Professional Documents
Culture Documents
eng_mai_abdelwahab@hotmail.com
From: Dr.Hamdy Elkamhawy
Appendices 1- Modern Engineering Consultant Office Profile.
2- Top Engineering Services Profile.
Proposal for
Engineering Services
(Technical consultancy services)
A. Scope of work
• Creating the elaborate BOQ for the infrastructure work of the port terminal,
C. Fee Breakdown:
Unit Total
Code Item UOM QTY Fee Fee
(USD) (USD)
1.1 The elaborate BOQ for MEP works L.S. 1 13000 13000
1.2 The elaborate BOQ for Civil works L.S. 1 9000 9000
Monthly
2.0 Technical support throughout the entire project duration fee 6 18000 108000
D. Services Duration:
- The approximate duration of the service’s implementation for items
(1.1,1.2) is 6 weeks from the date of receiving the full documentents
package including the BIM model.
- The technical support service item (2.0) duration is 6 months.
E. General Expectations:
Please note that this proposal excludes the features such as:
- Geotechnical (soil) investigations (soils investigations are not part of our scope of work)
- Materials testing (testing concrete, steel, stone, rock, welds, etc.)
F. Changes
Changes that are made to the design for whatever reason following our completing our
work are charged extra.
Please note that this proposal will be valid for only 21 calendar days.
We look forward to being of service to you on this project. Please call should you have
any questions.