Professional Documents
Culture Documents
1.1 GENERAL
This method statement shall be viewed with the NCRTC document for Method Statement of Slab
Track System for PORR Slab in the Underground Section. The Floating Track Slab with discrete
bearing for the Steel Spring MSS system is supported on the 1st stage concrete/ tunnel invert (U/G
track) by means of a steel spring element to transfer the load to the substructure. These discrete
bearings are all-time accessible from the top and provide advantages for night maintenance. This
Document shall be read in conjunction with latest revisions of all the drawing and documents
indicated in reference.
The surface of 1st stage concrete tunnel invert (U/G track) shall be cleaned of any loose material,
dust, and debris. There should not be any undulations/ extrusion like nails, metal wire gravels, etc.
exceeding 2-3mm in height, water should not be present on the surface. The location of Steel
Springs shall be marked by GERB personnel and the surface shall be made flat (trowel-finish) within
a tolerance of ± 3 mm.
In case top of first stage concrete differs (higher or lower) from the desired the level accounting
tolerance as stated above, same shall be made good to required level by chipping or grouting with
Fosroc Conbextra GP2 or equivalent make and grade in a band of 600 mm wide i.e. 300 mm on
either side of center line of GSI or KYM elements as marked at site and for a full width of 2500 mm
of floating slab i.e. 1250 mm with respect to floating track slab center line as shown in below section.
Fig 6 – Schematic Details for Levelling (600 mm x 2500 mm) at MSS Locations
The track drainage shall be provided on the second stage concrete as per drainage provisions
already considered and shown in project General Arrangement (GA) Drawings. However, in small
stretch in down line and in upline (if so required though not envisaged at this stage), central drain
in first stage concrete shall be provided as per details indicated in GA drawings. Schematic details
shown in Figure below
Details - Z
Fig 8 – Typical Site Picture showing Debonding sheet placed over First Stage Concrete
1.5 REINFORCEMENT
Steel housings shall be marked and placed as per the eneral arrangement drawings under the
supervision of GERB installation engineer. Reinforcement shall then be placed as per the track slab
reinforcement drawings and suitable shuttering / formwork shall be placed at sides and other
opening areas
At the end of each FST, suitable notch at each end of the FST is envisaged to install the KYM
steel spring elements. Notch shall be provided as per the dimension details indicated in the
KYM elements shall be placed after installation of GSI elements under GERB supervision.
Levelling shall be done using necessary shims to be supplied by GERB.
L Shape Steel
embedment w/ lugs
Plan Section
Fig 10 – Schematic Details of Notch for KYM Elements at each FST end
Section Detail - X
Fig 11 – Sacrificial Formwork/Embedment Plate at each FST end for KYM Element
Tape by GERB
Concreting of floating track slab (second stage concrete) shall be done as per engineering drawings
provided by GERB. It is recommended that the full segment of the slab is cast without interruption
except under unavoidable circumstances.
Needle vibrators may be used to ensure that the required concrete quality is achieved by avoiding
honey-combing in the slab.
The PORR track slab and the LWR Rails shall be installed and adjusted at 30mm down with respect
to the final designed rail level. During placing of PORR slabs over second stage concrete 2 pieces
of buffer plank shall be placed between 2 PORR slabs at each ends of 2400 long gap over foam
sheet 270mmx2400mmx40 mm thick so that during grouting for PORR slab, lids over the housing
remain accessible post grouting and design gap of 270 mm remains available for ease of opening
the lid in future.
Both foam pieces and buffer plank (preferably wooden) shall be removed after grouting is over.
During the installation of spring elements, the final rail level shall be achieved using shims as per
standard GERB practice. The lifting of the track slab shall be carried out only after curing of grout
and second stage concrete.
In view of 270 mm gap between PORR slabs, lid of the housing of steel spring element which is
circular in shape matching with housing at top shall be modified slightly at the edges along the
longitudinal direction of track so that total width of lid is reduced slightly by 2 to 3 mm to provide
extra ease while opening of the housing lid in post installation situation. Lid can any way always be
slightly tilted also while opening which is otherwise is not regular event as such.
About 268 mm
The lifting of the floating track slab (second stage concrete) shall be performed only after the
concrete has gained the design strength as per the below installation guidelines
Lifting process is done by compressing the spring unit with the help of
hydraulic jacks and then shimming to the desired height by hydraulic
jacks and other tools, supplied by GERB on returnable basis.
Once the final desired rail level is achieved, the shims are locked with a
locking plate and the lid is sealed.
The gaps between the two adjacent sides of track slabs (second stage
concrete with and without MSS/Tunnel wall as the case may be) both in
the longitudinal and lateral direction are covered with an EPDM sheet to
prevent the ingress of any dust particles and debris.
GERB shall provide a “Hydraulic Jacking System” for the lifting and installation of a floating track
slab. This shall also comprise of E-pumps (110, 220 V) or hand pumps, jacking devices, manifolds
with pressure gauges, compression adaptors, and hoses. During installation of Spring units / lifting
of slab, the track contractor shall provide the required workmen for transporting the material to the
location and to assist GERB installation team.
Usually, with 4 to 5 workmen and 2 GERB engineers, a single slab of approximately 100 m can be
installed in one day. More teams can be assigned depending on project schedule requirement.
No Description
Dwg/Doc No
1 General Arrangement Drawing with MSS N1351723-01-DN to 08-DN
2 Reinforcement Drawings - Downline N1351723-12 to 35 DN
3 Bar Bending Schedule N1351723/BBS -12 to 35 DN