(RFI)
Engineer's Signature:
Consultants Comments:
5 Architect 5 Structure 5 MEP&F 5 Infrastructure 5 Others (_________)
WWP Response-- As per ARCH. Intent , we are OK with Crank beam (MB +10.308). Accordingly RC pardi is not required.
Consultant's Signature:
Authorized Signatory
Name:
Signature:
Date:
Important: Permission to proceed does not relieve contractor from full compliance with contractual obligations