F0 33:SAFETY ORGANIZATION

JOB SAFE PRACTICE (5.19.2)

DEPARTMENT SAFETY EMPLOYEE JOB TITLE SAFETY ENGINEER


JOB/TASK TITLE FOC Splicing/Cable Termination works inside Hajar/Nujha S/S
STEPS HAZARDS CONTROLS REQUIRED TO OBSERVATION
STEP# LIST ALL STEPS IN PERFORMING THIS TASK IN EACH STEP , WHAT MINIMIZE /ELEMINATE HAZARD
COULD CAUSE INJURY,LOSS
DAMAGE
INTERUPTION,OR
POLUTION?
3. Insertion of communication cards to 1. Loose cable
the Panels connection 1. Tool box talk must be
2. Operation by conducted before
unauthorized starting the activities
person. 2. Ensure the workers are
3. Damage of the competent
circuit 3. Suitable footwear shall
4. Failure of the be provide & other PPE's
setting (Safety gloves, safety
glasses etc.)
4. Color codes for the
wires should use for easy
identification of
connection.
5. Barricade the work
area with warning tape.
6. All activities should be
done in the presence of
concern witness.

Prepared by: Approved by: Element 5.19 Page No: Page 1 of 2 Revision No: 00
Reference No:
F0 33:SAFETY ORGANIZATION
JOB SAFE PRACTICE (5.19.2)

7. Never touch the sharp


edges of electric wires.
8. Clean the permises
after the day task finish.

COMPILED BY Mr Shariq, Mr.Emad DATE 02- July-2020


MANAGER MANAGER

Prepared by: Approved by: Element 5.19 Page No: Page 2 of 2 Revision No: 00