MINISTRY OF PUBLIC WORKS FICHTNER
EVN Group
TECHNICAL SUBMITTAL
CONTRACTOR'SSIGNATURE
REQU^TE.D BY: REVIEWED & APPROVED BY:
^^
ip Kuf(iaran Erasmo Vellucci
^
QAQC Mechanical Engineer Project Manager
Distribution
. Client Buyer's Engineer . Project Company I Contractor a Others:
DOCUMENT REVISIONHISTORY
DESCRIPTION
REVNO. DATE OUR TRANSMITTAL THEIR TRANSMITTAL
BUYER'S ENGINEERREVIEW
DOCUMENT REVIEWSTATUS [_| Approved Approved as Noted Not Approved
COMMENTS
REVIEWED BY:
-tk
I - Information
"Approval Status: Approved
A -Approval Approved as Noted
Not Approved
Sub-Contract: Delivery, Assembly & Commissioning Supervision of Lime dosing station Date: 11/12/2022 SUB-CONTRACTOR:
Activity Name: Installation of Lime Dosing system SCHAUB Umwelttechnik GmbH
Structure Identification: Building / Position 21.1 / 21.3
Location: UAH Plant
Nature of Inspection Inspection Authority
H - Hold Point: A critical operation that must be inspected and formally approved before any further work can proceed.
S - Surveillance: A point where site inspection is carried out without any required notification or formal record. 1 - SCHAUB 3 - Buyer's Engineer (BE)
W - Witness Point: A point where site inspection is carried out after giving notification to the specified party to witness. 2 - WTE 4 - Third Party / MPW
R - Record Review: A critical operation that required documents to be submitted and reviewed for approval.
Item Inspection
Test / Inspection Activity Description Reference Document Form of Record Testing Reference Frequency Activity Acceptance Crieria Remarks
No.
1. SCHAUB 2. WTE 3. BE 4. [Client]
2.0 Installation
Equipment Drawing
2.1 Foundation release for Equipment erection Shop Drawing Civil survey report Shop Drawing 100% H S S S
Assembly Instructions
Equipment Drawing
Equipment Drawing Equipment Drawing
2.6 Electrical & Instrumentation installations and final check Equipment Drawing Control panel 100% H W W S
Installation manual Assembly Instructions
diagram
22.11.2022
121.114 – lime milk plant – WTE Kuwait
Confidentiality
This document and all information contained therein must be treated with absolute confidentiality. No infor-
mation contained herein may be replicated or disclosed to third parties without the consent of the author.
_______________________________________________________________________________________
www.schaub-systems.com
Seite 1 von 9
121.114 – lime milk plant – WTE Kuwait
Seite 2 von 9
121.114 – lime milk plant – WTE Kuwait
CONTENT
1 In general ......................................................................................................................................................... 4
2 Main devices .................................................................................................................................................... 4
3 Weight of the main parts ................................................................................................................................. 4
4 Hoisting devices ............................................................................................................................................... 5
5 Assembly of the plant ...................................................................................................................................... 5
5.1 Silo ........................................................................................................................................................... 6
5.2 Slide gate, rotary feeder and screw conveyor ......................................................................................... 8
5.3 Lime slaking and dosing tanks .................................................................................................................. 8
5.4 Wet scrubber, vapor suction side pipe and clean gas pipe ...................................................................... 8
5.5 Piping ....................................................................................................................................................... 8
5.6 Electrical installation ................................................................................................................................ 8
5.7 Compressed air supply ............................................................................................................................. 9
5.8 Instrumentation ....................................................................................................................................... 9
6 Use of the assembly parts list .......................................................................................................................... 9
________________________________________________________________________________________
ANNEX:
1) 121.114_Versandstückliste Linie 1_final
2) 121.114_Versandstückliste Linie 2_final
3) 2413-h_PID_Lime-slaking-plant_1
4) 2413-h_PID_Lime-slaking-plant_2
5) 2416-d_Arrangement_WTE-Kuwait-plant_1
6) 2416-d_Arrangement_WTE-Kuwait-plant_2
7) 07_94924 A17057 WTE Kuwait plant 1_wiring-diagram_2022-07-14_en_EN_C
8) 07_94924 A17057 WTE Kuwait plant 2_wiring-diagram_2022-07-14_en_EN_C
9) 05_2416-d_Arrangement_WTE-Kuwait-plant_1 – electrical
10) 05_2416-d_Arrangement_WTE-Kuwait-plant_2 – electrical
Seite 3 von 9
121.114 – lime milk plant – WTE Kuwait
1 IN GENERAL
Take care on the accident prevention regulations at site. The work must be carried out by qualified skilled workers.
The fitter must wear the conformable protective clothing.
The assembly of the devices is carried out according to the drawings listed at the end. All flange connections must
be carried out stressless.
For the assembly all documentation of the single parts should be taken into consideration.
2 MAIN DEVICES
4 HOISTING DEVICES
The hoisting devices have to be dimensioned according to the local conditions. The devices have to be handled
professional. The devices must be handled at the suspension points.
Staying under suspended loads is strictly prohibited. General regulations and rules for reducing and preventing
hazards must be observed.
The assembly of the plant must be carried out according to the arrangement drawings and the flow sheet (PID).
For the assembly, please take also care to each operation manual of the single parts. The components of the plant
will be mounted according to the lime path (starting at the silo). First the whole plant will be positioned and
aligned. If all components are aligned, they will be fixed on the platforms and foundations. All flange connections
must be carried out with a sealing.
The assembly of the plant should follow these written assembly steps. According to space problems and local
conditions the assembly process can vary.
Seite 5 von 9
121.114 – lime milk plant – WTE Kuwait
5.1 Silo
To assemble the silo it is necessary to have two cranes. The silo should be assembled at the foundation. All small
parts like filling pipe, cable tray, ladder, measuring equipment can be assembled while the silo is lying. After
that, the discharge bottom can be assembled to the silo.
Figure 1
Figure 2
The 1st bigger crane brings the silo now into an upright position during the 2nd small crane supports the silo on
the feet.
Seite 6 von 9
121.114 – lime milk plant – WTE Kuwait
Figure 3
After the silo is in upright position the silo gets placed by the 1st bigger crane on its final position and can be fixed
at the foundation. Please urgently observe the height of the silo flange to the ground, otherwise problems may
occur with the following components! The anchoring of the silo can be seen in the static calculation of the silo.
The crane must hold the silo until the anchor bolts are tightened. After that, the rest of the filling pipe, the railings
and the filter can be adjusted and assembled. For the installation of the components of the silo please see “2416-
d_Arrangement_WTE-Kuwait-plant_1” and “2416-d_Arrangement_WTE-Kuwait-plant_2”.
The anchoring must be grouted directly after installation. At the latest before the first filling of the silo, this grout-
ing must have hardened.
Seite 7 von 9
121.114 – lime milk plant – WTE Kuwait
Flange the slide gates on the discharge bottom and the rotary feeders (ldoUH620/720) under the construction of
the silo-feet. The sealing of the flange connection is carried out by a Teflon sealing. The screw conveyors
(ldoUH630/730) have to be assembled to the rotary feeders and the support on the slaking tank and the support
by the chain on the silo feet. This step can just be done, when the two tanks are on their position. The inlets of
the screw conveyors are carried out with loose flanges, so that the position can be adjusted as needed.
For the installation of these components please see also the arrangement drawings.
The lime slaking tanks should be aligned according to the outlet of the screw conveyor (ldoUH630/730) and the
arrangement drawing. The slaking tank must fit to the dosing tank. Before the tanks are fixed to the floor, the
other large components are to be positioned, consisting of: Wet separator and pump cabinet. When these com-
ponents are placed without collisions, they can be mounted to the floor. After assembling the tanks, the agitators
can be brought in. Now the remaining accessories of the tanks (overflow and drainpipe, compensators) can be
assembled.
5.4 Wet scrubber, vapor suction side pipe and clean gas pipe
The wet scrubber components are pre-assembled and have to be aligned and sealed on site. The final fixing of
the wet scrubber on the floor will be done after the vapor suction side pipe is installed on the dosing tank and
connected to the wet scrubber. For adjusting the height of the wet scrubber, there is a small platform for the wet
scrubber.
After this, the fan with its adapter pieces can be put and screwed on top of the wet scrubber. Between these
components, a sealing by using Teflon strips is foreseen. According to the Arrangement drawings the clean gas
pipe can be done, after mounting the fan with its adapter pieces. The pipe can be assembled as shown on the
drawings. The supports for the pipes can be assembled as needed according to the local conditions at site. For
each direction of the pipe we delivered insert pieces for adjusting the length.
In order to avoid damages at the devices, the Instrumentation, which is not preassembled, will be installed at the
end. The instruments will be installed at the connections according to the flow sheet and the assembly drawings.
The complete instrumentation, which are delivered by SCHAUB, are shown in the assembly parts list.
5.6 Electrical installation
The electrical installation with its cable trays and cables can be done.
Seite 8 von 9
121.114 – lime milk plant – WTE Kuwait
- On the assembly parts list are all parts listed, which are needed for the assembly of the plant.
- The main packages are marked.
- The positions under the main package are the single parts, of which the package consists of. All these
parts belong to this function unit.
- The screws, nuts… under a position, belongs to this position.
- If possible, the single parts will be pre-assembled to a unit.
- All parts will be delivered at site with the position numbers marked on it .
- The package number is written in the second column.
Seite 9 von 9