Professional Documents
Culture Documents
SIEMENS
Power Generation
Classement des documents SKB :
BRG-GG-740-069
Original / Original: NO Original / Original-No.: Code Projet Original :
Orig.-PC :
TABLE OF CONTENTS
4. PRECAUTIONS............................................................................................................................................11
HEALTH, SAFETY AND ENVIRONMENT.................................................................................................................11
5. PERFORMANCE..........................................................................................................................................11
COLD COMMISSIONING PREPARATORY CHECKS...................................................................................................11
5.1.1 Piping Preparatory Checks...............................................................................................................11
5.1.2 Mechanical Preparatory Checks.......................................................................................................11
5.1.3 Instrumentation Preparatory Checks................................................................................................12
5.1.4 Electrical Preparatory Checks..........................................................................................................12
5.1.5 Logics Checks....................................................................................................................................14
DYNAMIC COMMISSIONING...................................................................................................................................14
5.1.6 Preparation for Dynamic Commissioning........................................................................................14
5.1.7 Dynamic Commissioning Procedure.................................................................................................15
5.1.8 Operational Test................................................................................................................................15
6. ASSESSMENT AND POST-COMMISSIONING STATUS.....................................................................15
7. APPENDICES................................................................................................................................................17
ANNEX 1 – LIST OF REFERENCE DOCUMENTS......................................................................................................17
ANNEX 2 – GLOSSARY OF TERMS.........................................................................................................................18
ANNEX 3 – PERMIT TO WORK FORMAT................................................................................................................19
ANNEX 4 – PRE-COMMISSIONING INSPECTION TEST REPORT FORMATS..............................................................20
ANNEX 5 – COMMISSIONING INSPECTION TEST REPORT FORMATS.....................................................................21
ANNEX 6 – COMMISSIONING PUNCH-LIST FORMAT.............................................................................................22
Annex 7 – System Commissioning Handover Certificate Format.......................................................................23
Objective
The objective of this document is to detail the various preparatory checks, actual
preparation for commissioning and dynamic commissioning procedure including the post
commissioning operational tests procedure for lighting system.
System Overview
In respect of the function, lighting levels, quality and reliability of electric supply system,
the lighting system shall be divided and classified as follows:
Normal AC lighting
DC Escape lighting fed from 125 V DC Distribution board.
Normal lighting is the lighting set up and sized so as to enable normal operating
activities. Normal lighting is fed from the normal power supply system and is available as
long as the normal AC power supply exists. During 220 kV / GT blackout, the emergency
operation initiated by DCS will start the EDG and within 10 seconds the EDG will come
into full operation with a part of lighting fixtures connected to the normal AC switchgear.
The plant lighting will not be disrupted during the blackout.
The DC Escape lighting is provided in places of emergency exits, access to the control
room and other strategic points essential for personnel movement. This lighting system is
fed from DC Lighting sub-distribution boards which will be in turn fed from Station
125V DC Distribution board. This lighting system is sized so as to provide minimum
suitable conditions of escape or survival and enable communication activities, immediate
aid, evacuation of people or remedy actions to safeguard the power plant.
Design Data
The lighting system is designed to give minimum illumination levels as given in the table
below.
The table furnished below gives the type of lighting fixtures provided for each area and
the level of lighting expressed in average lux when measured on an useful horizontal
plane at 80cm above the floor.
Normal AC Lighting
For external lighting, HPSV Floodlights installed on 15m column are used. High pressure
sodium vapour lamps installed on 9m poles are used for road lighting with photocell
control. A photocell is located at the substation to control automatic lighting system.
Indoor lighting is generally provided by fluorescent luminaire type. For high ceilings,
high pressure mercury vapour lamps are used.
Supply
The source of power supply is from 400V – 230 V Main Lighting Distribution board
which is fed from two (2) Lighting Transformers, each of rating 200 KVA. This Main
Lighting Distribution board feeds respective area lighting sub-distribution boards from
which lighting fixtures are fed. Road lighting fixtures and 32 A & 63 A power socket
outlets are fed with 400 V AC – 3 phase power supply. Lighting and power socket
distribution is done from the same lighting sub-distribution board located in any
particular area.
DC Escape Lighting
Escape lights are provided in critical points for the safety of the people. Escape lighting is
also be provided in the proximity of communication points with control rooms and or/aid
centre (telephones, interphones etc.) Escape light points are provided along all passage
routes, escape routes guaranteeing sufficient light for the movement of personnel.
Supply
This lighting system is fed from DC Lighting sub distribution boards which is in turn fed
from Station 125V DC Distribution board. The lamps are of incandescent type with 25W
power.
The switching on or switching off of exterior lighting is done either automatically using a
photo electric cell, or manually from the guardhouse.
The document describes the various steps required to successfully commission the
Lighting System. This document serves as a basic guideline however deviation from the
procedures may be necessary based on actual site conditions and vendor.
specific requirements. The document incorporates vendor information and engineering
data that is available at the time of operation.
Type of Measurements
The Lux Level of the lighting system to be measured and recorded each building and
plant area.
Special Tools and Test Equipment
As far as Lighting system concern there is no any such special tools are required.
However necessary arrangements to be made based on site conditions.
1. Multimeter
2. Lux Meter
3. Megger (500V)
3. PREREQUISITES
Construction
achievement of
BZL
Visual inspection
& Static pre
commissioning
tests
Mechanical
Completion of
BZL
Prerequisites for
commissioning
of BZL System
Dynamic Tests
Commissioning
Completion of sys
BZL
BZL System
Handover to
operations
4. PRECAUTIONS
1. Ensure the work area is clean and all the pre-commissioning debris has been
removed.
2. The working Engineer requires to be certified by the senior Electrical Engineer.
3. Ensure there should not be any supports hanging over the Lighting fixtures and
Distribution boards.
4. Ensure the CO2 hand held type fire extinguishers are provided in appropriate places.
5. Ensure all necessary permits to work have been raised and outstanding permits have
been closed.
6. Commissioning work Team, in advance of the Pre-Com/Com activities taking place
shall issue a Livening-Up Notice (LUN). The LUN form is issued by
Commissioning to notify Construction and all contractors of the Pre-Com/Com
activities on specific equipment, lines, devices, systems or areas.
7. Personnel involved in the pertinent Pre-Com/Com activities shall not leave the work
area unattended when equipment is in operation or dynamic/pressure operations are
taking place.
8. Conduct daily Tool Box meeting at the work place before starting the work.
9. Brief the commissioning team regarding the escape routes and necessary preventive
action.
5. PERFORMANCE
Distribution Boards
Protection
CT’s
General
The following logic checks should be under taken as part of the pre-commissioning
sequence.
1. All trips from transformer protective devices to switchgear Panel.
Dynamic Commissioning
5.1.6 Preparation for Dynamic Commissioning
System status
The Lighting system distribution system is commissioned and can be safely fed with LV
supply.
Preservation status
The Lighting system is always kept in live condition, so no preservation is applicable for
this system.
Reinstatement status
Restore any temporary arrangements made to simulate the trip commands in the Lighting
system while doing the pre-commissioning activities.
7. APPENDICES
Engineering Documents
List of Drawings
Before starting the commissioning activity of the Lighting system the work permit format
must be filled and approved by the Commissioning Manager with counter signing by Site
HSE manager.
All the safety actions to be followed before starting the commissioning activity.
E-008A – Earthing
E-028A – Ex Enclosures