Dear Sir,
Please go ahead.
Thanks & Regards,
Durga Prasad Pattanaik
Dear Sir,
Please find attached MS, Checklist & Approved JSA for Bridge finishing work. We have already done
the sample at Br. 70 jointly. KIndly approve the same to start the activity.
Biranchi Mohanty
Assistant Manager-Quality (BU-Railways)
This Email and any attachments therewith are for the sole use of the intended recipient(s) and may
contain confidential and privileged information. If you are not the intended recipient, please notify
the sender immediately and destroy / delete this message or copies thereof and any attachments
therewith. Any unauthorized use, disclosure or copying of this message and the attachments
thereto (in whole or part), in any manner is strictly prohibited and may constitute unlawful act.
While KEC takes reasonable precautions to protect its IT Systems, the recipient acknowledges that
emails could be illegally intercepted, corrupted, lost, destroyed, arrive late or incomplete or contain
viruses and in such an event KEC will not be liable for any errors, omissions, viruses, damages in the
contents of such message and attachments therewith.
https://outlook.office.com/mail/sentitems/id/AAQkAGNkOTkwNjA1LTcwZDUtNDA5ZC1hNjA5LThiYzgyMWIyY2FmZAAQACPUz1pV0gxMrvGGO… 1/1
METHOD STATEMENT FOR BRIDGE FINISHING WORK 1
This Method statement details the procedure for the repairing and touchup works of minor
bridges & HPC Culverts of Dhamra Railway Doubling project.
2. MANPOWER REQUIRMENTS
Supervisor
Charge hands for Grinding
Chipper, mason, Helpers as per site requirement
3. MATERIAL REQUIRMENTS
Fosroc Nitobond SBR
Asian/Berger/Birla waterproof putty (Exterior)
OPC 53 Cement
Fine Sand (Zone-III & IV)
4. EQUIPMENT REQUIREMENT
Honda DG
Dewatering Pump
AG7 grinder & AG4 Grinders
Painting brush/Roller
Putty plates (Putty Patti)
Small mason trowel
Chisel & Hammer
Wire brush & Cotton cloth
Iron Pan
Curing shall be done on repairing area for 3days. After curing, surface shall be smoothened
by grinding with GC-120 wheel & AG4 grinders.
The same shall be get checked by client representative and after confirmation, 2 coats white
wash will be applied using Berger/Asian/Birla base distemper mixed water.
The final bridge shall be checked by client representative and RFI will be certified.
6. RESPONSIBILITIES
Find out the scope of repairing at any bridges and arrange a pre-visit inspection with
client and discuss about the repairing method.
Ensure the effective works are carried out according to SOP and all the equipment
required to execute the works are available as per the methodology.
Ensure the proper mixing of paste with Nitobond SBR.
Co-ordinate with the client for the ongoing repairing/stage checking if any
After completion of repairing the RFI closing from client.
DHAMRA RAILWAY DOUBLING PROJECT
OPERATIONAL RECORDS FOR SITE
Format No. -KEC/DHAMRA-RLY/BFW/36
Package:- Phase-2
Drawing No.: