Summary of US & ABK Asset

(Dated: 08-Sep-2023)
Planned Progress: 13.30%
Achieved Progress: 8.98%
Variance: -4.32%
Phase-01 - Assessment Phase
Sr. No. Description Remarks/Concerns

1-Umm Shaif
a) USSC ---- Completed (Signature Pending on 150 no's of P&IDs out of 423
completed)
RLMU of P&IDs is 100% completed for all three
1 b) USGIF --- Site visit is pending.
sites
c) WHT----- Site visit is pending.
2-ABK
a) Site visit is pending.

Umm Shaif:
a) 28 No's of OPs are deleted during Site Visit & 146 No's (count) of OPs are added
by client, hence, the additional OPs quantity is 118 No's. Still client final
2 OP&Ms Finalization is 100% completed
confirmation on OPs addition is pending.
ABK:
a) Site Visit is not conducted due to unavailability of accommodation.

1-Umm Shaif
a) USSC ---- Completed and will be shared for internal review by
b) USGIF --- Site visit is pending.
3 PDR
c) WHT----- Site visit is pending.
2-ABK---Target date of completion is 26-Sep-2023.
a) Site visit is pending.

Phase-02 - Development of OP&Ms

Two Jnr. Engineers Join LHR office and 4 more Engineer will be added in US Team
by 15-Sep-2023, Mr. Hari to confirm whether his Asset is in a position that we can
1 USSC
start working on Developing of OP&Ms or not. In case of no, we can shift these
resources to other assets.

2 USGIF Site visit is pending


3 WHT Site visit is pending
4 ABK Site visit is pending
Summary of Lower Zakum Asset
(Dated: 14-Feb-2024)
Planned Progress:

Progress Analysis Achieved Progress:

Variance:

Budgeted Manhours
Consumed Manhours %
Manhours Analysis
Variance B/W Achieved Progress Vs Consumed

Reason for -Ve Variance

Phase-01 - Assessment Phase

Sr. No. Description

1 RLMU of P&IDs (881 Completed)

2 OP&Ms Finalization

3 PDR

Phase-02 - Development of OP&Ms

1 OPs Status

2 OMs Status
Summary of Lower Zakum Asset
(Dated: 14-Feb-2024)
23.83%

18.17%

-5.66%

55559.00
11.33%

6.84%

1-Delay in site mobilization due to unavailability of Accomodation


2-Limitited availability (Two Resources Only, however as per plan, 8 Resouces were
required) of acomodation for partial time.

Remarks/Concerns

a) ZWSC ---- All P&IDs RLMU is completed.


b) WHT --- All P&IDs RLMU completed.
c) ZCSC----- All P&IDs RLMU completed.

No addition, 7 OPs are deleted.

75% completed based on the input received from site (general attachments, general section
of PDR word file).

1- 175 No's of OPs are submitted to client.


2- 20 No's of OPs are in progress.

* Additonal Resources needs to be hired for development of OPs.

1- Working on Om is not yet started.

* Additonal Resources needs to be hired for development of OMs.


Summary of UAD, ST-Arz & SARB Asset
(Dated: 14-Feb-2023)
Planned Progress:
Progress Analysis Achieved Progress:
Variance:
Budgeted Manhours
Manhours Consumed Manhours %
Analysis
Variance B/W Achieved Progress
Vs Consumed
Phase-01 - Assessment Phase

Sr. No.
Description

RLMU of P&IDs is 100%


1
completed for all three sites

OP&Ms Finalization is 100%


2
completed

3 PDR

Phase-02 - Development of OP&Ms

OPs Status
1 UAD
2 ST/Arz
3 SARB
Total
OMs Status
1 UAD
2 ST/Arz
3 SARB
Total
Summary of UAD, ST-Arz & SARB Asset
(Dated: 14-Feb-2023)
34.66%
36.66%
2.00%
19202.00
37.50%

-0.84%

Remarks/Concerns

1- UAD- (RLMU Completed 100%, however, 150 No's of P&IDs Signature are pending from Client.
2- ST/Arz (RLMU Completed 100%)
3- SARB (RLMU Completed 100%)

5 No's of OPs are deleted during Site Visit & 18 No's of OPs are added by client, hence, the additional
OPs quantity is 13 No's.

1-UAD ---- Rev. A Submitted on 04-Oct-2023, however, still feedback is awaited


2-ST/Arz--- Rev. A Submitted on 24-Oct-2023, however, still feedback is awaited on Arz part.
3-SARB----Rev. A Submitted on 30-Oct-2023, however, still feedback is awaited

OPs Status
25 No's of OPs are submitted & 10 No's of OPs are in Progress
20 (ST) + 15 (Arz) 35 No's of OPs are submitted & 10 No's of OPs are in Progress
40 No's of OPs are submitted & 5 No's of OPs are in Progress
95 No's of OPs are submitted and 25 no's of OPs are in Progress
OMs Status
01 No of OM is in progress
Not yet started
01 No of OM is in progress and Target Submission date is 15-Feb-2024
2 no's of OMs are in Progress
Summary of Lower Zakum Asset Team
(Dated: 14-Feb-24)

Internal Training Project Consumed Total Consumed No's of OPs Average Manhours
Sr. No. Name Station Consumed Manhours Manhours Manhours Average Mandays Spent/OP
Developed/Updated Spent/OP
(14-Feb-24) (14-Feb-24) (14-Feb-24)

1 Mr. Muhammad Waqas AUH 420 18 438 500 0.88 0.11

2 Mr. Chinmay Khairnar AUH 568 0 568 50 11.36 1.42

3 Mr. Jazib Yaseen LHR 768 28 796 29 27.45 3.43

4 Mr. Zeeshan Ashraf LHR 764 100 864 53 16.30 2.04

5 Mr. Muhammad Abdullah LHR 740 116 856 36 23.78 2.97

6 Mr. Shehroz Ahmed LHR 522 50 572 38 15.05 1.88

7 Mr. Muzamil Nadeem LHR 216 36 252 10 25.20 3.15

8 Mr. Muhammad Sarib LHR 124 0 124 4 31.00 3.88


Summary of UAD Team
(Dated: 14-Feb-24)

Internal Training Project Consumed Total Consumed


Sr. No. Name Station No's of OPs Average Manhours Average Mandays Remarks
Consumed Manhours Manhours Manhours
Developed/Updated Spent/OP Spent/OP
(14-Feb-24) (14-Feb-24) (14-Feb-24)

1 Mr. Uzair Jan AUH 650 0 650 20 32.50 4.06

2 Mr. Usman Ali AUH 508 0 508 20 25.40 3.18

3 Mr. Inam Ullah LHR 872 238 1110 20 55.50 6.94 10 are under review Mr. Appani & Mr. Husnain has to expedite the s

4 Mr. Muhammad Salman Shah LHR 596 230 826 16 51.63 6.45 7 are under review Mr. Appani & Mr. Husnain has to expedite

5 Mr. Umar Hussain Shah LHR 580 252 832 27 30.81 3.85 12 are under review Mr. Appani & Mr. Husnain has to expedite

6 Mr. Mubashir Ahmed LHR 658 213 871 18 48.39 6.05 6 are under review Mr. Appani & Mr. Husnain has to expedite

Internal Training Project Consumed Total Consumed


Sr. No. Name Station No's of OMs Average Manhours Average Mandays Remarks
Consumed Manhours Manhours Manhours
Developed/Updated Spent/OM Spent/OM
(14-Feb-24) (14-Feb-24) (14-Feb-24)

He is working on UAD Operating Manual and still it is under


1 Mr. Abu Bakar Sudais LHR 0 266 266 1 266.00 33.25
developemnt , already 266 Manhours are consumed