You are on page 1of 2

A Approved

B Approved with Comments


C Rejected
Sn System Contractor Approval Date Approval Status
1 Chillers York A
2 Fire suppression system & FM200 Iteqan C
3 Fire alarm system Iteqan C
4 Aquarium Red Sea 11-Mar-24 A
5 UPS Setra 30-Jan-24 A
6 Access control system Setra 11-Mar-24 B
7 Roller shutter Inprogress
8 Elevator KONE
9 Transformer & switchgear Setara
10 X-ray Inprogress
11 Boilers Energy & Building
Master
12 CCTV Falcon Security
13 KLE In-House
14 Water microbiological testing
15 Water chemical testing Moteto 16-Jan-24 A
16 Animal Care SSP Animeilia
17 Sports equipment’s Inprogress
18 BMS,CCMS,LCS Siemens
19 R.O. In-House
20 Pest control Rokill
21 Waste disposal Seder
22 Crestron Intelligent control Inprogress
23 Generator Inprogress
24 Out playground like Tennis court In-House
25 Gate barrier / Road blocker Inprogress
26 Jacuzi /Sauna In-House
27 Waste Management Seder
28 Lighting control system, CMS Inprogress
29 IP Telephony/ TV, Public Address/ Inprogress
Audiovisual
30 Lifting stations In-House
31 RO Maintenance In-House
32 Intrusion systems Inprogress
33 Heat Exchangers In-House
34 Crac units, agreed only for emergecy In-House
call
35 Stone and marble polishing Inprogress
36 TH PARTY Support Service Inprogress
37 Air Duct Cleaning In-House
38 Heliport lighting system N/A
39 Specialized entertainment systems Inprogress
(cinema, snow room, etc.)
FMC Comments PO/Contract
Done
Not Done
Frequincies & SOW to be changed as per NFPA.
Not Done
Done
Done
Approved with comments. Done

Done