LOOTAH BUILDING & CONSTRUCTION

Report on MIRBEH & QIDFA-CHANNEL & DIKE


LOCATION-2
INSIDE THE DAM-EXCAVATION FOR CUTTING

OUTSIDE THE DAM-COMPACTED GRANULAR SUBBASE


OUTSIDE THE DAM-GROUTED RIPRAP

OUTSIDE THE DAM-LOOSE RIPRAP


OUTSIDE THE DAM

S.No Item Description Unit Quantity


1 Excavation for Cutting-Soil/Rock/Artificial Hard m3 256,800
3
2 Compacted Suitable Excavated Material m 63,722
3
3 Grouted RipRap m 18,060
4 Loose RipRap m3 22,610

Comment: Partial work is done at initial stages ,we have to rectify and continue the pending works

Eng.Ahmed El Sheikh