900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects

Fuel Oil System


SR Originator Comments HEP Reply
(27-12-2021)
1. KE-OPS HEP to Provide Set points for the auto start/auto stop of Oil Feed
Pump A (00EKG10AP001) w.r.t tank Level in the functional testing
file

2. KE-OPS HEP to Provide Set points for the auto start/auto stop of Oil Feed
Pump B (00EKG10AP002) w.r.t tank Level in the functional testing
file

3. KE-OPS HEP to Provide Set points for the auto start/auto stop of Oil Feed
Pump C (00EKG10AP003) w.r.t tank Level in the functional testing
file

4. KE-OPS HEI to clarify interlock test of oil feed pumps. Please refer to
below picture

5. KE-OPS HEI to Provide the pressure set points for interlock test of oil feed
pumps A/B/C (00EKG10AP001/2/3)

6. KE-OPS HEI to incorporate the Level Tx (00EGB01CL201) testing of Day


tank in the functional testing and to provide alarm set points for

PAGE \* MERGEFORMAT 6
900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects
Fuel Oil System
the tank low and high levels.

7. KE-OPS HEI to clarify, the behaviour of fuel oil delivery pumps


(00EKG20AP001/2) w.r.t Day tank high levels, in the
commissioning procedure

8. KE-OPS HEI to incorporate functional testing MOV (10/20EKG10AA010) in


the Attachment 2

9. KE-OPS HEI to provide the checklist for valves testing of fuel oil system
and ensure no passing in any isolating valve and provide its
report/certificate.

10. KE-OPS HEI to provide the setpoints for the Sewage pumps auto start
logic

11. KE-OPS HEI to Provide the calibration certificate for the process
instrumentation.

12. KE-OPS HEI to ensure and incorporate functional testing for the Fire
Fighting (Sprinkle/Foam system) of Day tank and pump house

13. KE-OPS HEI to provide and incorporate the functional testing of Black
start pump (00EKG40AP010) in the attachment 2.

14. KE-OPS HEI to Provide Valve line up (Status) for starting the fuel oil
system for the functional testing.

15. KE-OPS No info/testing regarding Delivery pumps and sewage pump at


plant 2. HEI to please provide the necessary info and incorporate
in the procedure

16. KE-OPS HEI to use the same names for the booster pumps as its different
in both Attachment 2 (Functional Testing) and Commissioning
procedure.

PAGE \* MERGEFORMAT 6
900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects
Fuel Oil System
17. KE-OPS In commissioning procedure, it is written that Booster pump
should be start from local in case of any other running pump trip,
While in Attachment 2 its Auto start interlocking is discussed, HEI
to clarify please.

18. KE-I&C Logic drawing to be shared before commissioning

19. KE-I&C All Instrument health and loop check will verify by giving source
from local.

20. KE-I&C Data Sheet and Alarm Values shared before commissioning if any.

21. KE-I&C All Field Instruments must be the part of commissioning


documents.

22. KE-I&C Checklist of individual valves position to be added

23. KE-I&C All field instruments calibration report

24. KE-I&C All valves feedback should be demonstrated & included in


Functional Test.

25. KE-I&C Demonstration of each & every logic as per control drawing
should be part of functional test

26. KE-I&C Cold loop test results to be shared before cold commissioning.

27. KE-I&C Instrument wiring diagram to be shared before cold


commissioning.

28. KE-I&C In control system there should not be any single point of failure.
29. KE-Mech We have two waste oil pumps, one at BQPS-II & one at BQPS-III.
Correction required

PAGE \* MERGEFORMAT 6
900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects
Fuel Oil System
30. KE-Mech HEP to submit detailed procedure for flushing of complete oil
piping scope.
31. KE-Mech HEP to provide the acceptance criteria of fuel oil quality
32. KE-Mech With respect to point 6.4, KE/OE to witness the parameters
(flowrates/pressure) at EDG/BSDG diesel tanks and FF room
tanks together with main oil tank.
33. KE-ELE OEM drawings and manual to be submitted to understand OEM
operational philosophy
34. KE-ELE Please share list of electrical checks on Heater, Motors, MCCs and
groundings
35. KE-ELE Specification of all installed electrical equipment required;
heaters and motors.
36. KE-ELE Please share Lux level report in commissioning report
37. KE-ELE Please share grounding resistance test report of area.
38. KE-ELE Please share Hazardous Location identification report for Fuel Oil
System (Equipment must be rated according to Zone)
39. KE-ELE Kindly share motor protection settings
40. KE-ELE Please include all basic electrical checks in commissioning report;
kindly include IR report, phase sequence test; voltage and current
recorded during solo- run and load run.

OE-MECH HEP to perform 4 Hrs run test for all Fuel Oil and black start
41. pumps. HEP to provide log sheets including all testing parameters
for run test.
OE-MECH HEP to provide O&M manual of Fuel oil pumps and equipment
42. along with performance characteristics curves of pumps. These
curves hall be available at site during commissioning.
OE-MECH HEP to update Attached no 01 point no 06. CCCW pumps should
43. be changed to fuel oil pumps.

PAGE \* MERGEFORMAT 6
900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects
Fuel Oil System
OE-MECH HEP to update Attached no 01 point no 06. CCCW pumps
44. should be changed to fuel oil pumps.
HEP shall perform change over and trip test of Fuel Oil pumps
while the whole system is running.
OE-MECH Emergency push button functional test shall be done while the
45. pumps are in service.
OE-I&C Following points should also be included as checklist in (Prepare
46. conditions before system commissioning) and should be duly
signed by KE/OE before commissioning.
 Applicable ITP inspections are completed
 Preliminary punch list CAT ”A” points are closed
 Erection completion certificate (ECC) got signed
 IO list, trip alarm set points, cause and effect matrix,
control logic description provided to KE/OE.
 Instrument (including analyzers) calibration/functional
testing is witnessed by KE/OE and Instruments are pasted
with valid calibration sticker.
Related DCS graphics reviewed and approved by KE/OE.
OE-I&C For loop/functional testing of each field instrument i.e. valves,
47. transmitters, Analyzers etc. detailed procedure to be provided
and should be tested and offered for witnessing to KE/OE.
OE-I&C Trip Alarm set points, Interlock list, cause and effect matrix,
48. control logic description should be confirmed to be updated and
attached as annex. Also witnessing to be offered to KE/OE during
their testing.

OE-I&C Any changes in terms of I&C - Control have to take in


49. consideration the final status of:
1.Control Software Backups,
2.Application software Backups,
3.Backups of HMI's, Server & Historian,

PAGE \* MERGEFORMAT 6
900 MW BQPS-III Combined Cycle Plant & Associated Transmission Projects
Fuel Oil System
4.Switches Configuration File
5. Passwords
6. IP address/access
7. Interfaces configuration mapping and backup
8. As-build for I/O Lists, diagrams, matrix and drawings
9. Lists with all system bypasses, permissive, interlocks.