Professional Documents
Culture Documents
Digitally signed by
Syed Tasneem Digitally signed by Firoz Alam
V3 Middle East
Date: 2021.09.13
10:41:19 +03'00'
Date: 2021.09.13 21:31:10
+03'00'
2021.09.14
11:57:01 +03'00'
Project : MISK Precinct 4 School Campus Phase 1
Revision No.: 00
Revision History
Page 1 of 18
Project : MISK Precinct 4 School Campus Phase 1
Table of Contents
1 Scope ............................................................................................................................................... 6
1.1 Activities .............................................................................................................................. 6
1.2 Purpose:............................................................................................................................... 6
1.3 Communication: .................................................................................................................. 6
1.4 Control Measures: ............................................................................................................... 6
2 Project Access and Egress. .............................................................................................................. 8
3 Construction Methodology ............................................................................................................. 8
3.1 Storage and handling........................................................................................................... 8
3.2 Key material required .......................................................................................................... 9
3.3 Site Preparation:.................................................................................................................. 9
3.4 Preparation:......................................................................................................................... 9
3.5 Installation: ........................................................................................................................ 10
3.6 Cleaning and Handover: .................................................................................................... 10
3.7 House Keeping ................................................................................................................... 10
4 Project Organization ..................................................................................................................... 10
4.1 Manpower ......................................................................................................................... 10
4.2 Responsibilities: ................................................................................................................. 11
5 Lighting .......................................................................................................................................... 13
6 Plant and Equipment..................................................................................................................... 14
6.1 Equipment ......................................................................................................................... 14
6.2 Tools & Equipment for Works: .......................................................................................... 14
7. Personnel Training Certification ................................................................................................... 14
7.1 Site Induction .................................................................................................................... 14
7.2. Pre-Task Briefing................................................................................................................ 15
7.3. Tool’s Box Talk ................................................................................................................... 15
8. Hazardous Materials and Substances ........................................................................................... 15
8.1 KSA Regulations ................................................................................................................. 15
8.2 Storage and Handling ........................................................................................................ 16
9. Waste Management ..................................................................................................................... 16
10. HSE Risks and Control Measures............................................................................................... 17
Page 3 of 18
Project : MISK Precinct 4 School Campus Phase 1
Page 4 of 18
Project : MISK Precinct 4 School Campus Phase 1
ABBREVIATIONS:
SAB Saudi Arabian BAYTUR
COSHH Control of Substances Hazardous to Health
MISK/Client Mohammed Bin Salman Bin Abdul Aziz Al Saud Foundation
PPE Personal protective equipment
QA/QC Quality Assurance & Quality control
QHSE Quality, Health, safety & environment
RWRR Riyadh Western Ring Road
TBT Tool Box Talk
Page 5 of 18
Project : MISK Precinct 4 School Campus Phase 1
1 Scope
This method statement describes the activities and process of Installation of HVAC duct
insulation for MiSK Precinct 4-School Project and all other miscellaneous works include
preparation, placing, and protection as per the project requirement.
The purpose of this method statement is to conduct a systematic work execution for the
Installation of HVAC duct insulation that will produce and deliver a safe execution procedure in
accordance with the approved JSA and Lifting procedure.
It is the Policy of BAYTUR to provide a safe and healthy place of employment. In areas where
scaffolding is to be erected, dismantled, altered, moved or accessed for any purpose, the
following procedure shall be utilized.
1.1 Activities
Installation of HVAC duct insulation will comprise the following activities.
Site preparation
Preparation
Installation
1.2 Purpose:
The purpose of this document is to ensure that the standards and specification of the Misk
School Campus Phase 1 Project and that of BAYTUR is effectively implemented during the
process of Installation of HVAC duct insulation. This method statement provides the necessary
support to the team with relevant information regarding the specific project requirement and
a guideline for a procedure to work safely.
1.3 Communication:
The contents of this method statement shall be explained and demonstrated to all involved
personnel based on specific task allocation. Site Engineer / Supervisor, subcontractors’
signatures shall be taken on the approved method statement as a matter of record.
Daily (at the start of each shift) the Works Supervisor and HSEO will complete a Pre-works
briefing with ALL labor based on the activities to be complete in the shift (pre-works briefing
will be signed by ALL labor to demonstrate that they have understood the activities and
associated controls. They will then complete a site walk to ensure and verify that all the controls
are in place. Both the RAM and Pre-works briefing will be located on site with the Works
Supervisor for reference and review.
Page 6 of 18
Project : MISK Precinct 4 School Campus Phase 1
Page 7 of 18
Project : MISK Precinct 4 School Campus Phase 1
o Riggers / slingers when working at height (back of vehicles, high loads will wear safety
harness and will be clipped on to Yoyo attached to the secondary hook on the crane.
The main exit from the project sites shall remain the same gates as a main security check point
with security management, traffic management and HSE operatives
3 Construction Methodology
Page 8 of 18
Project : MISK Precinct 4 School Campus Phase 1
All duct insulation to be external unless otherwise noted and in accordance with
3.4 Preparation:
Prior to the commencement of any construction activities, areas and access will be
inspected to confirm that they are in suitable condition for construction work to commence.
Ensure that the all relevant IFC drawing shall be latest approved for installation.
Ensure that the civil inspection clearances have been completed prior to proceed the
commenced the works.
Ensure that the area shall be relatively clean, free of dust and contaminants (moisture, oil,
etc.).
Insulation shall be clean and dry when installed and during application of any finish.
Space ambient temperature during application of finishing of insulation shall not be less
than 12.8°C unless recommended otherwise by the insulation manufacturer.
Vapor barriers, sealers and adhesives shall be applied only to thoroughly dry insulation.
Page 9 of 18
Project : MISK Precinct 4 School Campus Phase 1
3.5 Installation:
Any separation of joints or cracking of the insulation due to poor workmanship shall be
made good before the job is accepted.
Vapor barriers and insulation shall be complete over the full length of surface, without
penetration for hangers, duct or seams and duct accessories.
Install insulation with smooth and even surfaces, with round shapes laid to true circular
and concentric shape, shaped to blend with fitting insulation and adjacent covering,
with full length section and tight to insulated object.
Apply insulation materials, accessories and finishes in accordance with the
manufacturers' recommendations.
All debris resulting from the supply and/ or application of the insulation shall be
Removed.
Ensure that the insulation shall be supplied and installed according to the Contract
Documents.
Finish insulation neatly at hangers, supports and other protrusions.
Ensure that where insulation passes through a fire barrier sleeve all gaps are caulked with
approved fire resistant material.
Flexible connection will be wrapped with insulation overlapped and secured to ductwork
shoes and plenums by the use of metal bands.
Ensure that all insulation works looks neat and tidy.
4 Project Organization
4.1 Manpower
SN. DESCRIPTION
1 Project director
2 Construction manager
3 Site engineer
4 HSE Manager
5 Safety officer
6 Logistics superintendent
Page 10 of 18
Project : MISK Precinct 4 School Campus Phase 1
7 Works Supervisor
8 Safety Officer
9 Operator
10 Skilled labor (carpenters ,erectors, Masons, steel fixture ,welders
Note: Above listed manpower shall be assigned as per requirements of each work during the
mobilization stage.
4.2 Responsibilities:
Page 11 of 18
Project : MISK Precinct 4 School Campus Phase 1
Make safety integral to each operation by promoting worker involvement in the work
planning and hazard identification process.
Maintain active and visible involvement using open communication with employees
regarding safety items on the project.
Review and understand contractual obligations regarding HSE.
Manage the site and interface with third parties in a manner consistent with contract
agreements and the applicable standard of reasonable care.
Verify this HSE plan is current and amended when project activities or conditions change.
Verify SAB site personnel and sub-contractor issued a current copy of HSE plan prior to
commencing field activities.
Conduct an HSE orientation for all SAB/Subcontractor team members prior to entering the
project work areas;
Verify that safety meetings are conducted and documented in the project file as needed
throughout the course of the project (e.g., as tasks or hazards change).
Verify that project health and safety forms and permits are being used as outlined in the
HSE plan.
Coordinate with the HSE personnel regarding SAB operational performance, and third-party
interfaces.
Verify appropriate personal protective equipment (PPE) use, availability, and training.
Notify human resources representative and HSE of injuries and follow up on injured
employee’s progress.
Conduct accident investigations including root cause analysis;
Maintain HSE records and documentation.
Facilitate Client or government agency inspections including accompanying inspector and
providing all necessary documentation and follow-up.
Page 12 of 18
Project : MISK Precinct 4 School Campus Phase 1
Deliver field HSE training as needed based on project-specific hazards and activities.
Ensure that programs are effectively functioning to prevent and control hazards on the
project.
4.2.9 Supervisor
Following the instruction given by site engineer to assure site work organization for Labors,
tools, materials and equipment accurately to achieve mobilization work.
4.2.10 Operators
• Operate equipment safely and effectively for work activities.
• Ensure that equipment is maintained in good and safe working condition.
• Perform regular equipment maintenance to ensure work continuity with high quality.
5 Lighting
Adequate lighting shall be proceeded with mobile tower lights in term of additional hour’s
requirements. Further refer to project needs if agreed for additional hours work or night
shift, lighting arrangements shall be arranged accordingly.
Page 13 of 18
Project : MISK Precinct 4 School Campus Phase 1
6.1 Equipment
All equipment, plants, machineries, and lifting gears shall be fully serviceable, tested, checked,
and certified by third party. All personal shall be fully trained, qualified and competent to carry
out their allotted tasks. All cranes and any appropriate lifting gears shall be assemble/rigged
in accordance with manufacturers’ recommendations and procedures.
All crane lift operations shall be provided with a crane lift plan prepared by a competent person
before commencing of lift and shall be communicated to all parties involved in the lift
operation.
Generator for electricity shall be provided with drip tray to control any spillage. Upon arrival SAB
safety officer shall conduct inspection for each equipment and document all the inspections
for records. Each equipment shall be arranged with complete file for all certifications. After
approval the equipment shall be allowed to site for work. Following remain outlined to focus:
The capacity / size of the tools and equipment will be judged in accordance with site
conditions, requirements, and availability at the time of execution.
Fuel shall be provided by mobile fuel tanker on daily basis for the equipment on site.
SAB shall rely on Mini-Tankers for on-site refueling.
The refueling and maintenance will be carried out in the designated location.
SN DESCRIPTION
1 Forklift
2 Floor crane
3 Tool box e.g. Hammer; screw driver; utility knife
4 Ladder
5 Drilling machines
6 Chain block
7 Scaffolding
8 Measuring Tapes
9 Water Level / Spirit Level
Note: Above listed equipment shall be assigned as per requirements of each work during the
mobilization stage
Page 14 of 18
Project : MISK Precinct 4 School Campus Phase 1
required for all employees who may be affected by any operations identified and within their
scope of works.
All new starters working with on this project will receive the company HSE induction after
commencing employment.
A member of the Environment, Safety and Health Department will carry out this induction.
Page 15 of 18
Project : MISK Precinct 4 School Campus Phase 1
SAB shall ensure that their equipment and activities are in full legal compliance with the limits
set out in the standards. Further refer to SAB HSE Plan
9. Waste Management
SAB shall pay particular attention to waste management and actively pursue and demonstrate
waste reduction, reuse and recycling. The following is a list of the different categories of
materials that will be generated during the project:
Recyclable Materials
Waste/Refuse Materials
Reusable Materials
SAB shall ensure that:
Page 16 of 18
Project : MISK Precinct 4 School Campus Phase 1
Everyone should make every effort to keep the environment clean while performing the project
activities.
Any waste whether liquid, solid, or nonhazardous shall be collected in an approved designated
skip, transported and disposed of by an approved recycling facilities or municipality disposal
facilities.
Evidence and records shall be maintained and presented to Client as and when required.
Every one shall ensure continuous good housekeeping by continuous waste removal from site
to avoid waste accumulation.
SAB shall support environment and special emphasis shall be ascertained for good
housekeeping during the construction of the project. HOUSE KEEPING is perhaps the most
important single item influencing the safety of construction job.
Suitable waste containers shall be provided and emptied on regular basis. Waste collection
points will be designated as per the phases and locations and maintained (in proper and
suitable containers). All refusals and rubbish will be disposed outside the job
Risk Assessment:
This approved RAMS and associated documents, will be located with the Works Supervisor for reference as
required.
The works Supervisor and HSEO will complete daily Pre-Start Briefings based on the approved RAMS.
If the risk has changed and does not reflect the approved RAM.
The Works Supervisor is to discuss with HSE to review and update gain advanced approval before resubmission.
Are there any PTW / Clearances required? (if yes obtained)? Yes / No
2. Safety and Are barriers / signs needed for the work area? Yes / No
Security
Does utilities / fire systems need isolating? Yes / No
3. Safety What PPE / safety equipment is required? (Circle relevant boxes)
Equipment Safety Footwear Safety Helmet Hi-Visibility Vests Gloves
Eye Protection Hearing Protection Dust/COVID Masks
Other (state)
Page 17 of 18
Project : MISK Precinct 4 School Campus Phase 1
4. Plant and List ALL items of Plant and Equipment being used:
Equipment
Confirm that the Works Supervisor and HSEO will check daily as part of the Pre- Yes / No
Works Briefing;
Plant & Tools for suitability
All Plant has got 3rd Party inspection (e.g., by TUV)
Confirm ALL competencies are suitable for the Plant & Tools
5. Excavations Have all PTW / Clearances been obtained. Have all services been marked? Are Yes / No N/A
all shoring material on site before starting works?
6. Working at Which is the most appropriate for access (circle as required)
Height Podium Access Tower MEWP Scaffolding Rope / Harness Access
Note: Ladders are for access only. Step Ladders only where one of the above can’t be used and
supported by a specific risk assessment
If MEWP - Confirm operators are trained Yes / No N/A
If scaffolding / access tower – Confirm they will be erected by competent Yes / No N/A
persons and a scaff-tag system used?
If Rope or safety harness – confirm you have an approved safe system of work Yes / No N/A
7. Manual Can heave / awkward items be moved and stacked securely? Yes / No N/A
Handling If lifting apparatus required? Yes / No
8.Housekeeping Are materials in safe areas and stacked securely? Yes / No N/A
Are materials segregated from other people / members of the public? Yes / No N/A
9. Environment Are there facilities for the disposal of materials? Yes / No N/A
Are there any risks to local ecology / archeology? Yes / No N/A
Has consideration been given to prevention of nuisance dust/noise to Yes / No N/A
neighbors
10. Welfare / Are suitable first aid and welfare facilities available at the work-area? Yes / No
First Aid
Page 18 of 18
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 1 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 2 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 3 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 4 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 5 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 6 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 7 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 8 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 9 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Working at Falling from height that can lead to 5 3 15 1. Use suitable platform for the 2 2 4
height significant injuries or even death job.
2. All suitable ladders shall be
Fall of materials from height that inspected prior to use
can lead to injuries of personnel 3. Workers involved in working at
below height shall attend working at
Collapse of scaffolding platform height training
4. Single cleat ladders shall not
Slips, trips and fall exceed 4.5m in length between
supports (base and top landing)
5. Inclined ladders shall follow the
4 to 1 ratio rule
6. When scaffolding platform is
required, a trained and certified
scaffolder shall only be allowed
to erect, dismantle and modify
the scaffolding
7. Certified scaffold inspector
shall inspect the scaffolding
before it can be use by the
workers.
8. Scaffold erection, dismantling
and modification shall only be
performed by a competent
scaffolder. Barriers and signs
required
Page 10 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 11 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Page 12 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Fire protection Fire and explosion that can cause 4 2 8 1. Provision of suitable and 2 2 4
fatality, serious injuries or sufficient numbers of portable
fire extinguisher including fire
points (e.g. at storage area,
offices, work equipment, hot
works)
Page 13 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Construction Manager: Agreed and Accepted by: Reviewed by: Approved by:
RISK OWNER ACTION OWNER HSE MANAGER PROJECT DIRECTOR
Name: Name: Name: ALBERT CUSI Name: NASER AWAD
LIKELIHOOD
Very May
Certain (5) Likely (3) Unlikely (1)
Likely (4) happen (2)
Death (5) 25 20 15 10 5
SEVERITY
Page 14 of 15
Doc. Ref no.
MISK Precinct 4-School (Phase 1) MISK-SAB-RA-170-I06-21
Risk Assessment Rev.0
Probability can be recorded in the following Severity can be recorded in the following format: Score Priority Action
format: This represents a low
Minor injury (first aid on site) risk, although control
1
Unlikely 1 1-4 LOW
measures must be
Minor injury (treatment off site)
May happen 2 maintained
2
Likely Over 3 days injury
3
Action required soon to
3 control risks, control
Very likely 4 Major injury 4 5-10 MEDIUM measures may be
necessary in the short
Certain 5 Fatality 5 term
Action required urgently
to control risks. Further
11-25 HIGH
resources may be
needed
Page 15 of 15