Hydropower Energy & General Construction SP LLC.

SITE SURVEY & DRAWING SCHEDULE


Project Name
G-432023 Rehabilitation of Graveyards in Al Ain Region.

Cemetery Name Registeration Number Site Survey

OGL
Benchmark Used for
Plot Code (MePS)
Survey Works
Start Date Finish Date

MAZYAD -019 B2S-2020-001613 (New) 16-Jan-2024 16-Jan-2024

MAZYAD -168 B2N-2019-006468 16-Jan-2024 16-Jan-2024

MAZYAD -112 B2N-2019-006472 16-Jan-2024 16-Jan-2024

UMM GHAFA -003 B2S-2019-007699 11-Jan-2024 11-Jan-2024


EAST

UMM GHAFA -242 B2S-2019-007698 17-Jan-2024 17-Jan-2024

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


EAST
Hydropower Energy & General Construction SP LLC.

SAA' -101 B2SE-2019-07701 17-Jan-2024 17-Jan-2024

SAA' -781 B2N-2019-006478 23-Jan-2024 23-Jan-2024

SAA' -782 B2N-2019-006482 23-Jan-2024 23-Jan-2024

AL KHARIR -104 B2N-2019-006477 18-Jan-2024 18-Jan-2024

TOWN CENTER -003 B2S-2019-007669

AL MUTAWA'A -007 B2S-2019-007677

AL MUTARED -123 B2SE-2019-07653 11-Jan-2024 11-Jan-2024


TOWN CENTER

AL FOAH -913 B2S-2020-000650 (New)

QATTARA -115 B2N-2019-006121

CITY CENTER -116 B2SE-2019-07674

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


Hydropower Energy & General Construction SP LLC.

AL AFLAJ -001A B2N-2019-006097

AL AMERAH -189 B2S-2019-007398


WEST

RAMAH -008 B2N-2019-006488

AL KHAZNA -900 B2S-2019-007707

SWEIHAN -152 B2S-2019-007709

AL HAYAR -618 B2N-2019-006498

AL HAYAR -125 B2M-2019-006500


NORTH

AL HAYAR -234 B2N-2019-006503

AL HAYAR -511 B2N-2019-006501

NAHIL -582 B2N-2019-006505

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


Hydropower Energy & General Construction SP LLC.

NAHIL -405A B2N-2019-006515

AL WAQAN -614 B2M-2019-006484


SOUTH

AL ARAD -761 B2M-2019-006486

AL QUA' -300 B2N-2019-006485

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


Hydropower Energy & General Construction SP LLC.

ey Drafting Works

Obstructions OGL Drawings Obstruction Drawings

Start Date Finish Date Start Date Finish Date Start Date Finish Date

16-Jan-2024 16-Jan-2024

16-Jan-2024 16-Jan-2024

16-Jan-2024 16-Jan-2024

11-Jan-2024 11-Jan-2024

17-Jan-2024 17-Jan-2024

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


Hydropower Energy & General Construction SP LLC.

17-Jan-2024 17-Jan-2024

23-Jan-2024 23-Jan-2024

23-Jan-2024 23-Jan-2024

18-Jan-2024 18-Jan-2024

18-Jan-2024

19-Apr-1900

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


Hydropower Energy & General Construction SP LLC.

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


Hydropower Energy & General Construction SP LLC.

G-432023 Rehabilitation of Boundary Walls of Graveyards in Al Ain Region


STATUS
APPROVED
RETURN WITH COMMENTS
REJECTED
UNDER REVIEW (TESSCO)
UNDER REVIEW (AACM)
UNDER PROCESS (HPE)