You are on page 1of 96

SEWAGE TREATMENT PLANT - STP

TECHNICAL SPECIFICATIONS
I) TECHNICAL SPECIFICATIONS:
1.0 OPERATING PRINCIPLE:

In order to conserve water, Sewage Treatment Plant has been designed to ensure that treated
effluent (water) characteristics are well below the permissible limits of local/national pollution
control norms even under varying flow conditions which are typical for such systems. This
implies that the selected process shall be able to withstand the shock load situation.

The sewage treatment plant has been designed Total Capacity 500 m3/day (2 x 250 m3/day)
capacity to handle of soil and toilet waste, including kitchen waste. Entire sewage treatment plant
is underground & consists of Collection cum Equalization Tank with submersible pumps, SBR
tanks, sludge holding tank and Intermediate water storage tank, Bypass Pump, drainage pump
for plant room drainage, Tertiary treatment comprising of filter feed pump, multigrade pressure
sand filter, activated carbon filter Softening plant with & softener with brine tank, Ultrafiltration
system, pipe and fitting, valves and associate electrical works.

The sewage treatment plan has been designed for the following characteristics:-

■ RAW SEWAGE (INFLUENT) / TREATED EFFLUENT CHARACTERISTICS:

a) The STP shall be designed based on the following parameters:

 Daily average flow : 500 KLD (2 Nos. x 250 KLD)

 pH : 6.5 - 8.5

 BOD5 : 250 - 350 mg/l

 S. Solids : 250 - 300 Mg/l

 COD : 600 - 800 mg/l

 Oil & Grease : Upto 50 mg/l

b) Effluent Discharge Parameter :-

 pH : 5.5 - 9.0

 BOD : less than 10 mg/l

 COD : Less than 50 mg/l

 Total Nitrogen : Less than 10 mg/L

 Dissolved Phosphares : Less than 1 mg/L

 TSS : Not more than 10 mg/l

 Fecal Coliform (FC) : 100 MPN/100 ml

TS-1
Component – I [Pre Treatment]:

• Screen Chambers.
• Oil & Grease removal chamber.
• Collection cum Equalization Tank
• Solids handling sewage transfer pumps.
• Bypass pump from equalization tank to municipal sewer.

Component – II [Secondary / Biological Treatment] :

• Anoxic Tank
• SBR Tanks
• Intermediate water storage Tank
• Sludge Holding Tank
• Sludge recirculation pump
• Filter Press complete with Filter Press Feed Pumps

Component – III [Tertiary Treatment]:

• Filter Feed Pumps


• Multigrade pressure Sand Filter
• Activated Carbon Filter
• Ultrafiltration feed cum Irrigation Water Storage Tank
• Irrigation Water Transfer pump (VFD Based)
• Flushing Water Transfer Pump (VFD Based)
• Softener feed pump
• Water Softener with brine tank
• Soft water storage tank
• Soft Water Transfer Pump
• Ultrafiltration system with UF feed & UF Back Wash Pump

 PROCESS DESCRIPTION:

a) Sewage generated from various sources including waste water generated from the kitchen &
pantry after passing through a oil & grease trap will be carried through battery of manholes inter
connected through soil pipes under gravity flow and will be collected in the collection cum
equalization tank after passing through screen chambers near the STP.
b) Manually cleaned bar screens will be installed in the screen chamber to screen of any large
pieces.

c) Coarse bubble aeration system will be provided to keep the sewage in homogeneous condition.

d) From the Collection cum Equalization Tank, the waste water will be pumped via submersible
solids handling pumps into adjoining SBR tanks.
e) Screened Sewage shall be fed into the SBR Process tanks for biological treatment to remove
BOD, COD, Suspended solids, Nitrogen and Phosphorous.
f) It shall perform biological organic removal, Nitrification, De-Nitrification and Phosphorous
removal. It shall be capable of simultaneous sludge stabilization. The oxygen required shall be
supplied through diffused aeration system. The system shall have a SVI <120 for higher setting
rates and shall be designed in such a way that growth of filamentious bacteria is restricted.
Complete operation of SBR including decanting rate, Sludge Recirculation and wasting of excels
sludge shall be controlled by PLC.

g) Compressed air will be supplied through positive displacement twin lobe type air blowers for
collection cum equalization tank, sludge holding tank & SBR Tanks.

h) Treated waste water after Intermediate water storage tank will be clear, odourless, low BOD, low

TS-2
suspended solids.

i) For improving the treated waste water quality, treated waste water after Intermediate tank will be
passed through multigrade Pressure Sand Filter followed by Activated Carbon Filter for further
reduction of Suspended Solids, BOD, COD, etc. so as to make it suitable for Irrigation purpose /
ultrafiltration process.

j) Treated water after filtration system will be clear, odorless, low BOD, low suspended solids.

k) The Treated Water after Filtration process will be collected / stored in the Ultrafiltration feed cum
Irrigation Water Storage tank.

l) VFD based Flushing Water transfer pump shall be provided to transfer the Flushing Water from
UG Storage tank to overhead flushing water storage tank of respective buildings.

m) VFD based Irrigation Water Transfer Pumps shall be provided along with pressure sensor system
for Irrigation water supply distribution system for Landscape Area, Planter & Green Area.

n) Soft Water Transfer Pumps shall be provided for Soft water supply distribution system For
Cooling Tower Make up.

o) Sludge Dewatering:

Sludge Dewatering comprising of following components :-


[a] Sludge Holding tank
[b] Filter Press Feed Pump / Screw Pump
[c] Filter Press
[d] Poly dosing System.

p) Excess Sludge from bottom of SBR tanks will be transfer to the Sludge Holding tank through the
Sludge Recirculation Pump. Diffused Aeration shall be provided in the tank for Aerobic digestion
of Sludge.

q) Sludge shall be transferred to Filter Press through Filter Press Feed Pump / Screw Pump.

r) Sludge dewatering process (separation of Sludge (solid) and liquid (water)] shall be carried
through Filter Press and form a Filter cake (dewatered sludge) which shall be used in Manure.

Re-Use & Disposal of Treated Effluent

Considering the site planning and various conditions of the project, the various opting available
for re-use of the treated wastewater from the Sewage Treatment Plant are:

 Flushing Purpose

Use for Flushing purpose for Water Closet (WC) and Urinals: The Treated Effluent from Flushing
Water Storage Tank pumped into the Flushing Water overhead water tank through water lifting
pumps and supplied to all WC & Urinals through gravity system.

 Horticulture Purpose

Use for horticultural purposes in the campus for watering the lawn hydrants and planters etc. The
treated effluent from the STP shall be pumped into the Garden Hydrant Ring, which shall be laid
for the entire site.

 Make-up Water Cooling Tower make up


Use for make-up water for Cooling Towers: The treated effluent from the STP shall be used for
make-up water tank for Cooling Towers purpose by providing water softener / Brine tank and soft
water Lifting Pumps and Distribution System.

TS-3
SPECIFICATION FOR WATER SUPPLY PUMPS :

2.0 PUMPING SETS FOR FILTER FEED PUMPS/SOFTENER FEED PUMP/SOFT WATER
LIFTING PUMP & ULTRA FILTRATION FEED AND BACKWASH PUMPS:

a) The pump shall be horizontal/vertical, single stage/multistage, monoblock/ end suction/back pull-
out design with axial suction port and radial discharge part/inlet & outlet parts are the same level
(line).
b) Material of construction (MoC) :
1. Pump Housing : Cast Iron
2. Pump Impeller : Stainless steel SS-304
3. Pump Shaft : Stainless steel SS-304
c) The shaft, impeller and chambers shall be made of stainless steel.
d) The inlet and discharge point shall be made of cast iron.
e) Water supply pump speed shall be 2900 rpm.
f) Each pump shall be provided with a totally enclosed fan cooled induction motor of suitable HP.
g) The Motor shall be suitable for 415± 10% volts, 3 phase, 50 Hz cycles AC Power supply.
h) IE Efficiency class shall be IE2 as per international standards.
i) The pump set shall be provided with Mechanical shaft seal.
j) Encloser class (IEC-34-5) for Electrical motor shall be IP55.
k) Insulation class (IEC85) of Electrical motor shall be ‘F’ class.
l) Performance curve tolerance shall be as per ISO 9906 : 2012 3B.
m) Maximum operating pressure/pressure rating shall be PN10/PN16 (10.0 Kg./Cm2 and 16.0
Kg./Cm2).
n) Flange standard shall be DIN/EN.
o) Each pump shall be provided with Isolation valve (Ball valve/Butterfly valve) on suction & delivery
pipe of pumping set.
p) Each pumping set shall be provided with Non Return valve on Delivery pipe of pump.
q) Each pumping set shall be provided with 63 mm size ‘Bourdon’ type pressure gauge with
Forged/Brass ball valve with inter connection piping.
r) Pump or the whole set shall be stable on rubber vibration eliminating pads appropriate for each
pump as recommended by the Manufacturer and accepted by Project Manager.
s) Contractor shall submit the following Technical submittal for Consultant approval.
1. Technical Data sheet.
2. Performance curve duly marked with duty parameter.
3. Dimension detail.
4. GA/Foundation drawing.
5. Electrical Motor detail (Technical Data sheet).
6. Manufacturer Technical catalogue.

TS-4
3.0 VARIABLE SPEED HYDOPENUMATIC SYSTEM FOR FLUSHING OHT FILLING &
IRRIGATION WATER SUPPLY DISTRIBUTION SYSTEM:

3.1 General :

• This section of the specification covers the supply, installation, testing, commissioning of the
Variable Speed Hydropneumatic Booster system.

• Booster should consist of the components as per the below specifications as Minimum.

• Complete system shall be tested at the manufacturer’s local factory, in accordance to the
provisions of the appropriate standard before delivery.

• Manufacturer should have facility of witness test with proper test bed.

3.2 System Descriptions:

• The variable speed booster system shall be supplied and installed as designed.

• The system shall comprise of number of pumps, as mentioned in BOQ, in parallel and it shall be
a package system manufactured by the manufacturer of the pumps at their factory.

• System assembled by the dealers locally will not be accepted. The system shall consist of:

• Vertical In Line Multistage Centrifugal pumps. The quantity shall be as per BOQ.

• Variable Frequency Drives (VFD). The quantity shall be as per BOQ.

• Pre-pressurized bladder or diaphragm type pressure vessel complete with pre-charged nitrogen
gas to the design pressure settings.

• Control panel complete with MCCB, MCB, fuses, microprocessor based dedicated Pump Logic
with built in graphical display as per manufacturer.

• Pipe work and valves, pressure transmitter, pressure gauge, check valve, ball valve/gate valve
and all necessary fittings etc to the satisfactory operation of the system and to make system as
complete. Only supply & delivery line will be connected to start the system.

• All these components should be as per the specifications written in 3.3.

3.3 Components of Variable Speed Booster:

3.3.1 Pumps and Motors:

3.3.1.1 Type of Pump:

• The pump shall be of approved make of vertical-in-line /horizontal multistage centrifugal type
suitable for speed up to 2900 rpm.

• The suction and discharge port shall be in line with each other. The maximum operating liquid
temperature for the pump shall be up to 120 deg C.

• The motors shall be vertically stool mounted on top of the pump casing and the pump casing shall
be designed to take the dynamic load of the motor. The motor shall be provided with thrust
bearing to cater for the downward thrust of the pump.

• The manufacturer of the pump should have a local factory with at least 5 years of experience and
able to provide after sales service. The factory must have a pump testing facilities with approved
test bed to carry out pump as well as complete booster performance witness testing.

TS-5
3.3.1.2 Pump Selection :

 Each pump shall have the stable characteristics and the operating point shall fall within the
acceptable range on the pump curve. Duty point should not be selected at extreme right or left
side of the curve.

 The pump performance curve shall be complying with the tolerance according to ISO 9906,
Annex A.

3.3.1.3 Pump Head and Base :

 The motor terminal housing shall be of a completely watertight design with tight cable glands to
prevent ingress of water. For bigger motor, the housing shall have provision for the lubrication of
the motor bearing to enable the pump to run effectively with only periodic withdrawal for
maintenance and lubrications, if required.

 For motor sizes more than 7.5 kw, extended coupling should be provided to enable the changing
of the mechanical shaft seal without the need to lift up or dismantling of the motor. For pumps up
to 7.5 Kw mechanical seal should be changeable without dismantling/opening pump.

3.3.1.4 Shaft, Impeller and Guide Vanes :

 All the inter stage components (impeller, intermediate chambers, diffusers) as well as sleeves
and guide vanes shall be made of stainless steel 304 material.

 The impeller shall be fitted to a rounded shaft with split cone and split cone nut to prevent the
stages of the pump been collapsed. For smaller pumps splined shaft is acceptable.

3.3.1.5 Mechanical Seal :

 The mechanical shaft seal shall be of cartridges type with seal faces of silicon carbide material.

 It should be possible to change mechanical seal without opening the pump to reduce downtime.

3.3.1.6 Motor :

• The electric motor shall be of total enclosed fan cooled (TEFC) squirrel cage induction type
suitable for operation on a 415V / 3 ph/ 50 Hz voltage supply. The motor shall be designed based
on 40 deg C ambient temperature and up to a maximum of 2900 rpm. The motor shall be of class
F insulation and a minimum of IP 55 enclosure with a maximum surface temperature of 120 deg
C.

• The motor shall comply with the requirement of BS 4999 or other compatible IEC standard.

• All motors shall be sized for pump operation based on non-overloading conditions for the full QH
curve. The motor shall also be suitable for at least 40 start/stop per hour.

• Direct on line starting method is required for motor up to 5.5 kw and star delta starting is required
from 7.5 kw onwards.

All motor should be of minimum Class – I efficiency.

3.3.2 Variable Frequency Drives (VFD) :

• VFD shall be Pulse Width Modulation (PWM) type, microprocessor controlled design labelled as
CE. Drive shall have customer modifiable adjustments of 2 to 600 seconds accel & decel time,
Minimum & Maximum frequency, V/I ratio and Carrier frequency. Speed reference signal shall be
customer selectable for 4-20 mA, 0-5 VDC and 0-10 VDC. The VFD shall be suitable for
elevations up to 1005 meters above sea level without de-rating. Maximum operating ambient

TS-6
temperature shall be to 45 Deg C. shall be suitable for environment condition up to 95% non-
condensing.

• Built-in DC link filters to avoid power factor correcting devices like Capacitors, line reactors etc.,

• Energy saving mode with boost function (Sleep/ Wake Mode), Quick set up menu.

• VFD should be mounted inside the panel cabinet.

3.3.3 Dedicated Pump Logic Controller (PLC):

PLC should be as per pump manufacturer standard. General purpose PLC programmed for
boosting application will not be accepted by contractor separately.

The microprocessor controller based Pump Logic controller (PLC) shall be of standard software
configure type

a) The PLC should have the following features as minimum:

 Built-in PI-controller.

 External input signal both digital and analog.


 Alarm output.
 Operation output.
 Graphical Display VGA 240 x 320 pixels.
 Ethernet connection port (RJ 45).
 External BUS communication port.
 Service port.
 Built-in HELP TEXT.
 Built-in start up wizard.
 Upgradeable soft ware program.
 Back light for specific button to be light up only when applicable.
 Backlight to be dimmed when not used for more the 15 min.
 Adjustable contrast for display.
 Selectable service language.
 Selectable units between SI and US.
 Manual entry of pumps data.
 Primary and Standby sensors.
 Data logging.

b) The PLC should be able to perform the following functions as minimum:

 Selectable auto/manual mode for both system and individual pump from Controller
 Selectable pump speed (user define speed in %)
 Max speed
 Min speed
 Set point influence
 Additional set point up to 6 set point
 Adjustable number of start/stop
 Adjustable system time and error correction value
 Adjustable ON/OFF band (stop function)
 Selectable number of standby pump(s)
 Pump test function
 Security setting with pass word for operation and setting
 External fault input
 Selectable dry running protection for either digital or analog signal
 Selectable auto/manual reset for dry running protection
 Selectable open/close loop operation
c) The PLC should be able to display the following alarms, whenever it occurs:

TS-7
 Alarm log up to 24 event
 Time and date of log alarm
 Current alarm with alarm code and description
 Water shortage
 Max pressure
 Min pressure
 Alarm all pump
 External Fault
 Dissimilar sensor
 Primary sensor
 Fault sensor
 Communication fault
 Over temperature, pump
 Other fault, pump
 VFD not ready
 Fault, Ethernet

d) The PLC should be able to display the following values :

 System status
 Individual pump status
 Pump hour run
 Individual pump speed
 Set pressure
 Actual pressure
 Date and Time
 Menu code and sub code for individual display

3.3.4 Control Panel:

The panel shall be equipped with all the necessary electrical components, VFD and the PLC, as
mentioned above. The control panel and the PLC shall cover the following functions as minimum:

a) Flexibility and simplicity in allowing the necessary re-adjustment of the booster system delivery
pressure to operate the pumps within the specified maximum and minimum delivery ranges
including built in set up wizard and help text.

b) Built-in frictional loss compensation or influence factor, which will automatically increase the
delivery pressure setting according to the increase in flow demand. This shall be able to minimize
the system pressure differences and provide a more constant pressure in the supply line. This is
also to save the energy consumption of the motor when running and low speed.

c) Automatic changeover of the pumps to be controlled by the PLC to ensure equal running of all
the pumps.

d) When the system is not operating for more than 24 hours, it shall automatically start the pumps
for a few seconds per day. This will ensure the readiness of all the pumps at all times. The
standby pumps shall be activated upon failure of duty pump. In the event of PLC failure, the
pumps shall be able to start/stop manually.

e) The PLC shall be able to cut off the booster system when excess pressure in the discharge
common manifold is registered (maximum limit provision). In a reverse situation, the PLC panel
shall be able to cut off the booster system when low pressure in the common suction manifold is
registered (minimum limit).

f) Capability of receiving either analogue or digital input signal concerning shortage of water supply,
preventing the pumps from dry running.

g) It should automatically start the pumps when the level is back to normal.

TS-8
h) In case of pump failure due to motor overload, the standby pump is switched on automatically.
Alarm signal is displayed on the VGA Display unit and alarm lights are activated.

i) The control panel door shall be displayed with at least the following components:

• Graphical display as per manufacturer standard

• Pumps selections up to 6 pumps

• Pump status button (including individual pump speed, system Pressure and estimated flow rate)

• System status, alarm, operation & setting button

• Additional Buttons for changing values, accepting changes, help For scrolling data etc

j) Connection for necessary devices for programming, supervising and monitoring operation
data/system, status shall be incorporated into the panel/ PLC.

k) Pump Selector Mode

Selection should be provided to enable any pump to be the lead pump, first duty pump, second
duty pump and standby pump as desired. There shall be alternating mode selection too, where
all pumps are operated cyclically upon each call for pumping.

l) Pump Isolation

It shall be possible to isolate any pump for maintenance without affecting the performance of the
system in the automatic mode.

m) Alarm

Alarm should be displayed in case of any problem. Alarms should be as per details given in PLC
section.

All panels/controllers shall be tested at the factory according to the procedures stipulated, before
dispatch. The manufacturer shall carry all spare-parts for the controllers. All spares of the
controllers shall be readily available for a minimum period of 10 years after the production of the
particular model of controller has been discontinued.

3.3.5 Hydro Pneumatic Pressure Tank:

The hydro-pneumatic tank shall be of bladder or diaphragm type with pre-pressurized


air/nitrogen. It shall be capable of handling the designed effective system protection
(ESP) Volume to protect pump and operating controls by ensuring that the actual pump
operation conform to the manufacturer's specified minimum running time and maintaining
the designed pressure range.

The shell shall be constructed with deep-drawn carbon steel.

The diaphragm/membrane shall be of heavy-duty type. This diaphragm/membrane should


be the only component in contact with the liquid.

The tank shall have a maximum operating pressure of 10 bars and shall be able to handle
a maximum liquid temperature of 90oC.

TS-9
3.3.6 Pressure Transmitter:

Pressure transmitters shall be field mounted and shall transmit an isolated 4-20mA DC signal
indicative of process variable to the pump logic controller via standard two wire 24 DC system.
Unit shall have stainless steel wetted parts and it should be installed at the discharge header. It
should have watertight, electrical enclosure capable of withstanding minimum 10 bar static
pressure.

3.3.7 Headers & Accessories:

The suction and discharge manifolds shall be of Hot Dipped Galvanized MS. Both manifolds shall
be designed to attach to the system piping at either end of the manifold. Delivery manifold shall
include a pressure gauge. The discharge manifold shall include a socket to install a pressure
transducer with a 4-20mA output. The pressure transducer shall be factory installed and wired.

Isolation valves shall be installed on the suction and discharge of each pump. A check valve shall
be installed on the discharge of each pump (optional on the suction side for suction lift
applications). Base frame should also be made of galvanized sheet.

3.4 Booster System Working:

The system shall be under the control of a microprocessor based pump logic controller (PLC). 2
nos. of pressure transmitter (primary and standby) shall be incorporated into the system to detect
the pressure at the discharge manifold and feedback to the PLC.

The system shall maintain a constant pressure at all times regardless of the system demand. The
activation of the next duty pump in a high demand situation shall not base on a different set point.
However the PLC should have a flow test function to determine the numbers of pumps in
operation and a stop function into the controller to stop all pumps from operation, whenever there
is no demand, which prevent and reduce wear and tear of the system as well as reduce energy
consumption. The controller shall also ensure alternation of all pumps for even running hours.

The lead pump shall operate when the system pressure reduces to the preset point. If demand
escalates, the lag pumps shall commence operation as required. During next operation lead
pump to become lag and lag pump to become lead pump automatically. The system shall vary
the frequency of each pump (in case of multi VFD system) and it will be equalized to ensure
smooth operation to meet the specific demand. Under decreasing hydraulic demand, the reverse
to the above description shall apply.

Operations

The control circuit shall enable automatic and manual operations of the system.

a) Automatic Operation

Everything will be controlled by PLC in this case.

b) Manual Operation

Either one or all pumps shall be capable of being started and stopped by their respective push
buttons or MCB’s.

The control panel should have starters for this purpose

TS-10
4.0 SUBMERSIBLE SEWAGE & DRAINAGE PUMPS:

4.1 Submersible pumps for sewerage & drainage shall be Non-clog, Non-self-priming, single stage
centrifugal pump design for handling Raw sewage & drainage application.

4.2 The pump shall be designed for intermittent and continuous operation and submerged
installation.

4.3 The vane for Sewage pump will be open type, while for drainage pump etc. it will be of semi open
type.

4.4 The pump shall be equipped with grinder system having Grinder type impeller that grinds
distractible solids in small pieces so that they can be led away through pipes of relatively small
diameter.

4.5 Single Mechanical Seal shall be provided. Primary shaft seal shall be of SCI/SCI and secondary
shaft seal shall be of carbon/ceramic material.

4.6 Solid Handling/Free Passage


a) Drainage pumps – 10mm Particle size.
b) Sewage pump – 30-40mm maximum particle size.

4.7 Curve tolerance shall be as per ISO 9906: 2012 3132.

4.8 Pressure rating shall be PN10 (maximum).

4.9 Flange Standard shall be DIN Standard.

4.10 Material of construction (MoC)


a) Pump housing : Cast iron (CI)
b) Impeller : Cast iron (CI)
c) Shaft : Stainless steel (SS 304)

4.11 Electrical Motor


4.11.1 Each Pump shall be provided with Water cooled squirrel cage induction motor suitable for 415
volts, 3 phase, 50 Hz cycles AC Power supply.

4.11.2 Voltage tolerance shall be ± 10% volts or as per selected Model number.

4.11.3 Maximum starts per hour shall be 20-30 starts/hour or as per selected Model number.

4.11.4 Start Method shall be direct-on-line [DOL].

4.11.5 Rated speed shall be maximum 2900 rpm.

4.11.6 Encloser class (IEC 34.5) shall be IP 68.

4.11.7 Insulation class (IEC85) shall be class ‘F’ or as per manufacturer recommendation.

4.11.8 The pumping set shall be provided with 10 meter length of cable.

4.11.9 The pump shall be equipped with temperature bi metal sensor thermal switch for Motor protection
in case of overheating or as per manufacturer recommendation.
4.12 Each pump shall be provided with liquid level controller for operating the pump between
predetermined levels.
4.13 Installation – Auto coupling system or chain pully system.

4.14 Pump shall be provided with all accessories and devices necessary and required for the pump to
make the complete working system.

TS-11
5.0 SLUDGE RECIRCULATION PUMP:

5.1 Sludge Recirculation pump shall be Horizontal suction type centrifugal sludge disposal pump.

5.2 Pump shall be provided with Non- clog impeller to handle the suspended solids.

5.3 Solid handling size shall be 7mm–10mm or as per selected model number/Manufacturer
recommendation.

5.4 Pump shall be quick automatic self priming action. Design for automatic air release during
priming.

5.5 Material of construction shall be cast iron body, cast iron impeller, stainless steel shaft.

5.6 Rated speed shall be 2300 RPM.

5.7 Each pumping set should be provided with 63 mm dia gun metal “Bourdon“ type pressure gauge
with gun metal ball/forged valve and connecting piping.

5.8 Pump or the whole set shall be stable on rubber vibration eliminating pads appropriate for each
pump as recommended by the manufacture and accepted by the Project Managers.

5.9 Each Pump shall be provided with totally enclosed fan cooled induction motor of suitable HP. The
motor shall be suitable for 415 ± 10% volts, 3phase, 50 cycles AC Power supply and shall
conform to IS: 325 operating at 2300 RPM rated speed.

5.10 Stuffing Box arrangement with Mechanical seal shall be provided.

6.0 CHEMICAL DOSING PUMP :

6.1 Chemical dosing system comprising of metering pump, 100 ltr. Capacity HDPE Chemical Grade
Tank with level gauge and lid on top.

6.2 Motor driven metering pump with mechanically activated diaphragm. The output of the plug
should be adjustable operation from 10-100%. Pump construction shall be corrosion resistant
polypropylene or similar material dosing pump.

6.3 Each pump shall be provided with an injector assembly with suction and delivery piping complete
in all respects.

7.0 FILTER PRESS FEED PUMPS / SCREW PUMP:

7.1 These pumps shall be used for pumping sludge to Filter press. The pumps shall be designed to
operate satisfactorily without detrimental surges, vibration, noise, or dynamic imbalance. Over the
required head range, the head-capacity curve of the pump shall have a continuously rising head
characteristic with decreasing capacity over the whole range of total head. The pump shall have
the maximum efficiency at the specified duty point. The unit shall be designed to operate safely at
the maximum speed attainable in the reverse direction of rotation due to sewage returning
through the pump at times when power supply of the motor is interrupted. The first critical speed
of the pump set shall be at least 30% above the operating speed.

7.2 The pumps shall run smooth without undue noise and vibration. The velocity of vibration shall be
within 4.5 mm/sec. The noise level shall be limited to 85 dBA at a distance of 1.86 m.

7.3 All rotating parts shall be statically and dynamically balanced as per ISO standards.

7.4 A stationary coupling guard shall be provided for the coupling conforming to all relevant safety
codes and regulations. Guards shall be designed for easy installation and removal. They shall be
complete with necessary support accessories and fastener.

TS-12
7.5 The pumping unit shall be provided with a common base plate. The base plate shall be of
sufficient size and rigidity to maintain the pump and motor in proper alignment and position.

7.6 The pump design shall be as per IS 6595 and pump performance shall be as per IS 9137.

7.7 The power rating of the pump motor shall be the larger of following

(i) 115% of power required by the pump at the duty point


(ii) 110% of maximum power required by pump from zero discharge to runoff point total head

7.8 Material of Construction

[a] Pump casing : Cast Iron (CI)


[b] Rotor : SS-304
[c] Shaft : Stainless Steel-410
[d] Sealing : Gland Packing
[e] Stator : EPDM rubber
[f] Base Plate : MS epoxy painted

7.9 Parameters of Pump

[a] Capacity : As per BOQ


[b] Head : To pump to Filter press or As per BOQ
[c] Efficiency : Minimum 30 %
[d] Pump speed : 960 rpm (maximum)
[e] Ball passing size: 25 mm minimum

Applicable code

Design : IS 6595
Performance : IS 9137

7.10 Testing

[a] Material test certificate : Casing, Impeller, Shaft


[b] Hydrostatic test : 1.5 times shutoff head or twice the rated head

[c] Discharge head : whichever is greater

[d] Performance test : IS 5120 and IS 9137 at full speed

[e] Mechanical balancing : As per ISO 1940, Gr. 6.3 or better


Pump shall be offered for visual inspection
[f] Visual inspection : before shipment. The pump components shall
not be painted before inspection.
Field performance tests required for satisfactory
[g] Field Tests
operation

8.0 BLOWERS AND AERATION SYSTEM:

8.1 Blower shall be of the rotary positive displacement type (Twin Lobe Type Air Blower).

8.2 Each Blower shall be provided with Suction filter and Silencer, Pressure gauges, Pressure relief
valve (Safety valve), drain, and air flow indicator.

8.3 Bearing housing and gear boxes shall be separated from the blower housings by air spaces.

TS-13
8.4 Bearing at the drive end may be oil or grease lubricated. The gears and bearings at the non-drive
end shall be oil lubricated.

8.5 The noise level shall not exceed 85 dBA at 3 meters from the Blower.

8.6 Each blower shall be provided with following components but not limited to

a) Suction (inlet) Air filter


b) Suction (inlet) Silencer
c) Pressure gauge with Isolation cock
d) Pressure Relief valve/Safety valve (Spring loaded type)
e) Non-Return valve on delivery line
f) Isolation valve/Butterfly valve in both inlet and delivery branch.
g) Common base frame for Electrical motor & blower
h) Belt guard/coupling guard
i) Bellows type coupling on inlet and delivery branches
j) Pulleys & Vee belt coupling.
k) The interconnecting piping work shall be flanged to GI pipes of class ‘C’ (heavy duty)
conforming to IS 1239.
l) A drain cock shall be provided at the lowest point in each delivery pipe work along with valve.
m) Individual stop valve and safety valves shall be provided for each unit.
n) Blower shall be driven by squirrel cage induction type electrical motor through V-belt.

8.7 Material of Construction (MoC):

[a] Main Casing, Side Plates and Rotor : Cast Iron (CI) Gr. FG 200 IS : 210 (1993).

[b] Shaft : EN 19 (BS 970 : 1955)

[c] Gears : 20 Mn CR5 / 16 Mn CR 5 / BS 970 – 3 / AISI S120,


Hardened & ground

[d] Seals : Lip seals

[e] Bearing : Anti friction

[f] Base frame : MS Fabricated

8.8 Performance Testing:

Performance testing as per Standard procedure STP-01 based on BS 1571-2: 1975 and ISO
1217: 2009.

8.9 Construction Features included the following:

• 100% oil free delivery.


• Factory engineered, Factory Assembled.
• Rotary oil sealing.
• Anti-friction bearing.
• Air cooled design.
• Easy rotor time setting.
• Extended shaft design for cool running.
• Dynamically balanced rotor shaft assembly (Grade 10.3 ISO 1940 – 1986).
• Large Inlet & outlet connections for minimal loss.
• Higher Efficiency
• Low power consumption
• All major component shall be Interchangeable.

8.10 Blower Operation:

TS-14
8.10.1 The Air Blowers shall be of such design as to achieve energy efficient operation continuously
over the range of design airflow rates at the discharge pressure that shall remain practically
constant.

8.10.2 Air Blower shall be fitted with a variable speed motor and be capable of operating between 80%
and 110% of its nominal peak airflow demand.

8.10.3 Actual blower head/discharge pressure head & selection to be finalized by STP Contractor based
on the Final STP Civil construction drawing to suit the actual water level of the process tank and
of the delivery manifold.

8.10.4 Design mass flow rate at maximum inlet temperature shall be as per Air Blower Manufacturer
guide line/recommendation.

8.10.5 The blower unit shall be capable to operate at maximum duty for continuous operation.

8.10.6 The blower motor and blower shall not exceed the manufacturer’s recommended maximum
speed.

8.10.7 A blower removal system shall be provided so that any one blower can be removed as single unit.

8.10.8 The contractor shall submit the following document/drawing for Consultant approval

a) Technical Datasheet for Twin Lobe Type Air Blower/Electrical Motor.


b) Manufacturer catalogue/technical detail.
c) Performance curve of blower of selected Model number.
d) Performance table duly highlighted the duty points.
e) GA drawing reflecting the dimension detail/foundation sizes.
f) Standard certified factory test sheet showing the results of each test shall be supplied in
triplicate to the consultant along with delivery of the blower.

8.10.9 Low Flow Switch

8.10.9.1A low air flow switch is located on the discharge of each air blower, for blower protection.

8.10.9.2If the switch is active, an alarm occurs and the PLC changes the lead to the next available
blower.

8.10.9.3If there is no other blower available, a different alarm occurs and PLC shuts down the respective
train.

8.11 Ancillary Equipment:

8.11.1 The blowers shall be providing with the usual ancillary equipment for aeration duty, including:-

a) Discharge pressure relief valve.

b) Discharge check valve.

c) Discharge isolation valves.

d) Vacuum switch, pressure switch, oil level indicator and any other mounting devices shall be
mounted outside the acoustic enclosure (Note: Provision & installation of vacuum switch to
be confirmed by blower manufacturer).

e) Pressure gauge with Isolation cock on delivery line of each blower.


f) Vibration observation mounting pads.

g) All required/support structure.

TS-15
8.12 Suction (Inlet) Filter:

Filters shall be used to remove dust, etc. contained in the suction air. For this purpose, a filter
shall be mounted directly to the suction silencer of each blower. The filter element shall be non-
textile cloth or equivalent, and the element passage speed shall be 2 m/s max. The Contractor
shall indicate the useful life period for the diffuser. (b) The blowers shall receive filtered air
individual replaceable filter elements suitable for the intended duty. (c) The filter elements shall be
housed in an airtight housing which shall allow easy replacement of the filter elements.
Replacement of elements shall be possible without the use of tools. (d) If the filter/silencer
elements supplied are located out of doors a weatherproof cover shall protect the filter element
from rain. (e) The filter unit shall be fitted with suitable vacuum gauges to indicate the suction
pressure into each blower. The gauges shall be industrial Bourdon of Schaffer type gauges with a
nominal diameter of 150 mm. The scale shall be suitably selected and shall include a red line to
indicate the point at which the filter elements require renewal. (f) Each blower intake shall be
fitted with a differential pressure switch, which shall indicate an alarm signal in the event of
excessive pressure drop in the blower intake.

8.12.1 Provision & installation shall be as per Manufacturer guide line & recommendation.

8.12.2 Provision & installation of vacuum gauge & differential pressure switch shall be as per
manufacturer operation & maintenance guide line /manual/recommendation.

8.13 Flexible Sleeve:

8.13.1 The blower discharge shall be fitted with an approved flexible sleeve with fixing clamps and a
flanged outlet spigot for connection to site pipe work. If the blower inlet is via a common plenum
the inlet pipe shall be also fitted with a flexible connection. Flanges shall be drilled to Table D
and shall comply with the required standard. Sleeves shall be manufactured from an approved
non-metallic material suitable for the duty and location in which the blowers are to be installed.

8.14 Pressure Relief Valve/Safety Valve:

8.14.1 The pressure relief valve shall be sized and adjusted to allow the full flow of the blower to be
discharged in the event of a blockage or valve closure in the downstream pipeline and without
overloading the drive motor. Each blower shall be fitted with a suitable pressure switch, which
shall shut down the blower in the event of excessive discharge pressure. The pressure setting
shall be lower than the set pressure of the pressure relief valves. The pressure relief valve shall
be installed at a height above 2m from the floor and away from blower suction point. The
pressure relief valve shall be fitted with a silencer.

8.15 Non-Return Valve (NRV)

8.15.1 A non-return valve shall be installed on the discharge pipe work of each blower, upstream of the
blower isolation valve.

8.16 Isolation Valve/Butterfly Valve

8.16.1 Isolating valves shall be installed on the delivery pipe work of the blowers; such that each blower
and all associated pipe work and valves upstream of the common distribution manifold can be
dismantled without disruption to the normal operation of the plant.
8.17 Temperature Sensor

8.17.1 Temperature sensor complete with gauge of an approved type shall be supplied for each main
distribution pipe work and for the blower room.

8.17.2 Provision & installation of temperature sensor with gauge shall be as per manufacturer operation
& maintenance guide line/recommendation.

8.18 AIR PIPING:

TS-16
8.18.1 The pipe works, instrumentation and the diffusers shall be correctly sized to deliver the required
quantity of air at the available pressure to meet all operating conditions.

8.18.2 The pipe work to the tank shall be sized for 125% of the required oxygen transfer capacity to
cater for the higher loading.

8.18.3 The aeration headers shall be designed for removal/replacement from/to the reactor tank without
taking the reactor off-line or dewatering the reactor.

8.18.4 The Contractor shall be required to demonstrate removal and replacement of the headers with
the reactor on-line.

8.18.5 All air piping from the blower-motor unit to the air header shall be MS class ‘C’ Epoxy pipe with
flexible reinforced rubber connecting sleeves shall be provided wherever required.

8.18.6 The air supply headers shall run from the main air distribution pipe work to the down comers.
Pipe work shall have inbuilt flexibility such as packer flanges for future modifications and to allow
for reasonable construction tolerances on the structures to which it is attached. An isolation valve
for each main air supply pipe shall be installed at the point of connection to the main distribution
pipe work. The design of the main air supply header shall incorporate all components necessary
to enable the easy connection of the main distribution pipe work to the main air supply header.

8.18.7 UPVC Schedule-40 pipe & fitting shall be provided for submerged air piping installation.

8.18.8 Many factors need to be incorporated in the design of the air distribution pipe work to minimize
the potential of noise problems occurring.

8.18.9 Factors to be considered in the design of the air pipe work to minimize noise level shall include:

a) The diameter of the pipe work, to keep velocities low.

b) The connection of the blower discharge pipes to the manifold should be” wye”, not at right
angles.

c) No blind flange at the end of the manifold.

d) The manifold shall be designed to ensure air travels in one direction.

e) The air pipe work shall be designed to minimize changes of direction and use large radius
bends.

f) Flexible connections shall be provided between the diffuser assembly nits and the main air
supply pipe work to allow for any differential movements.
g) Expansion and contraction shall be fully allowed for in the design and installation of the air
distribution pipe work.

h) Pipe work shall have inbuilt flexibility such as packer flanges for reasonable construction
tolerances on the structures to which it is attached.

8.18.10 Pipe shall be designed to ensure the efficient operation of the aeration system and compliance
with the noise limitations.

8.18.11 All valves in the air delivery system shall be correctly selected for the duty.

8.18.12 However the air piping submerged in sewage has to be in UPVC Schedule-40 conforming to IS
specification.

TS-17
8.19 DIFFUSERS:

8.19.1 Technical Specification of Coarse Bubble Diffusers:

• Each Diffuser shall be designed to efficiently release air at the location shown on the Drawing.

• The Diffusers shall be Disc type, Non-clog, EPDM membrane based coarse diffusers.

• Material of Construction [MoC]:

[a] Diffuser Base:

(i) The Diffuser base shall be molded high rigidity Poly Propylene (PP).

(ii) The Diffuser base shall be one-piece construction and shall have ¾” NPT threads for connection
to the air header system.

[b] Diffuser Diaphragm:

The Diffuser Diaphragm Membrane shall be EPDM rubber compounded.

[c] Diaphragm Retainer Ring:

The Diaphragm Retainer Ring shall be molded PP and shall be of one-piece construction.

• Operation:

[a] The diffuser diaphragm shall be designed to open air pressure, to release air in a steady uniform
Stream of bubbles and to close when air flow to the diffuser is stopped, thus preventing back flow
of fluid and prevent clogging with solid or biomass.

[b] The diffusers shall be designed to operate at design air flow of 3.0 m3/hr with a maximum
recommended, air flow rate of 10.0 m3/hr.

[c] The diffusers diaphragm membrane shall be engineered to operate at minimum pressure drop to
deliver maximum performance at minimum energy consumption.

[d] Standard oxygen Transfer Efficiency – 10.4% per meter submergence.

8.19.2 Contractor shall submit the following Technical Submittal & Detail: -

[a] Technical Data Sheet

[b] Manufacturer Catalogue

[c] Air requirement & quantity of Diffusers.

[d] Head loss curve.

[e] Oxygen Transfer per M3 per Mts. Submergence.

[f] Diffusers Detailed Drawing (Layout Plan).

8.19.3 Technical Specification of Tubular Type Fine Bubble Diffusers:

• Each Diffusers shall be designed to efficiently release air at the location shown on the Drawing.

• The Diffusers shall be Tube type.

• Material of Construction [MoC]:

TS-18
[a] Diffuser Internal Support :

The Diffuser internal support frame shall be poly propylene (PP) pipe with stub with end
connection of 3/4" BSP suitable for connecting with pipe.

[b] Diffuser Diaphragm:

The Diffuser Diaphragm Membrane shall be EPDM / rubber compounded, PTFE Layered.

8.19.4 Technical specification of Fine bubble diffusers:

8.19.4.1 Air diffuser system consist of tube type porous membrane of Acid resistant EPDM based rubber
with diameter not exceeding 65mm diameter size, single piece injection molded PP support tube,
S.S. clamps.

8.19.4.2 Entire diffuser has to be manufactured assembled, tested in factory premises. No site work is
permitted.

8.19.4.3 Flat surfaces facing upwards as membrane surfaces shall not be accepted.

8.19.4.4 Operating temperature of membrane shall be 40°C and temperature tolerance should be + 30°C.

8.19.4.5 The bubbles produced from the diffusers are of extremely small size between 0.5 to 0.8mm (less
than 1.0mm), thus the total surface are ‘that interacts is larger and contact time of bubble is large
due to slow rise of bubbles.

8.19.4.6 Flow rate/ Through

a) Optimum : 7.5-10 M3/Hr.


b) Minimum : 2.0 M3/Hr.
c) Maximum : 10.0 M3/Hr.

8.19.4.7 Maximum allowable pressure: 0.7 Kg./Cm2

8.19.4.8 Standard oxygen transfer efficiency: 6% per meter submergence.

8.20 Fixing Arrangement

8.20.1 The diffuser will be retained in place by two clamps. It shall be fitted to the pipe lateral by CLIPIN
arrangement. The laterals are connected to a pipe header. The wetted parts of the system are
made of non-corrosive material specifically SS 304. During power shutdown at the sewage
treatment plant the membrane will contract and lose around the PP support pipe and means shall
be provided to prevent any back flow. All hardware accessories including clamps, fasteners, fan-
hooks, eye bolts, should be of SS 304 materials only.

8.21 Air Diffuser Assembly

8.21.1 Each diffuser shall consist of the following:

• Minimum 65 mm OD PP injection molded support pipe.


• Porous membrane made of EPDM based rubber lateral.
• RCC support block with SS 304 clamping.
• Flexible Hose pipe (drop pipe for each diffuser assembly)
• PP Ropes for Lifting and guide position.
• Hose clamp
• Pipe connector
• GI barrel nipple with connector for connection with pipe.

8.22 Operation:

TS-19
[a] The diffuser diaphragm shall be designed to open air pressure, to release air in a steady uniform
Stream of bubbles and during shut down conditions the membrane will contract and close around
the PP support frame. Thus preventing back flow.

[b] The diffusers shall be designed to operate at design air flow of 2.0 m3/hr with a maximum
recommended, air flow rate of 10.0 m3/hr.

[c] The diffusers diaphragm membrane shall be engineered to operate at minimum pressure drop to
deliver maximum performance at minimum energy consumption.

[d] Standard oxygen Transfer Efficiency – 10.0% per meter submergence.

8.23 Contractor shall submit the following Technical Submittal & Detail :-

[a] Technical Data Sheet

[b] Manufacturer Catalogue

[c] Air requirement & quantity of Diffusers.

[d] Head loss curve.

[e] Oxygen Transfer per M3 per Mts. Submergence.

[f] Diffusers Detailed Drawing (Layout Plan).

9.0 MULTIGRADE SAND FILTER / ACTIVATED CARBON FILTER:

9.1 Filter shall be designed in accordance with the code of unfired pressure vessel conforming to I.S.
2825.

9.2 Filter shall be multigrade Pressure sand filter/activated carbon filter may be altered to suite
contractor’s own design of the most efficient performance.

9.3 Filters shall be vertical type of diameter as specified in Bill of Quantities (BOQ). The shell and
dished ends shall be fabricated from M.S. sheet. Filter vessel shall suitable to withstand a
working pressure as given in Bill of Quantities. The shell shall have a minimum thickness of 5 mm
and dished ends 6mm or as per manufacturer recommendations.

9.4 Each filter shall have at least one pressure tight manhole cover for inspection and repairs.

9.5 Each filter shall be provided with screwed or flanged connections for inlet, outlet, individual drain
connections and all face piping, isolation valves (Ball valve / Butterfly valve) and all other
connections necessary and required.

9.6 Face piping shall be of GI. Class “C”

10.0 WATER SOFTENER WITH BRINE TANK:

10.1 Softeners shall be designed to give required hardness as specified in the Bill of Quantities (BOQ).
Softener shall provided with suitable grade of Cation exchange resins in quantity as given in BOQ
or to be indicated by the contractor at the time of tendering.

10.2 Softener vessel shall be of Mild Steel Epoxy Point [MSEP]. Vessel shall be suitable for a working
pressure given in bill of quantities. The shell shall have a minimum thickness of 5 mm and dished
ends 6 mm mentioned in BOQ or as per manufacturer / Vender recommendation / Calculation.

10.3 The vessel shall have an internal collecting and distribution system of manufacturer’s design.

TS-20
10.4 Softener shall have a set of face piping for inlet, outlet, brine injection with all valves. Suitable
drain shall be provided.

10.5 Softener shall have one set of hydraulic injectors with control valve, brine delivery pipes with
adjustable indicating clamps.

10.6 Softener shall have one cylindrical HDPE/FRP saturator and mixing tank, provided with brine
delivery piping with adjustable level indicating clamp and control valves complete. The tank shall
be of capacity as given in the schedule of quantities.

10.7 Softener shall have charge of supporting gravel, sand and “Cation” resin in requisite quantity.

10.8 One water testing kit with instructions for testing water samples.

10.9 The contractor shall submit the following Shop Drawing / Document for consultants Approval.

[i] Fabrication Drawing / Detail for softener vessel.

[ii] Drawing Reflecting the arrangement / placement of cation exchanges resins & other supporting
media.

[iii] Drawing Reflecting the arrangement of valves & interconnecting piping complete with sequence
of operation for valves.

[iv] Technical Data Sheet of cation exchange resins complete with make & Model Number.

[v] Detail of Brine Tank.

[vi] Technical Data Sheet of Softener with Brine Tank.

11.0 FILTER PRESS:


11.1 Filter Press is device/equipment to separate solid from liquid under Pressure and consisting of
two fixed head pieces and moveable pressure piece with chambers formed by Plates and frames
or recessed chamber plates in between the fixed head piece and the movable. Pressure piece is
operated by a mechanical or a hydraulic closing device.

Where in a Excess Sludge Slurry is pumped through Screw Pump / Filter Press Feed Pump into
the Filter Press and is dewatered under Pressure.

Basically, each Filter Press is designed based on the volume and type of slurry that needs to be
dewatered.

11.2 Component of Filter Press:

The Main component of a filter Press include the following:-

[1] Frame

[2] Filter Plates

[3] Manifold

[4] Filter Cloth.

[1] Frame :

• The steel frame acts as a clamping device for the Filter Plate.

[2] Filter Plates :

TS-21
• A Filter cake forms in the chambers between Filter Plates.

[3] Manifold :

• Standard manifold consist of piping & valves which control the Slurry Inlet and connect the four
corner filtrate discharge Part into a common discharge pipe.

[4] Filter Cloth :

• A cloth Filter that is attached to both sides of filter plate. Solid build up on the cloth to form a filter
cake, separating liquid from solids.

11.3 Filter Press Working :

[1] Excess Sludge / Slurry are pumped into the Filter Press. The solids are distributed evenly on the
filter cloths during the Feed (fill) cycle.

[2] Solids begin to build on the filter cloth, trapping the ensuring particles and building a filter cake.
The filter cake acts as a depth filter for solid / liquid separation. Filtrate exits the plates through
the corner port into the manifold.

[3] When the correct valves in the Manifold are open, the filtrate exists the Filter Press through the
Filtrate outlet. As the Filter Press feed Pump builds pressure, the solids build within the chamber
until they are completely full of the Filter cake.

[4] Once the chambers are full, the fill cycle is complete and the filter press is ready to be emptied.

• The Vendor / Contractor shall submit the following document for Consultant approval :-

[a] Technical Data Sheet


[b] Manufacturer catalogue / Technical detail.

[c] Dimension Detail

[d] Make & Model Number along with selection of model number.

11.4 TECHNICAL DETAIL:

• Type : Side Feed & Bottom Discharge

• Mechanism : Hydraulic

• MoC of Plate : PP

• Nos. of Plate : As per BOQ or As per selected model number of Approved


make.

• Plate size : As per BOQ or As per selected model number of Approved


make.

• Operating Pressure : 4 - 5 bar

• Cake Holding Capacity : As per selected model number / Manufacturer

• Filtration Area : As per selected model number / Manufacturer

11.5 Polyelectrolyte Dosing :

TS-22
The polyelectrolyte will be dosed online at the filter press inlet. Minimum dosage of polyelectrolyte
shall be 1.2 kg/T of dry solids in sludge at 0.1% solution strength. There shall be two poly-dosing
tanks and each tank shall be equipped with slow speed mixer (100 rpm) to prepare
polyelectrolyte solution. The solution will be fed using positive displacement metering type dosing
pumps. The pumps shall be interlocked with Filter Press so that it can only be running in auto
when Filter Press is on and should shut down when Filter Press stops. The dosing system shall
be housed in Filter Press house itself.

Number of Tanks : 1 no. (1W)


Design Capacity : Capable of dosing for 500 KLD flow
Maximum concentration of Polymer solution : 0.1 %
Number of Polymer dosing pumps : 1 no. working

12.0 Decanting Mechanism

12.1 The decanting mechanism shall be of stainless steel (SS-304) and all the other accessories such
as gear box etc. shall be provided on the operating platform. The hydraulic discharge capacity of
the decanting mechanism shall be proportional to the selected basin area

12.2 There should be max 1 decanting mechanism per basin.

12.3 Each decanter mechanism shall be inclusive of local control boxes with manual operation
selection and function buttons, communication to main PLC

12.4 All other accessories, whether specified or not, but required for completeness of contract shall be
in contractor’s scope.

13.0 Automation and Control

13.1 PLC based automation system with application software to control all pumps, valves, blowers,
VFD, decanters, limit switches and probes as per bidder’s design including I/Os with 20% spares,
power supplies, UPS.

13.2 HMI Panel to comprise up-to-date standard PC with monitor, printer, mouse, internet connection,
RS-view, RS-links (gateway version), entire process and operator software with dynamic flow
charts, pictures, screens, alarms, historical trends, reports, animated graphic software etc.

13.3 SCADA based Automation system to monitor continuously in each tank the followings (Optional):

a. Filling volume
b. Filling quantity
c. Discharge quantity
d. DO-level (Optional)
e. Temperature
f. Oxygen Uptake Rate
g. Energy requirements
h. Blower speeds (Optional)
i. Decanter speed
j. Equipment operation hours
k. Flow of inlet sewage and effluent outlet
l. All tank levels

TS-23
14.0 HUMAN MACHINE INTERFACE (HMI):

14.1 The HMI shall be suitable for day to day operation by non-computer literate personnel in the
monitoring and operation of the treatment works.

14.2 Human Machine Interface (HMI) shall be provided at Monitoring Room.

14.3 The SCADA system shall provide efficient and safe operation of the process plant by detection
of alarm and error conditions, to alert the Contractor to these conditions by both visual and
audible alarm, to monitor all important system parameters and providing facilities for plant
optimization.

14.4 The system will allow Contractors, technicians and Engineers to issue commands to change
system parameters, start and stop equipment, provide configuration tools and operate
diagnostic facilities from Contractor Workstations (OW) and Engineering workstation (EW),
after successful log-on by security password.

14.5 The System shall perform all the necessary functions for the optimum monitoring, control and
operation of the entire system.

14.6 The HMI shall be constructed to a high standard to provide a high profile feature and focal point
for visitors to the Sewage Treatment Plant (STP).

14.7 SCADA/HMI system shall be housed in an air-conditioned environment.

15.0 TECHANICAL SPECIFICATION FOR ULTRAVOILET UNITS :

• UV lamp type - Low pressure, high performance


• UV lamp configuration - Water Tank.
• Ballast type - Matched high frequency electronic ballasts.
• Quartz sleeve type - High UVT self guiding quartz sleeves
• Input Voltage - 230-240V Ac, 50-60Hz, 1 Phase.
• Lamp run hour counters - Common for all lamps.
• System status indicators - Power on and individual lamp status.
• Lamp fail alarm - Audio – visual
• UV chamber installation - Vertical or horizontal
• UV chamber - Electro – polished SS 316L with full penetration
automatic welds.
• UV sensor part - UV intensity monitor and sensor shall be
included.
• UV Dosage - > 600 J/m2
• Maximum operating pressure - 0-6 Kg/cm2
• Inlet /outlet sizes - As per model no/manufacturer recommended.
• Flow rate - As per BOQ
• Reactor dimension - As per model no/manufacturer recommendation.
• Control Panel dimension - As per model no/manufacturer recommendation.
• Total running time counter
• Lamp lift remaining counter
• Lamp replacement reminder

16.0 FORGED BRASS BALL VALVES AND BUTTERFLY VALVE:

16.1 FORGED BRASS BALL VALVES:

16.1.1 The Contractor shall supply and install all ball valve as indicated on the drawing & BOQ.

16.1.2 The valve shall be suitable for monitoring on horizontal/vertical pipe line.

16.1.3 Screwed female end shall confirm to IS 554/BS21/IS013.

TS-24
16.1.4 Ball valve shall be full bore, quarter turn & lever operated.

16.1.5 Ball valve shall have forged brass hard chrome plated ball, PTFE body ring and gland packing,
chrome plate finish.

16.1.6 Seat & Test pressure shall be 16 Kg./Cm2 and 25 Kg./Cm2 or as specified in BOQ.

16.1.7 Material of Construction (MoC)

a) Body, Bonnet, Ball, Steam : Forged brass & gland.


b) Body seat ring, Thrust washer & gland packing : PTEF.
c) Lever : Aluminum Alloy/Mild steel.
d) Nut : Brass (Chrome plated).

16.1.8 Each valve shall have manufacturer name, size & pressure rating.

16.1.9 Valve of size from 15mm dia to 40mm dia shall be Ball valve.

16.2 BUTTERFLY VALVE:

16.2.1 Butterfly valve shall be installed at pipe line to seal the water or air and to adjust the flow.

16.2.2 Valve shall be suitable for throttling operations and for infrequent operation after period of
inactivity.

16.2.3 The body of the valve shall be made from cast iron.

16.2.4 Valve shall have fabricated steel, cast iron or ductile iron discs with a resilient rubber sealing ring.

16.2.5 Valve steam, shall be stainless steel designed for both torsion and shearing stresses when the
valve is operated with permanently self-lubricated shaft stub bearing, sized to withstand bearing
loads.

16.2.6 Butterfly valves shall be provided with hand-wheels and rack and pinion gear operation.

16.2.7 The valve shall be open by turning the handwheel in an anticlockwise direction.

16.2.8 The direction of valve opening and closing shall be marked on the hand-wheel casting.

16.2.9 The valve shall be designed to hold the disc in any intermediate position between fully opened
and fully closed without creeping or fluttering by manual or electric operation.

16.2.10 Butterfly valve shall confirms to IS : 13095.

16.2.11 The Butterfly shall be suitable for working and test pressure of the system as specified in BOQ.

16.2.12 All valve 50mm and above shall be Butterfly valve.

16.2.13 The Contractor shall supply and install all Butterfly valve/isolation valve as indicated on the
drawing/BOQ and as required for the proper and efficient operation & maintenance of the entire
system.

16.2.14 Each valve shall have a purpose made reference, manufacturer name, sizes & pressure rating.

16.2.15 Contractor shall furnish all valves and accessories material necessary in the piping whether or not
shown on drawing.

TS-25
17.0 Cast Iron Y-Strainer:

17.1 Y-Type Strainer shall be best quality flanged ends to BS Table-F.

17.2 Stainless steel (SS-304) perforated sheet screen (ø 3mm perforation) is guided in body & cover.
Large screening are makes the strainer efficient in performance the strainer efficient in
performance.

17.3 Y-strainer shall be of cast iron body & cover, stainless steel (type 304) screen carbon steel nuts &
studs, brass/bronze drain plug, rubber gasket.

17.4 Test Pressure (Hydrostatic)

[a] Shell – 24.0 Kg./cm2 (340 Psig)

[b] Minimum working pressure – 16.0 Kg./cm2 (225 Psig)

18.0 NON-RETURN VALVES:

18.1 The Contractor shall supply and install all Non-Return valve as indicated on the drawing & BOQ.

18.2 The valve shall be suitable for mounting on horizontal/vertical pipe line.

18.3 The valve shall be dual plate wafer type Non-Return valve complete with 2 Nos. matching
flanges, rubber insertion, nut, bolts & washer etc.

18.4 Valve upto 40mm dia shall be Gunmetal construction and 50mm and above shall be cast iron
construction with flanged end.

18.5 All valve supplied shall be suitable for the working pressure and test pressure of the system as
specified in BOQ.

18.6 Standard

a) Design Standard : IS 5312-1, 1984


b) Flanged end to IS 1538

18.7 Material of Construction (MoC)


a) Body : Cast iron
b) Flap : Bronze/SS
c) Pin, Washer & Spring : Stainless steel (AISI 316/304)
d) Body Ring : EPDM/Nitrile rubber
e) Retainer Hook : Carbon steel

19.0 G.I PIPES & FITTINGS :

19.1 All pipes inside the buildings and where specified, outside the building shall be galvanized steel
tubes conforming to IS: 1239 of Class specified. When Class is not specified they shall be Heavy
Class.

19.2 Fittings shall be of malleable cast iron galvanized of approved make. Each fitting shall have
manufacturer’s trade mark stamped on it. Fittings for G.I pipes shall include couplings, bends,
tees, reducers, nipples, unions, bushes etc. Fittings etc. shall conform to IS: 1879. (part 1 to
X)1987.

19.3 Pipes and fittings shall be jointed with screwed joints using Teflon tape suitable for water pipes.
Care shall be taken to remove burr from the end of the pipe after cutting by a round file. All pipes
shall be fixed in accordance with layout and alignment shown on the drawings. Care shall be
taken to avoid air pockets. Necessary vents and drains shall be provided at all high and low
points respectively. G.I pipes inside toilets shall be fixed in wall chases well above the floor. No

TS-26
pipes shall be run inside a sunken floor as far as possible. Pipes may be run under the ceiling or
floors and other areas as shown on drawings

19.4 Clamps

19.4.1 G.I pipes in shafts and other locations shall be supported by G.I clamps of design approved by
the Architect/Consultants. Pipes in wall chases shall be anchored by iron hooks. Pipes at ceiling
level shall be supported on structural clamps fabricated from MS structurals as described in
Clause Clamps of Cast Iron Pipes and Fittings. Pipes in shafts shall be supported on slotted
angles/ channels as specified/ as directed.

19.5 Unions

19.5.1 Contractor shall provide adequate number of unions on all pipes to enable easy dismantling later
when required. Unions shall be provided near each gunmetal valve, stop cock or check valve and
on straight runs as necessary at appropriate locations as required for easy dismantling and/ or as
directed by Architect/Consultants.

19.6 Flanges

19.6.1 Flanged connections shall be provided on pipes as required for maintenance/ ease in dismantling
or where shown on the drawings, all equipment connections as necessary and required or as
directed by the Architect/Consultants. Connections shall be made by the correct number and
size of the GI nuts/ bolts as per relevant IS Standards and made with 3mm thick insertion rubber
washer/ gasket. Where hot water or steam connections are made insertion gasket shall be of
suitable high temperature grade and quality approved by the Architect/Consultants. Bolt hole dia
for flanges shall conform to match the specification for CI sluice valve as per IS:780. Gaskets
shall conform to IS:11149.

19.7 Trenches

19.7.1 All G.I pipes below ground shall be laid in trenches with a minimum cover of 600mm. The width
and depth of the trenches shall be as follows :-

Dia of pipe Width of trench Depth of trench

15mm to 50mm 300mm 750mm

65mm to 100mm 450mm 1000mm

19.8 Sand Filling

19.8.1 GI pipes in trenches shall be protected with fine sand 150mm all around before filling in the
trenches.

19.9 Painting

19.9.1 All pipes above ground shall be painted with one coat of red lead and two coats of synthetic
enamel paint of approved shade and quality to give an even shade. Pipes shall be painted to
standard colour code specified by the Architect/Consultants.

19.10 Pipe protection

19.10.1 Where specified in the schedule of quantities all pipes in chase below ground shall be protected
against corrosion by applying two coats of bitumen pain wrapping with polythene tape and
finishing with one more coat of bitumen paint.

TS-27
20.0 M.S. PIPE AND FITTING:
20.1 General:

20.1.1 All materials shall be new of the best quality conforming to the specifications and subject to the
approval of the Project Manager.

20.1.2 Pipes and fittings shall be fixed truly vertical, horizontal as required in a neat workmanlike
manner.

20.1.3 Pipes shall be fixed in a manner as to provide easy accessibility for repair and maintenance and
shall not cause obstruction in shafts, passages etc.

20.1.4 Pipes shall be securely fixed to walls and ceilings by suitable clamps at intervals specified. Only
approved type of anchor fasteners shall be used for RCC ceilings and walls.

20.1.5 Valves and other appurtenances shall be so located that they are easily accessible for
operations, repairs and maintenance.

20.2 M.S. Piping:

20.2.1 Pipes and fittings of following types and ISI marked only shall be used:

Type of Pipe
Size Grade Ends/Fitting Code
/ (dia)

IS: 1239
M.S Pipes Upto 50 mm dia Heavy Screwed
(Part I)
IS: 1239
MS Fittings - do- Heavy -do-
(Part II)
65 mm & above
Bevel, Butt Welded, IS: 1239
M S Pipes dia and upto Heavy
3 layers (Part I)
150 mm dia
Heavy, machine
formed from IS IS: 1239
MS Fittings -do- -do-
marked heavy (Part III)
grade pipes
Above 150 mm 6.0 mm wall Bevel, Butt welded, 3
M S Pipes IS: 3589
dia thickness layers
MS Fittings -do- Schedule 40 -do- IS: 3589

20.2.2 MS pipes for 25 mm and above welded connections shall be used. Only Electro galvanized nuts
/bolts shall be used.

20.2.3 The piping system and components shall be capable of with standing 150 % of the working
pressure including water hammer effects.

20.2.4 Flanged joints shall be used for connections to vessels, equipment, flanged valves and also on
suitable straight lengths of pipeline of strategic points to facilitate erection and subsequent
maintenance work.
20.2.5 Flange thickness shall be as per table below IS : 6392 – 1971. Table – 17/18.
250 mm dia : 26 mm;
200 mm dia : 24 mm;
150 mm dia : 22 mm;
125 mm dia : 22 mm;
100 mm dia : 20 mm;
80 mm dia : 20 mm;
65 mm dia : 18 mm.

TS-28
20.3 Pipe Protection:

20.3.1 All pipes above ground and in exposed locations shall be painted with epoxy paint/anti corrosive
paint.

20.4 Welding:

20.4.1 Joints between M.S. Pipes and fittings shall be made with the pipes and fittings having “V” groove
and welded with electrical resistance welding in an approved manner.

20.4.2 Weld Electrodes shall be of approved make, of grade and type as suitable for the job and meeting
the approval of the engineer.

20.4.3 Joints shall be given a first weld in full width without burrs on the full dia of the pipe. Welding shall
be carried out vertically from the surface to be welded. Weld fluxes shall not be so plastic such as
to fall or drip down.

20.4.4 After application of first coat the weld shall be ground and then another layer of welding shall take
place. The weld shall also be cleaned by grinding.

20.4.5 All pipe cutting shall be by oxy acetylene gas welding only. The cut surface shall be cleaned and
ground by a electric grinder before further welding.

20.4.6 Pipe cutting or welding in inaccessible areas shall be avoided. Pipes shall not welded in trenches
unless the bottom edge of the pipe does not have clear space for working with electrode.

20.4.7 For supports, angle pieces shall be cut by oxy acetylene gas and cleaned by electric grinder. All
cutting for bolt inserts shall be by electric drill.

21.0 UPVC SCH-40 PIPES & FITTINGS:

UPVC SCH-40 Water Distribution System shall be Flowguard UPVC SCH-40 (Unplasticized
Polyvinyle Chloride) Water Supply Piping System with pipe as per ASTM D-1785 at maximum
working pressure of 600 psi (42.19 Kg/cm2) at 23oC (from ½” - 2”), using solvent welded UPVC
SCH-40 fitting i.e. Tees, elbows, couplers, unions, reducers, bushing etc. including transition
fitting (connection between UPVC SCH-40 and metal pipe / G.I.) i.e. Brass adapter (both male
and female threaded) all conforming to ASTMD-2466 with only UPVC solvent cement conforming
to ASTM D-2564 - with only Clamps/structural metal supports as required/directed at site
including cutting chases and filling the same with cement concrete/cement mortar as required. All
termination points for installation of faucets shall have brass termination fittings. Installation shall
be to the satisfaction of consultant/manufacturers of pipes and fittings.

 Outside Diameters and Wall Thicknesses for UPVC SCH 40, ASTM D-1785 Pipe

Nom Size Min Max. Work


Max. Work
Avg. OD Avg. OD Min Wall Wall Pre. at
Pre. at
(inch) (mm) Thick (in) Thick 23oC
(inch) (mm) 23oC PSI
(mm) (kg/cm2)
½” 15 0.840 21.34 0.109 2.77 600 42.19
¾” 20 1.050 210.67 0.113 2.87 480 33.75
1” 25 1.315 33.40 0.133 3.38 450 31.64
1 1/4” 32 1.660 42.16 0.140 3.56 370 210.01
1 ½” 40 1.900 410.26 0.145 3.68 330 23.20
2” 50 2.375 60.32 0.154 3.91 280 19.69
2 ½” 65 2.875 73.02 0.203 9.16 300 21.09
3” 80 3.500 810.90 0.216 9.49 260 110.28
4” 100 4.500 114.30 0.237 10.02 220 19.47

TS-29
Nom Size Min Max. Work
Max. Work
Avg. OD Avg. OD Min Wall Wall Pre. at
Pre. at
(inch) (mm) Thick (in) Thick 23oC
(inch) (mm) 23oC PSI
(mm) (kg/cm2)
6” 150 10.625 1610.28 0.280 9.11 180 12.66
8” 200 10.625 219.08 0.322 10.18 160 11.25
10” 250 10.750 273.05 0.365 9.27 140 9.84
12” 300 12.750 323.85 0.406 10.31 130 9.14

21.1 JOINING FLOWGUARD PIPES AND FITTINGS:

a) Cutting :
Pipe shall be cut with either with a wheel type plastic pipe cutter or hacksaw blade, and care shall
be taken to make a square cut, which provides optimal bonding area within a joint.

b) Deburring/Beveling :
Burrs and fillings should be removed from the outside and inside of pipe with a pocket knife or file
otherwise burrs and fillings may prevent proper contact between pipe and fittings during
assembly.

c) Fitting/Preparation :
A clear dry rag/cloth should be used to wipe dirt and moisture from the fitting sockets and tubing
end. The tubing should make contact with the socket wall 1/3 or 1/2 of the way into the fitting
socket. Pipes and fittings that are too tight or too loose shall not be used.

d) Solvent Cement Application :


UPVC solvent cement conforming to ASTM D2564 should be used for joining pipe with fittings.
An even coat of solvent cement should be applied on the pipe end and a thin coat inside the
fitting socket, otherwise too much of cement solvent can cause clogged water ways.

e) Assembly :
After applying the solvent cement on both pipe and fitting socket, pipe should be inserted into the
fitting socket within 30 seconds and rotating the pipe 1/4 to ½ turn while inserting so as to ensure
even distribution of solvent cement with the joint. The assembled system should be holded for 10
seconds (approximately) in order to allow the joint to set up.

UPVC Cement for SCH 40 and Interference fit

S.No. Pipe Size (In.) mm Cement Type Min. Vis. (cP) IPS-Weld On

½” – 2”
1. Medium Bodied 500 705
15 – 50 mm
2½” – 12”
2. Heavy Bodied 1600 717
65 – 300 mm

• Testing:

Once an installation is completed and cured or per above mentioned recommendations, the
system should be hydrostatically pressure tested at 150 psi (10 bar) for one hour. During
pressure testing, the system should be filled with water and if a leak is found, the joint should be
cut out and replacing the same with new one by using couplers.

• Transition of flow guard UPVC SCH 40 to Metals :

When making a transition connection to metal threads, special Brass (Male and female adapters)
should be used.

TS-30
• Threaded Sealants:
Teflon tap shall be used to make threaded connections leak proof.

• Solvent Cement:
UPVC solvent cement conforming to ASTM D2564 should be used for joining pipe with fittings
and valves. UPVC cement solvent have a minimum shelf life of 1 year. Solvent have a minimum
shelf life of 1 year. Aged cement solvent will often change colour or began to thicken and become
gelatinous or jelly to like and when this happens, the cement should not be used. The cement
solvent should be used within 30 days after opening the company’s seal and tightly close the seal
after using in order to avoid its freezing. The freezed cement solvent should be discarded
immediately and fresh one should be used.

 Hangers and Supports:

Most hangers designed for metal pipe are suitable for flow ground. Hangers should not have
rough or sharp edges which come in contact with the tubing.

Supports should be as per the below mentioned table:

Schedule-40

Recommended Support Spacing (in feet)


Nom. Pipe Size Temperature oC
S.No.
(in) (mm) 19.5 210.6 39.7 410.8 60
1 ½ 15 4½ 4½ 4 2½ 2½
2 ¾ 20 5 4½ 4 2½ 2½
3 1 25 5½ 5 4½ 3 2½
4 1¼ 32 5½ 5½ 5 3 3
5 1½ 40 6 5½ 5 3½ 3
6 2 50 6 5½ 5 3½ 3
7 2½ 65 6½ 6 5½ 4 3
8 3 80 7 7 6 4 3½
9 4 100 7½ 7 6½ 4½ 4
10 6 150 8½ 8 7½ 5 4½
11 8 200 9½ 9 8½ 5½ 5
12 10 250 10½ 9½ 9 6½ 5½
13 12 300 12 10½ 9½ 7 6

22.0 CPVC PIPES & FITTINGS & VALVES FOR WATER SUPPLY DISTRIBUTION SYSTEM:

CPVC Water Distribution System shall be CPVC (Chlorinated Polyvinyl Chloride) Water Supply
Piping System with pipe as per CTS SDR-11 at maximum working pressure of 400 psi (210.1
Kg/cm2) at 23oC and 100 psi (9.0 Kg/cm2) at 82oC (from ½” - 2”), using solvent welded CPVC
fitting i.e. Tees, elbows, couplers, unions, reducers, bushing etc. including transition fitting
(connection between CPVC and metal pipe / G.I.) i.e. Brass adapter (both male and female
threaded) all conforming to ASTMD-2846 with only CPVC solvent cement 5conforming to
ASTMF-493 - with only Clamps/ structural metal supports as required/directed at site including
cutting chases and filling the same with cement concrete/cement mortar as required. All
termination points for installation of faucets shall have brass termination fittings. Installation shall
be to the satisfaction of consultant/manufacturers of pipes and fittings.

TS-31
 Outside Diameters and Wall Thicknesses for CPVC 4120, SDR 11 Plastic Pipe

Nominal Size Outside Diameter, in. (mm) Wall Thickness, in. (mm)
(in.) (mm) Average Tolerance Minimum Tolerance
½ 15 0.625 (19.9) + 0.003 (+ 0.08) 0.068 (1.73) + 0.020 (+ 0.51)
¾ 20 0.875 (22.2) + 0.003 (+ 0.08) 0.080 (2.03) + 0.020 (+ 0.51)
1 25 1.125 (210.6) + 0.003 (+ 0.08) 0.102 (2.59) + 0.020 (+ 0.51)
1-1/4 32 1.375 (34.9) + 0.003 (+ 0.08) 0.125 (3.18) + 0.020 (+ 0.51)
1-1/2 40 1.625 (41.3) + 0.004 (+ 0.10) 0.148 (3.76) + 0.020 (+ 0.51)
2 50 2.125 (54.0) + 0.004 (+ 0.10) 0.193 (4.90) + 0.023 (+ 0.58)

 Pressure Ratings for CPVC, SDR 11 Plastic Pipe

Nominal Size Pressure Rating, PSI (Kg/cm2)


(in.) (mm) 73.4oF (23oC) 180oF (82oC)
½ 15 400 (210.1) 100 (9.0)
¾ 20 400 (210.1) 100 (9.0)
1 25 400 (210.1) 100 (9.0)
1-1/4 32 400 (210.1) 100 (9.0)
1-1/2 40 400 (210.1) 100 (9.0)
2 50 400 (210.1) 100 (9.0)

22.1 JOINING FLOWGUARD PIPES AND FITTINGS :

• Cutting :

Pipe shall be cut with either with a wheel type plastic pipe cutter or hacksaw blade, and care shall
be taken to make a square cut, which provides optimal bonding area within a joint.

• Deburring/Beveling :

Burrs and fillings should be removed from the outside and inside of pipe with a pocket knife or file
otherwise burrs and fillings may prevent proper contact between pipe and fittings during
assembly.

• Fitting/Preparation :

A clear dry rag/cloth should be used to wipe dirt and moisture from the fitting sockets and tubing
end. The tubing should make contact with the socket wall 1/3 or 2/3 of the way into the fitting
socket.

• Solvent Cement Application :

CPVC solvent cement conforming to ASTM - F493 should be used for joining pipe with fittings. An
even coat of solvent cement should be applied on the pipe end and a thin coat inside the fitting
socket, otherwise too much of cement solvent can cause clogged water ways.

Assembly :
After applying the solvent cement on both pipe and fitting socket, pipe should be inserted into the
fitting socket within 30 seconds and rotating the pipe 1/4 to ½ turn while inserting so as to ensure
even distribution of solvent cement with the joint. The assembled system should be holded for 10
seconds (approximately) in order to allow the joint to set up.

• Set and Cure Times: remake the joint to avoid potential solvent cement set and cure times shall
be strictly adhered to as per the below mentioned table.

TS-32
Minimum cure prior to pressure testing at 150 psi:

Ambient Temperature Pipe Sizes


During Cure Period ½” - 1” 1 ¼” - 2”
Above 15 C 1 Hr 2 Hrs
4 - 15 C 2 Hrs 4 Hrs
Below 4 C 4 Hrs 8 Hrs

Special care shall be exercised when assembling flow guard systems in extremely low
temperature (below 4 C) or extremely high temperature (above 45 C) in extremely hot
temperatures, make sure that both surfaces to be joined are still wet with cement solvent when
putting them together.

1. Testing:

Once an installation is completed and cured or per above mentioned recommendations,


the system should be hydrostatically pressure tested at 150 psi (10 bar) for one hour.
During pressure testing, the system should be filled with water and if a leak is found, the
joint should be cut out and replacing the same with new one by using couplers.

2. Transition of flow guard CPVC to Metals :

When making a transition connection to metal threads, special Brass (Male and female
adapters) should be used.

3. Threaded Sealants:
Teflon tap shall be used to make threaded connections leak proof.

4. Solvent Cement:

CPVC solvent cement conforming to ASTMF 493 should be used for joining pipe with
fittings and valves. CPVC cement solvent have a minimum shelf life of 1 year. Solvent
have a minimum shelf life of 1 year. Aged cement solvent will often change colour or
began to thicken and become gelatinous or jelly to like and when this happens, the
cement should not be used. The cement solvent should be used within 30 days after
opening the company’s seal and tightly close the seal after using in order to avoid its
freezing. The freeze cement solvent should be discarded immediately and fresh one
should be used.

 Hangers and Supports :


Most hangers designed for metal pipe are suitable for flow ground. Hangers should not
have rough or sharp edges which come in contact with the tubing.

Supports should be as per the below mentioned table :


Horizontal and Vertical Support
Spacing
Size of pipe 21 deg. C (70oF) 49 deg. C (120oF) 71 deg. C (160oF) 82 deg. C
(180oF)
Inch (mm) Ft. cm Ft. cm Ft. cm Ft. Cm
½” (15) 9.5 (169.7) 4.5 (139.16) 3.0 (91.44) 2.5 (710.2)
¾” (20) 9.5 (169.7) 9.0 (152.4) 3.0 (91.44) 2.5 (710.2)
1” (25) 10.0 (182.88) 9.5 (169.7) 3.5 (1010.68) 3.0 (91.44)
1 ¼” (32) 10.5 (1910.12 10.0 (182.88) 3.5 (1010.68) 3.5 (1010.68)
)
1 ½” (40) 9.0 (213.36) 10.0 (182.88) 3.5 (1010.68) 3.5 (1010.68)
2” (50) 9.0 (213.36) 10.5 (1910.12) 4.0 (121.92) 3.5 (1010.68)

TS-33
23.0 INSTRUMENTATION :

23.1 Electromagnetic Flow meter :

• Full bore electromagnetic flow meter shall consist of flow sensors (i.e. flow tube), transmitter and
remote flow indicator cum integrator.
• The flow meter shall have flanged connection and shall be inserted in the sludge line.

• The flow computer/ transmitter shall be microprocessor based and shall have diagnosis facility.

• Remote flow indicator cum integrator shall be provided on the control panel.

• To ensure full electromagnetic compatibility the flow tube flanges and transmitter housing shall be
connected earth.

23.2 Pressure Gauges:


Pressure gauges shall comply with BS 1780. Snubber shall be provided where the gauge is
subjected to pressure pulsations and / or vibrations. The internal parts of pressure gauge shall be
of stainless steel material. In chlorine applications the diaphragm shall be silver or tantalum for
other fluids an appropriate diaphragm material shall be used. The pressure gauges shall be
provided with diaphragm seal arrangement.

The minimum diameter for round pressure gauges shall be 150mm unless specified otherwise or
where the gauge forms part of a standard item of equipment. The accuracy of pressure gauges
shall be ±1% over the operating range.

23.3 Electronic Digital Type Turbine Flow Meter :


Providing, fixing, testing & commissioning of Electronic Digital Type Turbine Flow Meter/Totalizer
having following specification.

● Internal Part (Roter) : Stainless steel SS 304.


● Mounting : Inline horizontal or vertical.
● Reading : M3/Hour and Kilo-litter
● Flow rate display : 4 digitals LED.
● Totalizer display : 8 digitals LED.
● Output : 4-20mA (Integrated with BMS).
● Power supply : 220V AC/24 V DC
● Accuracy : ± 1%.
● Repeatibility : ± 1%.
● Operating temperature : 0-50°C.
● Media : Liquid.
● Maintenance : Provision of bypass arrangement (Piping & Valves)

24.0 STATUTORY AUTHORITIES APPROVAL:

24.1 As and when notified in writing or instructed by the Construction Manager/Consultant/Client


Representative, the Contractor shall submit Drawings & Reports and attend all tests and
Inspection carried out by Local Pollution Board Authorities, Water Authority and other Statutory
Authorities and shall forthwith execute free of charge any rectification work ordered by the
Construction Manager/Consultant/Client Representative as a result of such tests and inspections
where these indicate non-compliance with statutory regulation.

24.2 The Contractor shall be responsible for the submission of all necessary forms, drawing and report
to Statutory Authorities which shall confirm in layout to the latest Architectural Plans submitted to
and kept by these Authorities.

TS-34
24.3 The submission shall comply with the requirements set forth in current code of Practice and
Circular letters of the Statutory Authorities.

24.4 The required drawings to be submitted shall be forwarded to the Construction Manager/
Consultant/Client’s Representative for checking before submission.

24.5 The Contractor shall notify the Construction Manager/ Consultant/Client’s Representative at
atleast seven days in advance of his application for Local Authority test & inspection on receipt of
a confirmed date for test and inspection the Contractor shall inform the Construction Manager/
Consultant/Client’s Representative without delay.

25.0 PRELIMINARY COMMISSIONS CHECKS :

25.1 Ensure that all equipments cleaned, lubricated and checked for serviceability before setting to
work. Particular attention is drawn to the removal of building debris from the pipe work system.

25.2 Special attention is drawn to the need for thoroughly flushing out all pipe work systems to ensure
that all foreign matter is removed.

25.3 All automatic controls and safety devices shall be inspected and checked for service ability before
the working fluid or electricity is applied for all.

26.0 COMMISSIONING :

26.1 When the various installations have been completed and the Preliminary commissioning checks
carried out, the Contractor shall set to work, regulate and calibrate all system in the entire
installation. Special attention shall be paid to the following items:

a) That all valves, switches, controls, etc. are regulate and capable of proper operation and in
the case of isolation valves that they are capable of light shutoff.

b) That all apparatus is silent in Accordance with the requirement as specified in various section
of Technical Specification.
c) That all instruments are correctly calibrated and read accurately.

d) That all services are tested in accordance with details in the relevant clauses of this
specification.

e) Operate pumps, blowers & STP membrane etc. to ensure that all control systems are
functioning correctly and properly set, sequenced or interlock.

27.0 FINAL ACCEPTANCE TESTS :

27.1 Following commissioning and inspection of the entire installation, and prior to issue the
completion certificate, the Contractor shall carry out final, acceptance tests in accordance with
programme to be agreed with the Construction Manager/Consultant/Client’s Representative.

27.2 If the results of the acceptance test show that Plant, Systems and or equipment fails to perform to
the efficiencies or other performance figures as given in this specification, the Contractor shall
adjust modify and if necessary, replace the equipment without additional cost in order that the
required performance is obtained.
27.3 Where acceptance tests are required by the relevant Authorities having jurisdiction, these tests
shall be carried out by the Contractor prior to the issue of completion certificate to the acceptance
of the Authorities.

TS-35
28.0 REJECTION OF PLANT :
28.1 Any item of Plant or System or component which fails to comply with requirements of this
specification in any respect whatsoever at any stage of manufacture test, erection or on
completion at site may be rejected by the Construction Manager/Consultant/Client’s
Representative either in whole or in part as he considers necessary/appropriate.

28.2 Adjustment and/or modification work as required as required by the Construction Manager/
Consultant/Client’s Representative so as to comply with the Authority’s requirements and the
intent of the specification shall be carried out by the Contractor at his own expense and to the
satisfaction of the Authority/ Construction Manager/ Consultant/Client’s Representative.

28.3 After works have been accepted, the Contractor may be required to carry out assist in carrying
out additional performance tests as reasonably required by Construction Manager/ Consultant/
Client’s Representative.

29.0 HANDING OVER OF DOCUMENTS :

29.1 All testing and commissioning shall be done by the Contractor to the entire satisfaction of the
Construction Manager and all testing & commissioning documents shall be handed over to the
Construction Manager.

29.2 The Contractor shall also handover all maintenance and operation Manuals, all certificates and all
other documentation as per the terms of the contract to the Construction Manager.

29.3 The operation and maintenance manual shall include : -

a) Description of work carried out/installed.


b) Operation instruction.
c) Maintenance instruction including procedure for preventive maintenance.
d) Manufacturer catalogues.
e) Spare parts list.
f) Trouble shooting charts.
g) Drawings.
h) Type and routine test certificate of major items.
i) Detail of all brought out item should be part of this maintenance manual.

30.0 ON SITE TRAINING :

30.1 Upon completion of all work and all tests, the contractor shall furnish necessary operators labour
and helpers for operating the entire installation for such periods so as enable the client’s staff to
get acquainted with operation of the system.

30.2 During this period the Contractor shall train the client’s personnel in the operation, adjustment
and Maintenance of all equipment installed.

31.0 MAINTENANCE DURING DEFECT LIABILITY PERIOD :

31.1 COMPLAINTS

31.1.1 The Contractor shall receive calls for any and all problems experienced in the operation of the
system under this contract, attend to these within 10 hours of receiving the complaint and shall
take steps to immediately correct any deficiencies that may exit.

31.2 REPAIRS

31.2.1 All equipment that requires repairing shall be immediately serviced and repaired since period of
Mechanical Maintenance runs concurrently with defect liability period, all replacement parts and
labour shall be supplied promptly free of charge to the client.

TS-36
31.3 The Vendor shall be responsible for the operation and maintenance of the STP Plant including
chemicals and other consumable for first one year.

32.0 PERFORMANCE OF STP PLANT :

32.1 Basic Design Parameter given in the Bill of Quantity (BOQ)/Technical Specification are the
general guide line purpose. The performance of STP Plant is Contractor/Vendor responsibility.

33.0 NORMS:

33.1 STP Contractor should follow the concern Indian and Local norm. Pollution Control Board /MOEF
recommendation shall be followed by STP Contractor.

34.0 TECHNICAL DATA SHEET:


Contractor to furnish complete technical data & detail on the format as mentioned below:

Contractor furnishes the performance curves, dimension detail, installation detail, pump & motor
detail catalogue while submitting the tender.

34.1 SEWAGE & DRAINAGE TRANSFER PUMP (SUBMERSIBLE PUMP):

Location: STP Room

STP Plant
Waste Water
Raw Sewage Room
Description: Transfer Pump
Transfer Pump Drainage Sump
to Municipal Line
pump
A) Pump:

1.1 Quantity

1.2 Make

1.3 Model

1.4 Capacity/Discharge in LPS

1.5 Pumping Head

1.6 Shut off Head

1.7 No. of Stages

1.8 Power Requirement

1.9 Efficiency

1.10 Mechanical Seal

1.11 Material (body)


Material (Impeller)/type of
1.12
impeller
1.13 Material (Shaft)

1.14 Outer/Inner Casing

1.15 Top Bracket

1.16 Delivery end I.D.


Max. solids handling
1.17
capacity

TS-37
STP Plant
Waste Water
Raw Sewage Room
Description: Transfer Pump
Transfer Pump Drainage Sump
to Municipal Line
pump
Minimum/maximum
1.18 submergence for cut out/
cut in
1.19 Pump Type

B) Motor:

1.1 Make

1.2 Model

1.3 R.P.M

1.4 Power Supply

1.5 Rated Power

1.6 Rated Current

1.7 Type of Enclosure

1.8 Class of Insulation


Details of Additional
1.9
protection in winding
1.10 Motor Efficiency

1.11 Type of rotary movement


Size and type of cable for
1.12
connections
1.13 At 100% Load

a) Current

b) Efficiency (%)

c) Power Factor (%)

d) Speed (RPM)

1.14 Start Current

1.15 Full Load Torque (kg.m)

1.16 Number of Start per hour

1.17 Design Standard

1.18 Voltage Tolerance (%)

1.19 Frequency tolerance (%)

TS-38
34.2 SLUDGE RECIRCULATION PUMP:

Location : Plant Room

Description: SBR Reactor - I SBR Reactor - II

Pump:

Quantity :

Make :

Model :

No. of Stages :

Power Requirement :

Efficiency :

Discharge in L.P.S :

Total Head :

Suction end I.D. :

Delivery end I.D. :

Pump Type :

Material:

a) Body :

b) Impeller :

c) Shaft :

Type of impeller :

Is it suitable for direct coupling. :

Motor:

Make :

Model :

R.PM :

Rating :

Over Load Capacity :

Class of Insulation :
Details of Additional protection in
:
winding
Motor Efficiency :
Is it suitable for direct coupling to
:
pump ?
Type of rotary movement :
Size and type of cable for
:
connections

TS-39
34.3 FILTER FEED PUMPS:

Location : STP Room

Description:

Pump:

Quantity

Make

Model

No. of Stages

Power Requirement

Efficiency

Pump Type

Capacity/ Discharge in LPS

Total Head

Suction end I.D.

Delivery end I.D.

Material:

a) Body

b) Impeller

c) Shaft

Type of impeller

Is it suitable for direct coupling.

Motor:

Make

Model

R.PM
Rating
Over Load Capacity

Class of Insulation
Details of Additional protection in
winding
Motor Efficiency
Is it suitable for direct coupling to pump
?
Type of rotary movement

Size and type of cable for connections

TS-40
34.4 FILTER PRESS FEED PUMP / SCREW PUMP :

Location : Plant Room

Description: STP Area


A) Pump:
1.1 Quantity :
1.2 Make :
1.3 Model :
1.4 Capacity/Discharge in l.p.s. :
1.5 Pumping Head :
1.6 Shut off Head :
1.7 No. of Stages :
1.8 Power Requirement :
1.9 Efficiency :
1.10 Mechanical Seal :
1.11 Material (body) :
1.12 Material (Impeller)/type of impeller :
1.13 Material (Shaft) :
1.14 Outer/Inner Casing :
1.15 Top Bracket :
1.16 Delivery end I.D. :
1.17 Max. solids handling capacity :
Minimum/maximum submergence for cut
1.18 :
out/cut in
1.19 Pump Type :
B) Motor:
1.1 Make :
1.2 Model :
1.3 R.P.M :
1.4 Power Supply :
1.5 Rated Power :
1.6 Rated Current :
1.7 Type of Enclosure :
1.8 Class of Insulation :
Details of Additional protection in
1.9 :
winding
1.10 Motor Efficiency :
1.11 Type of rotary movement :
1.12 Size and type of cable for connections :
1.13 At 100% Load
a) Current :
b) Efficiency (%) :
c) Power Factor (%) :

TS-41
Description: STP Area
d) Speed (RPM) :
1.14 Start Current :
1.15 Full Load Torque (kg.m) :
1.16 Number of Start per hour :
1.17 Design Standard :
1.18 Voltage Tolerance (%) :
1.19 Frequency tolerance (%) :

34.5 ULTRA FILTRATION FEED PUMPS :

Location : Plant Room

Description: Ultrafiltration Feed Pump

Pump:

Quantity :

Make :

Model :

No. of Stages :

Power Requirement :

Efficiency :

Pump Type :

Capacity/ Discharge in l.p.s. :

Total Head :

Suction end I.D. :

Delivery end I.D. :

Material:

a) Body :

b) Impeller :

c) Shaft

Type of impeller :

Is it suitable for direct coupling. :

Motor:

Make :

Model :

R.PM :

Rating :

TS-42
Description: Ultrafiltration Feed Pump

Over Load Capacity :

Class of Insulation :
Details of Additional protection in
:
winding
Motor Efficiency :
Is it suitable for direct coupling to
:
pump ?
Type of rotary movement :
Size and type of cable for
:
connections

34.6 ULTRAFILTRATION BACK WASH PUMPS :

Location : Plant Room

Description: Ultrafiltration Back Wash Pump

Pump:

Quantity :

Make :

Model :

No. of Stages :

Power Requirement :

Efficiency :

Pump Type :

Capacity/ Discharge in l.P.S. :

Total Head :

Suction end I.D. :

Delivery end I.D. :

Material:

a) Body :

b) Impeller :

c) Shaft

Type of impeller :

Is it suitable for direct coupling. :

Motor:

Make :

Model :

TS-43
Description: Ultrafiltration Back Wash Pump

R.PM :

Rating :

Over Load Capacity :

Class of Insulation :
Details of Additional protection in
:
winding
Motor Efficiency :
Is it suitable for direct coupling to
:
pump ?
Type of rotary movement :
Size and type of cable for
:
connections

34.7 VFD BASED HYDROPNUEMATIC SYSTEM FLUSHING WATER SUPPLY TO FILL THE
OVERHEAD FLUSHING WATER STORAGE TANK :

Location : Plant Room

Description: VFD Based Flushing Water Lifting Pump

Pump:
Quantity
Make
Model
No. of Stages

Power Requirement

Efficiency

Pump Type

Capacity/ Discharge in l.p.s.

Total Head

Suction end I.D.

Delivery end I.D.

Material:
a) Body
b) Impeller
c) Shaft
Type of impeller
Is it suitable for direct coupling.
Motor:
Make

TS-44
Description: VFD Based Flushing Water Lifting Pump

Model

R.PM

Rating

Over Load Capacity

Class of Insulation
Details of Additional
protection in winding
Motor Efficiency
Is it suitable for direct
coupling to pump ?
Type of rotary movement
Size and type of cable for
connections
Detail of VFD

Pressure Vessel:

Make

Model Number

Material of construction (Vessel/Bladder)

34.8 VFD BASED HYDROPNUEMATIC SYSTEM IRRIGATION WATER SUPPLY DISTRIBUTION


SYSTEM :

Location : Plant Room

VFD Based Irrigation Water Supply


Description:
Distribution system
Pump:
Quantity
Make
Model
No. of Stages

Power Requirement

Efficiency

Pump Type

Capacity/ Discharge in l.p.s.

Total Head

Suction end I.D.

Delivery end I.D.

TS-45
VFD Based Irrigation Water Supply
Description:
Distribution system
Material:
d) Body
e) Impeller
f) Shaft
Type of impeller
Is it suitable for direct coupling.
Motor:
Make

Model

R.PM

Rating

Over Load Capacity

Class of Insulation
Details of Additional
protection in winding
Motor Efficiency
Is it suitable for direct
coupling to pump ?
Type of rotary movement
Size and type of cable for
connections
Detail of VFD

Pressure Vessel:

Make

Model Number

Material of construction (Vessel/Bladder)

34.9 SOFTENER FEED PUMPS:

Location: STP Room

Description:

Pump:

Quantity

Make

Model

No. of Stages

TS-46
Description:

Power Requirement

Efficiency

Pump Type

Capacity/ Discharge in LPS

Total Head

Suction end I.D.

Delivery end I.D.

Material:

a) Body

b) Impeller

c) Shaft

Type of impeller

Is it suitable for direct coupling.

Motor:

Make

Model

R.PM

Rating

Over Load Capacity

Class of Insulation
Details of Additional protection in
winding
Motor Efficiency
Is it suitable for direct coupling to pump
?
Type of rotary movement

Size and type of cable for connections

34.10 SOFT WATER LIFTING PUMP :

Location: STP Room

Description:

Pump:
Quantity
Make
Model

TS-47
Description:

No. of Stages
Head/Stage
Power Requirement
Efficiency
Discharge in LPS
Total Head
Suction end I.D.
Delivery end I.D.
Pump Type
Material
a) Body
b) Impeller
c) Shaft
Type of impeller
Is it suitable for direct coupling
Motor:
Make
Model
R.PM
Rating
Over Load Capacity
Class of Insulation
Details of Additional protection in
winding
Motor Efficiency
Is it suitable for direct coupling to pump
?
Type of rotary movement
Size and type of cable for connections

34.11 MULTIGRADE PRESSURE SAND FILTER:

Location : STP Room

Quantity
Material of construction
Model
Diameter
Height on straight

TS-48
Max. flow rate (Ltr/Sec)
Min. flow rate (Ltr/Sec)
Working pressure

Backwash duration (Minutes)


Back wash flow rate
Pressure drop across the filter Kg/Sq.cm
Max. inlet turbidity (NTU)
Turbidity in filtered water
Velocity of water flowing through filter

Details of filtering media

Source of back wash water

34.12 ACTIVATED CARBON FILTER :

Quantity

Material of construction

Model

Diameter

Height on straight

Max. flow rate (Ltr/Sec)

Min. flow rate (Ltr/Sec)

Working pressure

Backwash duration (Minutes)

Back wash flow rate

Pressure drop across the filter Kg/Sq.cm

Max. inlet turbidity (NTU)

Turbidity in filtered water

Velocity of water flowing through filter

Details of filtering media

Source of back wash water

TS-49
34.13 WATER SOFTENER + BRINK TANK :

Location : STP Room

Quantity

Item No.

Tag No.

Description

Quantity

Make

Model No.

Rated Capacity

Flow Rate (cum/hr)

Input Water Hardness (PPM)

Output Water Hardness (PPM)

Quantity of Resin (Ltrs)

Salt Required per Generation (Kg)

Working Pressure (Kg/Sq.cm)

Test Pressure (Kg/Sq.cm)

Regeneration Cycle

Inlet Max Head (Kg/Sq.cm)

Regeneration

Material of Construction

Pressure Vessel

Pipes

Valves

MOC of Brine Tank

Capacity of Brine Tank (Ltrs)

Dimension of Brine Tank

Inlet Valve Size (mm)

Outlet Valve Size (mm)

Drain Valve Size (mm)

Working Height (Kg)

TS-50
34.14 DOSING SYSTEM:

Location : STP Room

Chlorine Dosing Chlorine Dosing


Poly Dosing
System in for Ultra
System for
Intermediate Filtration
Dewatering
Tank system
a) Chlorine Dosing Pump:

Quantity

Model

Pump Type

Make

Material of construction

Flow rate

b) Dosing Tank:

Quantity

Capacity

Material of Construction

34.15 AIR BLOWER:

Location : Plant Room

Air Blower for Collection


cum Equalization & Sludge Air Blower for SBR 1 & 2
Description:
Holding Tank (AB-1)
(AB-2)
Quantity

Blower Type

Service

Blower make

Blower model No.

Operation

Capacity (fad)

Inlet pressure

Differential pressure

Blower speed

Power consumption

TS-51
Air Blower for Collection
cum Equalization & Sludge Air Blower for SBR 1 & 2
Description:
Holding Tank (AB-1)
(AB-2)
Motor rating

Inlet Temperature

Outlet Temperature

Power Transmission

Specific gravity

Inlet & Outlet size


Material of
Construction
Casing & End Cover
Rotors with Integral
Shaft
Timing gear
Side Plats, cover &
pulley
Sealing

34.16 COARSE BUBBLE MEMBRANE AERATORS:

Description:
Quantity
Location
Make
Model No.
Shape of Aerator
Type of Bubble
Bubble Size
Moc of Membrane
Detail of Fittings for Aerator

Moc of Membrane support

Operating temperature of Membrane

Temperature Tolerance

Type of Air Discharge

No. of Air Discharge Ports

Air flow rate per Aerator

End Connection

TS-52
34.17 FINE BUBBLE MEMBRANE AERATORS :

Description:

Quantity

Location

Make

Model No.

Shape of Aerator

Type of Bubble

Bubble Size

Moc of Membrane

Detail of Fittings for Aerator

Moc of Membrane support

Moc of Membrane clamps

Moc of End Cap

MoC of End Connectors

Size of End Connector

Operating temperature of Membrane

Temperature Tolerance
Effective Surface Area of Membrane per
Aerator
Air flow rate per Aerator

34.18 UV SYSTEM

Description: UV Unit after ACF

NOS OFFERED

QUANTITY

CAPACITY

MAKE

TS-53
35.0 ELECTRICAL WORK:

35.1 SCOPE:

The scope of this section comprises of Design, Manufacturing, supply, erection, testing and
commissioning of Electrical Power/ control panels, Cabling / wiring and earthing of all STP
equipment components and accessories, including supply, installation and wiring of remote
control with indicating lamps.

The following exclusions from this contract may be provided by Owner, through other agencies,
as per special conditions of contract.

i) Wiring and earthing of incoming breakers in the STP control panel

ii) Supply, installation, wiring and earthing of 15 amps three pin socket in vicinity of each Required
miscellaneous equipment. if any and each single phase ventilation fan.

35.2 GENERAL:

Work shall be carried out in accordance with the specifications of local rules, Indian Electricity Act
1910 as amended upto date, and rules issued there under, regulations of the Fire Insurance
Company and Indian Standard Code of practice No. IS: 732-1963 (revised).Wiring for items of
work not covered by any of the above regulations, shall be carried out in accordance with the
CPWD specifications.

36.0 MV SWITCHGEAR PANELS & DISTRIBUTION BOARDS:

36.1 This section shall cover supply, assembly, installation, connection, testing and commissioning of
medium voltage cubicle type MV Switchgear panels as described in these specifications,
drawings and schedule of quantities. The MV Switchgear and Distribution boards are designated
as:

Main Distribution Boards


Sub-Distribution Boards
Motor Control Centers

36.2 MEASUREMENT:

The unit rate per item shall include design supply, assembly, installation, connection, testing and
commissioning of MV Switchgear and Distribution boards, with all the components in place,
internal cabling, as specified in this specification, and shown on the drawing, and load schedule
complete with supply and fixing of M.S. channel / angle iron support on wall/floor etc.

In case of MV Switchgear issued by owner for erection, the unit rate shall include inspection,
receiving, storage, installation, field testing and commissioning activities including co- ordination
with the suppliers of the MV Switchgear. The rate shall be quoted per set of MV Switchgear
panel, as identified in the BOQ. The details of design/Constructional features of these MV
Switchgear panels are specified here below.

36.3 GENERAL :

36.3.1 SYSTEM RATING:

All the Main Panels / MDBs / SMDBs / MCCs / DBs, shall be suitable for operation on three
phase/ single phase, 415/240 volts, 50 Hz neutral solidly grounded at transformer and short
circuit level not less than 65kA/50kA/35kA ( Icu = Ics ) at 415 volt as specified in BOQ.

The Main Panels / MDBs / SMDBs / MCCs / DBs shall be designed to withstand heaviest
condition at site, with maximum expected ambient temperature of 50ºC, 90-95 percent humidity
and dusty weather. They shall not de-rate up-to 50ºC temperature.

TS-54
36.3.2 STANDARDS AND CODES:

The Panels shall comply with the latest edition of relevant Indian Standards and Indian Electricity
Rules and Regulations. The following Indian Standards shall be complied with:

IS 8623-1,2,3 Factory built assembles of switchgear and control gear for voltages upto
and including 1000 V AC & 1200 V DC.

IS 60947-1 L.V. switchgear and control gear - General rules

IS 60947-2 L.V. switchgear and control gear – Circuit Breakers.

IS 60947-3 L.V. switchgear and control gear – Switches, Disconnectors, switch


disconnectors and fuse combination units.

IS 60947-4/1 L.V. switchgear and control gear – Contactors and Motor startors
(Electromechanical)

IS 60947-4/2 L.V. switchgear and control gear - Contactors and Motor startors (AC
semiconductor controllers and starters)
IS 60947-4/3 L.V. switchgear and control gear - AC semiconductor controllers and
contactors for Non-Motor Loads.
IS 60947-5/1 L.V. switchgear and control gear – Control Circuit Devices and
Switching elements – Electromechanical.

IS 60898-1 Electrical Accessories- Circuit Breakers for overcurrent protection for


Household and similar installation – Circuit breakers for AC operation.

IS 60898-2 Electrical Accessories- Circuit Breakers for overcurrent protection for


Household and similar installation – Circuit breakers for AC & DC
operation.

IS 12640-1 RCCB for Household or similar use

IS 12640-2 RCBO for Household or similar use

IS 11353-85 Guide for uniform system of marking and identification of conductors and
apparatus terminals.

IS 60947-1/ Degree of protection provided by enclosures for low voltage switch gear
IEC-60529 and control gears.

IS 2675-83 Enclosed distribution fuse boards and cutouts for Voltages not
Exceeding 1000 V.

IS 2551-82 Danger notice plates.

IS 9926 Fuse wires used in rewirable type Electric fuses upto 650 Volts.

IS 13703 HRC fuse links for voltage above 650V.

IS 2705 Current Transformers(Part- I,II & III)

IS 3156 Voltage Transformers(Part- I,II & III)

IS 13875 Digital measuring instruments for measurement & control

IS 3231 Relays

TS-55
IS-5578 & Marking and arrangement for switchgear, busbars, main connection and
IS 11353 & auxiliary wiring.

36.3.3 SHOP DRAWINGS:

Prior to fabrication of the MV Switchgear Panels / MDBs / SDBs / MCC, the contractor shall
submit following for approval from Engineer / Consultants:

a. GA drawings with dimension and construction details.


b. Schematic Drawings.
c. Control schematic drawings.
d. Bill of Material with Catalogue No., Model No., Rating etc. of equipment and components.
e. Bus Bar sizing Calculations for Temperature rise and Short Circuit withstand capacity.
f. Manufacturer’s Catalogue as required by Engineer / Consultant.

36.3.4 INSPECTION:

At all reasonable times during production and prior to transport of the distribution boards to site,
the contractor shall arrange and provide all the facilities at their plant for inspection by
Engineer/Consultant or authorised representative.

36.3.5 TEST CERTIFICATES:


Following Type Test reports and certificates are required to be submitted by the contractor /
Manufacturer:

a. Temperature rise Test.


b. Short Circuit Withstand capacity.
c. Degree of protection.

Testing of MV Switchgear panels shall be carried out at factory and or at site as specified in
Indian Standards in the presence of Engineer/Consultants the test results shall be recorded on
prescribed forms. The test certificates for the test carried out at factory or at site shall be
submitted in six copies to the Engineer / Consultants for approval.

36.4 CONSTRUCTION:

CUBICLE TYPE MV SWITCHGEAR PANELS / MDBs / SMDBs / MCC:

36.4.1 STRUCTURE:

The MV Switchgear Panels / MDBs / SDBs / MCCs shall be sheet steel enclosed cubicle pattern,
floor mounted free standing, totally enclosed dead front, compartmentalized, multitier, Form 3B
design. The panels shall be extensible type with provision for bus bar extensions. Generally all
MV Switchgear Panels / MDBs / SDBs / MCCs shall be of front access only & suitable for top &
bottom entry of cables unless otherwise specifically specified.

All CRCA sheet steel used in the construction of MV Switchgear Panels / MDBs / SDBs / MCCs
shall be 2mm thick and shall be folded and braced as necessary to provide a rigid support for all
components. Sheet steel shrouds and partitions shall be of minimum 2 mm thickness. Joints of
any kind in sheet steel shall be seam welded, all welding slag grounded off and welding pits
wiped smooth with plumber metal. The height of the panels should not be more than 2400 mm.
The operating levels of the top most cubicle shall not be more than 1800 mm. The operating level
of the lower most cubicle shall not be less than 500 mm.

The MV Switchgear Panels / MDBs / SDBs / MCCs shall be totally enclosed, completely dust and
vermin proof. Gaskets between all adjacent units and beneath all covers shall be provided to
render the joints dust proof. All doors and covers shall be fully gasketed with foam rubber and/or
rubber strips and shall be lockable. Doors shall have concealed hinges.

TS-56
All panels and covers shall be properly fitted and secured with the frame, and holes in the panel
correctly positioned. Fixing screws shall enter into holes tapped into an adequate thickness of
metal or provided with bolt and nuts. Self threading screws shall not be used in the construction
of the MV Switchgear Panels / MDBs / SDBs / MCCs etc.
A base channel of 75mm x 40mm x 5mm thick shall be provided at the bottom. A clearance of
300mm between the floor of the MV Switchgear Panels / MDBs / SDBs / MCCs and the bottom of
the lower most unit shall be provided.

The MV Switchgear Panels / MDBs / SDBs / MCCs shall be preferably arranged in multitier
formation. These shall be of adequate size with a provision of 20 Percent spare space to
accommodate possible future additional switch gear. The size of the boards shall be designed in
such a way that the internal space is sufficient for hot air movement, and the electrical component
do not attain temperature more than 40 degree Celsius above ambient temperature.

Knockout holes of appropriate size and number shall be provided in the MV Switchgear Panels /
MDBs / SDBs / MCCs in conformity with the number, and size of incoming and outgoing
conduits/cables. Size of the terminal connectors and holes in the bus bars shall be suitable to the
numbers and size of external cables.

Alternatively the MV Switchgear Panels / MDBs / SDBs / MCCs shall be provided with removable
undrilled sheet steel gland plates (3mm thick) at top / bottom, to drill holes for cable/ conduit
entry, at site.

The switch boards shall be designed to facilitate easy inspection, maintenance and repair.

The MV Switchgear Panels / MDBs / SDBs / MCCs shall be sufficiently rigid to support the
equipment without distortion under normal and short circuit condition. They shall be suitably
braced for short circuit duty. Provision shall be made for permanently earthing the frames and
other non current carrying parts of the switchgear by two independent earth connections.

36.4.2 PROTECTION CLASS:

All indoor MV Switchgear Panels / MDBs / SDBs / MCCs shall have degree of protection
conforming to class IP 52. While outdoor panels shall be weather proof dust and water tight IP-
55.

36.4.3 METAL TREATMENT & FINISH:

All sheet steel work used in the construction of switchboard shall undergo a 9 tank (min.) process
of degreasing, pickling in acid, cold rinsing, phosphating, passivating and then spraying with a
high corrosion resistant primer. The primer shall be baked in an oven followed by finishing
treatment of two coats of epoxy paint alternatively these shall be powder coated to the specified
shade of IS.5 of approved colour and stoved. Inside the doors shall be painted ivory white, matt
finished. The total thickness of paint shall not be less than 60 microns.

36.4.4 BUS BARS :

The Bus bars shall be of three phase four wire system with separate neutral and earth bar. The
busbars, and interconnection between busbars and various components shall be of high
conductivity, high strength aluminium alloy complying with the requirement of grade 63401
(E91E) of IS 5082. The busbar shall be of rectangular cross section designed to withstand full
load current for phase busbars and half rated / full rated (as per BOQ) current for neutral busbars
and shall be extensible on both sides. The bus bar shall be rated for the frame size of the main
incoming breaker, but in any case not less than 200 amp. capacity. The busbar shall have
uniform cross section through out the length.

The busbars and interconnections shall be coated with heat resistant sleeves & colour coding.
The busbars shall be supported on unbreakable, non hygroscopic insulated supports of FRP
SMC supports at sufficiently close intervals to prevent busbar sag and shall effectively withstand

TS-57
without damage electromagnetic stresses in the event of short circuit. The neutral as well as earth
bar shall also be capable of withstanding the fault level.

The busbars shall be housed in a separate compartment. The busbar shall be isolated with 3mm
thick bakelite sheet to avoid any accidental contact. All busbars connections shall be done by
drilling holes in busbars and connecting by chromium plated brass bolts and nuts. Additional
cross section of bus bars shall be provided in all Panels/ Distribution boards to cover up the holes
drilled in the busbars. Spring and flat washers shall be used for tightening the bolts. Minimum
Clearances between Phase –to - Phase and Phase –to – neutral shall be maintained as per
relevant IS

All connections between bus-bars and circuit breakers/switches and between circuit
breakers/switches and cable terminals shall be through solid copper bus-bars / aluminium bus-
bars / cables of proper size to carry rated full load current and fault current, as defined in the
BOQ/SLD. These strips / bars shall be insulated with insulating heat resistant paint with colour
coding. Current density shall be 0.8Amps/Sq.mm (min.) for aluminium busbars. Contractor to
submit Bus Bar sizing calculations for review and approval. Bus-bar temp. shall not exceed
beyond 85 deg.C (i.e. 35 deg.C above ambient of 50 deg.C)

36.4.5 CIRCUIT COMPARTMENTS :

Each circuit breaker shall be housed in separate compartments and shall be enclosed on all
sides. Sheet steel hinged lockable door shall be duly interlocked with the breaker units in "ON"
and "OFF" positions. Safety interlocks shall be provided for air circuit breaker to prevent the
breaker from being drawn-out when the breaker is in "ON" position.

The door shall not form an integral part of the drawout position of the circuit breaker. All
instruments and indicating lamp shall be mounted on the compartment door. Sheet steel barrier
shall be provided between the tiers in a vertical section. Humidistat controlled, 240V operated
space heaters to be provided in the cable alley.

36.4.6 INSTRUMENT COMPARTMENT :

Separate and adequate compartment shall be provided for accommodating instruments,


indicating lamps, control contactors/relays, and control fuses etc., These components shall be
accessible for testing and maintenance without any danger of accidental contact with live parts of
the circuit breaker units, bus bars and connections.

36.4.7 TERMINALS :

The outgoing terminals and neutral link shall be brought out to a cable alley suitably located and
accessible from the panel front. The current transformers for instruments metering shall be
mounted on the terminal blocks. No direct connection of incoming or outgoing cables to internal
components of the MV Switchgear Panels / MDBs / SDBs / MCCsis permitted, only one
conductor may be connected in one terminal.

36.4.8 WIREWAYS :

A horizontal PVC wire way with screwed covers shall be provided at the top to take
interconnecting control wiring between different vertical sections.

36.4.9 CABLE COMPARTMENTS :

Cable compartments of adequate size shall be provided in the MV Switchgear Panels / MDBs /
SDBs / MCCs for easy termination of all incoming and outgoing cables entering from bottom or
top. Adequate supports shall be provided in the cable compartments to support cables. All
outgoing and incoming feeder terminals shall be brought out to terminal blocks in the cable
compartment.

TS-58
36.4.10 EARTHING :

Aluminium earth bars of suitable size but not less than 25 mm x 6 mm shall be provided in the
Panels/Distribution Boards for the entire length of the panel. The frame work of the MV
Switchgear Panels / MDBs / SDBs / MCCs shall be connected to this earth bar. Provision shall
be made for connection from this earth bar to the main earthing bar coming from the earth pit on
both sides of the MV Switchgear Panels / MDBs / SDBs / MCCsand to take tapping to the
outgoing earthing strips to connect to the main distribution boards.
The earth continuity conductor of each incoming and outgoing feeder shall be connected to this
earth bar. The armour shall be properly connected with earthing clamp, and the clamp shall be
ultimately bonded with the earth bar. CT earthing also shall be connected to this earth bar.

36.4.11 LABELS :

Engraved PVC labels shall be provided on all incoming and outgoing feeders. Single line circuit
diagram showing the arrangements of circuit inside the MV Switchgear Panels / MDBs / SDBs /
MCCs shall be pasted on inside of the panel door and covered with transparent laminated plastic
sheet.

36.4.12 INTERNAL COMPONENTS :

The MV Switchgear Panels / MDBs / SDBs / MCCs shall be equipped complete with all type of
required number of circuit breakers, contactors, relays, fuses, meters, instruments, indicating
lamps, push buttons, equipment, fittings, bus-bars, cable boxes, cable glands etc., and all the
necessary internal connections /wiring as required and as indicated on relevant drawings.
Components necessary for proper complete functioning of the Panels/Distribution boards, but not
indicated on the drawings shall be supplied and installed on the distribution boards. All Control
wiring shall be done with 1.5sq.mm FRPVC insulated copper wires and for CT Circuits, it shall be
done with 2.5 sq.mm. FRPVC insulated copper wires.

All parts of the MV Switchgear Panels / MDBs / SDBs / MCCs carying current including the
components, connections, joints and instruments shall be capable of carrying their specified rated
current continuously, without temperature rise exceeding the permissible values as per the
relevant specifications at any part of the MV Switchgear Panels / MDBs / SDBs / MCCs. Panels
shall be provided with the Cubicle illumination lamps and 5/15 amp. Socket shall be provided in
the Cubicles.

All units of the same rating and specifications shall be fully interchangeable.

36.5 COMPONENTS OF MV SWITCHGEAR PANELS / MDBs / SDBs / MCCs AND DBs:

36.5.1 GENERAL :

The type, size and rating of the components shall be as indicated on the relevant drawings &
BOQ.

While selection of the type and capacity of the components the prevailing site conditions like
room temperature, Humidity, Outdoor/Indoor conditions etc. should be considered. Thermal and
magnetic trip rating shall be compensated for the ambient temperature.

The switchgear ratings indicated on the drawings are anticipated at defined ambient conditions
within the enclosure.

36.5.2 AIR CIRCUIT BREAKERS:

The air circuit breaker shall comply with the requirements of IS:60947-2 and shall meet following
minimum requirements:-

i) Air circuit Breaker shall be suitable for nominal operating Voltage of 415V. ACB shall be
designed and tested for Rated Voltage of 690V and for rated insulation voltage of 1000V.

TS-59
ii) A service short circuit breaking capacity shall be as specified and equal to short circuit withstand
values for one second. All short circuit ratings shall be Ics values (Ics = 100% Icu).

iii) Mechanical and electrical endurance of the Air circuit Breaker should be the best among the
frame size selected for applicable rating.

iv) ACBs shall be rated for Impulse withstand voltage of 12 KV.

v) Electrical overload performance at 6 times the rated current, 110% of the rated voltage as
recovery voltage and 0.5 power factor.

vi) Dielectric test of 2.5 KV applied for one minute on main circuits. Test evidence from a recognized
independent laboratory/institution shall be furnished for compliance of the breakers with the
above requirements.

vii) Each pole of the ACB's shall be equipped with an inverse time delay thermal over current trip
device and an electromagnetic instantaneous over current trip device. The ACB's shall be
equipped with under voltage trip release. The trip devices shall be direct acting. ACB shall be
capable of providing short circuit, overload, and earth-fault protection (in absolute values) if
required, thru microprocessor-based control unit sensing the true RMS values to ensure accurate
measurement meeting the EMI/EMS requirement as per the standard.

viii) Disconnecting devices of approved type shall be provided to facilitate the removal of the circuit
breakers from the housing for test and maintenance purposes.

ix) The ACB's shall be fitted with detachable type re- quenching device on each pole. The ACB's
shall have auxiliary contacts for signaling, interlocking etc. The ACB's shall have slow close
facilities for checking contact operation and contact gap adjustment.

x) All contacts subject to arcing shall be tipped with arc resisting material. Main contacts shall be
silver plated to ensure reliability in service.

xi) Isolating contacts shall be of the silver plated, multi-finger, spring loaded type with minimum
Resistance to achieve minimum watt losses in the Switchgear.

xii) Facilities shall be provided to isolate the circuit breaker for inspection purpose. Feature of contact
wear inspection indicating the life of contacts shall be provided. The ACB shall have double
insulation (class-II) with moving and fixed contacts totally enclosed for enhanced safety and
inaccessibility to live parts.

The breaker shall have three distinct positions with in the cassette as follows:

a) `Service Position' - with main and auxiliary contacts connected.

b) `Test Position' - with power contacts fully disconnected and control circuit contacts
connected.

c) `Isolated position' - With both power and control circuit contacts fully disconnected.

xiii) Interlocks shall be provided to :

a) Prevent the breaker from being isolated unless it is in the OFF position.

b) Prevent the breaker from being racked into the service position unless it is in the OFF
position.

c) Prevent the breaker from being accidentally pulled completely OFF the guide rail.

TS-60
xiv) Safety shutters of an insulation material shall be provided to prevent access to all live contacts,
when the breaker is in the inspection position or completely withdrawn.

xv) Facilities for pad locking the safety shutters when breaker is completely withdrawn shall be
provided. Facilities shall be provided for earthing the circuit breaker.
xvi) Air circuit breaker shall be capable of clearing the maximum fault current which can occur.

xvii) All electrical closing of breaker should be with Electrical motor wound stored energy spring
closing mechanism with Mechanical indicator to provide ON/OFF/Spring Charged status of ACB.

xviii) For all ACBs the operating handle should be provided for charging the spring in continuous
action. The spring shall be released with ON/OFF push button command in one operation at the
correct speed independent of operator speed. A direct mechanical coupling should indicate the
ACB in ON to OFF position thus qualifying to disconnection as per the IS/IEC indicating the true
position of all the contacts.

xix) One set of NO/NC potential free contacts to be provided for operation on building management
system. ACBs should be readily compatible for communication with BMS/SCADA Systems and
remote operation.

xx) ACBs should be suitable for designing and study of fault discrimination between up streams &
down streams breakers.

xxi) All accessories like shunt release, under-voltage release, motor mechanism etc. shall be front
mounted, requiring no adjustments and can be fitted at site.

Emergency panels and Panels supplying to Life Safety System (As per NBC-2016, Part-4) shall
not be provided with U/V release.

36.5.3 MOULDED CASE CIRCUIT BREAKERS (MCCB):

MCCBs shall satisfy the requirements of IS:60947 and shall be of current limiting type. MCCB
shall provide type `C' protection to the contactors as per IEC 158-1B. MCCBs shall be quick
make, quick break, independent manual type with trip free feature with mechanical ON, OFF, and
TRIP indications. A trip button shall be provided for tripping the breaker.

MCCBs shall be suitable for nominal operation voltage of 415V and rated for 690V (min.).

The rated insulation voltage of MCCB shall be 800 V (min.) and it should be suitable for rated
impulse withstand voltage of 8 KV.

MCCB, below 250A, shall have variable thermal and magnetic releases for O/C and Short Circuit
protection. MCCB of 250A and above shall have microprocessor based O/C and S/C protection.

MCCB should be so selected as to achieve total selectivity with both current & time
discrimination.

MCCBs shall be provided with under-voltage, shunt- trip and earth fault releases as per BOQ and
the requirement of system. Emergency panels and Panels supplying to Life Safety System (As
per NBC-2016, Part-4) shall not be provided with U/V release.

Mechanical and Electrical life of MCCBs should be the best among the frame size selected for the
applicable rating.

Isolating contacts of MCCB shall be silver plated with minimum contact resistance so as to
achieve minimum power loss in the switchgear.

Alarm and auxiliary contacts, terminal shrouds, sliding type front operation kit with facility for door
interlocking and pad locking shall be provided.

TS-61
36.5.4 FUSE SWITCH UNITS:

The fuse switch units shall be 3 pole double break type suitable for load break duty, quick make
and break action. Separate neutral link shall be provided in the switch. All fuse switch units shall
be provided with hinged doors duly interlocked with operating mechanism so as to prevent
opening of the door when the switch is in "ON" position and also prevent closing of the switch
when the door is not properly secured. All contacts shall be silver plated and all live parts shall
be shrouded. The incoming and outgoing terminals of switch shall be adequately sized to receive
proper size of cables. High rupturing capacity (HRC) fuse links shall be provided with switch
fuse units and shall be in accordance with IS: 13703 and having rupturing capacity of not less
than 55 MVA at 400 volts. HRC fuse links shall be provided with visible indicators to show that
they have operated. The switch fuse unit shall be manufactured in accordance with IS:60947 as
amended to date.

36.5.5 MINIATURE CIRCUIT BREAKER :

Miniature circuit breakers shall be quick make and break type and conform to IS / IEC 60898-
part-I & 2. The housing of MCBs shall be heat resistant and having a high impact strength. The
fault current of MCBs shall not be less than 10000 amps, at 230 volts. The MCBs shall be flush
mounted and shall be provided with trip free manual operating mechanism with mechanical "ON"
and "OFF" indications.

The circuit breaker dollies shall be of the trip free pattern to prevent closing the breaker on a
faulty circuit.

The MCB contacts shall be silver nickel and silver graphite alloy and tip coated with silver.
Proper arc chutes shall be provided to quench the arc immediately. MCB's shall be provided with
magnetic fluid plunger release for over current and short circuit protection.

The over load or short circuit devices shall have a common trip bar in the case of DP and TPN
Miniature Circuit Breakers. All the MCB's shall be tested and certified as per Indian Standards,
prior to installation.

36.5.6 FUSE :

Fuses shall be of high rupturing capacity (HRC) fuse links and shall be in accordance with
relevant ISS and having rupturing capacity of not less than 55 MVA at 400 volts. The back up
fuse rating for each motor/ equipment shall be so chosen that the fuse does not operate on
starting of motors/equipment.

36.5.7 RESIDUAL CURRENT CIRCUIT BREAKER:

The RCCB shall comply with IS:12640 part-1 / IEC:1008. The RCCB shall be current operated
independent of the line voltage. The RCCB shall be rated for current sensitivity of a min of 30mA
and a max of 300 mA at 230/400 V AC. The terminals shall be protected against finger contact to
IP:20 degree of protection. The RCCB shall have a minimum of 20,000 electrical operations.

a) Testing Provision

A test device shall be incorporated to check the integrity of the earth leakage detection system
and the tripping mechanism. When the unit is connected to service, pressing the test know shall
trip the RCCB and the operating handle shall move to the “OFF” position.

TS-62
36.5.8 CONTACTORS:

The contactors shall meet with the requirements of IS:60947.

The contactors shall have minimum making and breaking capacity in accordance with utilization
category AC3 and shall be suitable for minimum class II intermittent duty.

If the contactor forms part of a distribution board then a separate enclosure is not required, but
the installation of the contactor shall be such that it is not possible to make an accidental contact
with live parts.

36.5.9 VOLTMETER: (Digital)

Voltmeter shall comply with IS 13875 (Latest edition) requirements. The dial of the meter shall be
square in shape 96 x 96 Sqmm.

The voltmeter selector push button shall be arranged to provide line to line voltage reading and
line to neutral voltage reading.

36.5.10 AMMETER: ( Digital)

Ammeter shall comply with IS 13875 (Latest edition). The dial of the ammeter shall be square in
shape of 96 x 96 Sq.mm for main panels. The Ammeter shall be flush pattern with dust and
moisture proof enclosure. Separate current transformer shall be provided for all ammeters.
Selector Push Button shall be provided for measuring current in different phases.

36.5.11 CURRENT TRANSFORMER:

Where ammeters are called for C.T's shall be provided for current measuring. Each phase shall
be provided with separate current transformer of suitable accuracy class and protection class (as
per BOQ and SLD) and suitable VA burden for operation of associated metering and controls.
Current transformer shall be in accordance with IS:2705 as amended up to date.

36.5.12 TERMINALS:

The outgoing terminals and neutral links shall be brought out to a terminal block suitably located
in the control panels. The current transformer for instruments, metering and for protection shall
be mounted on the bus bars. Separate cable compartment shall be provided for incoming and
outgoing cables.Wherever copper cable is connected to the Aluminium bus bar, it should be
through tinned, heavy duty, copper lugs.

36.5.13 WIRE WAYS:

A horizontal wire way screwed covers shall be provided at the top to take in the connecting
control wiring different vertical sections.

36.5.14 CABLE COMPARTMENTS:

Cable compartments of adequate size shall be provided in the control panels for easy termination
of all incoming and outgoing cables entering from bottom or top. Adequate and proper supports
shall be provided in cable compartments to support cables. All incoming and outgoing terminals
shall be brought out to terminal blocks in the cable compartment.

36.5.15 ROTARY SWITCHES:

Switches upto 60 amps shall be rotary type with compact and robust construction, built up from
one or more stacks with contacts and a positioning mechanism, with stop as required. The
terminals shall be shrouded with insulation to prevent accidental contact with live parts. Rotary
switches shall be backed up with moulded type HRC fuse fittings of appropriate rating.

TS-63
36.5.16 SELECTOR SWITCH:

When called for, selector switches of rated capacity shall be provided in control panels, to give
the choice of operating equipment in selective mode.

36.5.17 SWITCHES:

Switches beyond 60 amps shall be panel mounted double break type and suitable for load break
duty, quick make and break action, manufactured in accordance with IEC: 60947, part-3. Switch
contacts shall be silver plated and shall be backed up with HRC fuses of appropriate rating. The
switch handles shall be located at the front.

36.5.18 STARTERS:

Each motor shall be provided with a starter of suitable rating. Starter shall be in accordance with
IEC: 60947, part-4. Direct on line starters / Star-Delta starter / Soft strater shall be provided for
motors as per BOQ.

All starters shall have auxiliary contacts for inter locking, control & indication. Starters (contactors)
shall have 3 main and 4 auxiliary contacts and shall be air break type suitable for making and
breaking contact a minimum power factor of 0.35. For design consideration of contactors, the
starting current of connected motor shall be assumed to be 6 times the full load current of the
motor in case of direct-on-line starters and 3 times the full load current of the motor in case of star
delta/reduces Voltage starters. In case of soft starters the current shall be limited to 1.8 times.

Main and auxiliary contacts shall be silver or silver alloy. The insulation for contactor coils shall be
of class "E". Operating coils of contactors shall be suitable for 240 ± 10% volts AC, 50 cycles
supply system. The contactor shall drop out when voltage drops to 90% of the rated voltage. The
housing of the contactors shall be heat resistant and having high impact strength. Each starter
shall have thermal overload protection on all three phases.

36.5.19 OVER LOAD RELAYS:

Contactors shall be provided with a three element, positive acting ambient temperature
compensated time lagged hand-reset/self reset type thermal over load relay with adjustable
setting. Hand reset button shall be flush with the front door for resetting with starter compartment
door closed, Relays shall be directly connected for motors below

35 HP capacity. C.T. operated relays shall be provided for motors above 35 HP capacity. Heater
circuit contactors may not be provided with overload relays.

36.5.20 SINGLE PHASE PREVENTERS:

Single phase preventers shall be provided as per schedule of quantities and shall be in
conformity with relevant IS standards. Single phase preventers shall act when the supply voltage
drops down to 90% of the rated voltage or on failure of one or more phases.

36.5.21 TIME DELAY RELAYS:

Time delay relays shall be adjustable type with time delay adjustment from 0-180 seconds and
shall have one no. auxiliary contacts for indicating lamp connection.

36.5.22 INDICATING LAMP AND METERING:

All meters and indicating lamps shall be in accordance with the relevant ISS. The meters shall be
flush mounted and draw out type. The indicating lamp shall be LED type. Each main panel shall
be provided with operated ammeter of suitable range with three Nos. CTs of suitable ratio with
three way and off selector switch, phase indicating lamps, and other indicating lamps as called
for. Indicating lamps shall be backed up with 2 Amp. SPMCB.

TS-64
36.5.23 TOGGLE SWITCH:

Toggle switches, where called for, shall be in conformity with IS: 3854-1997 and shall be of 5
Amps rating.

36.5.24 PUSH BUTTON STATIONS:

Push button station shall be for manual starting and stopping of motors/equipment as called for.
Red and Green colour push buttons shall be provided for starting and stopping operations. Start
or stop indicating flaps shall be provided for push buttons. Push buttons shall be suitable for
panel mounting/projection mounting and accessible from front without opening door, lock lever
shall be provided for stop push button. One set of normally open and one set of normally closed
contacts shall be provided in push button stations. The push buttons contacts shall be suitable
for 15 Amps current capacity.

36.6 Tests required to be done at Manufacturer’s work at the time of Inspection:

• Checking of Effectiveness of Mechanically actuating devices, locks, interlocks etc.

• Checking of Proper mounting of devices & switchgears.

• Checking of Proper laying and dressing of cables & wires.

• Checking of clearness between conductors, between conductor & enclosure as per approved
drawings.

• Checking of tightness and proper contact of conductor (Bus Bars, Cables, Wires etc)

• Checking the rating and Model Nos. of ACB/MCCBs/MCBs/SPDs/ CTs etc as per approved
BOM.

• Checking of wiring control & power and ferruling as per control schematic drawings.

• Checking of electrical operation, electrical interlocking, tripping of ACBs through relays & tripping
of MCCB.

• Checking of insulation resistance of :-

Power and control AC circuit & DC circuits.

• Checking of Electrical continuity of protective circuit (body earthing)

• Checking of panel size as per approved drawing

• Checking of DG Set incomer position as per approved drawing

• Checking of bus bar sizes as per approved drawing


• Checking of earth bus bar size as per approved drawing

• Checking of thickness of painting by Elcometer.

• Checking of sheet thickness by Screw gauge

• Checking of provision for dual source energy meter and wire ducts (as applicable)

• Checking of provision for Knocks out for gas flooding system(as applicable)

TS-65
36.7 INSPECTION, INSTALLATION, TESTING AND COMMISSIONING:

36.7.1 Inspection:

• The LT panels / MCC shall be inspected and checked as per inspection manual of the
manufacturer.
• Various electrical components and accessories of the Panels shall be checked as per drawing /
BOM for the respective Panel.
• The Components of LT Panels / MCC shall be checked for rigid mounting, earthing connections,
proper rating and size of components, internal wiring, etc.
• All mechanical fasteners and electrical connections shall be checked and tightened before
installation.
• Type test certificates for all ACB / MCCB for similar rating shall be reviewed.
• Prior to dispatch of the LT panels, following tests shall be carried out :
a) Mechanical endurance test shall carry out by closing and opening of all the ACBs, MCB's
switches etc.
b) Over voltage and Insulation resistance test shall be carried out between phases and
between phases to earth bus, keeping the isolating switch in ON position. Similar test
shall be carried out keeping the isolating switch in closed position.
c) All the interlocks, controls and tripping mechanism of the switch gears shall be
tested for their proper functioning and as per control logics.

36.7.2 Pre-Installation Checks:

• Prior to the commencement of the works, access and installation areas will be inspected to
confirm they are in a suitable condition to commence installation.
• To carry out pre-Installation Inspection of switch-gear panels plinth, for leveling, prior to off
loading and positioning.
• Protection to be ensured, to protect the openings during installation and until the final connections
are made to the Panels.
• Check equipment schedule for correct location and reference for the switchgear and panels.
• If the switchgear or panels cannot be installed immediately, then the same shall be stored in
clean, dry and properly ventilated location.

36.7.3 Installation:

36.7.3.1 Panels Installation Procedure

• Fully crated panels shipped on a timber sub-base will only be lifted under the sub-base, using soft
slings with spreader bars on the topside of the crate. Otherwise the same shall be lifted from
panel lifting Hooks, as per manufacturer’s instruction.
• When the panels has been moved its final destination, it will be un-crated, unpacked and
removed from its timber base.
• Lower panels onto lengths of steel conduit or skate (rolling devices), for movement to final
location.
• Care will be taken to ensure the panels do not un-balance whilst being moved to its final location.
• Once in its final location, rolling devices will be removed from under the panels. Caution will be
exercised against over balancing, while the panels are being moved.
• Finally the panels should be free standing, self supporting assembly, and will be bolted to the
foundation with anchor bolts ensuring the assembly is horizontal and vertically in alignment as
detailed on the construction shop drawings.

TS-66
36.7.3.2 Assembling the Switchgear & Panels At Site

• When the panels are shipped in more than one module, it will be necessary to bolt in individual
section together, as per construction drawing, in the presence of manufacturer/supplier
representative.
• All fishplates to interconnect bus bars will be carefully installed after removing the appropriate
cover plates.
• All connections will be torqued to the required figure as per data from the manufacturer.

36.7.4 Pre-commissioning Checks:

• The panels shall be provided with terminals for both power and control cables. The terminal will
be positioned in such manner as to facilitate optimum access to suit the specified type of entry.
As detailed on the construction/shop drawing.
• Operate all components (i.e.. fuse switches, circuit breakers, contactors, relays etc.) by hand to
ensure that there are no damage to the moving parts.
• A thorough inspection will be carried out to determine that no foreign matter (tools etc.) have
been left in the panels after field installation is completed.
• Particular attention will be given to the Bus-bar compartment, ensuring it is free of debris and
moisture. All compartments shall be thoroughly cleaned.
• All bus-bar and circuit connections shall be checked carefully to find these are tightened and
torqued from the factory, as it is possible for connections to vibrate loose during shipments.
• All connections are checked for tightness/torque prior to energization in accordance with the
manufacturer’s recommendation.
• All components/door interlocks should be adjusted correctly and must operate freely.

36.7.5 Testing & Commissioning:

• Megger tests on the medium voltage bus shall be applied between each phase separately and
ground with other phases tied to ground.
• All breakers shall be racked-out. Each breaker shall be given a megger test in the racked-out and
closed position. Megger tests shall be applied between each phase to ground and to each other
phase.
• A suitable motor driven or electronic megger shall be used. Each test shall be held until a
constant reading is obtained.
• All test readings shall be recorded.
• All circuit breakers shall be operated through at least three (3) open-close-open cycles in both the
rack-in and test positions by manual operation and by control circuits from each control point.
• All indication lights, annunciators, alarms and targets shall be observed to determine correct
operation and breaker mechanism shall be observed for correct alignment, freedom of binding
and good contact.
• All breakers shall be checked for ease of rack-in and rack-out and checked to determine that the
breaker cannot be moved out of operation position while the breaker is closed.
• The interchangeability of the circuit breakers shall be demonstrated.
• PT and CT data shall be recorded and PT and CT circuits shall bechecked with a multi-tester.
• Protective relays shall be adjusted and calibrated with an injection type test arrangement (multi-
amp or equal). Results shall be recorded and the co-ordination of the protective relaying shall be
proved.
• After initial energization, switch gear shall be checked for correct phase sequence.

TS-67
37.0 LT CABLES AND CABLE TRAYS:

37.1 GENERAL SCOPE :

Supply, installation, storing, laying, fixing, jointing / termination, testing and commissioning of
Medium Voltage XLPE/PVC insulated, PVC Sheathed armoured aluminium/ copper conductor
cables laid in built up trenches, directly buried underground, on cable trays, in pipes, clamped
directly to wall or Structures etc. as called for in the drawing.

a) Type :

Medium voltage cables shall be circular, multicore annealed copper or aluminium


conductor, XLPE/PVC insulated, PVC sheathed and steel wire armoured or steel tape
armoured construction or unarmoured. The conductors of cable shall be stranded. Sector
shaped stranded conductors shall be used for cables of 50 sqmm size and above. The
cables shall conform to IS:1554 Part-I and IS:7098 part-I, in all respects.

Conductors shall be insulated with high quality XLPE/PVC base compound. Insulation
and outer sheathing compounds shall conform to IS:5831 – 84.

A common covering shall be applied over the laid-up cores by an extruded sheath of un-
vulcanised rubber compound.

Armouring of galvanised round steel wires or galvanised flat steel strips shall be provided
over the inner sheath.

Outer sheath of FRLSH-PVC shall be extruded over the armouring cables shall be
manufactured and tested in accordance with IS 5831.

Unless otherwise specified, all control cables shall be multicore, 1100V grade PVC
insulated, armoured and overall FRLSH-PVC sheathed with stranded copper conductors
of 2.5 sq.mm, conforming to IS 1554 Part I. Cores shall be identified by colour scheme of
PVC insulation.

b) Rating :

The cables shall be rated for a voltage of 1100 Volts.

c) Core Identifications :

Cores shall be provided with the following colour scheme of XLPE/PVC insulation

1. Single Core : Green yellow for earthing.

2. Two Cores : Red and Black, Blue & Black, Yellow & Black.

3. Three Cores : Red, Yellow & Blue

4. Four Core : Red, Yellow, Blue & Black

d) Selection of Cable:

• Cables sizes shall be selected considering the current carrying capacity, voltage drop,
maximum short circuit duty and the period of short circuit to meet the present and future
anticipated loads.

• While deciding cable sizes, the derating factors for type and depth of laying, grouping,
ambient temperature, ground temperature and soil resistivity shall be taken into account.

TS-68
37.2 STANDARDS :

The following standards and rules shall be applicable.

IS 7098, Part -I, 1988  XLPE insulated LT cables

IS 3975 Mild steel wires, formed wires and tapes from armouring of
cables.
IS 1255 Code of Practice for installation and maintenance of Power
cables upto and including 33 KV ratings.
IS 10418 Drums for Electric Cables
IS 1554  PVC insulated (heavy duty) electric cables Part I for working
voltages upto and including 1100 V.

IS 8130, 1984  Conductors for insulated electric cables and flexible cords.

IS 3961  Recommended current ratings for cables:(Part 2) PVC


Insulated and PVC sheathed heavy duty cables.

IS 5831  PVC insulation and sheath of electric cables.

IS 10810  Methods of Tests for Cables.


IS 4905 Methods for random sampling

The individual cores shall have continuous numbering of the core all along its length and also be
provided with identification ferrules at both ends. Individual control cables shall have 20% spare
cores.

FRLSH cables ( Category – C2) shall be used to prevent flame propagation, smoke reduction
and to avoid toxic gas emission in the event of a fire. FRLSH compound shall be tested
rigorously for oxygen index as per ASTM D2863, acid gas generation to IEC 754-1, smoke
density to ASTM D 2843 and flammability SS 424 1475 class F3, IEEE 383 and IEC 332-1.

Manufacturer's name, ISI Mark, cable size and type shall be clearly embossed at regular intervals
on all cables.

37.3 FIRE RESISTANCE CABLES:

Fire resistance / fire survival cables shall be rated for 600/1000V. The cables shall confirm to the
compliance of BS 7846 for requirement of construction and performance for stranded Aluminium
conductor, armoured, fire resistance cables.

The circuit integrity performance of the cables, under fire conditions shall be confirming to the
category F120 as per BS 7846 and category 3 as per BS 8519. Type test reports of cables to be
submitted for review and approval, before the procurement of material. Cables shall be in
compliance to the following test requirements (as per BS 7846 – 2015):-

a. Resistance to the Fire alone 950 deg.C for 180 min.


(Category F2 test, as per BS 6387-2013, Cat. C, Annex.D.2)

b. Resistance to fire with water 650 deg.C for 30 min.


(Category F2 test, as per BS 6387-2013, Cat. W, Annex.D.3)

c. Resistance to fire with mech. Shock 950 deg.C for 15 min.


(Category F2 test, as per BS 6387-2013, Cat. Z, Annex.D.4)

d. Resistance to fire with mech. Shock and water jet 850 deg.C for 120 min.
(Category F120 test, as per BS 8491-2008, for cable dia. > 20mm.)

TS-69
e. The Fire resistant cables of dia. < 20mm. to be used for fire detection & alarm system,
Emergency Lighting and other life safety system, must meet BSEN 50200 PH 120
classification and Test for 2 hours as per BS 8434-2 with direct flame, indirect impact and
water spray.

Fire resistance / fire survival cables shall have limited evolution of smoke and acid gases, under
fire condition, in compliance to the BS EN 50268 and BS EN 50267-2-1.

Conductor shall be covered with special grade Mica Glass tape suitable to withstand the high
temperature under fire condition. Insulation over the conductor shall be either XLPE (GP 8)
confirming to BS 7655-1-3 OR High Module Ethylene Propylene Rubber HEPR (GP 6) confirming
to BS 7655-1-2. Insulation shall be applied by extrusion process and cross linked to form a
compact and homogeneous layer.

The cores of cables shall be laid – up in the required sequence. The fillers of synthetic material
and binder tapes of glass fiber may be used to form a compact and circular shape of the cable.

Bedding of the cable shall be done with the polymeric material compatible with the operating
temperature of the cable, through the process of extrusion.

Cables shall be provided with single layer of wire armouring of galvanized steel.

The overall sheath of cable shall be an extruded layer of Polymeric material confirming to the
requirements for LTS 1 specified in the BS 7655-6.1.

37.4 INSPECTION :

All cables shall be tested inspected at manufacturers works. However upon receipt at site cables
shall be checked for physical damages during transit.

37.5 JOINTS IN CABLES :

The contractor shall take care to see that all the cables received at site are apportioned to various
locations in such a manner as to ensure maximum utilisation and avoidance of straight cable
jointing. This apportioning shall be got approved by the Construction manager/ Consultant
before the cables are cut to lengths.

Where straight joints in cable are unavoidable, the use and location of such straight joints shall be
got approved by Construction manager/Consultant.

37.6 JOINTING BOXES FOR CABLES :

Cable joint boxes shall be of appropriate size, suitable for PVC insulated armoured cables of
particular voltage rating.

37.7 JOINTING OF CABLES :

All cable joints shall be made in suitable, approved cable joint boxes, jointing of cables in the joint
boxes and the filling in of compound shall be done in accordance with manufacturer's instructions
and in an approved manner. All straight joints shall be done in epoxy mould boxes with epoxy
resin (Tropolin/M-Seal resin or approved equal). All jointing accessories shall be of RACHEM or
approved equal. All terminal leads of conductors shall be Crimped with suitable size Lugs.

All cables shall be joined colour to colour and tested for continuity and insulation resistance
before jointing commences. The seals of cables shall not be removed until preparations for
jointing are completed. Joints shall be finished on the same day as commenced and sufficient
protection from the weather shall be arranged. The conductors shall be efficiently insulated with
high voltage insulating tape and by using spreaders of approved size and pattern. The joints
shall be completely filled with epoxy compound and tapped so as to ensure that the box is
properly filled.

TS-70
Epoxy compound shall be filled as follows :

Equal quantities of resin and hardener shall be mixed thoroughly by hand until the mixture is free
from white patches and has uniform colour. No water, oil or any other liquid shall be added to the
mixture to make it soft as this will affect the properties of the compound. The mixture shall be
used within 30-40 minutes of mixing. The surface on which epoxy compound is to be used, shall
be free from dust, rust, oil, grease and shall be dry. The joint shall neither be disturbed nor moved
till the epoxy compound is completely hardened. A smooth surface can be made by rubbing a
damp cloth smoothly on the compound before it sets. The joints shall be painted after it has
completely hardened.

Alternatively, ready mix of epoxy cable jointing compound may also be used.

37.8 CABLE MARKERS/CABLE TAGS :

37.8.1 Cable Markers:

All underground cables and cable joints shall be marked on the surface by markers generally
manufactured and tested to the requirements of relevant ISS. Approved CI cable markers shall
be provided at every 30m along the route of the cables and at both ends of road crossing,
indicating cable joints and cables as applicable. Special CI markers shall be provided at all
buried cable joints indicating "Electrical Cable Joints". CI plates duly engraved with the size of
the cable and the place it serves shall be tied to the cable at regular intervals of 5m for easy
identification of cables.

37.8.2 Cable Tags:

Cable tags shall be made out of 2 mm thick aluminium sheets, each tag 32 mm in dia with one
hole of 2.5 mm dia. 6 mm below the periphery shall be provided for clamping the same with
cables.

Cable designation are to be punched with letter/number punches and the tags are to be tied to
cables with piano wires of approved quality and size. Tags shall be tied inside the panels beyond
the glands as well as below the glands at cable entires. Along trays, tags are to be tied at all
bends on straight lengths, tags shall be provided at every 5 meter.

37.9 TERMINATION OF CABLES :

Cable termination shall be done in terminal box or cable end box or distribution boards, or
apparatus/equipments. Terminations are to be made with double compression gland and of the
tinned nickel plated, anti- corrosive, three piece improved pattern which is to grip inner and outer
PVC sheaths as well as the armour of the cable. The cable ends or the core conductor are to be
connected by solderless lugs or sockets using crimping tool of approved make for all cables.
Copper cables shall be connected/joined with tinned, heavy duty, copper lugs/sockets. Wherever
Aluminium cables are connected with copper bus bar, bi-metallic, heavy duty lugs shall be used
for termination.

All terminations of cable conductors and base conductors shall be mechanically and electrically
sound and shall comply with the requirements of relevant Standards and Indian electricity
regulations.

The connectors or connecting sockets are to have such dimensions so as to limit temperature
rise.

When required the water tightness of the terminal boxes may be obtained by filling with a
compound preferably plastic flame retarding and non-dripping type within the normal range of
temperatures.

TS-71
When the cable is cut during the course of installation the open ends are to be sealed
immediately by means of self-adhesive non hygroscopic tape over a wax water seal to make an
air and watertight joint.

37.10 INSTALLATION OF CABLES:

Cable shall be laid in a manner as indicated on the drawings. Generally cables are laid in the
following manner.

i. In the underground masonary trench.


ii. On the cable tray/or on cable ladders.
iii. Buried underground.
iv. Through pipe sleeves.

Various installation methods are discussed in the following paragraphs.

Cables shall be laid by skilled and experienced workmen using adequate rollers to minimize
stretching of the cable. The cable drums shall be placed on jacks before unwinding the cable. The
cable drums shall be rotated in a direction as indicated by the manufacturer. Care shall be
exercised in laying cables to avoid forming kinks. The drums shall be unrolled and cables run
over wooden rollers, placed at intervals not exceeding 2 meters.

37.10.1 General

All cables shall be adequately protected against any risk of mechanical damage to which they
may be liable in normal conditions of service.

When cable pass through holes in metal work, precautions shall be taken to prevent abrasion of
the cables on any sharp edges.

In every vertical cable ladders, channel or duct or trunking or cable trench containing cables and
exceeding three meters in length, internal barriers shall be provided so as to prevent the air at the
top of the unit from attaining an excessively high temperature. In every vertical cable shaft, cable
trench or any passage of cable through wall, ceiling, floor barriers against spread of fire and
smoke shall be provided for compliance with IEE regulations. `Viper' CABLEMASTIC fr 903 fire
resistant painting shall be applied on all XLPE/PVC power cables.

Where cable passes through walls, ceiling, floor, it shall run through sleeve of PVC pipes or hume
pipes of adequate diameter. After pulling the cable through sleeve, both the ends of the sleeve
shall be sealed water tight with fire resistance material to prevent spread of fire and seepage of
water.

Generally along each cable route either in trench or in cable trays/ladders or in pipe separate Two
Nos. of earth strips/wires shall run exposed.

Where an installation comprises medium voltage cables as well as extra low voltage circuits,
precaution shall be taken in accordance with relevant regulations and shall be physically
separated by minimum of 300mm distance.

Metal sheaths and armour of all cables, metal conduits, ducts, trunking, and bare earth continuity
conductors associated with such cables, which might otherwise come into fortuitous contact with
other fixed metal work shall be effectively bonded there to earth so as to prevent appreciable
potential difference at such possible points of contact.

37.10.2 Underground Installations

The cables shall be laid in an excavated trench. The depth of the trench shall be minimum 750
mm below the final ground level but shall be decided on the number of cables to be laid in the
trench so that the vertical distance between two adjacent layers of cables shall not be less than

TS-72
350mm. The width of the trench shall be decided on the number of cables to be laid in the trench
so that the distance between two adjacent cables shall not be less than one cable diameter.

a) Width of Trench:

i) The minimum width of trench for laying single cable shall be 350 mm.

ii) Where more than over cable is to be laid in the same trench in horizontal formation, the width of
trench shall be increased such that the inter axial spacing between the cables, except whether
otherwise specified shall be at least 200 mm.

iii) There shall be clearance of at least 150 mm between axis of the end cables and the sides of the
trench.

b) Depth of Trench:

i) Where cables are laid in single tier formation, the total depth of the trench shall not be less than
750 mm.

ii) When more than one tier of cables is unavoidable and vertical formation of laying adopted, depth
of trench in (i) above shall be increased by 300 mm for each additional tier to be formed.

In addition to above, where gradients and changes in depth are unvoidable, these shall be
gradual. The cables shall be protected by placing precast concrete tiles or burnt bricks over the
cables on top layer of sand and for the full length of underground cables. Where more than one
cable is running in the same trench, the concrete tiles/bricks shall cover all the cables and shall
project a minimum of 150mm on either side of the cables.

In any case the top layer of the cables shall be minimum 600 mm below the finished level of the
ground.

The top of the cable trench shall be well compacted till the finished level of the ground and shall
be approved by the Construction manager/Consultant If required a laboratory compaction test
shall be carried out in presence of the Construction manager/Consultant.

H.V., M.V., cables shall not be laid in the same trench/cable tray and/or along side of water main.

Cables under road crossings and any surfaces subjected to heavy traffic shall be protected by
running them through hume pipes of suitable size at a suitable depth.

Where cables cross one another, the cables of higher voltages shall be laid at lower level than
the cable of lower voltage.

The relative position of the cables laid in the same trench shall be preserved and the cables shall
not cross each other as far as possible. At all changes in direction in horizontal and vertical
planes, the cable shall be bent smooth with a radius of bend not less than 15 times the diameter
of the cable. Minimum 3 meters long loop shall be provided at both sides of every straight joint
and 5 meters at each end of the cable. Distinguishing marks shall be made at the cable ends for
identification.

Proximity to Communication Cables:

MV Cables and communication cables shall as per as possible cross at right angles where power
cables are laid in proximity to communication cables the horizontal and vertical clearance shall
not normally be less than 600 mm.

Insulation tapes of appropriate voltage and in red, yellow, and blue colors shall be wrapped just
below the sockets for phase identification.

TS-73
All the excavation and back fill including timbering, shoring, and pumping required for the
installation of the cables shall be carried out as indicated on the drawing and as per requirements
laid down elsewhere or as per Construction manager/Consultant direction. Trenches shall be dug
true to line and grades. Back fill for trenches shall be filled in layers not exceeding 150mm. At
each layer compaction test shall be carried out in presence of Construction manager/Consultant
Each layer shall be properly rammed and consolidated before laying the next layer. The
contractor shall restore all surfaces, roadways, side walls, curbs, walls, landscaping or other
works cut for excavation to their original condition, the satisfaction of the Construction
manager/Consultant. Suitable approved type cable markers shall be installed along the cable
route & wherever change of direction takes place.

37.10.3 Cables Installed Inside the Building

The cables inside the building shall be installed in one of the following manner, as indicated in the
drawing and approved by the Construction manager/Consultant.

37.10.3.1 Installed in Built-up Trench

The cables laid on the bottom of the structural trenches shall not lay freely upon the trench
bottom. They shall be raised to prevent the possibility of their coming into contact with deleterious
materials.

The cables laid in the trench shall be laid on angle iron brackets/cable tray/cable ladder/cable
troughs/cable racks as indicated on the drawings, and as approved by the Construction
manager/Consultant. Where cables are clamped to the wall a minimum clearance of 100mm shall
be maintained between wall and cable and minimum 150mm vertical clearance shall be
maintained between two cables. Where cables are laid on brackets the brackets shall not be
fixed more than 500mm apart to avoid sag in the cables. Where the cables are laid on cable
tray/ladder/troughs /racks, minimum 300mm distance shall be observed between adjacent tier of
tray/ladder/ troughs/racks, and cable shall be fixed minimum 25mm away from the wall, and
minimum of one cable diameter distance shall be observed between two adjacent cables. Cables
shall be properly fixed with the tray/ ladder/ troughs/ racks with cable tie or saddles or straps.

37.10.3.2 Cables on Cable Trays / Ladders under the Ceiling or on Wall

Where cables are installed under above suspended ceiling or below ceiling or on wall, they shall
be laid on a ladder / perforated G.I. cable tray and shall be run in such positions that they are not
liable to be damaged by contact with the floor or the ceiling or other fixtures.

The ladder / perforated cable tray shall be properly fixed with channels, angles, tie rod, flats to the
ceiling. The metal inserts for fixing channels, angles, tie rod, flats shall be put in place while
casting the slab. If insert plates are not placed in position, Anchor fasteners shall be used to
support cable trays if required. The cable tray route shall be co-ordinated with other services to
avoid crisscross of all the services. While laying the cables on the tray minimum one cable
diameter distance shall be observed between two adjacent cables about 20% space shall be kept
spare for any future installation.

The width of the cable tray shall be selected so as to accommodate required number of cables to
be laid on it, with minimum separation of minimum one cable diameter between two adjacent
cables. The cables shall be tied with the cable tray with nylon strip/ Aluminium clamps/GI clamps.

All steel work shall be treated in accordance with the following procedure and in accordance with
IS : 6005 "Code of Practice for Phosphating Iron and Steel".

Oil, grease, dirt and swab shall be thoroughly removed by emulsion cleaning.

Rusting and scale shall be removed by Pickling with dilute acid followed by washing with running
water, rinsing with slightly alkaline hot water and over drying.

TS-74
The phosphate coating shall be sealed by the application of two coats of ready mixed stoving
type zinc chromate primer.

After application of the primer, two coats of finishing stove enameled paint shall be applied.

The final finished thickness of paint film on steel shall not be less than 50 microns and shall not
be more than 100 microns.

Finish painted surface of steel shall present an aesthetically pleasing appearance free from
uneven surface.

The finish painting shall be black matt as per ISS or as approved by consultants.

37.10.3.3 Cables Installed in the Mechanical Room

The cable reaching the motors in the mechanical room or plant room or machines room or service
area shall be laid on cable tray except where indicated in masonry underground trenches.

The unarmored cable reaching the motors shall be protected by rigid galvanized conduits up to a
height of 300mm above the floor. Above that height, the cable shall be protected by means of oil
tight flexible metallic G.I. conduits to the terminal box of the motor. The connection between the
rigid conduit and the flexible conduit shall be done by a screwed coupling of an approved type.
The flexible conduit shall be properly fixed with the terminal box of the motor by means of double
hexagonal check nut.

37.11 CABLE TRAY SPECIFICATION :

37.11.1 GI Cable tray shall be manufactured / fabricated to the design as per IEC 61537 and shall be
tested for safe working load with a span length of 2.5 Mtrs.

Cable trays shall be manufactured from steel as per IS 2062, and galvanised. The thickness of
galvanization shall be not less than 80 microns.

Cable trays shall generally be of the following type:

i. for power cables of medium voltage and high voltage - ladder type with slotted channels.

ii. for control cables and extra low voltage cables - perforated sheet steel type.

Perforated cable trays shall be generally of channel type and the perforations in the trays shall be
either 8 x 15mm or 10 x 20 mm oval holes. Control cables, extra low voltage cables and
instrument cables shall be laid on perforated cable trays.

Ladder type cable trays shall be made out of perforated hot dip galvanised M.S. Sheet 2 mm
thick. The size of the side channel/rails shall be 75x20x2mm hot dip galvanised M.S. Sheet. The
size of the rungs shall be 35x15x2 mm hot dip galvanised M.S. sheet. The pitch of the rungs shall
be not more than 250mm centre to centre. Rungs shall be welded to the side rails as per
requirement.

Cable trays shall be of standard sizes :

Length 2500 mm

Width 150/300/450/600/750/1000mm as required

Side Heights of perforated and ladder type cable trays shall be as per IEC 61537.

Cable trays shall be hot dip galvanised, the thickness of galvanising shall be not less than 80
microns. Quality of zinc used for galvanising shall be 98.8% purity.

TS-75
37.11.2 Accessories for Cable Trays

Following accessories of cable trays, as required, shall be supplied with the cable trays.

Coupler plates

Circular bends - Horizontal and Vertical.

Tees - Horizontal and Vertical.

Reducers

4-way cross

Tray covers

Fasteners.

Accessories also shall be galvanised, thickness of galvanising should not be less than 80
microns.

Fabrication of Tray / Ladder and accessories at site and welding is not permitted. In unavoidable

circumstances, If any cut or holes are made in the trays/Ladder/accessories, zinc spray need to
be applied over the surface. The metal edge has to be protected by edge protection sleeves to
avoid cable damage. Screwed connections and internal fixing Devices should not create any
damage to the cable when correctly fixed.

37.12 TESTING :

Prior to laying cables, and prior to energizing the cables, following tests shall be carried out :-

37.12.1 Insulation Resistance test between phases and phase to neutral and phase to earth with a 500V
megger.

37.12.2 Continuity test of all the phases, neutral and earth continuity conductor.

37.12.3 Sheathing continuity test.

37.12.4 Earth resistance test of all the phases and neutral.

All tests shall be carried out in accordance with relevant Indian Standard Code of practice and
Indian Electricity Rules. The Contractor shall provide necessary instruments, equipments and
labour for conducting the above test and shall bear all expenses in connection with such tests.
All tests shall be carried out in the presence of the Construction manager/Consultant and results
shall be recorded in the prescribed forms.

37.13 STORING :

All the cables shall be supplied in drums. On receipt of cables at site, the cables shall be
inspected and stored in drums with flanges of the cable drum in vertical position. The end of the
cable shall be sealed for water tightness.

TS-76
38.0 EARTHING:

38.1 SCOPE:

All the non-current carrying metal parts of electrical installation shall be earthed as per IS: 3043.
All equipment, metal conduits, rising main cable armour, switch gear, distribution boards, meters,
all other metal parts forming part of the work shall be bonded together and connected by two
separate and distinct conductors to earth electrodes. Earthing shall be in conformity with the
provisions of Rules 32, 61, 62, 67 and 68 of IER 1956.

38.1.1 G.I.PIPE EARTH STATION :

G.I. pipe shall be of medium class, 40 mm dia and 4.5 m length. Galvanising shall conform to
relevant Indian Standards. G.I. pipe electrode shall be cut tappered at the bottom and provided
with holes of 12 mm dia drilled not less than 7.5 cm from each other up to 2 M of length from
bottom. The pipe electrode shall be as far as practicable embedded below permanent moisture
level. Except where rock is encountered, pipes shall be driven to a depth of at least 4.5 mtr.
Where rock is encountered at a depth of less than 2.5mtr the electrode may be buried inclined to
the vertical and the inclinations shall not be more than 30 deg from the vertical. The pipe
electrode shall be made of one piece. Earth leads to the electrode shall be laid in a heavy duty
GI pipe and connected to the pipe electrode with brass bolts, nuts and washers. GI pipe shall be
terminated in a wire meshed funnel. The funnel shall be enclosed in a masonry chamber of 450
mm x 450 mm dimensions. The chamber shall be provided with C.I. frame and CI inspection
cover. The earth station shall also be provided with a suitable permanent identification label tag.
The earth electrode shall conform to IS:3043 latest edition. The soil around the earthing
electrode shall be treated to reduce the resistivity of the soil by filling the complete depth of
electrode with alternative layers of charcoal and salt.

38.1.2 PLATE EARTH STATION :

Plate electrodes shall be made of G.I./copper (CU) plate of 6.30mm/3.15mm thick and 600 x
600mm size. The plate shall be buried vertically in ground at a depth of not less than 4.5 meters
to the top of the plate, the plate being encased in charcoal to a thickness of 300 mm all round. It
is preferable to bury the electrode to a depth where subsoil water is present. Earth leads to the
electrode shall be laid in a heavy duty GI pipe and connected to the plate electrode with brass
bolts, nuts and washers. A GI pipe of not less than 20 mm dia shall be clamped with bolts verti-
cally to the plate and terminated in a wire meshed funnel. The funnel shall be enclosed in a
masonry chamber of 450 mm x 450 mm dimensions. The chamber shall be provided with GI
frame and CI inspection cover. The earth station shall also be provided with a suitable permanent
identifications label tag. The earth electrode shall conform to IS: 3043 latest edition.

38.1.3 EARTHING CONDUCTORS :

All earthing conductors shall be of high conductivity copper/or GI as specified and shall be
protected against mechanical damage and corrosion. The connection of earth electrodes shall be
strong secure and sound and shall be easily accessible. The earth conductors shall be rigidly
fixed to the walls, cable trenches, cable tunnel, conduits and cables by using suitable clamps.

Main earth bus shall be taken from the main medium voltage panel to the earth electrodes. The
number of electrodes required shall be arrived at taking into consideration the anticipated fault on
the medium voltage net work.

Earthing conductors for equipment shall be run from the exposed metal surface of the equipment
& connected to a suitable point on the sub main or main earthing bus. All switch boards,
distribution boards and isolators disconnect switches shall be connected to the earth bus.
Earthing conductors shall be terminated at the equipment using suit able lugs, bolts, washers and
nuts.

All conduits cable armouring etc., shall be connected to the earth all along their run by earthing
conductors of suitable cross sectional area. The electrical resistance of earthing conductors shall

TS-77
be low enough to permit the passage of fault current necessary to operate a fuse/ protective
device or a circuit breaker and shall not exceed 2 Ohms.

38.1.4 EARTHING OF EQUIPMENTS:

Shall be in galvanised Iron Strips/wires, or copper strips/wires as mentioned in Schedule of


Quantities.

a. G.I.Earthing:

The main panel shall be connected to the main earthing system of the building by means of 2
Nos. 25mm x 6mm GI strips. All single phase metal clad switches and control panels shall be
earthed with minimum 3mm diameter GI conductor wire. All 3 phase motors and equipment shall
be earthed with two numbers distinct and independent GI wires/tapes as follows:

i. Motors upto and including 2 Nos. 4mm dia GI wires


10 HP rating.

ii. Motors 12.5 HP to 40 HP 2 Nos. 6mm dia GI wires.

iii. Motors 50 to 75 HP 2 Nos. 25 x 3mm GI strips.

iv. Motor above 75 HP 2 Nos. 25mm x 6mm GI strips

All the switches shall be earthed with two numbers distinct and independent GI wires/tapes as
follows:

i. 3 phase switches and control 2 Nos. 4mm dia GI wires


panels upto 60 Amps rating.

ii. 3 phase switches and control 2 Nos. 8mm dia GI wires


panel 63 Amps to 100 Amps
rating.

iii. 3 phase switches and control 2 Nos. 25 x 3mm GI tapes.


panels 125 Amps to 200 Amps
rating.

iv. 3 phase switches and control 2 Nos. 25mm x 6mm GI


panels, bus ducts above 200 tapes.
Amps rating.

b. Copper Earthing:

The main panel shall be connected to the main earthing system of the building by means of 2
Nos. 25mm x 3mm copper tapes. All single phase metal clad switches and control panels be
earthed with minimum 2mm diameter copper conductor wired. All 3 phase motors and equipment
shall be earthed with two numbers distinct and independent copper wires/tapes as follows:

i. Motors upto and including 2 Nos. 3mm dia copper wire


including 10 HP rating.

ii. Motors 12.5 HP to 40 HP capacity 2 Nos. 4mm dia copper wire

iii. Motors 50 to 75 HP capacity 2 Nos. 6mm copper wires.

iv. Motor above 75 HP 2 Nos. 25mm x 3mm copper wires.

All the switches shall be earthed with two numbers dis tinct and independent copper wires/tapes
as follows:

TS-78
i. 3 phase switches and control panels 2 Nos. 3mm dia copper Wires.
upto 60 Amps rating.

ii. 3 phase switches and control panel 2 x 6mm dia copper wire.
125 amps to 200 Amps rating

iii. 3 phase switches and control panels 2 Nos. 4mm dia copper wires.
63 Amps to 100 Amps rating

iv. 3 phase switches and control panels, 2 Nos. 3mm x 6mm copper.
bus ducts above tapes 200 Amps
rating.

The earthing connections shall be tapped off from the main earthing of electrical installation. The
overlapping in earthing strips at joints where required shall be minimum 75mm. These straight
joints shall be rivetted with and brazed in approved manner. Sweated lugs of adequate capacity
and size shall be used for all termination of wires. Lugs shall be bolted to the equipment body to
be earthed after the metal body is cleaned off paint and/other only substance and properly tinned.

38.1.5 MOTORS:

All motors shall be confirming to energy efficient motors. IS : 12615 – 2018 (Energy Class IE-3).
Motors shall be suitable for (wherever specified) 3 phase, (wherever specified) 415V ± 10%,
50Hz ± 5%, combined variation of ± 10% motors shall be TEFC having class ‘F’ insulation with
temperature rise limited to class ‘B’. Motors, to be used with smoke ventilation Fans, shall be
provided with class “H” insulation. Degree of protection IP 55, motors shall be suitable to work at
500C ambient temperature.

38.1.6 VARIABLE FREQUENCY DRIVE:

38.1.6.1 GENERAL REQUIREMENTS :

a) This specification covers complete variable frequency drives (VFDs) designated on the drawing
schedules to be variable speed. All standard and optional features shall be included within the
VFD.

The VFD shall not be a general purpose product, but a dedicated engineered design required for
the system.

The VFD and its options shall be factory mounted and tested as a single unit under full load
before dispatch.

The VFD shall be tested to UL 508C. The appropriate UL label shall be applied. VFD shall be
manufactured in ISO 9000, 2000 certified facilities.

The VFD shall be CE marked and conform to the European Union Electro Magnetic Compatibility
directive.

The VFD shall be UL listed for a short circuit current rating of 100 kA and labeled with this rating.

The manufacturer shall have been engaged in the production of this type of equipment for a
minimum of thirty years.

The VFD shall be supported locally by the manufacturer who will provide full technical support,
spares holding and trouble shooting capability from their own local facility. A training course shall
be provided by the manufacturer to the consultant / contractor / maintenance engineers.

To ensure adequate technical and factory support, VFDs manufactured by others and brand
labeled shall not be acceptable.

TS-79
38.1.6.2 TECHNICAL REQUIREMENTS :

a) The VFD shall convert incoming fixed frequency three-phase AC power into an adjustable
frequency and voltage for controlling the speed of three-phase AC motors. The motor current
shall closely approximate a sine wave. Motor voltage shall be varied with frequency to maintain
desired motor magnetization current suitable for the driven load and to eliminate the need for
motor derating.

When properly sized, the VFD shall allow the motor to produce full rated power at rated motor
voltage, current, and speed without using the motor's service factor. VFDs utilizing sine
weighted/coded modulation (with or without 3rd harmonic injection) must provide data verifying
that the motors will not draw more than full load current during full load and full speed operation.

b) The VFD shall convert incoming fixed frequency three-phase AC power into an adjustable
frequency and voltage for controlling the speed of three-phase AC motors. The motor current
shall closely approximate a sine wave. Motor voltage shall be varied with frequency to maintain
desired motor magnetization current suitable for the driven load and to eliminate the need for
motor derating.

When properly sized, the VFD shall allow the motor to produce full rated power at rated motor
voltage, current, and speed without using the motor's service factor. VFDs utilizing sine
weighted/coded modulation (with or without 3rd harmonic injection) must provide data verifying
that the motors will not draw more than full load current during full load and full speed operation.

The VFD shall include an input full-wave bridge rectifier and maintain a fundamental
(displacement) power factor near unity regardless of speed or load.

c) The VFD shall have a dual 5% impedance DC link reactor (harmonic filters) on the positive and
negative rails of the DC bus to minimize power line harmonics and protect the VFD from power
line transients. The chokes shall be non-saturating. Swinging chokes that do not provide full
harmonic filtering throughout the entire load range are not acceptable.

VFDs with saturating (non-linear) DC link reactors shall require an additional 3% AC line reactor
to provide acceptable harmonic performance at full load, where harmonic performance is most
critical.

IEEE519, 1992 recommendations shall be used for the basis of calculation of total harmonic
distortion (THD) at the point of common coupling (PCC). On request VFD manufacturer shall
provide THD figures for the total connected load. The contractor shall provide details of supply
transformer rating, impedance, short circuit current, short circuit impedance etc to allow this
calculation to be made.

All VFDs shall contain integral EMC Filters to attenuate Radio Frequency Interference
conducted to the AC power line. The VFDs shall comply with the emission and immunity
requirements of IEC 61800-3: 2004, Category C1 with 50m motor cable (unrestricted distribution).
The suppliers of VFDs shall include additional external EMC filters, if required, to meet
compliance to this requirement.

The VFD’s full load output current rating shall meet or exceed the normal rated currents of
standard IEC induction motors. The VFD shall be able to provide full rated output current
continuously, 110% of rated current for 60 seconds and 120% of rated torque for up to 0.5
second while starting.

The VFD shall provide full motor torque at any selected frequency from 20 Hz to base speed
while providing a variable torque V/Hz output at reduced speed. This is to allow driving direct
drive fans without high speed derating or low speed excessive magnetization, as would occur if a
constant torque V/Hz curve was used at reduced speeds. Breakaway current of 160% shall be
available.

TS-80
A programmable automatic energy optimization selection feature shall be provided as standard in
the VFD. This feature shall automatically and continuously monitor the motor’s speed and load to
adjust the applied voltage to maximize energy savings.

The VFD must be able to produce full torque at low speed to operate direct driven fans.

Output power circuit switching shall be able to be accomplished without interlocks or damage to
the VFD.

An Automatic Motor Adaptation algorithm shall measure motor stator resistance and reactance to
optimize performance and efficiency. It shall not be necessary to run the motor or de-couple the
motor from the load to perform the test.

Galvanic isolation shall be provided between the VFD’s power circuitry and control circuitry to
ensure operator safety and to protect connected electronic control equipment from damage
caused by voltage spikes, current surges, and ground loop currents. VFDs not including either
galvanic or optical isolation on both analog I/O and discrete digital I/O shall include additional
isolation modules.

VFD shall minimize the audible motor noise through the use of an adjustable carrier frequency.
The carrier frequency shall be automatically adjusted to optimize motor and VFD operation while
reducing motor noise. VFDs with fixed carrier frequency or only manually adjustable carrier
frequency are not acceptable.

The VFD shall allow up to at least 100 meters of SWA (Single Wire Armour) cable to be used
between the VFD and the motor and allow the use of MICS (Mineral Insulated Copper Sheath)
cable in the motor circuit for fire locations. VFDs not meeting this requirement of 100meters of
cable length between motor & cable because of generation of high U peak Voltage and high dv /
dt on the motor terminals, which may cause motor windings to fail or significantly curtail it’s life,
shall be compensated with the use of external suitable dv/dt or sine wave filters.

38.1.6.3 PROTECTIVE FEATURES:

A minimum of Class 20 I2t electronic motor overload protection for single motor applications shall
be provided. Overload protection shall automatically compensate for changes in motor speed

Protection against input transients, loss of AC line phase, output short circuit, output ground fault,
over voltage, under voltage, VFD over temperature and motor over temperature. The VFD shall
display all faults in plain English text. Codes are not acceptable.

Protect VFD from input phase loss. The VFD should be able to protect itself from damage and
indicate the phase loss condition. During an input phase loss condition, the VFD shall be able to
be programmed to either trip off while displaying an alarm, issue a warning while running at
reduced output capacity, or issue a warning while running at full commanded speed. This function
is independent of which input power phase is lost.

Protect from under voltage. The VFD shall provide full rated output with an input voltage as low
as 90% of the nominal. The VFD will continue to operate with reduced output, without faulting,
with an input voltage as low as 70% of the nominal voltage.

VFD shall include current sensors on all three output phases to accurately measure motor
current, protect the VFD from output short circuits, output ground faults, and act as a motor
overload. If an output phase loss is detected, the VFD will trip off and identify which of the output
phases is low or lost.

If the temperature of the VFD’s heat sink rises to 80°C, the VFD shall automatically reduce its
carrier frequency to reduce the heat sink temperature. It shall also be possible to program the
VFD so that it reduces its output current limit value if the VFD’s temperature becomes too high.

TS-81
In order to ensure operation during periods of overload, it must be possible to program the VFD to
automatically reduce its output current to a programmed value during periods of excessive load.
This allows the VFD to continue to run the load without tripping.

The VFD shall have temperature controlled cooling fan(s) for quiet operation, minimized losses,
and increased fan life. At low loads or low ambient temperatures, the fan(s) may be off even
when the VFD is running.

Protect from output switching : The VFD shall be fully protected from switching a contactor /
isolator at the output with out causing tripping e.g.: for switching on/off the isolators of the AHU /
ventilation fans / pumps near the motor with VFD in ON mode.

The VFD shall store in memory the last 10 alarms. A description of the alarm, and the date and
time of the alarm shall be recorded.

When used with a pumping system, the VFD shall be able to detect no-flow situations, dry pump
conditions, and operation off the end of the pump curve. It shall be programmable to take
appropriate protective action when one of the above situations is detected.

TS-82
38.1.6.4 INTERFACE FEATURES:

a) Hand, Off and Auto keys shall be provided on the control panel to start and stop the VFD and
determine the source of the speed reference. It shall be possible to either disable these keys or
password protect them from undesired operation.

b) There shall be an “Info” key on the keypad. The Info key shall include “on- line” context sensitive
assistance for programming and troubleshooting.

c) The VFD shall be programmable to provide a digital output signal to indicate whether the VFD is
in Hand or Auto mode. This is to alert the Building Automation System whether the VFD is being
controlled locally or by the Building Automation System.

d) Password protected keypad with alphanumeric, graphical, backlit display can be remotely
mounted. Two levels of password protection shall be provided to guard against unauthorized
parameter changes.

e) All VFDs shall have the same customer interface. The keypad and display shall be identical and
interchangeable for all sizes of VFDs.

f) To set up multiple VFDs, it shall be possible to upload all setup parameters to the VFD’s keypad,
place that keypad on all other VFDs in turn and download the setup parameters to each VFD. To
facilitate setting up VFDs of various sizes, it shall be possible to download from the keypad only
size independent parameters. Keypad shall provide visual indication of copy status.

g) Display shall be programmable to communicate in multiple languages including English.

h) A red FAULT light, a yellow WARNING light and a green POWER-ON light shall be provided.
These indications shall be visible both on the keypad and on the VFD when the keypad is
removed.

i) A quick setup menu with factory preset typical HVAC parameters shall be provided on the VFD.
The VFD shall also have individual Fan, Pump, and Compressor menus specifically designed to
facilitate start-up of these applications.

j) A three-feedback PID controller to control the speed of the VFD shall be standard.

k) This controller shall accept up to three feedback signals. It shall be programmable to compare the
feedback signals to a common setpoint or to individual setpoints and to automatically select either
the maximum or minimum deviating signal as the controlling signal. It shall also be possible to
calculate the controlling feedback signal as the average of all feedback signals or the difference
between a pair of feedback signals.

The VFD shall be able to apply individual scaling to each feedback signal.

For fan flow tracking applications, the VFD shall be able to calculate the square root of any or all
individual feedback signals so that a pressure sensor can be used to measure air flow.

The VFD’s PID controller shall be able to actively adjust its setpoint based on flow. This allows
the VFD to compensate for a pressure feedback sensor which is located near the output of the
pump rather than out in the controlled system.

The VFD shall have three additional PID controllers which can be used to control damper and
valve positioners in the system and to provide setpoint reset.

Floating point control interface shall be provided to increase/decrease speed in response to


contact closures.

TS-83
Five simultaneous meter displays shall be available. They shall be selectable from (at a
minimum), frequency, motor current, motor voltage, VFD output power, VFD output energy, VFD
temperature in degrees, feedback signals in their own units, among others.

Programmable Sleep Mode shall be able to stop the VFD. When its output frequency drops below
set “sleep” level for a specified time, when an external contact commands that the VFD go into
Sleep Mode, or when the VFD detects a no-flow situation, the VFD may be programmed to stop.
When the VFD’s speed is being controlled by its PID controller, it shall be possible to program a
“wake-up” feedback value that will cause the VFD to start. To avoid excessive starting and
stopping of the driven equipment, it shall be possible to program a minimum run time before sleep
mode can be initiated and a minimum sleep time for the VFD.

A run permissive circuit shall be provided to accept a “system ready” signal to ensure that the
VFD does not start until dampers or other auxiliary equipment are in the proper state for VFD
operation. The run permissive circuit shall also be capable of initiating an output “run request”
signal to indicate to the external equipment that the VFD has received a request to run.

VFD shall be programmable to display feedback signals in appropriate units, such as inches of
water column (in-wg), pressure per square inch (psi) or temperature (°F). Examples can be room
temperature in 0C , return air temperature in 0C , supply air temperature in 0C, CO2 concentration
in ppm, pressure in bar, differential pressure in PSI etc.

VFD shall be programmable to sense the loss of load. The VFD shall be programmable to signal
this condition via a keypad warning, relay output and/or over the serial communications bus. To
ensure against nuisance indications, this feature must be based on motor torque, not current, and
must include a proof timer to keep brief periods of no load from falsely triggering this indication.

Standard Control and Monitoring Inputs and Outputs:

i) Four dedicated, programmable digital inputs shall be provided for interfacing with the
systems control and safety interlock circuitry.
ii) Two terminals shall be programmable to act as either as digital outputs or additional
digital inputs.
iii) Two programmable relay outputs, Form C 240 V AC, 2 A, shall be provided for remote
indication of VFD status.
a) Each relay shall have an adjustable on delay / off delay time.

iv) Two programmable analog inputs shall be provided that can be either direct-or-reverse
acting.

a) Each shall be independently selectable to be used with either an analog voltage


or current signal.
b) The maximum and minimum range of each shall be able to be independently
scalable from 0 to 10 V dc and 0 to 20 mA.
c) A programmable low-pass filter for either or both of the analog inputs must be
included to compensate for noise.

l) The VFD shall provide front panel meter displays programmable to show the value of each
analog input signal for system set-up and troubleshooting,

a) One programmable analog current output (0/4 to 20 mA) shall be provided for
indication of VFD status. This output shall be programmable to show the
reference or feedback signal supplied to the VFD and for VFD output frequency,
current and power. It shall be possible to scale the minimum and maximum
values of this output.

b) It shall be possible to read the status of all analog and digital inputs of the VFD
through serial bus communications.

TS-84
c) It shall be possible to command all digital and analog output through the serial
communication bus.

m) Optional Control and Monitoring Inputs and Outputs

i) It shall be possible to add optional modules to the VFD in the field to expand its
analog and digital inputs and outputs.

ii) These modules shall use rigid connectors to plug into the VFD’s control card.

The VFD shall automatically recognize the option module after it is powered up.
There shall be no need to manually configure the module.

Modules may include such items as:

1. Additional digital outputs, including relay outputs


2. Additional digital inputs
3. Additional analog outputs
4. Additional analog inputs, including Ni or Pt temperature sensor inputs.
5. It shall be possible through serial bus communications to control the status of all
optional analog and digital outputs of the VFD.

n) Standard programmable firefighter’s override mode allows a digital input to control the VFD and
override all other local or remote commands. It shall be possible to program the VFD so that it will
ignore most normal VFD safety circuits including motor overload. The VFD shall display
FIREMODE whenever in firefighter’s override mode. Fire mode shall allow selection of forward
or reverse operation and the selection of a speed source or preset speed, as required to
accommodate local fire codes, standards and conditions.

o) A real-time clock shall be an integral part of the VFD.

a) It shall be possible to use this to display the current date and time on the VFD’s
display.

b) Ten programmable time periods, with individually selectable ON and OFF


functions shall be available. The clock shall also be programmable to control
start/stop functions, constant speeds, PID parameter setpoints and output relays.
Is shall be possible to program unique events that occur only during normal work
days, others that occur only on non-work days, and others that occur on specific
days or dates. The manufacturer shall provide free PC-based software to set up
the calendar for this schedule.

c) All VFD faults shall be time stamped to aid troubleshooting.


d) It shall be possible to program maintenance reminders based on date and time,
VFD running hours, or VFD operating hours.
e) The real-time clock shall be able to time and date stamp all faults recorded in the
VFD fault log.

p) The VFD shall be able to store load profile data to assist in analyzing the system demand and
energy consumption over time.

q) The VFD shall include a sequential logic controller to provide advanced control interface
capabilities. This shall include:

a. Comparators for comparing VFD analog values to programmed trigger values.


b. Logic operators to combine up to three logic expressions using Boolean algebra
c. Delay timers.
d. A 20-step programmable structure

TS-85
r) The VFD shall include a Cascade Controller which allows the VFD to operate in closed loop set
point (PID) control mode one motor at a controlled speed and control the operation of 3 additional
constant speed motor starters.

38.1.6.5 OPTIONAL FEATURES:

All optional features shall be built and mounted by VFD manufacturer as an inbuilt factory
solution. All optional features shall be UL listed by the VFD manufacturer as a complete
assembly and carry a UL label.

38.1.6.6 SERVICE CONDITIONS:

a) Ambient temperature at full speed, full load operation with continuous drive rated output current:
i) -10 to 45°C for ratings upto 90 kW without derating.
ii) -10 to 40°C for ratings 110 kW and higher without derating.

b) Relative Humidity : 0 to 95%, non-condensing.


c) Elevation : Up to 3,300 feet without derating.
d) AC line voltage variation : + 10% of nominal with full output.
e) VFD Enclosure protection : IP 55, integral, with no additional cabinets.
f) Side Clearances : No side clearance shall be required for cooling.
g) All power and control wiring shall be done from the bottom.
h) All VFDs shall be plenum rated.

38.1.6.7 QUALITY ASSURANCE:

a) To ensure quality, the complete VFD shall be tested by the manufacturer. The VFD shall drive a
motor connected to a dynamometer at full load and speed and shall be cycled during the
automated test procedure.

b) All optional features shall be functionally tested at the factory for proper operation.

38.1.6.8 SUBMITTALS:

a) This specification lists the minimum VFD performance requirements for this project. Each supplier
shall list any exceptions to the specification. If no departures from the specification are identified,
the supplier shall be bound by the specification.

38.1.6.9 DRAWINGS:

Shop drawings for control panels and wiring of equipment showing the route of conduit/cable
shall be submitted by the contractor for approval of Architect/Consultant before starting the
fabrication of panel and starting the work. On completion, four sets of completion "As-installed"
drawings incorporating all details like, conduit routes, number of wires in conduit, location of
panels, switches, junction/pull and cable route etc. shall be furnished by the Contractor.

38.1.6.10 TESTING:

Before commissioning of the equipment, the entire electrical installation shall be tested in
accordance with Code of practice IS: 732-1963 (Revised) and test report furnished by a qualified
and authorised person. The entire electrical installation shall be got approved by Electrical
Inspector and a certificate from Electrical Inspector shall be submitted. All tests shall be carried
out in the presence of supervisor.

38.1.6.11 PAINTING:

All sheet steel work shall undergo a process of degreasing, through cleaning, and painting with a
high corrosion resistant primer. All panels shall then be backed in an over the finishing treatment
shall be by application of synthetic enamel paint of approved shade.

TS-86
ANNEXURE- A

APPLICABLE CODES, STANDARDS AND PUBLICATIONS

1.0 All equipment, supply, erection, testing and commissioning shall comply with the requirements of
Indian Standards and code of practices. All equipment and material being supplied by the
Contractor shall meet the requirements of IS., Tariff advisory committee’s regulation (fire
insurance), electrical inspectorate and Indian Electricity rules and other Codes/Publications as
given below.

A) General :

SP : 6 (1) Structural steel sections

IS : 27 Pig lead

IS : 325 Three phase induction motors

IS : 554 Dimensions for pipe threads where pressure tight joints are required on
the threads.

IS : 694 PVC insulated cables for working voltages up to and including 1100 V.

IS : 779 Specification for water meters (domestic type)

IS : 782 Specification for caulking lead

IS : 800 Code of Practice for general construction in steel

IS : 1068 Electroplated coatings of nickel plus chromium and copper plus nickel
plus chromium

IS : 1172 Code of basic requirements for water supply drainage and sanitation

IS : 1367 (Part- 1) Technical supply conditions for threaded steel fasteners : Part 1
introduction and general information.

IS : 1367 (Part- 2) Technical supply conditions for threaded steel fasteners : Part 2 product
grades and tolerances.

IS : 1554 (Part- 1) PVC insulated (heavy duty) electric cables : Part 1 for working voltages
up to and including 1100V.

IS : 1554 (Part- 2) PVC insulated (heavy duty) electric cables : Part 2 for working voltages
from 3.3 kV up to and including 11 kV.

IS : 1726 Specification for cast iron manhole covers and frames

IS : 1742 Code of practice for building drainage.

IS : 2064 Selection, installation and maintenance of sanitary appliances - Code of


practice.

IS : 2065 Code of practice for water supply in buildings.

IS : 2104 Specification for water meter boxes (domestic type)

IS : 2373 Specification for water meters (bulk type)

TS-87
IS : 2379 Colour code for identification of pipe lines

IS : 2527 Code of practice for fixing rainwater gutters and down pipes for roof
drainage.

IS : 2629 Recommended practice for hot dip galvanizing on iron and steel

IS : 3114 Code of practice for laying of cast iron pipes

IS : 4111 (Part 1) Code of practice for ancillary structures in sewerage system : Part 1
manholes

IS : 4127 Code of practice for laying glazed stoneware pipes.

IS : 4853 Recommended practice for radiographic inspection of fusion welded butt


joints in steel pipes

IS : 5329 Code of practice for sanitary pipe work above ground for buildings.

IS : 5455 Cast iron steps for manholes.

IS : 6159 Recommended practice for design and fabrication of material prior to


galvanizing

IS : 7558 Code of practice for domestic hot water installations

IS : 8321 Glossary of terms applicable to plumbing work

IS : 9668 Code of practice for provision and maintenance of water supplies and
fire fighting.

IS : 9842 Preformed fibrous pipe insulation

IS : 9912 Coal tar based coating materials and suitable primers for protecting iron
and steel pipe lines.

IS : 10221 Code of practice for coating and wrapping of underground mild steel
pipelines

IS : 10234 Recommendations for general pipeline welding.

IS : 10446 Glossary of terms relating to water supply and sanitation.

IS : 11149 Rubber Gaskets

IS : 11790 Code of practice for preparation of butt-welding ends for pipes, valves,
flanges and fittings.

IS : 12183 (Part 1) Code of practice for plumbing in multistoreyed buildings : Part 1 Water
supply

IS : 12251 Code of practice for drainage of building basements

IS : 5572 Code of practice for sanitary pipe work

IS : 6700 Specification for design, installation, testing and maintenance of services


supplying water for domestic use within buildings and their curtilages.

IS : 8301 Code of practice for building drainage

TS-88
BSEN : 274 Sanitary tapware, waste fittings for basins, bidets and baths. General
technical specifications.

B) PIPES AND FITTINGS:


IS : 458 Specification for precast concrete pipes (with and without
reinforcement)

IS : 651 Salt glazed stone-ware pipes and fittings

IS : 1239 (Part 1) Mild steel tubes, tubulars and other wrought steel fittings Part 1 Mild
Steel tubes

IS : 1239 (Part 2) Mild steel tubes, tubulars and other wrought steel fittings : Part 2 Mild
steel tubulars and other wrought steel pipe fittings.

IS : 1536 Centrifugally cast (spun) iron pressure pipes for water, gas and sewage

IS : 1537 Vertically cast iron pressure pipes for water, gas and sewage.

IS : 1538 Cast iron fittings for pressure pipes for water, gas and sewage

IS : 1729 Sand cast iron spigot and socket soil, waste and ventilating pipes,
fittings and accessories.

IS : 1879 Malleable cast iron pipe fittings

IS : 1978 Line pipe

IS : 1979 High test line pipe

IS : 2501 Copper tubes for general engineering purposes

IS : 2643 (Part 1) Dimensions for pipe threads for fastening purposes : Part 1 Basic profile
and dimensions.

IS : 2643 (Part 2) Dimensions for pipe threads for fastening purposes : Part 2 Tolerances

IS : 2643 (Part 3) Dimensions for pipe threads for fastening purposes : Part 3 Limits of
sizes.

IS : 3468 Pipe nuts

IS : 3589 Seamless or electrically welded steel pipes for water, gas and sewage
(168.3 mm to 2032 mm outside diameter)

IS : 3989 Centrifugally cast (spun) iron spigot and socket soil, waste and
ventilating pipes, fittings and accessories.

IS : 4346 Specifications for washers for use with fittings for water services.

IS : 4711 Methods for sampling steel pipes, tubes and fittings

IS : 6392 Steel pipe flanges

IS : 6418 Cast iron and malleable cast iron flanges for general engineering
purposes.

IS : 7181 Specification for horizontally cast iron double flanged pipe for water, gas
and sewage.

TS-89
C) VALVES :

IS : 778 Specification for copper alloy gate, globe and check valves for water
works purposes

IS : 780 Specification for sluice valves for water works purposes (50 mm to 300
mm size)

IS : 1703 Specification copper alloy float valves (horizontal plunger type) for
water supply fittings

IS : 2906 Specification for sluice valves for water works purposes (350 mm to
1200 mm size)

IS : 3950 Specification for surface boxes for sluice valves

IS : 5312 (Part 1) Specification for swing check type reflux (non return) valves : Part 1
Single door pattern

IS : 5312 (Part 2) Specification for swing check type reflux (non return) valves : Part 2
Multi door pattern

IS : 12992 (Part 1) Safety relief valves, spring loaded : Part 1 – Design

IS : 13095 Butterfly valves for general purposes.

D) WATER QUALITY TOLERANCE :

IS : 3025 Method of sampling and test (physical and chemical) for water and waste
(Part 1 to 44) water

IS : 4764 Tolerance limits for sewage effluents discharged into inland surface waters

IS : 10500 Drinking water

E) PUMPS AND VESSELS :

IS : 1520 Specification for horizontal centrifugal pumps for clear cold fresh water

IS : 2002 Steel plates for pressure vessels for intermediate and high temperature
service including boilers

IS : 2825 Code for unfired pressure vessels

IS : 4682 (Part 1) Code of practice for lining of vessels and equipment for chemical
processes Part 1 : Rubber lining

IS : 5600 Specification for sewage and drainage pumps

IS : 8034 Specification for submersible pump sets for clear, cold, fresh water

IS : 8418 Specification for horizontal centrifugal self priming pumps

TS-90
F) QUALITY ASSURANCE AND QUALITY CONTROL :

1.0 The work shall conform to high standards of design and workmanship, shall be structurally sound
and aesthetically pleasing quality standards prescribed shall form the backbone for the quality
assurance and quality control system.

2.0 At the site level the Contractor shall arrange the materials, their stacking/storage in appropriate
manner to ensure the quality. Contractor shall provide equipment and manpower to test
continuously the quality of materials, assemblies etc. as directed by the Engineer-in-Charge. The
test shall be conducted continuously and the result of tests maintained. In addition the Contractor
shall keep appropriate tools and equipment for checking alignments, levels, slopes and evenness
of surface.

3.0 The Engineer- in-Charge shall be free to carry out tests as may be considered necessary by him
at his sole discretion, from time to time, in addition to those specified in this document. The
Contractor shall provide the samples and labour for collecting the samples nothing extra shall be
payable to the Contractor for samples or for the collection of the samples.

4.0 The test shall be conducted at the site laboratory that may be established by Engineer-in-Charge
or at any other standard Laboratory selected by Engineer- in-Charge.

5.0 The contractor shall transport the samples to the laboratory for which nothing extra shall be
payable. In the event of Contractor failing to arrange transportation of the samples in proper time
Engineer-in-Charge shall have them transported and recover two times the actual cost from the
Contractor’s bills.

6.0 Testing charges shall be borne by the Engineer-in-Charge.

7.0 Testing may be witnessed by the Contractor or his authorized representative. Whether witnessed
by the Contractor or not, the test results shall be binding on the Contractor.

TS-91
ANNEXURE – B

PIPE COLOUR CODE

S.No. Pipe lines Ground Colour 1st Colour Band 2nd Colour Band

Filtered water (all cold water


1. Sea green French blue Signal red
lines after filter)
Drinking water (normal
2. Sea green Light orange
temperature)
Drinking water (chilled
3. Sea green Light orange Signal red
temperature)

4. Domestic hot water Sea green Light grey

5. Drainage Black

6. LPG Canary yellow

7. Fire Lines Red

This colour code is as per I.S. 2379-1983.

TS-92
ANNEXURE – I

SHEET FOR LISTING DEVIATIONS

Although deviations are generally not acceptable, but in case it becomes pertinent as per Vendor, then
he is requested to specifically give the details of deviations, if any on this sheet and continuation thereof
in the below mentioned format only.

Deviation mentioned at any other place shall not be considered.

Item Description
S.No. Deviation by Tenderer/Bidder Approved By
As per Tender

TS-93
LIST OF MAKES FOR SEWAGE TREATMENT PLANT 500 KLD CAPACITY (2 X 250 KLD) BASED ON
SEQUENTIAL BATCH REACTOR (SBR) PROCESS WITH ULTRAFILTRATION SYSTEM

S.N DESCRIPTION MAKE


1 Manhole covers and frames as per IS:1729 NECO / or Approved equivalent
2 D.I. Manhole Covers & Frames NECO / or Approved equivalent
3 G.I.Pipes - Is : 1239 Tata Steel / Prakash Surya / Jindal Hissar
4 PVC Pipe Astral / Finolex / Prince/ Supreme
5 G.I.Fittings - Is : 1239 UNCO / R Brand / Unik / DRP
6 G. I. Pipe Sealent Henkel - Loctite 55 / or Approved equivalent
7 Pipe clamp & supports Chilly / Euroclamp / or Approved equivalent
GM / Forged Brass Valves / Air Release Advance / Audco / Honeywell / Zoloto
8
Valve / LP Valve
Sluice / Butterfly / Non Return Valves /
9 Advance / Audco / Honeywell /LP Valve
Strainers
10 Pressure Reducing Valve Advance / Audco / Honeywell / LP Valve
Zoloto / Advance / Audco / Honeywell / LP Valve /
11 Motorized Butterfly Valves
Danfoss
12 Solenoid Valve Uflow / Aira / Advance / Audco / Honeywell / LP Valve
13 Manual Bar Screens Jash/Micro
14 Hydropneumatic System Grundfoss / Wilo / Xylem / Kirloskar
Clear Water Pump / Transfer Pumps For
15 Grundfoss /Wilo / Xylem / Kirloskar
Water Supply
16 Submersible Pump / Self Priming Pump Grundfoss / Wilo /Xylem / Kirloskar
17 Filter Press DFP / Pharmatech / Sachin
18 Air Diffusers Scogen / Rehau-Germany/OTT
19 Air Blowers Everest / Kay / TMVT
20 SBR Decanter Premiertech / Xylem /
21 Submersible Mixer for Anoxic Grundfos / WILO / Ebara / Aqua (Italy)
22 MS Vessels Thermax/Ion Exchange
23 Screw Pumps Roto/Rotomac/UT
24 Pressure Switches Switzer/Danfoss
25 VFD ABB/Danfoss/Seimens
26 Panel Adlec/Tricolite/Advance
27 Cables Polycab/Havells/Axelon/Finolex
28 Cable Tray National/Profab/Elcon
29 Switchgears ABB / L & T/Seimmens/Scheineder
30 UV Alfaa/Sukrut
31 Digital Turbine Type Flow Meter Aster/Ztech/Electronet/ABB
32 Electromagnetic Flowmeter Aster/Ztech/Electronet/ABB
Anti-Vibration Mounting & Flexible Dunlop / Kanwal Industrial Corporation (Easyflex) /
33
Connection Resistoflex
34 Pressure Gauge H Guru/Waree/Feibig
35 Water Level Indicator / Level Controller Patson / Minilec / Cirrus / Tecnika / Techrol / Auto Pump
36 Level Switch Chaston/Aster/Pune Techtrol

TS-94
37 Fastener Fisher / Hilti
38 Paints Asian Paints / Berger
39 MH / Water Tank Plastic Steps KGM / Supreem / Pranali Industries
40 Dosing Pump E Dose / Asia LMI/Toshcon/Prominent
41 Plastic Tanks Polycon/Vectus/Sintex
42 Skid Mounted UF System / UF Membranes Dupont / SUEZ (GE) / Koch / Qua
43 Geared Motors Moto Vario/Elecon/Rotomotive
List of Approved Makes of Medium Voltage Equipment

S.No Details of Material/ Equipment’s Manufacture Name

Power/aux, contractors/overload relays with


1 Siemens / Schneider/ L&T / ABB
built in single phase preventer
Switchgears
2 Siemens / Schneider/ L&T / ABB
(ACB’s. MCB, MCCB )
Current Transformer
3 Automatic Electric / Precise / Pragati / Matrix
(Epoxy cast Resin)
LED type Indicating Lamps,
4 Technik / Vaishno Electricals / RASS / ESBEE
Push Buttons
5 LT Panel Fabricator Adlec/Tricolite/Advance
6 Bus bar Hindalco
Electronics Digital meter
7 (A/V/PF / HZ/KW/KWH) Siemens / Schneider / L&T
Networkable
PVC insulted XPLE aluminum / copper
8 conductor armoured MV cable up to 1100 V Polycab/Havells/Axelon
grade
9 LT Joining Kit / Termination 3M/Raychem
Cable Glands Double Compression with
10 Dowells / Comet
earthing Links
11 Bimetallic/ copper /Al. cables lug Dowells / Comet /Cosmos
PVC insulted copper conductor stranded
12 Polycab/Havells/Axelon
flexible FRLS wire (pre twisted)
13 Metallic conduit (ISI Approved) AKG / BEC
Cable tray (perforated/ Ladder type )
14 National/Profab/Elcon
/raceway prefabricated
15 Selector Switch, Toggle Switch Kaycess / Slazer / Technik
16 MCCB ABB / L&T / Schneider / Siemens / Nagar

17 Relays / Contactors L&T / ABB / Siemens / Schneider / Automatic Electric

18 Current Transformer Kappa / Pragati / AE / Gilbert & Maxwell

Note- Client & consultant has a right to select any of the make from above list.

TS-95

You might also like