Summary of 2 Sites
Summary of 2 Sites
(Dated: 08-Sep-2023)
Planned Progress: 13.30%
Achieved Progress: 8.98%
Variance: -4.32%
Phase-01 - Assessment Phase
Sr. No. Description Remarks/Concerns
1-Umm Shaif
a) USSC ---- Completed (Signature Pending on 150 no's of P&IDs out of 423
completed)
RLMU of P&IDs is 100% completed for all three
1 b) USGIF --- Site visit is pending.
sites
c) WHT----- Site visit is pending.
2-ABK
a) Site visit is pending.
Umm Shaif:
a) 28 No's of OPs are deleted during Site Visit & 146 No's (count) of OPs are added
by client, hence, the additional OPs quantity is 118 No's. Still client final
2 OP&Ms Finalization is 100% completed
confirmation on OPs addition is pending.
ABK:
a) Site Visit is not conducted due to unavailability of accommodation.
1-Umm Shaif
a) USSC ---- Completed and will be shared for internal review by
b) USGIF --- Site visit is pending.
3 PDR
c) WHT----- Site visit is pending.
2-ABK---Target date of completion is 26-Sep-2023.
a) Site visit is pending.
Two Jnr. Engineers Join LHR office and 4 more Engineer will be added in US Team
by 15-Sep-2023, Mr. Hari to confirm whether his Asset is in a position that we can
1 USSC
start working on Developing of OP&Ms or not. In case of no, we can shift these
resources to other assets.
Variance:
Budgeted Manhours
Consumed Manhours %
Manhours Analysis
Variance B/W Achieved Progress Vs Consumed
2 OP&Ms Finalization
3 PDR
1 OPs Status
2 OMs Status
Summary of Lower Zakum Asset
(Dated: 14-Feb-2024)
23.83%
18.17%
-5.66%
55559.00
11.33%
6.84%
Remarks/Concerns
75% completed based on the input received from site (general attachments, general section
of PDR word file).
Sr. No.
Description
3 PDR
OPs Status
1 UAD
2 ST/Arz
3 SARB
Total
OMs Status
1 UAD
2 ST/Arz
3 SARB
Total
Summary of UAD, ST-Arz & SARB Asset
(Dated: 14-Feb-2023)
34.66%
36.66%
2.00%
19202.00
37.50%
-0.84%
Remarks/Concerns
1- UAD- (RLMU Completed 100%, however, 150 No's of P&IDs Signature are pending from Client.
2- ST/Arz (RLMU Completed 100%)
3- SARB (RLMU Completed 100%)
5 No's of OPs are deleted during Site Visit & 18 No's of OPs are added by client, hence, the additional
OPs quantity is 13 No's.
OPs Status
25 No's of OPs are submitted & 10 No's of OPs are in Progress
20 (ST) + 15 (Arz) 35 No's of OPs are submitted & 10 No's of OPs are in Progress
40 No's of OPs are submitted & 5 No's of OPs are in Progress
95 No's of OPs are submitted and 25 no's of OPs are in Progress
OMs Status
01 No of OM is in progress
Not yet started
01 No of OM is in progress and Target Submission date is 15-Feb-2024
2 no's of OMs are in Progress
Summary of Lower Zakum Asset Team
(Dated: 14-Feb-24)
Internal Training Project Consumed Total Consumed No's of OPs Average Manhours
Sr. No. Name Station Consumed Manhours Manhours Manhours Average Mandays Spent/OP
Developed/Updated Spent/OP
(14-Feb-24) (14-Feb-24) (14-Feb-24)
3 Mr. Inam Ullah LHR 872 238 1110 20 55.50 6.94 10 are under review Mr. Appani & Mr. Husnain has to expedite the s
4 Mr. Muhammad Salman Shah LHR 596 230 826 16 51.63 6.45 7 are under review Mr. Appani & Mr. Husnain has to expedite
5 Mr. Umar Hussain Shah LHR 580 252 832 27 30.81 3.85 12 are under review Mr. Appani & Mr. Husnain has to expedite
6 Mr. Mubashir Ahmed LHR 658 213 871 18 48.39 6.05 6 are under review Mr. Appani & Mr. Husnain has to expedite