You are on page 1of 71

PIPING ISOMETRIC BK91-1310-CPF-169-PIP-IDX-0001

Doc. No.
DRAWING INDEX FOR
Revision 1
FUEL GAS SYSTEM Date of
08-04-2023
Issue
Page 1 of 8

BLOCK 9 DEVELOPMENT PROJECT PHASE 1


EPCC OF CPF - OIL TREATMENT SYSTEM
AND AUXILIARY SYSTEMS PROJECT

PIPING ISOMETRIC DRAWING INDEX FOR


FUEL GAS SYSTEM
Document No: BK91-1310-CPF-169-PIP-IDX-0001

The EPC Contractor shall have full responsibilities for the


correctness of Isometrics in terms of consistency w.r.t PID /
UID, PMS, Process information, Project specifications, 3D
Model, Stress analysis and Piping layouts. Review of
Isometric drawings by PMT/PMC, shall not relieve the EPC
Contractor of any of these responsibilities.

1 RE-ISSUED FOR CONSTRUCTION 08-04-2023 Xin Y.C. WANG X.D. LI F.L. CAI F.F.

0 ISSUED FOR CONSTRUCTION 04-01-2023 Xin Y.C. WANG X.D. LI F.L. CAI F.F.

REV. DESCRIPTION DATE PREP'D CHK'D REV'D APP'D

Template No.: BK91-1000-000-GEN-TMP-0011


Revision: 2
Date: 06.07.2021

ISSUED FOR CONSTRUCTION


PIPING ISOMETRIC BK91-1310-CPF-169-PIP-IDX-0001
Doc. No.
DRAWING INDEX FOR
Revision 1
FUEL GAS SYSTEM Date of
08-04-2023
Issue
Page 2 of 8

REV DATE REVISION DETAILS

0 04-01-2023 ISSUED FOR CONSTRUCTION

1 08-04-2023 RE-ISSUED FOR CONSTRUCTION

Template No.: BK91-1000-000-GEN-TMP-0011


Revision: 2
Date: 06.07.2021

ISSUED FOR CONSTRUCTION


STAGE Detailed Design
EPCC of CPF-OIL Treatment System and
PROJECT
Auxiliary Systems Project
DOC. NO. 08-04-2023

AREA CPF PAGE NO. 3 of 8


PIPING ISOMETRIC DRAWING INDEX FOR
DOCUMENT Rev. 1
FUEL GAS SYSTEM

NOTES:
1) Pipe Quantity is in meters and other quantities in Nos.
2) All dimensions, elevations and co-ordinates indicated in the isometric drawings are in mm unless otherwise specified.
3) All dimenions and elevations refer to centre line of pipe unless otherwise specified.
4) In case of any discrepancy in Process Data / Line Data in the isometric drawing with respect to the line list, Approved line list shall be governed.
5) Location of Hydrostatic vents & drains indicated on isometrics are for reference only. Final locations shall be decided by construction contractor.
The same shall be recorded on red marked up drawings and updated in AS-Built drawings.
6) “HOLDS” wherever applicable are indicated on isometrics.
7) Height of the shoe indicated under support tags on isometrics of sloping line is as per working point BOP elevation and TOS (Top of Steel)
elevation at support point.Shoe profile to be adjusted according to the slope of the line.
8) Fabrication/Erection of Pipe work, Painting, Insulation and Pipe supports shall confirm to relevant Project specifications / Standards.
9) Construction contractor shall verify all dimensions and elevations prior to fabrication and installation / demolition of piping.
10) All Tie-Ins (Vendor + Existing Area) shall be verified before fabrication. Last Weld joints shall be done after TIE IN verification.
11) Full Couplings & Union for CS-Galvanised Piping shall be adjusted at site suitably.
12) Well connected lines untill the first support to be fabricated after WELL Nozzle Orientation & Elevation confirmation.
13) Field & Shop weld requirements for pipe supports shall be followed inline with Pipe Support Specification and Drawings Doc.
BK91-1310-CPF-999-PIP-DPS-0001.
14) Vertical height adjustments for the pipe shoes, T-Supports, L-Supports shall be done at site based on the installed pipe BOP requirements.
15) CS Pipe sleeve protection shall be provided at GRE pipe crossings with roads, concrete trenches and pits.
16) Supports on water hydrant and foam hydrant please reference BK91-1310-CPF-999-FRF-DWG-0001 Installation Drawing
for Fire Fighting Equipment.
17) Piping routing may changed during the revising of the stress analysis report.
18) Gaskets/Bolts length for the instrumentations gauges/transmitters with flush ring will be updated after have the vendor information.

ISSUED FOR CONSTRUCTION


EPCC of CPF-OIL Treatment STAGE Detailed Design
PROJECT System and Auxiliary Systems
Project DOC. NO. BK91-1310-CPF-169-PIP-IDX-0001

AREA CPF PAGE NO.

Piping Isometirc Drawing Index for FUEL GAS


DOCUMENT Rev. 1 4 of 8 .
SYSTEM
SR.NO ISSUED Isometric Dwg No. Line ID Sheet No. Rev.0 Rev.1 Rev.2 Rev.3 HOLD Index Rev. REMARKS

1 X PG-CPF-169-017(136A) 10"-PG-CPF-169-017-1A3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

2 PG-CPF-169-017(136A) 10"-PG-CPF-169-017-1A3(136A) 2 04-01-2023 N 0

3 X PG-CPF-169-017(169) 10"-PG-CPF-169-017-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

4 X PG-CPF-169-017(169) 10"-PG-CPF-169-017-1A3(169) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

5 X PG-CPF-169-022(136A) 10"-PG-CPF-169-022-3A3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

6 X PG-CPF-169-022(136A) 10"-PG-CPF-169-022-3A3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

7 PG-CPF-169-022(136A) 10"-PG-CPF-169-022-3A3(136A) 3 04-01-2023 N 0

8 X PG-CPF-169-023(136A) 10"-PG-CPF-169-023-3A3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

9 X PG-CPF-169-023(136A) 10"-PG-CPF-169-023-3A3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

10 PG-CPF-169-023(136A) 10"-PG-CPF-169-023-3A3(136A) 3 04-01-2023 N 0

11 X PG-CPF-169-023(136A) 10"-PG-CPF-169-023-3D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

12 PG-CPF-169-002(169) 12"-PG-CPF-169-002-1A3(169) 1 04-01-2023 N 0

13 X PG-CPF-169-002(169) 12"-PG-CPF-169-002-3A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

14 PG-CPF-169-002(169) 12"-PG-CPF-169-002-3A3(169) 2 04-01-2023 N 0

15 X PG-CPF-169-002(169) 12"-PG-CPF-169-002-3A3(169) 3 04-01-2023 08-04-2023 N 1 Updated as per stress

16 PG-CPF-169-002(169) 12"-PG-CPF-169-002-3A3(169) 4 04-01-2023 N 0

17 X PG-CPF-169-002(169) 12"-PG-CPF-169-002-3A3(169) 5 04-01-2023 08-04-2023 N 1 Updated as per stress

18 X PG-CPF-169-003(169) 12"-PG-CPF-169-003-3A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

19 X PG-CPF-169-003(169) 12"-PG-CPF-169-003-3A3(169) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

20 PG-CPF-169-003(169) 12"-PG-CPF-169-003-3A3(169) 2A 04-01-2023 N 0

21 X PG-CPF-169-003(169) 12"-PG-CPF-169-003-3A3(169) 3 04-01-2023 08-04-2023 N 1 Updated as per stress

22 X PG-CPF-169-009(169) 16"-PG-CPF-169-009-3A3(169)-H80 1 04-01-2023 08-04-2023 N 1 Updated as per stress

23 X PG-CPF-169-009(169) 16"-PG-CPF-169-009-3D3-H80(1)(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

24 X PG-CPF-169-009(169) 16"-PG-CPF-169-009-3D3-H80(1)(169) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

25 PG-CPF-169-009(169) 16"-PG-CPF-169-009-3D3-H80(1)(169) 3 04-01-2023 N 0

26 X PG-CPF-169-009(169) 16"-PG-CPF-169-009-3D3-H80(2)(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

27 PG-CPF-169-130(169) 6"-PG-CPF-112-130-1D3-P30(169) 1 04-01-2023 N 0

28 X PG-CPF-169-130(169) 6"-PG-CPF-112-130-1D3-P30(169) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

29 X PG-CPF-169-061(169) 6"-PG-CPF-169-061-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

ISSUED FOR CONSTRUCTION .


EPCC of CPF-OIL Treatment STAGE Detailed Design
PROJECT System and Auxiliary Systems
Project DOC. NO. BK91-1310-CPF-169-PIP-IDX-0001

AREA CPF PAGE NO.

Piping Isometirc Drawing Index for FUEL GAS


DOCUMENT Rev. 1 5 of 8 .
SYSTEM
SR.NO ISSUED Isometric Dwg No. Line ID Sheet No. Rev.0 Rev.1 Rev.2 Rev.3 HOLD Index Rev. REMARKS

30 X PG-CPF-169-061(169) 6"-PG-CPF-169-061-1D3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

31 PG-CPF-169-061(169) 6"-PG-CPF-169-061-3A3(169) 1 04-01-2023 N 0

32 PG-CPF-169-095(136A) 6"-PG-CPF-169-095-1A1(136A) 1 04-01-2023 N 0

33 X PG-CPF-169-095(136A) 6"-PG-CPF-169-095-1A1(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

34 PG-CPF-169-001(169) 8"-PG-CPF-169-001-3A3(169) 1 04-01-2023 N 0

35 PG-CPF-169-001(169) 8"-PG-CPF-169-001-3A3(169) 2 04-01-2023 N 0

36 PG-CPF-169-001(169) 8"-PG-CPF-169-001-3A3(169) 3 04-01-2023 N 0

37 PG-CPF-169-018(169) 8"-PG-CPF-169-018-1A3(169) 1 04-01-2023 N 0

38 PG-CPF-169-018(169) 8"-PG-CPF-169-018-1A3(169) 2 04-01-2023 N 0

39 VH-CPF-169-037(169) 2"-VH-CPF-169-037-1A3(169) 1 04-01-2023 N 0

40 X VH-CPF-169-020(136A) 20"-VH-CPF-169-020-1D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

41 X VH-CPF-169-020(136A) 20"-VH-CPF-169-020-1D3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

42 X VH-CPF-169-025(136A) 20"-VH-CPF-169-025-1D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

43 X VH-CPF-169-025(136A) 20"-VH-CPF-169-025-1D3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

44 X VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

45 X VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

46 X VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 3 04-01-2023 08-04-2023 N 1 Updated as per stress

47 X VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 4 04-01-2023 08-04-2023 N 1 Updated as per stress

48 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 5 04-01-2023 N 0

49 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 6 04-01-2023 N 0

50 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 7 04-01-2023 N 0

51 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 8 04-01-2023 N 0

52 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 9 04-01-2023 N 0

53 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 10 04-01-2023 N 0

54 X VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 11 04-01-2023 08-04-2023 N 1 Updated as per stress

55 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 12 04-01-2023 N 0

56 X VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 13 04-01-2023 08-04-2023 N 1 Updated as per stress

57 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-1D3(136A) 14 04-01-2023 N 0 DELETE

58 VH-CPF-169-026(136A) 20"-VH-CPF-169-026-3D3(136A) 1 04-01-2023 N 0

ISSUED FOR CONSTRUCTION .


EPCC of CPF-OIL Treatment STAGE Detailed Design
PROJECT System and Auxiliary Systems
Project DOC. NO. BK91-1310-CPF-169-PIP-IDX-0001

AREA CPF PAGE NO.

Piping Isometirc Drawing Index for FUEL GAS


DOCUMENT Rev. 1 6 of 8 .
SYSTEM
SR.NO ISSUED Isometric Dwg No. Line ID Sheet No. Rev.0 Rev.1 Rev.2 Rev.3 HOLD Index Rev. REMARKS

59 X VH-CPF-169-024(136A) 6"-VH-CPF-169-024-1D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

60 X VH-CPF-169-024(136A) 6"-VH-CPF-169-024-1D3(136A) 2 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

61 VH-CPF-169-024(136A) 6"-VH-CPF-169-024-1D3(136A) 3 04-01-2023 N 0

62 X VH-CPF-169-024(136A) 6"-VH-CPF-169-024-1D3(136A) 4 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

63 X VH-CPF-169-062(169) 6"-VH-CPF-169-062-1D3(169) 1 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

64 X VH-CPF-169-021(136A) 8"-VH-CPF-169-021-1D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

65 X VH-CPF-169-021(136A) 8"-VH-CPF-169-021-1D3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

66 X VH-CPF-169-035(136A) 8"-VH-CPF-169-035-1D3(136A) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

67 X VH-CPF-169-035(136A) 8"-VH-CPF-169-035-1D3(136A) 2 04-01-2023 08-04-2023 N 1 Updated as per stress

68 VH-CPF-169-035(136A) 8"-VH-CPF-169-035-1D3(136A) 3 04-01-2023 N 0

69 VL-CPF-169-201(169) 6"-VL-CPF-169-201-1D3(169) 1 04-01-2023 N 0

70 X AOC-CPF-169-007(169) 2"-AOC-CPF-169-007-1D3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

71 X AOC-CPF-169-034(169) 2"-AOC-CPF-169-034-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

72 X AOC-CPF-169-066(169) 3"-AOC-CPF-169-066-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

73 X CW-CPF-169-069(169) 6"-CW-CPF-169-069-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

74 X CW-CPF-169-070(169) 6"-CW-CPF-169-070-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

75 X FG-CPF-169-004(169) 12"-FG-CPF-169-004-1A1(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

76 FG-CPF-169-004(169) 12"-FG-CPF-169-004-1A1(169) 2 04-01-2023 N 0

77 X FG-CPF-169-004(169) 12"-FG-CPF-169-004-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per stress

78 FG-CPF-169-054(169) 6"-FG-CPF-169-054-1A1(169) 1 04-01-2023 N 0

79 FG-CPF-169-054(169) 6"-FG-CPF-169-054-1A1(169) 2 04-01-2023 N 0

80 FG-CPF-169-057(169) 6"-FG-CPF-169-057-1D3(169) 1 04-01-2023 N 0

81 X HC-CPF-169-010(169) 2"-HC-CPF-169-010-1A3-H40(169) 1 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

82 HC-CPF-169-010(169) 2"-HC-CPF-169-010-1A3-H40(169) 2 04-01-2023 N 0

83 HC-CPF-169-010(169) 2"-HC-CPF-169-010-1A3-H40(169) 3 04-01-2023 N 0

84 HC-CPF-169-010(169) 2"-HC-CPF-169-010-1A3-H40(169) 4 04-01-2023 N 0

85 HC-CPF-169-010(169) 2"-HC-CPF-169-010-1A3-H40(169) 5 04-01-2023 N 0

86 HC-CPF-169-010(169) 2"-HC-CPF-169-010-1D3-H40(169) 1 04-01-2023 N 0

87 HC-CPF-169-033(169) 2"-HC-CPF-169-033-1D3(169) 1 04-01-2023 N 0

ISSUED FOR CONSTRUCTION .


EPCC of CPF-OIL Treatment STAGE Detailed Design
PROJECT System and Auxiliary Systems
Project DOC. NO. BK91-1310-CPF-169-PIP-IDX-0001

AREA CPF PAGE NO.

Piping Isometirc Drawing Index for FUEL GAS


DOCUMENT Rev. 1 7 of 8 .
SYSTEM
SR.NO ISSUED Isometric Dwg No. Line ID Sheet No. Rev.0 Rev.1 Rev.2 Rev.3 HOLD Index Rev. REMARKS

88 X HC-CPF-169-060(169) 2"-HC-CPF-169-060-1D3(169) 1 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

89 HC-CPF-169-060(169) 2"-HC-CPF-169-060-1D3(169) 2 04-01-2023 N 0

90 HC-CPF-169-060(169) 2"-HC-CPF-169-060-1D3(169) 3 04-01-2023 N 0

91 HC-CPF-169-011(169) 3"-HC-CPF-169-011-1D3-H50(169) 1 04-01-2023 N 0

92 HC-CPF-169-011(169) 3"-HC-CPF-169-011-1D3-H50(169) 2 04-01-2023 N 0

93 HC-CPF-169-011(169) 3"-HC-CPF-169-011-1D3-H50(169) 3 04-01-2023 N 0

94 HC-CPF-169-011(169) 3"-HC-CPF-169-011-1D3-H50(169) 4 04-01-2023 N 0

95 IA-CPF-169-063(169) 1"-IA-CPF-169-063-1Z0(169) 1 04-01-2023 N 0

96 IA-CPF-169-063(169) 1"-IA-CPF-169-063-1Z0(169) 2 04-01-2023 N 0

97 X IA-CPF-169-063(169) 1"-IA-CPF-169-063-1Z0(169) 3 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

98 IA-CPF-169-027(136A) 2"-IA-CPF-169-027-1Z0(1)(136A) 1 04-01-2023 N 0

99 IA-CPF-169-027(136A) 2"-IA-CPF-169-027-1Z0(1)(136A) 2 04-01-2023 N 0

100 IA-CPF-169-027(136A) 2"-IA-CPF-169-027-1Z0(1)(136A) 3 04-01-2023 N 0

101 IA-CPF-169-027(169) 2"-IA-CPF-169-027-1Z0(2)(169) 1 04-01-2023 N 0

102 IA-CPF-169-027(169) 2"-IA-CPF-169-027-1Z0(2)(169) 2 04-01-2023 N 0

103 IA-CPF-169-027(136A) 2"-IA-CPF-169-027-1Z0(3)(136A) 1 04-01-2023 N 0

104 X IA-CPF-169-027(136A) 2"-IA-CPF-169-027-1Z0(4)(136A) 1 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

105 NG-CPF-169-067(169) 2"-NG-CPF-169-067-1A1(169) 1 04-01-2023 N 0

106 NG-CPF-169-067(169) 2"-NG-CPF-169-067-1A1(169) 2 04-01-2023 N 0

107 X NG-CPF-169-067(169) 2"-NG-CPF-169-067-1A1(169) 3 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

108 UA-CPF-169-071(169) 2"-UA-CPF-169-071-1A1(169) 1 04-01-2023 N 0

109 X UA-CPF-169-071(169) 2"-UA-CPF-169-071-1A1(169) 2 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

110 SO-CPF-169-028(169) 1"-SO-CPF-169-028-1D3(1)(169) 1 04-01-2023 N 0

111 X SO-CPF-169-028(169) 1"-SO-CPF-169-028-1D3(2)(169) 1 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

112 X SO-CPF-169-028(169) 1"-SO-CPF-169-028-1D3(2)(169) 2 04-01-2023 08-04-2023 N 1 Updated to optimize the pipe route.

113 X SO-CPF-169-028(169) 1"-SO-CPF-169-028-1D3(2)(169) 3 04-01-2023 08-04-2023 N 1 sheet increase


114 X SO-CPF-169-013(169) 2"-SO-CPF-169-013-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

115 SO-CPF-169-013(169) 2"-SO-CPF-169-013-1D3(169) 1 04-01-2023 N 0

116 SO-CPF-169-013(169) 2"-SO-CPF-169-013-1D3(169) 2 04-01-2023 N 0

ISSUED FOR CONSTRUCTION .


EPCC of CPF-OIL Treatment STAGE Detailed Design
PROJECT System and Auxiliary Systems
Project DOC. NO. BK91-1310-CPF-169-PIP-IDX-0001
8 of 8 .

AREA CPF PAGE NO.

Piping Isometirc Drawing Index for FUEL GAS


DOCUMENT Rev. 1
SYSTEM
SR.NO ISSUED Isometric Dwg No. Line ID Sheet No. Rev.0 Rev.1 Rev.2 Rev.3 HOLD Index Rev. REMARKS

117 X SO-CPF-169-065(169) 3"-SO-CPF-169-065-1D3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

118 X WD-CPF-169-036(169) 2"-WD-CPF-169-036-1Z0(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

119 X VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N10-3C0(1)(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

120 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N10-3C0(2)(169) 1 04-01-2023 N 0

121 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N12-1A3(169) 1 04-01-2023 N 0

122 X VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N13-3C0(1)(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

123 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N13-3C0(2)(169) 1 04-01-2023 N 0

124 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N14-3C0a(169) 1 04-01-2023 N 0

125 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N14-3C0b(169) 1 04-01-2023 N 0

126 X VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N2-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

127 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N3-1A3(169) 1 04-01-2023 N 0

128 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N4-1A3(169) 1 04-01-2023 N 0

129 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N8a-1A3(169) 1 04-01-2023 N 0

130 VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N8b-1A3(169) 1 04-01-2023 N 0

131 X VT-CPF-169-V-01(169) 2"-VT-CPF-169-V-01-N9-1A3(169) 1 04-01-2023 08-04-2023 N 1 Updated as per vendor information

ISSUED FOR CONSTRUCTION .


ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION
ISSUED FOR CONSTRUCTION