You are on page 1of 11

TECHNICAL REPORT

ON
GEOTECHNICAL INVESTIGATION
Name of Project

BR. No. 2B CH - 6045.250


Name of Client

ISO/IEC 17025:2017 ACCREDITED

Regd. Office Work Office

C-2, Vardhmannagar, A-14, CP Nagar Part-2


Nr. Arjun Tower,Ghatlodia, Opp. Arjun Tower, Ghatlodia,
Ahmedabad - 380061 Ahmedabad - 380061

********
E-mail: vishwasgeotech@gmail.com | Web: www.vishwasgeotech.com | Ph: +91 9925965217
INDEX

Sr. No. Contents

1 Introduction

2 Field Investigation

3 Laboratory Investigation

4 Results

5 Soil Stratifications

6 Summary

7 Conclusion & Recommendation

8 Appendix

a. Tables

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


GEOTECHNICAL INVESTIGATION REPORT

1 Introduction:

For foundation analysis of the structure on the site, it is necessary

1 To determine soil profile of the site.


2 To know physical properties and strength characteristics of soil at various depths.
3 To determine the Safe Bearing Capacity of the soil at different depths for the
different width of footings for the test point.
4 To locate the presence of ground water level.
5 To give conclusion and recommendation.

The soil exploration work was carried out at the project site / location given by the client.

The following points were decided:

1 Bore hole - 01
2 Depth of Borehole 5.00 meters

Based on the above points the detailed Geotechnical Program includes

A Field Investigation

1 Drilling of Bore hole


2 Collection of soil samples (Disturbed & Undisturbed)
3 Conducting standard penetration test

B Laboratory Investigation

For Soil
1 Bulk density and moisture contents
2 Grain size analysis
3 Index properties
4 Shear tests

C Recommendations

Based on the above investigations, the results are to be obtained. The findings would be
based on interpretation of results, analysis and computations as per relevant Indian standards.

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


2 Field Investigation

2.1 Boring

Bore Hole No. Location Depth Investigation (m)

0
Bore hole - 01 5.00

BR. No. 2B CH - 6045.250


The exploratory boreholes of 100/150 mm diameter were drilled by Percussion
& Hand Augering method. The depth of the test bore at the
proposed location is 5.00 Meter

2.2 Sampling

2.2.1 Disturbed samples

Disturbed samples were collected during boring and also from the split spoon
sampler. The samples collected were logged, labeled and placed in polyethylene
bags and sent to laboratory for testing.

2.2.2 Undisturbed samples

Undisturbed samples were collected in thin walled Shelby tubes, sealed with
wax, labeled and transported to laboratory for testing.

2.2.3 Standard Penetration Test

The standard penetration tests were conducted in accordance with IS 2131-1981.


The test gives N – Value, which is the number of blows of last 30cms penetration
of split spoon sampler with 65Kg. hammer free fall from 75cms height.

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


3 Laboratory Investigation

The following laboratory tests were conducted on undisturbed and disturbed soil samples
collected from various depths to find physical properties and strength characteristics. To
measure the soil properties in the laboratory, following tests were conducted.

Sr. No. Tests Recommended Procedures Type Samples


1 Sample Preparation IS 2720 Pt. I DS / UDS
2 Moisture Contents IS 2720 Pt. II DS / UDS
3 Dry Unit Weight LAMBE UDS
4 Specific Gravity IS 2720 Pt. III DS
5 Liquid Limit IS 2720 DS
6 Plastic Limit IS 2720 Pt. V DS
7 Grain Size Analysis IS 2720 Pt. IV DS
8 Soil Classification IS 1498 DS / UDS
9 Direct Shear Test IS 2720 Pt. XIII UDS

4 Results
1 S.B.C./A.B.P. are shown in Summary.

2 The laboratory test results of borehole are shown in Table No. 1.


3 The Borelog details of borehole are shown in Table No.-2

5 Soil Stratification

Borehole No. Depth (meter) Description

0.00 to 1.50 Non plastic silty Sand mix

BH- 01 1.50 to 2.00 Non plastic silty Sand mix with rock particles

2.00 to 5.00 Highly weathered rock of weak in strength

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


6 A-Typical Calculation for Allowable Bearing Pressure (As per IS 12070 – 1987)
based on Core Strength

Calculation for Permissible Bearing Pressure of Rock

Safe Bearing Pressure(Gross) (qs) = Nj * qc

Where Nj = Empirical coefficient depending upon spacing of discontinuities.


& Including a Factor of Safety of 3

3+S/Bt 0.14
Nj =
10 √1+300ᵟ/S

ᵟ = thickness of discontinuities in cm, 0.4


S = spacing of discontinuities in cm, 30
Bt = footing width in cm. 700

Type of Discontinuity Nj
Very Wide 0.40
Wide 0.25
Moderately 0.10

qc = Average unconfined compressive strength of rock


= 46 Kg/cm2 at 3.00 meter depth

Considering Moderately Discontinuity & Computing the above values,

qs = 0.14 46

2
= 6.26 Kg/cm

Gross Safe Bearing Pressure = 6.26 Kg/cm2

S.B.P.(Gross) = 62.60 t/m2

Correction for Submerged Condition = 0.50

Correction for Cavities = 1.00

Correction for Slope = 0.50


2
Say A.B.P. = 16 t/m (After Applying Corrections)

Report No-VGPL / 23-24 / 0412/003 Vishwas Geotech Pvt. Ltd.


7 Summary
Analysis of A.B.P. BH-01
Depth Depth Type Size Net S.B.C. t/m2 Recomm.
Below Below of of Shear Settlement Net
Exisitng Natural Foundation Foundation Criterion Criteria S.B.C.
G. L. G. L. C &  Value t/m2
(meter) (meter) mtr. x mtr.
2.00 2.00 Rectangular 7.00 x 3.00 13.00 13.00

2.50 2.50 Rectangular 7.00 x 3.00 14.00 14.00

3.00 3.00 Rectangular 7.00 x 3.00 16.00 16.00

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


8 Conclusion & Recommendations:

 The study of the soil investigation at the site at various depths indicates
layers as shown in the general stratifications.
 Ground water table is not encountered at the time of investigation.
 Any variation in stratification in any of the foundation location shall be studied
thoroughly before executing the foundation work.
 For design of foundation, it is recommended that sub-soil condition should be
considered in the influence zone of foundation.
 The depth of Foundation is to be considered from natural ground level.
 S.B.C. / A.B.P. is recommended by considering all the parameters affecting to soil
& rock at the field as well as in the laboratory.
 If at the time of actual excavation major solution cavaties have been found which
have rendered the ground surface uneven, the depth of foundation should be taken
to a level such that 80 percent rock area is available. It must be ensured that the raft
does not over hang at any corner.
 Otherwise excavate the filled up soil up to 80 percent area level and backfill it by
Iean concrete of required strength. However, the rock has to be excavated up to
the pre-selected foundation level.
 If after excavation, loose pockets of talus deposit are found out at a few places, the
same should be cleaned and backfilled with lean concrete.
 If very deep observation pits have been made at the site, the same should be
backfilled by lean concrete up to the foundation level.
 Due attention should be paid to problems of foundation on hetrogeneous rocks
particularly foundations on rock slopes and necessary remedial measures should
be taken.
 Care should be taken to remove loosened pieces of rock from the foundation after
blasting (if required) and washing & air jetting has been done so that foundation rest
on practically undisturbed rock mass.
 Depth of rock may vary other than exploration point so it is advisable to rest the
foudation on rock surface by removing upper loose granular soil strata.

Date-01/05/2023

For, Vishwas Geotech Pvt. Ltd.

Authorised Signatory

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


NOTATIONS

C Cohesion

 Angle of internal friction of soil

DS Disturbed Sample

UDS Undisturbed Sample

SPT Standard Penetration Test

NP Non Plastic Soils

Cc Compression Index

Pc Pre Consolidation pressure

TUU Unconsolidated undrained traixial test

DUU Unconsolidated undrained direct shear test

HWR Highly Weathered Rock

MWR Moderately Weathered Rock

FR Fresh Rock

TCU Consolidated Undrained traixial test

DCU Consolidated Undrained Directshear test

REFERENCE
Indain Standards IS 2720 Pt. II, III, IV, V, XIII, XXXI, XXVI, XXV IS 1498, IS 6403, IS 1904, IS
IS : 12070 - 1987, IS : 8009 - Pt- 1 - 1973, IS : 4453 - 1967

Murthy V.N.S. Soil Mechanics and Foundation engineering ( Dhanpat Rai and Sons Delhi )

Lambe T.W. Soil testing or Engineers ( Wilery Easter Ltd., New Delhi )

Peck. R.S. Hanson W.E. Foundation Engineering ( Asia Publishing House )

Nayak N.V. Foundation Engineering Manual ( Dhanpat Rai and Sons )

Kaniraj S.R. Design aids in soil mechnaics and foundation Engineering


( Tata Mc Graw Hill Publishing Co. Ltd. )

Alam Singh Modern Geotechnical Eng. ( IBT Publishing & Distrubutors Delhi. )

Report No-VGPL / 23-24 / 0412 /003 Vishwas Geotech Pvt Ltd.


Vishwas Geotech Pvt. Ltd. Borehole Lat: TABLE - 2
SUMMARY OF EXPLORATION DATA Co-ordinates Long:
Ahmedabad Borehole - 01
Particle Atterberg's Shear Consoli For
Size Limit Parameters Test Rock
Analysis

Unconfined Compressive Strength (kg/cm )


2
Gravel % - 4.75 mm & above

Modulus of Elasticity (Mpa)


Sand % - 0.075 to 4.75 mm

Natural Moisture Wn %
Clay % - Less than 0.002 mm

Water Absorption (%)


Silt % - 0.002 to 0.075 mm

Free Swell Index (%)


Cohesion kg/sq.cm.
Sample No. & Type

Specific Gravity Gs
Dry Density gm/cc
IS Classification

Plasticity Index

p.c. kg/sq.cm.
Depth in mtr.

Liquid Limit

Plastic Limit

Type of Test

Silt Factor
Hatching

Hardness
Visual Description

Porosity
Degree
of Soil & Stratum

c.c.
To

No.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Non plastic silty
0.00 0.50 DS Sand SM 2 79 19 22 NP NP
Non plastic silty
Sand mix with rock
1.50 1.95 UDS particles SM 19 71 10 18 NP NP 1.61 5.40 2.62 0.00 32 DUU

2.00 2.45 SPT HWR


Highly weathered
2.50 3.50 UDS HWR 1.68 2.68 5.60 0.37 2 41 12207
rock of weak in
strength
3.50 4.50 UDS HWR 1.70 2.69 5.50 0.37 2 50 13115

4.50 4.95 SPT HWR

Report No-VGPL / 23-24 / 0412/003 Vishwas Geotech Pvt Ltd.


BORELOG

Borehole - 01 Depth of Bore : 5.00 Mtr


Thickness of Layer (M)

Un Disturbed Sample

Core Recovery (%)


Method of Boring

Disturbed Sample
S.P.T. No. of Blows
Bore Diameter

Depth ( M)

RQD (%)
N- Value
Hatching

Remark
G.W.L.
Casing

VISUAL SOIL
DESCRIPTION N1 N2 N3

0.00 0.00
Non plastic silty
1.50 Sand mix rock
particles
1.00

1.50
Non plastic silty
0.50 Sand mix with rock
2.00 particles 18 22 32 54 2.00

2.50 17.33 NIL

3.00

Highly weathered
Machine Driling

3.50 18.00 NIL


3.00 rock of weak in
Not Used
150 mm.

strength
-

4.00

29 34 39 73 4.50

5.00

6.00

7.00

8.00

9.00

Report No-VGPL / 23-24 / 0412/ 003 Vishwas Geotech Pvt Ltd.

You might also like