Site Quality

DAILY SITE DIARY


Management
System

PROJECT NO: ZIMPLATS PROJECT: 40.5 MWp Solar Farm

CONTRACTOR: Shenxin DATE: 23/04/2024


RAIN: 0 mm 28°C Max 20°C Min

NAME COMPANY ITEM + -

Victor Jecca Engineering Forklift 2


Chiremba PLANT
Pile driver 2 1
Telehandler 1
PERSONNEL Drilling 2
machine
Project 1
Manager
Engineers 3
Admins 2
Electrician 10
Electrician 10
assistants
Machine 4
operators
Plant and fitter 3
SHEQ 3
Surveyors 3
CONTACT DETAILS victor@jeccaengineering.co.zw Other 87

INCIDENTS/ SAFETY

Work permits, pre-task risk assessments, machine checklists


Adequate ppe for all workers


Y N
Is the Contractor working safely?
e

jecca-engineering-site-diary
WORK STARTED/ RESTARTED/COMPLETED AGAINST TARGETS

ACTIVITY ACHIEVEMENTS TARGETS COMMENT(S)


Ramming (Rectification of 0 300 Rectification of posts. One
posts) ramming machine on breakdown.
Cable laying (m) 0 5000 Sand bedding in cable trenches
Drilling block 3 (holes) 16 200 Contract with hired drill rig ended
today with the last 16 holes
Distribution (pile posts) 0 500 Not distributed today
Distribution block 4 west 12 800 Block 4 west side distribution on
side (dampers) checked tables
Distribution block 4 west 135 800 Block 4 east side distribution left
side(row tubes) slices
Distribution block 4 52 800 Block 4 east side distribution left
(Bearings) slices
Distribution block 4 west 588 1000 Distribution on block 4 east side
side(pv modules) left slices
Laser alignment (tables) 10 20 Only 1 laser device
PV modules installation 7 20 Partly dependant on tracker
(tables) components installation quality
checks and cable laying activity
Tracker components 10 20 Quality check and rectification of
installation (tables) tables

Pictures of work started and completion of daily work to be issued with Site Diary.
Y √
N

WORK TEMPORARILY SUSPENDED/ DELAYS/ DISRUPTION/ POTENTIAL CLAIMS

One ramming machine on breakdown.

Ground compaction in pv yard temporarily suspended because of inspections. Working towards the closure of
inspections
Completion of earthing disturbed by other parallel activities

GENERAL ITEMS

1 proof test experiment done today 23/04/24

Need for another laser devices.

jecca-engineering-site-diary
DEVIATIONS √
Has the Contractor supplied his daily report on the state of all deviations? Y N

Are all deviations safe for use by the travelling public? Y N
If NO, give details.

CONTRACTOR: Shenxin DATE: 23/04/2024 SIGN:

CLECK OF WORKS: DATE: 23c/04/2024 SIGN: