DAILY SITE PROGRESS REPORT


CRK-MIT-ELV-DSPR-
EFFECTIVE DATE: 06-Dec-2023 REPORT ID: 23-0291

CONTRACTOR: MILLENNIUMIT ESP DISCIPLINE: ELV

WORK START TIME: 8.00 am WORK FINISH TIME: 18.00 pm

01 | STAFF 03 | ACTIVITY PERFORMED ON YESTERDAY


CATEGORY NOS ACTIVITY / OUTCOME WORK DONE MANPOWER
Project Manager 1 SE# LEV CATEGORY NOS
PLANNED ACTUAL
ACTIVITY
Engineer 1
Draftsman 1 L02 GI Conduiting 40% 30%
QS HO
Engineering Intern 2 L-6 Guest room sunk box 80% 85%
installation
L13 Cable tray installation 10% 5%

TOTAL 5

02 | MANPOWER (ALL) 04 | ACTIVITY PLAN TO BE PERFORMED ON TODAY


CATEGORY NOS ACTIVITY / OUTCOME OUTPUT MANPOWER
TECHNICIAN 5 SE# LEV ACTIVI UNIT QTY CATEGORY NOS
ELV | HELPER 4 TY

ELV Technician 2
L02- L03 GI Conduiting
1 1
ELV Helper 1
L-13 Cable tray installation 1 1 ELV Helper 2
ELV Technician 1

Guest Rooms TV and WiFi ELV Helper 1


TOTAL 9 L-13 1 1
Sunk box installation ELV Technician 2

(PM / DEPARTMENT HEAD)

PREPARED BY CHECKED BY CONFIRMED BY


(NCC TEAM)

Sanjeewa Liyanage Amila Gamage

Engineer - Network Project Manager - ELV

SIGNATURE

DATE 06-Dec-2023 06-Dec -2023