You are on page 1of 5

SIEMENS Inbetriebsetzung-Programm

Commissioning Procedure
Seitenzahl / No. of Pages
1 von / of 5
Handhabung: Intern / Handling: Restricted
BQPS III PK1024 10/20 CP-MKG &MDC030 321506
Kraftwerk/Power Plant KW-Nr./Plant Code Block/Unit Inhaltskennzeichen/Contents Code DCC Zähl-Nr./Reg. No.

System/Titel: MKG Generator Gas System Anlagen: 4


System/Title Generator No. MK700192/MK700197 Appendices:

Betroffene Systeme:
MKG – Generator Gas System
Included Systems:
MKA Generator
MKC Collector
System-Schnittstellen: MKD Generator Bearings
System-Interfaces: MKF Stator Water System
MKQ Generator Waste Gas System
MKW Generator Seal Oil System
TOP-Referenzen:
TOP-References: TOP-10/20MKG

*) Nicht zutreffendes
streichen Erstellt Erstellt/Geprüft*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)
*) Delete as appropriate Prepared by Prepared/Verified by Verified/Released by Verified/Released by

Dienststelle
Department SE G SV EU FS 4 4 2 SE G SV EU FS 4 2 3
Name Songarden
Name Abram
Datum Digital Digital signiert von Abram Frank
Date Songard unterschrieben von
Songarden Felix
DN: cn=Abram Frank, o=Siemens,
email=frank.abram@siemens.com
Unterschrift
Signature
en Felix Datum: 2020.09.01
09:39:42 +02'00'
Datum: 2020.09.04 09:01:59 +02'00'

Geprüft/Freigeg.*) Geprüft/Freigeg.*) Geprüft/Freigeg.*) Geprüft/Freigeg.*)


Verified/Released by Verified/Released by Verified/Released by Verified/Released by

Dienststelle
Department
Name
Name
Datum
Date
Unterschrift
Signature

Geändert: Geprüft/Freigegeben:
modified by: Reviewed/released by:

Rev. Name/Kurzzeichen Dienststelle/Firma Datum Fachabteilung, Ibs-Leitung, Projektleitung


Index Name/Signature Department/Company Date Techn. Department, Com. Management, Project Management

Verteiler:
Copies to

Siemens Gas and Power GmbH & Co. KG Transmittal, reproduction, dissemination and/or editing of this document Project Site
as well as utilization of its contents and communication thereof to others
without express authorization are prohibited. Offenders will be held Execution
liable for payment of damages. All rights created by patent grant or
Service Power Generation registration of a utility model or design patent are reserved.
Kraftwerk: BQPS III IBS-Kennzeichen: CP-MKG Seite: 2 von / of 5
Power Plant PK1024 Com. Code No. Page

Legende/Legend:
Inbetriebsetzung-Programm: MKG Generator Gas System Anlagen/Appendices AP
Checkliste/Checklist CL
Commissioning Procedure Generator No. MK700192/MK700197 Funktionsdiagramm/Function Diagram FD
Herstelleranweisung/Manufacturer Instruction MI
IBS-Anweisung/Commissioning Instruction CI
Betriebs- und Instandhaltungs Handbuch/ OMM
Operation and Maintenance Manual
Inbetriebsetzung/Commissioning IBS
Protokoll/Test Record TR
Zeichnung/Drawing DWG
Spezifikation/Specification SPE
Haltepunkt/Hold Point (h)

Kennung Tätigkeit Referenz Dokument Haltepunkt Bestätigt


Code Activity Reference Record Hold Point Confirmed
A-MKG-01 Cleaning / Preservation
 Verify general cleanliness of system See documentation of the
executing construction
department and
AP-CG001
A-MKG-02 System / Components check
 of TOP- scope according to valid P&ID P&ID: DPIVCS-70006025 „As Built“ P&ID

Issue E- und M-Erection Clearance Certificates ECC

A-MKG-03.1 Electrical commissioning


 of Feeders See documentation of
 of Cables electrical commissioning
 of Consumers and load list
SPE: DPIVCS-70006127 „As Built“ SPE

 of protective grounding of feeders, cable supports, con- See documentation of


sumers, rack, piping, I&C cables electrical commissioning
and
DWG: DSPPG-0139725

Siemens Gas and Power GmbH & Co. KG Transmittal, reproduction, dissemination and/or editing of this document as well as utilization of its Project Site Execution
contents and communication thereof to others without express authorization are prohibited. Offenders
Service Power Generation will be held liable for payment of damages. All rights created by patent grant or registration of a utility
model or design patent are reserved.
Kraftwerk: BQPS III IBS-Kennzeichen: CP-MKG Seite: 3 von / of 5
Power Plant PK1024 Com. Code No. Page

Legende/Legend:
Inbetriebsetzung-Programm: MKG Generator Gas System Anlagen/Appendices AP
Checkliste/Checklist CL
Commissioning Procedure Generator No. MK700192/MK700197 Funktionsdiagramm/Function Diagram FD
Herstelleranweisung/Manufacturer Instruction MI
IBS-Anweisung/Commissioning Instruction CI
Betriebs- und Instandhaltungs Handbuch/ OMM
Operation and Maintenance Manual
Inbetriebsetzung/Commissioning IBS
Protokoll/Test Record TR
Zeichnung/Drawing DWG
Spezifikation/Specification SPE
Haltepunkt/Hold Point (h)

Kennung Tätigkeit Referenz Dokument Haltepunkt Bestätigt


Code Activity Reference Record Hold Point Confirmed
A-MKG-03.2 Electrical commissioning
 of Instruments See documentation of I&C
commissioning
See measuring point list
SPE: DPIVCS-70006131 „As Built“ SPE

A-MKG-03.3 Explosion Protection


 Check rating plates of components to special operating See measuring point list
conditions (if applicable) are maintained with for this SPE: DPIVCS-70006131 „As Built“ SPE
project valid explosion protection. See load list
Safety class (IP) for water, dust, temperature etc. to the SPE: DPIVCS-70006127 „As Built“ SPE
environmental conditions. See actual “Test Plan
Explosion Protection”

TOP Hand over TOP- Certificate

A-MKG-04 Check of interlock


 Function check FD „As Built“ FD

A-MKG-05.1 Commissioning of components


 Hand operated valves P&ID: DPIVCS-70006025 „As Built“ P&ID
AP-CG001

Siemens Gas and Power GmbH & Co. KG Transmittal, reproduction, dissemination and/or editing of this document as well as utilization of its Project Site Execution
contents and communication thereof to others without express authorization are prohibited. Offenders
Service Power Generation will be held liable for payment of damages. All rights created by patent grant or registration of a utility
model or design patent are reserved.
Kraftwerk: BQPS III IBS-Kennzeichen: CP-MKG Seite: 4 von / of 5
Power Plant PK1024 Com. Code No. Page

Legende/Legend:
Inbetriebsetzung-Programm: MKG Generator Gas System Anlagen/Appendices AP
Checkliste/Checklist CL
Commissioning Procedure Generator No. MK700192/MK700197 Funktionsdiagramm/Function Diagram FD
Herstelleranweisung/Manufacturer Instruction MI
IBS-Anweisung/Commissioning Instruction CI
Betriebs- und Instandhaltungs Handbuch/ OMM
Operation and Maintenance Manual
Inbetriebsetzung/Commissioning IBS
Protokoll/Test Record TR
Zeichnung/Drawing DWG
Spezifikation/Specification SPE
Haltepunkt/Hold Point (h)

Kennung Tätigkeit Referenz Dokument Haltepunkt Bestätigt


Code Activity Reference Record Hold Point Confirmed
A-MKG-05.2 Commissioning of components
 Solenoid valves P&ID: DPIVCS-70006025 „As Built“ P&ID
AP-CG001

A-MKG-05.3 Commissioning of components


 Motor drives P&ID: DPIVCS-70006025 „As Built“ P&ID
AP-CG001

A-MKG-05.4 Commissioning of components


 Fans P&ID: DPIVCS-70006025 „As Built“ P&ID
AP-CG001

A-MKG-06.1 Commissioning of systems


 Gas dryer P&ID: DPIVCS-70006025 „As Built“ P&ID
AP-CG001

A-MKG-06.2 Commissioning of systems


 Function check of H2-consumption measurement FD „As Built“ FD

A-MKG-06.3 Commissioning of systems


 Function check of interlocks and alarms FD „As Built“ FD

Siemens Gas and Power GmbH & Co. KG Transmittal, reproduction, dissemination and/or editing of this document as well as utilization of its Project Site Execution
contents and communication thereof to others without express authorization are prohibited. Offenders
Service Power Generation will be held liable for payment of damages. All rights created by patent grant or registration of a utility
model or design patent are reserved.
Kraftwerk: BQPS III IBS-Kennzeichen: CP-MKG Seite: 5 von / of 5
Power Plant PK1024 Com. Code No. Page

Legende/Legend:
Inbetriebsetzung-Programm: MKG Generator Gas System Anlagen/Appendices AP
Checkliste/Checklist CL
Commissioning Procedure Generator No. MK700192/MK700197 Funktionsdiagramm/Function Diagram FD
Herstelleranweisung/Manufacturer Instruction MI
IBS-Anweisung/Commissioning Instruction CI
Betriebs- und Instandhaltungs Handbuch/ OMM
Operation and Maintenance Manual
Inbetriebsetzung/Commissioning IBS
Protokoll/Test Record TR
Zeichnung/Drawing DWG
Spezifikation/Specification SPE
Haltepunkt/Hold Point (h)

Kennung Tätigkeit Referenz Dokument Haltepunkt Bestätigt


Code Activity Reference Record Hold Point Confirmed
B-MKG-01 Commissioning of systems
during start-up and at rated speed
 Check of operation values SPE: DPIVCS-70006131 „As Built“ SPE
B-MKG-02 Commissioning of systems
on load
 Check of operation values TR 2.7-8160-MK700192
TR 2.7-8160-MK700197
B-MKG-03 Commissioning of systems
 Perform the proof test procedures, which verify the cor- Operation Manual,
rect function of SIL-relevant protection loops/s. Part “Maintenance
(requirement of functional safety standards) Documentation” (TP2)
in collaboration with I&C commissioning

Issue of Commissioning Clearance Certificates CCC

Siemens Gas and Power GmbH & Co. KG Transmittal, reproduction, dissemination and/or editing of this document as well as utilization of its Project Site Execution
contents and communication thereof to others without express authorization are prohibited. Offenders
Service Power Generation will be held liable for payment of damages. All rights created by patent grant or registration of a utility
model or design patent are reserved.

You might also like