TITLE OF THE

ACTIVITY: Construction And Installation Of Manhole (Precast)


Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 1 of 10
Date:
INITI CONTROL MEASURES RISK
RISK FINAL
AL (EL – Elimination, RE – Reduction, IS – RATIN
RATING RISK
TASK STEP HAZARDS RISKS RISK Isolation, EC – Engineering Control, AC – CONTROLLER G
LEVE
LEVE Administration Control, PPE – Personal R
S L RR S L L
L Protective Equipment) R

 Safety Induction shall be provided to all


 Lack of training
employees.
 Poor supervision
Inadequate
 Conduct daily TBT prior to commencement of
barriers and
signage may lead work.
to invasion of
unauthorized  Provide HSE internal training to all operatives
personnel/equipm as per required site training matrix.
ent to our work
General safety  Provide proper supervision over workforce all
area.
practices that are
the time.
applicable for all steps  Lack of clear  Operatives being 5 3 15 H Site Supervisor 4 1 4 L
involved in the activity unaware of workplace
access and  Provide means of clear access and egress for
hazards.
egress may lead all operatives.
to entrapment
of operatives  Work area shall be demarcated all the time
during
using suitable barricading equipment and
emergency
conditions signage’s.
 Lack of drinking
 Always follow PTW system.
water and over
exposure to
 Ensure water thermos is issued to all
direct sunlight
may lead to heat operatives those who work directly under
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 2 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
stress for sunlight.
operatives
 Lone working  Ensure compliance to MOHRE summer mid-
and lack of day break.
emergency
preparedness  Verify sufficient number of umbrellas provided
may lead to to teams which work under direct sunlight.
non-compliance
of legal  Follow Buddy system strictly. Lone working
requirements shall not be permitted.
 Poor
housekeeping  Daily Housekeeping shall be done at the end
affects industrial
of every working shift. Waste disposal shall be
hygiene and
increases the done in line with local legal legislations.
risk of fire.
 Lack of PPE may  All employees shall be effectively wearing Site
increase the Mandatory PPE as per site requirement PPE
severity of Code. [That includes safety helmet, Suitable
physical injuries goggles, appropriate respiratory mask, hand
to operatives gloves, safety shoes and cover all (for labour
during category)]
workplace
incidents.  First Aid Kit & First Aider shall be available at
site.
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 3 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
 Emergency vehicle shall be kept ready all the
time

 Skill personnel should be employed


 Poor  The worker should understand the local
communication.  Difficult to response in language.
Mobilization of  Personnel with an emergency.  Ensure young workers should be monitor by a
Foreman/site
personnel Partial disability,  Failure to follow 2 2 4 L competent foreman. 1 2 2 L
engineer
young workers  Safety awareness training should be given to all
workplace safety.
 Less experience  Poor execution of workers.
personnel  Ensure worker are medically fit to carry out
structure.
their task.
 Lack of
communication  Safety orientation to workers, toolbox talk to
 Inadequate worker period to commencement of activity.
 Injury to personnel
General Preparation procedure used  Ensure site engineers and foremen are aware of
 Heavy rain Site in charge,
(surveying)  Incompetent 3 3 6 M weather condition. 1 3 3 L
 High wind project engineer
 Unskilled  Ensure safety warning signages are display
personnel around the working area.
 Weather  Provide shelter to the workers
condition
Loading, transportation  Damage of  Injury to personnel 2 4 8 M  Trained certified operator and rigger, using Site engineer 1 4 4 L
of precast manhole and equipment, loss  Hit by load, falling of tagline
installation of production. load  Ensure equipment suitable for the task and
 Injury due to  Inappropriate lifting competent supervision standby, full body PPE
manual handling and slinging must be worn.
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 4 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
 Barricade the area, conduct tools box and
of materials
inspection of lifting equipment/accessories.
 Harm and
techniques.  Ensure all materials selection should be in
fingers cut
 Hydraulic oil leaks standard of construction.
injury.
 Vehicle movements at  Materials should storage in a designated area
 Falling object
site incorrect and fully barricaded.
from height.
equipment used to  Ensure unloading of materials should be under
 Speeding of
install precast units supervision of a foreman.
vehicle at the
into trench.  Ensure regular maintenance of vehicles
working area.
 Equipment too close to  Manal handling training to all personnel to
 Poor
the edge of trench carryout loading and unloading activities.
maintenance of
causing collapse of  Vehicles should be overloaded.
vehicle and
trench.  Provide proper warning sign board.
heavy
 Make sure all access is clear before start
equipment.
activity.
 Ensure proper PPE must be worn (helmet,
 Toxicity, safety shoes, coveralls, goggles, hand gloves)
handling of  Physical effect in and follow the instructions as per MSDS.
Usage of chemicals human body
chemical,  Ensure that MSDS of chemical are available at
(epoxy coating) improper  Chemical burns to the site/store, all the chemicals waste will be
bitumen board, water 2 3 6 M Workmen 1 3 3 L
access/ egress. users segregated and disposed as per DM
proofing.
 Environmental  Suffocation, contact  Personal hygiene should be maintained by all
pollution, fire with skin and eyes. workers.
hazards  MSDS should be communicated to all through
TBT and provide required first aid kit.
Working in extreme  Adverse  Employee collapses/ 2 4 8 M  Briefing personnel on the symptoms of heat Workmen/ 1 4 4 L
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 5 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
weather stroke / stress and ensure close supervision
requiring medical
condition, heavy standby, monitoring workers
attention/ death, heat
wind, dust,  Training first aider on duty at all time.
weather conditions stroke,
storm, extreme  Shift rotating workers and regular shot rest foremen
heat, humidity periods / cool hydration drinks.
 Dehydration heat
and poor  Working hours will be review based on Dubai
cramps sunburn.
visibility Municipality summer timings
 Ensure full body PPE must be worn at all levels
(respiratory mask, hand gloves, goggles, safety
shoes, coveralls etc.)
 Toolbox talk to raise awareness to all workers.
 Continuous supervision is required to ensure
workers are following safe system of work.
 Eye wash station to be provided and first aid
Dust generating the kid with first aider. Engineer,
 Lung diseases
workplace  Death Respiratory 5 4 20 H  Ensure housekeeping toolbox talk conducted supervisor, PM 5 1 5 L
and dermatitis
system block to all worker, extreme care to be taken while AND HSE Officer.
working on dusty area.
 Appropriate safety personal protective
equipment must always be worn.
 Spray water to reduced dust generating during
demolition activities.
 Warning signs must be displayed at site.
 Barricade the area with safety mesh
Access/Egress  Unauthorized Injury to public. 3 4 12 M Flagman/site 3 1 3 L
entry to site Major injury to workers.  Ensure access to the site must be controlled to supervisor
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 6 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
ensure the safety of all workers and visitor.
 Banksman in place to ensure any awkward
reversing.
 Conduct tools box talk on safe operating
system/speed limits.
 Ensure access and egress routes free from
materials and equipment.
 Vehicle collision
 Ensure mandatory personal protective
 Poor
equipment (PPE)must always be worn (safety
access/egress
helmet, coveralls, safety shoes, Hi-visibility
vest etc.)
 Barriers should be erected around unattended
excavations, secured with sandbags where
necessary and warning signage in place such
as deep excavation, men at work, reduce
speed, warning flashlight etc.
 Ensure manual handling training and
 Fatigue
instruction provided to all workers.
 Ligament
 Eliminate the need of manual handling by
strains, muscle
Manual handling using mechanical aids wherever possible. Workmen and
strains  Death, injuries 3 5 15 M 3 1 3 L
 Assess the load and weights marked on all supervisor
 Abdominal
loads.
hernias.
 Personal protective equipment must be worn
 Hand injury
(hand gloves)
Pouring of concrete  Fall from height  Personnel injury 2 3 6 M  Ensure shoring is in place and check by Site in charge, 1 3 3 L
 Falling of object competent personnel. project engineer
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 7 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
 Do not overload the mortar pan.
 Ensure concrete mixer machine is not keep
near the edge of the excavation area
overload.  Provide ladder for access and use manual
handling technique to carry smaller load.
 Provide barriers and handrail to prevent slip,
trip and fall.
 Fall fr5om
height.
 Ensure all scaffolding materials should be
 Falling object.
transferred from lower level to higher level
 In adequate
through buckets
experience Workmen, site in
Erection of scaffolding  Injury to personnel  Ensure scaffolding erection should be
scaffolder 2 4 8 M charge, safety 1 4 4 L
scaffolding collapse. monitored by a competent supervisor.
 In adequate officer
 Scaffolding tubes should not have any bends.
base plate.
 Ensure safety harness must be worn at all time
 In appropriate
while working at height
bracing for
scaffolding
Installation of precast  Improper  Injury to personnel, 2 10 20 H  Ensure competent supervisor and adequate Workmen 1 10 9 M
units and support storage of back ache. inspection provided training instruction,
reinforcement  Back sprain conduct toolbox meeting prior to start the job
bars and usage of appropriate PPE.
 Inhalation of  Ensure toolbox training to all the workers, on
particles work at height/lifting and the use of PPE at site.
 Fall from height  Ensure all workers are using safety harness to
 Slip, trip and fall avoid fall from height and adequate warnings
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 8 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
signs in place.
 Safe working platform should be provided,
 Lack of training
guard rails should be in place
and experience.
 Ensure proper access egress (Ladder provided
and secured)
 Ensure worker should take extreme care while
working on wet soil.
 Movement of  Fatality or injury to  Curing should be done in a specific time.
Curing of precast units. water tanker workers, damage to  Operators /driver should have valid license, Site in charge,
2 3 6 M 1 3 3 L
 Slip/Trip machinery, vehicle and relevant certificates for equipment and vehicle. project engineer
 Wet soil property.  Ensure flagman standby, control the movement
of water tanker, reverse alarm and light should
be in good working conditioned
 Hazardous wastes should be stored in
designated areas and label with signage
 Conduct training on safe handling of
Waste hazardous materials and the important of
 Contamination of HSE / PM
Materials/Hazardous  Environment PPEs (safety hand gloves, dust mask, full body
environment /damage 4 3 12 M Engineers and 4 1 4 L
Wastes Impact coveralls, safety helmet, goggles etc.)
to natural flora. workmen
 Safety signages should be at place, segregated
and disposed as per DM guidelines.
 Ensure housekeeping should be maintained at
all level and proper materials storage at site.
Emergency situation  Fire and  Body 3 5 15 H  Emergency access route shall be kept always Workmen, HSE, 3 1 3 L
Explosion injuries/Fatality/Severe free from obstruction. PM, Engineer and
 Fumes/smoke, burns, property  Emergency contact numbers to be affixed at pedestrians or
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 9 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
Earthquake/ prominent locations.
nearby building  HSE Training on emergency situation.
collapse,  Emergency Cluster point shall be identified
damage pass by.
riots/accident and signposted accordingly.
etc.  Emergency procedure must be shared on
Toolbox Talk Scenario based drill.

RR: Risk Rating Likelihood


Likelihood (L) (LxS)
Severity (S) RISK LEVEL =
(% of Compliance) Resultant Risk Level 0 1 2 3 4 5
being either High,
Medium or Low.

1 91 to 100 1 First-aid case 1–4 Low 1 1 2 3 4 5

2 81 to 90 2 Minor (Hospital referred) 2 2 4 6 8 10

Severity
5 – 10 Medium
3 71 to 80 3 Reportable (3 - 21 days medical rest) 3 3 6 9 12 15
4 25 to 70 4 Major (Hospital admission/≥21 days medical rest 4 4 8 12 16 20
12 - 25 High
5 0 to 24 5 Fatality 5 5 10 15 20 25
TITLE OF THE ACTIVITY: Construction And Installation Of Manhole (Precast)
Asses.
Assessment Number: QRC-RA-001 27/10/2022 Revision Date: 00 Page Number: 10 of 10
Date:
RISK CONTROL MEASURES RISK
INITIA FINAL
RATING (EL – Elimination, RE – Reduction, IS – RATING
L CONTROLLE RISK
TASK STEP HAZARDS RISKS Isolation, EC – Engineering Control, AC –
R RISK R R LEVE
S L Administration Control, PPE – Personal S L
R LEVEL R L
Protective Equipment)
Legal Reference: Chapter 5, Federal Labour Law (8), UAE 1980/ Ministerial Order No. 32, UAE 1982/ Code of Construction Safety Practice, Dubai 2008

Prepared by Approved by
Workmen Representative
Risk Assessment Committee/ HSE Management Representative/ Project Manager

Name & Name & Name &


Designation Designation Designation

Signature Signature Signature