Project Plan
Project Plan
Day 1: Deploying to Production Date & Time: May 24 2024 Venue: House(Abodeso)
Day 2: Post Launch Monitoring Date & Time: May 26 2024 Venue: House(Abodeso)
Week 6 Development
Week 7 Testing
Day 1: Client Testing Date & Time: May 03 2024 Venue: House(Abodeso)
Day 2: Address
Date & Time: Client
May Feedback
05 2024 Venue: House(Abodeso)
Week 8 Refinement
Day 1: Implementing Updates Date & Time: June 7 2024 Venue: ACLC
Day 1: Resolving Issues Date & Time: May 10 2024 Venue: House(Abodeso)
Day 2: Adding new
Date Features
& Time: June 9 2024 Venue: ACLC
Day 2: Checking the Performance Date & Time: May 12 2024 Venue: House(Abodeso)
Week 9 Deployment
Day 1: Find and Fix the Problems Date & Time: May 17 2024 Venue: House(Abodeso)
Day 2: Test Again
Date & Time: May 19 2024 Venue: House(Abodeso) Total cost: 1200
Software Development
Week 1 Meeting and Planning
Day 1: Project Meeting Date & Time: March 15 2024 Venue: Virtual
Day 2: Establishing Project Team Date & Time: March 16 2024 Venue: Virtual
Meeting
Day 1: Client Interview Date & Time: March 22 2024 Venue: San Miguel
Day 2: Analyzing Business Needs Date & Time: March 23 2024 Venue: San Miguel
Week 3 Design
Day 1: Creating Wireframe Date & Time: April 05 2024 Venue: House (Abodeso)
Day 2: Designing Mockups Date & Time: April 07 2024
Week 4 Development
Day 1: Building User Interface Date & Time: April 12 2024 Venue: House (Abodeso)
Day 2: Implementing Responsive Design Date & Time: April 14 2024 Venue: House (Abodeso)