Risk evaluation for the Installation of Distribution Poles (Dungu Sarki).

POTENTIAL HAZARD PEOPLE AT RISK MEASURES PUT IN PEOPLE WHO ARE


PLACE RESPONSIBLE

Pole Collapse Workers, House Measures are taken to


resident, People guarantee that
Around individuals maintain a
safe distance from the
erection of poles.

In instances where a
pole is being erected in
close proximity to a
residential dwelling,
measures are taken to
evacuate the occupants
prior to commencing
the operation.

Security personnel are


stationed alongside the
Hiab equipment in order
to manage and regulate
any potential crowds.

Suspended Load Workers It is guaranteed that no


individuals are
positioned beneath a
suspended weight.

Mechanical Failure The Hiab undergoes a


thorough inspection
every morning prior to
the commencement of
work, encompassing
checks on its brakes,
hydraulics, oil and fuel
levels among others.

Dust Workers It is ensured that the


workers are using nose
mask.

Breaking of Pole Gentle lifting techniques


are employed to
prevent the risk of pole
breakage.

Poles not erected The Site and Distribution


properly Leads are responsible
for ensuring that the
poles are erected in a
precise and vertically
aligned manner.

Assessed by Awa Precious Osariemen (HSE OFFICER)