REYROSE Construction

& Supply DEV’T CORP.


Crossing Tiniwisan, Alviola Village, Baan Km. 4, Butuan City
PCAB License No. 22934; SEC-CS201532655; ISO Certified 9001-2015
Tel No. (085) 342-3319 / Fax No.: 341-2785
Email: rrcs_dc@yahoo.com

ACCOMPLISHMENT REPORT
Project Name: Construction of Sanitary Landfill Phase I, San Isidro, Magsaysay, Misamis Oriental

Location: San Isidro, Magsaysay, Misamis Oriental


Description: Sanitary Landfill
Duration: 180 calendar days
Implementing Agency: LGU - Magsaysay

A. Project Quantities
Scope of Work % of Total Unit Quantity Remarks
C4 Pipes and Fittings, 160mm dia, HDPE SDR 28.90% cu.m 1,528.00 On-going
Laying of High-Density Polyethylene Liners, 70.60% cu.m 7.00 not yet started
Project Billboard 0.51% kgs. 78.36 Completed

B. Day To Day Work Activity


February 5 to February 29
Scope of Work 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
C4 Pipes and Fittings, 160mm dia, HDPE SDR 11
Laying of High-Density Polyethylene Liners, 1.5mm NO ACTIVITY OF SITE DUE TO UNAVAILABILITY OF LINER
Project Billboard

C. Project Work Accomplishment


Commulative
Scope of Work Actual Accomplished % Accomplished
Accomplishment
C4 Pipes and Fittings, 160mm dia, HDPE SDR 11 50% 14.4482% 14.45%
Laying of High-Density Polyethylene Liners, 1.5mm 50% 35.30% 35.30%
Project Billboard 100% 0.51% 0.51%

Accomplishment ( % ) 50.25%
Cummulative Accomplishment ( % ) 143.10%
Schedule Cummulative Accomplishment ( % ) 100.00%
Slippage : 43.10%

Issues and Concern on and at site :


unavailability of liner

Scheduled plan for the next 15 days:


Waiting for Liner

Prepared by :

Arlim G. Abejay
Project Engineer
to February 29
21 22 23 24 25 26 27 28 29 30 31 1

AVAILABILITY OF LINER

28.896% 50.00%
70.598% 50.00%
0.506% 100.00%