Professional Documents
Culture Documents
PROPOSED REHABILITATION OF NAIROBI COMMUTER RAIL ADMINISTRATIVE OFFICES AT KENYA RAILWAYS HEADQUARTERS
HOARDING /SITE SECURITY Props Erect hoarding to the perimeter of the site and
1 WEEK create a controlled access system
SETTING UP SITE OFFICE /STORE Prefabricate Assembly of a prefabricated site office building with
d office connection to water and power
building
SITE CLEARANCE/DEMOLITIONS AND Hand tools General site clearance and demolitions
CARTING AWAY TO COLLECTION POINT
D WINDOW REPAIR AND FINISHES Hand Tools Removal of existing pelmet boxes and replacing with
binds
Including polishing and cleaning of terrazzo window
boards
E MECHANICAL AND PLUMBING WORKS 2 WEEKS Tools Installation of sanitary fittings
Sanitary Construction of timber tank platform
Fittings ]
Cement
Timber
F FLOOR FINISHES Tools Fix tiles including cementing and grouting
2 WEEKS Tiles Polishing of tiles after installation
Cement
G WALL FINISHES Tools Application of pain works with stripping of the
Paint existing paint works
H GATE HOUSE/DRIVEWAYAND FOOT Tools Painting works to the gatehouse
PATH WORKS Paints Laying down tile work
Sand Clearing driveway in preparation of bituminous
Paving Slabs primer
Leveling and compacting
I ELECTRICAL WORKS AND ICT WORKS 2 WEEKS Tools Inspection of existing Electricals
Upgrading and striping where necessary
J SITE CLEARANCE Tools Clearance of all materials that was introducd into the
site by contractor
Clearance of any debris available
Closing down of site office