STRUCTURAL WORKS
Project : Nara Residences by Rockwell FOR Reference No. : 91-RLC-FOR-<contractor>-001
Package : Date Filed : January 29, 2020
29-Jan-2020
10:00AM
RECTIFICATION OF CRACKS ON SLAB SOFFIT. NOT DONE PHOTO
PODIUM LEVEL -
NEAR FIRE EXIT 2
Attachments : PHOTO
Comments :
Prepared by : Noted by :
Please submit
corrective measures on
or before :
______________________
CHRIS GECHA
RLC - PMT FOR Initiator RLC - Coordinator RLC - General Manager 30-Jan-20
PART II: CONTRACTOR'S RESPONSE
We acknowledge receipt of Non-Compliance Received:
Report and give response/feedback with respect to
the agreed date
Correct/Preventive Measures:
Inspected by : Noted by :
FOR NO 1
COMMENTS