JSA (Job Safety Analysis) Sheet

Activity Name:-Cement feeding from Bulker to silo Ref-

Location:- Date :

Sr.No. Sub-Activity Name Type Of Hazard Risk(s) Involved Risk Control measures
Untrained worker,lack of Only inducted worker shall be deputed at the work place.
1 Manpower Mobilization Personal injury
skill awareness Given Tool Box Talk to all workers.
Use of required PPEs such as safety Helmet, refractive jacket, Safety shoes,Ear
3 Pre-inspection before operation Negligence of operator Personal injury Property damage
Plug, Safety goggle,Nose mask

Cement feeding through cement Use of required PPEs such as safety Helmet, refractive jacket, Safety shoes,Ear
3 Cement dust Silicosis
storage to hoper Plug, Safety goggle,Nose mask

Driver having valid driving licences, and ensure that he will be stand th' out the
Un-inspected machinary Personal injury Property damage operation.The vechile have stopper and reverse horn.
Banks man should be provide for giving signal.

Improper fixing of Flange spread of Cement dust Flange should be fixed properly by means of nut bolting.

Uninspected hand tools Personal injury Property damage All hand tools should be inspected before its use for damage.

Hose pipe should be inspected periodically and also before its use for any
leakage and damage.
Damage hose pipe Air leak
Fixing of Bulker to Air Blower for Pressue gauge should be in working condition. All moving parts should be
4 guarded properly.
unloading the Cement / Fly Ash
Ensure that cement should be fill to its defined mark.

Provide level indicator.

Provide caution sign board.

Improper feeding Spread of Cement dust Entry of personnel is strictly restricted in the area of feeding.

Hand wash and eye wash facility should be provide.

Work area shall be barricated.

Work Shall be carried out under contineuous Supervision.

5 Removing of Bulker from Air Blower Un-inspected hand tools Personal injury Property damage All hand tools should be inspected before its use for damage.

6 Work during night hrs. Unadequate illumination Darkness Adequate illumination should be provided during night hrs.
Conduting Mock-Drill For emmergency preparednace
7 In case of Emmergency Confusion Personal Injury Emmergency path way and Assembly Point shall be clean and clear.
Emmergency communication and Emmergency contact nos. should be displayed.

Name & Signature of Site Engineer / Supervisor :___________ Name & Signature of Site In-charge :___________

Name & Signature of Project In-charge :__________ Name & Signature of HSE Officer : ______