Discipline : PJT Document Type : PLN Revision: R01 Status: N/A Rev Date: 22-09-2020 Page 1 of 4
Introduction:
Hi- Development Project fabrication yard evaluation and QMS audit of Aveon offshore was carried out for two days
been 5th and 6th October 2020 as stated in the notification Ref P04-20001-AO- EAN-001 from 10AM at their Eagle
cement road, Rumuolumeni Port Harcourt River State Nigeria.
The Auditors Arrived at the Aveon yard by 9:45Am, Security Clearance and Access control checks was conducted.
The Audit Opening meeting started at 10:15Am at the conference Hall with the introduction of all members
present. The purpose and scope of the Audit was elaborated by the lead Assessor, the attendance of the opening
taken and signed by the following.
Discipline : PJT Document Type : PLN Revision: R01 Status: N/A Rev Date: 22-09-2020 Page 2 of 4
Item Classification
Activity/ Observation FVR? Ref.
Ref Critical SFI
Quality management Systems :
Discipline : PJT Document Type : PLN Revision: R01 Status: N/A Rev Date: 22-09-2020 Page 3 of 4
Environmental management:
5. Procurement:
Fabrication Mgt/project Management:
6.
Fabrication / Construction:
A 35 man office is available for client use and 100
man accommodation space for client is also
available.
7.
The fabrication shop floor has the following
fabrication machines
Rolling machine
Beveling machines
Overhead Crane
Load out:
8.
By Land
The company have an access gage area of …
By sea
The Jetty has a dimension
9. Fabrication Yard facility:
The entire perimeter of the facility is fenced
except for the jetty area with 24 hours
surveillance cameras covering around and
within the company premises.
The facility has a 5 Fabrication shop floors, one
of which is a clean shop and a paint shop
A jetty of dimension
There is also an open fabrication area of
Discipline : PJT Document Type : PLN Revision: R01 Status: N/A Rev Date: 22-09-2020 Page 4 of 4
dimension
The following fabrication machines was sighted
are as follows