PRE HYDROSTATIC TEST CHECKLIST

PT. SUPREME ENERGY MUARA LABOH PT. USAHA ANUGRAH PRATAMA

Project Title : Wetland Pond Name of Activity : Hydro test


Area/Unit : Ex Workshop Rekind Date : Kamis, 28/3/2024

No Description of Check Yes No N/A


Check that the Fabrication Routing and Inspection Plan (ITP) has been endorsed by all
1 parties (Periksa apakah Rencana Perutean dan Inspeksi Fabrikasi (ITP) telah disetujui oleh
semua pihak)

Check the Material & Weld Tracebility Record has been endorsed by the relevant parties
2
( Periksa Catatan Ketertelusuran Material & Las telah disahkan oleh pihak terkait)

Check all millcertificates have been endorsed by the relevan parties (Periksa semua
3
sertifikat pabrik telah disahkan oleh pihak terkait)

Check that the welder has been approved/tested according to established procedures
4
(Periksa apakah tukang las telah disetujui/diuji sesuai dengan prosedur yang ditetapkan)

Check all NDE have been completed and reports reviewed and endorsed (Periksa semua
5
NDE telah diselesaikan dan laporan telah ditinjau dan disahkan)
Ensure final dimension been carried out with the reports endorsed (Pastikan dimensi akhir
6
telah dilakukan dengan laporan yang disahkan)
Check that Post Weld Heat Treatment has been completed with the report and charts
7 endorsed (Periksa apakah Perlakuan Panas Pasca Pengelasan telah selesai dengan laporan
dan grafik yang disahkan)
Check that tensile tests have been performed and all reports have been reviewed and
8 validated (Periksa apakah uji tarik telah dilakukan dan semua laporan telah diperiksa dan
disetujui)
Ensure the Hydrostatic, Test prosedure benn Approved (Pastikan Hidrostatis, Prosedur Uji
9
Disetujui)
Check all pressure gauges are working with a validity of 6 months and with the calibration
10 certificates (Periksa semua pengukur tekanan berfungsi dengan masa berlaku 6 bulan dan
dengan sertifikat kalibrasi)

11 Check the pressure recorder is working (Periksa perekam tekanan berfungsi)


Check the hydrostatic pressure has been approved (Periksa tekanan hidrostatik telah
12
disetujui)
Check the total chlorine content of the test water is below 50 ppm (Periksa kandungan
13
klorin total air uji di bawah 50 ppm)
Check that all flanges are of the correct rating (Periksa apakah semua flange memiliki nilai
14
yang benar)

15 Check that all nozzles are flanged up (Periksa apakah semua nosel terpasang ke atas)

Nuts and stud bolts examined visuallyand deemed to beundamaged and of the correct size
16 and type (Mur dan baut stud diperiksa secara visual dan dianggap tidak rusak serta ukuran
dan jenisnya benar)

Are the joint are pulled up evenly on opposing stud bolts? (Apakah sambungan ditarik ke
17
atas secara merata pada baut tiang yang berlawanan?)

All nuts pulled up to required tightnes? (Semua mur ditarik hingga kekencangan yang
18
dibutuhkan?)

No visible damage to gasket when joint completed (Tidak ada kerusakan yang terlihat
19
pada paking saat sambungan selesai)

No excessive length of stud bolt protruding through each nut (Tidak ada baut stud yang
20
terlalu panjang yang menonjol melalui setiap mur)

Visual inspection on all welds have been carried out and deemed satisfactory (Inspeksi
21
visual pada semua lasan telah dilakukan dan dianggap memuaskan)

Prepared by, Checked & Approved by,


Imploment Party
PT. Usaha Anugerah Pratama PT . Supreme Energy Muara Laboh