You are on page 1of 3

Project: :Construction of Bridge across Krishna river, Jamkhandi taluk, Bhagalkot district.

Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 7

Item
Description Unit No L B D Quantity Rate Amount
No.
1 Construction of embankment with
approved material obtained from
approved borrow areas complete with
all leads and lifts as per Technical
Specification Clause 305.
Approach ramp Cu.m. 1 Volume = 42273.0 42273
Straight Portion Cu.m. 1 Volume = 580.0 580
Total Quantity = 42853 200 8570600
2 Construction of Sub grade & earthen /
un paved shoulders satisfying the
requirements of minimum 10% CBR
value as indicated in the drawings and
specification with approved material
with all leads & lifts all complete as per
Technical Specification Clause No 305.
Subgrade layer
Approach ramp Cum 1 495.00 Area = 6.20 3069
Straight Portion Cum 2 50.00 Area = 6.20 620
Between pavement layers
Approach ramp Cum 2 495.00 Area = 1 990
Straight Portion Cum 4 50.00 Area = 1 200
Total Quantity = 4879 250 1219750
3 Providing and laying coarse graded
granular sub-base (GSB) Grading-I
complete as per MoRT&H Technical
Specification Clause 401.
Approach ramp Cum 1 495.00 Area = 1.935 958
Straight Portion Cum 2 50.00 Area = 1.935 194
Total Quantity = 1151 1400 1611855
4 Providing and laying wet mix macadam
(WMM) base complete as per MoRT&H
Technical Specification Clause 406.

Approach ramp Cum 1 495.00 Area = 1.969 975


Straight Portion Cum 2 50.00 Area = 1.969 197
Total Quantity = 1172 1530 1792479
5 Providing and laying dense bituminous
macadam (BM) course in profile
corrective course/ new pavement road
layers complete as per MoRT&H
Technical Specification Clause 507.

Approach ramp Cum 1 495.00 7.50 0.05 186


Straight Portion Cum 2 50.00 7.50 0.05 38
Total Quantity = 223 6000 1338750
6 Providing and laying Bituminous
concrete (SDBC) with VG-30 new
pavement road layers complete as per
MoRT&H Technical Specification Clause
509.
Project: :Construction of Bridge across Krishna river, Jamkhandi taluk, Bhagalkot district.

Subject: Estimation
Detailed estimate
of MajorofBridge
Approaches road for Major Bridge Bridge - 7

Item
Description Unit No L B D Quantity Rate Amount
No.
Approach ramp Cum 1 495.00 7.50 0.04 149
Straight Portion Cum 2 50.00 7.50 0.04 30
Total Quantity = 179 6800 1213800
7 Providing Grouted Revetment with
rough stone (HBG) of not less than 300
mm size grouted with 0.20 cum of CC
(1:4:8) including cost, seigniorage
charges and conveyance of materials to
site and including labour charges for
packing the stones for revetment etc.,
complete for finished item of work as
per MoRT&H specification 2504 ( 4th
revision ) for Embankment Revetment
& Toe walls (600x600mm)
a) For Embankment Revetment Cum 2 495.00 Area = 2.96 2930
b) For Toe walls along Embankment Cum 2 495.00 0.6 0.6 356
Total Quantity = 3287 1060 3484008
8 Providing and laying filter material with
Gravel underneath pitching in slopes
including cost, seigniorage charges and
conveyance of materials to site including
labour charges etc., complete for
finished item of work as per MoRT&H
Specification 2504 (4th Revision) for
Cum 2 495.00 Area = 1.48 1465
Embankment.
Total Quantity = 1465 1390 2036628
9 Construction of Earthen drain as per
drawing and Technical specifications
Cum 2 495.00 Area = 1.125 1114
Total Quantity = 1114 150 167063
10 Provision of Highmast Lightening as per
drawing and technical specifications
Cum 44 44
Total Quantity = 44 50000 2200000

Total Cost = 23634933


Backup for earthwork quantities Bridge - 7

Maximum Height 7.5 m


Earth work area at Maximum Height 165 Sq.m Audto cad
Earth work area at Minimum Height 5.8 Sq.m Audto cad
Average Area 85.4 Sq.m
Length of Ramp 495 m
Earth work quantity for Approach Ramp 42273 Cu.m
Length of Ramp of in Straight portion 100 m
Earth work quantity for Straignt Portion 580 Cu.m

Rivetment area at Maximum Height 4.96 Sq.m


Rivetment area at Mnimum Height 0.96 Sq.m
Average Area 2.96 Sq.m
Length of Ramp 495 m

Rivetment area at Maximum Height 2.48 Sq.m


Rivetment area at Mnimum Height 0.48 Sq.m
Average Area 1.48 Sq.m
Length of Ramp 495 m

You might also like