WORK METHOD STATEMENT

Details of Work Touchup painting all equipment electrical

Date Location
20 / 03 / 2024 All area
No Sequence of Work
1. Preparation Work
- TBM before start activity
- Make sure PPE is used in accordance with type his job And in circumstances worthy
use
- Follow instructions ordered by the SPV/Foreman
2. Preparation And checking tools , materials and work area
- Check all tool that will used , make sure in circumstances Good
- Check condition the stairs will use it , make sure already tagged and validated
- Mix all appropriate paint and thinner dosage instructions
- Check work area make sure in safe conditions _ And Ready For done
3. Activity work
- Clean the material to be painted using advance
- So Brush on the existing paint mixed using roll or paintbrush
- After work finished do housekeeping around the work area

Equipment, tools and machinery to be used:


- Forward
- Brush/Roll paint
- Stick long
- Stairs ( if required )
- Screw driver
- Ropes

The chemical to be used:

Responsible Person/Supervisor for the activity


Prepared by
Matmarfan
(Foreman)
Reviewed by
R. ADI. P
(Supervisor/Engineer)
Approved by (Area
D.O LEE
Authority)
Approved by PTW
Team