b/N 2'-4
1 7 1 4.70 W-11 2.80
0.10 L=1.1+1.8*2=4.7 35.00
3.29 w-7 2 -1 1 2.80 Deduction
1 7 2 6.50 L=2.9+1.8*2=6.5 1.20 D-6
0.10 -6.72
9.1 2 -1 1 2.80 Deduction
1 7 2 5.63 W-6 1.20 D-7
0.10 L=2.03+1.8*2=5.63 -6.72
7.882 2 1 1 5.81 On axis 4 b/N B'-D'
1 7 1 5.45 W-9 2.80
0.10 L=1.85+1.8*2=5.45 32.54
3.815 2 1 1 5.64
1 1 1 5.55 W-10 2.80
0.10 L=1.95+1.8*2=5.55 31.58
0.555 2 -2 1 2.69 Deduction
1 7 2 7.4 At WD edges 2.80 WD-2
0.1 WD-16 -30.13
10.36 L=1.8+2.8*2=7.4 2 1 1 3.10 On axis D'/4-5
1 7 2 7.03 WD-17 2.80
0.1 L=1.43+2.8*2=7.03 17.36
9.842

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 -1 1 3.10 Deduction 1 -1 1 2.69 Deduction( first floor)\


0.50 W-4 1.80 W-2
-3.1 -4.84
2 1 1 5.34 On axis 5 b/N B'-D' 2 1 1 0.70 Around duct
2.80 2.80
29.9 3.92

2 -1 1 2.69 Deduction 1 -1 1 2.69 Deduction( ground floor)\


1.80 W-2 2.80 W-2
-9.68 -7.53
2 1 1 0.70 Around duct
2.80 518.42 m² Total item 9.02a
3.92 B) exposed beams, columns
4th- 8TH floor and Staircases
5 1 1 6.45 On axis C b/N 2'-4 Intermediate & Top Tie beam
2.80 2 1 2 5.40 Second- Third floor
90.3 0.22 Internal
5 -1 1 2.80 Deduction 4.75 ON AXIS 3 -(C-D)
1.20 D-6 FB-3
-16.8 2 1 1 5.40 Bottom
5 -1 1 1.50 W-12 0.25 ON AXIS 3 -(C-D)
0.80 2.7 FB-3
-6
5 1 1 6.02 On axis 2' b/N C-D 2 1 1 5.64 Internal

3.00 0.22 ON AXIS 4 -(C-D')


90.3 2.48 FB-5
5 -1 1 2.90 Deduction 2 1 1 4.75
1.20 D-6 0.22
-17.4 2.09
5 1 1 6.45 On axis D b/N 2'-4 2 1 1 2.95 Bottom
2.80 0.05 ON AXIS 4 -(C-D')
90.3 0.3 FB-5
5 -1 1 2.80 Deduction 2 1 1 2.69
1.20 D-6 0.25
-16.8 1.35
5 -1 1 2.80 Deduction 2 1 1 5.34 Internal
1.20 D-7 0.22 ON AXIS 5-(B'-D')
-16.8 2.35
5 1 1 5.81 On axis 4 b/N B'-D' 2 1 1 5.34 Bottom
2.80 0.05 ON AXIS 5-(B'-D')
81.34 0.53
5 1 1 5.64 2 1 1 5.09
2.80 0.10
78.96 1.02
5 -2 1 2.69 Deduction 2 1 1 6.25 Internal
2.80 WD-2 0.22 ON AXIS C (4-2')
-75.32 2.75 FB-9
5 1 1 3.10 On axis D'/4-5 2 1 1 3.56 Bottom
2.80 0.05 ON AXIS C (4-1)
43.4 0.36 FB-9
5 -1 1 3.30 Deduction
0.50 W-4
-8.25
5 1 1 5.54 On axis 5 b/N B'-D'
2.80
77.56
5 -1 1 2.69 Deduction
1.80 W-2
-24.21
5 1 1 0.70 Around duct
2.80

9.80
2 1 1 5.64 ground - first
2.80
31.58
2 1 1 3.10 On axis D'/4-5
2.80
17.36
2 -1 1 3.30 Deduction
0.50 W-4
-3.30
2 1 1 5.54 On axis 5 b/N B'-D'
2.80
31.02

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

2 1 1 1.20 4 1 1 1.20 WD-6

0.10 0.10
0.24 0.48
2 1 1 1.49 W-12 4 1 1 1.49 W-12
0.10 0.10
0.3 0.6
2 1 1 6.25 Internal 4 1 1 6.45 Internal
0.22 ON AXIS D -(4-2') 0.22 ON AXIS D -(4-2')
2.75 FB-10 5.68 FB-10
2 1 1 3.85 Bottom 4 1 1 4.05 Bottom
0.05 ON AXIS D -(4-1) 0.05 ON AXIS D -(4-1)
0.39 FB-10 0.81 FB-10
2 1 1 2.40 4 1 1 2.40
0.10 0.10
0.48 0.96
4TH- 7th floor TOP TIE BEAM @ top of 8th floor
4 1 2 5.80 Internal 1 1 1 5.59 Internal
0.22 ON AXIS 3 -(C-D) 0.22 ON AXIS 4 -(C-D')
10.21 FB-3 1.23 RB-5
1 1 1 4.69
4 1 1 5.80 Bottom 0.22
0.25 ON AXIS 3 -(C-D) 1.03
5.8 FB-3 1 1 1 2.69 Bottom
0.25 ON AXIS 4 -(C-D')
4 1 1 5.84 Internal 0.67 RB-5
0.22 ON AXIS 4 -(C-D') 1 1 1 5.21
5.14 FB-5 0.05
4 1 1 4.75 0.26
0.22 Internal
4.18 1 1 1 6.45 ON AXIS C (4-2')
4 1 1 3.15 Bottom 0.22 RB-8
0.05 ON AXIS 4 -(C-D') 1.42 Bottom
0.63 FB-5 ON AXIS C (4-2')
4 1 1 2.89 1 1 1 2.69 RB-8
0.25 0.10
2.89 0.27 Internal
4 1 1 5.54 Internal 1 1 1 6.45 ON AXIS D (4-2')
0.22 ON AXIS 5-(B'-D') 0.22 RB-8

4.88 1.42
4 1 1 5.54 Bottom Bottom
0.05 ON AXIS 5-(B'-D') 1 1 1 2.40 ON AXIS D (4-2')
1.11 0.10 RB-8
4 1 1 5.09 0.24
0.10 1 1 1 4.05
2.04 0.05 Internal
4 1 1 6.45 Internal 0.2 ON AXIS C-D (5-4)
0.22 ON AXIS C (4-2') 1 1 2 3.45 RB-1
5.68 FB-9 0.22
4 1 1 3.76 Bottom 1.52 Bottom
0.05 ON AXIS C (4-2')
0.75 FB-9

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

ON AXIS C-D (5-4) 2 1 1 0.80


1 1 1 3.45 RB-1 0.20
0.25 0.32
0.86 Internal Fourth- Eigth Floor
ON AXIS 4-5 (B'-D') 5 2 1 1.60 ON AXIS 3 C & D
1 1 1 3.10 RB-9 2.80
0.22 44.8
0.68 Bottom 5 2 1 0.70
ON AXIS 4-5 (B'-D') 0.20
1 1 1 3.10 RB-9 1.4
0.05 5 1 1 0.25 ON AXIS 4 & D'

0.16 2.80
1 1 1 5.59 Internal 3.5
0.22 ON AXIS 5 (B'-D') 5 1 1 0.20
1.23 0.20
1 1 1 5.09 Bottom 0.2
0.25 ON AXIS 5 (B'-D') 5 1 1 0.55 On axis 5 C'-D'
1.27 2.80
1 1 1 0.50 7.7
0.05 5 1 1 0.40
0.03 0.20
89.17 m² Sub total (m ) to item
2
0.4
EXPOSED COLUMNS 109.36 m² Sub total (m2) to item
A) Elevation columns main stair case
Ground floor Ground-8th Floor
1 1 1 0.60 On axis 6 b/n B-E 9 1 1 2.40 SECTION A-A
2.80 1.03 sofit
1.68 22.25
1 1 1 1.60 ON AXIS 4 & 5, C' & D 9 1 1 1.03 Landing 1
2.80 1.27
4.48 11.77
1 1 1 1.60 FIRST FLOOR 9 1 1 2.40 side
2.80 ON AXIS 4 & 5, C' & D 0.22
4.48 4.75
Second- Third Floor 9 7 0.5 0.29 Riser side
2 2 1 2.80 ON AXIS 3 C & D 0.15
2.80 1.37
31.36 SECTION B-B
2 2 1 1.30 9 1 1 1.93 sofit
0.20 1.03

1.04 17.89
2 1 1 0.45 ON AXIS 4 & D' 9 1 1 1.27 Landing 1
2.80 1.03
2.52 11.77
2 1 1 0.40 9 1 1 1.93 side
0.20 0.22
0.16 3.82
2 1 1 0.95 On axis 5 C'-D' 9 7 0.5 0.29 Riser side
2.80 0.15
5.32 1.37

______________ ______________ ______________


Contractor Consultant Client
Takeoff Sheet
Project:- SHDE Housing Dev't Project Contractor. __ Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- 16____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Payment No._final payment_

Ite.

Ite.
x Dim. Qty Description x Dim. Qty Description

SECTION C-C Exposed beam


9 1 1 2.00 sofit 7 1 1 6.85 SECOND- Eigth Floor
1.15 0.22 FB -9 On Axis C b/n 2'-4

20.7 10.55
9 1 1 2.00 side 7 1 1 6.85 FB - 10 On Axis D b/n 2'-4
0.22 0.22
3.96 10.55
1 5 0.5 0.29 Riser side 7 1 1 5.40 FB - 3 On Axis 3 b/n C-D
0.15 0.69
0.11 26.08
99.76 m² Sub total (m2) to item 7 1 1 5.97 FB - 5 On Axis 4 b/n C-D
0.22
9.19
b) Plastered Soffit 7 1 1 2.69 FB - 5 On Axis 4 b/n C-D
lobby 0.25
6 1 1 5.92 on Axis 2'-4, C-D 4.71
6.60 7 1 1 5.64 FB - 5 On Axis 4 b/n C-D
234.43 on Axis 4-5, C-D 0.34
7 1 1 2.69 13.42
3.55 7 1 1 3.10 FB - 13 On Axis C' b/n 4-5
66.85 0.93
7 1 1 0.53 20.18
1.14 7 1 1 3.10 FB - 11 On Axis D' b/n 4-5
4.23 305.51 m³ 0.34
7 1 1 0.55 On axis 5 C'-D' 7.38
2.80 7 1 1 7.04 FB - 6 On Axis 5 b/n B'-D'
10.78 0.34
7 1 1 0.40 16.76
0.20 463.77 m² Sub total (m2) to item
0.56 Total Item to Exposed Soffit, Beam &
762.06 m²
1 1 1 8.44 at roof level Column
3.55 C. Internal Lift wall and Retaining Wall
29.96 1 1 0.5 2.30 Ground Floor
Deduction For Columns 3.30 On Axis B'/4-5
2nd- 3rd Floor 3.80
2 -2 1 0.35 On axis 3 b/N C-D 1 1 0.5 2.60 On Axis 4/B-C'
0.60 3.30
-0.84 4.29
2 -1 1 0.05 On axis 5 b/N B'-D'
0.05 First Floor

-0.01 1 1 0.5 2.60 On Axis 4/B-C'


2 -1 1 0.35 On axis 5 D' 3.30
0.35 4.29
-0.25
4th - Roof level floor 2nd-7th floor
5 -2 1 0.15 On axis 3 b/N C-D 1 1 0.5 2.40 On Axis 4/B-C'
0.40 3.30
-0.6 3.96
6 -1 1 0.05 On axis 5 b/N B'-D'
0.05 16.34 m² Total Item to 9.02.C
-0.02
6 -1 1 0.15 On axis 5 D'
0.15
-0.14

______________ ______________ ______________


Contractor Consultant Client
Project:- Saving Houses B+G+8 Typology Revision
Client:- Addis Ababa Saving Houses Development Enterprise
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC
Item No Description Unit Contract QTY Contract Amount Executed Qty

A-SUB STRUCTURE
1. EXCAVATION AND EARTH WORK
1.01 Clear and remove top soil to an average depth of 200mm. 1,226.45 12,105.06 975.61
M2
Bulk excavation in ordinary soil to a depth not exceeding 1500mm
1.02 1,796.52 123,169.41 1,300.42
from reduced level. M3
Ditto to Item 1.02 but to a depth 1500mm from reduced level but not
1.03 1,616.61 127,890.02 1,264.33
exceeding 3000mm. M3
Ditto to Item 1.03 but to a depth 3000mm from reduced level but not
1.04 1,441.50 128,898.93 1,228.69
exceeding 4500mm. M3
Ditto to Item 1.03 but to a depth 4500mm from reduced level but not
1.05 1,133.41 105,962.50 702.71
exceeding 6000mm. M3
Ditto to Item 1.03 but to a depth 6000mm from reduced level but not
1.06 200.00 21,332.00 650.52
exceeding 7500mm. M3
Pit excavation in ordinary soil to a depth not exceeding 1500mm
1.07 29.04 1,728.17 29.04
from reduced ground level. M3
Ditto to Item 1.07 but to a depth 1500mm from reduced level but not
1.08 29.04 2,699.27 29.04
exceeding 3000mm. M3
Trench excavation in ordinary soil to a depth not exceeding 1500mm
1.09 46.38 2,760.07 ###
from reduced ground level. M3
Excavation in soft rock
Bulk excavation for mat in soft rock to reduced level, depth
1.10 - ###
exceeding 3000mm but not exceeding 4500mm. M3
1.11 Ditto but exceeding 4500mm but not exceeding 6000mm. M3 - ###
1.12 Ditto but exceeding 6000mm but not exceeding 7500mm. M3 - ###
1.13 Ditto but exceeding 7500mm but not exceeding 9000mm. M3 - ###
Excavation in hard rock - ###
Bulk excavation for mat in soft rock to reduced level, depth up to
1.14 - ###
1500mm. M3
1.15 Ditto but exceeding 1500mm but not exceeding 3000mm. M 3
- ###
1.16 Ditto but exceeding 3000mm but not exceeding 4500mm. M3 - ###
1.17 Ditto but exceeding 4500mm but not exceeding 6000mm. M3 - ###
1.18 Ditto but exceeding 6000mm but not exceeding 7500mm. M3 - ###
Excavation in boulders
1.19 Boulder excavation with entity bigger than 5m 3. M3 - ###
Fill around retaining wall with selected material from site and
1.20 700.00 39,081.00 -
compact in layers not exceeding 200mm thick. M3

Fill around retaining wall with selected material from quarry waste
1.21 950.00 103,360.00 -
and compact in layers not exceeding 200mm thick.
M3

Fill around isoleted footing with selected material from quarry


1.22 53.10 5,777.28 41.44
waste and compact in layers not exceeding 200mm thick.
M3

Fill around Masonary wall with selected material from quarry


1.23 23.19 2,523.07 ###
waste and compact in layers not exceeding 200mm thick.
M3
Backfill under mat foundation with non expansive selected material
from quary compacted thickness should not be more than 20cm and
1.24 720.12 153,212.73 347.92
the field density should attain 95% of the maximum dry density
according to AASHTO T-180. M3
1.25 Ditto to Item 1.16 but under hard rock. M3 51.40 5,592.32 59.34
1.26 Ditto to Item 1.17 but under strip footing. M3 29.87 3,249.86 24.82
Fill under mat foundation with selected material from site waste
1.27 1.00 58.76
and compact in layers not exceeding 200mm thick. M3
Cart away surplus excavated materials from the site as per the
1.28 6,591.41 419,081.85 4,792.05
Engineer's instruction and direction. M3
250mm thick basaltic stone hardcore well rolled, consolidated and
1.29 191.31 19,081.26 213.36
blinded with crushed stone. M2
TOTAL CARRIED TO SUMMARY ......................... 16,830.35 1,277,563.56 ###
2. CONCRETE WORK
50mm lean concrete quality C-5, with minimum cement content of
2.01 -
150 kg/m3, of concrete:
a) Under footing pad M2 12.96 718.89 12.96
b) Under mat slab M2 620.52 34,420.24 640.17
c) Under strip footing M2 53.79 2,983.73 48.06
d) Under masonry wall M2 23.25 1,289.68
e) Under basement floor slab M2 128.49 7,127.34 128.49
f) under ground floor slab M2 62.82 3,484.63 62.46
g) under grade beam M2 15.00 832.05 8.23

192
Reinforced concrete quality C-25, 360 kg of cement/m 3 filled in to
2.02 form work and vibrated around rod reinforcement (Formwork and
reinforcement measured separately)
a) In footing pad M3 2.89 2,987.94 2.89
b) In 1100mm thick mat slab M3 707.23 731,198.02 729.58
c) in strip footing. M3 12.10 12,510.07 12.02
d) In 150mm thick basement slab M2 128.49 19,926.23 131.65
e) In foundation column M3 1.44 1,488.80 0.79
f) In basement column M3 47.20 48,799.61 49.97
g) In shear wall M3 11.11 11,486.52 12.90
h) In retaining wall M3 113.56 117,408.55 115.14
i) In grade beam M3 27.80 28,742.14 25.18
j) In ramp beam M3 5.37 5,551.99 4.12
k) In 160mm thick ground floor slab M2 690.23 114,177.85 537.14
l) In 180mm thick ground floor slab M2 -
m) In 100mm thick ground floor slab M2 81.45 8,421.12 62.46
n) In 200mm thick ramp slab M2 99.68 20,611.83 96.17
o) In 150mm thick ramp slab M2 17.58 2,726.31
p) In stair case M3 6.70 6,927.06 -
Provide, cut and fix in position sawn structural wood or steel
2.03
formwork which ever is appropriate.
a) In footing pad M2 6.80 775.61 6.80
b) In 1100mm thick mat slab M2 128.08 14,608.80 128.08
c) in strip footing. M2 24.29 2,770.52 22.86
e) In foundation column M2 19.20 2,189.95 10.47
f) In basement column M2 300.80 34,309.25 289.14
g) In shear wall M2 81.23 9,265.09 92.99
h) In retaining wall M2 905.36 103,265.36 912.36
i) In grade beam M2 216.43 24,686.01 215.21
j) In ramp beam M2 39.46 4,500.81 41.14
k) In ground floor slab M2 601.25 68,578.58 555.54
m) In ramp slab M2 99.68 11,369.50 95.00
o) In stair case M2 30.79 3,511.91 17.08
Mild steel reinforcement according to structural drawings. Price
2.04 includes cutting, bending, placing in position and tying wire and
concrete spacers.
a) Dia 6 mm plain bar Kg - -
b) Dia 8 mm deformed bar kg 3,437.64 17,463.21 10,012.49
c) Dia 10 mm deformed bar kg 11,740.34 59,640.93 11,129.33
d) Dia 12 mm deformed bar kg 5,968.75 25,307.50 3,941.50
e) Dia 14 mm deformed bar kg 3,668.77 15,555.58 5,408.65
f) Dia 16 mm deformed bar kg 20,298.16 86,064.20 25,838.36
g) Dia 20 mm deformed bar kg 35,408.60 150,132.46 24,009.03
h) Dia 24 mm deformed bar kg 8,222.84 34,864.84 -
10mm thick and 100mm high Styrofoam expansion joint between
2.05 56.50 1,130.00 56.50
ground slab and grade beam. Ml
TOTAL CARRIED TO SUMMARY ......................... 94,124.63 1,853,810.70 ###
3. MASONRY WORK

500mm thick hard trachytic roughly dressed stone masonry


3.01 9.38 6,457.19
foundation wall below ground level bedded in cement mortar (1:3)
M3
3.02 Ditto but exposed part above ground level. M3 3.13 2,397.52
TOTAL CARRIED TO SUMMARY ......................... 12.51 8,854.71 ###
TOTAL A ......................... 110,967.49 3,140,228.97 ###
B-SUPER STRUCTURE
1. CONCRETE WORK

Reinforced concrete quality C-25, 360 kg of cement/m3 filled in to


1.01 form work and vibrated around rod reinforcement (Formwork and
reinforcement measured separately)

a) In elevation columns M3 143.62 166,972.61 194.49


b) In floors and top tie beams M3 240.12 279,163.51 249.28
c) In staircase and landing M3 28.58 33,227.11 27.41
d) In RC shear wall for lift shaft M3 65.10 75,685.26 61.85
e) In RC gutter M3 7.02 8,161.45 6.84
f) In150mm thick floor slab M2 214.30 37,371.78 ###
Roof slab M2 - 27.87
g) In160mm thick floor slab M2 202.49 37,667.19 459.25
h) Extra 6cm volume slab for bathroom areas. M3 10.63 12,358.44 11.23

i) Concrete fillers around columns & beam connection at floor levels 15.23 17,706.40 4.54
M3
Reinforced Concrete Quality C-30, 400 Kg of Cement filled in to
1.02 form work and vibrated around rod reinforcement (formwork ###
measured separately)
a) In Roof Beams m3 32.59 39,466.49 ###
b) In Roof & terrace slabs m3 15.00 18,165.00 ###

193
Ribbed slab for suspended floor slab made of 60 mm thick concrete
slab in C-25,60x240 mm one way concrete girder with c/c spacing of
1.03 400mm including 200x400x240mm hollow concrete ribbed block 3,263.33 1,168,892.17 2,886.31
and all according to the detail structural drawing.
M2
Provide, cut and fix in position structural wood or steel formwork
1.04
appropriately.
a) In elevation columns M2 1,157.36 132,008.48 1,368.80
b) In floors and top tie beams M2 1,662.39 229,825.42 1,446.63
c) In staircase and landing M2 322.42 44,574.57 185.89
d) In RC shear wall for lift shaft M2 505.84 69,932.38 508.94
e) In RC gutter M2 100.18 13,849.89 98.57
f) In floor slab M2 405.36 46,235.36 453.33
g) In roof & terrace slab M2 40.00 4,562.40 27.87
h) roof beam M2 217.02 24,753.30 173.26

i) Concrete fillers around columns & beam connection at floor levels 38.95 5,384.84 65.71
M2
Pre-cast element (PB1) to the size of 2940x120x80mm made of
1.05 0.027m3 of concrete in C-25/ beam. Price include transportation and 352.00 8,423.36 320.00
placing in position according to structural detail drawing. Pcs
Pre-cast element (PB2) to the size of 5030x120x80mm made of
1.06 0.048m3 of concrete in C-25/ beam. Price include transportation and 800.00 32,184.00 795.00
placing in position according to structural detail drawing. Pcs
Pre-cast element (PB2') to the size of 3450x120x80mm made of
1.07 0.033m3 of concrete in C-25/ beam. Price include transportation and -
placing in position according to structural detail drawing. Pcs
Pre-cast element (PB3) to the size of 4960x120x80mm made of
1.08 0.048m3 of concrete in C-25/ beam. Price include transportation and -
placing in position according to structural detail drawing. Pcs
Mild steel reinforcement according to structural drawings. Price
1.09 includes cutting, bending, placing in position and tying wire and -
concrete spacers.
a) Dia 6 mm plain bar Kg 2,090.57 10,620.10 5,207.79
b) Dia 8 mm deformed bar kg 19,089.36 96,973.95 14,748.96
c) Dia 10 mm deformed bar kg 12,356.36 54,491.55 10,926.73
d) Dia 12 mm deformed bar kg 10,186.63 44,923.04 8,793.40
e) Dia 14 mm deformed bar kg 7,328.28 32,317.71 10,613.67
f) Dia 16 mm deformed bar kg 15,045.72 66,351.63 13,487.96
g) Dia 20 mm deformed bar kg 15,281.92 67,393.27 15,057.61
h) Dia 24 mm deformed bar kg 1,126.19 4,966.50 1,078.71
TOTAL CARRIED TO SUMMARY ......................... 92,344.56 2,884,609.13 ###
2. BLOCK WORK
20cm thick Class B external HCB wall which can satisfy the designed
2.01 strength, bedded in cement mortar (1:3). Price shall include mortar 2,514.35 144,298.55 3,053.21
bedding. M2
2.02 Ditto as item 2.01 but for 100mm HCB wall. M2 2,493.70 131,916.73 2,169.86
TOTAL CARRIED TO SUMMARY ......................... 5,008.05 276,215.28 ###
Supply and 3. ROOFING ANDwater
fix toch applied WATER PROOFING
proofing WORK
membrane of 4mm thick
which passes (ASTM D6222) and granular finish for roof water
proofing system(minimum slope 1/20), flexible to 0 degree
reinforced with polyster non-woven fabric which satisfys minimum
tensile strength requirement(unit weight 4kg/m2) and the reverse is
faced with polyethylene film to ease installation works. The unit
price includes the cost of finishing(knotting) material as per
3.01 manufacturer`s instruction, primer, and other related works like M2 40.00 13,684.40 71.14
cleaning of ll dirt, trace, of grease, oil and loose particles as per
manufacturere instruction. The supplier shall give construction
guarantee for the works & installation shall be done by technically
qualified person. The method of application shall comply with the
requirement of manufacturer`s instruction. All the insatallation shall
satisfy BS standard(EN 13707) for roofs. Price includes all incidental
works there
Supply and to.apply cementitious damp proofing material strictly
following manufacturer`s instruction. Special attention shall be
given or material shall conform to the quality requirements of BS of
other equivalent instituitions. The supplier shall give construction
3.02 warranty for the works & application shall be done by technically -
qualified person. The method of application shall comply with the
requirement of manufacturer`s instruction. The supplier shall
submit product with recommended shelf life. Price includes all
incidental works there to. The application shall be made to:
a) all upper wet rooms m2 200.00 46,308.00 456.21
b) concrete retaining wall to the height of NGL m2 450.00 104,193.00 349.68
d) lift shaft internal wall m2 42.00 9,724.68 ###
e)sump well m2 136.00 31,489.44 ###
f) cafeteria terrace m2 201.00 46,539.54 226.05
Average 70mm thick light weight concrete in mix (1:2:5) cement,
pumice and sand laid over RC roof slab with proper slope towards
3.03 40.00 572.00 71.19
down pipe and corners angled at 45 0 at parapet and roof slab
connection as shown on the detail drawing. M2
Apply 30 mm thick smooth finished cement sand screed laid on top
3.04 of light weight concrete area in mortar mix (1:3) with proper slope 40.01 1,979.69 71.14
towards down pipe. M2

194
Supply & fix approved quality pre-coated EGA 500 mm or
equivalent roof cover Fixed on steel purlin. Price shall include G-28
galvanized flat metal sheet roof ridge, valley gutter & flushing
3.05 412.34 72,641.94 417.02
works as per the detail drawing and all the necessary materials and
accessories needed to complete the work. Roof measured in
horizontal projection (with out addition for slopes & laps). M2
Supply & fix approved quality G-28 galvanized flat metal sheet
a
gutter dev. length 67cm. ml - 51.83
Supply and fix steel roof truss & purlin complex as per the structural
design. The price includes all the angle iron pieces, connection bolts,
3.06 - ###
plates & accessories for fixing purlins & roof structure connection
need plates for strengthening.
40x40x2.5 RHS Truss Member (40X40X3mm) KG 712.53 24,297.27 926.84
30x30x2.5 RHS Truss Member KG 362.33 12,355.45 426.26
80x80x3 RHS Purlin Member (30x30x2mm) KG 1,033.19 35,231.78 2,402.85
30x30x2 RHS Purlin Member KG 719.16 24,523.36
80x80x3 RHS Purlin Member KG -
70x50x3 RHS Purlin Member KG -

40x30x5 angle cleat plate used for connection of purlin with truss -
pcs
25x25x8 plate for the connection of truss with concrete pcs -
dia 20 J-bolt for connection of truss with concrete beam/column or
pcs -
truss
Supply and fix Ø110 PVC down pipe including elbows and other
3.07 296.45 6,818.35 326.70
necessary materials and accessories to complete the work.
Ml
TOTAL CARRIED TO SUMMARY ......................... 4,685.01 430,358.90 ###
5. CARPENTRY AND JOINERY -
Flush Wooden Doors -
All according to drawing -
Supply and fix 34mm thick patterned MDF panels on both sides
with ASSA Or equivalent locks,hinges & handles that comply
EN/ASTM standard & shall be approved by the designer prior to
fixing. The door frame shall be out of solid Austrralia pine and
5.01 thetransome made of solidwooden frame with 4mmthick frosted
glass according to the detaildrawing&window door schedule. The
toilet door shall be painted with water resistance oil paint to a height
of 30cm from base.price also includes providing door stopper and all
the necessary accessories and transportation.
Type D6size = 1200x 2950mm Pcs 24.78 105,525.63 24.78
Type D6 size = 1200x 2750mm Pcs 69.30 295,114.05 69.30
Type D4 size = 700x 2950mm Pcs 57.82 246,226.40 57.82
Type D5 size = 800x 2950mm Pcs 66.08 281,401.68 66.08
Plastic Celling 40.46
TOTAL CARRIED TO SUMMARY ......................... 217.98 928,267.76 ###
6. Plastering & Pointing
6.01 Apply two coats of plastering in cement mortar (1.3)
a) To all internal wall surfaces, M2 7,632.26 547,538.33 7,888.50
b) To external wall surfaces, M2 1,804.53 150,588.03 2,438.29
c) To Suspended slab & stair case M2 720.68 51,701.58 3,637.98
d) To exposed beams, columns & stair case M2 2,524.84 210,697.90 1,671.59
e) To exposed lift wall and retaining wall M2 452.80 32,483.87 283.84
f) To all internal wall to receive ceramic wall tile, M2 1,086.30 77,931.16 820.56
g) To all lift shaft shear wall to receive ceramic wall tile, M2 109.92 7,885.66 54.58
TOTAL CARRIED TO SUMMARY ......................... 14,331.33 1,078,826.54 ###
7.FINISHING
50mm thick cement sand screed smoothly finished flooring in
7.01 748.93 37,888.37 1,895.04
mortar mix (1:3) at basement garage. M2
280x30mm Terrazo window sill cut to appropriate size, weathered
and mounted on & including 30mm thick cement mortar (1:3)
7.02 339.47 81,876.77 424.99
bedding. Price includes bullnosing and making water drip as
shown on the detail drawing. Ml
b) Ditto as item a but, for Terrazzo copping on verendah, balcony &
- 88.76
roof parapet of size 180*30mm. Ml
Marble flooring to stair case bedded on and including cement sand
mortar mix 1:3 and joints grouted in appropriate color filler setting
7.03 ###
coat mortar. Pattern and color of the tile shall be approved by the
Architect.
20mm thick to landing. M2 42.51 54,671.26 32.86
- Tread size 30x340mm M2 292.38 428,982.86 83.00
- Riser size 20x10mm M2 315.83 390,928.06 47.91
Supply and fix 200x150x6 mm white glazed Ceramic wall tiles stuck
7.04 to wall with cement mortar mix (1:2) backing and 2 mm joints to be 936.31 70,934.85 840.85
grouted in white cement. M2
7.05 Ditto but for lift shaft ( granite wall ) M2 49.92 90,298.29 51.60
100mm thick precast concrete pavement in concrete class C-15
around the building open jointed on and including 400mm selected
7.06 122.39 8,898.98 123.76
material compacted fill and 100mm thick redash or equivalent
bedding material. M2
Apply 42mm thick cement screed in 1:3 cement mortar ratio to
7.07 427.23 22,446.66 1,053.11
receive porceline ceramic tile. M2

195
Supply and fix 8mm thick non slippery porcelain ceramic floor
tiles. Price includes tiles, adhesives glue, cross spacers, sealant, and
7.08 1,212.54 66,992.83 1,053.11
all accessories. Size, pattern, quality and color shall be approved by
the architect. M 2

Supply and fix 10cm high porcelain skirting - 327.67


Supply and fix 8mm thick non slippery ceramic floor tiles. Price
includes tiles, adhesives glue, cross spacers, sealant, and all
- 546.87
accessories. Size, pattern, quality and color shall be approved by the
architect.
7.09 Supply and fix 10cm high ceramic skirting Ml 514.27 14,157.85 465.36

Supply and fix 20mm thick marble floor tiles. Price shall include
7.10 438.98 564,563.40 540.91
cement screed, mirror polishing and all necessary works.
M2
7.11 Supply and fix 10cm high Marble skirting Ml 397.54 68,917.53 285.37
20mm thick white Terrazo tile bull nosed marble window sill
7.12 bedded on cement mortar (1:3) ratio. Price shall include cement 309.47 14,950.50 10.08
screed, mirror polishing and all necessary works. Ml
Ditto but 30x3cm marble threshold bedded on cement mortar (1:3)
7.13 ratio. Price shall include cement screed, mirror polishing and all 363.56 467,567.24 ###
necessary works. Ml
Supply and fix 2mm thick PVC floor finish with appropriate
7.14 -
adhesive. M2
7.15 Suppy and fix 10cm high PVC skirting. Ml -
7.16 Gypsum Plastering to:
Finishing for Lobby and Corridor at Residential Houses
(All materials shall be supplied by the contractor)
a) Internal Plastered vertical surface m2 808.52 16,954.66 656.02
b) Plastered Soffit m2 1,468.54 30,795.28 664.37
c) wall surface m2 3,213.30 67,382.90 ###
Finishing for Lobby and Corridor at Shops
(All materials shall be supplied by the contractor)
a) Internal Plastered vertical surface m2 244.30 5,122.97 984.42
b) Plastered Soffit m2 1,468.54 30,795.28 1,372.73
c) wall surface m2 486.69 10,205.89
7.17 Apply fine coat cement plaster to -
Basment floors
a) Plastered Vertical Surface m2 133.16 2,663.20
b) Plastered Soffit m2 751.21 15,024.20
c) wall surface m2 121.66 2,433.20
7.18 Residential house,toilets,shower & kitchen rooms -
a) To internal wall surface m2 556.15 11,123.00
b) To plastered concrete soffit m2 601.30 12,026.00
TOTAL CARRIED TO SUMMARY ......................... 16,364.70 2,588,602.05 ###
8. GLAZING
Supply and fix 4mm thick clear glass glazing to all curtain walls,
8.01 windows, & doors. Price shall include all structural silicon and 1,215.90 19,454.40
accessories. M2
Supply and fix 4mm thick frosted glass glazing to doors. Price shall
8.02 25.34 405.44
include all structural silicon and accessories. M2
8.03 700X600mm fix to walls bathroom mirror pcs -
TOTAL CARRIED TO SUMMARY ......................... 1,241.24 19,859.84 ###
9. PAINTING
Apply kadisco or equivalent type Quartz paint to external plaster
9.01 wall Surface according to complete manufacturing instruction 5,236.25 836,281.49 2,677.02
M2
application.
9.02 Apply three coats of approved type plastic emulsion paint to ###
a) all internal wall surfaces, M2 7,632.26 170,733.66 518.42
b) exposed beams and columns M2 2,924.84 82,217.25 762.06
c) internal lift wall & retaining wall M2 882.00 24,793.02 16.34
TOTAL CARRIED TO SUMMARY ......................... 16,675.35 1,114,025.42 ###
TOTAL B ..................... 150,868.22 9,320,764.92 ###
TOTAL A + B ..................... 261,835.71 12,460,993.89 ###

196
Steel Reinforcement bar Takeoff Sheet
Summery
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- ____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Production
No. Location Remark
Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Sub Structure
Page 1 - - - - - 3,917.31 8,046.49 -
Page 2 - - - - - 4,048.30 7,441.23 -
Page 3 - - - - - 7,600.97 3,165.95 -
Page 4 - - - 502.61 1,983.20 8,419.16 2,397.92 -
Page 5 - 254.38 - 1,195.25 324.62 269.06 - -
Page 6 - 108.94 - - 215.23 66.76 19.74 -
Page 7 - 207.37 186.58 - 425.08 50.84 39.47 -
Page 8 - 145.99 46.65 - 135.05 157.11 66.12 -
Page 9 - 87.37 - - 168.78 - - -
Page 10 - 112.81 - - 142.43 210.61 - -
Page 11 - 151.37 1,251.82 140.04 44.97 87.16 - -
Page 12 - 903.69 255.28 258.89 - - - -
Page 13 - 1,781.39 - - - - - -
Page 14 - 1,117.29 169.80 172.09 - - - -
Page 15 - 30.89 624.38 643.27 - - - -
Page 16 - 374.10 681.48 - - - - -
Page 17 - 145.77 712.98 - - - - -
Page 18 - 690.56 287.77 145.45 - - - -
Page 19 - 280.39 181.89 - 321.45 397.15 181.57 -
Page 20 - 483.22 - - 135.00 613.92 2,058.46 -
Page 21 - 270.06 330.59 - 1,512.86 - 592.08 -
Page 22 882.35 1,034.59 435.30
Page 23 - 897.05 1,690.65 - - - - -
Page 24 - 705.31 1,318.74 - - - - -
Page 25 - 371.00 2,356.14 173.69 - - - -
Page 26 - 11.15 - 274.92 - - - -
Total Weight Summary (kg) - 10,012.49 11,129.33 3,941.50 5,408.65 25,838.36 24,009.03 - -
Steel Reinforcement bar Takeoff Sheet
Summery
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- ____________________
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Production
No. Location
______________ ______________ ______________ Remark
Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Sub Structure
MAT SLAB
ALONG X - AXIS
CSX5 20 0.11 2.4 1 23 23 12.00 276.00
20 0.11 2.4 1 23 23 2.33 53.59
20 0.11 2.4 1 23 23 2.05 47.15
16 0.11 2.4 1 23 23 12.00 276.00
MSX5 20 0.11 3.5 1 32 32 12.00 384.00
20 0.11 3.5 1 32 32 2.33 74.56
16 0.11 3.5 1 32 32 8.14 260.48
16 0.11 3.5 1 32 32 5.90 188.80
20 0.11 1.05 1 10 10 12.00 120.00
16 0.11 1.05 1 10 10 9.26 92.60
CSX4 20 0.11 3 1 27 27 12.00 324.00
20 0.11 3 1 27 27 12.00 324.00
20 0.11 3 1 27 27 3.75 101.25
16 0.11 3 1 27 27 9.26 250.02
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 12.00 324.00
MSX4 20 0.11 2.5 1 23 23 12.00 276.00
20 0.11 2.5 1 23 23 12.00 276.00
20 0.11 2.5 1 23 23 9.85 226.55
16 0.11 2.5 1 23 23 9.26 212.98
16 0.11 2.5 1 23 23 12.00 276.00
16 0.11 2.5 1 23 23 12.00 276.00
CSX3 20 0.11 2.5 1 23 23 12.00 276.00
20 0.11 2.51 1 23 23 12.00 276.00
20 0.11 2.51 1 23 23 9.85 226.55
Total Length - - - - - 2,480.88 3,261.65 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - - - - 3,917.31 8,046.49 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
16 0.11 2.51 1 23 23 9.26 211.30
16 0.11 2.51 1 23 23 12.00 273.82
16 0.11 2.51 1 23 23 12.00 273.82
MSX3 20 0.11 2.5 1 23 23 12.00 272.73
20 0.11 2.5 1 23 23 12.00 272.73
20 0.11 2.5 1 23 23 9.85 223.86
20 0.11 2.5 1 23 23 5.60 127.27
20 0.11 2.5 1 23 23 5.03 114.32
16 0.11 2.5 1 23 23 9.26 210.45
16 0.11 2.5 1 23 23 12.00 272.73
16 0.11 2.5 1 23 23 12.00 272.73
CSX2 20 0.11 2.18 1 20 20 2.31 45.78
20 0.11 2.18 1 20 20 12.00 237.82
20 0.11 2.18 1 20 20 4.60 91.16
20 0.11 2.18 1 20 20 10.15 201.15
20 0.11 2.2 1 20 20 9.85 197.00
16 0.11 2.18 1 20 20 9.26 183.52
16 0.11 2.18 1 20 20 12.00 237.82
16 0.11 2.18 1 20 20 12.00 237.82
MSX1 20 0.11 1.85 1 17 17 12.00 201.82
20 0.11 1.85 1 17 17 10.53 177.10
20 0.11 1.85 1 17 17 11.00 185.00
20 0.11 1.85 1 17 17 9.85 165.66
20 0.11 1.85 1 17 17 12.00 201.82
16 0.11 1.85 1 17 17 11.18 188.03
16 0.11 1.85 1 17 17 12.00 201.82
CSX1 20 0.11 1.38 1 13 13 12.00 150.55
20 0.11 1.38 1 13 13 12.00 150.55
Total Length - - - - - 2,563.84 3,016.31 -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - - - - 4,048.30 7,441.23 -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
20 0.11 1.38 1 13 13 9.85 128.05
16 0.11 1.38 1 13 13 12.00 156.00
20 0.11 1.38 1 13 13 12.00 156.00
16 0.11 1.38 1 13 13 9.26 120.38
ALONG y - AXIS
CSy1 16 0.11 2.05 1 20 20 5.97 119.40
16 0.11 2.05 1 20 20 12.00 240.00
16 0.11 2.05 1 20 20 12.00 240.00
16 0.11 2.05 1 20 20 5.97 119.40
MSy1 16 0.11 3 1 27 27 5.97 161.19
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 5.97 161.19
CSy2 16 0.11 3 1 27 27 5.97 161.19
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 5.97 161.19
MSy2 16 0.11 3 1 27 27 5.97 161.19
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 5.97 161.19
CSy3 20 0.11 3 1 27 27 12.00 324.00
20 0.11 3 1 27 27 4.28 115.56
20 0.11 3 1 27 27 8.73 235.71
16 0.11 3 1 27 27 8.20 221.40
16 0.11 3 1 27 27 10.81 291.87
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 2.60 70.20
MSy3 20 0.11 3 1 27 27 12.00 324.00
Total Length - - - - - 4,813.79 1,283.32 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - - - - 7,600.97 3,165.95 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 4.62 124.74
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 5.97 161.19
CSy4 20 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 10.81 291.87
16 0.11 3 1 27 27 10.82 292.14
16 0.11 3 1 27 27 12.00 324.00
MSy4 16 0.11 3 1 27 27 10.81 291.87
20 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 10.82 292.14
CSy5 20 0.11 3 1 27 27 12.00 324.00
16 0.11 3 1 27 27 10.82 292.14
16 0.11 3 1 27 27 10.81 291.87
16 0.11 3 1 27 27 12.00 324.00
MSy5 14 0.11 3 1 27 27 12.00 324.00
14 0.11 3 1 27 27 5.83 157.41
14 0.11 3 1 27 27 5.83 157.41
14 0.11 3 1 27 27 12.00 324.00
CSy6 14 0.11 2.05 1 19 19 12.00 228.00
14 0.11 2.05 1 19 19 5.83 110.77
14 0.11 2.05 1 19 19 5.83 110.77
14 0.11 2.05 1 19 19 12.00 228.00
Kebelito 16 1.5 627.21 1 558 558 3.00 1674.00

MAT EDGE
Reinforcement bar
ON AXIS 1' b/n A-C 12 0.11 12.1 1 110 110 2.00 220.00
ON AXIS 1 b/n C-E 12 0.11 12.9 1 117 117 2.00 234.00
ON AXIS 2 b/n E-G 12 0.11 6.12 1 56 56 2.00 112.00
Total Length - - - 566.00 1,640.36 5,331.96 972.00 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - - 502.61 1,983.20 8,419.16 2,397.92 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
ON AXIS 5 b/n A-F 12 0.11 30.9 1 281 281 2.00 562.00
ON AXIS A & G b/n 1'-5 12 0.11 16.7 2 152 304 2.00 608.00
ON AXIS C & Eb/n 1-2 12 0.11 4.85 2 44 88 2.00 176.00
Grade Beam
ON AXIS 2 & 3 b/n A-F
GB-1
TOP BAR 14 2 2 4 10.05 40.20
14 2 2 4 6.65 26.60
14 2 2 4 6.65 26.60
14 2 2 4 10.05 40.20
Negative 14 2 2 4 2.45 9.80
16 2 2 4 4.00 16.00
16 2 2 4 4.00 16.00
16 2 2 4 4.00 16.00
14 2 2 4 4.00 16.00
14 2 2 4 2.45 9.80
BOTTOM BAR 16 2 3 6 6.80 40.80
16 2 3 6 6.80 40.80
16 2 3 6 6.80 40.80
14 2 3 6 6.80 40.80
14 2 3 6 6.80 40.80
STIRRUP 8 0.12 5.4 2 46 92 1.40 128.80
8 0.12 5.4 2 46 92 1.40 128.80
8 0.12 5.4 2 46 92 1.40 128.80
8 0.12 5.4 2 46 92 1.40 128.80
8 0.12 5.4 2 46 92 1.40 128.80
ON AXIS 4 b/n A-B'
GB-2
TOP BAR 14 1 2 2 8.85 17.70
Total Length - 644.00 - 1,346.00 268.50 170.40 - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 254.38 - 1,195.25 324.62 269.06 - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
14 1 2 2 4.00 8.00
Negative 14 1 2 2 2.45 4.90
14 1 2 2 4.00 8.00
14 1 1 1 2.45 2.45
BOTTOM BAR 14 1 3 3 6.80 20.40
14 1 3 3 6.75 20.25
STIRRUP 8 0.15 5.4 1 37 37 1.40 51.80
8 0.15 4.48 1 31 31 1.40 43.40
ON AXIS 4 b/n C-F
GB-3
TOP BAR 16 1 2 2 8.95 17.90
14 1 2 2 10.05 20.10
Negative 16 1 2 2 2.14 4.28
20 1 2 2 4.00 8.00
14 1 1 1 3.62 3.62
BOTTOM BAR 16 1 3 3 6.70 20.10
14 1 3 3 5.70 17.10
14 1 3 3 6.80 20.40
STIRRUP 8 0.12 5.39 1 46 46 1.40 64.40
8 0.12 4.28 1 37 37 1.40 51.80
8 0.12 5.4 1 46 46 1.40 64.40
ON AXIS 6 b/n B-E
GB-4
TOP BAR 14 1 2 2 10.65 21.30
14 1 2 2 9.25 18.50
14 1 1 1 2.45 2.45
14 1 1 1 4.40 4.40
14 1 1 1 4.05 4.05
14 1 1 1 2.10 2.10
Total Length - 275.80 - - 178.02 42.28 8.00 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 108.94 - - 215.23 66.76 19.74 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
14 1 2 2 6.45 12.90
14 1 2 2 7.45 14.90
14 1 2 2 5.30 10.60
STIRRUP 8 0.15 5.75 1 39 39 1.40 54.60
8 0.15 6.82 1 46 46 1.40 64.40
8 0.15 4.63 1 32 32 1.40 44.80
ON AXIS B & E b/n 1-6
GB-5
TOP BAR 14 2 2 4 6.90 27.60
14 2 2 4 10.00 40.00
14 2 2 4 10.55 42.20
Negative 14 2 1 2 2.60 5.20
14 2 1 2 2.90 5.80
14 2 2 4 3.30 13.20
20 2 2 4 4.00 16.00
16 2 2 4 2.80 11.20
BOTTOM BAR 14 2 3 6 8.40 50.40
14 2 3 6 10.60 63.60
14 2 3 6 7.70 46.20
STIRRUP 8 0.12 3.4 2 29 58 1.40 81.20
8 0.12 3.1 2 27 54 1.40 75.60
8 0.12 4.3 2 37 74 1.40 103.60
8 0.12 4.2 2 36 72 1.40 100.80
10 0.12 6.3 4 54 216 1.40 302.40
ON AXIS D b/n 1-4
GB-6
TOP BAR 14 1 2 2 8.45 16.90
16 1 2 2 10.50 21.00
Negative 14 1 1 1 2.10 2.10
Total Length - 525.00 302.40 - 351.60 32.20 16.00 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 207.37 186.58 - 425.08 50.84 39.47 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
14 1 1 1 3.30 3.30
20 1 2 2 3.95 7.90
20 1 2 2 2.75 5.50
BOTTOM BAR 14 1 3 3 5.60 16.80
14 1 3 3 5.70 17.10
16 1 4 4 7.70 30.80
STIRRUP 8 0.12 4.58 1 39 39 1.40 54.60
8 0.12 4.4 1 38 38 1.40 53.20
8 0.12 6.3 1 54 54 1.40 75.60
GB-7
TOP BAR 14 1 2 2 9.15 18.30
BOTTOM BAR 14 1 2 2 8.45 16.90
STIRRUP 8 0.12 3.4 1 29 29 1.40 40.60
8 0.12 3.1 1 27 27 1.40 37.80
ON AXIS C b/n 4-1
GB-8
TOP BAR 16 1 2 2 8.45 16.90
16 1 2 2 10.50 21.00
Negative 14 1 1 1 2.10 2.10
14 1 1 1 3.30 3.30
20 1 2 2 3.95 7.90
20 1 2 2 2.75 5.50
BOTTOM BAR 14 1 3 3 5.60 16.80
14 1 3 3 5.70 17.10
16 1 4 4 7.70 30.80
STIRRUP 8 0.12 4.5 1 39 39 1.40 54.60
8 0.12 4.4 1 38 38 1.40 53.20
10 0.12 6.3 1 54 54 1.40 75.60
ON AXIS F b/n 5-3
Total Length - 369.60 75.60 - 111.70 99.50 26.80 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 145.99 46.65 - 135.05 157.11 66.12 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
GB-9
TOP BAR 14 1 2 2 7.25 14.50
14 1 2 2 3.55 7.10
BOTTOM BAR 14 1 2 2 4.40 8.80
14 1 2 2 5.70 11.40
STIRRUP 8 0.15 3.1 1 22 22 1.40 30.80
8 0.15 4.4 1 30 30 1.40 42.00
ON AXIS C' b/n 5-4
GB-10
TOP BAR 14 1 2 2 4.90 9.80
BOTTOM BAR 14 1 2 2 4.20 8.40
Negative 14 1 1 1 1.70 1.70
STIRRUP 8 0.15 3.63 1 25 25 1.40 35.00
ON AXIS b/n 2-1
GB-11
TOP BAR 14 1 2 2 8.10 16.20
Negative 14 1 1 1 2.80 2.80
14 1 1 1 2.80 2.80
BOTTOM BAR 14 1 3 3 7.40 22.20
STIRRUP 8 0.12 6.75 1 57 57 1.40 79.80
ON AXIS b/n 5-4
GB-12
TOP BAR 14 1 2 2 4.90 9.80
Negative 14 1 1 1 1.70 1.70
BOTTOM BAR 14 1 3 3 4.20 12.60
STIRRUP 8 0.15 3.4 1 24 24 1.40 33.60
ON AXIS b/n 6-5
GB-13
TOP BAR 14 1 2 2 4.90 9.80
Total Length - 221.20 - - 139.60 - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 87.37 - - 168.78 - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
BOTTOM BAR 14 1 2 2 4.20 8.40
STIRRUP 8 0.15 3.69 1 26 26 1.40 36.40
RAMP BEAM
ON AXIS 2 b/n E--F
FB-1
TOP BAR 16 1 4 4 7.05 28.20
BOTTOM BAR 14 1 3 3 6.70 20.10
STIRRUP 8 0.12 5.78 1 49 49 1.40 68.60
ON AXIS 3 b/n E--G
FB-1'
TOP BAR 16 1 4 4 4.26 17.04
16 1 4 4 9.65 38.60
BOTTOM BAR 14 1 3 3 4.70 14.10
14 1 3 3 3.30 9.90
14 1 3 3 6.20 18.60
STIRRUP 8 0.12 4.93 1 42 42 1.40 58.80
8 0.12 5.78 1 49 49 1.40 68.60
ON AXIS F b/n 2-5
FB-2
TOP BAR 16 1 2 2 7.45 14.90
16 1 2 2 5.80 11.60
16 1 2 2 3.62 7.24
Negative 16 1 2 2 1.70 3.40
16 1 2 2 2.90 5.80
16 1 2 2 3.30 6.60
BOTTOM BAR 14 1 3 3 9.70 29.10
14 1 3 3 5.87 17.61
STIRRUP
ON AXIS F b/n 2-3 8 0.12 4.39 1 38 38 1.40 53.20
Total Length - 285.60 - - 117.81 133.38 - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 112.81 - - 142.43 210.61 - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
ON AXIS F b/n 3-4 8 0.12 4.52 1 39 39 1.40 54.60
ON AXIS F b/n 4-5 8 0.12 3.18 1 28 28 1.40 39.20
ON AXIS 4 & 5 b/n F-G
FB-3
16 2 4 8 6.90 55.20
14 2 3 6 6.20 37.20
STIRRUP 8 0.12 5.03 2 43 86 1.40 120.40
8 0.13 3.4 1 27 27 6.26 169.02

RAMP slab
B/n slab E-F & 2-3
Horizontal bars 10 0.12 4.93 1 42 42 6.43 270.06
Vertical bars 10 0.12 5.98 1 51 51 5.43 276.93
B/n slab F-G & 2-3
Horizontal bars 10 0.12 4.9 1 42 42 5.53 232.26
Vertical bars 10 0.12 5.08 1 43 43 14.15 608.45
B/n slab F-G & 3-4
Horizontal bars 10 0.12 4.95 1 42 42 5.53 232.26
B/n slab F-G & 4-5
Horizontal bars 10 0.12 3.4 1 29 29 5.53 160.37
Ramp slab
ON AXIS E B/n 2-3
Negative 10 0.12 4.39 1 38 38 2.75 104.50
on axis F b/n 2-3
Negative 12 0.12 4.39 1 38 38 4.15 157.70
ON axis F B/n 3-4
Negative 10 0.12 4.4 1 38 38 2.15 81.70
ON axis F B/n 4-5
Negative 10 0.12 3.4 1 29 29 2.15 62.35
Total Length - 383.22 2,028.88 157.70 37.20 55.20 - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 151.37 1,251.82 140.04 44.97 87.16 - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
ON axis G B/n 2-3
Negative 10 0.12 4.39 1 38 38 2.15 81.70
ON axis G B/n 3-4
Negative 10 0.12 4.95 1 42 42 2.15 90.30
ON axis G B/n 4-5
Negative 10 0.12 3.4 1 29 29 2.15 62.35
ON axis 2 B/N E-F
Negative 10 0.12 5.4 1 46 46 1.95 89.70
ON axis 3 B/n E-F
Negative 10 0.12 5.4 1 46 46 1.95 89.70
ON axis 3 B/N F-G
Negative 12 0.12 5.08 1 43 43 3.60 154.80
ON axis 4 B/N F-G
Negative 12 0.12 5.08 1 43 43 3.18 136.74
Ramp slab(Entrance)
ON AXIS F-G B/n 5-6
Horizontal bars 8 0.15 3.46 1 24 24 5.53 132.72
Vertical bars 8 0.15 5.53 1 38 38 3.26 123.88
G.FLOOR SLAB
B/n slab A-B & 1-2
Horizontal bars 8 0.13 6.75 1 53 53 6.40 339.20
Vertical bars 8 0.13 5.93 1 47 47 7.26 341.22
B/n slab A-B & 2-3
Horizontal bars 8 0.13 4.9 1 39 39 6.40 249.60
Vertical bars 8 0.13 5.93 1 47 47 5.40 253.80
B/n slab A-B & 3-5
Horizontal bars 8 0.13 4.95 1 39 39 6.40 249.60
8 0.13 3.45 1 28 28 6.40 179.20
Vertical bars 8 0.13 5.85 1 46 46 9.10 418.60
Total Length - 2,287.82 413.75 291.54 - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 903.69 255.28 258.89 - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
B/n slab B-C & 1-2
Horizontal bars 8 0.13 6.75 1 53 53 3.65 193.45
Vertical bars 8 0.13 3.13 1 25 25 7.26 181.50
B/n slab B-C & 2-3
Horizontal bars 8 0.13 4.95 1 39 39 6.10 237.90
Vertical bars 8 0.13 5.58 1 44 44 5.40 237.60
B/n slab B-C & 3-5
Horizontal bars 8 0.13 4.95 1 39 39 6.10 237.90
8 0.13 3.45 1 28 28 5.00 140.00
Vertical bars 8 0.13 4.48 1 35 35 9.10 318.50
8 0.13 1.12 1 9 9 5.40 48.60
B/n slab C-D & 1-2
Horizontal bars 8 0.13 6.75 1 53 53 6.40 339.20
Vertical bars 8 0.13 5.87 1 46 46 7.26 333.96
B/n slab C-D & 2-3
Horizontal bars 8 0.13 4.93 1 39 39 6.40 249.60
Vertical bars 8 0.13 5.92 1 47 47 5.40 253.80
B/n slab C-D & 3-5
Horizontal bars 8 0.13 4.93 1 39 39 6.40 249.60
8 0.13 2.05 1 17 17 3.35 56.95
8 0.13 1.4 1 12 12 4.64 55.68
Vertical bars 8 0.13 2.84 1 23 23 9.10 209.30
8 0.13 3.04 1 24 24 5.40 129.60
8 0.13 1.55 1 13 13 1.90 24.70
B/n slab D-E & 1-2
Horizontal bars 8 0.13 6.75 1 53 53 6.45 341.85
Vertical bars 8 0.13 5.93 1 47 47 7.26 341.22
B/n slab D-E & 2-3
Horizontal bars 8 0.13 6.5 1 51 51 6.45 328.95
Total Length - 4,509.86 - - - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 1,781.39 - - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Vertical bars 8 0.13 4.93 1 39 39 5.40 210.60
B/n slab D-E & 3-5
Horizontal bars 8 0.13 4.93 1 39 39 6.45 251.55
8 0.13 3.45 1 28 28 5.15 144.20
Vertical bars 8 0.13 4.63 1 37 37 9.10 336.70
8 0.13 1.29 1 11 11 5.40 59.40
B/n slab E-F & 1-2
Horizontal bars 8 0.13 6.75 1 53 53 6.26 331.78
Vertical bars 8 0.13 5.75 1 45 45 7.26 326.70
ON slab E-F & 3-5
Horizontal bars 8 0.13 4.93 1 39 39 6.26 244.14
Vertical bars 8 0.13 3.4 1 27 27 6.26 169.02
8 0.13 5.75 1 45 45 9.10 409.50
G.FLOOR SLAB
Negative bar
on axis A B/n 1-2
Negative 8 0.13 6.7 1 53 53 2.30 121.90
ON AXIS A B/N 2-3
Negative 8 0.13 4.4 1 35 35 2.30 80.50
ON AXIS A B/N 3-4
Negative 8 0.13 4.4 1 35 35 2.30 80.50
ON AXIS A B/N 4-5
Negative 8 0.13 3.4 1 27 27 2.30 62.10
ON AXIS B B/N 1-2
Negative 12 0.12 6.7 1 57 57 3.40 193.80
ON AXIS B B/N 2-3
Negative 10 0.14 4.4 1 32 32 4.30 137.60
ON AXIS B B/N 3-4
Negative 10 0.14 4.4 1 32 32 4.30 137.60
Total Length - 2,828.59 275.20 193.80 - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 1,117.29 169.80 172.09 - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
ON AXIS B B/N 4-5
Negative 10 0.14 3.4 1 25 25 4.30 107.50
B/n AXIS B-B' &1-2
Negative 12 0.13 6.7 1 53 53 2.40 127.20
on axis B' B/n 4-5
Negative 10 0.14 3.4 1 25 25 1.80 45.00
on axis C B/n 1-2
Negative 12 0.12 6.3 1 54 54 2.30 124.20
on axis C B/n 2-3
Negative 10 0.14 4.4 1 32 32 4.30 137.60
on axis C B/n 3-4
Negative 10 0.14 4.76 1 35 35 4.30 150.50
on axis C' B/n 4-5
Negative 10 0.14 3.1 1 23 23 3.60 82.80
on axis D B/n 1-2
Negative 12 0.12 6.5 1 55 55 4.30 236.50
on axis D B/n 2-3
Negative 10 0.14 4.54 1 33 33 4.30 141.90
on axis D B/n 3-4
Negative 10 0.14 4.46 1 33 33 4.30 141.90
on axis D' B/n 4-5
Negative 10 0.14 3.1 1 23 23 2.92 67.16
on axis E B/n 1-2
Negative 12 0.12 6.5 1 55 55 4.30 236.50
on axis E B/n 2-3
Negative 8 0.13 4.29 1 34 34 2.30 78.20
on axis E B/n 3-4
Negative 10 0.14 4.4 1 32 32 4.30 137.60
on axis E B/n 4-5
Total Length - 78.20 1,011.96 724.40 - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 30.89 624.38 643.27 - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Negative 10 0.14 3.4 1 25 25 4.30 107.50
on axis F B/n 1-2
Negative 8 0.13 6.7 1 53 53 2.30 121.90
on axis F B/n 3-4
Negative 8 0.13 4.4 1 35 35 2.30 80.50
on axis E B/n 4-8
Negative 8 0.13 3.4 1 27 27 2.30 62.10
ON axis 1 b/n A-B
Negative 8 0.13 5.85 1 46 46 2.65 121.90
on axis 1 b/n B-C
Negative 8 0.13 3.13 1 25 25 2.65 66.25
on axis 1 b/n C-D
Negative 8 0.13 5.45 1 43 43 2.65 113.95
on axis 1 b/n D-E
Negative 8 0.13 5.55 1 44 44 2.65 116.60
on axis 1 b/n E-F
Negative 8 0.13 5.7 1 45 45 2.65 119.25
on axis 2 b/n A-B
Negative 10 0.1 5.4 1 55 55 4.30 236.50
on axis 2 b/n B-C
Negative 10 0.1 2.95 1 31 31 4.30 133.30
on axis 2 b/n C-D
Negative 10 0.1 5.45 1 56 56 4.30 240.80
on axis 2 b/n D-E
Negative 10 0.1 5.45 1 56 56 4.30 240.80
on axis 2 b/n E-F
Negative 8 0.1 5.4 1 55 55 2.63 144.65
on axis 3 b/n A-B
Negative 10 0.14 5.4 1 40 40 3.64 145.60
Total Length - 947.10 1,104.50 - - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 374.10 681.48 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
on axis 3 b/n B-C
Negative 10 0.141 5.4 1 39 39 3.64 141.96
on axis 3 b/n C-D
Negative 10 0.14 5.45 1 40 40 3.64 145.60
on axis 3 b/n D-E
Negative 10 0.14 5.45 1 40 40 3.64 145.60
on axis 3 b/n E-F
Negative 8 0.13 5.4 1 43 43 1.95 83.85
on axis 4 b/n A-B
Negative 10 0.13 5.4 1 43 43 4.30 184.90
on axis 4 b/n B-C
Negative 10 0.14 4.28 1 32 32 4.30 137.60
on axis 4 b/n C-D
Negative 10 0.14 2.84 1 21 21 4.30 90.30
on axis 4 b/n D'-E
Negative 10 0.14 4.28 1 32 32 4.30 137.60
on axis 4 b/n E-F
Negative 10 0.14 5.4 1 40 40 4.30 172.00
on axis 5 b/n A-B
Negative 8 0.13 5.85 1 46 46 1.55 71.30
on axis 5 b/n B-C
Negative 8 0.13 4.33 1 34 34 1.55 52.70
Negative 8 0.13 2.84 1 23 23 1.55 35.65
B/n axis 5 b/n D'-E
Negative 8 0.13 4.58 1 36 36 1.55 55.80
B/n axis 5 b/n E-F
Negative 8 0.13 5.7 1 45 45 1.55 69.75
solid slab
basement floor mesh
Total Length - 369.05 1,155.56 - - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 145.77 712.98 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
B/n axis 1-2 b/n A-B
Horizontal bars 8 0.2 4.05 1 20 20 11.25 225.00
Vertical bars 8 0.2 11.25 1 56 56 4.05 226.80
B/n axis 1-2 b/n E-F
Horizontal bars 8 0.2 3.98 1 20 20 5.25 105.00
Vertical bars 8 0.2 5.25 1 26 26 3.98 103.48
Ground floor MESH
B/n axis 5-6 b/n B-C
Horizontal bars 8 0.2 5.6 1 29 29 3.60 104.40
Vertical bars 8 0.2 3.6 1 19 19 5.60 106.40
B/n axis 5-6 b/n C-D'
Horizontal bars 8 0.2 3.55 1 19 19 7.22 137.18
Vertical bars 8 0.2 7.22 1 37 37 3.55 131.35
B/n axis 5-6 b/n D'-E
Horizontal bars 8 0.2 3.6 1 19 19 4.63 87.97
Vertical bars 8 0.2 4.63 1 24 24 3.60 86.40
Footing Pad
on axis 6 B/N (B,C,D',E)
F1 12 0.2 1.65 4 9 36 1.95 70.20
12 0.15 1.65 4 12 48 1.95 93.60
strip footing
on axis 1 B/N A-C 8 0.15 0.9 1 14 14 12.10 169.40
10 0.15 12.1 1 82 82 2.20 180.40
on axis A B/N 1-2 8 0.15 0.9 2 14 28 4.05 113.40
10 0.15 4.05 2 28 56 2.20 123.20
on axis 1 b/n E-F 8 0.15 0.9 1 14 14 6.17 86.38
10 0.15 6.17 1 42 42 2.20 92.40
on axis 2 B/N F-G 8 0.15 0.9 1 14 14 4.65 65.10
10 0.15 4.65 1 32 32 2.20 70.40
Total Length - 1,748.26 466.40 163.80 - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 690.56 287.77 145.45 - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
on axis G B/N 2-5 8 0.15 0.9 1 14 14 14.90 208.60
10 0.15 14.9 1 100 100 2.20 220.00
on axis 5 B/N F-G 8 0.15 0.9 1 14 14 4.88 68.32
10 0.15 4.88 1 34 34 2.20 74.80
Foundation Column
ON AXIS 6-(B,C,D',E)
C2 (30*30) 14 4 8 32 3.53 113.00
stirup 1 8 0.2 2.18 4 12 47.625 1.10 52.39
Basement COLUMN
ON AXIS 1-(A,B,F)
C1 (30*30) 14 3 8 24 5.16 123.84
stirup 1 8 0.2 4.1 3 21 64.5 1.10 70.95
starter bar 14 3 8 24 1.21 29.04
ON AXIS 1-(C,E)
C2(60*60) 16 2 12 24 5.24 125.76
stirrups 4 8 0.2 4.1 2 21 43 2.30 98.90
stirrups 5 8 0.2 4.1 2 43 86 0.65 55.90
starter bar 20 2 8 16 2.30 36.80
ON AXIS 1-(D)
C2(60*60) 16 1 12 12 5.24 62.88
stirrups 4 8 0.2 4.1 1 21 21.5 2.30 49.45
stirrups 5 8 0.2 4.1 1 43 43 0.65 27.95
starter bar 20 1 8 8 2.30 18.40
ON AXIS 2-(A)
C2(60*60) 16 1 12 12 5.24 62.88
stirrups 4 8 0.2 4.1 1 21 21.5 2.30 49.45
stirrups 5 8 0.2 4.1 1 43 43 0.65 27.95
starter bar 20 1 8 8 2.30 18.40
ON AXIS 2-(G)
Total Length - 709.86 294.80 - 265.88 251.52 73.60 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 280.39 181.89 - 321.45 397.15 181.57 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
ON AXIS 2-(G)
C1 (30*30) 14 1 6 6 4.66 27.96
stirup 1 8 0.2 4.1 1 21 21.5 1.10 23.65
starter bar 14 1 6 6 1.21 7.26
ON AXIS 2-(B,C,D,E,F)
C4(80*80) 20 5 12 60 5.40 324.00
stirup 1 8 0.2 4.1 5 21 107.5 3.10 333.25
stirup 2 8 0.2 4.1 5 21 107.5 1.90 204.25
starter bar 20 5 12 60 2.30 138.00
ON AXIS 3-(G)
C1 (30*30) 14 1 6 6 5.16 30.96
stirup 1 8 0.2 4.1 1 21 21.5 1.10 23.65
starter bar 14 1 6 6 1.21 7.26
ON AXIS 3-(A)
C2(60*60) 16 1 12 12 5.40 64.80
stirrups 4 8 0.2 4.1 1 21 21.5 2.30 49.45
stirrups 5 8 0.2 4.1 1 43 43 0.65 27.95
starter bar 20 1 8 8 2.30 18.40
ON AXIS 3-(B,C,D,E,F)
C4(80*80) 20 5 8 40 5.40 216.00
stirup 1 8 0.2 4.1 5 21 107.5 3.10 333.25
stirup 2 8 0.2 4.1 5 21 107.5 1.90 204.25
starter bar 20 5 12 60 2.30 138.00
ON AXIS 4-(G)
C1 (30*30) 14 1 6 6 5.16 30.96
stirup 1 8 0.2 4.1 1 21 21.5 1.10 23.65
starter bar 14 1 6 6 1.21 7.26
ON AXIS 4-(A,B,D',E,F)
C2(60*60) 16 5 12 60 5.40 324.00
Total Length - 1,223.35 - - 111.66 388.80 834.40 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 483.22 - - 135.00 613.92 2,058.46 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
stirrups 4 8 0.2 4.1 5 21 107.5 2.30 247.25
stirrups 5 8 0.2 4.1 5 43 215 0.65 139.75
starter bar 20 5 8 40 2.30 92.00
ON AXIS 5-(A,B,C',E,F)
C1 (30*30) 14 5 6 30 5.16 154.80
stirup 1 8 0.2 4.1 5 21 107.5 1.10 118.25
starter bar 14 5 6 30 2.06 61.80
ON AXIS 5-(G)
C1 (30*30) 14 1 6 6 5.16 30.96
stirup 1 8 0.2 4.1 1 21 21.5 1.10 23.65
starter bar 14 1 6 6 1.21 7.26
ON AXIS 5-(B',D')
C2(60*60) 20 2 12 24 5.40 129.60
stirrups 4 8 0.2 4.1 2 21 43 2.30 98.90
stirrups 5 8 0.2 4.1 2 43 86 0.65 55.90
starter bar 20 1 8 8 2.30 18.40
section 4-4
W2(U) 14 0.15 2.55 2 18 36 6.57 236.52
14 0.15 2.55 4 18 72 5.16 371.52
10 0.15 2.55 2 18 36 5.60 201.60
W3(U) 14 0.15 1.8 1 13 13 6.57 85.41
14 0.15 1.8 2 13 26 5.16 134.16
10 0.15 1.8 1 13 13 5.00 65.00
W4(U)BAR 14 0.15 0.625 1 10 10 6.57 65.70
14 0.15 0.625 2 10 20 5.16 103.20
D 10 0.15 4.6 1 32 31.6667 5.00 158.33
E 10 0.15 4.6 1 63 63.3333 1.70 107.67
Negative 10 0.15 1 4 4 0.80 3.20
Total Length - 683.70 535.80 - 1,251.33 - 240.00 - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 270.06 330.59 - 1,512.86 - 592.08 - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Slant area 12 0.25 4.8 4 19 76 2.25 171.00
ON AXIS 3&5 b/n B-C' 12 0.25 1.5 6 6 36 2.85 102.60
ON AXIS B&C' b/n 3-5 12 0.25 4.5 4 18 72 2.85 205.20
12 0.25 0.55 2 2 4 2.85 11.40
Retaining wall 8 0.15 4.42 1 30 30 11.92 357.60
Horizontal (w1) 8 0.15 4.42 1 30 30 11.92 357.60
ON AXIS 5 A-G 8 0.15 4.42 1 30 30 11.92 357.60
8 0.15 4.42 1 30 30 11.92 357.60
8 0.15 4.42 1 30 30 6.32 189.60
8 0.15 4.42 1 30 30 6.32 189.60
8 0.15 4.42 1 30 30 7.07 212.10
8 0.15 4.42 1 30 30 7.07 212.10
vertical
ON AXIS 5 b/n (A-B-B'-C-C') 10 0.15 13.52 1 91 91 4.75 432.25
10 0.15 13.52 1 91 91 4.75 432.25
u shape (b) 10 0.15 13.52 1 91 91 3.20 291.20
ON AXIS 5 b/n (C'-D-D')
10 0.15 2.7 1 19 19 2.94 55.86
10 0.15 2.7 1 19 19 2.94 55.86
10 0.15 1.2 1 9 9 4.75 42.75
10 0.15 1.2 1 9 9 4.75 42.75
u shape (b) 10 0.15 3.9 1 27 27 3.20 86.40
ON AXIS 5 b/n (D'-E)
10 0.15 0.69 1 6 6 4.75 28.50
10 0.15 0.69 1 6 6 4.75 28.50
10 0.15 3 1 21 21 2.94 61.74
10 0.15 3 1 21 21 2.94 61.74
10 0.15 0.69 1 6 6 4.75 28.50
10 0.15 0.69 1 6 6 4.75 28.50
Total Length - 2,233.80 1,676.80 490.20 - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 882.35 1,034.59 435.30 - - - - -
______________ ______________ ______________
Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
u shape (b) 10 0.15 4.38 1 30 30 3.20 96.00
ON AXIS 1 b/n (E-G)
10 0.15 10.73 1 73 73 4.75 346.75
10 0.15 10.73 1 73 73 4.75 346.75
u shape (b) 10 0.15 10.73 1 73 73 3.20 233.60
horizontal (w2)
ON AXIS 2 b/n (F-G) 8 0.15 4.42 1 30 30 6.20 186.00
8 0.15 4.42 1 30 30 6.20 186.00
vertical 10 0.15 5.03 1 35 35 4.75 166.25
10 0.15 5.03 1 35 35 4.75 166.25
u shape (b) 10 0.15 5.03 1 35 35 1.50 52.50
Horizontal (w3)
ON AXIS 1 A-F
8 0.15 4.42 1 30 30 6.67 200.10
8 0.15 4.42 1 30 30 6.67 200.10
8 0.15 4.42 1 30 30 5.92 177.60
8 0.15 4.42 1 30 30 5.92 177.60
8 0.15 4.42 1 30 30 11.92 357.60
8 0.15 4.42 1 30 30 11.92 357.60
8 0.15 4.42 1 30 30 7.14 214.20
8 0.15 4.42 1 30 30 7.14 214.20
vertical
ON AXIS 1 b/n (A-C) 10 0.15 11.4 1 77 77 5.20 400.40
10 0.15 11.4 1 77 77 5.20 400.40
u shape (b) 10 0.15 11.4 1 77 77 1.50 115.50
ON AXIS 1 b/n (C-E) 10 0.15 4.64 1 32 32 4.75 152.00
10 0.15 4.64 1 32 32 4.75 152.00
10 0.15 2.7 1 19 19 2.94 55.86
10 0.15 2.7 1 19 19 2.94 55.86
Total Length - 2,271.00 2,740.12 - - - - - -
0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 897.05 1,690.65 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
u shape (b) 10 0.15 12.02 1 81 81 3.20 259.20
ON AXIS 1 b/n (E-F)
10 0.15 5.6 1 38 38 5.20 197.60
10 0.15 5.6 1 38 38 5.20 197.60
u shape (b) 10 0.15 5.6 1 38 38 1.50 57.00
Horizontal (w4)
ON AXIS A b/n (1-5) 8 0.15 4.42 1 30 30 6.67 200.10
8 0.15 4.42 1 30 30 6.67 200.10
8 0.15 4.42 1 30 30 6.32 189.60
8 0.15 4.42 1 30 30 6.32 189.60
8 0.15 4.42 1 30 30 9.07 272.10
8 0.15 4.42 1 30 30 9.07 272.10
VERTICAL
ON AXIS A b/n (1-2) 10 0.15 4.3 1 30 30 5.20 156.00
10 0.15 4.3 1 30 30 5.20 156.00
10 0.15 2.4 1 17 17 4.75 80.75
10 0.15 2.4 1 17 17 4.75 80.75
u shape (b) 10 0.15 4.3 1 30 30 1.50 45.00
ON AXIS A b/n (2-4) 10 0.15 2.8 1 20 20 4.75 95.00
Err:522 10 0.15 2.8 1 20 20 4.75 95.00
10 0.15 12 1 81 81 2.94 238.14
u shape (b) 10 0.15 8.8 1 60 60 3.12 187.20
ON AXIS A b/n (4-5) 10 0.15 3.3 1 23 23 4.75 109.25
10 0.15 3.3 1 23 23 4.75 109.25
u shape (b) 10 0.15 3.3 1 23 23 3.20 73.60
Horizontal (w5)
ON AXIS A b/n (1-2) 8 0.15 4.42 1 30 30 7.70 231.00
8 0.15 4.42 1 30 30 7.70 231.00
VERTICAL
Total Length - 1,785.60 2,137.34 - - - - - -
Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 705.31 1,318.74 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
ON AXIS A b/n (1-1') 10 0.15 4.3 1 30 30 5.20 156.00
10 0.15 4.3 1 30 30 5.20 156.00
u shape (b) 10 0.15 4.3 1 30 30 1.50 45.00
ON AXIS A b/n (1'-2) 10 0.15 2.4 1 17 17 4.75 80.75
10 0.15 2.4 1 17 17 4.75 80.75
u shape (b) 10 0.15 2.4 1 17 17 3.20 54.40
Horizontal (w6)
ON AXIS A b/n (2-5) 8 0.15 4.42 1 30 30 11.92 357.60
8 0.15 4.42 1 30 30 11.92 357.60
8 0.15 4.42 1 30 30 2.87 86.10
8 0.15 4.42 1 30 30 2.87 86.10
VERTICAL 10 0.15 12.7 1 86 86 4.75 408.50
10 0.15 12.7 1 86 86 4.75 408.50
u shape (b) 10 0.15 12.7 1 86 86 3.20 275.20
L-BAR 10 0.1 114.7 1 1148 1148 1.60 1836.80
L Connectin re.bar
ON AXIS A,2,F,2G,5, 10 0.1 4.42 6 44 264 1.20 316.80
Stair case
section A-A 1 12 0.15 1.03 1 8 8 4.46 35.68
2 12 0.15 1.03 1 8 8 2.48 19.84
3 12 0.15 1.03 1 8 8 2.15 17.20
4 12 0.15 1.03 1 8 8 1.85 14.80
5 8 0.15 1.03 6 8 48 0.53 25.44
6 12 0.15 1.03 1 8 8 2.20 17.60
6' 12 0.15 1.03 1 8 8 1.40 11.20
section B-B 1 8 0.15 1.03 6 8 48 0.55 26.40
2 12 0.15 1.03 1 8 8 1.69 13.52
3 12 0.15 1.03 1 8 8 3.94 31.52
4 12 0.15 1.03 1 8 8 2.00 16.00
5 12 0.15 1.03 1 8 8 2.28 18.24

Total Length - 939.24 3,818.70 195.60 - - - - -


Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 371.00 2,356.14 173.69 - - - - -
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
______________ ______________ ______________
Contractor Consultant Client
Steel Reinforcement bar Takeoff Sheet
Sub structure
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- _ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
section C-C 8 0.15 1.15 5 9 45 0.55 24.75
12 0.15 1.15 1 9 9 2.00 18.00
12 0.15 1.15 1 9 9 2.00 18.00
12 0.15 1.15 1 9 9 3.67 33.03
section D-D 14 12 0.15 1.03 6 8 48 4.13 198.24
15 12 0.15 1.03 1 8 8 2.32 18.56
16 12 0.15 1.03 1 8 8 1.77 14.16
17 12 0.15 1.03 1 8 8 1.20 9.60
18 8 0.2 1.03 1 6 6 0.58 3.48

Total Length - 28.23 - 309.59 - - - - -


Unit Wt kg/m 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 11.15 - 274.92 - - - - -
Steel Reinforcement bar Takeoff Sheet
Summery
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- ____ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Production
No. Location Remark
Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Supper Structure
Page 1 - 332.39 - - 65.33 - 1,594.67 -
Page 2 - 419.49 - - 410.67 - 1,294.68 -
Page 3 - 667.75 - - 37.33 - 2,508.45 -
Page 4 - 1,634.11 - - 74.67 4,977.01 2,103.86 -
Page 5 - 601.25 - - 242.28 662.36 - -
Page 6 - 97.88 78.61 - 28.23 236.22 453.31 -
Page 7 - - 598.61 - 32.64 204.72 347.60 -
Page 8 - 18.25 131.30 - 183.04 253.59 66.91 -
Page 9 - 313.00 - - 431.50 61.98 - -
Page 10 - 141.57 46.65 - 255.58 176.69 65.38 -
Page 11 - 91.25 205.58 - 197.49 61.27 160.85 145.99
Page 12 - 188.57 - - 95.63 293.38 - -
Page 13 - 100.65 234.95 - 60.45 381.49 863.20 -
Page 14 - 91.80 468.18 - - 585.18 758.70 -
Page 15 - 395.95 - - 654.41 331.59 132.23 -
Page 16 - 391.52 - - 224.10 51.79 80.92 266.90
Page 17 - 446.27 - - 251.35 1,333.31 - -
Page 18 - 263.14 612.58 - 29.62 585.02 3,403.23 -
Page 19 - 606.92 1,222.28 - - 1,666.63 659.18 -
Page 20 - 1,266.19 - - 1,755.47 382.12 330.58 509.71
Steel Reinforcement bar Takeoff Sheet
Summery
Project:- SHDE Housing Dev't Project Contractor. ________________
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- ____ 15
Consultant:- K2N Architecture and Engineering Consultancy PLC Date. ___________________
Production
No. Location Remark
Page 21 - 494.94 - - 761.07 697.60 187.00 156.11
Page 22 - 269.55 71.08 - 333.87 13.90 - -
Page 23 - 62.57 493.85 - 369.23 75.00 38.73 -
Page 24 - 451.72 - - 427.74 126.90 8.14 -
Page 25 - 80.58 - - 767.06 193.30 - -
Page 26 - - 203.61 1,292.36 1,916.87 - - -
Page 27 - - 2,387.42 726.17 1,008.02 - - -
Page 28 - 280.37 123.94 2,118.90 - 136.93 - -
Page 29 - 384.70 341.69 91.57 - - - -
Page 30 - 893.66 265.90 - - - - -
Page 31 - 280.21 272.13 - - - - -
Page 32 - 724.55 924.76 1,621.19 - - - -
Page 33 - 579.84 1,369.71 628.19 - - - -
Page 34 653.68 292.88 281.25 - - - - -
Page 35 4,554.11 237.99 254.82 - - - - -
Page 36 - 1,571.06 204.67 2,315.02 - - - -
Page 37 - 15.74 34.18 - - - - -
Page 38 - 60.67 98.99 - - - - -
Total Weight Summery ( kg) 5,207.79 14,748.96 10,926.73 8,793.40 10,613.67 13,487.96 15,057.61 1,078.71 -

______________ ______________ ______________


Contractor Consultant Client
Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Location Dia No. No. bars Len Floor Total Dia 6 Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia 20

MAT SLAB

ALONG X - AXIS

CSX5 20 1 23 12.00 1 273.82


273.82
20 1 23 2.33 1 53.17
53.17
20 1 23 2.05 1 46.78
46.78
16 1 23 12.00 1 273.82
273.82
MSX5 20 1 32 12.00 1 381.82
381.82
20 1 32 2.33 1 74.14
74.14
16 1 32 8.14 1 259.00
259.00
16 1 32 5.90 1 187.73
187.73
20 1 10 12.00 1 114.55
114.55
16 1 10 1 88.39
9.26 88.39
CSX4 20 1 27 12.00 1 327.27
327.27
20 1 27 12.00 1 327.27
327.27
20 1 27 3.75 1 102.27
102.27
16 1 27 1 252.55
9.26 252.55
16 1 27 1 327.27
12.00 327.27
16 1 27 1 327.27
12.00 327.27
MSX4 20 1 23 1 272.73
12.00 272.73
20 1 23 1 272.73
12.00 272.73
20 1 23 1 223.86
9.85 223.86
16 1 23 1 210.45
9.26 210.45
16 1 23 1 272.73
12.00 272.73
16 1 23 1 272.73
12.00 272.73
CSX3 20 1 23 1 272.73
12.00 272.73
20 1 23 1 273.82
12.00 273.82
20 1 23 1 224.76
9.85 224.76
16 1 23 1 211.30
9.26 211.30
16 1 23 1 273.82
12.00 273.82
16 1 23 1 273.82
12.00 273.82
MSX3 20 1 23 1 272.73
12.00 272.73
20 1 23 1 272.73
12.00 272.73
20 1 23 1 223.86
9.85 223.86
20 1 23 1 127.27
5.60 127.27
20 1 23 1 114.32
5.03 114.32
16 1 23 1 210.45
9.26 210.45
16 1 23 1 272.73
12.00 272.73
16 1 23 1 272.73
12.00 272.73

CSX2 20 1 20 1 45.78
2.31 45.78
20 1 20 1 237.82
12.00 237.82
20 1 20 1 91.16
4.60 91.16
20 1 20 1 201.15
10.15 201.15
20 1 20 1 197.00
9.85 197.00
16 1 20 1 183.52
9.26 183.52
16 1 20 1 237.82
12.00 237.82
16 1 20 1 237.82
12.00 237.82
MSX1 20 1 17 1 201.82
12.00 201.82
20 1 17 1 177.10
10.53 177.10
20 1 17 1 185.00
11.00 185.00
20 1 17 1 165.66
9.85 165.66
20 1 17 1 201.82
12.00 201.82
16 1 17 1 188.03
11.18 188.03
16 1 17 1 201.82
12.00 201.82
CSX1 20 1 13 1 150.55
12.00 150.55
20 1 13 1 150.55
12.00 150.55
20 1 13 1 123.57
9.85 123.57
16 1 13 1 150.55
12.00 150.55
20 1 13 1 150.55
12.00 150.55
16 1 13 1 116.17
9.26 116.17

ALONG y - AXIS

CSy1 16 1 20 1 117.23
5.97 117.23
16 1 20 1 235.64
12.00 235.64
16 1 20 1 235.64
12.00 235.64
16 1 20 1 117.23
5.97 117.23
MSy1 16 1 27 1 162.82
5.97 162.82
16 1 27 1 327.27
12.00 327.27
16 1 27 1 327.27
12.00 327.27
16 1 27 1 162.82
5.97 162.82
CSy2 16 1 27 1 162.82
5.97 162.82
16 1 27 1 327.27
12.00 327.27
16 1 27 1 327.27
12.00 327.27
16 1 27 1 162.82
5.97 162.82
MSy2 16 1 27 1 162.82
5.97 162.82
16 1 27 1 327.27
12.00 327.27
16 1 27 1 327.27
12.00 327.27
16 1 27 1 162.82
5.97 162.82
CSy3 20 1 27 1 327.27
12.00 327.27
20 1 27 1 116.73
4.28 116.73
20 1 27 1 238.09
8.73 238.09
16 1 27 1 223.64
8.20 223.64
16 1 27 1 294.82
10.81 294.82
16 1 27 1 327.27
12.00 327.27
16 1 27 1 70.91
2.60 70.91
MSy3 20 1 27 1 327.27
12.00 327.27
16 1 27 1 327.27
12.00 327.27
16 1 27 1 123.06
4.62 123.06
16 1 27 1 319.64
12.00 319.64
16 1 27 1 159.02
5.97 159.02
CSy4 20 1 27 1 327.27
12.00 327.27
16 1 27 1 294.82
10.81 294.82
16 1 27 1 295.09
10.82 295.09
16 1 27 1 327.27
12.00 327.27
MSy4 16 1 27 1 294.82
10.81 294.82
20 1 27 1 327.27
12.00 327.27
16 1 27 1 327.27
12.00 327.27
16 1 27 1 295.09
10.82 295.09
CSy5 20 1 27 1 327.27
12.00 327.27
16 1 27 1 295.09
10.82 295.09
16 1 27 1 294.82
10.81 294.82
16 1 27 1 327.27
12.00 327.27
MSy5 14 1 27 1 327.27
12.00 327.27
14 1 27 1 159.00
5.83 159.00
14 1 27 1 159.00
5.83 159.00
14 1 27 1 327.27
12.00 327.27
CSy6 14 1 19 1 223.64
12.00 223.64
14 1 19 1 108.65
5.83 108.65
14 1 19 1 108.65
5.83 108.65
14 1 19 1 223.64
12.00 223.64

Grade Beam -

ON AXIS 2 & 3 b/n A-F

GB-1

TOP BAR 14 2 2 10.05 1 40.20 40.20

14 2 2 6.65 1 26.60 26.60

14 2 2 6.65 1 26.60 26.60

14 2 2 10.05 1 40.20 40.20

Negative 14 2 2 2.45 1 9.80 9.80

16 2 2 4.00 1 16.00 16.00

16 2 2 4.00 1 16.00 16.00

16 2 2 4.00 1 16.00 16.00


14 2 2 4.00 1 16.00 16.00
14 2 2 2.45 1 9.80 9.80
BOTTOM BAR 16 2 3 6.80 1 40.80 40.80
16 2 3 6.80 1 40.80 40.80
16 2 3 6.80 1 40.80 40.80
14 2 3 6.80 1 40.80 40.80
14 2 3 6.80 1 40.80 40.80
STIRRUP 8 2 46 1.40 1 128.80 128.80
8 2 46 1.40 1 128.80 128.80
8 2 46 1.40 1 128.80 128.80
8 2 46 1.40 1 128.80 128.80
8 2 46 1.40 1 128.80 128.80
ON AXIS 4 b/n A-B'
GB-2
TOP BAR 14 1 2 8.85 1 17.70 17.70
14 1 2 4.00 1 8.00 8.00
Negative 14 1 2 2.45 1 4.90 4.90
14 1 2 4.00 1 8.00 8.00
14 1 1 2.45 1 2.45 2.45
BOTTOM BAR 14 1 3 6.80 1 20.40 20.40
14 1 3 6.75 1 20.25 20.25
STIRRUP 8 1 37 1.40 1 51.80 51.80
8 1 31 1.40 1 43.21 43.21
ON AXIS 4 b/n C-F -
GB-3
TOP BAR 16 1 2 8.95 1 17.90 17.90
14 1 2 10.05 1 20.10 20.10
Negative 16 1 2 2.14 1 4.28 4.28
20 1 2 4.00 1 8.00 8.00
14 1 1 3.62 1 3.62 3.62
BOTTOM BAR 16 1 3 6.70 1 20.10 20.10
14 1 3 5.70 1 17.10 17.10
14 1 3 6.80 1 20.40 20.40
STIRRUP 8 1 46 1.40 1 64.28 64.28
8 1 37 1.40 1 51.33 51.33
8 1 46 1.40 1 64.40 64.40
ON AXIS 6 b/n B-E -
GB-4
TOP BAR 14 1 2 10.65 1 21.30 21.30
14 1 2 9.25 1 18.50 18.50
14 1 1 2.45 1 2.45 2.45
14 1 1 4.40 1 4.40 4.40
14 1 1 4.05 1 4.05 4.05
14 1 1 2.10 1 2.10 2.10
14 1 2 6.45 1 12.90 12.90
14 1 2 7.45 1 14.90 14.90
14 1 2 5.30 1 10.60 10.60
STIRRUP 8 1 39 1.40 1 55.07 55.07
8 1 46 1.40 1 65.05 65.05
8 1 32 1.40 1 44.61 44.61
ON AXIS B & E b/n 1-6 -
GB-5
TOP BAR 14 2 2 6.90 1 27.60 27.60
14 2 2 10.00 1 40.00 40.00
14 2 2 10.55 1 42.20 42.20
Negative 14 2 1 2.60 1 5.20 5.20
14 2 1 2.90 1 5.80 5.80
14 2 2 3.30 1 13.20 13.20
20 2 2 4.00 1 16.00 16.00
16 2 2 2.80 1 11.20 11.20
BOTTOM BAR 14 2 3 8.40 1 50.40 50.40
14 2 3 10.60 1 63.60 63.60
14 2 3 7.70 1 46.20 46.20
STIRRUP 8 2 29 1.40 1 82.13 82.13
8 2 27 1.40 1 75.13 75.13
8 2 37 1.40 1 103.13 103.13
8 2 36 1.40 1 100.80 100.80
8 2 54 1.40 1 149.80 149.80
ON AXIS D b/n 1-4
GB-6 -
TOP BAR 14 1 2 8.45 1 16.90 16.90
16 1 2 10.50 1 21.00 21.00
Negative 14 1 1 2.10 1 2.10 2.10
14 1 1 3.30 1 3.30 3.30
20 1 2 3.95 1 7.90 7.90
20 1 2 2.75 1 5.50 5.50
BOTTOM BAR 14 1 3 5.60 1 16.80 16.80
14 1 3 5.70 1 17.10 17.10
16 1 4 7.70 1 30.80 30.80
STIRRUP 8 1 39 1.40 1 54.83 54.83
8 1 38 1.40 1 52.73 52.73
8 1 54 1.40 1 76.07 76.07
ON AXIS D' b/n 6-4
GB-7
TOP BAR 14 1 2 9.15 1 18.30 18.30
BOTTOM BAR 14 1 2 8.45 1 16.90 16.90
STIRRUP 8 1 28 1.40 1 39.67 39.67
8 1 27 1.40 1 37.57 37.57
ON AXIS C b/n 4-1
GB-8
TOP BAR 16 1 2 8.45 1 16.90 16.90
16 1 2 10.50 1 21.00 21.00
Negative 14 1 1 2.10 1 2.10 2.10
14 1 1 3.30 1 3.30 3.30
20 1 2 3.95 1 7.90 7.90
20 1 2 2.75 1 5.50 5.50
BOTTOM BAR 14 1 3 5.60 1 16.80 16.80
14 1 3 5.70 1 17.10 17.10
16 1 4 7.70 1 30.80 30.80
STIRRUP 8 1 39 1.40 1 53.90 53.90
8 1 38 1.40 1 52.73 52.73
8 1 54 1.40 1 74.90 74.90
ON AXIS F b/n 5-3
GB-9 -
TOP BAR 14 1 2 7.25 1 14.50 14.50
14 1 2 3.55 1 7.10 7.10
BOTTOM BAR 14 1 2 4.40 1 8.80 8.80
14 1 2 5.70 1 11.40 11.40
STIRRUP 8 1 22 1.40 1 30.33 30.33
8 1 30 1.40 1 42.47 42.47
ON AXIS C' b/n 5-4
GB-10
TOP BAR 14 1 2 4.90 1 9.80 9.80
BOTTOM BAR 14 1 2 4.20 1 8.40 8.40
Negative 14 1 1 1.70 1 1.70 1.70
STIRRUP 8 1 25 1.40 1 35.28 35.28
ON AXIS b/n 2-1
GB-11
TOP BAR 14 1 2 8.10 1 16.20 16.20
Negative 14 1 1 2.80 1 2.80 2.80
14 1 1 2.80 1 2.80 2.80
BOTTOM BAR 14 1 3 7.40 1 22.20 22.20
STIRRUP 8 1 57 1.40 1 80.15 80.15
ON AXIS b/n 5-4
GB-12
TOP BAR 14 1 2 4.90 1 9.80 9.80
Negative 14 1 1 1.70 1 1.70 1.70
BOTTOM BAR 14 1 3 4.20 1 12.60 12.60
STIRRUP 8 1 24 1.40 1 33.13 33.13
ON AXIS b/n 6-5
GB-13
TOP BAR 14 1 2 4.90 1 9.80 9.80
BOTTOM BAR 14 1 2 4.20 1 8.40 8.40
STIRRUP 8 1 26 1.40 1 35.84 35.84

RAMP BEAM
ON AXIS 2 b/n E--F
FB-1
TOP BAR 16 1 4 7.05 1 28.20 28.20
BOTTOM BAR 14 1 3 6.70 1 20.10 20.10
STIRRUP 8 1 49 1.40 1 68.83 68.83
ON AXIS 3 b/n E--G
FB-1'
TOP BAR 16 1 4 4.26 1 17.04 17.04
16 1 4 9.65 1 38.60 38.60
BOTTOM BAR 14 1 3 4.70 1 14.10 14.10
14 1 3 3.30 1 9.90 9.90
14 1 3 6.20 1 18.60 18.60
STIRRUP 8 1 42 1.40 1 58.92 58.92
8 1 49 1.40 1 68.83 68.83
ON AXIS F b/n 2-5
FB-2
TOP BAR 16 1 2 7.45 1 14.90 14.90
16 1 2 5.80 1 11.60 11.60
16 1 2 3.62 1 7.24 7.24
Negative 16 1 2 1.70 1 3.40 3.40
16 1 2 2.90 1 5.80 5.80
16 1 2 3.30 1 6.60 6.60
BOTTOM BAR 14 1 3 9.70 1 29.10 29.10
14 1 3 5.87 1 17.61 17.61
STIRRUP
ON AXIS F b/n 2-3 8 1 38 1.40 1 52.62 52.62
ON AXIS F b/n 3-4 8 1 39 1.40 1 54.13 54.13
ON AXIS F b/n 4-5 8 1 28 1.40 1 38.50 38.50
ON AXIS 4 & 5 b/n F-G
FB-3
16 2 4 6.90 1 55.20 55.20
14 2 3 6.20 1 37.20 37.20
STIRRUP 8 2 42 1.40 1 117.37 117.37
8 1 27 6.26 1 169.98 169.98

RAMP slab
B/n slab E-F & 2-3
Horizontal bars 10 1 42 6.43 1 270.60 270.60
Vertical bars 10 1 51 5.43 1 276.03 276.03
B/n slab F-G & 2-3
Horizontal bars 10 1 42 5.53 1 231.34 231.34
Vertical bars 10 1 43 14.15 1 613.17 613.17
B/n slab F-G & 3-4
Horizontal bars 10 1 42 5.53 1 233.64 233.64
B/n slab F-G & 4-5
Horizontal bars 10 1 29 5.53 1 162.21 162.21

Ramp slab
ON AXIS E B/n 2-3
Negative 10 1 38 2.75 1 103.35 103.35
on axis F b/n 2-3
Negative 12 1 38 4.15 1 155.97 155.97
ON axis F B/n 3-4
Negative 10 1 38 2.15 1 80.98 80.98
ON axis F B/n 4-5
Negative 10 1 29 2.15 1 63.07 63.07
ON axis G B/n 2-3
Negative 10 1 38 2.15 1 80.80 80.80
ON axis G B/n 3-4
Negative 10 1 42 2.15 1 90.84 90.84
ON axis G B/n 4-5
Negative 10 1 29 2.15 1 63.07 63.07
ON axis 2 B/N E-F
Negative 10 1 46 1.95 1 89.70 89.70
ON axis 3 B/n E-F
Negative 10 1 46 1.95 1 89.70 89.70
ON axis 3 B/N F-G
Negative 12 1 43 3.60 1 156.00 156.00
ON axis 4 B/N F-G
Negative 12 1 43 3.18 1 137.80 137.80

Ramp slab(Entrance)
ON AXIS F-G B/n 5-6
Horizontal bars 8 1 24 5.53 1 133.09 133.09
Vertical bars 8 1 38 3.26 1 123.45 123.45

GROUND FLOOR SLAB -


B/n slab A-B & 1-2
Horizontal bars 8 1 53 6.40 1 338.71 338.71
Vertical bars 8 1 47 7.26 1 338.43 338.43
B/n slab A-B & 2-3
Horizontal bars 8 1 39 6.40 1 247.63 247.63
Vertical bars 8 1 47 5.40 1 251.72 251.72
B/n slab A-B & 3-5
Horizontal bars 8 1 39 6.40 1 250.09 250.09
8 1 28 6.40 1 176.25 176.25
Vertical bars 8 1 43 9.10 1 389.35 389.35
B/n slab B-C & 1-2
Horizontal bars 8 1 53 3.65 1 193.17 193.17
Vertical bars 8 1 25 7.26 1 182.06 182.06
B/n slab B-C & 2-3
Horizontal bars 8 1 39 6.10 1 238.37 238.37
Vertical bars 8 1 44 5.40 1 237.18 237.18
B/n slab B-C & 3-5
Horizontal bars 8 1 39 6.10 1 238.37 238.37
8 1 28 5.00 1 137.69 137.69
Vertical bars 8 1 35 9.10 1 322.70 322.70
8 1 9 5.40 1 46.52 46.52
B/n slab C-D & 1-2
Horizontal bars 8 1 53 6.40 1 338.71 338.71
Vertical bars 8 1 46 7.26 1 335.08 335.08
B/n slab C-D & 2-3
Horizontal bars 8 1 39 6.40 1 249.11 249.11
Vertical bars 8 1 47 5.40 1 251.31 251.31
B/n slab C-D & 3-5
Horizontal bars 8 1 39 6.40 1 249.11 249.11
8 1 17 3.35 1 56.18 56.18
8 1 12 4.64 1 54.61 54.61
Vertical bars 8 1 23 9.10 1 207.90 207.90
8 1 15 5.40 1 81.83 81.83
8 1 12 1.90 1 22.65 22.65

B/n slab D-E & 1-2


Horizontal bars 8 1 53 6.45 1 341.35 341.35
Vertical bars 8 1 47 7.26 1 338.43 338.43
B/n slab D-E & 2-3
Horizontal bars 8 1 51 6.45 1 328.95 328.95
Vertical bars 8 1 39 5.40 1 210.18 210.18
B/n slab D-E & 3-5
Horizontal bars 8 1 39 6.45 1 251.05 251.05
8 1 28 5.15 1 141.82 141.82
Vertical bars 8 1 37 9.10 1 333.20 333.20
8 1 11 5.40 1 58.98 58.98
B/n slab E-F & 1-2
Horizontal bars 8 1 53 6.26 1 331.30 331.30
Vertical bars 8 1 45 7.26 1 328.38 328.38
ON slab E-F & 3-5
Horizontal bars 8 1 39 6.26 1 243.66 243.66
Vertical bars 8 1 27 6.26 1 169.98 169.98
8 1 45 9.10 1 411.60 411.60

GROUND FLOOR SLAB Negative bar


on axis A B/n 1-2
Negative 8 1 53 2.30 1 120.84 120.84
ON AXIS A B/N 2-3
Negative 8 1 35 2.30 1 80.15 80.15
ON AXIS A B/N 3-4
Negative 8 1 35 2.30 1 80.15 80.15
ON AXIS A B/N 4-5
Negative 8 1 27 2.30 1 62.45 62.45
ON AXIS B B/N 1-2
Negative 12 1 57 3.40 1 193.23 193.23
ON AXIS B B/N 2-3
Negative 10 1 32 4.30 1 139.44 139.44
ON AXIS B B/N 3-4
Negative 10 1 32 4.30 1 139.44 139.44
ON AXIS B B/N 4-5
Negative 10 1 25 4.30 1 108.73 108.73
B/n AXIS B-B' &1-2
Negative 12 1 53 2.40 1 126.09 126.09
on axis B' B/n 4-5
Negative 10 1 25 1.80 1 45.51 45.51
on axis C B/n 1-2
Negative 12 1 54 2.30 1 123.05 123.05
on axis C B/n 2-3
Negative 10 1 32 4.30 1 139.44 139.44
on axis C B/n 3-4
Negative 10 1 35 4.30 1 150.50 150.50
on axis C' B/n 4-5
Negative 10 1 23 3.60 1 83.31 83.31
on axis D B/n 1-2
Negative 12 1 55 4.30 1 237.22 237.22
on axis D B/n 2-3
Negative 10 1 33 4.30 1 143.74 143.74
on axis D B/n 3-4
Negative 10 1 33 4.30 1 141.29 141.29
on axis D' B/n 4-5
Negative 10 1 23 2.92 1 67.58 67.58
on axis E B/n 1-2
Negative 12 1 55 4.30 1 237.22 237.22
on axis E B/n 2-3
Negative 8 1 34 2.30 1 78.20 78.20
on axis E B/n 3-4
Negative 10 1 32 4.30 1 139.44 139.44
on axis E B/n 4-5
Negative 10 1 25 4.30 1 108.73 108.73
on axis F B/n 1-2
Negative 8 1 53 2.30 1 120.84 120.84
on axis F B/n 3-4
Negative 8 1 35 2.30 1 80.15 80.15
on axis E B/n 4-8
Negative 8 1 27 2.30 1 62.45 62.45
ON axis 1 b/n A-B
Negative 8 1 46 2.65 1 121.90 121.90
on axis 1 b/n B-C
Negative 8 1 25 2.65 1 66.45 66.45
on axis 1 b/n C-D
Negative 8 1 43 2.65 1 113.75 113.75
on axis 1 b/n D-E
Negative 8 1 44 2.65 1 115.78 115.78
on axis 1 b/n E-F
Negative 8 1 45 2.65 1 118.84 118.84
on axis 2 b/n A-B
Negative 10 1 55 4.30 1 236.50 236.50
on axis 2 b/n B-C
Negative 10 1 31 4.30 1 131.15 131.15
on axis 2 b/n C-D
Negative 10 1 56 4.30 1 238.65 238.65
on axis 2 b/n D-E
Negative 10 1 56 4.30 1 238.65 238.65
on axis 2 b/n E-F
Negative 8 1 55 2.63 1 144.65 144.65
on axis 3 b/n A-B
Negative 10 1 40 3.64 1 144.04 144.04
on axis 3 b/n B-C
Negative 10 1 39 3.64 1 143.04 143.04
on axis 3 b/n C-D
Negative 10 1 40 3.64 1 145.34 145.34
on axis 3 b/n D-E
Negative 10 1 40 3.64 1 145.34 145.34
on axis 3 b/n E-F
Negative 8 1 43 1.95 1 82.95 82.95
on axis 4 b/n A-B
Negative 10 1 40 4.30 1 170.16 170.16
on axis 4 b/n B-C
Negative 10 1 32 4.30 1 135.76 135.76
on axis 4 b/n C-D
Negative 10 1 21 4.30 1 91.53 91.53
on axis 4 b/n D'-E
Negative 10 1 32 4.30 1 135.76 135.76
on axis 4 b/n E-F
Negative 10 1 40 4.30 1 170.16 170.16
on axis 5 b/n A-B
Negative 8 1 46 1.55 1 71.30 71.30
on axis 5 b/n B-C
Negative 8 1 34 1.55 1 53.18 53.18

B/n axis 5 b/n B'-D


Negative 10 1 12 1.15 1 13.88 13.88
B/n axis 5 b/n C-C'
Negative 8 1 23 1.55 1 35.41 35.41
B/n axis 5 b/n D'-E
Negative 8 1 36 1.55 1 56.16 56.16
B/n axis 5 b/n E-F
Negative 8 1 45 1.55 1 69.51 69.51

solid slab
basement floor mesh
B/n axis 1-2 b/n A-B
Horizontal bars 8 1 20 11.25 1 227.81 227.81
Vertical bars 8 1 56 4.05 1 227.81 227.81
B/n axis 1-2 b/n E-F
Horizontal bars 8 1 20 5.25 1 104.48 104.48
Vertical bars 8 1 26 3.98 1 104.48 104.48
Ground floor MESH
B/n axis 5-6 b/n B-C
Horizontal bars 8 1 29 3.60 1 104.40 104.40
Vertical bars 8 1 19 5.60 1 106.40 106.40
B/n axis 5-6 b/n C-D'
Horizontal bars 8 1 19 7.22 1 135.37 135.37
Vertical bars 8 1 37 3.55 1 131.70 131.70
B/n axis 5-6 b/n D'-E
Horizontal bars 8 1 19 4.63 1 87.97 87.97
Vertical bars 8 1 24 3.60 1 86.94 86.94
Footing Pad -
on axis 6 B/N (B,C,D',E)
F1 12 4 12 1.95 1 93.60 93.60
12 4 12 1.95 1 93.60 93.60
strip footing
on axis 1 B/N A-C 8 1 14 12.10 1 169.40 169.40
10 1 82 2.20 1 179.67 179.67

on axis A B/N 1-2 8 2 14 4.05 1 113.40 113.40


10 2 28 2.20 1 123.20 123.20

on axis F B/N 1-2 10 2 14 4.05 1 113.40 113.40


10 2 28 2.20 1 123.20 123.20

on axis 1 b/n E-F 8 1 14 6.17 1 86.38 86.38


10 1 42 2.20 1 92.69 92.69

on axis 2 B/N F-G 8 1 14 4.65 1 65.10 65.10


10 1 32 2.20 1 70.40 70.40

on axis G B/N 2-5 8 1 14 14.90 1 208.60 208.60


10 1 100 2.20 1 220.73 220.73

on axis 5 B/N F-G 8 1 14 4.88 1 68.32 68.32


10 1 34 2.20 1 73.77 73.77
Foundation Column ( ( -3.30)-
(+0.00) -
ON AXIS 6-(B,C,D',E)
C2 (40*40) 16 4 8 5.35 1 171.20 171.20
stirup 2 8 4 15 1.50 1 90.00 90.00
stirup 3 8 4 15 0.45 1 27.00 27.00
Basement COLUMN ( -3.30)- ( +0.00)

ON AXIS 1-(A,B,F)
C1 (30*30) 14 3 8 5.05 1 121.20 121.20
stirup 1 8 3 15 1.10 1 49.50 49.50
ON AXIS 1-(C,D,E)
C2(60*60) 20 3 8 5.40 1 129.60 129.60
stirup 4 8 3 15 2.30 1 103.50 103.50
stirup 5 8 3 15 0.65 1 29.25 29.25
ON AXIS 2-(G) -
C2 (40*40) 16 1 8 5.35 1 42.80 42.80
stirup 2 8 1 15 1.50 1 22.50 22.50
stirup 3 8 1 15 0.45 1 6.75 6.75
ON AXIS 2-(A,F)
C3(60*60) 20 2 8 5.40 1 86.40 86.40
stirup 4 8 2 15 2.30 1 69.00 69.00
stirup 5 8 2 15 0.65 1 19.50 19.50
ON AXIS 2-(B,C,D,E)
C4(80*80) 20 4 12 5.40 1 259.20 259.20
stirup 8 8 4 15 3.10 1 186.00 186.00
stirup 9 8 4 15 1.90 1 114.00 114.00
ON AXIS 3-(G) -
C2 (40*40) 16 1 8 5.35 1 42.80 42.80
stirup 2 8 1 15 1.50 1 22.50 22.50
stirup 3 8 1 15 0.45 1 6.75 6.75
ON AXIS 3-(A,E,F)
C3(60*60) 20 3 8 5.40 1 129.60 129.60
stirup 4 8 3 15 2.30 1 103.50 103.50
stirup 5 8 3 15 0.65 1 29.25 29.25
ON AXIS 3-(B,C,D)
C4(80*80) 20 3 12 5.40 1 194.40 194.40
stirup 8 8 3 15 3.10 1 139.50 139.50
stirup 9 8 3 15 1.90 1 85.50 85.50
ON AXIS 4-(G) -
C2 (40*40) 16 1 8 5.35 1 42.80 42.80
stirup 2 8 1 15 1.50 1 22.50 22.50
stirup 3 8 1 15 0.45 1 6.75 6.75
ON AXIS 4-(A,B,B',E,F)
C3(60*60) 20 5 8 5.40 1 216.00 216.00
stirup 4 8 5 15 2.30 1 172.50 172.50
stirup 5 8 5 15 0.65 1 48.75 48.75
ON AXIS 5-(A-B-C'-E-F-G) -
C2 (40*40) 16 6 8 5.35 1 256.80 256.80
stirup 2 8 6 15 1.50 1 135.00 135.00
stirup 3 8 6 15 0.45 1 40.50 40.50
ON AXIS 5-(B',D')
C3(60*60) 20 2 8 5.40 1 86.40 86.40
stirup 4 8 2 15 2.30 1 69.00 69.00
stirup 5 8 2 15 0.65 1 19.50 19.50
ON AXIS 5-(B,C,D',E) -
C2 (40*40) 16 4 8 5.35 1 171.20 171.20
stirup 2 8 4 15 1.50 1 90.00 90.00
stirup 3 8 4 15 0.45 1 27.00 27.00
Total length (m) - 17,602.87 6,992.68 1,553.78 2,962.75 14,806.50 9,675.71
Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467
Total weight (Kg) - 6,947.27 4,312.16 1,379.76 3,580.98 23,374.55 23,866.78
-
Lift shear Wall -
section 4-4
W2 14 2 18 3.90 1 140.47 140.47
14 2 18 3.34 1 120.24 120.24
10 2 18 5.60 1 201.60 201.60

W3 14 1 13 3.92 1 50.96 50.96


14 1 13 3.34 1 43.42 43.42
10 1 12 5.00 1 60.00 60.00
-
W4 14 1 8 1.50 1 11.50 11.50
D 10 1 13 5.00 1 65.00 65.00
14 1 10 3.92 1 40.51 40.51
10 1 10 3.34 1 34.51 34.51
E 10 1 38 1.70 1 64.60 64.60
Retaining wall
Horizontal (w1)
ON AXIS 5 A-G
8 1 23 12.00 1 274.40 274.40
8 1 23 12.00 1 274.40 274.40
8 1 23 12.00 1 274.40 274.40
8 1 23 12.00 1 274.40 274.40
8 1 23 6.40 1 146.35 146.35
8 1 23 6.40 1 146.35 146.35
8 1 23 7.15 1 163.50 163.50
8 1 23 7.15 1 163.50 163.50
vertical
ON AXIS 5 b/n (A-B-B'-C-C') 10 1 91 3.43 1 312.59 312.59
10 1 91 3.43 1 312.59 312.59
u shape (b) 10 1 91 3.28 1 298.92 298.92
ON AXIS 5 b/n (C'-D-D')
10 1 19 3.02 1 57.38 57.38
10 1 19 3.02 1 57.38 57.38
10 1 9 3.43 1 30.87 30.87
10 1 9 3.43 1 30.87 30.87
u shape (b) 10 1 22 3.28 1 70.85 70.85
ON AXIS 5 b/n (D'-E)
10 1 6 3.43 1 19.21 19.21
10 1 6 3.43 1 19.21 19.21
10 1 21 3.02 1 63.42 63.42
10 1 21 3.02 1 63.42 63.42
10 1 6 3.43 1 19.21 19.21
10 1 6 3.43 1 19.21 19.21
u shape (b) 10 1 30 3.28 1 99.06 99.06
ON AXIS 1 b/n (E-G)
10 1 73 3.43 1 248.79 248.79
10 1 73 3.43 1 248.79 248.79
u shape (b) 10 1 73 3.28 1 237.91 237.91
horizontal (w2)
ON AXIS 2 b/n (F-G) 8 1 23 6.20 1 141.77 141.77
8 1 23 6.20 1 141.77 141.77
vertical 10 1 35 3.85 1 132.95 132.95
10 1 35 3.85 1 132.95 132.95
u shape (b) 10 1 35 1.62 1 55.94 55.94
Horizontal (w3)
ON AXIS 1 A-F
8 1 23 6.75 1 154.35 154.35
8 1 23 6.75 1 154.35 154.35
8 1 23 6.00 1 137.20 137.20
8 1 23 6.00 1 137.20 137.20
8 1 23 12.00 1 274.40 274.40
8 1 23 12.00 1 274.40 274.40
8 1 23 7.22 1 165.10 165.10
8 1 23 7.22 1 165.10 165.10
vertical
ON AXIS 1 b/n (A-C) 10 1 77 3.85 1 296.45 296.45
10 1 77 3.85 1 296.45 296.45
ON AXIS 1 b/n (C-E)
10 1 33 3.43 1 113.19 113.19
10 1 33 3.43 1 113.19 113.19
10 1 21 3.02 1 63.42 63.42
10 1 21 3.02 1 63.42 63.42
u shape (b) 10 1 73 3.28 1 239.44 239.44
ON AXIS 1 b/n (E-F)
10 1 39 3.85 1 150.15 150.15
10 1 39 3.85 1 150.15 150.15
u shape (b) 10 1 39 1.62 1 63.18 63.18
Horizontal (w4)
ON AXIS A b/n (1-5) 8 1 23 6.75 1 154.35 154.35
8 1 23 6.75 1 154.35 154.35
8 1 23 6.40 1 146.35 146.35
8 1 23 6.40 1 146.35 146.35
8 1 23 9.15 1 209.23 209.23
8 1 23 9.15 1 209.23 209.23
VERTICAL
ON AXIS A b/n (1-1') 10 1 30 3.85 1 114.22 114.22
10 1 30 3.85 1 114.22 114.22
10 1 17 3.43 1 58.31 58.31
10 1 17 3.43 1 58.31 58.31
u shape (b) 10 1 17 3.28 1 55.76 55.76
ON AXIS A b/n (2-4) 10 1 20 3.43 1 67.46 67.46
10 1 20 3.43 1 67.46 67.46
10 1 41 3.02 1 123.82 123.82
u shape (b) 10 1 60 3.28 1 195.71 195.71
ON AXIS A b/n (4-5) 10 1 24 3.43 1 81.18 81.18
10 1 24 3.43 1 81.18 81.18
u shape (b) 10 1 24 3.28 1 77.63 77.63

Horizontal (w5)
ON AXIS A b/n (1-2) 8 1 23 7.70 1 176.07 176.07
8 1 23 7.70 1 176.07 176.07
VERTICAL
ON AXIS A b/n (1-1') 10 1 30 3.85 1 114.22 114.22
10 1 30 3.85 1 114.22 114.22
ON AXIS A b/n (1'-2) 10 1 17 3.43 1 58.31 58.31
10 1 17 3.43 1 58.31 58.31
u shape (b) 10 1 17 3.28 1 55.76 55.76

Horizontal (w6)
ON AXIS A b/n (2-5) 8 1 23 12.00 1 274.40 274.40
8 1 23 12.00 1 274.40 274.40
8 1 23 2.95 1 67.46 67.46
8 1 23 2.95 1 67.46 67.46
VERTICAL
10 1 86 3.43 1 293.84 293.84
10 1 86 3.43 1 293.84 293.84
u shape (b) 10 1 86 3.28 1 280.99 280.99

Total length (m) - 5,518.64 6,870.97 - 407.10 - -


Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467
Total weight (Kg) - 2,179.86 4,239.39 - 492.18 - -

Total length (m) - 23,121.509 13,863.644 1,553.780 3,369.847 14,806.499 9,675.710


Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467
Total weight (Kg) - 9,125.30 8,549.26 1,379.76 4,073.03 23,374.55 23,866.78
OTT G+7 L-SHAPE RESIDENCE

Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No.__________
Consultant: K2N Architecture and Engineering Consultancy PLC
Location Dia No. mem. No. bars Len Floor Total Dia 6 Dia 8 Dia 10 Dia 12 Dia 14 Dia 16 Dia 20 Dia 24
Elvation coloumn
Ground elvation coloumn( +3.30)
on axis 1-(A,B,F)
C1 (30*30) 14 3 8 3.52 1 84.48 84.48
stirup 1 8 3 15 1.10 1 49.50 49.50

on axis 1-(C,D,E)
C3 (60*60) 20 3 8 3.94 1 94.56 94.56
stirup 4 8 3 15 2.30 1 103.50 103.50
stirup 5 8 3 30 0.65 1 58.50 58.50

on axis 2-(A)
C3 (60*60) 20 1 8 3.94 1 31.52 31.52
stirup 4 8 1 15 2.30 1 34.50 34.50
stirup 5 8 1 30 0.65 1 19.50 19.50

on axis 2-(B,C,D,E,F)
C4 (60*60) 20 5 12 3.94 1 236.40 236.40
stirup 8 8 5 15 3.10 1 232.50 232.50
stirup 9 8 5 30 1.90 1 285.00 285.00

on axis 2-(G) -
C1 (30*30) 14 1 6 3.52 1 21.12 21.12
stirup 1 8 1 15 1.10 1 16.50 16.50

on axis 3-(A)
C3 (60*60) 20 1 8 3.94 1 31.52 31.52
stirup 4 8 1 15 2.30 1 34.50 34.50
stirup 5 8 1 30 0.65 1 19.50 19.50

-
on axis 3-(B,C,D,E,F)
C4 (60*60) 20 5 12 3.94 1 236.40 236.40
stirup 8 8 5 15 3.10 1 232.50 232.50
stirup 9 8 5 30 1.90 1 285.00 285.00

on axis 3-(G) -
C1 (30*30) 14 1 8 3.52 1 28.16 28.16
stirup 1 8 1 15 1.10 1 16.50 16.50

on axis 4-(A,B,D',E,F)
C3 (60*60) 20 5 8 3.94 1 157.60 157.60
stirup 4 8 5 15 2.30 1 172.50 172.50
stirup 5 8 5 30 0.65 1 97.50 97.50

on axis 4-(G) -
C1 (30*30) 14 1 8 3.52 1 28.16 28.16
stirup 1 8 1 15 1.10 1 16.50 16.50

on axis 5-(B',D')
C3 (60*60) 20 2 8 3.94 1 63.04 63.04
stirup 4 8 2 15 2.30 1 69.00 69.00
stirup 5 8 2 30 0.65 1 39.00 39.00

on axis 5-(A,B,C',E,F,G) -
C1 (30*30) 14 6 8 3.52 1 168.96 168.96
stirup 1 8 6 15 1.10 1 99.00 99.00

on axis 6-(B,C',D',E-) -
C1 (30*30) 14 4 8 3.52 1 112.64 112.64
stirup 1 8 4 15 1.10 1 66.00 66.00

1 st elvation coloumn (+6.60) -


on axis 1-(C,D,E)
C3 (60*60) 20 3 8 3.94 1 94.56 94.56
stirup 4 8 3 15 2.30 1 103.50 103.50
stirup 5 8 3 30 0.65 1 58.50 58.50

on axis 2-(A,B,C,D,E,F)
C3 (60*60) 20 6 8 3.94 1 189.12 189.12
stirup 4 8 6 15 2.30 1 207.00 207.00
stirup 5 8 6 30 0.65 1 117.00 117.00

on axis 3-(A,B,C,D,E,F)
C3 (60*60) 20 6 8 3.94 1 189.12 189.12
stirup 4 8 6 15 2.30 1 207.00 207.00
stirup 5 8 6 30 0.65 1 117.00 117.00

on axis 4-(A,B,D',E,F)
C3 (60*60) 20 5 8 3.94 1 157.60 157.60
stirup 4 8 5 15 2.30 1 172.50 172.50
stirup 5 8 5 30 0.65 1 97.50 97.50

on axis 5-(B',D')
C3 (60*60) 20 2 8 3.94 1 63.04 63.04
stirup 4 8 2 15 2.30 1 69.00 69.00
stirup 5 8 2 30 0.65 1 39.00 39.00
on axis 5-(C') -
C1 (30*30) 14 1 8 3.52 1 28.16 28.16
stirup 1 8 1 15 1.10 1 16.50 16.50
2 nd elvation coloumn (+9.90) -

on axis 1-(C,D,E)
C3 (60*60) 20 3 8 3.94 1 94.56 94.56
stirup 4 8 3 15 2.30 1 103.50 103.50
stirup 5 8 3 30 0.65 1 58.50 58.50

on axis 2-(A,B,C,D,E,F)
C3 (60*60) 20 6 8 3.94 1 189.12 189.12
stirup 4 8 6 15 2.30 1 207.00 207.00
stirup 5 8 6 30 0.65 1 117.00 117.00

on axis 3-(A,B,C,D,E,F)
C3 (60*60) 20 6 8 3.94 1 189.12 189.12
stirup 4 8 6 15 2.30 1 207.00 207.00
stirup 5 8 6 30 0.65 1 117.00 117.00

on axis 4-(A,B,D',E,F)
C3 (60*60) 20 5 8 3.94 1 157.60 157.60
stirup 4 8 5 15 2.30 1 172.50 172.50
stirup 5 8 5 30 0.65 1 97.50 97.50

on axis 5-(B',D')
C3 (60*60) 20 2 8 3.94 1 63.04 63.04
stirup 4 8 2 15 2.30 1 69.00 69.00
stirup 5 8 2 30 0.65 1 39.00 39.00
on axis 5-(C') -
C1 (30*30) 14 1 8 3.52 1 28.16 28.16
stirup 1 8 1 15 1.10 1 16.50 16.50

3 rd elvation coloumn (+13.20) -

on axis 1-(C,D,E)
C3 (60*60) 20 3 8 3.94 1 94.56 94.56
stirup 4 8 3 15 2.30 1 103.50 103.50
stirup 5 8 3 30 0.65 1 58.50 58.50

on axis 2-(A,B,C,D,E,F)
C3 (60*60) 20 6 8 3.94 1 189.12 189.12

235
OTT G+7 L-SHAPE RESIDENCE

stirup 4 8 6 15 2.30 1 207.00 207.00


stirup 5 8 6 30 0.65 1 117.00 117.00

on axis 3-(A,B,C,D,EF)
C3 (60*60) 20 6 8 3.94 1 189.12 189.12
stirup 4 8 6 15 2.30 1 207.00 207.00
stirup 5 8 6 30 0.65 1 117.00 117.00

on axis 4-(A,B,D',E,F)
C3 (60*60) 20 5 8 3.94 1 157.60 157.60
stirup 4 8 5 15 2.30 1 172.50 172.50
stirup 5 8 5 30 0.65 1 97.50 97.50

on axis 5-(B',D')
C3 (60*60) 20 2 8 3.94 1 63.04 63.04
stirup 4 8 2 15 2.30 1 69.00 69.00
stirup 5 8 2 30 0.65 1 39.00 39.00
on axis 5-(C') -
C1 (30*30) 14 1 8 3.52 1 28.16 28.16
stirup 1 8 1 15 1.10 1 16.50 16.50

4th -8th elvation coloumn (+16.50-29.70)

on axis 1-(C,D,E)
C3 (40*40) 16 3 8 3.94 5 472.80 472.80
stirup 2 8 3 15 1.50 5 337.50 337.50
stirup 3 8 3 30 0.45 5 202.50 202.50

on axis 2-(A,B,C,D,E,F)
C3 (40*40) 16 6 8 3.94 5 945.60 945.60
stirup 2 8 6 15 1.50 5 675.00 675.00
stirup 3 8 6 30 0.45 5 405.00 405.00

on axis 3-(A,B,C,D,E,F)
C3 (40*40) 16 6 8 3.94 5 945.60 945.60
stirup 2 8 6 15 1.50 5 675.00 675.00
stirup 3 8 6 30 0.45 5 405.00 405.00

on axis 4-(A,B,D',E,F)
C3 (40*40) 16 5 8 3.94 5 788.00 788.00
stirup 2 8 5 15 1.50 5 562.50 562.50
stirup 3 8 5 30 0.45 5 337.50 337.50

on axis 5-(B',D')
C3 (40*40) 16 2 8 3.94 5 315.20 315.20
stirup 2 8 2 15 1.50 5 225.00 225.00
stirup 3 8 2 30 0.45 5 135.00 135.00
on axis 5-(C') -
C1 (30*30) 14 1 8 3.52 5 140.80 140.80
stirup 1 8 1 15 1.10 5 82.50 82.50
WATER TANKER COLUMN -
on axis 4&5-(B',D')
C1 (40*40) 16 3 8 3.18 1 76.32 76.32
STIRRUP 1 8 3 14 1.50 1 60.75 60.75
STIRRUP 2 8 3 14 1.10 1 44.55 44.55

Total length (m) - 9,708.30 - - 668.80 3,543.52 2,931.36 -

Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552

Total weight (Kg) - 3,834.78 - - 808.58 5,595.22 7,231.67 -

TYPICAL FLOOR BEAM -


FIRST FLOOR
FB-1
ON AXIS 1 b/n C-E
TOP BAR 14 1 2 10.05 1 20.10 20.10
14 1 2 4.05 1 8.10 8.10
Negative 14 1 2 2.45 1 4.90 4.90
14 1 2 4.00 1 8.00 8.00
14 1 2 2.45 1 4.90 4.90
BOTTOM BAR 16 1 3 6.70 1 20.10 20.10
16 1 3 6.70 1 20.10 20.10
STIRUP 8 1 37 1.40 1 51.80 51.80
8 1 37 1.40 1 51.80 51.80
FB-2
ON AXIS 2 b/n A-G
TOP BAR 16 1 2 10.05 1 20.10 20.10
16 1 2 6.65 1 13.30 13.30
20 1 2 6.65 1 13.30 13.30
16 1 2 6.70 1 13.40 13.40
16 1 2 9.45 1 18.90 18.90
Negative 14 1 2 2.45 1 4.90 4.90
16 1 2 4.00 1 8.00 8.00
20 1 2 4.00 1 8.00 8.00
20 1 2 4.00 1 8.00 8.00
20 1 2 4.00 1 8.00 8.00
16 1 2 3.80 1 7.60 7.60
BOTTOM BAR 16 1 3 6.80 1 20.40 20.40
16 1 3 6.80 1 20.40 20.40
20 1 4 6.80 1 27.20 27.20
20 1 4 6.80 1 27.20 27.20
16 1 3 6.70 1 20.10 20.10
14 1 3 6.15 1 18.45 18.45
STIRUP 8 1 177 1.40 1 247.22 247.22
10 1 91 1.40 1 127.40 127.40
FB-3
ON AXIS 3 b/n A-G
TOP BAR 20 1 2 10.05 1 20.10 20.10
20 1 2 6.65 1 13.30 13.30
20 1 2 6.65 1 13.30 13.30
20 1 2 6.70 1 13.40 13.40
20 1 2 6.30 1 12.60 12.60
16 1 2 3.70 1 7.40 7.40
Negative 20 1 3 2.45 1 7.35 7.35
20 1 3 4.00 1 12.00 12.00
20 1 3 4.00 1 12.00 12.00
20 1 3 4.00 1 12.00 12.00
20 1 3 4.00 1 12.00 12.00
20 1 3 3.80 1 11.40 11.40
BOTTOM BAR 20 1 4 6.80 1 27.20 27.20
20 1 2 6.80 1 13.60 13.60
16 1 2 6.80 1 13.60 13.60
20 1 2 6.80 1 13.60 13.60
16 1 2 6.80 1 13.60 13.60
20 1 2 6.80 1 13.60 13.60
16 1 2 6.80 1 13.60 13.60
20 1 2 6.70 1 13.40 13.40
16 1 2 6.70 1 13.40 13.40
16 1 3 6.15 1 18.45 18.45
STIRUP 10 1 542 1.40 1 758.80 758.80
10 1 50 1.40 1 69.58 69.58
FB-4
ON AXIS 4 b/n A-B'
TOP BAR 16 1 2 8.85 1 17.70 17.70
16 1 2 4.00 1 8.00 8.00
Negative 20 1 2 2.45 1 4.90 4.90
20 1 2 3.60 1 7.20 7.20
16 1 2 2.05 1 4.10 4.10
BOTTOM BAR 16 1 4 6.80 1 27.20 27.20
14 1 4 6.75 1 27.00 27.00
STIRUP 10 1 55 1.40 1 77.00 77.00
10 1 46 1.40 1 64.12 64.12
FB-5

236
OTT G+7 L-SHAPE RESIDENCE

ON AXIS 4 b/n C-G


TOP BAR 16 1 2 8.95 1 17.90 17.90
16 1 2 6.70 1 13.40 13.40
16 1 2 9.45 1 18.90 18.90
Negative 20 1 2 2.14 1 4.28 4.28
20 1 2 4.00 1 8.00 8.00
20 1 2 3.62 1 7.24 7.24
20 1 2 3.80 1 7.60 7.60
BOTTOM BAR 16 1 4 6.70 1 26.80 26.80
16 1 3 5.70 1 17.10 17.10
16 1 4 6.70 1 26.80 26.80
16 1 3 6.10 1 18.30 18.30
STIRUP 10 1 152 1.40 1 212.38 212.38
8 1 33 1.40 1 46.85 46.85

FB-6
ON AXIS 5 b/n A-G
TOP BAR 14 1 2 9.95 1 19.90 19.90
16 1 2 6.75 1 13.50 13.50
14 1 2 7.25 1 14.50 14.50
14 1 2 6.10 1 12.20 12.20
14 1 2 6.30 1 12.60 12.60
14 1 2 3.70 1 7.40 7.40
Negative 14 1 2 3.60 1 7.20 7.20
16 1 2 3.95 1 7.90 7.90
14 1 1 3.95 1 3.95 3.95
14 1 2 2.60 1 5.20 5.20
14 1 1 3.80 1 3.80 3.80
BOTTOM BAR 14 1 3 6.80 1 20.40 20.40
14 1 3 5.60 1 16.80 16.80
14 1 3 9.15 1 27.45 27.45
14 1 3 5.70 1 17.10 17.10
14 1 3 6.70 1 20.10 20.10
14 1 3 6.15 1 18.45 18.45
STIRUP 8 1 213 1.40 1 298.85 298.85

FB-7
ON AXIS 6 b/n A-G
TOP BAR 14 1 2 10.65 1 21.30 21.30
14 1 2 9.25 1 18.50 18.50
Negative 16 1 2 4.40 1 8.80 8.80
16 1 2 4.05 1 8.10 8.10
BOTTOM BAR 14 1 2 6.45 1 12.90 12.90
16 1 3 7.45 1 22.35 22.35
14 1 2 5.30 1 10.60 10.60
STIRUP 8 1 116 1.40 1 161.93 161.93

FB-8
ON AXIS A -F-G b/n 2-5
TOP BAR 14 3 2 7.25 1 43.50 43.50
14 3 2 8.30 1 49.80 49.80
BOTTOM BAR 14 3 2 4.30 1 25.80 25.80
14 3 2 5.60 1 33.60 33.60
14 3 2 5.50 1 33.00 33.00
STIRUP 8 3 79 1.40 1 331.80 331.80

FB-9
ON AXIS B b/n 2-6
TOP BAR 14 1 2 6.80 1 13.60 13.60
14 1 2 5.05 1 10.10 10.10
14 1 2 8.40 1 16.80 16.80
Negative 14 1 1 2.56 1 2.56 2.56
BOTTOM BAR 14 1 2 4.60 1 9.20 9.20
14 1 2 4.30 1 8.60 8.60
14 1 2 5.60 1 11.20 11.20
14 1 2 5.60 1 11.20 11.20
STIRUP 8 1 102 1.40 1 142.33 142.33

FB-10
ON AXIS B-C b/n 2-3
TOP BAR 14 1 3 8.10 1 24.30 24.30
14 1 3 7.40 1 22.20 22.20
STIRUP 14 1 46 1.40 1 64.40 64.40

FB-11
ON AXIS C b/n 1-4
TOP BAR 14 1 2 8.55 1 17.10 17.10
20 1 2 10.50 1 21.00 21.00
Negative 16 1 2 3.95 1 7.90 7.90
20 1 2 2.75 1 5.50 5.50
BOTTOM BAR 14 1 2 5.70 1 11.40 11.40
14 1 2 5.70 1 11.40 11.40
16 1 4 7.70 1 30.80 30.80
STIRUP 8 1 62 1.40 1 86.33 86.33
10 1 54 1.40 1 76.07 76.07
FB-12
ON AXIS C-C'& D--E b/n 1-2
TOP BAR 16 2 2 8.10 1 32.40 32.40
Negative 16 2 1 2.80 1 5.60 5.60
16 2 1 2.80 1 5.60 5.60
BOTTOM BAR 14 2 2 7.40 1 29.60 29.60
16 2 2 7.40 1 29.60 29.60
STIRUP 8 2 46 1.40 1 128.80 128.80

FB-13
ON AXIS D b/n 1-4
TOP BAR 14 1 2 8.55 1 17.10 17.10
24 1 2 10.50 1 21.00 21.00
Negative 14 1 1 2.10 1 2.10 2.10
14 1 1 3.30 1 3.30 3.30
24 1 3 3.95 1 11.85 11.85
24 1 3 2.75 1 8.25 8.25
BOTTOM BAR 14 1 2 5.70 1 11.40 11.40
14 1 2 5.70 1 11.40 11.40
20 1 5 7.70 1 38.50 38.50
STIRUP 8 1 62 1.40 1 86.33 86.33
STIRUP 10 1 130 1.40 1 182.00 182.00

FB-14
ON AXIS E b/n 1-6
TOP BAR 14 1 2 6.90 1 13.80 13.80
14 1 2 10.00 1 20.00 20.00
20 1 2 10.55 1 21.10 21.10
Negative 16 1 2 4.00 1 8.00 8.00
20 1 2 2.80 1 5.60 5.60
BOTTOM BAR 14 1 2 8.40 1 16.80 16.80
14 1 2 10.60 1 21.20 21.20
16 1 4 7.70 1 30.80 30.80
STIRUP 8 1 103 1.40 1 144.20 144.20
10 1 109 1.40 1 152.13 152.13

FB-15
ON AXIS D' b/n 4-6
TOP BAR 14 1 2 9.15 1 18.30 18.30
Negative 14 1 1 2.60 1 2.60 2.60
BOTTOM BAR 14 1 3 8.45 1 25.35 25.35
STIRUP 8 1 44 1.40 1 62.07 62.07

237
OTT G+7 L-SHAPE RESIDENCE

FB-16
ON AXIS C' b/n 4-5
TOP BAR 14 1 3 4.80 1 14.40 14.40
Negative 14 1 2 4.10 1 8.20 8.20
STIRUP 8 1 24 1.40 1 33.60 33.60

FB-17
ON AXIS C b/n 5-6
TOP BAR 14 1 2 6.75 1 13.50 13.50
Negative 14 1 2 3.40 1 6.80 6.80
BOTTOM BAR 14 1 2 6.05 1 12.10 12.10
STIRUP 8 1 31 1.40 1 42.93 42.93

FB-18
ON AXIS B' b/n 4-5
TOP BAR 14 1 2 4.90 1 9.80 9.80
Negative 14 1 1 1.70 1 1.70 1.70
BOTTOM BAR 14 1 3 4.20 1 12.60 12.60
8 1 24 1.40 1 33.04 33.04
SECOND-THIRD FLOOR
FB-1
ON AXIS 1 b/n C-E
TOP BAR 16 1 2 10.05 2 40.20 40.20
16 1 2 4.05 2 16.20 16.20
Negative 16 1 2 2.45 2 9.80 9.80
16 1 2 4.00 2 16.00 16.00
16 1 2 2.45 2 9.80 9.80
BOTTOM BAR 16 1 4 6.70 2 53.60 53.60
16 1 3 6.70 2 40.20 40.20
STIRUP 8 1 109 1.40 2 305.20 305.20

FB-2
ON AXIS 2 b/n A-F
TOP BAR 14 1 2 10.05 2 40.20 40.20
16 1 2 6.65 2 26.60 26.60
16 1 2 6.65 2 26.60 26.60
16 1 2 10.05 2 40.20 40.20
Negative 14 1 2 2.45 2 9.80 9.80
16 1 2 4.00 2 16.00 16.00
20 1 2 4.00 2 16.00 16.00
20 1 2 4.00 2 16.00 16.00
20 1 2 4.00 2 16.00 16.00
16 1 2 2.45 2 9.80 9.80
BOTTOM BAR 16 1 3 6.80 2 40.80 40.80
16 1 3 6.80 2 40.80 40.80
20 1 3 6.80 2 40.80 40.80
20 1 3 6.80 2 40.80 40.80
16 1 3 6.80 2 40.80 40.80
STIRUP 8 1 91 1.40 2 254.80 254.80
10 1 136 1.40 2 380.80 380.80

FB-3
ON AXIS 3 b/n A-F
TOP BAR 20 1 2 10.05 2 40.20 40.20
20 1 2 6.65 2 26.60 26.60
20 1 2 6.65 2 26.60 26.60
20 1 2 10.05 2 40.20 40.20
Negative 20 1 3 2.45 2 14.70 14.70
20 1 3 4.00 2 24.00 24.00
20 1 3 4.00 2 24.00 24.00
20 1 3 4.00 2 24.00 24.00
20 1 3 4.00 2 24.00 24.00
20 1 3 2.45 2 14.70 14.70
BOTTOM BAR 20 1 3 6.80 2 40.80 40.80
20 1 3 6.80 2 40.80 40.80
20 1 3 6.80 2 40.80 40.80
20 1 3 6.80 2 40.80 40.80
20 1 3 6.80 2 40.80 40.80
STIRUP 10 1 271 1.40 2 758.80 758.80

FB-4
ON AXIS 4 b/n A-B'
TOP BAR 16 1 2 8.85 2 35.40 35.40
16 1 2 4.00 2 16.00 16.00
Negative 16 1 2 2.45 2 9.80 9.80
20 1 2 4.00 2 16.00 16.00
16 1 2 2.45 2 9.80 9.80
BOTTOM BAR 16 1 4 6.80 2 54.40 54.40
16 1 4 6.75 2 54.00 54.00
STIRUP 8 1 83 1.40 2 233.33 233.33

FB-5
ON AXIS 4 b/n C-F
TOP BAR 16 1 2 8.95 2 35.80 35.80
16 1 2 10.05 2 40.20 40.20
Negative 20 1 2 2.14 2 8.56 8.56
20 1 2 4.00 2 16.00 16.00
20 1 2 3.62 2 14.48 14.48
20 1 2 2.45 2 9.80 9.80
BOTTOM BAR 16 1 3 6.70 2 40.20 40.20
16 1 3 5.70 2 34.20 34.20
16 1 3 6.80 2 40.80 40.80
STIRUP 8 1 127 1.40 2 354.43 354.43

FB-6
ON AXIS 5 b/n B'-D'
TOP BAR 16 1 2 9.70 2 38.80 38.80
Negative 16 1 2 3.20 2 12.80 12.80
16 1 2 3.20 2 12.80 12.80
BOTTOM BAR 14 1 3 9.10 2 54.60 54.60
STIRUP 8 1 51 1.40 2 141.68 141.68

FB-7
on AXIS A,F b/n 2-4
TOP BAR 14 2 2 11.40 2 91.20 91.20
BOTTOM BAR 14 2 2 10.70 2 85.60 85.60
STIRUP 8 2 60 1.40 2 334.13 334.13

FB-8
on AXIS B b/n 2-4
TOP BAR 14 1 2 11.30 2 45.20 45.20
BOTTOM BAR 14 1 2 10.60 2 42.40 42.40
STIRUP 8 1 60 1.40 2 167.07 167.07

FB-9
on AXISC, E b/n 1-4
TOP BAR 14 2 2 8.60 2 68.80 68.80
16 2 2 10.50 2 84.00 84.00
Negative 20 2 2 3.95 2 31.60 31.60
20 2 2 2.75 2 22.00 22.00
BOTTOM BAR at 2nd floor 14 2 2 5.77 1 23.08 23.08
at 3rd floor 14 2 2 5.80 1 23.20 23.20
14 2 2 5.70 2 45.60 45.60
14 2 2 7.70 2 61.60 61.60
16 2 2 7.70 2 61.60 61.60

238
OTT G+7 L-SHAPE RESIDENCE

STIRUP 8 2 102 1.40 2 573.07 573.07

FB-10
on AXIS D b/n 1-4
TOP BAR 14 1 2 8.60 2 34.40 34.40
24 1 2 10.50 2 42.00 42.00
Negative 14 1 1 3.30 2 6.60 6.60
24 1 2 3.95 2 15.80 15.80
at 2nd floor 24 1 3 2.75 1 8.25 8.25
BOTTOM BAR at 2nd floor 14 1 2 5.78 1 11.56 11.56
14 1 2 5.70 2 22.80 22.80
at 2nd floor 16 1 2 7.70 1 15.40 15.40
at 2nd floor 20 1 2 7.70 1 15.40 15.40
Negative at 3rd floor 24 1 3 3.03 1 9.09 9.09
BOTTOM BAR at 3rd floor 14 1 2 5.80 1 11.60 11.60
at 3rd floor 16 1 2 8.70 1 17.40 17.40
at 3rd floor 20 1 2 8.70 1 17.40 17.40
STIRUP 8 1 102 1.40 2 286.53 286.53

FB-11
on AXIS D b/n 4-5
TOP BAR 14 1 2 5.10 2 20.40 20.40
Negative 14 1 1 1.70 2 3.40 3.40
BOTTOM BAR 14 1 3 4.40 2 26.40 26.40
STIRUP 8 1 24 1.40 2 66.27 66.27

FB-12
on AXIS B b/n 4-5
TOP BAR 14 1 2 4.90 2 19.60 19.60
Negative 14 1 1 1.70 2 3.40 3.40
BOTTOM BAR 14 1 3 4.20 2 25.20 25.20
STIRUP 8 1 24 1.40 2 66.27 66.27

FB-13
on AXIS C b/n 4-5
TOP BAR 14 1 2 4.90 2 19.60 19.60
Negative 14 1 1 1.70 2 3.40 3.40
BOTTOM BAR 14 1 3 4.20 2 25.20 25.20
STIRUP 8 1 24 1.40 2 66.27 66.27

Beam b/n 1-2 & C-E ( 2 beams) 16 2 2 8.10 2 64.80 64.80


Remain / no desidn 16 2 1 2.80 2 11.20 11.20
Taken from 1st floor (FB-12) 16 2 1 2.80 2 11.20 11.20
14 2 2 7.40 2 59.20 59.20
16 2 2 7.40 2 59.20 59.20
STIRUP 8 2 46 1.40 2 257.60 257.60
Fourth- Eighth floor
FB-1
ON AXIS 1 b/n C-E
TOP BAR 16 1 2 10.05 5 100.50 100.50
16 1 2 4.05 5 40.50 40.50
Negative 16 1 2 2.45 5 24.50 24.50
16 1 2 4.00 5 40.00 40.00
16 1 2 2.45 5 24.50 24.50
BOTTOM BAR 16 1 4 6.70 5 134.00 134.00
16 1 3 6.70 5 100.50 100.50
STIRUP 8 1 109 1.40 5 763.00 763.00

FB-2
ON AXIS 2 b/n A-F
TOP BAR 14 1 2 10.05 5 100.50 100.50
16 1 2 6.65 5 66.50 66.50
16 1 2 6.65 5 66.50 66.50
16 1 2 10.05 5 100.50 100.50
Negative bar 14 1 2 2.45 5 24.50 24.50
16 1 2 4.00 5 40.00 40.00
20 1 2 4.00 5 40.00 40.00
20 1 2 4.00 5 40.00 40.00
20 1 2 4.00 5 40.00 40.00
16 1 2 2.45 5 24.50 24.50
BOTTOM BAR 16 1 3 6.80 5 102.00 102.00
16 1 3 6.80 5 102.00 102.00
20 1 3 6.80 5 102.00 102.00
20 1 3 6.80 5 102.00 102.00
16 1 3 6.80 5 102.00 102.00
STIRUP 8 1 91 1.40 5 637.00 637.00
10 1 136 1.40 5 952.00 952.00
FB-3
ON AXIS 3 b/n A-F
TOP BAR 20 1 2 10.05 5 100.50 100.50
20 1 2 6.65 5 66.50 66.50
20 1 2 6.65 5 66.50 66.50
20 1 2 10.05 5 100.50 100.50
Negative bar 20 1 3 2.45 5 36.75 36.75
20 1 3 4.00 5 60.00 60.00
20 1 3 4.00 5 60.00 60.00
20 1 3 4.00 5 60.00 60.00
20 1 3 4.00 5 60.00 60.00
20 1 3 2.45 5 36.75 36.75
BOTTOM BAR 20 1 3 6.80 5 102.00 102.00
20 1 3 6.80 5 102.00 102.00
20 1 3 6.80 5 102.00 102.00
20 1 3 6.80 5 102.00 102.00
20 1 3 6.80 5 102.00 102.00
STIRUP 10 1 271 1.40 5 1,897.00 1,897.00

FB-4
ON AXIS 4 b/n A-B'
TOP BAR 16 1 2 8.85 5 88.50 88.50
16 1 2 4.00 5 40.00 40.00
Negative bar 16 1 2 2.45 5 24.50 24.50
20 1 2 4.00 5 40.00 40.00
16 1 2 2.45 5 24.50 24.50
BOTTOM BAR 16 1 4 6.80 5 136.00 136.00
16 1 4 6.75 5 135.00 135.00
STIRUP 8 1 46 1.40 5 322.00 322.00
8 1 38 1.40 5 268.33 268.33

FB-5
ON AXIS 4 b/n C-F
TOP BAR 16 1 2 8.95 5 89.50 89.50
16 1 2 10.05 5 100.50 100.50
Negative bar 20 1 2 2.45 5 24.50 24.50
20 1 2 4.00 5 40.00 40.00
20 1 2 3.62 5 36.20 36.20
20 1 2 2.45 5 24.50 24.50
BOTTOM BAR 16 1 3 6.70 5 100.50 100.50
16 1 3 5.70 5 85.50 85.50
16 1 3 6.80 5 102.00 102.00
STIRUP 8 1 127 1.40 5 886.08 886.08

FB-6
ON AXIS 5 b/n B'-D'
TOP BAR 16 1 2 9.70 5 97.00 97.00
Negative bar 16 1 2 3.20 5 32.00 32.00
16 1 2 3.20 5 32.00 32.00
BOTTOM BAR 14 1 3 9.10 5 136.50 136.50

239
OTT G+7 L-SHAPE RESIDENCE

STIRUP 8 1 51 1.40 5 354.20 354.20

FB-7
on AXIS A&F b/n 2-4
TOP BAR 14 2 2 11.40 5 228.00 228.00
BOTTOM BAR 14 2 2 10.70 5 214.00 214.00
STIRUP 8 2 60 1.40 5 835.33 835.33

FB-8
ON AXIS B b/n 3-4
TOP BAR 14 1 2 11.30 5 113.00 113.00
BOTTOM BAR 14 1 2 10.60 5 106.00 106.00
STIRUP 8 1 60 1.40 5 417.67 417.67

FB-9
ON AXIS C&E b/n 2-4
TOP BAR 14 2 2 8.60 5 172.00 172.00
16 2 2 10.50 5 210.00 210.00
Negative bar 20 2 2 3.95 5 79.00 79.00
20 2 2 2.75 5 55.00 55.00
BOTTOM BAR 14 2 2 5.77 5 115.40 115.40
14 2 2 5.70 5 114.00 114.00
14 2 2 7.70 5 154.00 154.00
STIRUP 8 2 102 1.40 5 1,432.67 1,432.67

FB-10
ON AXIS D b/n 2-3
TOP BAR 14 1 2 8.60 5 86.00 86.00
24 1 2 10.50 5 105.00 105.00
Negative bar 14 1 1 3.30 5 16.50 16.50
24 1 2 3.95 5 39.50 39.50
24 1 3 2.75 5 41.25 41.25
BOTTOM BAR 14 1 2 5.78 5 57.80 57.80
14 1 2 5.70 5 57.00 57.00
16 1 2 7.58 5 75.80 75.80
20 1 2 7.58 5 75.80 75.80
STIRUP 8 1 102 1.40 5 716.33 716.33

FB-11
ON AXIS D' b/n 4-5
TOP BAR 14 1 2 5.10 5 51.00 51.00
Negative 14 1 1 1.70 5 8.50 8.50
BOTTOM BAR 14 1 3 4.40 5 66.00 66.00
STIRUP 8 1 24 1.40 5 165.67 165.67

FB-12
ON AXIS B' b/n 4-5
TOP BAR 14 1 2 4.90 5 49.00 49.00
Negative 14 1 1 1.70 5 8.50 8.50
BOTTOM BAR 14 1 3 4.20 5 63.00 63.00
STIRUP 8 1 24 1.40 5 165.67 165.67

FB-13
ON AXIS C' b/n 4-5
TOP BAR 14 1 2 4.90 5 49.00 49.00
Negative 14 1 1 1.70 5 8.50 8.50
BOTTOM BAR 14 1 3 4.20 5 63.00 63.00
STIRUP 8 1 24 1.40 5 165.67 165.67

Beam b/n 1-2 & C-E ( 2 beams) 16 2 2 8.10 5 162.00 162.00


Remain / no desidn 16 2 1 2.80 5 28.00 28.00
Taken from 1st floor (FB-12) 16 2 1 2.80 5 28.00 28.00
14 2 2 7.40 5 148.00 148.00
16 2 2 7.40 5 148.00 148.00
STIRUP 8 2 46 1.40 5 644.00 644.00
ROOF BEAM
RB-1
On axis b/n 5-4 & B'-D'
TOP BAR 14 1 2 4.90 1 9.80 9.80
BOTTOM BAR 16 1 2 4.40 1 8.80 8.80
STIRUP 8 1 32 1.20 1 38.20 38.20

RB-2
On axis 1 b/n C-E
TOP BAR 14 1 2 9.90 1 19.80 19.80
14 1 2 3.90 1 7.80 7.80
Negative 14 1 1 2.35 1 2.35 2.35
14 1 2 2.35 1 4.70 4.70
BOTTOM BAR 14 1 2 6.70 1 13.40 13.40
14 1 2 6.70 1 13.40 13.40
STIRUP 10 1 96 1.20 1 115.20 115.20

RB-3
on axis 2 & 3 b/n A-F
TOP BAR 14 2 2 9.90 1 39.60 39.60
14 2 2 6.60 1 26.40 26.40
14 2 2 6.60 1 26.40 26.40
14 2 2 9.90 1 39.60 39.60
Negative 14 2 1 2.35 1 4.70 4.70
14 2 1 4.00 1 8.00 8.00
14 2 1 4.00 1 8.00 8.00
14 2 1 4.00 1 8.00 8.00
14 2 1 4.00 1 8.00 8.00
14 2 2 2.35 1 9.40 9.40
BOTTOM BAR 14 2 2 6.70 1 26.80 26.80
14 2 2 6.70 1 26.80 26.80
14 2 2 6.80 1 27.20 27.20
14 2 2 6.80 1 27.20 27.20
14 2 2 6.80 1 27.20 27.20
STIRUP 10 2 283 1.20 1 679.20 679.20

RB-4
On Axis 4 b/n A-B'
TOP BAR 14 1 2 11.70 1 23.40 23.40
Negative 14 1 2 2.35 1 4.70 4.70
16 1 2 1.95 1 3.90 3.90
BOTTOM BAR 14 1 3 6.70 1 20.10 20.10
14 1 3 5.10 1 15.30 15.30
STIRUP 10 1 101 1.20 1 120.96 120.96

RB-5
On Axis 4 b/n C-F
TOP BAR 16 1 2 8.40 1 16.80 16.80
14 1 2 9.95 1 19.90 19.90
Negative bar 20 1 2 2.05 1 4.10 4.10
20 1 2 4.00 1 8.00 8.00
20 1 1 3.60 1 3.60 3.60
14 1 2 2.35 1 4.70 4.70
BOTTOM BAR 16 1 4 6.70 1 26.80 26.80
14 1 3 5.70 1 17.10 17.10
14 1 3 6.80 1 20.40 20.40
STIRUP 8 1 132 1.20 1 157.90 157.90

RB-6
On axis A,B,F b/n 4-2
TOP BAR 14 3 2 8.55 1 51.30 51.30
14 3 2 3.35 1 20.10 20.10

240
OTT G+7 L-SHAPE RESIDENCE

BOTTOM BAR 14 3 2 10.75 1 64.50 64.50


STIRUP 8 3 79 1.20 1 285.60 285.60

RB-8
On axis B'& D' b/n 4-5

TOP BAR 14 2 2 4.80 1 19.20 19.20

BOTTOM BAR 14 2 2 4.30 1 17.20 17.20

STIRUP 8 2 25 1.20 1 59.66 59.66

241
OTT G+7 L-SHAPE RESIDENCE

RB-9
On axis 5 b/n B'- D'

TOP BAR 16 1 2 9.60 1 19.20 19.20

negetive bar 16 1 1 2.15 1 2.15 2.15

20 1 2 1.65 1 3.30 3.30

BOTTOM BAR 16 1 4 9.10 1 36.40 36.40

STIRUP 8 1 56 1.20 1 67.71 67.71

RB-10

On axis C,D & E b/n 1-4

TOP BAR 14 3 2 8.35 1 50.10 50.10

14 3 2 10.40 1 62.40 62.40

negetive bar 14 3 2 2.20 1 13.20 13.20

14 3 2 2.90 1 17.40 17.40

BOTTOM BAR 14 3 2 10.60 1 63.60 63.60

14 3 2 7.70 1 46.20 46.20

STIRUP 8 3 67 1.20 1 240.17 240.17

STIRUP 8 3 136 1.20 1 489.60 489.60

WATER TANKER BEAM

RB-11

On axis 5 b/n B'- D'

TOP BAR 16 1 2 9.60 1 19.20 19.20

16 1 1 3.42 1 3.42 3.42

16 2 2 3.42 1 13.68 13.68

BOTTOM BAR 16 2 3 9.10 1 54.60 54.60

STIRRUP 8 1 66 1.20 1 78.80 78.80

RB-12

On axis 4 b/n B'- D'


TOP BAR 16 1 2 9.60 1 19.20 19.20

negetive bar 16 1 1 5.03 1 5.03 5.03

16 1 1 2.61 1 2.61 2.61

BOTTOM BAR 16 1 3 9.10 1 27.30 27.30


STIRRUP 8 1 46 1.20 1 54.93 54.93

RB-13
On axis B' b/n 4-5
TOP BAR 14 1 3 4.62 1 13.86 13.86
BOTTOM BAR 14 1 2 4.12 1 8.24 8.24
STIRRUP 8 1 19 1.20 1 23.20 23.20

RB-14
On axis B' - D' b/n 4-5
TOP BAR 14 1 3 4.62 1 13.86 13.86
BOTTOM BAR 14 1 2 4.12 1 8.24 8.24
STIRRUP 8 1 20 1.20 1 24.20 24.20

RB-15
On axis D' b/n 4-5
TOP BAR 14 1 3 4.80 1 14.40 14.40
BOTTOM BAR 14 1 2 4.25 1 8.50 8.50
STIRRUP 8 1 19 1.20 1 23.20 23.20

Total length (m) - 14,373.34 6,623.44 - 5,154.70 4,924.09 3,062.81 301.99


Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) - 5,677.47 4,086.66 - 6,232.03 7,775.14 7,555.95 1,072.67

Lift shear Wall


GROUND FLOOR
w2 14 2 37 3.94 1 288.93 288.93
10 2 23 5.60 1 257.60 257.60

w3 14 1 26 3.94 1 102.44 102.44


10 1 23 5.00 1 115.00 115.00

w4 14 1 13 3.94 1 49.91 49.91


14 1 15 1.15 1 17.63 17.63
10 1 4 0.80 1 3.20 3.20
10 1 9 5.00 1 45.00 45.00
10 1 30 1.70 1 51.00 51.00
FIRST- SECOND FLOOR
w2 12 2 37 3.94 2 577.87 577.87
10 2 23 5.60 2 515.20 515.20

w3 12 1 26 3.94 2 204.88 204.88


10 1 23 5.00 2 230.00 230.00

w4 12 1 13 3.94 2 99.81 99.81


12 1 15 1.15 2 35.27 35.27
10 1 4 0.80 2 6.40 6.40
10 1 9 5.00 2 90.00 90.00
10 1 30 1.70 2 102.00 102.00
THIRD- FIFTH FLOOR
w2 12 2 37 3.78 3 831.60 831.60
10 2 23 5.60 3 772.80 772.80

w3 12 1 26 3.78 3 294.84 294.84


10 1 23 5.00 3 345.00 345.00

w4 12 1 13 3.78 3 143.64 143.64


12 1 15 1.15 3 52.90 52.90
10 1 4 0.80 3 9.60 9.60
10 1 9 5.00 3 135.00 135.00
10 1 30 1.70 3 153.00 153.00
SIXTH-EIGHTH FLOOR
w2 10 2 37 3.78 3 831.60 831.60
10
2 23 5.60 3 772.80 772.80
10
w3 1 26 3.78 3 294.84 294.84

242
OTT G+7 L-SHAPE RESIDENCE

10 1 23 5.00 3 345.00 345.00

w4 10 1 13 3.78 3 143.64 143.64


10 1 15 1.15 3 52.90 52.90
10 1 4 0.80 3 9.60 9.60
10 1 9 5.00 3 135.00 135.00
10 1 30 1.70 3 153.00 153.00
ABOVE TOP TIE BEAM
w2 10 2 37 2.67 1 195.80 195.80
10 2 18 5.00 1 176.67 176.67

w3 10 2 26 2.67 1 138.84 138.84


10 2 18 5.00 1 176.67 176.67
w4 10 1 10 2.67 1 25.81 25.81
10 1 23 1.70 1 39.10 39.10
10 1 9 5.00 1 45.00 45.00
10 1 4 0.80 1 3.20 3.20
Total length (m) - - 6,370.26 2,240.81 458.91 - - -
Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) - - 3,930.45 1,989.84 554.83 - - -

Stair case
section A-A 8 6 8 0.55 10 259.60 259.60
12 1 8 2.00 10 157.33 157.33
12 1 8 4.23 10 332.76 332.76
12 1 8 2.00 10 157.33 157.33
12 1 8 2.57 10 202.17 202.17
12 1 8 2.00 10 157.33 157.33

section B-B 8 6 6 0.55 10 202.95 202.95


12 1 8 1.69 10 132.95 132.95
12 1 8 2.00 10 157.33 157.33
12 1 8 3.94 10 309.95 309.95

12 1 8 2.28 10 179.36 179.36

section C-C 8 5 9 0.55 10 238.33 238.33


12 1 9 2.00 10 173.33 173.33
12 1 9 2.00 10 173.33 173.33
12 1 9 3.67 10 318.07 318.07
SHOP STAIR
section E-E 8 10 6 0.55 1 34.38 34.38
12 1 8 2.20 1 17.60 17.60
12 1 8 2.20 1 17.60 17.60
12 1 8 6.32 1 50.56 50.56
12 1 8 2.00 1 16.00 16.00
12 1 8 3.50 1 28.00
1
section F-F 8 10 6 0.55 1 34.38 34.38
12 1 8 1.40 1 11.20 11.20
12 1 8 2.20 1 17.60 17.60
12 1 8 6.10 1 48.80 48.80
12 1 8 3.19 1 25.52 25.52
Total length (m) - 769.63 - 2,656.13 - - - -
Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) - 304.01 - 2,358.65 - - - -

SOLID SLAB
FIRST FLOOR -

B/n slab A-B &4-5


Horizontal bars 8 1 28 6.40 1 176.25 176.25
Vertical bars 8 1 47 3.95 1 184.13 184.13
B/n slab B-C & 4-5
Vertical bars 8 1 28 4.85 1 133.56 133.56
B/n slab B-C & 4-6
Horizontal bars 8 1 35 7.80 1 275.40 275.40
B/n slab B-C & 5-6
Vertical bars 8 1 29 7.80 1 223.80 223.80
B/n slab B'-C & 5-6
Vertical bars 8 1 10 4.10 1 39.42 39.42
B/n slab C-C' & 4-6
Horizontal bars 8 1 17 3.40 1 57.02 57.02
B/n slab C-C' & 4-5
Horizontal bars 8 1 12 4.54 1 53.43 53.43
Vertical bars 8 1 23 7.80 1 178.20 178.20
8 1 10 5.50 1 55.42 55.42
B/n slab C' -D' & 5-6
Vertical bars 8 1 25 4.10 1 103.45 103.45
B/n slab C-D & 5-6
Horizontal bars 8 1 29 7.70 1 220.93 220.93
B/n slab D'-E & 4-6
Horizontal bars 8 1 28 6.85 1 188.64 188.64
Vertical bars 8 1 37 7.80 1 285.60 285.60
Horizontal bars 8 1 29 6.85 1 196.54 196.54
B/n slab E-F & 4-5
Horizontal bars 8 1 27 6.26 1 169.98 169.98
Vertical bars 8 1 45 3.95 1 178.66 178.66
B/n slab F-G & 4-5
Horizontal bars 8 1 28 5.60 1 154.22 154.22
Vertical bars 8 1 40 3.95 1 158.30 158.30
B/n slab F-G & 3-4
Horizontal bars 8 1 39 5.60 1 217.97 217.97
Vertical bars 8 1 40 5.45 1 218.42 218.42
B/n slab F-G & 2-3
Horizontal bars 8 1 39 5.60 1 217.97 217.97
Vertical bars 8 1 40 5.45 1 218.42 218.42

Top Bar
B/n AXIS A 4-5
Horizontal bars 10 1 26 2.15 1 55.13 55.13
B/n AXIS B 4-5
Horizontal bars 10 1 26 4.30 1 110.26 110.26
B/n AXIS B 5-6
Horizontal bars 8 1 29 1.75 1 50.21 50.21
B/n axis C 5-6
Horizontal bars 10 1 37 4.70 1 173.90 173.90
B/n axis D' 4-5
Horizontal bars 8 1 28 1.75 1 48.19 48.19

243
OTT G+7 L-SHAPE RESIDENCE

B/n axis D' 5-6


Horizontal bars 10 1 27 3.30 1 88.16 88.16
B/n axis E 4-5
Horizontal bars 10 1 26 3.90 1 100.01 100.01
B/n axis E 5-6
Horizontal bars 8 1 29 1.75 1 50.21 50.21
B/n axis F 4-5
Horizontal bars 8 1 28 4.10 1 112.91 112.91
B/n axis G 2-3
Horizontal bars 8 1 39 1.95 1 75.90 75.90
B/n axis G 3-4
Horizontal bars 8 1 39 1.95 1 75.90 75.90
B/n axis G 4-5
Horizontal bars 8 1 28 1.95 1 53.70 53.70
B/n axis 2 F-G
Vertical bars 8 1 40 1.80 1 72.14 72.14
B/n axis 3 F-G
Vertical bars 10 1 43 3.60 1 156.00 156.00
B/n axis 4 A-B
Vertical bars 8 1 47 1.35 1 62.93 62.93
B/n axis 4 B-C
Vertical bars 8 1 35 1.35 1 47.67 47.67
B/n axis 4 C-C'
Vertical bars 8 1 23 1.35 1 30.84 30.84
B/n axis 4 D'-E
Vertical bars 8 1 37 1.35 1 49.43 49.43
B/n axis 4 E-F
Vertical bars 8 1 45 1.35 1 61.06 61.06
B/n axis 4 F-G
Vertical bars 10 1 43 3.20 1 138.67 138.67
B/n axis 5 b/n A-B
Vertical bars 8 1 47 1.35 1 62.93 62.93
B/n axis 5 b/n B-C
Vertical bars 10 1 38 2.80 1 106.87 106.87
B/n axis 5 b/n C-C'
Vertical bars 10 1 33 2.80 1 93.57 93.57
B/n axis 5 b/N D'-E
Vertical bars 10 1 40 2.80 1 110.83 110.83
B/n axis 5 b/n E-F
Vertical bars 8 1 45 1.35 1 61.06 61.06
B/n axis 5 b/n F-G
Vertical bars 8 1 40 1.35 1 54.10 54.10
B/n axis 6 b/n B-C
Vertical bars 8 1 44 1.45 1 63.69 63.69
B/n axis 6 b/n C-D'
Vertical bars 8 1 57 1.45 1 81.98 81.98
B/n axis 6 b/N D'-E
Vertical bars 8 1 37 1.45 1 53.09 53.09

SECOND-EIGHT FLOOR -
B/n slab A'-B' &4-5
Horizontal bars 8 1 9 4.70 7 296.10 296.10
8 1 9 4.45 7 280.35 280.35
Vertical bars 10 1 31 1.45 7 309.91 309.91
12 1 31 3.26 7 696.77 696.77
B/naxis 1 & C-D
Horizontal bars 8 1 8 6.55 7 366.80 366.80
Vertical bars 12 1 45 3.55 7 1,109.97 1,109.97
8 1 45 1.30 7 406.47 406.47
B/n axis B'-C' & 4-5
Horizontal bars 10 1 15 3.60 7 369.60 369.60
10 1 15 3.35 7 343.93 343.93
10 1 11 4.30 7 321.07 321.07
10 1 11 4.80 7 358.40 358.40
Vertical bars 10 1 20 4.20 7 586.04 586.04
10 1 20 3.95 7 551.16 551.16
B/n axis D'-E' & 4-5
Horizontal bars 8 1 9 4.70 7 296.10 296.10
8 1 9 4.45 7 280.35 280.35

Vertical bars 8 1 31 1.45 7 309.91 309.91

12 1 31 3.26 7 696.77 696.77

ROOF slab
B/n axis A'-B' &4-5
Horizontal bars 8 1 9 4.45 1 40.05 40.05
Vertical bars 8 1 31 1.45 1 44.27 44.27

10 1 38 2.45 1 92.90 92.90


B/naxis 1 & C-D

Horizontal bars 8 1 8 6.50 1 52.00 52.00


Vertical bars 10 1 55 2.30 1 126.88 126.88

8 1 44 1.30 1 57.63 57.63


B/n axis D'-E' & 4-5

Horizontal bars 8 1 9 4.45 1 40.05 40.05


Vertical bars 8 1 31 1.45 1 44.27 44.27

10 1 38 2.70 1 102.38 102.38


B/n axis B'-D' & 4-5

Horizontal bars 10 1 24 3.05 1 73.20 73.20


8 1 24 1.33 1 31.92 31.92

8 1 15 6.49 1 95.186666667 95.19


8 1 10 8.85 1 91.45 91.45

8 1 10 2.02 1 20.87 20.87


Vertical bars 8 1 39 1.53 1 60.08 60.08

8 1 39 3.95 1 155.10 155.10

8 1 55 1.53 1 84.05 84.05

8 1 17 1.90 1 31.67 31.67


WATER TANKER slab

ALONG AXIS 4-5 & B'-D'

Horizontal bars 10 1 24 8.85 1 212.40 212.40

Vertical bars 8 1 36 3.95 1 140.62 140.62

8 1 20 3.95 1 80.32 80.32

ON AXIS B' B/N 4-5

Horizontal bars 10 1 26 3.26 1 83.60 83.60

ON AXIS B/N B'-D' & B/N 4-5


Horizontal bars
10 1 24 3.08 1 73.92 73.92

ON AXIS D' B/N 4-5


Horizontal bars
10 1 26 3.26 1 83.60 83.60

ON AXIS 4 B/N B'-D'


Vertical bars 8 1 44 1.81 1 80.09 80.09
8 1 25 1.81 1 45.55 45.55

244
OTT G+7 L-SHAPE RESIDENCE

ON AXIS 5 B/N B'-D'


Vertical bars 8 1 44 1.81 1 80.09 80.09
8 1 25 1.81 1 45.55 45.55
Total length (m) - 8,630.59 4,822.37 2,503.51 - - - -
Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) - 3,409.08 2,975.40 2,223.12 - - - -

MESH SLAB
FIRST FLOOR
b/n Axis 2-3 & A-B
Horizontal bars 6 1 21 21 4.93 1 102.38 102.38
Vertical bars 6 1 17 17 5.93 1 103.38 103.38
b/n Axis 3-4 & A-B
Horizontal bars 6 1 21 21 4.93 1 102.38 102.38
Vertical bars 6 1 17 17 5.93 1 103.38 103.38
b/n Axis 2-3 & B-C

Horizontal bars 6 1 11 11 4.93 1 56.37 56.37


Vertical bars 6 1 17 17 3.13 1 54.57 54.57
b/n Axis 3-4 & B-C
Horizontal bars 6 1 20 20 4.93 1 96.63 96.63
Vertical bars 6 1 17 17 5.58 1 97.28 97.28
b/n Axis 1-2 & C-D
Horizontal bars 6 1 20 20 6.75 1 134.33 134.33
Vertical bars 6 1 24 24 5.67 1 133.25 133.25
b/n Axis 2-3 & C-D
Horizontal bars 6 1 21 21 4.93 1 102.22 102.22

Vertical bars 6 1 17 17 5.92 1 103.21 103.21

b/n Axis 3-4 & C-D


Horizontal bars
6 1 21 21 4.93 1 102.22 102.22

Vertical bars 6 1 17 17 5.92 1 103.21 103.21

b/n Axis 1-2 & D-E


Horizontal bars 6 1 20 20 6.75 1 134.55 134.55

Vertical bars 6 1 24 24 5.68 1 133.48 133.48

b/n Axis 2-3 & D-E


Horizontal bars 6 1 21 21 4.93 1 102.38 102.38
Vertical bars 6 1 17 17 5.93 1 103.38 103.38
b/n Axis 3-4 & D-E
Horizontal bars 6 1 21 21 4.93 1 102.38 102.38
Vertical bars 6 1 17 17 5.93 1 103.38 103.38
b/n Axis 2-3 & E-F
Horizontal bars 6 1 20 20 4.93 1 99.42 99.42
Vertical bars 6 1 17 17 5.75 1 100.24 100.24
b/n Axis 3-4 & E-F
Horizontal bars 6 1 20 20 4.93 1 99.42 99.42
Vertical bars 6 1 17 17 5.75 1 100.24 100.24
SECOND-EIGHT FLOOR
b/n Axis 2-3 & A-B
Horizontal bars 6 1 20 20 4.93 7 682.15 682.15
Vertical bars 6 1 17 17 5.93 7 723.66 723.66
b/n Axis 3-4 & A-B
Horizontal bars 6 1 21 21 4.93 7 716.66 716.66
Vertical bars 6 1 17 17 5.93 7 723.66 723.66
b/n Axis 2-3 & B-C
Horizontal bars 6 1 20 20 4.93 7 676.40 676.40
Vertical bars 6 1 17 17 5.58 7 680.95 680.95
b/n Axis 3-4 & B-C
Horizontal bars 6 1 20 20 4.93 7 676.40 676.40
Vertical bars 6 1 17 17 5.58 7 680.95 680.95
b/n Axis 1-2 & C-D
Horizontal bars 6 1 20 20 6.75 7 940.28 940.28
Vertical bars 6 1 24 24 5.67 7 932.72 932.72
b/n Axis 2-3 & C-D
Horizontal bars 6 1 21 21 4.93 7 715.51 715.51

Vertical bars 6 1 17 17 5.92 7 722.44 722.44

b/n Axis 3-4 & C-D


Horizontal bars 6 1 21 21 4.93 7 715.51 715.51

Vertical bars 6 1 17 17 5.92 7 722.44 722.44

b/n Axis 1-2 & D-E


Horizontal bars 6 1 20 20 6.75 7 941.85 941.85

Vertical bars 6 1 24 24 5.68 7 934.36 934.36


b/n Axis 2-3 & D-E
Horizontal bars 6 1 21 21 4.93 7 716.66 716.66
Vertical bars 6 1 17 17 5.93 7 723.66 723.66
b/n Axis 3-4 & D-E
Horizontal bars 6 1 21 21 4.93 7 716.66 716.66
Vertical bars 6 1 17 17 5.93 7 723.66 723.66
b/n Axis 2-3 & E-F
Horizontal bars 6 1 20 20 4.93 7 695.95 695.95
Vertical bars 6 1 17 17 5.75 7 701.69 701.69
b/n Axis 3-4 & E-F
Horizontal bars 6 1 20 20 4.93 7 695.95 695.95
Vertical bars 6 1 17 17 5.75 7 701.69 701.69
Total length (m) 17,861.81 - - - - - - -

245
OTT G+7 L-SHAPE RESIDENCE

Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) 3,965.32 - - - - - - -
PRECAST- BEAM EDGE
FIRST FLOOR
ALONG AXIS 2 A-B
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 2 B-B'
8 1 10 2.95 1 29.50 29.50
ALONG AXIS 2 C-D
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 2 D-E
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 2 E-F
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 4 A-B
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 4 B-B'
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 4 C-D
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 4 D-E
8 1 20 2.95 1 59.00 59.00
ALONG AXIS 4 E-F
8 1 20 2.95 1 59.00 59.00
SECOND to EIGHTH FLOOR
ALONG AXIS 2 A-B
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 2 B-C
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 2 C-D
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 2 D-E
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 2 E-F
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 4 A-B
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 4 B-B'
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 4 C-D
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 4 D-E
8 1 20 2.95 7 413.00 413.00
ALONG AXIS 4 E-F
8 1 20 2.95 7 413.00 413.00
PRECAST- BEAM CONECTION
FIRST FLOOR
ALONG AXIS 3 A-B
12 1 20 3.30 1 66.00 66.00
ALONG AXIS 3 B-C
12 1 10 3.30 1 33.00 33.00
ALONG AXIS 3 C-D
12 1 20 3.30 1 66.00 66.00
ALONG AXIS 3 D-E

12 1 20 3.30 1 66.00 66.00

ALONG AXIS 3 E-F

12 1 20 3.30 1 66.00 66.00


SECOND to EIGHTH FLOOR
ALONG AXIS 3 A-B
12 1 20 3.30 7 462.00 462.00
ALONG AXIS 3 B-C
12 1 20 3.30 7 462.00 462.00
ALONG AXIS 3 C-D
12 1 20 3.30 7 462.00 462.00
ALONG AXIS 3 D-E

12 1 20 3.30 7 462.00 462.00

ALONG AXIS 3 E-F

12 1 20 3.30 7 462.00 462.00


Total length (m) - 4,690.50 - 2,607.00 - - - -

Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552

Total weight (Kg) - 1,852.75 - 2,315.02 - - - -

Gutter REINFORCEMENT
ON AXIS 4 b/n D'-F
10 1 75 75 0.65 1 48.9 48.88
8 1 75 75 0.45 1 33.8 33.84
10 1 75 75 1.26 1 94.8 94.75
8 1 2 2 11.13 1 22.3 22.26
8 1 2 2 11.13 1 17.4 17.36
ON AXIS F B/N 2-4
10 1 81 81 0.65 1 52.7 52.65

246
OTT G+7 L-SHAPE RESIDENCE

8 1 81 81 0.45 1 36.5 36.45


10 1 81 81 1.26 1 102.1 102.06
8 1 2 2 12.00 1 24.0 24.00
8 1 2 2 12.00 1 18.7 18.72
ON AXIS 2 B/N E-F
10 1 5 5 0.65 1 3.3 3.25
8 1 5 5 0.45 1 2.3 2.25
10 1 5 5 1.26 1 6.3 6.30
8 1 2 2 0.60 1 1.2 1.20
8 1 2 2 0.60 1 0.9 0.94
ON AXIS E b/n 1-2
10 1 6 6 0.65 1 3.7 3.68
8 1 6 6 0.45 1 2.6 2.55
10 1 6 6 1.26 1 7.1 7.14
8 1 2 2 0.70 1 1.4 1.40
8 1 2 2 0.70 1 1.1 1.09
ON AXIS E near 1
10 1 2 2 0.65 1 1.0 0.98
8 1 2 2 0.45 1 0.7 0.68
10 1 2 2 1.26 1 1.9 1.89
8 1 2 2 0.75 1 1.5 1.50
8 1 2 2 0.75 1 1.2 1.17
ON AXIS A near 2
10 1 2 2 0.65 1 1.0 0.98
8 1 2 2 0.45 1 0.7 0.68
10 1 2 2 1.26 1 1.9 1.89
8 1 2 2 0.75 1 1.5 1.50
8 1 2 2 0.75 1 1.2 1.17
ON AXIS C b/n 1-2
10 1 6 6 0.65 1 4.1 4.14
8 1 6 6 0.45 1 2.9 2.87
10 1 6 6 1.26 1 8.0 8.02
8 1 2 2 0.81 1 1.6 1.61
8 1 2 2 0.81 1 1.3 1.26
ON AXIS 2 b/n A-C
10 1 81 81 0.65 1 52.7 52.65
8 1 81 81 0.45 1 36.5 36.45
10 1 81 81 1.26 1 102.1 102.06
8 1 2 2 12.00 1 24.0 24.00
8 1 2 2 12.00 1 18.7 18.72
ON AXIS A near 2
10 1 3 3 0.65 1 1.7 1.69
8 1 3 3 0.45 1 1.2 1.17
10 1 3 3 1.26 1 3.3 3.28
8 1 2 2 0.24 1 0.5 0.48
8 1 2 2 0.24 1 0.4 0.37
Total length (m) - 255.68 496.28 - - - - -
Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) - 100.99 306.21 - - - - -
Total Weight
Total length (m) 17,861.81 38,428.04 18,312.35 10,007.45 6,282.41 8,467.61 5,994.17 301.99
Unit weight (Kg/m) 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total weight (Kg) 3,965.32 15,179.07 11,298.72 8,886.61 7,595.44 13,370.36 14,787.62 1,072.67

247
Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Super Structure
Elevationelvation
Ground coloumn
coloumn( +3.30)
on axis 1-(C,D,E)
C3 (60*60) 20 3 8 24 4.10 98.40
stirrups 4 8 0.2 2.8 3 15 45 2.30 103.50
stirrups 5 8 0.2 2.8 3 30 90 0.65 58.50
on axis 2-(A)
C3 (60*60) 20 1 8 8 4.10 32.80
stirrups 4 8 0.2 2.8 1 15 15 2.30 34.50
stirrups 5 8 0.2 2.8 1 30 30 0.65 19.50
on axis 2-(B,C,D,E,F)
C3' (60*60) 20 5 12 60 4.10 246.00
stirrups 6 8 0.2 2.8 5 15 75 2.30 172.50
stirrups 7 8 0.2 2.8 5 15 75 1.40 105.00
on axis 2-(G)
C1 (30*30) 14 1 6 6 3.86 23.16
stirup 1 8 0.2 2.8 1 15 15 1.10 16.50
on axis 3-(A)
C3 (60*60) 20 1 8 8 4.10 32.80
stirrups 4 8 0.2 2.8 1 15 15 2.30 34.50
stirrups 5 8 0.2 2.8 1 30 30 0.65 19.50
on axis 3-(B,C,D,E,F)
C3' (60*60) 20 5 12 60 3.94 236.40
stirrups 6 8 0.2 2.8 5 15 75 2.30 172.50
stirrups 7 8 0.2 2.8 5 15 75 1.40 105.00
on axis 3-(G)
C1 (30*30) 14 1 8 8 3.86 30.88
Total Length - 841.50 - - 54.04 - 646.40 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 332.39 - - 65.33 - 1,594.67 - -

______________ ______________ ______________


Contractor Consultant Client

Page 248 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
stirup 1 8 0.2 2.8 1 15 15 1.10 16.50
on axis 4-(A,B,D',E,F)
C3 (60*60) 20 5 8 40 4.10 164.00
stirrups 4 8 0.2 2.8 5 15 75 2.30 172.50
stirrups 5 8 0.2 2.8 5 30 150 0.65 97.50

C1 (30*30) 14 1 8 8 3.86 30.88


stirrups 1 8 0.2 2.8 1 15 15 1.10 16.50
on axis 5-(B',D')
C3 (60*60) 20 2 8 16 4.10 65.60
stirrups 4 8 0.2 2.8 2 15 30 2.30 69.00
stirrups 5 8 0.2 2.8 2 30 60 0.65 39.00
on axis5(A,B,C',E,F,G)
C1 (30*30) 14 6 8 48 3.86 185.28
stirrups 1 8 0.2 2.8 6 15 90 1.10 99.00
on axis 6-(B,B',D',E-)
C1 (30*30) 14 4 8 32 3.86 123.52
stirrups 1 8 0.2 2.8 4 15 60 1.10 66.00
1 st elvation colo
on axis 1-(C,D,E)
C3 (60*60) 20 3 8 24 4.10 98.40
stirrups 4 8 0.2 2.8 3 15 45 2.30 103.50
stirrups 5 8 0.2 2.8 3 30 90 0.65 58.50
on axis 2(A,B,C,D,E,F)
C3 (60*60) 20 6 8 48 4.10 196.80
stirrups 4 8 0.2 2.8 6 15 90 2.30 207.00
stirrups 5 8 0.2 2.8 6 30 180 0.65 117.00
on axis 3(A,B,C,D,E,F)
Total Length - 1,062.00 - - 339.68 - 524.80 -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 419.49 - - 410.67 - 1,294.68 -

______________ ______________ ______________


Contractor Consultant Client

Page 249 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
C3 (60*60) 20 6 8 48 4.10 196.80
stirrups 4 8 0.2 2.8 6 15 90 2.30 207.00
stirrups 5 8 0.2 2.8 6 30 180 0.65 117.00
on axis 4-(A,B,D',E,F)
C3 (60*60) 20 5 8 40 4.10 164.00
stirrups 4 8 0.2 2.8 5 15 75 2.30 172.50
stirrups 5 8 0.2 2.8 5 30 150 0.65 97.50
on axis 5-(B',D')
C3 (60*60) 20 2 8 16 4.10 65.60
stirrups 4 8 0.2 2.8 2 15 30 2.30 69.00
stirrups 5 8 0.2 2.8 2 30 60 0.65 39.00
on axis 5-(C')
C1 (30*30) 14 1 8 8 3.86 30.88
2nd & 3rd elvation
stirrups 1 (+6.60-
coloumn 8 0.2 2.8 1 15 15 1.10 16.50
+13.20)
on axis 1-(C,D,E)
C3 (60*60) 20 6 8 48 4.10 196.80
stirrups 4 8 0.2 2.8 6 15 90 2.30 207.00
stirrups 5 8 0.2 2.8 6 30 180 0.65 117.00
on axis 2(A,B,C,D,E,F)
C3 (60*60) 20 12 8 96 4.10 393.60
stirrups 4 8 0.2 2.8 12 15 180 2.30 414.00
stirrups 5 8 0.2 2.8 12 30 360 0.65 234.00
on axis 3(A,B,C,D,E,F)
Total Length - 1,690.50 - - 30.88 - 1,016.80 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 667.75 - - 37.33 - 2,508.45 -

______________ ______________ ______________


Contractor Consultant Client

Page 250 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
C3 (60*60) 20 12 8 96 4.10 393.60
stirrups 4 8 0.2 2.8 12 15 180 2.30 414.00
stirrups 5 8 0.2 2.8 12 30 360 0.65 234.00
on axis 4-(A,B,D',E,F)
C3 (60*60) 20 10 8 80 4.10 328.00
stirrups 4 8 0.2 2.8 10 15 150 2.30 345.00
stirrups 5 8 0.2 2.8 10 30 300 0.65 195.00
on axis 5-(B',D')
C3 (60*60) 20 4 8 32 4.10 131.20
stirrups 4 8 0.2 2.8 4 15 60 2.30 138.00
stirrups 5 8 0.2 2.8 4 30 120 0.65 78.00
on axis 5-(C')
C1 (30*30) 14 2 8 16 3.86 61.76
4th -8th elvation
stirrups 1 (+16.50-
coloumn 8 0.2 2.8 2 15 30 1.10 33.00
29.70)
on axis 1-(C,D,E)
C2 (40*40) 16 15 8 120 3.94 472.80
stirrups 2 8 0.2 2.8 15 15 225 1.50 337.50
stirrups 3 8 0.2 2.8 15 30 450 0.45 202.50
on axis 2(A,B,C,D,E,F)
C3 (40*40) 16 30 8 240 3.94 945.60
stirrups 2 8 0.2 2.8 30 15 450 1.50 675.00
stirrups 3 8 0.2 2.8 30 30 900 0.45 405.00
on axis 3(A,B,C,D,E,F)
C3 (40*40) 16 30 8 240 3.94 945.60
stirrups 2 8 0.2 2.8 30 15 450 1.50 675.00
stirrups 3 8 0.2 2.8 30 30 900 0.45 405.00
on axis 4-(A,B,D',E,F)
C3 (40*40) 16 25 8 200 3.94 788.00
Total Length - 4,137.00 - - 61.76 3,152.00 852.80 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 1,634.11 - - 74.67 4,977.01 2,103.86 - -

______________ ______________ ______________


Contractor Consultant Client

Page 251 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
stirrups 2 8 0.2 2.8 25 15 375 1.50 562.50
stirrups 3 8 0.2 2.8 25 30 750 0.45 337.50
on axis 5-(B',D')
C3 (40*40) 16 10 8 80 3.94 315.20
stirrups 2 8 0.2 2.8 10 15 150 1.50 225.00
stirrups 3 8 0.2 2.8 10 30 300 0.45 135.00
on axis 5-(C')
C1 (30*30) 14 5 8 40 3.86 154.40
Stirrup 1 8 0.2 2.8 5 15 75 1.10 82.50
water tanker
on axis column
4&5-(B',D'&
D')
C1 (40*40) 16 3 8 24 2.67 64.08
Stirrup 2 8 0.2 2.47 3 13 39 1.50 58.50
Stirrup 3 8 0.2 2.47 3 13 39 0.45 17.55
Typical floor beam
FIRST FLOOR
FB-1
on axis 1 b/n C-E
Top bar 14 1 2 2 10.05 20.10
14 1 2 2 4.05 8.10
Negative 14 1 2 2 2.45 4.90
14 1 2 2 4.00 8.00
14 1 2 2 2.45 4.90
Bottom bar 16 1 3 3 6.70 20.10
16 1 3 3 6.70 20.10
stirrups 8 0.15 5.4 1 37 37 1.40 51.80
8 0.15 5.4 1 37 37 1.40 51.80
FB-2
on axis 2 b/n A-G
Total Length - 1,522.15 - - 200.40 419.48 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 601.25 - - 242.28 662.36 - - -

______________ ______________ ______________


Contractor Consultant Client

Page 252 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Top bar 16 1 2 2 10.05 20.10
16 1 2 2 6.65 13.30
20 1 2 2 6.65 13.30
16 1 2 2 6.70 13.40
16 1 2 2 9.45 18.90
Negative 14 1 2 2 2.45 4.90
16 1 2 2 4.00 8.00
20 1 2 2 4.00 8.00
20 1 2 2 4.00 8.00
20 1 2 2 4.00 8.00
16 1 2 2 3.80 7.60
Bottom bar 16 1 3 3 6.80 20.40
16 1 3 3 6.80 20.40
20 1 4 4 6.80 27.20
20 1 4 4 6.80 27.20
16 1 3 3 6.70 20.10
14 1 3 3 6.15 18.45
stirrups 8 0.12 21.07 1 177 177 1.40 247.80
10 0.12 10.8 1 91 91 1.40 127.40
FB-3
on axis 3 b/n A-G
Top bar 20 1 2 2 10.05 20.10
20 1 2 2 6.65 13.30
20 1 2 2 6.65 13.30
20 1 2 2 6.70 13.40
20 1 2 2 6.30 12.60
16 1 2 2 3.70 7.40
Negative 20 1 3 3 2.45 7.35
20 1 3 3 4.00 12.00
Total Length - 247.80 127.40 - 23.35 149.60 183.75 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 97.88 78.61 - 28.23 236.22 453.31 - -

______________ ______________ ______________


Contractor Consultant Client
20 1 3 3 4.00 12.00

Page 253 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
20 1 3 3 4.00 12.00
20 1 3 3 4.00 12.00
20 1 3 3 3.80 11.40
Bottom bar 20 1 4 4 6.80 27.20
20 1 2 2 6.80 13.60
16 1 2 2 6.80 13.60
20 1 2 2 6.80 13.60
16 1 2 2 6.80 13.60
20 1 2 2 6.80 13.60
16 1 2 2 6.80 13.60
20 1 2 2 6.70 13.40
16 1 2 2 6.70 13.40
16 1 3 3 6.15 18.45
stirrups 10 0.1 27 1 542 542 1.40 758.80
10 0.1 4.87 1 50 50 1.40 70.00
FB-4
on axis 4 b/n A-B'
Top bar 16 1 2 2 8.85 17.70
16 1 2 2 4.00 8.00
Negative 20 1 2 2 2.45 4.90
20 1 2 2 3.60 7.20
16 1 2 2 2.05 4.10
Bottom bar 16 1 4 4 6.80 27.20
14 1 4 4 6.75 27.00
stirrups 10 0.1 5.4 1 55 55 1.40 77.00
10 0.1 4.48 1 46 46 1.40 64.40
FB-5
on axis 4 b/n C-G
Total Length - - 970.20 - 27.00 129.65 140.90 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - 598.61 - 32.64 204.72 347.60 - -

______________ ______________ ______________


Contractor Consultant Client
Top bar 16 1 2 2 8.95 17.90
16 1 2 2 6.70 13.40

Page 254 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
16 1 2 2 9.45 18.90
Negative 20 1 2 2 2.14 4.28
20 1 2 2 4.00 8.00
20 1 2 2 3.62 7.24
20 1 2 2 3.80 7.60
Bottom bar 16 1 4 4 6.70 26.80
16 1 3 3 5.70 17.10
16 1 4 4 6.70 26.80
16 1 3 3 6.10 18.30
stirrups 10 0.1 15.07 1 152 152 1.40 212.80
8 0.15 4.87 1 33 33 1.40 46.20
FB-6
on axis 5 b/n A-G
Top bar 14 1 2 2 9.95 19.90
16 1 2 2 6.75 13.50
14 1 2 2 7.25 14.50
14 1 2 2 6.10 12.20
14 1 2 2 6.30 12.60
14 1 2 2 3.70 7.40
Negative 14 1 2 2 3.60 7.20
16 1 2 2 3.95 7.90
14 1 1 1 3.95 3.95
14 1 2 2 2.60 5.20
14 1 1 1 3.80 3.80
Bottom bar 14 1 3 3 6.80 20.40
14 1 3 3 5.60 16.80
14 1 3 3 9.15 27.45
Total Length - 46.20 212.80 - 151.40 160.60 27.12 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 18.25 131.30 - 183.04 253.59 66.91 - -

______________ ______________ ______________


Contractor Consultant Client
14 1 3 3 5.70 17.10
14 1 3 3 6.70 20.10
14 1 3 3 6.15 18.45

Page 255 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
stirrups 8 0.15 31.87 1 213 213 1.40 298.20
FB-7
on axis 6 b/n B-E
Top bar 14 1 2 2 10.65 21.30
14 1 2 2 9.25 18.50
Negative 16 1 2 2 4.40 8.80
16 1 2 2 4.05 8.10
Bottom bar 14 1 2 2 6.45 12.90
16 1 3 3 7.45 22.35
14 1 2 2 5.30 10.60
stirrups 8 0.15 17.2 1 116 116 1.40 162.40
FB-8
on axis A -F-G b/n 2-5
Top bar 14 3 2 6 7.25 43.50
14 3 2 6 8.30 49.80
Bottom bar 14 3 2 6 4.30 25.80
14 3 2 6 5.60 33.60
14 3 2 6 5.50 33.00
stirrups 8 0.15 11.7 3 79 237 1.40 331.80
FB-9
on axis B b/n 2-6
Top bar 14 1 2 2 6.80 13.60
14 1 2 2 5.05 10.10
14 1 2 2 8.40 16.80
Negative 14 1 1 1 2.56 2.56
Bottom bar 14 1 2 2 4.60 9.20
Total Length - 792.40 - - 356.91 39.25 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 313.00 - - 431.50 61.98 - - -

______________ ______________ ______________


Contractor Consultant Client
14 1 2 2 4.30 8.60
14 1 2 2 5.60 11.20
14 1 2 2 5.60 11.20
stirrups 8 0.15 15.1 1 102 102 1.40 142.80

Page 256 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
FB-10
on axis B b/n C b/n 2-3
Top bar 14 1 3 3 8.10 24.30
14 1 3 3 7.40 22.20
stirrups 14 0.15 6.75 1 46 46 1.40 64.40
FB-11
on axis C b/n 1-4
Top bar 14 1 2 2 8.55 17.10
20 1 2 2 10.50 21.00
Negative 16 1 2 2 3.95 7.90
20 1 2 2 2.75 5.50
Bottom bar 14 1 2 2 5.70 11.40
14 1 2 2 5.70 11.40
16 1 4 4 7.70 30.80
stirrups 8 0.15 9.1 1 62 62 1.40 86.80
10 0.12 6.4 1 54 54 1.40 75.60
FB-12
on axis C-C'& D--E b/n 1-2
Top bar 16 2 2 4 8.10 32.40
Negative 16 2 1 2 2.80 5.60
16 2 1 2 2.80 5.60
Bottom bar 14 2 2 4 7.40 29.60
16 2 2 4 7.40 29.60
stirrups 8 0.15 6.75 2 46 92 1.40 128.80
FB-13
Total Length - 358.40 75.60 - 211.40 111.90 26.50 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 141.57 46.65 - 255.58 176.69 65.38 - -

______________ ______________ ______________


Contractor Consultant Client
on axis D b/n 1-4
Top bar 14 1 2 2 8.55 17.10
24 1 2 2 10.50 21.00
Negative 14 1 1 1 2.10 2.10
14 1 1 1 3.30 3.30

Page 257 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
24 1 3 3 3.95 11.85
24 1 3 3 2.75 8.25
Bottom bar 14 1 2 2 5.70 11.40
14 1 2 2 5.70 11.40
20 1 5 5 7.70 38.50
stirrups 8 0.15 9.1 1 62 62 1.40 86.80
10 0.1 6.4 1 130 130 1.40 182.00
FB-14
on axis E b/n 1-6
Top bar 14 1 2 2 6.90 13.80
14 1 2 2 10.00 20.00
20 1 2 2 10.55 21.10
Negative 16 1 2 2 4.00 8.00
20 1 2 2 2.80 5.60
Bottom bar 14 1 2 2 8.40 16.80
14 1 2 2 10.60 21.20
16 1 4 4 7.70 30.80
stirrups 8 0.15 15.3 1 103 103 1.40 144.20
10 0.12 6.4 1 108 108 1.40 151.20
FB-15
on axis D' b/n 4-6
Top bar 14 1 2 2 9.15 18.30
Negative 14 1 1 1 2.60 2.60
Bottom bar 14 1 3 3 8.45 25.35
Total Length - 231.00 333.20 - 163.35 38.80 65.20 41.10 -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 91.25 205.58 - 197.49 61.27 160.85 145.99 -

______________ ______________ ______________


Contractor Consultant Client
stirrups 8 0.15 6.5 1 44 44 1.40 61.60
FB-16
on axis C' b/n 4-5
Top bar 14 1 3 3 4.80 14.40
Negative 14 1 2 2 4.10 8.20
stirrups 8 0.15 3.45 1 24 24 1.40 33.60

Page 258 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
FB-17
on axis C b/n 5-6
Top bar 14 1 2 2 6.75 13.50
Negative 14 1 2 2 3.40 6.80
Bottom bar 14 1 2 2 6.05 12.10
stirrups 8 0.15 4.45 1 31 31 1.40 43.40
FB-18
on axis B' b/n 4-5
Top bar 14 1 2 2 4.90 9.80
Negative 14 1 1 1 1.70 1.70
Bottom bar 14 1 3 3 4.20 12.60
stirrups 8 0.15 3.39 1 24 24 1.40 33.60
2nd -3rd FLOOR
FB-1
on axis 1 b/n C-E
Top bar 16 2 2 4 10.05 40.20
16 2 2 4 4.05 16.20
Negative 16 2 2 4 2.45 9.80
16 2 2 4 4.00 16.00
16 2 2 4 2.45 9.80
Bottom bar 16 2 4 8 6.70 53.60
16 2 3 6 6.70 40.20
stirrups 8 0.1 10.8 2 109 218 1.40 305.20
Total Length - 477.40 - - 79.10 185.80 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 188.57 - - 95.63 293.38 - - -

______________ ______________ ______________


Contractor Consultant Client
FB-2
on axis 2 b/n A-F
Top bar 14 2 2 4 10.05 40.20
16 2 2 4 6.65 26.60
16 2 2 4 6.65 26.60
16 2 2 4 10.05 40.20
Negative 14 2 2 4 2.45 9.80

Page 259 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
16 2 2 4 4.00 16.00
20 2 2 4 4.00 16.00
20 2 2 4 4.00 16.00
20 2 2 4 4.00 16.00
16 2 2 4 2.45 9.80
Bottom bar 16 2 3 6 6.80 40.80
16 2 3 6 6.80 40.80
20 2 3 6 6.80 40.80
20 2 3 6 6.80 40.80
16 2 3 6 6.80 40.80
stirrups 8 0.12 10.8 2 91 182 1.40 254.80
10 0.12 16.2 2 136 272 1.40 380.80
FB-3
on axis 3 b/n A-F
Top bar 20 2 2 4 10.05 40.20
20 2 2 4 6.65 26.60
20 2 2 4 6.65 26.60
20 2 2 4 10.05 40.20
Negative 20 2 3 6 2.45 14.70
20 2 3 6 4.00 24.00
20 2 3 6 4.00 24.00
20 2 3 6 4.00 24.00
Total Length - 254.80 380.80 - 50.00 241.60 349.90 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 100.65 234.95 - 60.45 381.49 863.20 - -

______________ ______________ ______________


Contractor Consultant Client
20 2 3 6 4.00 24.00
20 2 3 6 2.45 14.70
Bottom bar 20 2 3 6 6.80 40.80
20 2 3 6 6.80 40.80
20 2 3 6 6.80 40.80
20 2 3 6 6.80 40.80
20 2 3 6 6.80 40.80
stirrups 10 0.1 27 2 271 542 1.40 758.80

Page 260 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
FB-4
on axis 4 b/n A-B'
Top bar 16 2 2 4 8.85 35.40
16 2 2 4 4.00 16.00
Negative 16 2 2 4 2.45 9.80
20 2 2 4 4.00 16.00
16 2 2 4 2.45 9.80
Bottom bar 16 2 4 8 6.80 54.40
16 2 4 8 6.75 54.00
stirrups 8 0.12 9.88 2 83 166 1.40 232.40
FB-5
on axis 4 b/n C-F
Top bar 16 2 2 4 8.95 35.80
16 2 2 4 10.05 40.20
Negative 20 2 2 4 2.14 8.56
20 2 2 4 4.00 16.00
20 2 2 4 3.62 14.48
20 2 2 4 2.45 9.80
Bottom bar 16 2 3 6 6.70 40.20
16 2 3 6 5.70 34.20
16 2 3 6 6.80 40.80
Total Length - 232.40 758.80 - - 370.60 307.54 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 91.80 468.18 - - 585.18 758.70 - -

______________ ______________ ______________


Contractor Consultant Client
stirrups 8 0.12 15.07 2 127 254 1.40 355.60
FB-6
on axis 5 b/n B'-D'
Top bar 16 2 2 4 9.70 38.80
Negative 16 2 2 4 3.20 12.80
16 2 2 4 3.20 12.80
Bottom bar 14 2 3 6 9.10 54.60
stirrups 8 0.15 7.44 2 51 102 1.40 142.80
FB-7

Page 261 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
on axis A,F b/n 2-4
Top bar 14 4 2 8 11.40 91.20
Bottom bar 14 4 2 8 10.70 85.60
stirrups 8 0.15 8.8 4 60 240 1.40 336.00
FB-8
on axis B b/n 2-4
Top bar 14 2 2 4 11.30 45.20
Bottom bar 14 2 2 4 10.60 42.40
stirrups 8 0.15 8.8 2 60 120 1.40 168.00
FB-9
on axis E b/n 1-4
Top bar 14 4 2 8 8.60 68.80
16 4 2 8 10.50 84.00
Negative 20 4 2 8 3.95 31.60
20 4 2 8 2.75 22.00
Bottom bar 14 2 2 4 5.77 23.08
at 3rd floor 14 2 2 4 5.80 23.20
14 4 2 8 5.70 45.60
14 4 2 8 7.70 61.60
16 4 2 8 7.70 61.60
Total Length - 1,002.40 - - 541.28 210.00 53.60 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 395.95 - - 654.41 331.59 132.23 - -

______________ ______________ ______________


Contractor Consultant Client
stirrups 8 0.15 15.2 4 102 408 1.40 571.20
FB-10
on axis D b/n 1-4
Top bar 14 2 2 4 8.60 34.40
24 2 2 4 10.50 42.00
Negative 14 2 1 2 3.30 6.60
24 2 2 4 3.95 15.80
at 2nd floor 24 1 3 3 2.75 8.25
Bottom bar at 2nd floor 14 1 2 2 5.78 11.56
14 2 2 4 5.70 22.80

Page 262 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
at 2nd floor 16 1 2 2 7.70 15.40
at 2nd floor 20 1 2 2 7.70 15.40
Negative at 3rd floor 24 1 3 3 3.03 9.09
Bottom bar at 3rd floor 14 1 2 2 5.80 11.60
at 3rd floor 16 1 2 2 8.70 17.40
at 3rd floor 20 1 2 2 8.70 17.40
stirrups 8 0.15 15.2 2 102 204 1.40 285.60
FB-11
on axis D' b/n 4-5
Top bar 14 2 2 4 5.10 20.40
Negative 14 2 1 2 1.70 3.40
Bottom bar 14 2 3 6 4.40 26.40
stirrups 8 0.15 3.4 2 24 48 1.40 67.20
FB-12
on axis B' b/n 4-5
Top bar 14 2 2 4 4.90 19.60
Negative 14 2 1 2 1.70 3.40
Bottom bar 14 2 3 6 4.20 25.20
stirrups 8 0.15 3.4 2 24 48 1.40 67.20
Total Length - 991.20 - - 185.36 32.80 32.80 75.14 -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 391.52 - - 224.10 51.79 80.92 266.90 -

______________ ______________ ______________


Contractor Consultant Client
FB-13
on axis C' b/n 4-5
Top bar 14 2 2 4 4.90 19.60
Negative 14 2 1 2 1.70 3.40
Bottom bar 14 2 3 6 4.20 25.20
Top bar 8 0.15 3.4 2 24 48 1.40 67.20
Beam b/n1-2 &C-E(2 beams) 16 4 2 8 8.10 64.80
Remain / no 1st
Taken from desidn
floor 16 4 1 4 2.80 11.20
(FB-12) 16 4 1 4 2.80 11.20
14 4 2 8 7.40 59.20
16 4 2 8 7.40 59.20

Page 263 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
stirrups 8 0.15 6.75 4 46 184 1.40 257.60
4th- 8th floor
FB-1
on axis 1 b/n C-E
Top bar 16 5 2 10 10.05 100.50
16 5 2 10 4.05 40.50
Negative 16 5 2 10 2.45 24.50
16 5 2 10 4.00 40.00
16 5 2 10 2.45 24.50
Bottom bar 16 5 4 20 6.70 134.00
16 5 3 15 6.70 100.50
stirrups 8 0.1 11.4 5 115 575 1.40 805.00
FB-2
on axis 2 b/n A-F
Top bar 14 5 2 10 10.05 100.50
16 5 2 10 6.65 66.50
16 5 2 10 6.65 66.50
16 5 2 10 10.05 100.50
Total Length - 1,129.80 - - 207.90 844.40 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 446.27 - - 251.35 1,333.31 - - -

______________ ______________ ______________


Contractor Consultant Client
Negative bar 14 5 2 10 2.45 24.50
16 5 2 10 4.00 40.00
20 5 2 10 4.00 40.00
20 5 2 10 4.00 40.00
20 5 2 10 4.00 40.00
16 5 2 10 2.45 24.50
Bottom bar 16 5 3 15 6.80 102.00
16 5 3 15 6.80 102.00
20 5 3 15 6.80 102.00
20 5 3 15 6.80 102.00
16 5 3 15 6.80 102.00
stirrups 8 0.12 11.3 5 95 475.833 1.40 666.17

Page 264 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
10 0.12 16.9 5 142 709.167 1.40 992.83
FB-3
on axis 3 b/n A-F
Top bar 20 5 2 10 10.05 100.50
20 5 2 10 6.65 66.50
20 5 2 10 6.65 66.50
20 5 2 10 10.05 100.50
Negative bar 20 5 3 15 2.45 36.75
20 5 3 15 4.00 60.00
20 5 3 15 4.00 60.00
20 5 3 15 4.00 60.00
20 5 3 15 4.00 60.00
20 5 3 15 2.45 36.75
Bottom bar 20 5 3 15 6.80 102.00
20 5 3 15 6.80 102.00
20 5 3 15 6.80 102.00
20 5 3 15 6.80 102.00
Total Length - 666.17 992.83 - 24.50 370.50 1,379.50 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 263.14 612.58 - 29.62 585.02 3,403.23 - -

______________ ______________ ______________


Contractor Consultant Client
20 5 3 15 6.80 102.00
stirrups 10 0.1 28.2 5 283 1415 1.40 1981.00
FB-4
on axis 4 b/n A-B'
Top bar 16 5 2 10 8.85 88.50
16 5 2 10 4.00 40.00
Negative bar 16 5 2 10 2.45 24.50
20 5 2 10 4.00 40.00
16 5 2 10 2.45 24.50
Bottom bar 16 5 4 20 6.80 136.00
16 5 4 20 6.75 135.00
stirrups 8 0.12 5.7 5 49 242.5 1.40 339.50
8 0.12 4.58 5 39 195 1.40 273.00

Page 265 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
FB-5
on axis 4 b/n C-F
Top bar 16 5 2 10 8.95 89.50
16 5 2 10 10.05 100.50
Negative bar 20 5 2 10 2.45 24.50
20 5 2 10 4.00 40.00
20 5 2 10 3.62 36.20
20 5 2 10 2.45 24.50
Bottom bar 16 5 3 15 6.70 100.50
16 5 3 15 5.70 85.50
16 5 3 15 6.80 102.00
stirrups 8 0.12 15.7 5 132 660 1.40 924.00
FB-6
on axis 5 b/n B'-D'
Top bar 16 5 2 10 9.70 97.00
Negative bar 16 5 2 10 3.20 32.00
Total Length - 1,536.50 1,981.00 - - 1,055.50 267.20 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 606.92 1,222.28 - - 1,666.63 659.18 - -

______________ ______________ ______________


Contractor Consultant Client
16 5 2 10 3.20 32.00
Bottom bar 14 5 3 15 9.10 136.50
stirrups 8 0.15 7.44 5 51 253 1.40 354.20
FB-7
on axis A&F b/n 2-4
Top bar 14 10 2 20 11.30 226.00
Bottom bar 14 10 2 20 10.60 212.00
stirrups 8 0.15 9.4 10 64 640 1.40 896.00
FB-8
on axis B b/n 3-4
Top bar 14 5 2 10 11.30 113.00
Bottom bar 14 5 2 10 10.60 106.00
stirrups 8 0.15 9.4 5 64 320 1.40 448.00
FB-9

Page 266 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
on axis C&E b/n 2-4
Top bar 14 10 2 20 8.60 172.00
16 10 2 20 10.50 210.00
Negative bar 20 10 2 20 3.95 79.00
20 10 2 20 2.75 55.00
Bottom bar 14 10 2 20 5.80 116.00
14 10 2 20 5.70 114.00
14 10 2 20 7.70 154.00
stirrups 8 0.15 16 10 108 1076.67 1.40 1507.33
FB-10
on axis D b/n 2-3
Top bar 14 5 2 10 8.60 86.00
24 5 2 10 10.40 104.00
Negative bar 14 5 1 5 3.30 16.50
24 5 2 10 3.95 39.50
Total Length - 3,205.53 - - 1,452.00 242.00 134.00 143.50 -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 1,266.19 - - 1,755.47 382.12 330.58 509.71 -

______________ ______________ ______________


Contractor Consultant Client
24 5 3 15 2.93 43.95
Bottom bar 14 5 2 10 5.80 58.00
14 5 2 10 5.70 57.00
16 5 2 10 7.58 75.80
20 5 2 10 7.58 75.80
stirrups 8 0.15 15.9 5 107 535 1.40 749.00
FB-11
on axis D' b/n 4-5
Top bar 14 5 2 10 5.10 51.00
Negative 14 5 1 5 1.70 8.50
Bottom bar 14 5 3 15 4.40 66.00
stirrups 8 0.15 3.4 5 24 120 1.40 168.00
FB-12
on axis B' b/n 4-5
Top bar 14 5 2 10 4.90 49.00

Page 267 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Negative 14 5 1 5 1.70 8.50
Bottom bar 14 5 3 15 4.20 63.00
stirrups 8 0.15 3.4 5 24 120 1.40 168.00
FB-13
on axis C' b/n 4-5
Top bar 14 5 2 10 4.90 49.00
Negative 14 5 1 5 1.70 8.50
Bottom bar 14 5 3 15 4.20 63.00
stirrups 8 0.15 3.4 5 24 120 1.40 168.00
Beam b/n 1-2 & C-E ( 2 beams) 16 10 2 20 8.10 162.00
Remainfrom
Taken / no 1st
desidn
floor 16 10 1 10 2.80 28.00
(FB-12) 16 10 1 10 2.80 28.00
14 10 2 20 7.40 148.00
16 10 2 20 7.40 148.00
Total Length - 1,253.00 - - 629.50 441.80 75.80 43.95 -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 494.94 - - 761.07 697.60 187.00 156.11 -

______________ ______________ ______________


Contractor Consultant Client
stirrups 8 0.15 6.75 10 46 460 1.40 644.00
ROOF BEAM
RB-1
On axis b/n 5-4 & B'-D'
Top bar 14 1 2 2 4.90 9.80
Bottom bar 16 1 2 2 4.40 8.80
stirrups 8 0.12 3.7 1 32 32 1.20 38.40
RB-2
On axis 1 b/n C-E
Top bar 14 1 2 2 9.90 19.80
14 1 2 2 3.90 7.80
Negative 14 1 1 1 2.35 2.35
14 1 2 2 2.35 4.70
Bottom bar 14 1 2 2 6.70 13.40
14 1 2 2 6.70 13.40
stirrups 10 0.12 11.4 1 96 96 1.20 115.20

Page 268 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
RB-3
on axis 2 & 3 b/n A-F
Top bar 14 2 2 4 9.90 39.60
14 2 2 4 6.60 26.40
14 2 2 4 6.60 26.40
14 2 2 4 9.90 39.60
Negative 14 2 1 2 2.35 4.70
14 2 1 2 4.00 8.00
14 2 1 2 4.00 8.00
14 2 1 2 4.00 8.00
14 2 1 2 4.00 8.00
14 2 2 4 2.35 9.40
Bottom bar 14 2 2 4 6.70 26.80
Total Length - 682.40 115.20 - 276.15 8.80 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 269.55 71.08 - 333.87 13.90 - - -

______________ ______________ ______________


Contractor Consultant Client
14 2 2 4 6.70 26.80
14 2 2 4 6.80 27.20
14 2 2 4 6.80 27.20
14 2 2 4 6.80 27.20
stirrups 10 0.1 28.2 2 283 566 1.20 679.20
RB-4
On Axis 4 b/n A-B'
Top bar 14 1 2 2 11.70 23.40
Negative 14 1 2 2 2.35 4.70
16 1 2 2 1.95 3.90
Bottom bar 14 1 3 3 6.70 20.10
14 1 3 3 5.10 15.30
stirrups 10 0.1 9.98 1 101 101 1.20 121.20
RB-5
On Axis 4 b/n C-F
Top bar 16 1 2 2 8.40 16.80
14 1 2 2 9.95 19.90

Page 269 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Negative bar 20 1 2 2 2.05 4.10
20 1 2 2 4.00 8.00
20 1 1 1 3.60 3.60
14 1 2 2 2.35 4.70
Bottom bar 16 1 4 4 6.70 26.80
14 1 3 3 5.70 17.10
14 1 3 3 6.80 20.40
stirrups 8 0.12 15.67 1 132 132 1.20 158.40
RB-6
On axis A,B,F b/n 4-2
Top bar 14 3 2 6 8.55 51.30
14 3 2 6 3.35 20.10
Total Length - 158.40 800.40 - 305.40 47.50 15.70 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 62.57 493.85 - 369.23 75.00 38.73 - -

______________ ______________ ______________


Contractor Consultant Client
Bottom bar 14 3 2 6 10.75 64.50
stirrups 8 0.12 9.4 3 79 238 1.20 285.60
RB-8
On axis B'& D' b/n 4-5
Top bar 14 2 2 4 4.80 19.20
Bottom bar 14 2 2 4 4.30 17.20
stirrups 8 0.14 3.48 2 25 50 1.20 60.00
RB-9
On axis 5 b/n B'- D'
Top bar 16 1 2 2 9.60 19.20
negetive bar 16 1 1 1 2.15 2.15
20 1 2 2 1.65 3.30
Bottom bar 16 1 4 4 9.10 36.40
stirrups 8 0.14 7.76 1 56 56 1.20 67.20
RB-10
On axis C,D& E b/n 1-4
Top bar 14 3 2 6 8.35 50.10
14 3 2 6 10.40 62.40

Page 270 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
negetive bar 14 3 2 6 2.20 13.20
14 3 2 6 2.90 17.40
Bottom bar 14 3 2 6 10.60 63.60
14 3 2 6 7.70 46.20
stirrups 8 0.14 9.2 3 67 201 1.20 241.20
8 0.1 6.7 3 136 408 1.20 489.60
water tanker beam
RB-11
On axis 5 b/n B'- D'
Top bar 16 1 2 2 9.60 19.20
16 1 1 1 3.42 3.42
Total Length - 1,143.60 - - 353.80 80.37 3.30 - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 451.72 - - 427.74 126.90 8.14 - -

______________ ______________ ______________


Contractor Consultant Client
16 2 2 4 3.42 13.68
Bottom bar 16 2 3 6 9.10 54.60
stirrups 8 0.12 7.76 1 66 66 1.20 79.20
RB-12
On axis 4 b/n B'- D'
Top bar 16 1 2 2 9.60 19.20
negetive bar 16 1 1 1 5.03 5.03
16 1 1 1 2.61 2.61
Bottom bar 16 1 3 3 9.10 27.30
stirrups 8 0.18 8.06 1 46 46 1.20 55.20
RB-13
On axis B' b/n 4-5
Top bar 14 1 3 3 4.62 13.86
Bottom bar 14 1 2 2 4.12 8.24
stirrups 8 0.18 3.3 1 19 19 1.20 22.80
RB-14
On axis B' - D' b/n 4-5
Top bar 14 1 3 3 4.62 13.86
Bottom bar 14 1 2 2 4.12 8.24

Page 271 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
stirrups 8 0.18 3.45 1 20 20 1.20 24.00
RB-15
On axis D' b/n 4-5 0
Top bar 14 1 3 3 4.80 14.40
Bottom bar 14 1 2 2 4.25 8.50
stirrups 8 0.18 3.3 1 19 19 1.20 22.80
Lift shear Wall
GROUND -1 st FLOOR
w2 (section 1-1)
Vertical bars 14 0.15 2.6 4 36 144 3.94 567.36
Vertical bars 20 0.1 2.6 4 54 216 4.10
Total Length - 204.00 - - 634.46 122.42 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 80.58 - - 767.06 193.30 - - -

______________ ______________ ______________


Contractor Consultant Client
Horizontal bars (C) 10 0.15 3.3 4 22 88 5.60 492.80
Horizontal bars (C) 10 0.15 3.3 4 22 88 5.60 492.80
w3 (section 1-1)
Vertical bars 14 0.15 1.8 2 24 48 3.94 189.12
Horizontal bars (D) 10 0.15 3.3 2 22 44 5.00 220.00
w4 (section 1-1)
Vertical bars 14 0.15 0.65 4 10 40 3.94 157.60
14 0.15 1 2 14 28 1.15 32.20
Negative 10 0.15 2 4 8 0.80 6.40
Horizontal bars (D) 10 0.15 1.2 2 8 16 5.00 80.00
Horizontal bars (E) 10 0.15 2.1 4 14 56 1.70 95.20
SECOND FLOOR
w2 (section 2-2)
Vertical bars 12 0.15 2.6 2 36 72 3.78 272.16
Vertical bars 14 0.15 2.6 2 36 72 3.86 277.92
Horizontal bars (C) 10 0.15 3.3 2 22 44 5.60 246.40
Horizontal bars (C) 10 0.15 3.3 2 22 44 5.60 246.40
w3 (section 2-2)
Vertical bars 12 0.15 1.8 1 24 24 3.94 94.56

Page 272 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Horizontal bars (D) 10 0.15 3.3 1 22 22 5.00 110.00
w4 (section 2-2)
Vertical bars 14 0.15 0.65 2 10 20 3.94 78.80
14 0.15 1 1 14 14 1.15 16.10
Negative 10 0.15 1 4 4 0.80 3.20
Horizontal bars (D) 10 0.15 1.2 1 8 8 5.00 40.00
Horizontal bars (E) 10 0.15 2.1 2 14 28 1.70 47.60
3rd -5th FLOOR
w2 (section 2-2)
Vertical bars 12 0.15 2.6 6 36 216 3.78 816.48
Vertical bars 14 0.15 2.6 6 36 216 3.86 833.76
Horizontal bars (C) 10 0.15 3.3 2 22 44 5.60 246.40
Horizontal bars (C) 10 0.15 3.3 2 22 44 5.60 246.40
w3 (section 2-2)
Vertical bars 12 0.15 1.8 3 24 72 3.78 272.16
Horizontal bars (D) 10 0.15 3.3 3 22 66 5.00 330.00
Total Length - - 2,903.60 1,455.36 1,585.50 - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - 203.61 1,292.36 1,916.87 - - - -

______________ ______________ ______________


Contractor Consultant Client
w4 (section 2-2)
Vertical bars 12 0.15 0.65 6 10 60 3.78 226.80
12 0.15 1 3 13 40 1.15 46.00
Negative 10 0.15 3 4 12 0.80 9.60
Horizontal bars (D) 10 0.15 1.2 3 8 24 5.00 120.00
Horizontal bars (E) 10 0.15 2.1 6 14 84 1.70 142.80
6th-8th FLOOR
w2 (section 3-3)
Vertical bars 10 0.15 2.6 6 36 216 3.70 799.20
Vertical bars 14 0.15 2.6 6 36 216 3.86 833.76
Horizontal bars (C) 10 0.15 3.3 6 22 132 5.60 739.20
Horizontal bars (C) 10 0.15 3.3 6 22 132 5.60 739.20
w3 (section 3-3)
Vertical bars 12 0.15 1.8 3 24 72 3.78 272.16

Page 273 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Horizontal bars (D) 10 0.15 3.3 3 22 66 5.00 330.00
w4 (section 3-3)
Vertical bars 12 0.15 0.65 6 10 60 3.78 226.80
12 0.15 1 3 13 40 1.15 46.00
Negative 10 0.15 3 4 12 0.80 9.60
Horizontal bars (D) 10 0.15 1.2 3 8 24 5.00 120.00
Horizontal bars (E) 10 0.15 2.1 6 14 84 1.70 142.80
ABOVE TOP TIE BEAM
w2
Vertical bars 10 0.15 2.6 2 36 72 2.67 192.24
Horizontal bars (C) 10 0.15 2.5 2 17 34 5.00 170.00
w3
Vertical bars 10 0.15 1.8 2 24 48 2.67 128.16
Horizontal bars (D) 10 0.15 2.5 2 17 34 5.00 170.00
w4
Vertical bars 10 0.15 0.65 2 10 20 2.67 53.40
10 0.15 1 4 4 0.80 3.20
Total Length - - 3,869.40 817.76 833.76 - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - - 2,387.42 726.17 1,008.02 - - - -

______________ ______________ ______________


Contractor Consultant Client
Horizontal bars (D) 10 0.15 1.2 1 8 8 5.00 40.00
Horizontal bars (E) 10 0.15 2.1 2 14 28 1.70 47.60
Stair case
section A-A 8 0.15 1.03 54 8 432 0.55 237.60
12 0.15 1.03 9 8 72 2.00 144.00
12 0.15 1.03 9 8 72 4.23 304.56
12 0.15 1.03 9 8 72 2.00 144.00
12 0.15 1.03 9 8 72 2.57 185.04
12 0.15 1.03 9 8 72 2.00 144.00
section B-B 8 0.15 1.03 54 8 432 0.55 237.60
12 0.15 1.03 9 8 72 1.69 121.68
12 0.15 1.03 9 8 72 2.00 144.00
12 0.15 1.03 9 8 72 3.94 283.68

Page 274 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
12 0.15 1.03 9 8 72 2.28 164.16
section C-C 8 0.15 1.15 45 9 405 0.55
12 0.15 1.15 9 9 81 2.00 162.00
12 0.15 1.15 9 9 81 2.00 162.00
12 0.15 1.15 9 9 81 3.67 297.27
intermediate beam on staircase
TOP BAR 16 8 2 16 5.42 86.72
BOTTOM BAR 10 8 3 24 4.72 113.28
STIRRUP 8 0.2 3.37 8 18 144 1.40 201.60
SHOP STAIR
section E-E 8 0.2 1.05 10 6 60 0.55 33.00
12 0.15 1.05 1 8 8 2.20 17.60
12 0.15 1.05 1 8 8 2.20 17.60
12 0.15 1.05 1 8 8 6.32 50.56
12 0.15 1.05 1 8 8 2.00 16.00
12 0.15 1.05 1 8 8 3.50 28.00
Total Length - 709.80 200.88 2,386.15 - 86.72 - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 280.37 123.94 2,118.90 - 136.93 - - -

______________ ______________ ______________


Contractor Consultant Client
section F-F 8 0.2 1.05 10 6 60 0.55 33.00
12 0.15 1.05 1 8 8 1.40 11.20
12 0.15 1.05 1 8 8 2.20 17.60
12 0.15 1.05 1 8 8 6.10 48.80
12 0.15 1.05 1 8 8 3.19 25.52
SOLID SLAB
1st FLOOR
B/n slab A-B &4-5
Horizontal bars 8 0.13 3.45 1 28 28 6.40 179.20
Vertical bars 8 0.13 5.93 1 47 47 3.95 185.65
B/n slab B-C & 4-5
Vertical bars 8 0.13 3.45 1 28 28 4.85 135.80
B/n slab B-C & 4-6
Horizontal bars 8 0.13 4.46 1 35 35 7.80 273.00

Page 275 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
B/n slab B-C & 5-6
Vertical bars 10 0.14 3.6 1 27 27 7.80 210.60
B/n slab B'-C & 5-6
Vertical bars 10 0.14 1.12 1 9 9 4.10 36.90
B/n slab C-C' & 4-6
Horizontal bars 8 0.13 2.05 1 17 17 3.40 57.80
B/n slab C-C' & 4-5
Horizontal bars 8 0.13 1.4 1 12 12 4.54 54.48
Vertical bars 8 0.13 2.84 1 23 23 7.80
8 0.13 1.18 1 10 10 5.50 55.00
B/n slab C' -D' & 5-6
Vertical bars 10 0.14 3.15 1 24 24 4.10 98.40
B/n slab C-D & 5-6
Horizontal bars 10 0.14 3.6 1 27 27 7.70 207.90
B/n slab D'-E & 4-6
Total Length - 973.93 553.80 103.12 - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 384.70 341.69 91.57 - - - - -

______________ ______________ ______________


Contractor Consultant Client
Horizontal bars 8 0.13 3.45 1 28 28 6.85 191.80
Vertical bars 8 0.13 4.63 1 37 37 7.80 288.60
Horizontal bars 8 0.13 3.6 1 29 29 6.85 198.65
B/n slab E-F & 4-5
Horizontal bars 8 0.13 3.4 1 27 27 6.26 169.02
Vertical bars 8 0.13 5.75 1 45 45 3.95 177.75
B/n slab F-G & 4-5
Horizontal bars 8 0.13 3.45 1 28 28 5.60 156.80
Vertical bars 8 0.13 5.08 1 40 40 3.95 158.00
B/n slab F-G & 3-4
Horizontal bars 8 0.13 4.93 1 39 39 5.60 218.40
Vertical bars 8 0.13 5.08 1 40 40 5.45 218.00
B/n slab F-G & 2-3
Horizontal bars 8 0.13 4.93 1 39 39 5.60 218.40
Vertical bars 8 0.13 5.08 1 40 40 5.45 218.00

Page 276 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Top Bar
B/n AXIS A 4-5
Horizontal bars 10 0.14 3.45 1 26 26 2.15 55.90
B/n AXIS B 4-5
Horizontal bars 10 0.14 3.45 1 26 26 4.30 111.80
B/n AXIS B 5-6
Horizontal bars 10 0.14 3.6 1 27 27 1.75 47.25
B/n axis C 5-6
Horizontal bars 10 0.14 3.6 1 27 27 4.70 126.90
B/n axis D' 4-5
Horizontal bars 8 0.13 3.45 1 28 28 1.75 49.00
B/n axis D' 5-6
Horizontal bars 10 0.14 3.6 1 27 27 3.30 89.10
B/n axis E 4-5
Total Length - 2,262.42 430.95 - - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 893.66 265.90 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Horizontal bars 10 0.14 3.45 1 26 26 3.90 101.40
B/n axis E 5-6
Horizontal bars 10 0.14 3.6 1 27 27 1.75 47.25
B/n axis F 4-5
Horizontal bars 8 0.13 3.45 1 28 28 4.10 114.80
B/n axis G 2-3
Horizontal bars 8 0.13 4.93 1 39 39 1.95 76.05
B/n axis G 3-4
Horizontal bars 8 0.13 4.93 1 39 39 1.95 76.05
B/n axis G 4-5
Horizontal bars 8 0.13 3.45 1 28 28 1.95 54.60
B/n axis 2 F-G
Vertical bars 8 0.13 5.08 1 40 40 1.80 72.00
B/n axis 3 F-G
Vertical bars 10 0.12 5.08 1 43 43 3.60 154.80
B/n axis 4 A-B

Page 277 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Vertical bars 8 0.13 5.93 1 47 47 1.35 63.45
B/n axis 4 B-C
Vertical bars 8 0.13 4.46 1 35 35 1.35 47.25
B/n axis 4 C-C'
Vertical bars 8 0.13 2.84 1 23 23 1.35 31.05
B/n axis 4 D'-E
Vertical bars 8 0.13 4.63 1 37 37 1.35 49.95
B/n axis 4 E-F
Vertical bars 8 0.13 5.75 1 45 45 1.35 60.75
B/n axis 4 F-G
Vertical bars 10 0.12 5.08 1 43 43 3.20 137.60
B/n axis 5 b/n A-B
Vertical bars 8 0.13 5.93 1 47 47 1.35 63.45
Total Length - 709.40 441.05 - - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 280.21 272.13 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
B/n axis 5 b/n B-C
Vertical bars 10 0.14 4.46 1 33 33 2.80 92.40
B/n axis 5 b/n C-C'
Vertical bars 10 0.14 3.89 1 29 29 2.80 81.20
B/n axis 5 b/N D'-E
Vertical bars 10 0.14 4.63 1 34 34 2.80 95.20
B/n axis 5 b/n E-F
Vertical bars 8 0.13 5.75 1 45 45 1.35 60.75
B/n axis 5 b/n F-G
Vertical bars 8 0.13 5.08 1 40 40 1.35 54.00
B/n axis 6 b/n B-C
Vertical bars 10 0.14 5.58 1 41 41 1.45 59.45
B/n axis 6 b/n C-D'
Vertical bars 10 0.14 7.22 1 53 53 1.45 76.85
B/n axis 6 b/N D'-E
Vertical bars 10 0.14 4.63 1 34 34 1.45 49.30
2nd-8th FLOOR

Page 278 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
B/n slab A'-B' &4-5
Horizontal bars 8 0.15 1.2 7 9 63 4.70 296.10
8 0.15 1.2 7 9 63 4.45 280.35
Vertical bars 10 0.15 4.43 7 31 217 1.45 314.65
12 0.15 4.43 7 31 217 3.26 707.42
B/naxis 1 & C-D
Horizontal bars 8 0.15 1.05 14 8 112 6.55 733.60
Vertical bars 12 0.15 6.55 7 45 315 3.55 1118.25
8 0.15 6.55 7 45 315 1.30 409.50
B/n axis B'-C' & 4-5
Horizontal bars 10 0.15 2.05 7 15 105 3.60 378.00
10 0.15 2.05 7 15 105 3.35 351.75
Total Length - 1,834.30 1,498.80 1,825.67 - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 724.55 924.76 1,621.19 - - - - -

______________ ______________ ______________


Contractor Consultant Client
10 0.15 1.45 7 11 77 4.30 331.10
10 0.15 1.45 7 11 77 4.80 369.60
Vertical bars 10 0.15 2.84 7 20 140 4.20 588.00
10 0.15 2.84 7 20 140 3.95 553.00
B/n axis D'-E' & 4-5
Horizontal bars 8 0.15 1.2 7 9 63 4.70 296.10
8 0.15 1.2 7 9 63 4.45 280.35
Vertical bars 8 0.15 4.43 7 31 217 1.45 314.65
12 0.15 4.43 7 31 217 3.26 707.42
ROOF slab
B/n axis A'-B' &4-5
Horizontal bars 8 0.15 1.2 1 9 9 4.45 40.05
Vertical bars 8 0.15 4.43 1 31 31 1.45 44.95
10 0.15 4.43 1 31 31 2.45 75.95
B/naxis 1 & C-D
Horizontal bars 8 0.15 1.05 1 8 8 6.50 52.00
Vertical bars 10 0.12 6.5 1 55 55 2.30 126.50
8 0.15 6.5 1 44 44 1.30 57.20

Page 279 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
B/n axis D'-E' & 4-5
Horizontal bars 8 0.15 1.2 1 9 9 4.45 40.05
Vertical bars 8 0.15 4.43 1 31 31 1.45 44.95
10 0.12 4.43 1 38 38 2.70 102.60
B/n axis B'-D' & 4-5
Horizontal bars 10 0.15 3.45 1 24 24 3.05 73.20
8 0.15 3.45 1 24 24 1.33 31.92
8 0.15 2.05 1 15 15 6.49 97.35
8 0.15 1.4 1 10 10 8.85 88.50
8 0.15 1.4 1 10 10 2.02 20.20
Vertical bars 8 0.15 5.74 1 39 39 1.53 59.67
Total Length - 1,467.94 2,219.95 707.42 - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 579.84 1,369.71 628.19 - - - - -

______________ ______________ ______________


Contractor Consultant Client
8 0.15 5.74 1 39 39 3.95 154.05
8 0.15 8.09 1 55 55 1.53 84.15
8 0.15 2.35 1 17 17 1.90 32.30
WATER TANKER slab
on axis 4-5 & B'-D'
Horizontal bars 10 0.15 3.45 1 24 24 8.85 212.40
Vertical bars 8 0.15 5.19 1 36 36 3.95 142.20
8 0.15 2.9 1 20 20 3.95 79.00
on axis B' B/N 4-5
Horizontal bars 10 0.14 3.45 1 26 26 3.26 84.76
on axis B/N B'-D' & B/N 4-5
Horizontal bars 10 0.15 3.45 1 24 24 3.08 73.92
on axis D' B/N 4-5
Horizontal bars 10 0.14 3.45 1 26 26 3.26 84.76
on axis 4 B/N B'-D'
Vertical bars 8 0.12 5.19 1 44 44 1.81 79.64
8 0.12 2.9 1 25 25 1.81 45.25
on axis 5 B/N B'-D'
Vertical bars 8 0.12 5.19 1 44 44 1.81 79.64

Page 280 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
8 0.12 2.9 1 25 25 1.81 45.25
MESH SLAB
FIRST FLOOR
b/n Axis 2-4 & A-F
Horizontal bars 6 0.3 30.9 1 104 104 10.90 1,133.60
Vertical bars 6 0.3 10.9 1 37 37 30.90 1,143.30
b/n Axis 1-2 & C-E
Horizontal bars 6 0.3 7.55 1 26 26 12.90 335.40
Vertical bars 6 0.3 12.9 1 44 44 7.55 332.20
dd't b/n Axis 2-3 & B'-C
Total Length 2,944.50 741.48 455.84 - - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg 653.68 292.88 281.25 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Horizontal bars 6 0.3 5.18 1 18 18 (2.70) (48.60)
Vertical bars 6 0.3 2.45 1 9 9 (5.43) (48.87)
2nd-8th FLOOR
b/n Axis 2-4 & A-F
Horizontal bars 6 0.3 30.9 7 104 728 10.90 7,935.20
Vertical bars 6 0.3 10.9 7 37 259 30.90 8,003.10
b/n Axis 1-2 & C-E
Horizontal bars 6 0.3 7.55 7 26 182 12.90 2,347.80
Vertical bars 6 0.3 12.9 7 44 308 7.55 2,325.40
PRECAST-BEAM EDGE
FIRST FLOOR
Along Axis 2 A-B 8 1 1 20 20 2.95 59.00
Along Axis 2 B-B' 8 1 1 10 10 2.95 29.50
Along Axis 2 C-D 8 1 1 20 20 2.95 59.00
Along Axis 2 D-E 8 1 1 20 20 2.95 59.00
Along Axis 2 E-F 8 1 1 20 20 2.95 59.00
Along Axis 4 A-B 8 1 1 20 20 2.95 59.00
Along Axis 4 B-B' 8 1 1 20 20 2.95 59.00
Along Axis 4 C-D 8 1 1 20 20 2.95 59.00
Along Axis 4 D-E &E-F 8 1 2 20 40 2.95 118.00

Page 281 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
Along Axis C & E b/n 1-2 8 1 2 20 40 1.05 42.00
4th FLOOR
Along Axis 2 A-B 10 1 1 20 20 2.95 59.00
Along Axis 2 B-C 10 1 1 20 20 2.95 59.00
Along Axis 2 C-D 10 1 1 20 20 2.95 59.00
Along Axis 2 D-E 10 1 1 20 20 2.95 59.00
Along Axis 2 E-F 10 1 1 20 20 2.95 59.00
Along Axis 4 A-B 10 1 1 20 20 2.95 59.00
Along Axis 4 B-B' 10 1 1 20 20 2.95 59.00
Total Length 20,514.03 602.50 413.00 - - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg 4,554.11 237.99 254.82 - - - - - -

______________ ______________ ______________


Contractor Consultant Client
Along Axis 4 C-D 10 1 1 20 20 2.95 59.00
Along Axis 4 D-E &E-F 10 1 2 20 40 2.95 118.00
Along Axis C & E b/n 1-2 8 1 2 20 40 1.05 42.00
2nd to 8th FLOOR with out 4th
Along Axis 2 A-B 8 1 6 20 120 2.95 354.00
Along Axis 2 B-C 8 1 6 20 120 2.95 354.00
Along Axis 2 C-D 8 1 6 20 120 2.95 354.00
Along Axis 2 D-E 8 1 6 20 120 2.95 354.00
Along Axis 2 E-F 8 1 6 20 120 2.95 354.00
Along Axis 4 A-B 8 1 6 20 120 2.95 354.00
Along Axis 4 B-B' 8 1 6 20 120 2.95 354.00
Along Axis 4 C-D 8 1 6 20 120 2.95 354.00
Along Axis 4 D-E &E-F 8 1 12 20 240 2.95 708.00
Along Axis C & E b/n 1-2 8 1 12 20 240 1.05 252.00
PRECAST-BEAM CON.
FIRST FLOOR
Along Axis 3 A-B 12 1 1 20 20 3.30 66.00
Along Axis 3 B-C 12 1 1 10 10 3.30 33.00
Along Axis 3 C-D 12 1 1 20 20 3.30 66.00
Along Axis 3 D-E 12 1 1 20 20 3.30 66.00
Along Axis 3 E-F 12 1 1 20 20 3.30 66.00
Page 282 of 290
Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
2nd to 8th FLOOR
Along Axis 3 A-B 12 1 7 20 140 3.30 462.00
Along Axis 3 B-C 12 1 7 20 140 3.30 462.00
Along Axis 3 C-D 12 1 7 20 140 3.30 462.00
Along Axis 3 D-E 12 1 7 20 140 3.30 462.00
Along
GutterAxis 3 E-F 12 1 7 20 140 3.30 462.00
REINFORCEMENT
on axis 4 b/n D'-F
10 0.15 11.13 1 75 75 0.65 48.75
8 0.15 11.13 1 75 75 0.45 33.75
10 0.15 11.13 1 75 75 1.26 94.50
8 0.15 0.15 1 2 2 11.13 22.26
8 0.15 0.84 1 7 7 11.13 77.91
on axis 2 near F
10 0.15 0.75 1 6 6 0.65 3.90
8 0.15 0.75 1 6 6 0.45 2.70
10 0.15 0.75 1 6 6 1.26 7.56
8 0.15 0.15 1 2 2 0.75 1.50
8 0.15 0.84 1 7 7 0.75 5.25
Total Length - 3,977.37 331.71 2,607.00 - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 1,571.06 204.67 2,315.02 - - - - -

______________ ______________ ______________


Contractor Consultant Client
on axis 4 near F
10 0.15 0.75 1 6 6 0.65 3.90
8 0.15 0.75 1 6 6 0.45 2.70
10 0.15 0.75 1 6 6 1.26 7.56
8 0.15 0.15 1 2 2 0.75 1.50
8 0.15 0.84 1 7 7 0.75 5.25
on axis 2 B/N E-F
10 0.15 0.6 1 5 5 0.65 3.25
8 0.15 0.6 1 5 5 0.45 2.25
10 0.15 0.6 1 5 5 1.26 6.30
8 0.15 0.15 1 2 2 0.60 1.20

Page 283 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
8 0.15 0.84 1 7 7 0.60 4.20
on axis E b/n 1-2
10 0.15 0.75 1 6 6 0.65 3.90
8 0.15 0.75 1 6 6 0.45 2.70
10 0.15 0.75 1 6 6 1.26 7.56
8 0.15 0.15 1 2 2 0.70 1.40
8 0.15 0.84 1 7 7 0.70 4.90
on axis E near 1
10 0.15 0.75 1 6 6 0.65 3.90
8 0.15 0.75 1 6 6 0.45 2.70
10 0.15 0.75 1 6 6 1.26 7.56
8 0.15 0.15 1 2 2 0.75 1.50
8 0.15 0.84 1 7 7 0.75 5.25
on axis C b/n 1-2
10 0.15 0.75 1 6 6 0.65 3.90
8 0.15 0.75 1 6 6 0.45 2.70
10 0.15 0.75 1 6 6 1.26 7.56
8 0.15 0.15 1 2 2 0.81 1.61
Total Length - 39.86 55.39 - - - - - -
Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 15.74 34.18 - - - - - -

Page 284 of 290


Steel Reinforcement bar Takeoff Sheet
Super structure
Project:- SHDE Housing Dev't Project Contractor Amba
Client:- Saving House Dev't Enterprise (B-02 Office) Block:- __ 16
Consultant: K2N Architecture and Engineering Consultancy PLC Date. ___________________

Remark
bar Dia Number of Length Production
No. Location
no mm C/C S/L Mem. No.Bars T. Bars ml Ø6 Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø24
______________ ______________ ______________
Contractor Consultant Client
8 0.15 0.84 1 7 7 0.81 5.64
on axis 2 b/n A-C
10 0.15 12 1 81 81 0.65 52.65
8 0.15 12 1 81 81 0.45 36.45
10 0.15 12 1 81 81 1.26 102.06
8 0.15 0.15 1 2 2 12.00 24.00
8 0.15 0.84 1 7 7 12.00 84.00
on axis A near 2
10 0.15 0.24 1 3 3 0.65 1.95
8 0.15 0.24 1 3 3 0.45 1.35
10 0.15 0.24 1 3 3 1.26 3.78
8 0.15 0.15 1 2 2 0.24 0.48
8 0.15 0.84 1 7 7 0.24 1.68

Total Length - 153.60 160.44 - - - - - -


Unit Wt kg/m 0.22 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Total wt kg - 60.67 98.99 - - - - - -
______________ ______________ ______________
Contractor Consultant Client

Page 285 of 290


Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC

Supply and fix steel Roof Truss & Purlin Complex as per the structural design. The price includes all the angle
3.06 iron pieces, connection bolts, plates & accessories for fixing purlins & roof structure connection need plates for
strengthing.
Truss Type Member Size Length Timizing Total 40x40x3.0mm 30x30x2.5mm

Top Member 40x40x3.0 10.54 1 3 1 3 31.62


Lower Member 40x40x3.0 10.36 1 3 1 3 31.08
T-1 Vertical Posts 30x30x2.5 6.50 1 3 1 3 19.50
Diagonal Member 30x30x2.5 11.60 1 3 1 3 34.80
King post 40x40x3.0 2.00 1 3 1 3 6.00

Top Member 40x40x3.0 12.35 1 2 1 2 24.70


Lower Member 40x40x3.0 12.26 1 2 1 2 24.52
T-2 Vertical Posts 30x30x2.5 8.77 1 2 1 2 17.54
Diagonal Member 30x30x2.5 13.76 1 2 1 2 27.52
King post 40x40x3.0 2.00 1 2 1 2 4.00

Top Member 40x40x3.0 12.90 1 2 1 2 25.80


Lower Member 40x40x3.0 12.27 1 2 1 2 24.54
T-3 Vertical Posts 30x30x2.5 7.24 1 2 1 2 14.48
Diagonal Member 30x30x2.5 11.28 1 2 1 2 22.56
King post 30x30x2.5 2.00 1 2 1 2 4.00

Top Member 40x40x3.0 3.20 1 1 1 1 3.20


Lower Member 40x40x3.0 3.00 1 1 1 1 3.00
T-3' Vertical Posts 30x30x2.5 3.74 1 1 1 1 3.74
Diagonal Memb 30x30x2.5 4.62 1 1 1 1 4.62
King post 40x40x3.0 2.00 1 1 1 1 2.00

Top Member 40x40x3.0 10.96 1 2 1 2 21.92


Lower Member 40x40x3.0 10.27 1 2 1 2 20.54
T-4 Vertical Posts 30x30x2.5 5.60 1 2 1 2 11.20
Diagonal Member 30x30x2.5 8.72 1 2 1 2 17.44
King post 30x30x2.5 2.00 1 2 1 2 4.00

Top Member 40x40x3.0 5.50 1 1 1 1 5.50


Lower Member 40x40x3.0 5.18 1 1 1 1 5.18
T-4' Vertical Posts 30x30x2.5 2.77 1 1 1 1 2.77
Diagonal Member 30x30x2.5 4.43 1 1 1 1 4.43
King post 40x40x3.0 2.00 1 1 1 1 2.00

Top Member 40x40x3.0 8.43 1 2 1 2 16.86


Lower Member 40x40x3.0 8.20 1 2 1 2 16.40
T-5 Vertical Posts 30x30x2.5 5.55 1 2 1 2 11.10
Diagonal Member 30x30x2.5 9.14 1 2 1 2 18.28
King post 40x40x3.0 2.00 1 2 1 2 4.00

Total Length (m) 280.86 209.98


Unit Weight (kg/m) 3.30 2.03
Total Weight ( kg) 926.84 426.26
Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC

Lattice Purline Member Size Length Timizing Total 30x30x2.0mm

Upper Part 30x30x2.0 6.00 1 32 1 32 192.00


LP-1 Lower Part 30x30x2.0 5.47 1 32 1 32 175.04
Ver. Members 30x30x2.0 5.13 1 32 1 32 164.16
Diagonal Members 30x30x2.0 7.00 1 32 1 32 224.00

Upper Part 30x30x2.0 7.00 1 10 1 10 70.00


Lower Part 30x30x2.0 6.43 1 10 1 10 64.30
LP-2 Ver. Members 30x30x2.0 5.94 1 10 1 10 59.40
Diagonal Members 30x30x2.0 8.05 1 10 1 10 80.50

Upper Part 30x30x2.0 5.00 1 4 1 4 20.00


Lower Part 30x30x2.0 4.28 1 4 1 4 17.12
LP-3 Ver. Members 30x30x2.0 4.05 1 4 1 4 16.20
Diagonal Members 30x30x2.0 5.60 1 4 1 4 22.40

Upper Part 30x30x2.0 4.05 1 1 1 1 4.05


LP-4 Lower Part 30x30x2.0 3.56 1 1 1 1 3.56
Ver. Members 30x30x2.0 3.51 1 1 1 1 3.51
Diagonal Members 30x30x2.0 4.90 1 1 1 1 4.90

Upper Part 30x30x2.0 1.40 1 1 1 1 1.40


LP-5 Lower Part 30x30x2.0 0.68 1 1 1 1 0.68
Ver. Members 30x30x2.0 0.81 1 1 1 1 0.81
Diagonal Members 30x30x2.0 1.40 1 1 1 1 1.40

Upper Part 30x30x2.0 3.98 1 1 1 1 3.98


LP-6 Lower Part 30x30x2.0 3.60 1 1 1 1 3.60
Ver. Members 30x30x2.0 3.51 1 1 1 1 3.51
Diagonal Members 30x30x2.0 4.90 1 1 1 1 4.90

Upper Part 30x30x2.0 3.00 1 1 1 1 3.00


LP-7 Lower Part 30x30x2.0 2.46 1 1 1 1 2.46
Ver. Members 30x30x2.0 2.43 1 1 1 1 2.43
Diagonal Members 30x30x2.0 3.50 1 1 1 1 3.50

Upper Part 30x30x2.0 2.00 1 1 1 1 2.00


LP-8 Lower Part 30x30x2.0 1.56 1 1 1 1 1.56
Ver. Members 30x30x2.0 1.62 1 1 1 1 1.62
Diagonal Members 30x30x2.0 2.45 1 1 1 1 2.45

Upper Part 30x30x2.0 1.01 1 1 1 1 1.01


LP-9 Lower Part 30x30x2.0 0.37 1 1 1 1 0.37
Ver. Members 30x30x2.0 0.54 1 1 1 1 0.54
Diagonal Members 30x30x2.0 1.05 1 1 1 1 1.05

Upper Part 30x30x2.0 0.74 1 1 1 1 0.74


LP-10 Lower Part 30x30x2.0 0.32 1 1 1 1 0.32
Ver. Members 30x30x2.0 0.54 1 1 1 1 0.54
Diagonal Members 30x30x2.0 1.05 1 1 1 1 1.05

Upper Part 30x30x2.0 1.44 1 2 1 2 2.88


LP-11 Lower Part 30x30x2.0 0.68 1 2 1 2 1.36
Ver. Members 30x30x2.0 0.81 1 2 1 2 1.62
Diagonal Members 30x30x2.0 1.40 1 2 1 2 2.80
Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC
Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC
Upper Part 30x30x2.0 2.14 1 1 1 1 2.14
LP-12 Lower Part 30x30x2.0 1.58 1 1 1 1 1.58
Ver. Members 30x30x2.0 1.62 1 1 1 1 1.62
Diagonal Members 30x30x2.0 2.45 1 1 1 1 2.45

Upper Part 30x30x2.0 2.84 1 1 1 1 2.84


LP-13 Lower Part 30x30x2.0 2.45 1 1 1 1 2.45
Ver. Members 30x30x2.0 2.43 1 1 1 1 2.43
Diagonal Members 30x30x2.0 3.50 1 1 1 1 3.50

Upper Part 30x30x2.0 3.55 1 1 1 1 3.55


Lower Part 30x30x2.0 2.79 1 1 1 1 2.79
LP-14
Ver. Members 30x30x2.0 2.70 1 1 1 1 2.70
Diagonal Members 30x30x2.0 3.85 1 1 1 1 3.85

Upper Part 30x30x2.0 4.24 1 1 1 1 4.24


Lower Part 30x30x2.0 3.67 1 1 1 1 3.67
LP-15
Ver. Members 30x30x2.0 3.51 1 1 1 1 3.51
Diagonal Members 30x30x2.0 4.90 1 1 1 1 4.90

Upper Part 30x30x2.0 4.94 1 1 1 1 4.94


Lower Part 30x30x2.0 4.28 1 1 1 1 4.28
LP-16
Ver. Members 30x30x2.0 4.05 1 1 1 1 4.05
Diagonal Members 30x30x2.0 5.60 1 1 1 1 5.60

Upper Part 30x30x2.0 5.64 1 1 1 1 5.64


LP-17 Lower Part 30x30x2.0 5.16 1 1 1 1 5.16
Ver. Members 30x30x2.0 4.86 1 1 1 1 4.86
Diagonal Members 30x30x2.0 6.65 1 1 1 1 6.65

Upper Part 30x30x2.0 1.10 1 1 1 1 1.10


LP-18 Lower Part 30x30x2.0 0.66 1 1 1 1 0.66
Ver. Members 30x30x2.0 0.81 1 1 1 1 0.81
Diagonal Members 30x30x2.0 1.40 1 1 1 1 1.40

Upper Part 30x30x2.0 3.16 1 1 1 1 3.16


LP-19 Lower Part 30x30x2.0 2.80 1 1 1 1 2.80
Ver. Members 30x30x2.0 2.70 1 1 1 1 2.70
Diagonal Members 30x30x2.0 3.85 1 1 1 1 3.85

Upper Part 30x30x2.0 2.89 1 1 1 1 2.89


Lower Part 30x30x2.0 2.46 1 1 1 1 2.46
LP-20
Ver. Members 30x30x2.0 2.43 1 1 1 1 2.43
Diagonal Members 30x30x2.0 3.50 1 1 1 1 3.50

Upper Part 30x30x2.0 4.34 1 1 1 1 4.34


Lower Part 30x30x2.0 3.68 1 1 1 1 3.68
LP-21
Ver. Members 30x30x2.0 3.51 1 1 1 1 3.51
Diagonal Members 30x30x2.0 4.90 1 1 1 1 4.90

On Axis C/1'-2 30x30x2.0 6.80 1 1 1 1 6.80


On Axis 2/A-B 30x30x2.0 11.90 1 1 1 1 11.90
Gutter
On Axis 2/E-F 30x30x2.0 5.80 1 1 1 1 5.80
Supporting RHS
On Axis E/1-2 30x30x2.0 6.76 1 1 1 1 6.76
On Axis 4/D'-F 30x30x2.0 10.78 1 1 1 1 10.78
On Axis C/1'-2 (T-3) 30x30x2.0 12.90 1 1 1 1 12.90
On Axis 2/A-B(T-1) 30x30x2.0 10.54 1 2 1 2 21.08
Purlin
On Axis 2-3/C-E 30x30x2.0 8.58 1 1 1 1 8.58
Supporting RHS
On Axis 4/D'-E 30x30x2.0 5.62 1 1 1 1 5.62
On Axis 4/E-F(T-4) 30x30x2.0 10.96 1 1 1 1 10.96
Valley Gutter On T-2 30x30x2.0 12.35 1 1 1 1 12.35
Supporting On T-5 30x30x2.0 8.43 1 1 1 1 8.43
Project:- Saving Houses B+G+8 Typology Revision Block Type:- New B+G+8
Client:- Addis Ababa Saving Houses Development Enterprise Block No.____________
Contractor: ______________________ Payment No._final payment_
Consultant: K2N Architecture and Engineering Consultancy PLC
Total Length (m) 1430.27
Unit Weight (kg/m) 1.68
Total Weight ( kg) 2,402.85

926.84 kg 40X40X3mm RHS Truss Member


426.26 kg 30x30x2.5mm RHS Truss Member
2,402.85 kg 30x30x2mm RHS Purlin Member