You are on page 1of 278

PROJECT DESCRIPTION

THE PROVISION OF MV AND LV ELECTRIFICATION INFRASTRUCTURE AND C


INFILLS) WITHIN THE LIMLANGA CLUSTER - LIMPOPO OVER A PERIOD OF 4

Activity type Hazard


List activity
(Routine/Non-routine)
Hazard Identification Risk Nr
nr
Indicate R or N
1. Routine activities and situations create
List specific activities to be performed taking hazards through day-to-day operations
Anything with potential to cause of harm.
into consideration the equipment to be used, and normal # Note: A hazard can pose more than one risk. #
the personnel involved in the task. work activities;
2. Non-routine activities and situations
are occasional or unplanned;

Coronavirus( covid-19 ) in the Exposure to Biological agents, virusses,


R 1 1
workplace bacteria ,fungi (Covid-19)
(a) Exposure to surfaces or people
R 2.1 infected with Covid -19 (b) Respiratory 2.1
Epidemic / Pandemic Outbreaks

Driving of vehicles

Driving on public roads, Overspeeding of


vehicles,In community, On private
R 2.2 2.2
property, Mechanical failure /
Breakdown
Respiratory Epidemic / Pandemic
R 3 3
Outbreaks

Working in the field


3.1 Insects 3.1
Working in the field

3.2 Bees 3.2

3.3 Snakes 3.3


3.4 Wet or slippery or uneven surfaces 3.4

4.1 Collapse of excavation or trench 4.1

4.2 Dust 4.2

Excavations by Hands - digging


R
of holes, trenches

4.3 Awkward positioning 4.3

4.4 Defective Hand tools 4.4

Vibration 5.1
5.1
5.2 Noise 5.2

5.3 Fumes 5.3

Contact with underground Electrical


5.4 5.4
cables

Excavations using jack


hammers ,Pneumatic and
hydraulic machines and Drill R
Trucks - digging of holes,
5.5 Dust 5.5
trenches

5.6 Loading/Off-loading equipment/machines 5.6

Equipment failure (oil, pipes burste ,


5.7 5.7
loose fitted connections, etc)
5.8 Loose Debris ejecting from work place 5.8

6.1 Fumes 6.1

6.2 Dust 6.2

6.3 Noise 6.3


Compacting R

6.4 Vibration 6.4

6.5 Heat 6.5

7.1 Lifting heavy equipment 7.1


7.2 Loading / off- loading of the equipment 7.2

Working from man cage (Bucket) /


7.3 7.3
Working at heights

Vehicle Mounted cranes (diesel)


loading and off loading, R
equipment and planting of poles
7.4 Falling objects from man cage/bucket 7.4

7.5 Working close to live electrical apparatus 7.5

Unauthorised personnel operating lifting


7.6 7.6
equipment

7.8 Diesel fumes 7.8

8.1 Defective / broken hand tools 8.1

Using of hand tools - day to day


task e.g connect and disconnect R
customers etc.
8.2 Live electricity 8.2
Using of hand tools - day to day
task e.g connect and disconnect R
customers etc.
8.3 Working at heights 8.3

8.4 Tools falling from heights 8.4

9.1 Equipment falling from elevated position 9.1

Use of lifting machines & tackle R 9.2 Equipment under tension/strain 9.2

9.3 Defective lifting gears. 9.3

Low voltage operating/ Unauthorised personnel operating on


R 10 10
Connecting of new Customers electrical network

11.1 Working at heights 11.1

High Voltage Operating


/Upgrading of existing R
infratructure/ Transformers
Loading / off- loading of the equipment
11.2 /Transformers
11.2
High Voltage Operating
/Upgrading of existing R
infratructure/ Transformers
11.3 Electrical contact 11.3

Unauthorised personnel operating high


11.4 voltage equipment
11.4

12.1 Diesel fumes 12.1

12.2 Noise 12.2

12.3 Ergonomics / Awkward position 12.3

Planting of poles using a Vehicle


R
Mounted Crane
Planting of poles using a Vehicle
R
Mounted Crane

12.4 Working at heights 12.4

12.5 Mechanical failure of crane 12.5

12.6 Incorrect lifting tackle use 12.6

12.7 Substandard lifting methodology 12.7

Use of Ladders R 13 Working at heights 13

Tension on conductor drums and


14.1 conductors during Rolling out and 14.1
dismantling

Age and integrity of conductors and


14.2 14.2
structures

Rolling out and Stringing of


R
Conductor/ABC
14.3 Rolling out methodology 14.3
Rolling out and Stringing of
R
Conductor/ABC

14.4 Defective equipment 14.4

Environment / landscape/ Uneven


14.5 14.5
Terrain

Cable Termination R 15 Incorrect use of hack saw / stanley knife 15

16.1 Damaged Electrical cords and plugs 16.1

16.2 Noise 16.2


Operating Portable Electrical
R
Tools

16.3 Vibration 16.3


16.4 Dust 16.4

Drilling through asbestos roofs R 17 Asbestos material 17

18.1 Repetitive motion 18.1


Assemblilng, Erecting,
Dismantling of steel structures,
R
transformer, ct's, vt, line isolators
breakers

18.2 Working at heights 18.2

Physical Material Handling R 19 Inproper lifting technique 19


Incorrect stacking and storage
Stacking and Storage R 20 20

Substance abuse R 21 Performing work while intoxicated 21


Cleaning services of all area eg
Exposure to surfaces or people infected
Kitchen, eating utensils, ablution R 22 22
with Covid -19
facilities
Exposure to surfaces or people infected
Providing Security services R 23 23
with Covid -20

24.1 Fumes 24.1

24.2 Dust 24.2

Compacting R
Compacting R

24.3 Noise 24.3

24.4 Vibration 24.4

Emergency Risk N 25 Community Unrest 25

Contact with electricty,Flash


Working in Close proxity to live
R 26 overs,Mobile plant and workers , static 26
electrical apparatus
electricityt

Working in Asbestos affected


R 27 Exposure to asbestos dust 27
area

28.1 Dust 28.1

Stoning of Substations yards R


Stoning of Substations yards R
28.2 Repetitive motion 28.2

29.1 Cement Dust 29.1

Mixing of mitronite/ conductive


R
cement
29.2 Wet Concrete 29.2

28.1 Inadequate Illumination 28.1

Computer use/ office work R

Working on PC's, sitting position, use of


28.2 28.2
mouse and keyboard

Walking in and between office


R 29 Wet or slippery or uneven surfaces 29
environment
30.1 Improper microwave usage 30.1

Using of kitchen facilities R

30.2 Improper use of boiling water 30.2

31.1 Noise 31.1

Use of generators R
31.2 Heavy lifting 31.2

31.3 Petrol/ Diesel fumes 31.3


Unauthorised personnel operating lifting
32.1 32.1
equipment

32.2 Working at heights 32.2


Aerial Plarforms(Cherry Pickers,
MEWP, lifting people working on R
powerlines
33.3 Falling objects 33.3

33.4 Close proximity with live apparatus 33.4

34.1 Noise 34.1

34.2 Vibration 34.2

34.3 Saw dust 34.3

Chain Saw / pruners , Brush


cutters( petrol ) - Bush clearing R
and cutting away branches.
34.4 Fumes 34.4

Chain Saw / pruners , Brush


cutters( petrol ) - Bush clearing R
and cutting away branches.

34.5 Awkward posture 34.5

34.6 Heavy lifting 34.6

35.1 Ultra violet ARC 35.1

Use of welding machines R


35.2 Welding creating heat 35.2

Use of welding machines R


35.3 Defective welding machines 35.3

35.4 Welding fumes 35.4

Damaged power leads and incorrect


35.5 35.5
earthing

37.1 Insects and snakes 37.1

Line inspections R
Line inspections R

37.2 Slippery or uneven surfaces 37.2

Cutting of trees - removal/Installation of


38.1 a structure next/under the powerline tc, 38.1
carrying long objects under powerlines

38.2 Cable theft & Tampering 38.2

38.4 Illegal and unsafe connections 38.4


Public Safety R

38.5 Low hanging conductors 38.5


Building houses under Power lines /
38.6 38.6
Structures, Objects into lines, Veld fires

Hazardous Chemicals Incorrect use, handling, of Hazardous


R 39 39.1
Substances Chemiclas

Lack of Pre-planning through not adhering to


40 all required legislation
40.1
41.1

41 No input from Engineer on load study for


work to be completed
41 No input from Engineer on load study for
work to be completed

41.2

Dismantling of rotten wooden pole R


structure: (Preplanning)
Dismantling of rotten wooden pole R
structure: (Preplanning)

42 No fall protection plan in place 42.1


43 Excavations not planned adequetely 43.1

44 All tools required for job not on site 44.1

Feeder is not earthed as per ORHVS 45.1


45 (Equipotential zone not created)

46 Lack of skills to do the work 46.1


47 Lack of equipment required to do the work 47.1

Loading / off- loading of the equipment by 48.1


48 hand

Loading and Offloading material R

Loading / off- loading of the equipment by 49.1


49 VMC

50 Defective hand tools on site 50.1


51 Lack of training on assembling structure 51.1

No or inadequete inspections of tools and 52.1


Assembling of new wooden pole R
52 equipment used on site
structure

Not wearing PPE when asembling new 53.1


53 structure

54.1

54 Use of Petrol or Battery operated drill 54.2


54 Use of Petrol or Battery operated drill

54.3

55 Incompetant operator using VMC 55.1

Incorrect Lifting /Rigging of structure (Using


56 crane to pull pole out of ground) (using vmc 56.1
to break pole out of ground)
57 More than one VMC operator using the crane 57.1
on the same task

58 Using a VMC with a Lack of/ Inadequete or 58.1


expired load test certificate
59 VMC Operator not medically fit 59.1

60 Use of incorrect lifting tackle 60.1

Dismantling of rotten wooden pole R


structure
61 No or inadequete inspections of lifting tackle 61.1
62 Falling material/ equipment or line hardware 62.1

Incorrect/ Inadequate lifting techniques


63 (Material that is being picked up not 63.1
balanced)

64 Incompetant Rigger 64.1


65 Equipment moving out of control (guiderope) 65.1

66 Conductor/ Stay Wire or Earth Wire cut 66.1


under tension (Whiplash)

67 Use of manual woodsaw to cut down wooden 67.1


pole of existing structure
68 Use of Chainsaw to cut down pole of existing 68.1
structure

69.1

69 Drilling hole with drillrig


69.2

69.3

70 Excavation by hand 70.1


71 Excavation by machine 71.1

72 Lifting equipment over the SWL of the VMC 72.1

Erecting/ Installing new wooden R


pole structure

73 Incorrect/ Inadequate lifting tackle used 73.1


74 Load Study not conducted 74.1

75 Use of home made tools (Compacting soil 75.1


with manual compactor)

76 Falling from same level 76.1

77 Structural enginnering survey not conducted 77.1


(a) Exposure to surfaces or people infected with
Driving (COVID-19) Routine 78 Covid -19 (b) Respiratory Epidemic / Pandemic 78.1
Outbreaks
Fieldwork (COVID-19) Routine 79 Respiratory Epidemic / Pandemic Outbreaks 79.1
Office work (COVID-19) R 80 Respiratory Epidemic / Pandemic Outbreaks 80.1
Exposure to surfaces or people infected with
Office work - ventilation (COVID-19) R 81 Covid -19 81.1
Cleaning services of all area eg
Exposure to surfaces or people infected with
Kitchen, eating utensils, ablution R 82 Covid -19 82.1
facilities (COVID-19)
Providing Security services (COVID- Exposure to surfaces or people infected with
19)
R 83 Covid -20 83.1

Poor road access to new estsablished


R 84 84.1
campsite

2. Site Establishment

Installation of temporary electrical


R 85 supplies to site offices/working areas/ 85.1
presence of underground cables
Lack of Facilities
R 86 86.1

R 87 Angry customer 87.1

R 88 Dogs 88.1
3.Accessing customer facilities/
premises

R 89 Exposure to customer wild animals 89.1

4. Community protests R 90 Community unrest 90.1

Using of hand held drills to drill holes in


R 91 91.1
walls of customers.

7. Pre-paid meter installation


7. Pre-paid meter installation

R 92 Using of step ladder 92.1

Vibration
R 93 93.1

Flying debris, Grinding Dust


R 94 94.1
Using of Angle grinders - Cutting of
steel, stone and bricks Awkward position
R 95 95.1

Heavy lifting manually


R 96 96.1

Falling Objects
R 97 97.1

Cutting lose ends of conductor


Using of Big Bolt cutters- cutting of
conductors/ steel bars,
R 98 98.1

Falling of tools from elevated positions


R 99 99.1

Handling of equipment by machanical


machinery
R 100 100.1
Equipment under tension/strain

R 101 101.1

Defective lifting gears.

Use of Lifting gear / Kitos/ Turfor R 102 102.1

Breaking of conductors ,slings and poles


under tension.

R 103 103.1

Ultra violet ARC


R 104 104.1

Welding creating heat


R 105 105.1

Defective welding machines


R 106 106.1
Welding fumes
R 107 107.1
Welding using welding machines
Damaged power leads and incorrect
R 108 earthing 108.1
Welding using welding machines

Arc flash
R 109 109.1

Awkward position
R 110 110.1

Working at height
Handling; Climbing and working on
ladders
R 111 111.1

Fall from height


R 112 112.1

Damaged cords & equipment


R 117 117.1

Using non-calibrated tools


R 118 118.1

Rotating and moving Machinary


R 119 119.1
Using portable electrical tools
Using portable electrical tools
Physical material handling

R 120 120.1

Pinching of fingers between Trestle and


conductor drun

R 121 121.1

Working at height

R 122 122.1

Fall from height


Stringing and Tensioning of
conductors
R 123 123.1

Walking on uneven terrain


R 124 124.1
Equipment under tension/strain

R 125 125.1

Repetative motion
R 126 126.1

Members of the public climbing electrical


structures
R 127 127.1

Theft of electricity

R 128 128.1

Illegal and unsafe connections

Illegal Operating at High voltage


structures
R 129 129.1
Theft of conductors

R 130 130.1

Contact with live overhead powerlines


Walking directly underneath or in
proximity of overhead powerlines
R 131 131.1

Members of the public climbing or cutting


trees growing into power lines.
Tree cutting R 132 132.1

Live transformers

133 133.1

Unathorised access to Eskom Vandalism


R
installations
134 134.1

Theft of copper cables


135 135.1

Litter,general construction and maintenance


waste
R 136 136.1
Hazardous waste
R 137 137.1

Oil contaminated soil and materials


R 138 138.1

Disposal of printer ink and cartidges


R 139 139.1

Storage of Waste
Herbicides and contaminated containers
R 140 140.1

Mercury containing lamps and tubes


R 141 141.1

Asbestos waste
R 142 142.1

Poisonous Substances
R 143 143.1
SCOPE SPECIFIC B
ION INFRASTRUCTURE AND CONNECTIONS (HOUSEHOLDS AND
MPOPO OVER A PERIOD OF 48 MONTHS

Prepared by:

Refer to Occup

Associated risk Risk type Cause(s) of the risk Exposed group/employees Risk Owner
Who is accountable for making sure the
Who is exposed to the hazard controls and monitors are:
A chance that injury , ill health or damage could Safety or
What causes the risk to come into effect? i.e. visitors, members of the - in place,
occur as a result of uncontrolled hazard. health
public, etc. - implemented,
- regularly reviewed for effectiveness.

(a) Droplet infections during


coughing and sneezing (human to
human transmission)
(b) Contact with contaminated
surfaces
Outbreak of respiratory epidemic / (c) Close contact with an infected
Employees, vistors,
pandemic puts the emplyees at risk Health person or contaminated object / Site Supervisor, Employees
memebers of the public
of being infected and spreading the surface
disease (d) Failure to implement
precautionary measures such as
wearing of appropriate PPE,
(e) low immunity of staff,
(f) pre-existing medicals conditions
(a) Droplet infections during
coughing and sneezing (human to
human transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
Contracting Covid 19 - Outbreak of surface All drivers, Staff
respiratory epidemic / pandemic (d) Failure to implement coming into contact
Health Managers and Employees
puts the emplyees at risk of being precautionary measures such as with drivers, Members
infected and spreading the disease wearing of appropriate PPE, of public, Contractors
(e) low immunity of staff,
(f) pre-existing medicals conditions
(g) not adhereing to social
distancing requirements
(h) Lack of hand
sanitising or hand washing

Not adhering to the speed limit,Not


paying attention, not familiar with
Involved in accident, Risk of the road,making use of cellphone,
personnel being injured by distractions, exposed to unsafe
overspeeding vehicles. Drivers behavours, congested roads,
losing control of vehicles. Damaging Pedestrians and live stock, Taxi
Employees, vistors,
/ injury to member of public, Severe Safety and Truck on the road, Civil unrest. Site Supervisor, Employees
memebers of the public
Injuries when involved in an Negligent driving,Not adhering to
Accident, Personnel are at risk of speed limit by drives, Not adhering
being bumped by a vehicle or an to life saving rules, Faillure of
Accident observation by drivers and
pedesetrians and unavailability of
pedestrian crossings
(a) Droplet infections during
coughing and sneezing (human to
human transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement
precautionary measures such as
wearing of appropriate PPE,
Outbreak of respiratory epidemic / (e) low immunity of staff, All persons
pandemic puts the emplyees at risk (f) pre-existing medicals conditions performing fieldwork,
Health (g) not adhereing to social Managers and Employees
of being infected and spreading the Members of public,
disease distancing requirements Contractors
(h) Lack of hand
sanitising or hand washing
Not conducting adequate risk
Insects bites Health Employees, vistors Site Supervisor, Employees
assessment, Insect disturbance

Employees with Anaphylaxis for


Bee stings Health Employees, vistors Site Supervisor, Employees
bee stings

Working in the field, vegetation


Snake bites Health management & hot weather Employees, vistors Site Supervisor, Employees
condition
Rainy Weather conditions,not
Slip, Trip & Fall on wet floors or
Safety paying attention & loose gravel Employees, vistors Site Supervisor, Employees
uneven surfaces
&un even surface

Lack of training, Improper Shoring,


Lack of proper supervision,
Injury Safety Employees Site Supervisor, Employees
Inadequate Risk Assessment,
Inadequate PPE used,

Lung cancer Health Improper PPE used Employees Site Supervisor, Employees

Injury Safety Confined space, body positioning Employees Site Supervisor, Employees

Improper Tool inspections,


Injury Safety Employees Site Supervisor, Employees
improper use of tools

Joints adversely affected, damaged


Health Extensive periods of work Employees Site Supervisor, Employees
blood vessels, and nerves in fingers
Exposure long periods of work,
improper PPE used, Lack of
Hearing Discomfort /NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Extensive periods of work,


Lung irritations, Health Employees Site Supervisor, Employees
improper PPE used,

Inadequate drawings, Lack of


information, incorrect interpretation
Electrocution, Burns Safety Employees Site Supervisor, Employees
of drawings, lack of training
interpreting drawings

Lung cancer Health Improper PPE used Employees Site Supervisor, Employees

Injury Safety Incorrect lifting techniques, Employees Site Supervisor, Employees

Improper inspections, Lack of skill /


Injury Safety training, / experience, Lack of Employees Site Supervisor, Employees
maintenance
Ground formation, pressure
Injury Safety Employees Site Supervisor, Employees
applied to break the ground

Inadequate PPE used, or no PPE


Air pollution - Lung irritation Health Employees Site Supervisor, Employees
use

Inadequate PPE used, or no PPE


Lung cancer Health Employees Site Supervisor, Employees
use

Exposure long periods of work,


improper PPE used, Lack of
Hearing Discomfort /NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Joints adversely affected, damaged


Health Extensive periods of work Employees Site Supervisor, Employees
blood vessels, and nerves in fingers

Burns Safety Extensive periods of work Employees Site Supervisor, Employees

Fatigue, Back, shoulder, neck, foot


Safety Improper lifting technique Employees Site Supervisor, Employees
injuries
Not services cranes, Inadequate
Injury, damage to property, Fatality Safety inspection of lifting equipment, Employees Site Supervisor, Employees
Incorrect rigging, No Supervision

No proper guard rails around


Falling from heights Safety working platforms, Not using Employees Site Supervisor, Employees
Safety harness, No FAS training

Objects falling on staff, other People standing underneath the


Safety Employees Site Supervisor, Employees
equipment bucket, Hand tools not secured,

No training of operator,
encroaching safety clearance,
Burn wounds - Electrocution Safety Employees Site Supervisor, Employees
Unauthorized personnel, Improper
supervision

No training, Unauthorised
Property/lifting equipment damage, personel, No/Improper
Safety Employees Site Supervisor, Employees
Serious injuries to employees Supervision, Not following Safe
work procedures

Improper maintenance of
Air pollution - Lung
Health equipment, Taking up unsafe Employees Site Supervisor, Employees
irritation,infections
position

Hand injuries, cuts and bruises ,


Hand injuries, cuts and bruises ,
Safety electrocution, fractures, Injuries, Employees Site Supervisor, Employees
fractures, Fatalities
Incorrect handling of tools, Not
Electrocution ,burns Safety using insullated tools, unauthorised Employees Site Supervisor, Employees
operating

Improper / lack of using PPE,


inadequite fall protection plan, Lack
Falling from heights Safety Employees Site Supervisor, Employees
of Supervision, Improper Risk
Assessment

Objects falling on staff, other Not securing tools, or not using


Safety Employees Site Supervisor, Employees
equipment tool bag

Lack of maintenance, Not conducting


routine inspections, No test
Amputation, Fractures, Back,
Safety certificates, Not using correct tools for Employees Site Supervisor, Employees
shoulder neck, Fatalities , damage the task at hand, Incorrect lifting
techniques, Unauthorised used

Incorrect Lifting methodology,


Injury, damage to property Safety incorrect safe work loads of lifting Employees Site Supervisor, Employees
tackle, lack of maintenance

Lack of maintenance, Not conducting


routine inspections, No test
Injury, damage to property Safety certificates, Not using correct tools for
Employees Site Supervisor, Employees
the task at hand

No training, Unauthorised
Flash overs,burns, electrocutions,
Safety personnel, No Supervision, Not Employees Site Supervisor, Employees
injury, fatalities
following Safe work procedures
No proper guard rails around
working platforms, Not using
Falling from heights Safety Safety harness, No Supervision, Employees Site Supervisor, Employees
No Fall Protection Plan,
Inadequate Risk Assessment
Incorrect Lifting methodology,
Equipment falling on staff, other
Safety incorrect safe work loads of lifting Employees Site Supervisor, Employees
equipment
tackle, lack of maintenance

Flash overs,burns, electrocutions, Lack of training, inexperienced


Safety Employees Site Supervisor, Employees
injury, fatalities worker, not wearing PPE

No training, Unauthorised personel,


Property/ equipment damage,
Safety No Supervision, Not following Safe Employees Site Supervisor, Employees
Serious injuries/fatalities work procedures

Inadequate maintenance, taking up


Air pollution - Lung irritation Health unsafe position
Employees Site Supervisor, Employees

Exposure long periods of work,


improper PPE used, Lack of
Hearing Discomfort,NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Back, shoulder neck,


Safety Prolonged exposure Employees Site Supervisor, Employees
injuries/discomfort
No proper guard rails around
working platforms, Not using
Falling from heights Safety Safety harness, No Supervision, Employees Site Supervisor, Employees
No Fall Protection Plan,
Inadequate Risk Assessment

Inadequate maintenance,No
Damage to property / injury Safety Employees Site Supervisor, Employees
routine inspections

Lack of maintenance, Not conducting


routine inspections, No test
Damage to property / injury Safety certificates, Not using correct Employees Site Supervisor, Employees
equipment for the task at hand, Lack
of training, No Supervision

Inadequate training, not following


Damage to property / injury Safety Employees Site Supervisor, Employees
safework procedure

Not using Approved Safety


harness, No Supervision, No Fall
Falling from heights Safety Employees Site Supervisor, Employees
Protection Plan, Inadequate Risk
Assessment, Lack of training

Incorrect rolling out procedure, lack


Damage to property / Injury Safety Employees Site Supervisor, Employees
of training, No Supervison

No safety testing of poles, no line


Injury Safety patrol inspections, lack of Employees Site Supervisor, Employees
maintenance
Inadequate training, lack of
supervision, inadequate or lack of
Injury Safety Employees Site Supervisor, Employees
Risk Assessment, lack of PPE, Not
following safe work procedure

Inadequate training, lack of


supervision, inadequate or lack of
Injury Safety Risk Assessment, lack of PPE, Employees Site Supervisor, Employees
Inadequate Maintennce
program,No inspections

Inadequate Risk Assessment, Lack


Slip, Trip & Falls on uneven
Safety of Supervision, Inadequate PPE, Employees Site Supervisor, Employees
surfaces
Lack of concentration

Inadequate training, lack of


supervision, inadequate or lack of
Cuts Safety Employees Site Supervisor, Employees
Risk Assessment, lack of PPE, Not
following safe work procedure

Injury / Burns / Electrocution Safety Lack of Inpection and maintenance Employees Site Supervisor, Employees

Exposure long periods of work,


improper PPE used, Lack of
Hearing Discomfort, NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Joints adversely affected, damaged Lack of medical surveilance, lack


Health Employees Site Supervisor, Employees
blood vessels, and nerves in fingers of maintenance
Inadequate PPE, Lack of Risk
Lung Cancer Health Employees Site Supervisor, Employees
Assessment, No Supervision

Exposure long periods of work,


improper PPE used, Lack of
Lung cancer, Silicosis,
Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
Mesothelioma
monitoring an testing of equipment,
Lack of maintenance

Back, shoulder neck, Prolonged exposure/ insufficient


Health Employees Site Supervisor, Employees
injuries/discomfort, pains, strains breaks

No proper guard rails around


working platforms, Not using
Safety harness, No Supervision,
Falling from heights Safety Employees Site Supervisor, Employees
No Fall Protection Plan,
Inadequate Risk Assessment,
Incorrect tools

Overexetion, Sprains and strains Safety Lack of training Employees Site Supervisor, Employees
Improper stacking and storage
Overexertion, Sprains and Strains,
procedure, Lack of training,
Stacks collapsing Safety Employees Site Supervisor, Employees
insufficient storage , Lack of
demarcation, Walkways obstructed

Injury, damage to property Safety Lack of substance abuse testing Employees Site Supervisor, Employees
(a) Droplet infections during
coughing and sneezing (human to
human transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement
precautionary measures such as
wearing of appropriate PPE,
Outbreak of respiratory epidemic / (e) low immunity of staff,
pandemic puts the emplyees at risk (f) pre-existing medicals conditions Cleaning staff, Staff
Health (g) not adhereing to social Managers , Employees
of being infected and spreading the members
disease distancing requirements
(h) Lack of hand
sanitising or hand washing
(a) Droplet infections during
coughing and sneezing (human to
human transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement
precautionary measures such as
wearing of appropriate PPE,
(e) low immunity of staff,
(f) pre-existing medicals conditions
Outbreak of respiratory epidemic / (g) not adhereing to social Security officers, Staff
pandemic puts the emplyees at risk memebers, Members Managers , Security Service
Health distancing requirements
of being infected and spreading the (h) Lack of hand of Public, Contractors, provider (owners and staff)
disease sanitising or hand washing Service providers)

Inadequate maintenance, taking up


Air pollution - Lung irritation Health Employees Site Supervisor, Employees
unsafe position

Inadequate PPE, Lack of Risk


Lung Cancer Health Employees Site Supervisor, Employees
Assessment, No Supervision
Exposure long periods of work,
improper PPE used, Lack of
Hearing Discomfort, NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Joints adversely affected, damaged Lack of medical surveilance, lack


Health Employees Site Supervisor, Employees
blood vessels, and nerves in fingers of maintenance

Unsatisfied customers (Delays in


responding to faults, re-occurance
Employees, members
Injuries, damage to property Safety of similar faults, loadshedding, Site Supervisor, Employees
of public
Illegal Connections,
Disconnections of electricity

Working without supervision,


Injury, damage to property, encroaching minimum safework
Safety Employees Site Supervisor, Employees
Electrocutions clearences, lack of barricading

Exposure long periods of work,


Lung cancer, Silicosis, improper PPE used, Lack of
Health Employees Site Supervisor, Employees
Mesothelioma Medical Surveillance, Lack of
information, monitoring an testing

Inadequate PPE, Lack of Risk


Air pollution/lung irritation Health Employees Site Supervisor, Employees
Assessment, No Supervision
Injuries and discomfort of the back, Prolonged exposure/ insufficient
Health Employees Site Supervisor, Employees
neck, shoulders breaks

eye irritation, nose / throaght and


Health Inadequate PPE, Employees Site Supervisor, Employees
upper respiratory system

Inadequate PPE, Risk


Skin irrittation, chemical burns, Health Employees Site Supervisor, Employees
Assessment

Strain and or irritation of the eyes, Insufficient light,poor workplace


Health Employees Site Supervisor, Employees
headaches layout

Bad posture, incorrect work


Lower back pain, strains Health Employees Site Supervisor, Employees
position, poor workstation layout,

Rainy Weather conditions,not


Slip, Trip & Falls Safety paying attention & loose gravel Employees Site Supervisor, Employees
&un even surface
Liquids, food or container releasing Improper handling, not focusing at
Safety Employees Site Supervisor, Employees
hot steam task at hand

Improper handling, not focusing at


Spilling boiled water, Burns Safety Employees Site Supervisor, Employees
task at hand

Exposure long periods of work,


improper PPE used, Lack of
Hearing Discomfort, NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Fatigue, Back, shoulder, neck, foot


Safety Improper lifting technique Employees Site Supervisor, Employees
injuries

Inadequate maintenance, taking up


Air pollution - Lung irritation Health Employees Site Supervisor, Employees
unsafe position
No training, Unauthorised
Property/lifting equipment damage, personel, No/Improper
Safety Employees Site Supervisor, Employees
Serious injuries to employees Supervision, Not following Safe
work procedures

No proper guard rails around


Falling from heights Safety working platforms, Not using Employees Site Supervisor, Employees
Safety harness, No FAS training

Objects falling on staff, other People standing underneath the


Safety Employees Site Supervisor, Employees
equipment bucket, Hand tools not secured,

No training of operator,
encroaching safety clearance,
Burn wounds - Electrocution Safety Employees Site Supervisor, Employees
Unauthorized personnel, Improper
supervision

Exposure long periods of work,


improper PPE used, Lack of
Hearing Discomfort, NIHL Health Medical Surveillance, Lack of Employees Site Supervisor, Employees
monitoring an testing of equipment,
Lack of maintenance

Joints adversely affected, damaged Lack of medical surveilance, lack


Health Employees Site Supervisor, Employees
blood vessels, and nerves in fingers of maintenance

Lung Cancer, respiratory disease or Inadequate PPE, Lack of Risk


Health Employees Site Supervisor, Employees
discomfort Assessment, No Supervision
Inadequate maintenance, taking up
Air pollution - Lung irritation Health Employees Site Supervisor, Employees
unsafe position

Back, shoulder neck,


Safety Prolonged exposure Employees Site Supervisor, Employees
injuries/discomfort

Fatigue, Back, shoulder, neck, foot


Safety Improper lifting technique Employees Site Supervisor, Employees
injuries

Lack of proper ventilation, not


Arc eyes Safety using PPE, Inadequate training, Employees Site Supervisor, Employees
Lack of supervision
Inadequate training, inexperienced
Burn wounds Safety welder, not wearing PPE, Employees Site Supervisor, Employees
distraction

Electrocution Safety Lack of mainenance Employees Site Supervisor, Employees

Lack of proper ventilation, not


Respiratory diseases. Health using PPE, Inadequate training, Employees Site Supervisor, Employees
Lack of supervision, lack of training

Electrical shock . Burning from hot


Safety Lack of Inpection and maintenance Employees Site Supervisor, Employees
metals and tools.

Not conducting adequate risk


Insects and snakes bites Safety assessment, Insect, snake Employees, vistors Site Supervisor, Employees
disturbance
Inadequate Risk Assessment, Lack
Slip, Trip & Falls Safety of Supervision, Inadequate PPE, Employees Site Supervisor, Employees
Lack of concentration

incompentent person cutting trees/


Electrocutions Safety remove structure/installation of a Members of the public Site Supervisor, Employees
structure under powerline

incompentent person cutting trees/


Electrocutions Safety remove structure/installation of a Members of the public Site Supervisor, Employees
structure under powerline

Flash overs,burns, electrocutions, Incompetent/ Unauthorised person


Safety Members of the public Site Supervisor, Employees
injury, fatalities working with electricity

incompentent person cutting trees/


Flash overs,burns, electrocutions,
Safety remove structure/installation of a Members of the public Site Supervisor, Employees
injury, fatalities
structure under powerline
Flash overs,burns, electrocutions,
Safety No building plans Members of the public Site Supervisor, Employees
injury, fatalities

Chemical burns, skin irritations Incorrect use, Not wearing proper


Health Employees Site Supervisor, Employees
PPE

Required legislation requirements not


Non adherence to legislation can lead
in place for example no Fall protection
to serious injuries because not all safety Safety All Site Supervisor/ Manager
plan in place thus persons are not
requirements are not adhered to
protected as per CR10
Dismantling an existing wooden
Structure that is being dismantled may
structure while rotten section where not Safety All Site Supervisor/ Manager
collapse due to it being rotten
secured before dismantling started
Wooden pole structure that is being
assembled may be to heavy to lift with Safety Misusing the VMC by overloading it All Site Supervisor/ Manager
one VMC
Employees exposed to fall risk
positions not protected this can lead to
No protection in place for employees Safety employees not being rescued in time All Site Supervisor/ Manager
that can fall from heights
or to falling as the correct protection is
not in place
Excavations done not according to Not adhering to specifications and
Safety All Site Supervisor/ Manager
standard legislation related to excavations

Doing tasks in unsafe manner due to Safety Tools required not on site All Site Supervisor/ Manager
certain tools not being on site

Employee may be electrocuted when illegal operating or feeder energised


Safety All Site Supervisor/ Manager
the feeder is backfed or energised by backfeeding from a customer

Work can commence without proper


Employee training matrix not assessed
training and employees can be injured Safety All Site Supervisor/ Manager
adequately
as a result
Employees can take shartcuts abd
injure themselves by not having all Safety Inadequate planning All Site Supervisor/ Manager
required equipment on site

Employees can overexert themselves Safety Picking up heavy equipment by hand All Site Supervisor/ Manager

VMC move out of control and hit an Safety Untrained employee using VMC All Site Supervisor/ Manager
employee

Not locking out or discarding defective


Employees can use defetive tools Safety All Site Supervisor/ Manager
tools
Can cause serious communication or
Working on a structure untrained Safety All Site Supervisor/ Manager
other issues

Employees can work with defective Regular inspections are not conducted
Safety All Site Supervisor/ Manager
equipment or tools on site on tools and equipmnet

Employees are not issued with PPE or


Employees can make contact with Safety employees are not wearing the issued All Site Supervisor/ Manager
matetrial without PPE
PPE on site

Exposure to Noise Health Not wearing hearing protection All Site Supervisor/ Manager

Exposed to vibration for long periods


Exposure to Vibration Health All Site Supervisor/ Manager
of time
Exposure to Fumes Health Standing in the vicinity of fumes All Site Supervisor/ Manager

Operator does not have correct


operator using crane in unsafe manner Safety All Site Supervisor/ Manager
training or experience in place

Pole can break and fall on team Using the crane in an unsafe manner
Safety All Site Supervisor/ Manager
members not specified by the SWP
Oprator can become disorientated and More than one designated operator
Safety All Site Supervisor/ Manager
causse communication breakdown assigned

Not taking VMC into regular inspection


VMC can fail while in operation Safety All Site Supervisor/ Manager
and load test intervals
Operating the VMC while not medically Not maintaining your medical
Safety All Site Supervisor/ Manager
fit and injuring someone or oneself certificate of fitness

Lifting tackle can fail and injure an Safety Wrong selection of lifting tackle All Site Supervisor/ Manager
employee

Defective lifting tackle used as they


Lifting tackle can fail and injure an Safety were not inspected and identified as All Site Supervisor/ Manager
employee
defective
Equipment/Material can fall on top of The employee working at heights
Safety All Site Supervisor/ Manager
employees drops the material or equipment

Unbalanced equipment when lossened


Loosened equipment falls due to
can move because of gravity and Safety All Site Supervisor/ Manager
being unbalanced
possibly hit someone

Wrong selection of lifting tackle Safety Rigger not trained All Site Supervisor/ Manager
Colliding with employees Safety No guide rope to secure equipment All Site Supervisor/ Manager

Conductor can cause whiplash when Safety Conductor cut under tension All Site Supervisor/ Manager
cut

Pole can fall by not being secured Safety Pole not secured All Site Supervisor/ Manager
Pole can fall by not being secured Safety Pole not secured All Site Supervisor/ Manager

Inhalation of dust Health Exposure to dust All Site Supervisor/ Manager

Exposure to noise Health Not wearing hearing protection All Site Supervisor/ Manager

The rotating parts catches loose clothes Wearing loose clothes or long hair
Safety All Site Supervisor/ Manager
or long hair close to rotating auger

Moving the excavated material in an


Overexertion of body Safety All Site Supervisor/ Manager
unergonomical way
Unmaintained machine used to Safety Machinery not maintained All Site Supervisor/ Manager
excavate

VMC and lifting tackle fail due to the Lifting material or equipment above
Safety All Site Supervisor/ Manager
load being to heavy VMC and Lifting tackles SWL

Lifting tackle can fail and injure an Incorrect lifting tackle identified as the
Safety All Site Supervisor/ Manager
employee rigger is not formally trained
structure/load can collapse and fall on Structural engineer is not consulted on
Safety All Site Supervisor/ Manager
employees dismantling or contruction projects

Homemade tools can fail due to it not Using homemeade tools that are of
Safety All Site Supervisor/ Manager
being rigid enough poor quality

Tripping over conductor on ground,


Equipment and material due to them Safety Poor housekeeping on site All Site Supervisor/ Manager
being in the working area

structure can collapse and fall on Structural engineer is not consulted on


Safety All Site Supervisor/ Manager
employees dismantling or contruction projects
(a) Droplet infections during coughing and
sneezing (human to human transmission)
(b) Contact with contaminated surfaces
(c) Close contact with an infected person
or contaminated object / surface
(d) Failure to implement precautionary
measures such as wearing of appropriate
PPE
(e) low immunity of staff,
(f) pre-existing medical conditions
(g) not adhereing to social distancing
Contracting Covid 19 - Outbreak of All drivers, Staff coming
requirements
respiratory epidemic / pandemic puts the into contact with drivers,
Health (h) Lack of hand sanitising or hand Managers and Employees
emplyees at risk of being infected and Members of public,
washing
spreading the disease Contractors
(a) Droplet infections during coughing
and sneezing (human to human
transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement precautionary
Outbreak of respiratory epidemic / measures such as wearing of
appropriate PPE, All persons performing
pandemic puts the emplyees at risk of Health
(e) low immunity of staff, fieldwork, Members of Managers and Employees
being infected and spreading the
(f) pre-existing medicals conditions (g) public, Contractors
disease
not adhereing to social distancing
requirements (h)
Lack of hand sanitising or hand
washing
(a) Droplet infections during coughing
and sneezing (human to human
transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
Outbreak of respiratory epidemic / All persons performing
surface
pandemic puts the emplyees at risk of office work, Cleaning
Health (d) Failure to implement precautionary Managers , Employees
being infected and spreading the staff, Visitors, Members
measures such as wearing of
disease of Public, Contractors
appropriate PPE,
(e) low immunity of staff,
(f) pre-existing medicals conditions (g)
not adhereing to social distancing
requirements (h)
Lack of hand sanitising or hand
washing
(a) Droplet infections during coughing
and sneezing (human to human
transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement precautionary
measures such as wearing of
Outbreak of respiratory epidemic / appropriate PPE, All persons performing
pandemic puts the emplyees at risk of (e) low immunity of staff, office work, Cleaning
Health (f) pre-existing medicals conditions (g) staff, Visitors, Members Managers , Employees
being infected and spreading the
disease not adhereing to social distancing of Public, Contractors
requirements (h)
Lack of hand sanitising or hand
washing
(a) Droplet infections during coughing
and sneezing (human to human
transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement precautionary
measures such as wearing of
Outbreak of respiratory epidemic / appropriate PPE,
pandemic puts the emplyees at risk of (e) low immunity of staff, Cleaning staff, Staff
Health (f) pre-existing medicals conditions (g) Managers , Employees
being infected and spreading the members
disease not adhereing to social distancing
requirements (h)
Lack of hand sanitising or hand
washing
(a) Droplet infections during coughing
and sneezing (human to human
transmission)
(b) Contact with contaminated
surfaces
(c) Close contact with an infected
person or contaminated object /
surface
(d) Failure to implement precautionary
Outbreak of respiratory epidemic / measures such as wearing of Security officers, Staff
pandemic puts the emplyees at risk of appropriate PPE, memebers, Members of Managers , Security Service provider
Health
being infected and spreading the (e) low immunity of staff, Public, Contractors, (owners and staff)
disease (f) pre-existing medicals conditions (g) Service providers)
not adhereing to social distancing
requirements (h)
Lack of hand sanitising or hand
washing

Dust and noise


Disturbance to flora/fauna
Safety injury , Property damage Employees Site Supervisor/ Manager
Damage
to historical sites

Electrical shock/ burns. Safety injury , Property damage Employees Site Supervisor/ Manager
Poor Hygiene conditions, Workers
eating in the veld or in direct Safety/
injury, ill health Employees Site Supervisor/ Manager
sunlight, Workers working from their Health
vehicles.

Actions and conditions leading to


Safety ill health Employees Site Supervisor/ Manager
assult and/or rape

Possible attachesand bites by dogs Health Ill health Employees Site Supervisor/ Manager

Possible attachesand bites by dogs Safety ill health Employees Site Supervisor/ Manager

Actions and conditions leading to


possible theft, vandalism, gun shots, Safety injury, fatality Employees Site Supervisor/ Manager
assult and rape

Injuries and fatalities Safety fatality, Multiple injuries, fractures Employees Site Supervisor/ Manager
Risk of falling Safety Injuries Employees Site Supervisor/ Manager

Hand body vibration using a jack Health Injuries cable tunnel syndrome
hammer
Employees Site Supervisor/ Manager

Lower Respiratory diseases - Eye injury Safety Eye injury


Employees Site Supervisor/ Manager

Back, shoulder neck, feet Health Multiple injury


injuries/discomfort
Employees Site Supervisor/ Manager

Machinary can slip out of hand, to Safety Can injure back, sprain, fractures, cuts
heavy for the operator, spin out of and amputation
control Employees Site Supervisor/ Manager

Objects falling on staff, other equipment Safety Possible property damage - Injury to
staff
Employees Site Supervisor/ Manager

Head, hand, arm and eye injuries Safety Injury to staff


Employees Site Supervisor/ Manager

Head injuries, Fractures, Hand, arm and Safety Possible property damage - Injury to
eye injuries, property damage staff
Employees Site Supervisor/ Manager

Incorrect lifting technic used can injure Safety Multiple injury


back, sprain muscle, or fall on limphs
Employees Site Supervisor/ Manager
Equipment failure Safety Fatalities, Head injuries, Fractures,
Hand, arm and eye injuries,
Equipment falling on people in working
area Employees Site Supervisor/ Manager

Equipment failure Safety Fatalities, Head injuries, Fractures,


Hand, arm and eye injuries,
Equipment falling on people in working
area Employees Site Supervisor/ Manager

Possible property damage. Injury to Safety Fatalities, Head injuries, Fractures,


staff Hand, arm and eye injuries,
Equipment falling on people in working
area Employees Site Supervisor/ Manager

Arc eyes. Inhaling off hazardous fumes Health Multiple injury


Employees Site Supervisor/ Manager

Burn wounds Safety Multiple injury


Employees Site Supervisor/ Manager

Electrocution Safety Possible fatalities - Lost time injury


Employees Site Supervisor/ Manager

Lower Respiratory diseases. Health Multiple injury


Employees Site Supervisor/ Manager

Electrical shock . Burning from hot Safety Multiple injury


metals and tools. Employees Site Supervisor/ Manager
Burn wounds Safety Possible fatalities - Injury to
employees
Employees Site Supervisor/ Manager

Back, shoulder neck, feet Health Multiple injuries, bruises, scrattaches


injuries/discomfort
Employees Site Supervisor/ Manager

Fatigue, Back, shoulder, neck, foot Health Fatalities, Multiple injuries, bruises,
injuries fractures
Employees Site Supervisor/ Manager

Fractures, Back, shoulder neck, feet Health Fatalities, Multiple injuries, bruises,
injuries, fractures
Employees Site Supervisor/ Manager

Electrical shocks Safety Fatality, multiple injuries


Employees Site Supervisor/ Manager

Give incorrect result Safety Injuries, damage to equipment


Employees Site Supervisor/ Manager

Damaging Equipment, Injuries Safety Fractures, bruises, loss of limbs


Employees Site Supervisor/ Manager
Equipment falling on staff, other H&S Possible property damage, Injury to
equipment staff

Employees Site Supervisor/ Manager

Hand and arm injuries Health Strains / sprains/leg/ back injuries

Employees Site Supervisor/ Manager

Fatigue, Back, shoulder, neck, foot Health Multiple injury


injuries

Employees Site Supervisor/ Manager

Fractures, Back, shoulder neck, feet Health Multiple injury


injuries,

Employees Site Supervisor/ Manager

Staff falling/tripping Health Multiple injury


Employees Site Supervisor/ Manager
Equipment failure H&S Fatalities, Head injuries, Fractures,
Hand, arm and eye injuries,
Equipment falling on people in working
area Employees Site Supervisor/ Manager

Arm and joint injuries Safety Arm and joint injuries


Employees Site Supervisor/ Manager

Contact with electricity Safety Fatality, Injury, Loss of limb, Company


reputation
Employees Site Supervisor/ Manager

Contact with electricity Safety Electrocution


Fatality /injury
Property damage
No supply /power failure Employees Site Supervisor/ Manager
Fire/explosion

Fire Safety Property damage


Electrical contact No supply /power failure
Explosion Fire/explosion
Fatality /injury
Hostage cases to Eskom employees
Violence
Financial and asset loss Employees Site Supervisor/ Manager
Contact with electricity Safety fatality and severe injuries

Employees Site Supervisor/ Manager

Contact with electricity Safety Fatality,Injury


Employees Site Supervisor/ Manager

Contact with electricity Safety Fatality,Injury


Employees Site Supervisor/ Manager

Contact with electricity Safety Electrocution


Fatality /injury
Property damage
No supply /power failure Employees Site Supervisor/ Manager
Fire/explosion
,Injury

Contact with electricity Safety fatality and severe injuries


Employees Site Supervisor/ Manager

Security personel Safety fatalities and injuries


Employees Site Supervisor/ Manager

ground-, air-, water pollution - Health Damage to people and the


environmental risk enivronment
Employees Site Supervisor/ Manager
ground-, air-, water pollution - Health Damage to people and the
environmental risk enivronment
Employees Site Supervisor/ Manager

ground-, air-, water pollution - Health Damage to people and the


environmental risk enivronment
Employees Site Supervisor/ Manager

ground-, air-, water pollution - Safety Damage to people and the


environmental risk enivronment
Employees Site Supervisor/ Manager

ground-, air-, water pollution - Health Damage to people and the


environmental risk enivronment
Employees Site Supervisor/ Manager

ground-, air-, water pollution - Health Damage to people and the


environmental risk enivronment
Employees Site Supervisor/ Manager

ground-, air-, water pollution - Health Damage to people and the


environmental risk, lung related illness. enivronment
Employees Site Supervisor/ Manager

Poisoning of the body, irritation to skin Health injuries


& eyes
Employees Site Supervisor/ Manager
SPECIFIC BASELINE RISK ASSESSMENT (BRA)

Authorised by:
Name: Mardo van Tonder

Designation: Safety officer


Mardo van Tonder
Signed: MVT

Date: 23.09.2022

Refer to Occupational Health and Safety Risk assessment procedure 32-520

What are the possible


Exposure patterns Existing Controls
consequences?

Risk Priority Rating


Risk Priority Rating
Include:
- Preventative Controls
(controls implemented to eliminate hazards or reduce the
likelihood of the risk occurring), and

Consequence
- Reactive Controls

Likelihood
The frequency and duration the (controls implemented to reduce the immediate impact of the
Consider the worse case scenario
person/group is exposed to the hazard e.g. risk occurring)
without controls?
Daily for 3 hrs.
Elimination
Substitution
Engineering controls
Administrative controls
Personal protective equipment (PPE)

(a) Continuous diseases information sharing


(a) Potential productivity loss (b) Details regarding personal protection
(b) Increased sick leave (hand sanitising, social distancing, etc
(minimum 14 days quarintine) (c) Communication and implementation of
(c) World Health Organisation (WHO) guidelines
Daily Potential Unavailability of (d) Implementation of the Department of 5 C II
Critical Staff Health guidelines
(d) Potential deaths (e) Internal Epidemic / Pandemic Plan
(direct impact on Eskom (Contigency plans)
employees or famalies) (f) Ongoing internal Comms regarding the
outbreak
(a) Potential productivity loss (a) Continuous diseases information sharing
- hositalisation, isolation (b) Details regarding personal protection
(b) Increased sick leave (PPE eg masks, hand sanitising, social
(minimum 14 days distancing, etc
quarintine) (c) Communication and implementation of
(c) Potential Unavailability World Health Organisation (WHO) guidelines
of Critical Staff (d) Implementation of the Department of
(d) Potential Health guidelines
3 times a week for 12 hours deaths (direct impact on (e) Internal Epidemic / Pandemic Plan 5 C II
Eskom employees or (Contigency plans)
famalies) (f) Ongoing internal Comms regarding the
outbreak

Staff driving vehicles to have national driver's


license. Vehicles in roadworthy condition, only
transport authorised staff in vehicle, pre-trip
Fatalities,Injuries, Property
Daily
damage
checks,and obeying of all traffic laws, 4 C II
Adherence to life saving rules. Discuss in
safety meetings,Drivecam, Mix Telematics
reports
(a) Continuous diseases information sharing
(a) Potential productivity loss
(b) Details regarding personal protection
- hositalisation, isolation
((PPE eg maskshand sanitising, social
(b) Increased sick leave
distancing, etc
(minimum 14 days
(c) Communication and implementation of
quarintine)
World Health Organisation (WHO) guidelines
8 hours per day, 5 days a week (c) Potential Unavailability
(d) Implementation of the Department of
5 C II
of Critical Staff
Health guidelines
(d) Potential
(e) Internal Epidemic / Pandemic Plan
deaths (direct impact on
(Contigency plans)
Eskom employees or
(f) Ongoing internal Comms regarding the
famalies)
outbreak
OPERATIONAL CONTROL: Individuals to be
aware of their status regarding allergies. Seek
immediate emergency care for treatment.
Treatment may include: Wash the area well
Experience burning, pain, with soap and water. Apply a cold or ice pack
When ever the task is being
itching, rediness, headache, wrapped in a cloth, or a cold, wet washcloth to 2 B IV
perfomed
rash, nausea, vomiting the site. Protect against infection. Elevate the
site if the bite occured on an arm or leg (to
help prevent swelling). PROGRAMME: SHE
talks, medical surveillance and situational
awereness.

Allergic reaction ie. pain, Individuals to be aware of their status


When ever the task is being redness. swelling, itching, regarding allergies and inform rest of group.
2 B IV
perfomed sweating, anxiety, dizziness In the case of a bee sting, make use of a first
or fainting. Possible fatality. aider.

Leave snakes alone/Snake handlers. Always


be aware of your surroundings. Stay out of tall
grass unless you wear thick leather
Shock, fever, fainting, rapid
boots.Keep hands and feet out of areas you
When ever the task is being pulse and breathing
cannot see. It is very important to try and 2 B IV
perfomed difficulties and worse case
note what the snake looked like (colour, size
fatality.
etc).... to assist Medical Services or treating
physician to establish what anti-venom to
administer
Obey barricades & sign posting, PPE to be
When ever the task is being worn, be aware of where you are stepping,
Injury 2 B IV
perfomed clean up spills immediately, Safety talks &
Risk Assesment

When ever the task is being


Injury Supervision, Trainng, PPE, Risk Assessment 2 B IV
perfomed

When ever the task is being Supervision, Trainng, PPE, Risk Assessment,
Adverse effects on lungs 2 B IV
perfomed medical surveilance

When ever the task is being Supervision, Trainng, PPE, Risk Assessment,
Pains, strains, injuries 2 B IV
perfomed medical surveilance, regular breaks

When ever the task is being


Injury Supervision, Trainng, PPE, Risk Assessment 2 B IV
perfomed

Supervision,Risk Assessment, medical


When ever the task is being Hand -arm Vibration
surveilance, regular breaks, rotation of 2 B IV
perfomed Syndrome
workers
Supervision,Risk Assessment, medical
When ever the task is being
Noice Induces Hearing Loss surveilance, regular breaks, rotation of 2 B IV
perfomed
workers

Supervision,Risk Assessment, medical


When ever the task is being Respiratory discomfort /
surveilance, regular breaks, rotation of 2 B IV
perfomed complications
workers

When ever the task is being Burns, electrocution, shock, Supervision, Trainng, PPE, Risk Assessment,
2 B IV
perfomed death medical surveilance, regular breaks

When ever the task is being PPE, Risk Assessment, medical surveilance,
Adverse effects on lungs 2 B IV
perfomed regular breaks

When ever the task is being Supervision, Trainng, PPE, Risk Assessment,
Lower back Injury,spasms 2 B IV
perfomed medical surveilance

When ever the task is being Supervision, Trainng, PPE, Risk Assessment,
Injury 2 B IV
perfomed medical surveilance
When ever the task is being Supervision, Trainng, PPE, Risk Assessment,
Injury 2 B IV
perfomed medical surveilance

When ever the task is being PPE, Risk Assessment, medical surveilance,
Adverse effects on lungs 2 B IV
perfomed regular breaks

When ever the task is being PPE, Risk Assessment, medical surveilance,
Adverse effects on lungs 2 B IV
perfomed regular breaks

Supervision,Risk Assessment, medical


When ever the task is being
Noice Induces Hearing Loss surveilance, regular breaks, rotation of 2 B IV
perfomed
workers

Supervision,Risk Assessment, medical


When ever the task is being Hand -arm Vibration
surveilance, regular breaks, rotation of 2 B IV
perfomed Syndrome(HAVS)
workers

When ever the task is being Supervision,Risk Assessment, Incident


Burns 2 B IV
perfomed records regular breaks, rotation of workers

Use additional labour to reduce chance of


back injury, use of correct lifting techniques,
make use of trolleys to transfer equipment,
When ever the task is being Fatigue, Back, shoulder,
program, treatment of minor bacomplaints, 2 B IV
perfomed neck, foot injuries
use of correct PPE (Safety shoes, gloves
etc.), observations,Supervision, Risk
Assessment, Incident records
When ever the task is being Injury, damage to property, Keep safe working space around the
2 C III
perfomed Fatality machine, Supervision, Training of staff

Load test certificate, Safe working platforms,


When ever the task is being
perfomed
Falling from heights Supervision, Training of staff, Safety 4 C II
harnesses, Medical certificates of fitness,

Proper PPE, Keep working area underneath


operator safe. Make sure safe working loads
When ever the task is being Objects falling on staff, other
of tool and equipment (conductors, slings 2 C III
perfomed equipment
ext.). Visual inspections before use. Proper
training, medical surveillance

Proper PPE, Supervision, Proper training,


When ever the task is being
perfomed
Burn wounds - Electrocution authorisation for operator, relevant certificate 5 C II
for the aerial bucket, medical surveillances

Training/authorisation. correct lifting


Property/lifting equipment equipment. Supervision, Q52 Critical Task
When ever the task is being
perfomed
damage, Serious injuries to Procedure. Critical Task Training. 4 C II
employees Observations. pre-job brief. SHE talks.
Inspection certificate

Supervision and regular breaks, dust mask,


When ever the task is being Air pollution - Lung
Proper PPE, proper training and 2 B IV
perfomed irritation,infections
authorisation, medical surveillance

When ever the task is being Hand injuries, cuts and


perfomed bruises , fractures,
Routine inspections of equipment 2 B IV
Proper PPE, Supervision, Proper training,
When ever the task is being
perfomed
Electrocution ,burns authorisation for operator, relevant certificate 4 C II
for the aerial bucket, medical surveillances

When ever the task is being Use of approved FAS systems, Training, Risk
perfomed
Falling from heights
Assessment, Supervision
4 C II

Use of approved Tool bags, Training, Risk


When ever the task is being Objects falling on staff, other
perfomed equipment
Assessment, Supervision, Keep safe working
distance underneath
2 B IV

Amputation, Fractures, Load test certificate, Regular Maintenance


When ever the task is being
perfomed
Back, shoulder neck, records,Supervision, Training of staff, 4 C II
Fatalities , damage Medical certificates of fitness for operator,

Load test certificate, Inspections,Supervision,


When ever the task is being
perfomed
Injury, damage to property Rigging and slinging training, Risk
Assessment
2 B IV

Load test certificate, Inspections,Supervision,


When ever the task is being
Injury, damage to property Rigging and slinging training, Risk 2 C III
perfomed
Assessment

Flash overs,burns,
When ever the task is being ORHVS, Risk Assessment, Supervision, Job
perfomed
electrocutions, injury,
Observations
4 C II
fatalities

When ever the task is being Use of approved FAS systems, Training, Risk
perfomed
Falling from heights
Assessment, Supervision, Fall Protection Plan
4 C II
Load test certificate, Inspections,Supervision,
When ever the task is being Equipment falling on staff,
perfomed other equipment
Rigging and slinging training, Risk 4 C II
Assessment

Flash overs,burns,
When ever the task is being ORHVS, Risk Assessment, Supervision, Job
perfomed
electrocutions, injury,
Observations
4 C II
fatalities

Property/ equipment
When ever the task is being ORHVS, Risk Assessment, Supervision, Job
perfomed
damage, Serious
Observations
4 C II
injuries/fatalities

When ever the task is being PPE, Risk Assessment, medical surveilance,
perfomed
Air pollution - Lung irritation
regular breaks
2 B IV

When ever the task is being PPE, Risk Assessment, medical surveilance,
perfomed
Hearing Discomfort,NIHL
regular breaks
2 B IV

When ever the task is being Back, shoulder neck, PPE, Risk Assessment, medical surveilance,
perfomed injuries/discomfort regular breaks
4 C II
When ever the task is being Use of approved FAS systems, Training, Risk
perfomed
Falling from heights
Assessment, Supervision, Fall Protection Plan
4 C II

When ever the task is being Maintenance records, Risk Assessment, Load
perfomed
Damage to property / injury
Test certificates
2 C III

When ever the task is being Load test certificates, Supervision, Risk
perfomed
Damage to property / injury
Assessment, Inspections
3 C II

When ever the task is being Load test certificates, Supervision, Risk
perfomed
Damage to property / injury
Assessment, Inspections, Training
3 C II

When ever the task is being Use of approved FAS systems, Training, Risk
perfomed
Falling from heights
Assessment, Supervision, Fall Protection Plan
4 C II

When ever the task is being Maintenance records, Risk Assessment,


perfomed
Damage to property / Injury
Inspections, PPE, Training
2 C III

When ever the task is being


perfomed
Injury Line Inspection reports, Safe work procedures 2 C III
Training/authorisation. Correct lifting
equipment. Supervision, Critical Task
When ever the task is being
perfomed
Injury Procedure. Critical Task Training. 2 C III
Observations. pre-job brief. SHE talks.
Inspection certificate

When ever the task is being


perfomed
Injury Tool inspections, Risk Assessemnt, 2 C III

When ever the task is being Slip, Trip & Falls on uneven
perfomed surfaces
Risk Assessment, Supervision, PPE 2 C III

When ever the task is being Training, Supervision, Risk Assessment,


perfomed
Cuts
Safework procedures
2 B IV

When ever the task is being Inspections, Maintenance records,


perfomed
Injury / Burns / Electrocution
Supervision, Risk Assessment, PPE
3 C II

PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
Hearing Discomfort, NIHL regular breaks, Occupational Hygiene 2 C III
Surveys

Joints adversely affected, PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
damaged blood vessels, and regular breaks, Occupational Hygiene 2 C III
nerves in fingers Surveys
PPE, Risk Assessment, medical surveilance,
When ever the task is being
perfomed
Lung Cancer regular breaks, Occupational Hygiene 2 C III
Surveys

PPE, Risk Assessment, medical surveilance,


When ever the task is being Lung cancer, Silicosis, regular breaks, Occupational Hygiene
perfomed Mesothelioma Surveys, Asbestos Assessment Work
5 A II
Instruction-240-87103244, Asbestos Tracker,

Back, shoulder neck,


When ever the task is being Risk Assessment, Training, Supervision,
perfomed
injuries/discomfort, pains,
regular breaks
2 B IV
strains

Use of approved FAS systems, Training, Risk


When ever the task is being
perfomed
Falling from heights Assessment, Supervision, Fall Protection 4 C II
Plan, Safe work procedures

When ever the task is being Overexetion, Sprains and Risk Assessments, Training, Supervision,
perfomed strains Safework procedures,
3 C II
Good standard of housekeeping, Sufficient
Overexertion, Sprains and
When ever the task is being storage, demarcation,Risk Assesment,
perfomed
Strains, Stacks collapsing
Supervision,
2 C III

Daily screening, medical surveillance,


Daily Injury, damage to property
Employee awareness sessions
2 B IV
(a) Continuous diseases information sharing
(a) Potential productivity loss
(b) Details regarding personal protection
- hositalisation, isolation
((PPE eg maskshand sanitising, social
(b) Increased sick leave
distancing, etc
(minimum 14 days
(c) Communication and implementation of
quarintine)
World Health Organisation (WHO) guidelines
8 hrs per day, 5 days a week (c) Potential Unavailability
(d) Implementation of the Department of
5 C II
of Critical Staff
Health guidelines
(d) Potential
(e) Internal Epidemic / Pandemic Plan
deaths (direct impact on
(Contigency plans)
Eskom employees or
(f) Ongoing internal Comms regarding the
famalies)
outbreak
(a) Continuous diseases information sharing
(a) Potential productivity loss
(b) Details regarding personal protection
- hositalisation, isolation
((PPE eg maskshand sanitising, social
(b) Increased sick leave
distancing, etc
(minimum 14 days
(c) Communication and implementation of
quarintine)
World Health Organisation (WHO) guidelines
7 days a week (c) Potential Unavailability
(d) Implementation of the Department of
5 C II
of Critical Staff
Health guidelines
(d) Potential
(e) Internal Epidemic / Pandemic Plan
deaths (direct impact on
(Contigency plans)
Eskom employees or
(f) Ongoing internal Comms regarding the
famalies)
outbreak

When ever the task is being PPE, Risk Assessment, medical surveilance,
perfomed
Air pollution - Lung irritation
regular breaks
2 B IV

PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
Lung Cancer regular breaks, Occupational Hygiene 2 C III
Surveys
PPE, Risk Assessment, medical surveilance,
When ever the task is being
perfomed
Hearing Discomfort, NIHL regular breaks, Occupational Hygiene 2 C III
Surveys

Joints adversely affected, PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
damaged blood vessels, and regular breaks, Occupational Hygiene 2 C III
nerves in fingers Surveys

When ever the task is being


perfomed
Injuries, damage to property Emergency preparedness drills 2 C III

When ever the task is being Fatalities,Injuries, Property


perfomed damage
Adherence to ORHVS 5 C II

PPE, Risk Assessment, medical surveilance,


When ever the task is being Lung cancer, Silicosis, regular breaks, Occupational Hygiene
perfomed Mesothelioma Surveys, Asbestos Assessment Work
5 A II
Instruction-240-87103244, Asbestos Tracker,

PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
Lung Cancer regular breaks, Occupational Hygiene 2 C III
Surveys
Back, shoulder neck,
When ever the task is being Risk Assessment, Training, Supervision,
perfomed
injuries/discomfort, pains,
regular breaks
2 B IV
strains

eye irritation, nose /


When ever the task is being
throaght and upper
perfomed
respiratory system

When ever the task is being Skin irrittation, chemical


perfomed burns,

Sufficient lighting levels are provided and


maintained under all operating
Daily Eye injury, damage
circumstances , OHS surveys ,medical
2 B IV
surveilance .Hygiene Surveys

Safety talks,Awareness, Correct work station


layout, Avoid long working sessions,
Daily Musculoskeletal disorders
Ergonomically designed chairs, Hygiene
2 B IV
surveys

OPERATIONAL CONTROL: All staff to obey


warning signs and be on the look out for
Bruises, cuts, lacerations, slipping and tripping hazards. PROGRAMME:
Daily
fractures, broken bones use of warning signs when floors are wet ,
2 B IV
SHE talks, apply situational awareness. Hold
on to handrails
Daily Injury, burns, First Aid Safety discussions, PPE 2 B IV

Daily Injury, burns, First Aid Safety discussions, PPE 2 B IV

PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
Hearing Discomfort, NIHL regular breaks, Occupational Hygiene 2 C III
Surveys

Use additional labour to reduce chance of


back injury, use of correct lifting techniques,
make use of trolleys to transfer equipment,
When ever the task is being Fatigue, Back, shoulder,
program, treatment of minor bacomplaints, 2 B IV
perfomed neck, foot injuries
use of correct PPE (Safety shoes, gloves
etc.), observations,Supervision, Risk
Assessment, Incident records

When ever the task is being PPE, Risk Assessment, medical surveilance,
perfomed
Air pollution - Lung irritation
regular breaks
2 B IV
Training/authorisation. correct lifting
Property/lifting equipment equipment. Supervision, Q52 Critical Task
When ever the task is being
perfomed
damage, Serious injuries to Procedure. Critical Task Training. 4 C II
employees Observations. pre-job brief. SHE talks.
Inspection certificate

Load test certificate, Safe working platforms,


When ever the task is being
perfomed
Falling from heights Supervision, Training of staff, Safety 4 C II
harnesses, Medical certificates of fitness,
Proper PPE, Keep working area underneath
operator safe. Make sure safe working loads
When ever the task is being Objects falling on staff, other
of tool and equipment (conductors, slings 2 C III
perfomed equipment
ext.). Visual inspections before use. Proper
training, medical surveillance
Proper PPE, Supervision, Proper training,
When ever the task is being
perfomed
Burn wounds - Electrocution authorisation for operator, relevant certificate 5 C II
for the aerial bucket, medical surveillances

PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
Hearing Discomfort, NIHL regular breaks, Occupational Hygiene 2 C III
Surveys

Joints adversely affected, PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
damaged blood vessels, and regular breaks, Occupational Hygiene 2 C III
nerves in fingers Surveys

PPE, Risk Assessment, medical surveilance,


When ever the task is being
perfomed
Lung Cancer regular breaks, Occupational Hygiene 2 C III
Surveys
When ever the task is being PPE, Risk Assessment, medical surveilance,
perfomed
Air pollution - Lung irritation
regular breaks
2 B IV

When ever the task is being Back, shoulder neck, PPE, Risk Assessment, medical surveilance,
perfomed injuries/discomfort regular breaks
4 C II

Use additional labour to reduce chance of


back injury, use of correct lifting techniques,
When ever the task is being Fatigue, Back, shoulder, make use of trolleys to transfer equipment,
2 B IV
perfomed neck, foot injuries program, use of correct PPE (Safety shoes,
gloves etc.), observations,Supervision, Risk
Assessment, Incident records

When ever the task is being Welding PPE, Medical Surveillance, Welding
Eye injury, damage 2 B IV
perfomed Authorisation, Welding Zones,
When ever the task is being Regular inspections and maintenance of
Injuries, 2 B IV
perfomed welding machine, cabling and clamps

Work in ventilated area. Medical surveillances


When ever the task is being
Injury / Burns / Electrocution on people that uses it regularly. Only 2 B IV
perfomed
authorised operators. Training.

When ever the task is being Regular inspections of welding machine,


Injuries 2 B IV
perfomed cabling and clamps

When ever the task is being Inspections, Maintenance records,


Injury / Burns / Electrocution 2 B IV
perfomed Supervision, Risk Assessment, PPE

OPERATIONAL CONTROL: Individuals to be


aware of their status regarding allergies. Seek
immediate emergency care for treatment.
Treatment may include: Wash the area well
Experience burning, pain,
with soap and water. Apply a cold or ice pack
When ever the task is being itching, rediness, headache,
wrapped in a cloth, or a cold, wet washcloth to 2 B IV
perfomed rash, nausea, vomiting,
the site. Protect against infection. Elevate the
shortness of breath
site if the bite occured on an arm or leg (to
help prevent swelling). PROGRAMME: SHE
talks, medical surveillance and situational
awereness.
When ever the task is being Bruises, cuts, lacerations,
perfomed fractures
Risk Assessment, Supervision, PPE 2 C III

When ever the task is being Public Safety Awareness Campaings. Lin
perfomed
Injuries, fatalities
inspections& tree cutting
5 C II

When ever the task is being Public Safety Awareness Campaings. Lin
perfomed
Injuries, fatalities
inspections& tree cutting
5 C II

When ever the task is being Public Safety Awareness Campaings. Lin
perfomed
Injuries, fatalities
inspections& tree cutting
5 C II

When ever the task is being Public Safety Awareness Campaings. Lin
perfomed
Injuries, fatalities
inspections& tree cutting
5 C II
When ever the task is being Public Safety Awareness Campaings. Lin
perfomed
Injuries, fatalities
inspections& tree cutting
5 C II

When ever the task is being Awreness training, MSDS, Risk Assessment ,
Injuries 2 B IV
perfomed PPE, Safework procedures

Ensure that all employees are conversant and


Once or Twice a week - 8hr Fined/ Jailed or both
have sufficient knowledge on OHS Act and
Regulation that they can do the activities within
2 C III
the SCOPE of the OHS Act and its Regulations
Ensure input is received from structural engineer
as well as a load study conducted before
dismantling of rotten wooden poles are performed.
Team performing the task must follow the
available process
outlined in the task manuals: 240-77090523, 240-
97759751, 39-98. VMC operator to have valid
Training certificate for the correct code of crane
being operated with eg. Code 32. Drop Zone
must be created to ensure no one is in the drop
Once or Twice a week - 8hr Fatality, Injury zone area when there is a possiblity of objects 5 C II
falling from heights. Ensure all required Tools,
equipment and material is available as per the
Safe work procedures. Ensure all relevant PPE is
on site and worn as required. Conduct toolbox talk
and ensure all on site knows exactly what the
requirements are, Structural engineer to do regular
intervals of inspections as indicated on structural
engineering survey. SWP for dismantling,
assembly and erecting of a 5 pole structure to be
developed and implemented.
Ensure input is received from structural engineer
as well as a load study conducted before
dismantling of rotten wooden poles are performed.
Team performing the task must follow the
available process
outlined in the task manuals: 240-77090523, 240-
97759751, 39-98. VMC operator to have valid
Training certificate for the correct code of crane
being operated with eg. Code 32. Drop Zone
must be created to ensure no one is in the drop
Once or Twice a week - 8hr Fatality, Injury zone area when there is a possiblity of objects 5 B II
falling from heights. Ensure all required Tools,
equipment and material is available as per the
Safe work procedures. Ensure all relevant PPE is
on site and worn as required. Conduct toolbox talk
and ensure all on site knows exactly what the
requirements are, Structural engineer to do regular
intervals of inspections as indicated on structural
engineering survey. SWP for dismantling,
assembly and erecting of a 5 pole structure to be
developed and implemented.
Ensure input is received from structural engineer
as well as a load study conducted before
dismantling of rotten wooden poles are performed.
Team performing the task must follow the
available process
outlined in the task manuals: 240-77090523, 240-
97759751, 39-98. VMC operator to have valid
Training certificate for the correct code of crane
being operated with eg. Code 32. Drop Zone
must be created to ensure no one is in the drop
Once or Twice a week - 8hr Fatality, Injury zone area when there is a possiblity of objects 5 B II
falling from heights. Ensure all required Tools,
equipment and material is available as per the
Safe work procedures. Ensure all relevant PPE is
on site and worn as required. Conduct toolbox talk
and ensure all on site knows exactly what the
requirements are, Structural engineer to do regular
intervals of inspections as indicated on structural
engineering survey. SWP for dismantling,
assembly and erecting of a 5 pole structure to be
developed and implemented.
Ensure input is received from structural engineer
as well as a load study conducted before
dismantling of rotten wooden poles are performed.
Team performing the task must follow the
available process
outlined in the task manuals: 240-77090523, 240-
97759751, 39-98. VMC operator to have valid
Training certificate for the correct code of crane
being operated with eg. Code 32. Drop Zone
must be created to ensure no one is in the drop
Once or Twice a week - 8hr Injury zone area when there is a possiblity of objects 5 C II
falling from heights. Ensure all required Tools,
equipment and material is available as per the
Safe work procedures. Ensure all relevant PPE is
on site and worn as required. Conduct toolbox talk
and ensure all on site knows exactly what the
requirements are, Structural engineer to do regular
intervals of inspections as indicated on structural
engineering survey. SWP for dismantling,
assembly and erecting of a 5 pole structure to be
developed and implemented.

Proper pre task planning before any work to


ensure all required tools, equipment and material
Once or Twice a week - 8hr Injury
is on site, do not take any shortcuts due to
5 C II
equipment, material or tools that are not on site.

Ensure that the CNC Authorised person has done


operating as per ORHVS and supply has been
Once or Twice a week - 8hr Injury
isolated as well as all earthing requirements has
5 B II
been met before the permit is signed

Ensure training matrix is assessed and reviewed


Once or Twice a week - 8hr Injury annually and any training requirements must be 5 B II
addressed with EAL
Do proper pre-task planning prior to any work that
Once or Twice a week - 8hr Injury
needs to occur
5 C II

Use adequete lifting techniques when picking up


equipment, when equipment is to heavy ask for
Once or Twice a week - 8hr Strains and Sprains
assistance from another employee or use
5 C II
machinery where required

Team performing the task must follow the


available process outlined in the task manuals:
240-77090523, 240-97759751, 39-98. VMC
operator to have valid Training certificate for the
correct code of crane being operated with eg.
Code 32. Drop Zone must be created to ensure
Once or Twice a week - 8hr Injury, Fatality no one is in the drop zone area when there is a 5 C II
possiblity of objects falling from heights. Ensure
all required Tools, equipment and material is
available as per the Safe work procedures. Ensure
all relevant PPE is on site and worn as required.
Conduct toolbox talk and ensure all on site knows
exactly what the

Ensure tools are inspected as per Eskom


Once or Twice a week - 8hr Injury procedures, discard all damaged tools that cannot 5 B II
be fixed.
Employees to be trained on Line Construction.
Team performing the task must follow the
available process outlined in the task manuals:
240-77090523, 240-97759751, 39-98. VMC
operator to have valid Training certificate for the
correct code of crane being operated with eg.
Code 32. Drop Zone must be created to ensure
Once or Twice a week - 8hr Injury, Fatality
no one is in the drop zone area when there is a
5 C II
possiblity of objects falling from heights. Ensure
all required Tools, equipment and material is
available as per the Safe work procedures. Ensure
all relevant PPE is on site and worn as required.
Conduct toolbox talk and ensure all on site knows
exactly what to do.

Ensure tools are inspected as per Eskom


Once or Twice a week - 8hr Injury procedures, discard all damaged tools that cannot 5 B II
be fixed.

Ensure employees are wearing PPE at all times,


Once or Twice a week - 8hr Injury Site Supervisors not to allow work to continue 5 B II
without relevant PPE

Wear hearing protection when exposed to noise,


Once or Twice a week - 8hr NIHL
medical surveillance
4 C II

Once or Twice a week - 8hr HAVS Use anti-vibrating gloves, medical surveillance 4 C II
Once or Twice a week - 8hr Respiratory diseases
Use breathing apparatus when exposed to fumes,
medical surveillance
2 C III

VMC operators to be trained on SWP's on tasks


as well as formal VMC training on specific code of
equipment being used. Team performing the task
must follow the available process outlined in the
task manuals: 240-77090523, 240-97759751, 39-
98. VMC operator to have valid Training
certificate for the correct code of crane being
Once or Twice a week - 8hr Injury, Fatality operated with eg. Code 32. Drop Zone must be 5 B II
created to ensure no one is in the drop zone area
when there is a possiblity of objects falling from
heights. Ensure all required Tools, equipment and
material is available as per the Safe work
procedures. Ensure all relevant PPE is on site and
worn as required. Conduct toolbox talk and ensure
all on site knows exactly what the

VMC operators to be trained on SWP's on tasks


as well as formal VMC training on specific code of
equipment being used. Team performing the task
must follow the available process outlined in the
task manuals: 240-77090523, 240-97759751, 39-
98. VMC operator to have valid Training
certificate for the correct code of crane being
Once or Twice a week - 8hr Injury, Fatality operated with eg. Code 32. Drop Zone must be 5 C II
created to ensure no one is in the drop zone area
when there is a possiblity of objects falling from
heights. Ensure all required Tools, equipment and
material is available as per the Safe work
procedures. Ensure all relevant PPE is on site and
worn as required. Conduct toolbox talk and ensure
all on site knows exactly what the
VMC operators not to be changed over and over
on a specific task, VMC operators to be trained on
SWP's on tasks as well as formal VMC training on
specific code of equipment being used. Team
performing the task must follow the available
process outlined in the task manuals: 240-
77090523, 240-97759751, 39-98. VMC operator
to have valid Training certificate for the correct
Once or Twice a week - 8hr Injury, Fatality code of crane being operated with eg. Code 32. 5 C II
Drop Zone must be created to ensure no one is in
the drop zone area when there is a possiblity of
objects falling from heights. Ensure all required
Tools, equipment and material is available as per
the Safe work procedures. Ensure all relevant
PPE is on site and worn as required. Conduct
toolbox talk and ensure all on site knows exactly
what the

Take VMC in to LME that the LMI can do 6


monthly inspections and annual load test and
Once or Twice a week - 8hr Injury, Fatality
enaure that it is being tested to 110% of its
5 B II
capacity or to manufacturers specifications
Ensure VMC operators are at all times medically fit
Once or Twice a week - 8hr Injury, Fatality and send them for new medical before old one
expires
2 B IV

Lifting tackle to be inspected as per DMR 18,


Riggers must ensure that they have adequate
Once or Twice a week - 8hr Injury, Fatality
training in place to be able to identify the correct
5 C II
lifting tackle to be used

Once or Twice a week - 8hr Injury, Fatality Lifting tackle to be inspected as per DMR 18 5 C II
Drop Zone must be created to ensure no one is in
the drop zone area when there is a possiblity of
Once or Twice a week - 8hr Injury, Fatality objects falling from heights. Employees working on 5 C II
ground level to wear PPE such as Hardhats to
protect against head injuries.

Ensure that employees are aware of the center of


Once or Twice a week - 8hr Injury, Fatality gravity and what will happen if equipment is picked 5 C II
up unbalanced

Ensure that all identified riggers are formally


Once or Twice a week - 8hr Injury, Fatality
trained
5 C II
Always use a guide rope to move equipment or
Once or Twice a week - 8hr Injury, Fatality
material securely where possible
5 C II

Do not cut any conductor or earth wire under


Once or Twice a week - 8hr Injury, Fatality
tension
5 C II

Use gloves to prevent cuts from saw blades,


Once or Twice a week - 8hr Injury, Fatality Secure pole with VMC and lifting tackle befor pole 5 C II
is cut
Use gloves to prevent cuts from saw blades,
Once or Twice a week - 8hr Injury, Fatality Secure pole with VMC and lifting tackle befor pole 5 C II
is cut

Ensure dust masks is worn when drilling holes


Once or Twice a week - 8hr Respiratory diseases
operators and assistants to adhere at all times
2 C III

Wear hearing protection when exposed to noise,


Once or Twice a week - 8hr NIHL
medical surveillance
4 C II

Once or Twice a week - 8hr Injury, Fractures, fatality Do not wera loose clothing around rotating plant 4 C II

Ensure that you take regular breaks while


Once or Twice a week - 8hr Strains and Sprains excavating material on excavate in a controlled 3 C II
manner and maintain good posture
Ensure JCB or other excavation equipment are
Once or Twice a week - 8hr Injury, Fatality inspected before use, Only use equipmnet that are 5 B II
maintained regularly

Enure that correct lifting tackle and VMC is


identified as per SWL to ensure that equipment
Once or Twice a week - 8hr Injury, Fatality
being lifted are in the SWL and VMC or lifting
5 C II
tackle can handle the load

Ensure that all riggers are formally trained on the


Once or Twice a week - 8hr Injury, Fatality selection of relevant lifting tackle to be used in 5 C II
various scenarios
Ensure that the structural engineer is consulted
Once or Twice a week - 8hr Injury, Fatality
before any load is lifted or structure dismantled
5 C II

Inspect the homemade tools before they are being


Once or Twice a week - 8hr Injury used, ensure that on job training is given on the 3 B III
use of homemade tools

Ensure good housekeeping is maintained at all


Once or Twice a week - 8hr Injury, trip and fall
times and tripping hazards are minimized
4 C II

Ensure that the structural engineer is consulted


Once or Twice a week - 8hr Injury, Fatality
before any load is lifted or structure dismantled
5 C II
(a) Potential productivity loss - (a) Continuous diseases information sharing
hositalisation, isolation (b) (b) Details regarding personal protection (PPE eg
Increased sick leave (minimum 14 masks, hand sanitising, social distancing, etc
days quarintine) (c) Communication and implementation of World Health
(c) Potential Unavailability of Organisation (WHO) guidelines
Critical Staff (d) Implementation of the Department of Health
(d) Potential deaths (direct guidelines
impact on Eskom employees or (e) Internal Epidemic / Pandemic Plan (Contigency
famalies) plans)
(f) Ongoing internal Comms regarding the outbreak

3 times a week for 12 hours 5 D I


(a) Potential productivity loss - (a) Continuous diseases information sharing
hositalisation, isolation (b) (b) Details regarding personal protection ((PPE eg
Increased sick leave (minimum maskshand sanitising, social distancing, etc
14 days quarintine) (c) Communication and implementation of World
(c) Potential Health Organisation (WHO) guidelines
Unavailability of Critical Staff (d) Implementation of the Department of Health
(d) guidelines
Potential deaths (direct impact (e) Internal Epidemic / Pandemic Plan
on Eskom employees or (Contigency plans)
famalies) (f) Ongoing internal Comms regarding the
outbreak
8 hours per day, 5 days a week 5 D I
(a) Potential productivity loss -
hositalisation, isolation (b)
Increased sick leave (minimum 14
days quarintine)
(c) Potential Unavailability of
Critical Staff
(d) Potential deaths (direct
impact on Eskom employees or
(a) Continuous diseases information sharing
famalies)
(b) Details regarding personal protection (hand
sanitising, social distancing, etc
(c) Communication and implementation of World Health
Organisation (WHO) guidelines
8 hrs per day, 5 days a week (d) Implementation of the Department of Health
5 D I
guidelines
(e) Internal Epidemic / Pandemic Plan (Contigency
plans)
(f) Ongoing internal Comms regarding the outbreak
(a) Potential productivity loss - (a) Continuous diseases information sharing
hositalisation, isolation (b) (b) Details regarding personal protection ((PPE eg
Increased sick leave (minimum 14 maskshand sanitising, social distancing, etc
days quarintine) (c) Communication and implementation of World Health
(c) Potential Unavailability of Organisation (WHO) guidelines
Critical Staff (d) Implementation of the Department of Health
(d) Potential deaths (direct guidelines
impact on Eskom employees or (e) Internal Epidemic / Pandemic Plan (Contigency
famalies) plans)
(f) Ongoing internal Comms regarding the outbreak (g)
Maintenance schedule

8 hrs per day, 5 days a week 5 D I


(a) Potential productivity loss -
hositalisation, isolation (b)
Increased sick leave (minimum 14
days quarintine)
(c) Potential Unavailability of
Critical Staff
(d) Potential deaths (direct
impact on Eskom employees or
famalies)
(a) Continuous diseases information sharing
(b) Details regarding personal protection ((PPE eg
maskshand sanitising, social distancing, etc
(c) Communication and implementation of World Health
Organisation (WHO) guidelines
8 hrs per day, 5 days a week (d) Implementation of the Department of Health
5 D I
guidelines
(e) Internal Epidemic / Pandemic Plan (Contigency
plans)
(f) Ongoing internal Comms regarding the outbreak
(a) Potential productivity loss -
hositalisation, isolation (b)
Increased sick leave (minimum 14
days quarintine)
(c) Potential Unavailability of
Critical Staff
(d) Potential deaths (direct
impact on Eskom employees or
(a) Continuous diseases information sharing
famalies)
(b) Details regarding personal protection ((PPE eg
maskshand sanitising, social distancing, etc
(c) Communication and implementation of World Health
Organisation (WHO) guidelines
7 days a week (d) Implementation of the Department of Health
5 E I
guidelines
(e) Internal Epidemic / Pandemic Plan (Contigency
plans)
(f) Ongoing internal Comms regarding the outbreak

Water suppression dust control. Identify all


indigeneous flora/fauna prior to campsite
Medical/ Occupational establishment.
1 week for the Project 3 B III
disease Risk assessment done of area for new
campsite or old graves not identified due to
condition of area.

qualified electricians,Electricans used that has


got wiring licence,Using correct equipment to
1 week for the Project Injury, Fatality perform the work. 5 D I
Using adequate material for electrification of
the site offices/ working areas, etc.
Provide facilities affecting worker morale.
1 week for the Project Injury, Fatality Short distance to facilities. 5 C II

Public Safety campaigns, Protective Servives


Daily for 8 hrs Injury, Fatality 3 C II
and armed response, SAPS

Customer forums, public awareness


Daily for 8 hrs Injury, Fatality 3 C II
campaigns

Customer forums, public awareness


Daily for 8 hrs Injury, Fatality 3 C II
campaigns

Escort by protective services, SAPS, armed


Once a month Injury, Fatality 6 C I
response

Pre Task planning, SOP, SWP, risk


Daily for 8 hrs Injury, Fatality 5 3 II
assessment
Risk assessment, PPE (Fall arrest system,
site specific fall protection plan, Drop zone,
Daily for 8 hrs Injury, Fatality 5 3
Inspect equipment regulary, Medical
surveillance
Once a week for 2 hrs Rotation of jackhammer operator, Proper lifting 3 A IV
technique and training, medical surveillances, risk
Injury, Fatality assessment, exposure limit

Once a week for 2 hrs Eye protection, Toolbox talks, risk assessments 2 C III
Injury, Fatality

Once a week for 2 hrs Regular breaks 3 B III


Injury, Fatality

Once a week for 2 hrs Leather Gloves, Overall,- Safety Boots, Keep 4 B III
working area safe, Proper handling technique and
Injury, Fatality training,

Daily for 30 min Proper PPE, Keep working area underneath 5 B II


operator safe. Proper training, medical
Injury, Fatality surveillance

Daily for 30 min Training, correct PPE, Control cable ends 5 B II


Injury, Fatality

Daily for 30 min Proper PPE, Keep working area underneath 5 B II


operator safe. Proper training, medical
Injury, Fatality surveillance.

Daily for 2 hrs Leather Gloves, Overall, Safety Boots, Keep 4 B III
working area safe, Proper lifting technique and
Injury, Fatality training, medical surveillances
Daily for 2 hrs Proper PPE, Keep safe working space around the 5 B II
operator. Keep working area underneath operator
safe. Make sure safe working loads of tool and
Injury, Fatality equipment (conductors, slings ext.). Regular
testing of equipment. Visual inspections before
use. Proper training, medical surveillance

Daily for 2 hrs Proper PPE, Keep safe working space around the 5 B II
operator. Keep working area underneath operator
safe. Make sure safe working loads of tool and
Injury, Fatality equipment (conductors, slings ext.). Regular
testing of equipment. Visual inspections before
use. Proper training, medical surveillance.

Daily for 2 hrs Proper PPE, Keep safe working space around the 5 B II
operator. Keep working area underneath operator
safe. Make sure safe working loads of tool and
Injury, Fatality equipment (conductors, slings ext.). Regular
testing of equipment. Visual inspections before
use. Proper training, medical surveillance

Daily for 2 hrs Wear welding gloves. Wear welding helmet. 5 B II


Medical surveillances on people that uses it
Medical/ Occupational disease regularly. Only authorised people. Training.
Working area to shielded off
Weekly for 1 hrs Wear welding gloves. Wear welding helmet. Wear 5 B II
Injury, Fatality welding apron. Only authorised people. Training.
Working area to shielded off
Weekly for 1 hrs Regular inspections of welding machine, cabling 5 B II
Injury, Fatality and clamps
Weekly for 1 hrs Work in ventilated area. Medical surveillances on 5 B II
Injury, Fatality people that uses it regularly. Only authorised
operators. Training.
Weekly for 1 hrs Regular inspections of welding machine, cabling 5 B II
Injury, Fatality and clamps
Weekly for 1 hrs Supervision - Proper PPE, Proper training and 5 B II
authorisation
Injury, Fatality

Daily for 4 hrs Regular breaks 3 B III


Medical

Daily for 4 hrs Regular breaks - Safety shoes 5 B II

Medical

Daily for 4 hrs Leather Gloves - Dusk Mask - Overall - Safety 5 B II


Boots - Keep working area safe - Proper lifting
Lost time injury technique and training - medical surveillances.

Daily for 1 hr Periodical Inspections & Maintenance 5 C II


Injury, Fatality

Daily for 1 hr Periodical Inspections & Maintenance, Calibration 2 B IV


certificate to be done as per the intervals required
Injury, Fatality

Daily for 1 hr Use equipment as per safe working instructions, 5 C II


Wear correct PPE
Injury, Fatality
Daily for 1 hr Keep safe working space around the machine, 2 B IV
Supervision, Training of staff

Injury, Fatality

Daily for 3 hrs Redesign the brake mechanism on the conductor 2 B IV


drum and Trestle.

Injury, Fatality

Daily for 3 hrs Inspect FAS before use,hook up to suitable 5 B II


anchor point.

Injury, Fatality

Daily for 3 hrs Leather Gloves - Overall - Safety Boots -Hardhat - 5 B II


Proper training - medical surveillances.

Injury, Fatality

Daily for 3 hrs PPE to be worn, be aware of where you are 2 B IV


stepping, Safety talks,
Injury, Fatality
Daily for 3 hrs Proper PPE, Keep safe working space around the 5 B II
operator. Keep working area underneath operator
safe. Make sure safe working loads of tool and
Injury, Fatality equipment (conductors, slings ext.). Regular
testing of equipment. Visual inspections before
use. Proper training, medical surveillance

Daily for 3 hrs Take regular breaks and share the workload. 2 B IV
Injury, Fatality

Monthly for 1 hr a) Continue with awareness and educational 5 B II


campaigns; b) T&Q to revisit the anti climbing
Injury, Fatality device procedure / tool (with signage);

Monthly for 1 hr Educational and awareness campaigns; Audits 5 B II


and Disconnections

Injury, Fatality

Monthly for 1 hr Awareness programs 5 B II


Meter audits – provide illegal connections audit
feedback & remedial
Eskom billing staff to quantify losses incurred
Termination of illegal supply /connection
Engagement with the local authorities
Injury, Fatality Engagement with Operation Khanyisa
Involvement of SAPS
Intervention of Protective Services- report on theft
incidents
Monthly for 1 hr Property damage 5 B II
Fire/explosion
Electrocution
Fatality /injury
Legal liability
Injury, Fatality Financial and asset loss
Hostage cases to Eskom employees
Violence

Daily for 30 min Educational and awareness campaigns 5 B II


Injury, Fatality

Weekly for 1 hr Educational and awareness campaigns; 5 B II


Vegetation management plan
Injury, Fatality

Weekly for 1 hr a) Educational and awareness campaigns; b) 5 B II


Signage; c) Lock-out system

Injury, Fatality

Weekly for 1 hr NO unauthorised access allowed and adequate 5 B II


supervision to be in place at all times
Injury, Fatality

Weekly for 1 hr Adequate security measures to be in place on site 5 B II


and emergency preparedness plan.
Injury, Fatality

Daily for 30 min Waste management training, Safe working 2 B IV


procedures, applicable PPE, medical surveilance
Occupational disease
Daily for 30 min Waste management training, Safe working 2 B IV
procedures, applicable PPE, medical surveilance
Occupational disease

Daily for 30 min Waste management training, Safe working 2 B IV


procedures, applicable PPE, medical surveilance
Occupational disease

Daily for 30 min Waste management training, Safe working 2 B IV


procedures, applicable PPE, medical surveilance
Occupational disease

Daily for 30 min Waste management training, Safe working 2 B IV


procedures, applicable PPE, medical surveilance
Occupational disease

Daily for 30 min Waste management training, Safe working 2 B IV


procedures, applicable PPE, medical surveilance
Occupational disease

Daily for 30 min Waste management training, Safe working 2 B IV


procedures, applicable PPE, medical surveilance
Occupational disease

Daily for 30 min Wearing PPE (Gloves & Face Mask) 2 B IV


Injury, Fatality, Occupational
disease
do van Tonder

: Safety officer

.2022

Additional Controls or Tasks Aimed at improving Existing Legal and Other


Monitoring Mechanisms Control Owner
Controls Requirements
Include:
- Preventative Controls
(controls implemented to eliminate hazards or reduce the
likelihood of the risk occurring), and
- Reactive Controls
How we know if we are succeeding. Include comments Where relevant, list the
RCE (controls implemented to reduce the immediate impact of the Person allocated the
on effectiveness. relevant legislative and or
Risk Control risk occurring) responsibility for implementing
This may include i.e. measurements, inspections, Eskom requirements that
Effectiveness the agreed controls
supervision where necessary. prescribe the control.
Elimination
Substitution
Engineering controls
Administrative controls
Personal protective equipment (PPE)

Occupational
Health and Safety
Act 85 of 1993,
(a) Completed an exposure screening
section 8,14,
questionnaire (b) Conducts screening
Construction
through body temperature screening
Regulation 9,
Directive covid-19 Occupational Health and (c) In the event that a
Regulation for
Safety Measures in workplaces: COVID- case suspected there will be referrals as
Hazourdous
19(C19 OHS), 2020, Protective measures to per Department of Health Standard
Biological
ME be taken during covid-19 Work instruction 240- Operating Procedure (d) Utilisation Site Supervisor
Agents,6, 10,11,
154263529 , National Disatser Management of the current Eskom staff such as
240-77460915,
Act, Eskom engagement toolkit for Covid-19, (Security, Occupational Health and
32-
Not using airconditioning systems Safety) (e) Continuous
123,Regulations
awareness through information sharing
issued in terms of
(f) All Eskom
section 27(2) of
travelling restricted to essential staff
the Disaster
Management Act,
2002.
Disaster
Management Act
57 of 2002 Notice
No. R. 313 of 15
Employees to work from home or dispatched March 2020.
from home. Employees to only travel when it is Guidelines for the
absolutely necessary to do so. Employees to containment/mana
travel alone in a vehicle. Upon completion of gement of
the job the employee will go home without Coronavirus
engaging in any other activity at the CNC. ( Covid19),Outbre
Mostly Covid 19 incidents reported at Health and
If there is a need for an employee to work Managers ak, Pandemic or
effective Wellness
with another employee, social distancing shall Epidemic
be applied at all times. If social distancing Disaster
cannot be maintained due to the nature of the Response Plan
activity the employee shall wear the PPE that 240-100092892.
protects againsts infection by the Covid-19 Directive:COVID
virus 19 Occupational
Health and Safety
Measures in
workplaces(C19
OHS), 2020

National Road
Safety Act.
ESKOM
Procedure 240-
62946386 (Vehicle
Incident records, Speed fines and
and driver safety
Mostly Services records , Drive Cam Reports,
Adhere to existing controls Site Supervisor management) .
effective Mix Telematics reports,Coaching reports,
ESKOM
Procedure 32-
345(Eskom
Vehicle Safety
Specification) ,
Life saving rules
Disaster
Management Act
57 of 2002 Notice
No. R. 313 of 15
March 2020.
Guidelines for the
containment/mana
gement of
(a) Dispatch employees from home (b) Adhere Coronavirus
to requirements of relevant alert Level (c ) ( Covid19),Outbre
Covid 19 incidents reported at Health and
ME Adhere to Work Instruction, 240- Managers ak, Pandemic or
Wellness
154263529:Protective measures to be taken Epidemic
during the COVID-19 (Field Staff) Disaster
Response Plan
240-100092892.
Directive:COVID
19 Occupational
Health and Safety
Measures in
workplaces(C19
OHS), 2020
Occupational
Health and Safety
Act, 1993 (Act No.
Fully Incident records, Safety Awareness talks,
Adhere to existing controls Site Supervisor 85 of 1993)
effective Risk Assessment
Section 8, 14 ,
CR9,GSR3, 32-
123

Occupational
Health and Safety
Act, 1993 (Act No.
Mostly Incident records, Safety Awareness talks,
Adhere to existing controls Site Supervisor 85 of 1993)
effective Risk Assessment
Section 8, 14 ,
CR9,GSR3, 32-
123

Occupational
Health and Safety
Act, 1993 (Act No.
Fully Incident records, Safety Awareness talks,
Adhere to existing controls Site Supervisor 85 of 1993)
effective Risk Assessment
Section 8, 14 ,
CR9,GSR3, 32-
123
Occupational
Health and Safety
Act, 1993 (Act No.
Fully Incident records, Safety Awareness talks,
Adhere to existing controls Site Supervisor 85 of 1993)
effective Risk Assessment
Section 8, 14 ,
CR9,GSR3, 32-
123

Fully Incident records, Safety Awareness talks, Construction


Adhere to existing controls Site Supervisor
effective Risk Assessment Regulation 13

Fully General Safety


Adhere to existing controls Medical Surveillance Site Supervisor
effective Regulation 2

Fully Incident records, Safety Awareness talks, General Safety


Adhere to existing controls Site Supervisor
effective Risk Assessment Regulation 6

Fully Proper Tool Inspections, Risk General Safety


Adhere to existing controls Site Supervisor
effective Assessment, Supervisoin Regulation 2

Medical Surveillance, Risk Assessment,


Fully General Safety
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective Regulation 2
Maintenance records
Noise Induced
Hearing Loss
Medical Surveillance, Risk Assessment,
Fully Regulations 6(1)
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective and 7(1),Hearing
Maintenance records
Conservation
procedure 32-425

Medical Surveillance, Risk Assessment,


Fully General Safety
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective Regulation 2
Maintenance records

Fully Risk Assessment, Supervision,Proper Construction


Adhere to existing controls Site Supervisor
effective Tool Inspections, Maintenance records Regulation 13(g)

Medical Surveillance, Risk Assessment,


Fully General Safety
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective Regulation 2
Maintenance records

Ergonomics
Regulation 6,
Fully Risk Assessment, Supervision,Proper Management of
Adhere to existing controls Site Supervisor
effective Tool Inspections, Maintenance records Ergonomic Hazard
Exposure in the
workplace 34,370

Fully Risk Assessment, Supervision,Proper Construction


Adhere to existing controls Site Supervisor
effective Tool Inspections, Maintenance records Regulation 13
Risk Assessment, Supervision,Proper
Fully Construction
Adhere to existing controls Tool Inspections, Maintenance records, Site Supervisor
effective Regulation 13
Incident Records
Medical Surveillance, Risk Assessment,
Fully General Safety
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective Regulation 2
Maintenance records
Medical Surveillance, Risk Assessment,
Fully General Safety
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective Regulation 2
Maintenance records

Noise Induced
Hearing Loss
Medical Surveillance, Risk Assessment,
Fully Regulations 6(1)
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective and 7(1),Hearing
Maintenance records
Conservation
procedure 32-425

Medical Surveillance, Risk Assessment,


Fully General Safety
Adhere to existing controls Supervision,Proper Tool Inspections, Site Supervisor
effective Regulation 2
Maintenance records

Fully Risk Assessment, Supervision,Incident Construction


Adhere to existing controls Site Supervisor
effective Records Maintenance records Regulation 13

OHSA Section 14
- Duties of
Medical Surveillance, Risk Assessment, employees
Fully Supervision,Discussion of Task Manuals OHSA GSR 2(3)
Adhere to existing controls Site Supervisor
effective of Physical Material Handling, (c) - Personal
Observations, Incident Stats safety equipment
and facilities & 34
-106
Construction
Regulation
Fully Load test certificates,Risk Assessments,
Adhere to existing controls Site Supervisor 23,Driven
effective Tool Inspections
Machinery
Regulatio 18

Risk Assessment, Training Records, Construction


Fully Incident stats, Behaviour Observations, Regulation10,
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Working at
Plan Heights 32-418
National
Risk Assessment, Training Records,
Environmntal Air
Fully Incident stats, Behaviour Observations,
Adhere to existing controls Site Supervisor Quality Act,
effective Safework procedures, Fall Protection
General Safety
Plan
Regulation 2

Electrical
Fully ORHVS, Risk Assessemnt , Safework Machinery
Adhere to existing controls Site Supervisor
effective Procedures, Supervision Regulation
6,ORHVS

Fully ORHVS, Risk Assessemnt , Safework Driven Machinery


Adhere to existing controls Site Supervisor
effective Procedures, Supervision Regulation 18(11)

Fully
effective National
Environmntal Air
Medical Surveillance, Risk Assessment,
Fully Adhere to existing controls Site Supervisor Quality Act,
Supervision,
effective General Safety
Regulation 2

Fully Risk Assessment, Tool inspections, General Safety


Adhere to existing controls Site Supervisor
effective Observations, Incident Stats Regulation 2
Electrical
Fully ORHVS, Risk Assessemnt , Safework Machinery
Adhere to existing controls Site Supervisor
effective Procedures, Supervision Regulation
19,ORHVS
Risk Assessment, Training Records, Construction
Fully Incident stats, Behaviour Observations, Regulation10,
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Working at
Plan Heights 32-418

Fully Risk Assessemnt , Safework Procedures, Construction


Adhere to existing controls Site Supervisor
effective Supervision, Incident records Regulation 9

Driven Machinery
Fully Risk Assessemnt , Safework Procedures, Regulation 18,
Adhere to existing controls Site Supervisor
effective Supervision, Incident records Construction
Regulation 9

Fully Risk Assessemnt , Safework Procedures, Driven Machinery


Adhere to existing controls Site Supervisor
effective Supervision, Incident records Regulation 18

Fully Load test certificates,Risk Assessments, Driven Machinery


Adhere to existing controls Site Supervisor
effective Tool Inspections Regulation 18

Electrical
Fully ORHVS, Risk Assessemnt , Safework Machinery
Adhere to existing controls Site Supervisor
effective Procedures, Supervision Regulation 20,
ORHVS
Risk Assessment, Training Records, Construction
Fully Incident stats, Behaviour Observations, Regulation10,
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Working at
Plan Heights 32-418
Risk Assessment, Training Records,
Fully Incident stats, Behaviour Observations, Driven Machinery
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Regulation 18
Plan

Electrical
ORHVS, Risk Assessemnt , Safework
Fully Machinery
Adhere to existing controls Procedures, Supervision, Incident Site Supervisor
effective Regulation 20,
Records, Observations
ORHVS
Electrical
ORHVS, Risk Assessemnt , Safework
Fully Machinery
Adhere to existing controls Procedures, Supervision, Incident Site Supervisor
effective Regulation 20,
Records, Observations
ORHVS

National
Environmntal Air
Fully Medical Surveillance, Incident Records,
Adhere to existing controls Site Supervisor Quality Act,
effective Hygiene Surveys
General Safety
Regulation 2

Noise Induced
Hearing Loss
Fully Medical Surveillance, Incident Records, Regulations 6(1)
Adhere to existing controls Site Supervisor
effective Hygiene Surveys and 7(1),Hearing
Conservation
procedure 32-425

Ergonomics
Regulation 6,
Fully Medical Surveillance, Incident Records, Management of
Adhere to existing controls Site Supervisor
effective Hygiene Surveys Ergonomic Hazard
Exposure in the
workplace 34,370
Risk Assessment, Training Records, Construction
Fully Incident stats, Behaviour Observations, Regulation10,
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Working at
Plan Heights 32-418

Construction
Maintenance Records, Inspections, Regulation
Fully
Adhere to existing controls Authorisations, Risk Assessments, Site Supervisor 23,Driven
effective
Loadtest certificates Machinery
Regulation 18

Maintenance Records, Inspections,


Fully Driven Machinery
Adhere to existing controls Authorisations, Risk Assessments, Site Supervisor
effective Regulation 18
Loadtest certificates

Maintenance Records, Inspections,


Fully Driven Machinery
Adhere to existing controls Authorisations, Risk Assessments, Site Supervisor
effective Regulation 18
Loadtest certificates

Construction
Risk Assessment, Training Records, Regulation10,
Fully Incident stats, Behaviour Observations, Working at
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Heights 32-418,
Plan General Safety
Regulation 13 A

Maintenance Records, Inspections, Risk


Fully Construction
Adhere to existing controls Assessments,Observations,Safework Site Supervisor
effective Regulation 9
Procedures

Fully Construction
Adhere to existing controls Line Inspection Reports Site Supervisor
effective Regulation 9
Maintenance Records, Inspections, Risk
Fully Driven Machinery
Adhere to existing controls Assessments,Observations,Safework Site Supervisor
effective Regulation 18
Procedures

General Safety
Fully Maintenance Records, Inspections, Risk Regulation 2,
Adhere to existing controls Site Supervisor
effective Assessments,Observations, Construction
Regulation 9

General Safety
Fully Regulation 2,
Adhere to existing controls Risk Assessments,Observations,PPE Site Supervisor
effective Construction
Regulation 9

Fully Risk Assessments,Observations,PPE, General Safety


Adhere to existing controls Site Supervisor
effective Training,Incident Records Regulation 2

ORHVS, Risk Assessemnt , Safework Electrical


Fully
Adhere to existing controls Procedures, Supervision, Incident Site Supervisor Machinery
effective
Records, Observations Regulation 10

Noise Induced
Hearing Loss
Fully Medical Surveillance, Incident Records, Regulations 6(1)
Adhere to existing controls Site Supervisor
effective Hygiene Surveys and 7(1), General
Safety Regulation
2

Fully Medical Surveillance, Incident Records, General Safety


Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2
Fully Medical Surveillance, Incident Records, General Safety
Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2

Asbestos
Medical Surveillance, Incident Records, Regulation7,8 ,32-
Fully
Adhere to existing controls Hygiene Surveys, Asbestos monthly Site Supervisor 303 General
effective
Tracker Safety Regulation
2

Ergonomics
Regulation 6,
Fully Management of
Adhere to existing controls Incident Records Site Supervisor
effective Ergonomic Hazard
Exposure in the
workplace 34,370

Risk Assessment, Training Records, Construction


Fully Incident stats, Behaviour Observations, Regulation10,
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Working at
Plan Heights 32-418

Ergonomics
Regulation 6,
Fully Management of
Adhere to existing controls Incident Records Site Supervisor
effective Ergonomic Hazard
Exposure in the
workplace 34,370
General Safety
Regulation 8,
Construction
Fully Risk Assessments, Safework procedures,
Adhere to existing controls Site Supervisor Regulation 28,
effective Incident Recors, Supervision
Stacking and
Storage Standard
240-93411424

General Safety
Fully Regulations 2A,
Adhere to existing controls Monthly Sustance abuste testing stats Site Supervisor
effective 32-37 Substance
Abuse Procedure
(a) Train cleaning staff wrt COVID 19 Risks
Disaster
and control measures (b) Issue Relevant PPE
Management Act
and training on use (c ) Isuue relevant
57 of 2002 Notice
cleaning material and train wrt use and MSDS
No. R. 313 of 15
(d) Hourly cleaning of common surfaces in
March 2020.
kitchen and eating areas with alcohol based
Guidelines for the
cleanerHourly cleaning of common surfaces
containment/mana
in kitchen and eating areas with alcohol based
gement of
cleaner.
Coronavirus
Handrails, handles, lift and printers can be
( Covid19),Outbre
cleaned and sanitized every 2 hours. Covid 19 incidents reported at Health and
ME Managers ak, Pandemic or
Desks/tables can be cleaned twice a day if Wellness
Epidemic
employees need to sanitize in between (use
Disaster
sanitiser that will be placed per floor)
Response Plan
Dustbins can be emptied twice a day when the
240-100092892.
desks are being disinfected
Directive:COVID
The bathrooms can be cleaned twice a day in
19 Occupational
the morning and after lunch.
Health and Safety
Floors will be washed thrice a week
Measures in
(e ) Sanitisers to be placed in kitchens , put
workplaces(C19
up signage that staff must sanitise items
OHS), 2020
before use
Disaster
Management Act
57 of 2002 Notice
No. R. 313 of 15
March 2020.
Guidelines for the
containment/mana
gement of
Security companies informed via Security Coronavirus
manager to issue PPE to all employees (b) ( Covid19),Outbre
Covid 19 incidents reported at Health and
ME Adhere to requirements or relevenat Alert level Managers ak, Pandemic or
Wellness
(c ) Sanitisers placed at entrances by Eskom Epidemic
(d) No mask, no work Disaster
Response Plan
240-100092892.
Directive:COVID
19 Occupational
Health and Safety
Measures in
workplaces(C19
OHS), 2021

National
Environmntal Air
Fully Medical Surveillance, Incident Records,
Adhere to existing controls Site Supervisor Quality Act,
effective Hygiene Surveys
General Safety
Regulation 2

Fully Medical Surveillance, Incident Records, General Safety


Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2
Noise Induced
Hearing Loss
Fully Medical Surveillance, Incident Records, Regulations 6(1)
Adhere to existing controls Site Supervisor
effective Hygiene Surveys and 7(1), General
Safety Regulation
2

Fully Medical Surveillance, Incident Records, General Safety


Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2

Risk Assessment
procedure 32-
Fully 520Emergency
Adhere to existing controls Risk Assessment, Incident Reports Site Supervisor
effective Planning32-123,
Public Safety 240-
84520108

Operating
Regulation for
Fully
Adhere to existing controls Incident Reports Site Supervisor High Voltage
effective
Systems 240-
11467625

Asbestos
Medical Surveillance, Incident Records, Regulation7,8 ,32-
Fully
Adhere to existing controls Hygiene Surveys, Asbestos monthly Site Supervisor 303 General
effective
Tracker Safety Regulation
2

Fully Medical Surveillance, Incident Records, General Safety


Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2
Ergonomics
Regulation 6,
Fully Management of
Adhere to existing controls Incident Records Site Supervisor
effective Ergonomic Hazard
Exposure in the
workplace 34,370

General Safety
Regulation 2,
Fully Medical Surveillance, Incident Records, Safety and
Adhere to existing controls Site Supervisor
effective Hygiene Surveys, Occupational
Hygiene standard-
24068572545

General Safety
Regulation 2,
Fully Medical Surveillance, Incident Records, Safety and
Adhere to existing controls Site Supervisor
effective Hygiene Surveys, Occupational
Hygiene standard-
24068572545

General Safety
Regulation 2,
Fully Incident Records, Behaviour Safety OSHACT 8(1),32-
Adhere to existing controls Site Supervisor
effective Observations, Awareness Training, Signs 407 Behaviour
Safety
Observations
General Safety
Regulation 2,
Fully OSHACT 8(1),32-
Adhere to existing controls Incident Records Site Supervisor
effective 407 Behaviour
Safety
Observations
General Safety
Regulation 2,
Fully OSHACT 8(1),32-
Adhere to existing controls Incident Records Site Supervisor
effective 407 Behaviour
Safety
Observations

Noise Induced
Hearing Loss
Fully Medical Surveillance, Incident Records, Regulations 6(1)
Adhere to existing controls Site Supervisor
effective Hygiene Surveys and 7(1), General
Safety Regulation
2

OHSA Section 14
- Duties of
Medical Surveillance, Risk Assessment, employees
Fully Supervision,Discussion of Task Manuals OHSA GSR 2(3)
Adhere to existing controls Site Supervisor
effective of Physical Material Handling, (c) - Personal
Observations, Incident Stats safety equipment
and facilities & 34
-106

National
Environmntal Air
Fully Medical Surveillance, Incident Records,
Adhere to existing controls Site Supervisor Quality Act,
effective Hygiene Surveys
General Safety
Regulation 2
Fully ORHVS, Risk Assessemnt , Safework Driven Machinery
Adhere to existing controls Site Supervisor
effective Procedures, Supervision Regulation 18(11)

Risk Assessment, Training Records, Construction


Fully Incident stats, Behaviour Observations, Regulation10,
Adhere to existing controls Site Supervisor
effective Safework procedures, Fall Protection Working at
Plan Heights 32-418
National
Risk Assessment, Training Records,
Environmntal Air
Fully Incident stats, Behaviour Observations,
Adhere to existing controls Site Supervisor Quality Act,
effective Safework procedures, Fall Protection
General Safety
Plan
Regulation 2
Electrical
Fully ORHVS, Risk Assessemnt , Safework Machinery
Adhere to existing controls Site Supervisor
effective Procedures, Supervision Regulation
6,ORHVS

Noise Induced
Hearing Loss
Fully Medical Surveillance, Incident Records, Regulations 6(1)
Adhere to existing controls Site Supervisor
effective Hygiene Surveys and 7(1), General
Safety Regulation
2

Fully Medical Surveillance, Incident Records, General Safety


Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2

Fully Medical Surveillance, Incident Records, General Safety


Adhere to existing controls Site Supervisor
effective Hygiene Surveys Regulation 2
National
Environmntal Air
Fully Medical Surveillance, Incident Records,
Adhere to existing controls Site Supervisor Quality Act,
effective Hygiene Surveys
General Safety
Regulation 2

Ergonomics
Regulation 6,
Fully Medical Surveillance, Incident Records, Management of
Adhere to existing controls Site Supervisor
effective Hygiene Surveys Ergonomic Hazard
Exposure in the
workplace 34,370

OHSA Section 14
- Duties of
Medical Surveillance, Risk Assessment, employees
Fully Supervision,Discussion of Task Manuals OHSA GSR 2(3)
Adhere to existing controls Site Supervisor
effective of Physical Material Handling, (c) - Personal
Observations, Incident Stats safety equipment
and facilities & 34
-106

Fully General Safety


Adhere to existing controls Medical Surveillance, Incident stats Site Supervisor
effective Regulation 9
Fully General Safety
Adhere to existing controls Medical Surveillance, Incident stats Site Supervisor
effective Regulation 9

Fully General Safety


Adhere to existing controls Maintenance and Inspection records Site Supervisor
effective Regulation 9

Fully General Safety


Adhere to existing controls Medical Surveillance, Incident stats Site Supervisor
effective Regulation 9

Fully General Safety


Adhere to existing controls Maintenance and Inspection records Site Supervisor
effective Regulation 9

Occupational
Health and Safety
Act, 1993 (Act No.
Fully Incident records, Safety Awareness talks,
Adhere to existing controls Site Supervisor 85 of 1993)
effective Risk Assessment
Section 8, 14 ,
CR9,GSR3, 32-
123
General Safety
Fully Regulation 2,
Adhere to existing controls Risk Assessments,Observations,PPE Site Supervisor
effective Construction
Regulation 9

Fully Maintenance and Inspection reports, Public Safety 240-


Adhere to existing controls Site Supervisor
effective Incident records 84520108

Fully Maintenance and Inspection reports, Public Safety 240-


Adhere to existing controls Site Supervisor
effective Incident records 84520108

Fully Maintenance and Inspection reports, Public Safety 240-


Adhere to existing controls Site Supervisor
effective Incident records 84520108

Fully Maintenance and Inspection reports, Public Safety 240-


Adhere to existing controls Site Supervisor
effective Incident records 84520108
Fully Maintenance and Inspection reports, Public Safety 240-
Adhere to existing controls Site Supervisor
effective Incident records, Load Test certificates 84520108

Hazardous
Fully Chemical
Adhere to existing controls Incident Records Site Supervisor
effective Substance
Regulation 9 (a)

OHS Act 85 of 1993


Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
and its Regulations
Driven Machinery
Regulations, Eskom
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Procedures:240-
77090523, 240-
97759751, 39-98
Driven Machinery
Regulations, Eskom
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Procedures:240-
77090523, 240-
97759751, 39-98
Construction
Regulation 10,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
Eskom Procedure
32-418
Construction
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
Regulation 13

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

ORHVS, OHS Act


85 of 1993, Section
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager 8 Employers duties,
Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.
OHS Act 85 of 1993,
Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.
OHS Act 85 of 1993,
Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.
OHS Act 85 of 1993,
Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
Employees duties,
Driven Machinery
Regulations

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties.

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
Employees duties,
Construction
Regulation 13
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Driven Machinery
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98,
Construction
Regulation 13

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-99

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-98
OHS Act 85 of 1993,
Section 8 Employers
duties, Section 14
Employees duties,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-99

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties

OHS Act 85 of 1993,


Section 8 Employers
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager
duties, Section 14
Employees duties

OHS Act 85 of 1993,


Section 8 Employers
duties, Section 14
Employees duties,
Construction
Regulation 14,
Fully effective Maintain existing controls Inspection/ Supervision Site Supervisor/ Manager Construction
Regulation 11,
Driven Machinery
Regulations, Eskom
Procedures:240-
77090523, 240-
97759751, 39-99
(a) Disaster
Management Act 57 of
(a) Employees to work from home or dispatched from
2002 Notice No. R.
home. (b) Employees to only travel when it is absolutely
313 of 15 March 2020.
necessary to do so.(c ) Employees to travel alone in a
(b) Guidelines for the
vehicle. (d) Upon completion of the job the employee will
containment/managem
go home without engaging in any other activity at the
ent of Coronavirus
CNC.
( Covid19),Outbreak,
Mostly (e) If there is a need for an employee to work with Covid 19 incidents reported at Health and
Managers Pandemic or Epidemic
effective another employee, social distancing shall be applied at Wellness
Disaster Response
all times.(f) If social distancing cannot be maintained
Plan 240-100092892.
due to the nature of the activity the employee shall wear
(c ) Directive:COVID
the PPE that protects againsts infection by the Covid-19
19 Occupational
virus (g) Pool vehicles and company vehicles to be
Health and Safety
disinfected after every use (h) Issuing of COVID 19 PPE
Measures in
to employees.
workplaces(C19 OHS),
2020
Disaster Management
Act 57 of 2002 Notice
No. R. 313 of 15
March 2020.
Guidelines for the
(a) Dispatch employees from home (b) Adhere to
containment/managem
requirements of relevant alert Level (c ) Adhere to Work
ent of Coronavirus
Instruction, 240-154263529:Protective measures to be
Mostly Covid 19 incidents reported at Health and ( Covid19),Outbreak,
taken Managers
effective Wellness Pandemic or Epidemic
during the COVID-19 (Field Staff) (d) Issuing of COVID
Disaster Response
19 PPE to employees. (e )Temperature screening and
Plan 240-100092892.
completing COVID 19 questionaire
Directive:COVID 19
Occupational Health
and Safety Measures
in workplaces(C19
OHS), 2020
(a) Disaster
Management Act 57 of
2002 Notice No. R.
313 of 15 March 2020.
(b) Guidelines for the
(a) Dispatch employees from home / Work from home (b)
containment/managem
Adhere to requirements of relevant alert Level (c )Bring
ent of Coronavirus
1/3 of staff back to work, adhere to social distancing
Mostly Covid 19 incidents reported at Health and ( Covid19),Outbreak,
between cubicles, 1.5 meters (d) 1 occupant per cubicle Managers
effective Wellness Pandemic or Epidemic
(e ) Daily complete COVID 19 screening questionnaire
Disaster Response
(f) Issuing of COVID 19 PPE to employees.
Plan 240-100092892.
(g )Temperature screening at entrances
(c) Directive:COVID 19
Occupational Health
and Safety Measures
in workplaces(C19
OHS), 2020
(a) Disaster
Management Act 57 of
2002 Notice No. R.
313 of 15 March 2020.
(b) Guidelines for the
(a) Bring 1/3 of staff back to work during the morning, containment/managem
from 07h30 – 12h00 while it is still cool in the building ent of Coronavirus
with AC switched off (b) At CNC’s air conditioners can ( Covid19),Outbreak,
Mostly Covid 19 incidents reported at Health and
be switched off as the offices has natural ventilation, Managers Pandemic or Epidemic
effective Wellness
windows can be opened (c ) ERE to obtain quote for Disaster Response
smoke test to be done by AC company to determine Plan 240-100092892.
airflow at BBV (c )Directive:COVID 19
Occupational Health
and Safety Measures
in workplaces(C19
OHS), 2020 (d )
Ventilation guidelnes
(a) Train cleaning staff wrt COVID 19 Risks and control
measures (b) Issue Relevant PPE and training on use
(c ) Isuue relevant cleaning material and train wrt use
(a) Disaster
and MSDS (d) Hourly cleaning of common surfaces in
Management Act 57 of
kitchen and eating areas with alcohol based cleaner.
2002 Notice No. R.
Handrails, handles, lift and printers can be cleaned and
313 of 15 March 2020.
sanitized every 2 hours.
(b) Guidelines for the
Desks/tables can be cleaned twice a day if employees
containment/managem
need to sanitize in between (use sanitiser that will be
ent of Coronavirus
placed per floor)
Mostly Covid 19 incidents reported at Health and ( Covid19),Outbreak,
Dustbins can be emptied twice a day when the desks are Managers
effective Wellness Pandemic or Epidemic
being disinfected
Disaster Response
The bathrooms can be cleaned twice a day in the
Plan 240-100092892.
morning and after lunch. Printers to be wiped with
(c) Directive:COVID 19
sanitiser wipes
Occupational Health
Floors will be washed thrice a week
and Safety Measures
(e ) Sanitisers to be placed in kitchens , put up signage
in workplaces(C19
that staff must sanitise items before use (f ) Daily
OHS), 2020
complete COVID 19 screening questionnaire (g) Issuing
of COVID 19 PPE to employees. (h)Temperature
screening at entrances
(a) Disaster
Management Act 57 of
2002 Notice No. R.
313 of 15 March 2020.
(b) Guidelines for the
Security companies informed via Security manager to containment/managem
issue PPE: 2 x cloth masks, to all employees (b) Adhere ent of Coronavirus
to requirements or relevenat Alert level (c ) Sanitisers ( Covid19),Outbreak,
Mostly Covid 19 incidents reported at Health and
placed at entrances by Eskom (d) No mask, no work (e ) Managers Pandemic or Epidemic
effective Wellness
Daily complete COVID 19 screening questionnaire (f) Disaster Response
Issuing of COVID 19 PPE to employees. Plan 240-100092892.
(g )Temperature screening at entrances (c ) Directive:COVID
19 Occupational
Health and Safety
Measures in
workplaces(C19 OHS),
2021

Internal Audits
External Audits
Inspections
Visible Felt
Incident records, Safety Awareness talks, Managers and SHE Leadership
Fully effective Maintain existing controls inspections
Risk Assessment personnel
Site visits by
safety
practitioners

OHSA 85 of 1993
Incident records, Safety Awareness talks, Managers and Senior Reg 8
Fully effective Maintain existing controls
Risk Assessment Supervisor
OHSA 85 of 1993
Incident records, Safety Awareness talks, Managers and Senior Reg 8
Fully effective Maintain existing controls
Risk Assessment Supervisor

Occupational
Health and Safety
Incident records, Safety Awareness talks, Managers and Senior
Fully effective Maintain existing controls Act, 1993 (Act No.
Risk Assessment Supervisor
85 of 1993) and
32-95

PPE specification
Incident records, Safety Awareness talks, Managers and SHE 240-
Fully effective Maintain existing controls
Risk Assessment personnel 44175132 ,OHSA
CT and 32-95

PPE specification
240-
44175132,Occupa
Incident records, Safety Awareness talks, Managers and Senior
Fully effective Maintain existing controls tional Health and
Risk Assessment Supervisor
Safety Act, 1993
(Act No. 85 of
1993) and 32-95

Incident records, Safety Awareness talks, Managers and Senior OHSACT section
Fully effective Maintain existing controls
Risk Assessment Supervisor 8(1)

OHS Act and its


regulations,
Incident records, Safety Awareness talks, Managers and Senior Eskom Standards
Fully effective Maintain existing controls
Risk Assessment Supervisor and Procedures,
34-109, 34-328,
34-1784
Construction
Incident records, Safety Awareness talks, Managers and Senior
Fully effective Maintain existing controls Regulations
Risk Assessment Supervisor
Section 10

Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
and Safety Act,
1993 (Act No. 85 of
Incident records, Safety Awareness talks, Managers and Senior 1993)
Fully effective Maintain existing controls
Risk Assessment Supervisor

Occupational Health
and Safety Act,
1993 (Act No. 85 of
Incident records, Safety Awareness talks, Managers and Senior 1993)
Fully effective Maintain existing controls
Risk Assessment Supervisor

Occupational Health
and Safety Act,
1993 (Act No. 85 of
Incident records, Safety Awareness talks, Managers and Senior 1993)
Fully effective Maintain existing controls
Risk Assessment Supervisor

General Safety
Incident records, Safety Awareness talks, Managers and Senior Regulation 9
Fully effective Maintain existing controls
Risk Assessment Supervisor

General Safety
Incident records, Safety Awareness talks, Managers and Senior Regulation 9
Fully effective Maintain existing controls
Risk Assessment Supervisor
Incident records, Safety Awareness talks, Managers and Senior General Safety
Fully effective Maintain existing controls Regulation 9
Risk Assessment Supervisor
General Safety
Incident records, Safety Awareness talks, Managers and Senior Regulation 9
Fully effective Maintain existing controls
Risk Assessment Supervisor
Incident records, Safety Awareness talks, Managers and Senior General Safety
Fully effective Maintain existing controls Regulation 9
Risk Assessment Supervisor
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Construction
Regulation 8: (Fall
Incident records, Safety Awareness talks, Managers and Senior Protection Plan).
Fully effective Maintain existing controls
Risk Assessment Supervisor Working at Height
Procedure 32-418.
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
OHSACT 8(1)
Employer shall
provide and
maintain, as far as
reasonably
Incident records, Safety Awareness talks, Managers and Senior practicable, a
Fully effective Maintain existing controls working
Risk Assessment Supervisor
environment that is
safe and without risk
to the health of his
employees.

OHSACT 8(1)
Employer shall
provide and
maintain, as far as
reasonably
Incident records, Safety Awareness talks, Managers and Senior practicable, a
Fully effective Maintain existing controls working
Risk Assessment Supervisor
environment that is
safe and without risk
to the health of his
employees.

Construction
Regulation 10: (Fall
Incident records, Safety Awareness talks, Managers and Senior Protection Plan).
Fully effective Maintain existing controls Working at Height
Risk Assessment Supervisor
Procedure 32-418.

Construction
Regulation 10: (Fall
Incident records, Safety Awareness talks, Managers and Senior Protection Plan).
Fully effective Maintain existing controls Working at Height
Risk Assessment Supervisor
Procedure 32-418.

Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
and Safety Act,
1993 (Act No. 85 of
Incident records, Safety Awareness talks, Managers and Senior 1993)
Fully effective Maintain existing controls
Risk Assessment Supervisor

Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
and Safety Act,
Incident records, Safety Awareness talks, Managers and Senior 1993 (Act No. 85 of
Fully effective Maintain existing controls 1993)
Risk Assessment Supervisor

Occupational Health
and Safety Act,
1993 (Act No. 85 of
1993)

Incident records, Safety Awareness talks, Managers and Senior


Fully effective Maintain existing controls
Risk Assessment Supervisor
Occupational Health
and Safety Act,
1993 (Act No. 85 of
1993)
Incident records, Safety Awareness talks, Managers and Senior
Fully effective Maintain existing controls
Risk Assessment Supervisor

Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
and Safety Act,
Incident records, Safety Awareness talks, Managers and Senior 1993 (Act No. 85 of
Fully effective Maintain existing controls 1993)
Risk Assessment Supervisor

Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
Occupational Health
Incident records, Safety Awareness talks, Managers and Senior and Safety Act,
Fully effective Maintain existing controls 1993 (Act No. 85 of
Risk Assessment Supervisor
1993)
DOC NAME REG/BRA/01

EFFECTIVE DATE 10-Feb-24

REV 1

REV DATE 10-Feb-25

APPROVED BY EDWARD MUTSHAENI

Integrated Risk Management (IRM)


Target Date Current Status
reference number
Once a date has been Pending, Where applicable, add IRM system
agreed to, this can not be In Progress, reference number for tracking of
changed Complete treatment actions.

N/A N/A N/A


N/A N/A N/A 5

N/A N/A N/A


N/A N/A N/A
N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A


N/A N/A N/A
N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A
N/A N/A N/A
N/A N/A N/A
N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A
N/A N/A N/A
N/A N/A N/A
N/A N/A N/A
N/A N/A N/A
N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A

N/A N/A N/A


R Safety 1A Fully effective I

II
N Health 2B Mostly effective

III
3C Mostly ineffective
IV
4D None
5E

6
III II II I I
Consequence rating

5
6
Consequence criteria
Description

Health and Safety


No injuries or health effects(near misses)

First-aid treatment case, and temporary discomfort case

Medical treatment case; occupational disease with reversible/non-permanent effect

Lost Time Injury. Irreversible health effects/occupational disease with permanent consequence

Fatality or life threatening health effects


Multiple fatalities
Likelihood criteria
Score Descriptor Safety Occupational hygiene
Exposure
§ More than a “100 year event”
§ Exceptionally unlikely, even in the long-
A Highly unlikely
term future
Rare (once a year)

§ < 5% probability.
§ Could occur in “years to decades”
Short periods of time, a few times per
B Unlikely § May occur but not anticipated day/ intermittent (once in six months,
three months, or a month)
§ ≥ 5% and < 20% probability.

§ Could occur within “months to years”


Continuous for between one and two
C Possible § May occur shortly but a distinct hours (often/ weekly)
probability it will not, or ≥ 20% and < 70%
probability.

§ Could occur within “weeks to months”


Continuous for between two and four
D Likely
§ Balance of probability will occur hours (frequent/daily)
§ ≥ 70% and < 90% probability.

§ Could occur within “days to weeks”


E Unavoidable
§ Impact is imminent
Continuous for eight-hour shift

§ ≥ 90% probability.
Probability of exceeding OEL

No exposure (or exposure < 10% of OEL)

Low exposure (< 50% of OEL)

Moderate exposure (chronic exposure > 50%


of OEL or acute exposure ≥ OEL)

High exposure (chronic exposure > OEL, or


gv g
exposure exceeding OEL-STEL)

Very high exposure (chronic exposure > 2 x


OEL or exposure exceeding OEL-C)
RISK CONTROL EFFECTIVENESS GUIDE
RCE

Fully effective

Mostly effective

Mostly ineffective

None
SK CONTROL EFFECTIVENESS GUIDE
Guide
Nothing more to be done except review and monitor the existing controls.
Controls are well designed for the risk, are largely preventive and address
the root causes. Management believes that they are effective and reliable
at all times. Reactive controls only support preventive controls.

Most controls are designed correctly and are in place and effective. Some
more work to be done to improve operating effectiveness or management
has doubts about operational effectiveness and reliability of the controls.

While the design of controls may be largely correct in that they treat most
of the root causes of the risk, they are not currently operationally very
effective. There may be an over-reliance on reactive controls, or some of
the controls do not seem correctly designed in that they do not treat root
Virtually no credible control. Management has no confidence that any
degree of control is being achieved.
RISK MATRIX
6 I I

5 II II
Consequences
4 III III

3 IV III

2 IV IV

1 IV IV
A B
Likelihood

Priority Risk ranking Action required

Immediate action required, and these risks to


I Very high
be captured on IRM system.
Strong mandatory action required, and these
II High
risks to be captured on IRM system.
Action required, possibly at administrative
III Medium
level.

IV Low Minor or no action required.


RISK MATRIX
I I I

II I I

II I I

II II I

III II II

III III III


C D E
Likelihood

Action required

ction required, and these risks to


on IRM system.
datory action required, and these
aptured on IRM system.
ed, possibly at administrative

action required.

You might also like