FIRE FIGHTING TECHNICAL REPORT

Rev: 00

Effective Date: Oct,2023


‫مؤسسة الهدف واإلتقان للمقاوالت‬ Page 1 of 1

‫قسم أنظمة األمن والسالمة‬

CITY REGION: Dammam TR NO.:

PROJECT NAME: TBC DATE: 11-10-2023

BUILDING NO.: 15,16 and 17 UNIT NO.:

CLIENT CONTACT PERSON: Eng. Obay Saifeldin Bashir


Yes ☒ No ☐ (Please
TECHNICAL ISSUE REPORTED BY: Eng. Mohammed Saad ANY EVIDENCE/PHOTOS:
Attach)
REPORTED TO: Eng. Obay Saifeldin Bashir

DETAILED DESCRIPTION (WHO, WHAT, WHEN, WHERE)


We have sent our maintenance team to buildings no. (15,16&17) to inspect the firefighting system
Topics Covered in the inspection:
• Diesel Engine.
• Electrical pump.
• Jockey pump.
• Starting system.
• Fuel system.
• Electrical system.
• internal electronic parts in the pump control panel
• Lubricating system.
• Cooling system.

ROOT CAUSE ANALYSES / CORRECTIVE ACTION/ RECOMMENDATION


❖ ROOT CAUSE ANALYSES
• Corrosion.
• the Rust
• Incorrect Pipe Laying.
• Damaged Pipes and Joints.
• Underground leakage in the pipeline
• Wear and tear over the years for the pipes line
❖ CORRECTIVE ACTION
• Some electronic and mechanical parts were changed
❖ RECOMMENDATION:
• New exposed steel pipelines.
• New underground pipelines (HDPE pipe).

NOTE / REMARKS
FIRE FIGHTING TECHNICAL REPORT
Rev: 00

Effective Date: Oct,2023


‫مؤسسة الهدف واإلتقان للمقاوالت‬ Page 2 of 1

‫قسم أنظمة األمن والسالمة‬

NOTE: THE FIRE FIGHTING SYSTEM IS OUT OF SERVICE DUE TO UNDERGROUND LEAKAGE
REPORTED BY:
ENGINEER NAME Mohamed Saad