Close Variance Series No: Date Received Project Assigned To Description Corrective Actions Target Date Close out Date Remarks (Days)
Commit realistic schedule taking into account authorities approval for
Delay in the establishment of TSE - QatarEnergy the land, drawing approvals, PTW requirements, scanning report and GC21107800 - EPIC for Mitigation sent letter highlighting the delays in establishment survey reports and so on. 1 30-Oct-22 30-Jan-23 10-Jun-23 130.00 Complaint No. C364/001 of Hydrocarbon Emissions of TSE facilities by the date commited by Roots in the baseline schedule After initial delays due to aforementioned reasons, TSE was successfully established, Inspected and accupied
QA/QC Concern on the project - QatarEnergy sent
GC21107800 - EPIC for Mitigation Have backup candidates, for contingency, obtain approval of the 2 30-Oct-22 email highlighting inadequate QA/QC manpower 30-Oct-23 24-Oct-23 0.00 Complaint No. C364/002 of Hydrocarbon Emissions inspectors at least 1 month before start of construction and its effect on the day-to-day QA/QC processes
Close co-ordination with vendor and identify the issue in timely
manner would have avoided this issue Delay in issuance of Civil Drawings and its impact GC21107800 - EPIC for Mitigation on project progress - QatarEnergy sent email 3 3-Oct-23 As committed by consultant, drawings were released. 24-Oct-23 24-Oct-23 0.00 Complaint No. C364/003 of Hydrocarbon Emissions highlighting the delays in release of AFC drawings of all equipment foundation Roots fulfilled the commitment in commencing the site works as committed