You are on page 1of 2

REQUEST FOR A/C & VENTILATION WORK INSPECTION - 01

TYPE YOUR PROJECT NAME F - ABCD - 43FLBLDG - 21


Project : Date : Time :
Contractor : RFWI : Ref. Dwgs./Specs. ____

LOCATION :

SGN - SIGN / ACP - ACCEPT / RJT - REJECT


Mechanical Contractor Mechanical Contractor MDC ATMCI
DESCRIPTION OF WORK PIC / ENG Q. A. / Q. C. Q. A. / Q. C. Q. A. / Q. C.
SGN ACP RJT SGN ACP RJT SGN ACP RJT SGN ACP RJT
1.0 CONDENSER WATER SYSTEM, CONDENSER DRAIN & FUEL OIL SYSTEM
1.1 Pipe sleeving and riser block-outs
1.2 Pipe and fittings installation including hanger/ support
1.3 Painting
1.4 Valves and metering devices installation
1.5 Pipe hook-up to equipments
1.6 Equipment with controller setting and installation
1.7 Hydrotesting/ water treatment
1.8 Equipment testing and commissioning
1.9 Others (Please Specify) Drain Line
2.0 MECH'L VENTILATION, PRESSURIZATION, KITCHEN EXHAUST, DRYER EXHAUST & A/C SYSTEM
2.1 Duct Block-out and sleeving
2.2 Riser, plenum, main and branch duct installation
including hanger/ support (A/C Duct)
2.3 Painting
2.4 Insulation
2.5 Flexible duct installation
2.6 Diffuser, damper, grille, register & linear slot installation
2.7 Kitchen exhaust range hood installation
2.8 Machine connection (Main duct)
2.9 Blower/fan w/controller mounting & installation
2.10 Air testing and balancing
2.11 Blower/fan testing and commissioning
2.12 Others (Please Specify) Mock-up

REMARKS : (Those activities which are rejected must be reported within this section, the next activity must not be started until rectification is complete and re-inspected)

MECHANICAL CONTRACTOR: INSPECTED BY : REMARKS :


Accepted Rejected
REQUESTED BY : (Print Name) __________________________

SIGNATURE : _______________ POSITION : ________________ PROJECT SUPERVISOR

OPERATIONS:
QC
BY : (Print Name)

SIGNATURE : _______________ POSITION : ________________

ACCEPTED REJECTED
PROJECT MANAGER
APRPOVED BY : NOTED: (Print Name)
BY : (Print Name)
VP-CONSTRUCTION OPERATIONS

Note : This From shall be submitted 24 hrs. before inspection and accompanied with Shop Drawings.

Rev. 0 August 27, 2019


REQUEST FOR A/C & VENTILATION WORK INSPECTION - 02
F - ABCD - 43FLBLDG - 22
TYPE YOUR PROJECT NAME
Project : Date : Time :
Contractor : RFWI : Ref. Dwgs./Specs. _____

LOCATION :

SGN - SIGN / ACP - ACCEPT / RJT - REJECT


Mechanical Contractor Mechanical Contractor MDC ATMCI
DESCRIPTION OF WORK PIC / ENG Q. A. / Q. C. Q. A. / Q. C. Q. A. / Q. C.
SGN ACP RJT SGN ACP RJT SGN ACP RJT SGN ACP RJT
1.0 FAN / BLOWER
1.1 Roughing-Ins
1.2 Wiring-Ins
1.3 Termination / Slicing
1.4 Installation of Unit
1.5 Testing and Commissioning
2.0 CONTROL THERMOSTAT
2.1 Roughing-Ins
2.2 Wiring-Ins
2.3 Termination / Slicing
2.4 Installation of Unit
2.5 Testing and Commissioning
3.0 MOTOR CONTROL CENTERS (MCC)
3.1 Roughing-Ins
3.2 Wiring-Ins
3.3 Termination / Slicing
3.4 Installation of Unit
3.5 Testing and Commissioning

REMARKS : (Those activities which are rejected must be reported within this section, the next activity must not be started until rectification is complete and re-inspected).

MECHANICAL CONTRACTOR INSPECTED BY : REMARKS :


Accepted Rejected
REQUESTED BY : (Print Name) __________________________

SIGNATURE : _______________ POSITION : ________________ PROJECT SUPERVISOR

OPERATIONS:
QC
BY : (Print Name)

SIGNATURE : _______________ POSITION : ________________

ACCEPTED REJECTED NOTED: (Print Name)

APPROVED BY :
BY : (Print Name)
VP-CONSTRUCTION OPERATIONS

Note : This From shall be submitted 24 hrs. before inspection and accompanied with Shop Drawings.

Rev. 0 August 27, 2019

You might also like