Professional Documents
Culture Documents
Page
3 ANALYSIS PROGRAM
5 PILING CRITERIA
7 LOAD COMBINATIONS
9 RC PLINTH DESIGN
The size and location of two RC plinths of cooling water pump on an intersection gridline J,K and gridline 35,36
and intersection grid line K , L and gridline 35,36 were 1.65 mx 2.8m x0.3 m [New] and 1.6 mx 3.05m x0.3 m
[the original pump that it relocated], respectively
The two existing Chiller building(East side and West side ) are reinforced concrete building with WxLxH
is 19.3 meters, 136.5 meters and 15.1 meters respectively. that the number of bays is sixteenth , Both of
two existing Chiller buildings has 3 floors consisting of ground floor is mat foundation supporting many
Chiller machines and pumps , The 2nd floor is rc slab on beam for supported many cooling towers and RC water tanks ,
The 3rd floor is a mezzanine concrete roof to supported small machines . The new construction work It is located
on the ground floor and the 2nd floor.
However, the strength analysis of the original building due to the lateral force relying on information from the existing
structural drawings . We have not found a seismic detials for reinforcement so many position on As-built drawings
and the Existing building built for long years ago there is not design withstand earthquake in construction law on era
all above it was assumed that the original building (Existing) was not designed to withstand earthquakes.
therefore considering the lateral load of the building only the wind load . however we have applied
seismic force on the New adding reinforce concrete over an existing structure only
Mu
Ru = bd 2 N/mm2
0 . 85
'
1 1 2 '
0 . 85
fc
=
Ru f c
f y
As = bd mm2
Where ;
Mu = Ultimate moment kN×m
Ru = Resistance coefficient for ultimate
Moment kN/mm2
= Reinforcement steel ratio
= Strength reduction factor
= 0.90 ; for Moment
= 0.75 ; for Shear
bw = Width of considering section mm
bo = Perimeter of critical section mm
d = Effective depth mm
As = Area of reinforcement steel mm2
Remark
the property of existing data are refer from structure drawing " ITO -TB402-S030.000.00.00-00"
5.0 PILING CRITERIA
Layered system and soil parameter ref document (DPC12-T-ECC-201) , "DCAP Electric Chiller 8000 RT project "
Layer Depth (m) Thickness Soil type Consist STP Su Phi Total Unit
From To (m) Rel Density (blow/ft) (T/m^2.) (Degree) weight( t/m^3)
1 0 2.5 2.5 loose sand 3.0 29 1.43
2 2.5 3.3 0.8 loose sand 3.0 29 1.43
3 3.3 12 8.7 soft clay 1.34 1.51
4 12 16.5 4.5 medium stiff clay 3.22 1.73
5 16.5 18.5 2 stiff clay 7.21 1.88
6 18.5 22.5 4 stiff sandy clay 22.0 15.07 1.9
7 22.5 24 1.5 stiff sandy clay 14.0 7.28 1.9
8 24 25.5 1.5 stiff clay 11.0 5.72 1.9
9 25.5 26.5 1 Dense silty sand 35.0 37.1 1.9
10 26.5 28.5 2 medium dense sand 24.0 34.2 1.9
11 28.5 30.45 1.95 very dense sand 70.5 41 1.9
Remark ,
the ultimate bering capacity = 1100 t/m^2 is upper limit for BNBC (2015)
* = correction of SPT Value for overburden pressure Cn = 0.77log( 20/EOP), ksc. ,
** = correction of SPT due to Water table N' = 15+0.5(SPT*correcr factor - 15)
The ultimate pile capacity for Diven spun pile Dia 600 mm
Qu = 77.6 x3.1416x0.6 + 851.4*3.1416/4*0.6^2
= 387 ton.
Remark
Both an existing Cooling water pump and existing primary chilled water pump are moved gridline H-J to gridline J-K
and gridline G-H to gridline H-J of East side and West side,respectively
Exposure category C
Design wind velocity 38 m/s
Importance factor 1.15
Topographic factor 1
Cp = External pressure coefficient from Fig 6-6 use this below table
CP Wind X dir
X DIR Z DIR L= Hor dimention , parallel to wind = 19.30 m.
L/B = 0.14 7.07 B= Hor dimention, normal to wind = 136.50 m.
For windward wall 0.8 0.8 h= mean roof height = 17.89 m.
For leeward wall -0.5 -0.20 Roof degree = 1 Degree
For side wall -0.70 -0.70
UNIT; kg/m^2
Remark , Plus sign is pressure acting toward surface, minus sign is wind pressure away from surface.
6.2 the New RC plinth supporting Pumps
6.2.1 Dead load (DL)
This is member self-weight loading and loads of architecture materail that is fixed in position without moving
concrete plinth of Cooling water pump
- new pumps = 1.65x2.8x0.3x2.4 = 3.33 Ton
- the existing pump = 1.6x3.05x0.3x2.4 = 3.51 Ton
W Cooling water pump(existing) = 3.51+4.0 = 7.51 Ton. [Original pumps that relocated]
Therefore
F = 0.4ap SDS *W p /( Rp/Ip)*( 1+2z/h) = 0.046*W
< 1.6SDS*I*W p = 0.458* W
> 0.3*SDS*I*W p = 0.086*W [CONTROL]
In X-X dir
Moment at top of slab support = 647.58 x 1.315 m
= 852 kg-m.
In Z-Z dir
Moment at top of slab support = 647.58x1.215
= 787 kg-m.
Remark the CG. Of pump is height = 0.3 m+ 1.015m = 1.315 m above base.
Seismic force on Cooling water Pump ( 1 set ) , [ original pump that has been relocated ]
V = 645.9 kg.
In X-X dir
Moment at top of slab support = 645.86 x 1.325 m
= 856 kg-m.
Vertical force due to moment = 855.7645* (0.999) / (2*( 0.999)^2 + 2*( 0.333)^2 )
(outermost anchor) = 382 kg (+/-)
Vertical force due to moment = 855.7645* (0.333) / (2*( 0.333)^2+ 2*( 0.333)^2 )
( next 1 st row of outermost anchor) = 128 kg (+/-)
In Z-Z dir
Moment at top of slab support = 645.86x1.225
= 791 kg-m.
nh = constant ks =67Su/B
modulus of
Su
The Depth ( start horizontal
( kN/m3) ,
SPT-N subgrade (
dist ground level)
reaction kN/m2)
3
( kN/m ) ,
3 - 3.45 M 0 0.0
4.5 - 5.0 M 9.2 1027.3 ( Soft clay) The average ks = 1188 kN/m3
6 - 6.5 M 13 1451.7 Therefore kh = ks x B x L
7.5 - 8.0 M 15.7 1753.2 = 1188 x 0.6 mx 9.5 m
9.0 - 9.5 M 15.3 1708.5 = 6.77E+03 kN/m.
10.5 - 11.0 M 11.3 1261.8
12 - 12.5 M 25.9 2892.2 ( Soft clay) The average ks = 3533 kN/m3
13.5 - 14 M 31.4 3506.3 Therefore kh = ks x B x L
15 - 15.5 M 35.7 3986.5 = 3533 x 0.6 mx 7.5 m
16.5 - 17 M 53.9 6018.8 = 1.59E+04 kN/m.
18 - 18.5 M 90.40 10094.7 ( Hard clay)
18.5 - 18.95 M 90.40 10094.7 The average ks = 10094.7 kN/m3
19.5 - 19.95 M 90.40 10094.7 Therefore kh = ks x B x L
= 10094.7 x 0.6 mx 2.95 m
21 - 21.45 M 9 6500 = 3.92E+04 kN/m.
22.5 - 22.95 M 14 8200
24.0 - 24.45 M 11 7600
25.5 - 25.95 M 35 17000 ( dent sand )
27.0 - 27.45 M 24 8500 The average ks = 9,560 kN/m3
28.5 - 28.95 M 72 30000 Therefore kh = ks x B x L
30.0 - 30.45 M 69 36000 = 9560 x 0.6 mx 6.45 m
= 3.70E+04 kN/m.
Remark
nh is range 2710 - 8140 kN/m3 upon on medium and dent , respectively is inorganic silt
,Sand, normal consolidation clay acordding to ACI installation concrete pile.
B= the width of Bore pile = 600 mm , ,ks = subgrade modulus of clay, Su = undrained shear strength of clay