Professional Documents
Culture Documents
Tunnel (BBDMP)
LAB LAB
180,000
167,810
200,000
180,000
SIP RJKIP BBDMP
160,000
140,000
120,000
80,110
70,000
100,000
56,540
51,432
80,000
45,000
42,348
35,240
60,000
20,136
13,836
40,000
5,580
20,000
0
Aggregate Concrete Sample Cubes Steel Bar
(295,000 m3) (261,590 m3) (39,552 No.) (171,890 qtl.)
Objective of (Quality) Life
• Happiness (सख
ु ) • Peaceful (शान्ति) • Blissful(आनतद)
IQ-EQ-MQ-SQ
• Satisfaction is better than Success
• Success is evaluated by other person whereas Satisfaction is
evaluated by self.
QA&QC likely to based on Buddhism
बद्
ु धर् ् शरणर् ् गच्छामर्
(Let us follow experience & knowledge)
𝑬𝒒.𝑭𝒐𝒓𝒄𝒆 (=𝑴𝒙𝒂)
Earthquake Damage=
𝑫𝒆𝒔𝒊𝒈𝒏 & 𝑪𝒐𝒏𝒔𝒕𝒓𝒖𝒄𝒕𝒊𝒐𝒏 𝑸𝒖𝒂𝒍𝒊𝒕𝒚
Quality Assurance plan
• Quality Assurance (QA) is process oriented and focuses on
defect prevention
• Quality Assurance (QA) makes sure you are doing the right things,
the right way which is based on Method
-Management Tool
Skill
Practical Knowledge to do
Attitude
Willingness to do & Share
Quality Control System of Headworks of Sikta Irr. Project (SIP), Rani Jamara
Kularia Irr. Project (RJKIP) & Tunnel construction of Bheri Babai Diversion
Multipurpose Project (BBDMP)
× ×
100% 95%
Batching & Mixing But, this principle
× × does not apply
Transportation & Pouring 100% 95% here!
× ×
Compaction 100% 95%
=
level of finishing
Concrete Structure 100% 70% structure”
3C Relation
Obey the
Professional
Person from
wherever the
position
Consultant
Quality of Time Value
Cofferdam planning
15m deep Sump well for 11m deep
cutoff construction
11 m
Depth
Intake side
Optimaization of Design
Clean water in Intake of Karnali Flood-Support for Settling basin
Tunnel Construction of Bheri Babai Diversion
Multipurpose Project by using TBM
Bheri
Babai River
River
Underconstruction
Miss Communication among Two Group of Same Work
Two group working with same drawing from beginning point &
end point
Vision or Intension of Specification from
Engineer (Consultant or Client) & Contractor
Typo mistake
God is nowhere = God is no_where or God is now_here ?
There was mentioned in the specification only “tests shall be carried out by
contractor” and no any mentioned about equipment establishment and mode of
payment of the tests. Contractor claimed on this issue, what will be the solution?
Quality Assurance Plan
The Contractor (minor, moderate & major) shall submit Quality Assurance Plan
(QAP) to the Engineer for his approval which shall be based on the detailed
Program of the Works
The Quality Assurance Plan shall include the following:
The test schedule and testing program detailing the list of tests for compliance,
laboratory trials, site trials and trials sections, construction control tests and
their frequencies, Estimate of the number of tests to be carried out, list and
number of appropriate equipment to conduct them, list of tests to be conducted
outside the site laboratory, if any, identification of the outside laboratory where
proposed to carry out the test as in following table
Spec.limit Cond
Item as in Test No. of Spec./code Conduct Rem
Material Tests Requireme Qty. Equipment ucted
BoQ Frequency test Reference ed at arks
nt by
Quality Assurance Plan
• List of staff assigned to the laboratory, their position and responsibilities in the
quality control procedures, their qualification and experience,
• General description and detailed organization of the laboratory activities.
• The list of sources of materials,
• their main characteristics & identification mode as provided by the supplier
when required
• the program of supply and procurement of material and/or manufactured
articles in accordance with the Program
The Contractor shall implement the Quality Control (QC) in compliance with the
approved QAP.
The Engineer’s approval of the QAP shall not relieve the Contractor from his
responsibility of the quality of the Works as per the Conditions of Contract and these
Specifications
Project Organization Chart
Content of Quality Assurance of Plan (QAP)
Reporting of Activities
Verifying Performed
S.N. Activity Approved by
document by
Contractor’s
1. Site diary Site report Site Engineer
Representative (CR)
2. Progress report Progress report Site Engineer CR
3. Accident report Accident report Safety Officer CR
Planned vs. progress Program and progress
4. Site Engineer CR
report report
Environmental
5. Environmental report Environmental report CR
Engineer
Report to the Progress report to the
6. Site Engineer CR
engineer Engineer
7. Claims Measurement report QS Engineer CR
Note: Calibration of Testing Machine shall be carried out each year and it shall be
invalid if the machine is disturbed or moved.
Batching Plant Calibration
Quality Assurance Plan of Reinforcement Bar
Spec.limit Cond
Test No. of Spec./code Conduct Rem
Item Material Tests Requireme Qty. Equipment ucted
Frequency test Reference ed at arks
nt by
As per
Weight per
specified in Lab
running Site Lab
code for Staff
meter
different dia
No visible Lab
Bend test Site Lab
crack Staff
Universal
Tensile
Machine
Re bend Lab
No fracture Site Lab
test Staff
Quality Assurance Plan of Concrete M50/20 in BBDMP
Spec.limit
No. of Spec./code Conduct Conduct Rema
Item Material Tests Requiremen Qty. Test Frequency Equipment
test Reference ed at ed by rks
t
> 225 m2/kg; < each lot/Every 200 t
Fineness
10 % and part of it IS 4031 Part 2
each lot/Every 200 t
Setting time >125T Vicat Apparatus Lab Lab Staff
and part of it IS 4031
or
Cement IS 8112:1989 each lot/Every 200 t Part - 5
Consistency every
& IS 12269- and part of it
lot
1987 Cement mortar mould,
Comp. each lot/Every 200 t IS 4031
Tamping Rod, Trowel, Lab Lab Staff
Strength and part of it Part - 6
Crushing machine
As required/Every 100 t NS 305-2020
Gradation As Specified Sieves , balnance, trays Lab Lab Staff
and part of it or IS 460
Sand
Clay/Mica As required/At least IS 2386 Balance,sieve,measuring
<3.0 % Lab Lab Staff
content once every source Part-2 cylinder
A(5.1) As required/Every 250 t Every NS 305-2020
Gradation As Specified Sieves , balnance, trays Lab Lab Staff
Precast or part of it Week or IS 460
Concret ACV mould,Balance,
IS 2386
ACV <30 % As required/Every 500 t 2.36mm sieve, Crushing Lab Lab Staff
e Part-4
51555. machine
Segmen Flkiness/Elong 6 m3 As required/200 m3 & IS 2386 Thickness and Length
tal lining <40 % Lab Lab Staff
ation Indices each new source Part-1 gauge, Balance
work Aggregat Sodium
e Sulphate As required/At least Sodium Sulphate,
<15 % 8 ASTM C88 Lab Lab Staff
Soundness one for each source Oven,Balance
(SSS)
As required/At least BRE Digest
Shrainkage <0.065% 4 Out st
one for each source 35
ACV mould,Balance,
Every IS 2386
10% fine value >50KN. As required/Every 500 t 2.36mm sieve, Crushing Lab Lab Staff
Week Part-4
machine
Out st
water Quality As Specified As required
TBM
Platform
Employer’s
Camp
弃土场
Segment
Contractor’s Plant
Camp
Dumping
Site
Crushing Quarry
Plant Site
TBM Platform, Employer’s Camp & Contractor’s Camp
(28o21’30”N,81o43’10”E)
Employer’s
Camp
Contractor’s
Camp
Office & Quarter (Client-Consultant-Contractor) Environment
Safety Measures
Documentation of Special events
58
View of 16m Cutting
Hierarchy of Failures
I. Insufficient Supervision (Quality Control) in Construction
II. Insufficient Detailing in Drawings & Construction
III. Inadequate Structural Design
Design
Detailings
Supervision
Fineness of cement by
Sp. Gr. Test of Cement Setting Time Testing Consistency Test
Blaine Permeability Test
Curing of Cement
Mortar Preparation mortar cube
Expansion Test Cement Mortar Test
28 DAYS COMPRESSIVE STRENGTH OPC43
(STRENGTH VS PRODUCTION TIME PERIOD)
64.21
62.20
70
52.17
60
47.49
45.81
Old (>3month)
43.47
Strength, N/mm2
50
43
34.78
40 Fresh (1 Week)
28.42
28.42
30
Normal (5 Week)
20
10
0
Reqd.43 Prism 43 Jaypee 43 ACC 43
Cement Brand
2.Aggregates
Combined (0-40)mm
➢Gradings 100
90
percentage passing(%)
➢Single vs Crushers 80
70
60 upper limit
➢Clay content in FA 50
40
lower limit
30 actual curve
20
10
0
0.15 0.6 2.36 5 10 20 37.5 50
si eve si ze(mm)
63
Crushing & Screening Plant (BBDMP)
Jaw Crusher
Impact Cone
Crusher Crusher
Shape of Aggregates produced from
Different Crusher Plant
Production with
Jaw crusher
only
Production with
Jaw, Cone &
Impact crusher
(BBDMP)
Comparison of Aggregate Properties in
different Projects
Limiting Value
273.3
300
259.1
Sikta I.P.
250
RJK I.P.
200 BBDMP
137.8
Value
150
100
50
40
40
50
35
23.4
23.1
20.2
16.7
16.6
15.7
15.2
7.0
5.8
0
Agg.Crushing Ten % Fine Value Flakiness Index Elongation Index
Value (%) (KN) (%) (%)
Aggregate Properties
Sampling of Steel Bar (Fe 500D) before unloading at site
for the Test on the same day
Tensile Strength of Steel bar(Rhino 500D)
800
Reqd. Yld. Strength Yld. Strength Reqd. Ult. Strength Ult. Strength
700
Tensile Strength (MPa)
600
500
Fail
400 Slip Slip Slip
Slip Slip
300 Slip
220
100
110
120
130
140
150
160
170
180
190
200
210
230
Test No.
Strength of Sagarmatha OPC vs Shivam OPC
Sagarmatha 3 day Sagarmatha 7 day Sagarmatha 28 day
Shivam 3 day Shivam 7 day Shivam 28 day
Reqd. Strength 3 day Reqd. Strength 7 day Reqd. Strength 28 day
80
70
Comp. Strength (MPa)
60
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Test No.
Schematic Diagram of
Concrete Batching Plant
Batching Plant, SIP, Banke
71
Batching Plant,
Aggregates stored
BBDMP(50,m3/hr)
under Shade
Compressive Strength of Precast Segment
80
(M50)
7 day 28 day Design 28 day Strength Poly. (7 day) Poly. (28 day)
75
70
Comp. Strength (MPa)
65
60
55
50
45
Average 7day=53.52MPa; Average 28day=67.66MPa
40
Concrete Mix Ratio (W/C:C:FA:CA:Adm.)
SIP -0.370:1:1.54:2.74:1% Sika170N (Agg. 40 down)
35 RJKIP -0.400:1:1.48:2.89:5%Silica+0.25% Hyper (Agg. 40 down)
BBDMP-0.325:1:1.853:2.281:0.5% Sika 20HE (Agg. 20 down)
30
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400
Concrete Sample Id.
Cycle of Pre-cast Segment Production
from 28 no. Mould (4Segment/ring of 1.4m wide)
Cumulative Segment Production, Consumption & Balance
14000
12127
12127
12127
12127
12055
Segment Production Started : 3 Aug 2017
11959
11847
12000
11131
Segment Production End : 12 Jan 2019
11101
10913
10365
Tunnel Excavation Started : 15 Oct 2017
10040
Breakthrough Ceremony : 16 Apr 2019
9424
10000
9283
8612
8443
7922
Length (m)
7489
8000
7256
6773
6193
Cumulative Segment Production
5963
4733
Segment Balance
4222
3858
3487
4000
2857
2842
2206
2197
1817
1807
1753
1711
1654
1506
1502
1365
1311
2000
1296
1282
1230
1224
1215
1187
1131
1125
1113
1101
1096
996
447
447
343
168
72
27
27
11
0
0
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
2017 2018
Date 2019
Daily Tunnel Excavation by TBM
(15 Oct 2017 to 16 Apr 2019)
Ch. 0+150.7 of Ch. 12+206.2
Breakthrough on Apr 16, 2019
70
TBM Excavation Stoppages Best day : 61.77m (2 Aug 2018)
1. 19Oct-29Oct,17: For TBM trial test and lack of segment accessories
2. 19May-8Jun,18: Tunnel Crown Grouting
Average/working day : 28.65m
3. 8Jul -13Jul,18: TBM maintenance before Bheri Thrust zone location Average/day : 23.52m
60
4. 30Aug- 7Sep,18: California Switch installation at Ch.6+500 Average Monthly : 709m
5. 11Sep-14Sep,18: Rotary Dumper repair Best Week : 324.53m (2018 Aug 2-Aug 8)
6. 16Oct-22Oct,18: TBM Stuck at Ch.8+588 Best Month : 1062.67m (Aug, 2018)
50 7. 7Nov- 9Nov,18: Tihar Festival
8. 3Nov-18Nov,18: Rotary Dumper repair
9. 4Apr-15Apr,19: Preparation for breakthrough
40
Length (m)
30
Av./day=23.52m
20
10
11 15
12 13 14 16 17 18 19
0
2-Sep-18
18-Feb-18
15-Apr-18
22-Jul-18
17-Feb-19
15-Oct-17
29-Oct-17
10-Jun-18
24-Jun-18
12-Nov-17
26-Nov-17
7-Jan-18
29-Apr-18
14-Oct-18
28-Oct-18
16-Sep-18
30-Sep-18
11-Nov-18
25-Nov-18
9-Dec-18
23-Dec-18
6-Jan-19
14-Apr-19
10-Dec-17
24-Dec-17
21-Jan-18
4-Mar-18
13-May-18
27-May-18
20-Jan-19
3-Mar-19
18-Mar-18
17-Mar-19
31-Mar-19
4-Feb-18
1-Apr-18
8-Jul-18
5-Aug-18
3-Feb-19
19-Aug-18
Date
Tunnel Length Excavation by TBM (m)
2000
4000
6000
8000
0
10000
12000
14000
15-Oct 162
5-Nov 402
493
2017
Dec 904
1246
Jan 1407
1862
Feb 1909
2356
Mar 2412
3008
Apr 2914
4009
Target (m)
Progress(m)
May 3417
4884
Jun 3919
5417
2018
Jul 4422
6344
Aug 4924
7407
Sep 5427
8073
Oct 5929
8763
Nov 6432
Month/Year
9434
Dec 6934
10191
Jan 7437
11063
Feb 7939
11282
Mar 8442
12110
Apr 8944
12206
including DBM 16 Apr 2019
May 9447
Jun 9949
2019
Jul 10452
Aug 10954
Sep 11457
Cumulative Progress of Target & Tunnel Length
Oct 11959
12-Nov 12208
Tolerance of Tunnel Segment Steel Formwork & Segment
Tolerance of 1400mm Segment width is 1mm and 3mm for other dimension
Formworks
Formwork anchoring with Pickon & Form-Tight
Special formworks
CONCRETE QUALITY OF RC STRUCTURES
Durability & Quality of Small Element
Importance of Curing
Curing Effect of M20 Concrete
(Cement 350kg/m3)
45.00
7 day 28 day
40.00
Comp. Strength (N/mm2)
36.44
35.00
30.00 29.04
25.63 Lab Curing
25.00 22.88 23.49
20.00 19.13
15.00
5.00
0.00
Lab Curing Site Curing Without Curing
Curing Condition Without Curing
Curing
Precast Concrete is always better than Cast in Situ
Precast Beam(SIP)
88
7d/28d Strength Ratio
(Based on Thousandth tested cubes)
90
85
79.10 80.00
80
76.35
Ratio in %age
75.70
75 71.96
70
65
60
55
50
M15 M20 M25 M40 M50
Concrete Grade
Compliance of Strength as per IS 456:2000
(Amendment no. 4 - 2013 May)
Individual Mean of the Group of 4 Non-
Specified % age of
Cube Sample Test Overlapping
Grade cube pass
Results in Consecutive Test Results in N/mm2
>30 Cube shall ≥ (fck-3) ≥ fck + 0.825 X established Std. Dev. or
(with own STD) be pass N/mm2 (fck + 3) N/mm2 whichever is greater
more than
≤30 (Table 8 M 15 or 95% of ≥ (fck-2) ≥ fck + 0.825 X Std. Dev. (established or Table 8)
Std) above total cubes N/mm2 or (fck + 4) N/mm2 whichever is greater
If above condition is not satisfied, Engineer will decide based on the non-
structural and structural concrete with reqd. improvement or core test
Compound Wall
Modern concept of Compound wall
Non- Destructive Test
Schimdt Hammer &
Pulse velocity Measurement (Ultrasound Test)
Constructed on
BS 2024 BS 2061
Special Structures
Intersection of Road,
Twisted Hoover Dam
Dallas
Tower, Dubai
Review
• Quality Assurance (QA)
– Management Tool (before construction activity)
• Quality Control
– Controlling Tool (Under construction)
• QAP
– Work Schedule (weekly, monthly, yearly) in detail
– Job Description of each human resources
– General Working Methodology for all items
– Working Methodology for major item
– Quality Assurance of Plan of Each item in Table form
– Security Management
• Reporting
– QAP
– Tolerance & Testing
– QC
– ……
• Introduction to Batching Plant
• Calibration
• Tolerance Example of BBDMP
• Formworks
• Curing
शैक्षिक स्िर बबगानुम अर्ामि ् ववद्यार्ीको जीवन बबगानुम
अर्ामि ् दे श बबगानुम हो l
कुनैपनन र्ुलुकलाई ध्वस्ि पानम कुनै आणववक अस्र वा लार्ो दरु ीसम्र् प्रहार गने
िेप्याष्रको प्रयोग गनुम आवश्यक छै न, यसका लागग त्यो र्ुलुकको शैक्षिक स्िर ध्वस्ि
पाररददए र्ारै पयामप्ि छ र ववद्यार्ीहरुलाई परीिार्ा गचि चोनम ददए प्ु छ, िाफ्रक
- त्यस्िा डाक्टरका हािबाट बबरार्ीहरु र्नेछन ्...,
- त्यस्ता इन्जिनियरबाट निर्मित भविहरु ध्वस्त हुिेछि ्...,
- त्यस्िा अर्मववद्का हािबाट पैसा हराउनेछ...,
- त्यस्िा धामर्मक अमियतिाका हािबाट र्ानविा र्नेछ...,
- त्यस्िा तयायागधशको हािबाट तयाय हराउनेछ...