HSE

Observation Report

Date: 27-12-2022
Potential
Location Action required /
S.no Issues Photograph Risk Rectification Close Out Photo
Recommendations
Level
Edge protection has
fixed properly and
signage posted
Contractor need to
provide edge protection Life
Unstable Edge Critical
or any means of fall
1 Basement- protection for the protection fix properly
One
2 elevator pit was working
to prevent the workers day
observed
from falling to a lower
level

WAH & safe work


platform training
given to operatives
Operative was found Contractor need to and warning letter
working unsafe provide a safe & proper Life issued .
while performing the working platform and Critical
Level-2, One
2 job, potential risk of conduct awareness
A02-A working
fall from height training to the workforce day
(repeated by Meras regarding safe working
Operatives ) platform
HSE

Observation Report

Tools have secured


with lanyard and
TBT conducted
with operatives
Contractor need to Non-Life regarding stop the
Observed that hand ensure that all hand Critical drop .
3 Basement- tools are not secured tools used on work at 1>3
2 properly while height activity must be working
working at height secured to prevent from day
falling.

MSRA had already


submitted for
approval .
Contractor must have
approved MSRA in Non-Life
Approved MSRA is Critical
place for every ongoing
4 Basement- not available for activity on site, and
1>3
3 door installation working
carry out the installation day
work
procedure as per the
approved MSRA
HSE

Observation Report

Refresh power tool


safety training given
to operatives and
instructed them
Power tools were Non-Life power tool must be
Contractor need to
found left un Critical disconnect when
conduct refresh training
Basemnet- attendant without 1>3 work finished .
5 to all power tools
2 disconnecting the working
operators of Meras day
power by Meras
about power tools safety
operative

Instructed to HSE
personal regarding
quick response on
the radio .
Tried to Contractor ensure that Non-Life
communicate from all Two way radios must Critical
Basement- the Two way radio , 1>3
6 be in working condition working
3 No response from to respond immediately day
ABCC HSE depart in case of emergency
HSE

Observation Report

Informed to
responsible person
for removal of
Contractor need to files .Material /files
Observed that the Non-Life shifting is ongoing .
ensure that the
files/documents Critical
files/documents must be
Level-1, storage area is open 1>3
7 Stored/secured properly
A02-A and unsecured. working
at designated storage day
Potential risk of fire
area. If not needed must
hazard.
be removed from site.

Housekeeping has
conducted and
waste material
Contractor need to disposed .
advise their sub
Poor housekeeping contractor remove the Non-Life
was observed at waste from site on Critical
A02, A05 1>3
8 several places, regular basis, and working
evidence of Poor maintain a good day
Housekeeping housekeeping at all
over the building
premises

Prepared by:
Mohammed Vajid Ali
HSE

Observation Report

Life Critical Major failure e.g. fatality, LTI, major injury, or Immediate> 1 Working day (if not temporary suspended)
dangerous occurrence
Non-Life Critical Potential Minor injury Incident, Environmental or 1 > 3 working day
Welfare Issue.
Good Practice N/A None however look to share good practice