Weekly Progress Report

From 04 February 2024 to 10 February 2024

Project Name: Samana Miami-1


Client: Samana SIA Holdings
Consultant: AREC
Main Contractor: Reliant Contracting LLC
Subcontractor: AKBC

Prepared by:
 Project Data

Project Description: Construction of Proposed G+P+6 Residential


Building
Project Location: Al Barsha South Fourth, JVC, Dubai, UAE
Plot No: JVC14WNEW003
Plot Area: 2497.78 sqm , 26885.9 Ft^2
BUA: 12,586.07sqm , 135475.33 Ft^2
No. of Floors: G+P+6
1 BHK: 79
2 BHK: 10
No. of Retail: 4
No. of Parking: 107
Project Commencement date: 24th May 2023
Project Completion date: 24th May 2025
Project Duration: 732 Days
Project Duration Elapsed: 263 Days 35.92%
Project Duration Remaining: 469 Days 64.08%
Project Contract Value: 27,142,929.87 AED
Submitted Variations: 443877.5 AED
Approved Variations: 0.0 AED
Planned Value of Work Done: 37.6%
Actual value of work done: 36.5%
Difference: % Days
Total Payment Certified: 5,309,075.18 AED
As per Payment Certificate No: 07 Dated: 20 January 2024 for the period ending:
 Summary of Project Construction Status

 Previous Completed Main Activities:

 Excavation
 Foundation
 Substructure
 Basement Stairs & Pump Room
 Ground Floor Slab
 Ground to Podium Columns, Core walls, Staircase & Ramp
 Podium Slab
 Podium to 1st Floor Columns, Core walls, Staircase
 1st Floor Slab
 1st to 2nd Floor Columns, Core walls & Staircase Part-1
 2nd Floor Slab
 2nd to 3rd Floor Columns & Core walls
 3rd Floor Slab
 3rd to 4th Floor Columns & Core walls
 4th Floor Slab
 4th to 5th Floor Columns & Core walls
 5th Floor Slab Part-1
 1st Floor Block work
 1st Floor Block work Layout

 Ongoing Main Activates:

 5th Floor Slab Part-2 Decking, Shuttering, Reinforcement & PT


 5th to 6th Floor Columns Part-1 & Core wall Part-1 Reinforcement
 Post Tension Stressing Grouting
 1st Floor Swimming Pool
 1st Floor Block work
 4th Floor Slab De-Shuttering
 Substation Plaster Work
 5th to 6th Floor Columns & Core walls MEP Containment
 Steel Fabricating
 Critical Issues and concerns
Issue Description Action Required by

Swimming Pool Construction is pending Consultant


RFI is raised to the consultant to clear which details should be followed

Substation work is pending


Main Contractor has to handover the substation on 15/02/2024 Contractor

Backwash Tank work is pending


Main Contractor has Submitted RFI to Consultant Regarding Backwash Tank that is Consultant/Contractor
Replied with comments
Mutual Coordination is required

List of Provisional Sum Items

S. Item Description Contract Contractor Total w/ Actual Contractor Total W/ Difference


No. Price OHP OHP Price OHP OHP +/-
1
Garbage Room 60,000 3,000 63,000

2 Light Fixtures 150,000 7,500 157,500

3 Kitchen Cabinets 600,000 30,000 630,000

4 Wardrobes 550,000 27,500 577,500

5 Sanitary wares,
Mixtures & 300,000 15,000 315,000
Accessories

6 Gym & Kids Area 100,000 5,000 105,000


equipment

7 Landscaping 150,000 7,500 157,500

8 Swimming Pool & 250,000 12,500 262,500


Open Shower Area

9 Plunge Pools 1,250,000 62,500 1,312,500

10 Signages 80,000 4,000 84000


11 Column Guard,
Humps, Traffic 30,000 1,500 31,500
Mirrors, Wheel
Stoppers

12 Lifts 360,000 18,000 378,000

13 Mirror 50,000 2,500 52,500

14 Aluminum,
Glazing & Glass 2,500,000 125,000 2,625,000
Partition & Metal
works

15 Sauna & Steam 80,000 4,000 84,000


Rooms

16 Façade lighting 200,000 10,000 210,000

17 Façade Signage 50,000 2,500 52,500


Digital

18 Screening of roof
MEP services as 50,000 2,500 52,500
per Authority
Requirement
Site Progress Photos
5th Floor Slab Part-2 Shuttering

5th Floor Slab Part-1 Curing


5th to 6th Floor Core wall Part-1 Steel Fixing

1st Floor Swimming Pool


1st Floor Block work