Demolishing Concrete
Category: Concrete Demolition Hits: 39481

Customer
Estimating Productivity of feedback

Concrete Demolition counts

* Production rates listed are based on 8-hr shift. The above The
figures are for general estimation purpose only and must Experts
not be used to guarantee any production figure to the
Client
customer. The actual working results may vary according to
Reviews
the quality and structure of the material to be broken,
required degree of material size reduction, installation,
condition of the carrier, conditions at the worksite, haulage
of the broken material, skills of the operator etc. Estimating
Production
Task / Description Slow Ave Fast Units Rates
Hammer
Building
(2,200lb - Constants
Concrete
1,000kg) - Work
315C Excavator Demolition

Non-Reinforced 150cu.yd 200cu.yd 375cu.yd cu.yd & Concre


Demolit
Concrete - 115m3 - 153m3 - 287m3 m3/8hr
Cutting
Reinforced 140cu.yd 160cu.yd 240cu.yd cu.yd &
Back
Concrete - 107m3 - 122m3 - 184m3 m3/8hr Concre

Joinery

https://methvin.org/estimating-production-rates/demolition-renovation/235-demolishing-concrete 1/6
4/15/24, 1:04 AM Concrete Demolition

Sedimentary 165cu.yd 200cu.yd 300cu.yd cu.yd & Milling

Non
ProductsRock Examples - 126m3 - 153m3 Production
Pricing - 229m3 m3/8hr
Rates Contact Us
explosiv
Volcanic Rock 75cu.yd - 110cu.yd 150cu.yd cu.yd &
Structu
57m3 - 84m3 - 115m3 m3/8hr
Capabilities Services About Us Mechanical
Hammer &
Electrical
(3,740lb - Structural
Steel
1,700kg) - Excavation
330C Excavator Foundation
Plant
Non-Reinforced 275cu.yd 375cu.yd 490cu.yd cu.yd & Productions
Concrete - 210m3 - 287m3 - 375m3 m3/8hr Road
and
Rail
Reinforced 200cu.yd 150cu.yd 350cu.yd cu.yd &
Tunneling
Concrete - 153m3 - 115m3 - 268m3 m3/8hr &
Mining
Sedimentary 250cu.yd 150cu.yd 400cu.yd cu.yd & Retaining
structures
Rock - 191m3 - 115m3 - 306m3 m3/8hr

Volcanic Rock 135cu.yd 150cu.yd 275cu.yd cu.yd &

- 103m3 - 115M3 - 210m3 m3/8hr

Hammer

(6,946lb -

3,150kg) -

345C Excavator

Reinforced 300cu.yd 385cu.yd 850cu.yd cu.yd &

Concrete - 229m3 - 295m3 - 650m3 m3/8hr

Sedimentary 350cu.yd 440cu.yd 900cu.yd cu.yd &

Rock - 268m3 - 337m3 - 688m3 m3/8hr

Volcanic Rock 200cu.yd 275cu.yd 600cu.yd cu.yd &

- 153m3 - 210m3 - 459m3 m3/8hr

Demolishing Reinforced &


Unreinforced Concrete - manual
jack hammer
Task / Description Slow Ave Fast Units
Concrete Slabs, unreinforced 50- 3.2 - 1.9 hrs/m3

150mm

https://methvin.org/estimating-production-rates/demolition-renovation/235-demolishing-concrete 2/6
4/15/24, 1:04 AM Concrete Demolition

Concrete Slabs, unreinforced 150- 5.5 4.1 3.7 hrs/m3

Products300mm Examples Pricing Production Rates Contact Us


Concrete Slabs, reinforced 50-150mm 5.2 - 3.9 hrs/m3

Concrete Slabs, reinforced 150- 9.1 6.2 4.7 hrs/m3


Capabilities Services About Us
300mm

Concrete Walls, unreinforced 4.7 3.9 3.1 hrs/m3

Concrete Walls, reinforced 5.6 4.7 3.9 hrs/m3

Concrete Foundations, unreinforced 3.6 3.3 3.0 hrs/m3

Concrete Foundations, reinforced 5.4 5.1 4.8 hrs/m3

Concrete Beams 7.5 6.5 5.6 hrs/m3

Concrete Columns 9.2 8.2 7.3 hrs/m3

Tarmac paving 20-50mm thick 1.9 1.7 1.5 hrs/m3

Tarmac paving 50-100mm thick 2.1 - 1.6 hrs/m3

Tarmac paving 100-150mm thick 2.1 - 1.7 hrs/m3

Tarmac roadway 150mm thick - 3.6 - hrs/m3

Brickwork, walls and columns 2.4 1.8 1.3 hrs/m3

Brickwork, foundations 2.7 2.1 1.5 hrs/m3

Cutting Back Piles & Slabs -


Manual Jack Hammer
Task / Description Slow Ave Fast Units
Concrete Pile Caps, 50-300mm deep 0.6 - 0.3 hrs/no

and 0.6m dia

Concrete Pile Caps, 300-750mm deep 1.5 - 0.4 hrs/no

and 0.6m dia

Concrete Pile Caps, > 750mm deep 1.8 - 0.8 hrs/no

and 0.6m dia

Concrete Pile Caps, 50-300mm deep 1.9 - 0.8 hrs/no

and 1.1m dia

Concrete Pile Caps, 300-750mm deep 2.5 - 1.1 hrs/no

and 1.1m dia

Concrete Pile Caps, > 750mm deep 4.2 - 2.3 hrs/no

and 1.1m dia

https://methvin.org/estimating-production-rates/demolition-renovation/235-demolishing-concrete 3/6
4/15/24, 1:04 AM Concrete Demolition

Concrete Pile Caps, 50-300mm deep 9.2 - 8.2 hrs/no

Productsand 2.5m Examples


dia Pricing Production Rates Contact Us
Concrete Pile Caps, 300-750mm deep 10.1 - 9.5 hrs/no

and 2.5m dia


Capabilities Services About Us
Concrete Pile Caps, > 750mm deep 11.5 - 10.2 hrs/no

and 2.5m dia

Concrete, Cutting Slabs, 5-25m deep - 15.2 - m/hr

Concrete, Cutting Slabs, 25-50m deep - 11.5 - m/hr

Concrete, Cutting Slabs, 50-75m deep - 6.7 - m/hr

Concrete, Cutting Holes, coring - 0.2 - m3/hr

machine

Concrete, Cutting Back to expose - 2.5 - m/day

couplers 0.7m slab

You are here: Home Estimating Production Rates


Demolition Concrete Demolition

https://methvin.org/estimating-production-rates/demolition-renovation/235-demolishing-concrete 4/6
4/15/24, 1:04 AM Concrete Demolition

Products Examples Pricing Production Rates Contact Us

Capabilities Services About Us

Customer feedback counts

The Experts

Client Reviews

Estimating Manual

Takeoff Manual

Gantt Manual

Project Proverbs

Student Portal

Estimating Software

Contact Us

Training Courses

Company Policies

Glossary

Methvin's Advantage

https://methvin.org/estimating-production-rates/demolition-renovation/235-demolishing-concrete 5/6
4/15/24, 1:04 AM Concrete Demolition

Support Ticket

Products Examples Pricing Production Rates Contact Us

Capabilities Services About Us


Methvin is a leading provider of online applications for the construction industry and our
evolution is rooted in our commitment to offer only the most functional, flexible and easy to use
cloud-based estimating and tendering solution since 2018.

Contact Us
Login to the server
331 Rosedale Rd, Albany Auckland, New Zealand

support@methvin.org
Support and Knowledge Base
+1 347 759 6200

Copyright © 2024. methvin. | Privacy Policy | Terms of Use

https://methvin.org/estimating-production-rates/demolition-renovation/235-demolishing-concrete 6/6

You might also like